investor presentation june 13,...
TRANSCRIPT
INVESTOR PRESENTATION
JUNE 13, 2017
TSX:DPM 2
This presentation contains “forward looking information” or "forward looking statements" that involve a number of risks and uncertainties.
Forward looking information and forward looking statements include, but are not limited to, statements with respect to the future prices of
gold, copper and acid, toll rates, metals exposure and stockpile interest rate deductions, the estimation of mineral reserves and resources,
the realization of mineral estimates, the timing and amount of estimated future production and output, costs of production, capital
expenditures (including sustaining capex, non-discretionary capex and discretionary capex), costs and timing of the development of new
deposits, potential benefits of the rotary furnace installation, success of exploration activities, permitting time lines, currency fluctuations,
requirements for additional capital, government regulation of mining operations, environmental risks, unanticipated reclamation expenses,
title disputes or claims, limitations on insurance coverage and timing and possible outcome of pending litigation. Often, but not always,
forward looking statements can be identified by the use of words such as “plans”, “expects”, or “does not expect”, “is expected”, “budget”,
“scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “does not anticipate”, or “believes”, or variations of such words and
phrases or state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward
looking statements are based on the opinions and estimates of management as of the date such statements are made, and they involve
known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the
Company to be materially different from any other future results, performance or achievements expressed or implied by the forward
looking statements. Such factors include, among others: the actual results of current exploration activities; actual results of current
reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices
of gold, copper and acid; possible variations in ore grade or recovery rates; failure of plant, equipment or processes to operate as
anticipated; accidents, labour disputes and other risks of the mining and smelting industries; delays in obtaining governmental approvals
or financing or in the completion of development or construction activities, fluctuations in metal prices and toll rates, as well as those risk
factors discussed or referred to in this presentation under and in the Company’s annual information form under the heading "Risk Factors"
and other documents filed from time to time with the securities regulatory authorities in all provinces and territories of Canada and
available at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or
results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or
results not to be anticipated, estimated or intended. There can be no assurance that forward looking statements will prove to be accurate,
as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers are cautioned
not to place undue reliance on forward looking statements.
Forward Looking Statements
TSX:DPM 3
An Attractive Investment Opportunity Through
Operational Excellence & Disciplined Growth
1Company Highlights
Optimization of Existing Assets
2
3
4
Near Term Growth
Future Growth Pipeline• Organic growth potential with exploration assets in Serbia
• Actively evaluating M&A opportunities
• Attractive investment opportunity for a growth oriented value minded investor
• Strong management team with track record for successfully turning around poor performing assets
• Strong balance sheet with financial flexibility
• Focused on operational excellence and innovation to achieve margin improvements
• Strong reserve and resource base with continued exploration success
• Generating positive operating free cashflows
• 75% growth in gold production (first 5 year avg.) from the Krumovgrad open pit mine with first
production expected in Q4 2018
• Tsumeb smelter expansion growth potential
GROWTH OPTIMIZATION INNOVATION PEOPLE
TSX:DPM 4
Timok Gold Project
Serbia
Tsumeb Smelter
Namibia
Chelopech Mine
Bulgaria
Sabina
Canada
11%
Krumovgrad Gold Project
Bulgaria
DPM’s Global Portfolio of Assets
Operating assets
Development asset
Exploration assets
2016 Asset Diversification 2016 Revenue Diversification
Bulgaria
56% Namibia
38%
Canada
6%Ag 1%
Smelter
31%Gold
47%
Copper
22%
TSX:DPM 5
Business Strategy
TSX:DPM 6
Bulgaria… • Corporate Tax Rate: 10%
• Chelopech Royalty Rate: fixed at 1.5% of gross Cu,
Au and Ag metals contained in the ore during the
period
• Krumovgrad Royalty Rate: variable rate applied to
gross value of the Au and Ag metals contained in ore
mined. Rate depends on profitability of the operation,
based on a sliding scale between 1% and 4%
• GDP Forecast: +2.8% in 2017 (IMF)
• Mining industry forms 5% of the GDP (2015)
• Overview:
• Uninterrupted operations for 14 years (2003-
2017)
• Member of the EU since 2007
• 4th largest gold producer and 6th largest coal
producer in Europe
• Stable regulatory environment
• Elections held on March 26, 2017 – centre
right party won again
Namibia…• Corporate Tax Rate: 0% as Tsumeb has been granted
Export Processing Zone status
• GDP Forecast: +5.3% in 2017 (IMF)
• Mining industry forms 12% of the GDP (2014)
• Overview:
• Political party stability
• Ranked as Africa’s 4th most attractive country on Fraser
Institute’s Investment Attractiveness Index (ranked #33
globally) (2015 survey)
• World’s 5th largest producer of uranium and 9th largest
producer of diamonds
• Mining companies in the country include Glencore, Rio
Tinto, Anglo American, Paladin Energy, etc.
Mining Friendly Jurisdictions
TSX:DPM 7
Mineral Resources (11) Million Tonnes Au (Moz) Cu (Mlbs) Au (g/t) Cu (%)
Chelopech
M&I
Inferred
12.6
1.8
1.399
0.138
301
37
3.45
2.4
1.08
0.96
Krumovgrad
Inferred (Upper Zone) 0.3 0.013 1.31
Timok (12)
Indicated
Inferred
34.7
0.4
1.720
0.000
1.54
1.4
Tulare (13)
Inferred (Kiseljak)
Inferred (Yellow Creek)
459.0
88.0
3.000
0.800
2,200
600
0.2
0.3
0.22
0.3
Total Mineral Resources
Measured & Indicated
Inferred
47.4
549.5
3.119
3.951
301
2,837
Mineral Reserves (11) Million Tonnes Au (Moz) Cu (Mlbs) Au (g/t) Cu (%)
Chelopech
Proven
Probable
11.4
8.4
1.075
0.920
232
166
2.92
3.42
0.92
0.90
Krumovgrad
Proven (Upper Zone)
Proven (Wall)
Probable (Upper Zone)
Probable (Wall)
1.1
1.5
3.5
0.1
0.124
0.325
0.337
0.020
3.46
6.83
3.00
5.54
Total P&P Mineral Reserves 26.00 2.801 398 3.35
Strong Resources and Reserve Base
11 See footnotes contained in Appendix on slide 34
TSX:DPM 8
Trends- Metal prices and DPM share price
Historical Relative Trading, Year-to-Date (5)
Gold and Copper Price Trend, 2010 to Present (5)
GDXJ
GDX
Tier I
Tier III
Tier II
(25%)
0%
25%
50%
Jan-17 Feb-17 Mar-17 Apr-17 May-17
0%
6%
3%
(0%)
(7%)
(13%)
$1.80
$2.10
$2.40
$2.70
$3.00
$3.30
$3.60
$3.90
$4.20
$4.50
$4.80
$1,000
$1,100
$1,200
$1,300
$1,400
$1,500
$1,600
$1,700
$1,800
$1,900
$2,000
Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17
Gold Price Trend (US$/oz)
Copper Price Trend (US$/lb)
2010 201620152014201320122011 2017
Jan 2017 Feb 2017 Apr 2017Mar 2017 May 20175 See footnotes contained in Appendix on slide 34
Chelopech Mine, Bulgaria
OPTIMIZATION OF EXISTING ASSETS
TSX:DPM
CHELOPECH MINE
TSX:DPM 10
Chelopech – Continually Improving
Reduce Cash Cost / tonne of ore processed (US$/t) (3) Increase Ore Mined (Mt)
Reduced Total Capital Expenditures ($USM)
CONTINUE TO OPTIMIZE THROUGH INNOVATION
133
196
153
118
9987
27
2011 2012 2013 2014 2015 2016 Q1 2017
1.09
1.31
1.812.03 2.05 2.04
2.21 2.04-2.20
0.562
2010 2011 2012 2013 2014 2015 2016 2017F Q12017
56 55
4640 40
3733 32-36 33
2010 2011 2012 2013 2014 2015 2016 2017F Q12017
72.1
62.4
42.3
30.1
18.513.2 13-15
2.4
2011 2012 2013 2014 2015 2016 2017F Q12017
Adjusted EBITDA (US$M) (10)
3,10 See footnotes contained in Appendix on slide 34
TSX:DPM 11
Chelopech-Near Mine Exploration
Ore Mined / Reserves (Mt)
2006 2015 2016
21.5 21.5
14.1 Total ore
mined
since 2006
Ore Reserve
16.3
19.8
Drilling commenced at SE Breccia pipe zone
Plan view of level 440 showing ore-body outlines.
New High Grade Zone 153
•Essentially replaced depletion over the last 10 years
•Discovery of new Zone 153: high grade Cu and Au
mineralization located near existing infrastructure (11)
− EXT150_440_06: 84m @ 13.58g/t Au and 2.87% Cu incl.
46.5m @ 22.09g/t Au and 4.26% Cu
− EXT150_440_02: 16.8m @ 6.60g/t Au and 1.86% Cu incl. 6.7m @ 13.50g/t Au and 3.73% Cu
11 See footnotes contained in Appendix on slide 34
Chelopech Mine, Bulgaria
NEAR TERM GROWTH
TSX:DPM
KRUMOVGRAD GOLD PROJECT
TSX:DPM 13
Highlights
• High grade open pit mine producing gold concentrate through flotation
• 8 year mine life
• Total initial construction capital – $178.2 million
• Estimated annual production: gold = 85,700 oz; silver = 38,700 oz
• Project site falls entirely within the Eastern Rhodopes Natura 2000 protected area
• Ancient gold mine - extensive archaeological research completed
• Project designed in line with the environmental and social policy of the European Bank for
Reconstruction and Development and to meet the Performance Requirements of the bank
Krumovgrad–Fully Funded Near Term Growth
TSX:DPM 14
Krumovgrad – Robust Economics
Project
Economics
Remain Robust
with a
25% After-Tax
IRR
Production and Operating Costs (8)
Annual gold production 85,700 oz
Annual silver production 38,700 oz
First concentrate production Q4 2018
LOM 8 years
Total Annual Operating Costs / t ore processed
Mining costs
Processing costs
Tailings treatment & IMWF costs
General & administration
Royalty
$45.41
$15.03
$19.39
$1.88
$5.33
$3.78
Capital Costs
Construction capital to complete
Direct Costs
Indirect Costs
Contingency P50 (7.5% of direct + indirect costs)
$178.2 million
$117.1 million
$48.7 million
$12.4 million
Sustaining Capital $6.2 million
Closure and Rehabilitation Costs $6.0 million
Total cash cost per oz AuEq $403
Average Annual EBITDA (10) $66 million
8,10 See footnotes contained in Appendix on slide 34
TSX:DPM 15
Krumovgrad – Production Profile
* 85% recovery
Wall Upper Total Ore
kt kt W:O kt kt kt koz koz g/t
-1 648 419 1.83
1 2,663 1,822 2.16 13 796 809 89 50 3.42
2 2,148 1,015 0.90 221 583 803 129 67 5.01
3 2,034 1,156 1.32 177 636 813 146 74 5.59
4 3,211 2,466 3.31 19 818 837 91 51 3.40
5 3,211 2,513 3.60 399 375 773 151 79 6.06
6 3,211 2,645 4.67 326 460 785 83 49 3.29
7 3,096 2,441 3.73 320 469 789 72 44 2.83
8 2,224 1,765 3.85 119 476 595 45 29 2.37
Total / Avg 22,446 16,242 2.62 1,593 4,611 6,204 807 443 4.04
Year (-1) represents pre-strip period of 3 months.
Total Au Total Ag Au Grade
MINE PLAN (SCENARIO 2A) AND MILL FEED (CONSTRAINED BY ORE TYPE
THROUGHPUT) SUMMARY
YearRock Total Waste Strip Ratio
Ore Feed
0.0
1.0
2.0
3.0
4.0
5.0
0
1,000
2,000
3,000
4,000
-1 1 2 3 4 5 6 7 8
Strip
Rat
io (t
:t)
Tonn
age
(kt)
MINING SCHEDULE
Upper Wall Waste Strip Ratio
0
50
100
150
200
0
200
400
600
800
1,000
-1 1 2 3 4 5 6 7 8
Oun
ces
Au (k
oz)
Tonn
age
(kt)
PROCESSING
Mill Feed - Upper Mill Feed - Wall
Mill Feed Gold - Total
0
200
400
600
-1 1 2 3 4 5 6 7 8
Tonn
age
(kt)
STOCKPILE BALANCE
HGO LGO
89
129146
91
151
8372
45
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
3.42
5.015.59
3.4
6.06
3.292.83
2.37
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Mining Schedule (8)
Total Au contained in ore (000s oz)* (8)
Au Grade (g/t) (8)
8 See footnotes contained in Appendix on slide 34
TSX:DPM 16
Krumovgrad – Project Progress
Milestone Actual / Expected Completion (2)
Completion of the Detailed Project Execution Plan Q1 2016 (complete)
Complete Detailed Engineering Q1 2016 (complete)
Updated Capital Cost Estimate and Baseline Project Schedule Q1 2016 (complete)
Land Re-designation and Purchase Q1/2 2016 (both complete)
Approval of Technical Packages Q2 2016 (complete)
Construction Permit RECEIVED AUGUST 9, 2016
Mobilize Earthworks Contractor to Site and Commence Earthworks Q4 2016
Commence Main Civil/Mechanical/Electrical Construction Q3 2017
Commissioning and Start Up Q3 2018
First Concentrate Production Q4 2018
2 See footnotes contained in Appendix on slide 34
TSX:DPM 17
Krumovgrad – Earthworks Progress
South IMWF Road
The first concrete at the site – April 25th
Earthworks in the Process Plant Area
Hydro-seeding ROM Pad Slopes
TSX:DPM 18
• Extensive consultation program with stakeholders
• 33% reduction in project footprint in response to stakeholder concerns; integrated mine
waste facility instead of conventional tailings dam
• Mine design to minimize community health risks and environmental impact
• Stakeholders engagement plan, social management plan based on community needs
assessment, local consultative forums - operating at 8 nearby settlements
• Significant job creation
• Maximizing local employment during construction - equal opportunity program
• 230 jobs during operations phase (90% sourced locally)
• Vocational training and skills development for employees
• Significant SME funding available to build sustainable local business capacity
• Support for infrastructure development, education, health and social services
• Local procurement during all phases of the project
• Extensive biodiversity and water management plans and standards
• Water discharge to the environment will be drinking quality
• Minimization of noise, dust, vibration, traffic and blasting impacts
Krumovgrad - Sustainable Mining in Europe
TSX:DPM 19
Krumovgrad - Near Mine Exploration
Ada Tepe Gold Deposit and Surrounding Gold Prospects
Chelopech Mine, Bulgaria
FUTURE GROWTH PIPELINE
TSX:DPM
EXPLORATION
TSX:DPM 21
Serbia Exploration
Timok
Brownfields Exploration
Near Resource Drill Programs
Timok
Greenfields Exploration
TSX:DPM 22
Khalkos Exploration
Earn-in Arrangement
1) 51%: interest in the first three years:
$412,500 in cash, 70,000 DPM shares, $2.5 MM in expenditures
2) Additional 20% interest (for a total of 71%) in the following three years:
Exploration expenditures totalling $3,500,000
Dundee shall act as operator during both periods
Highlights
• Consists of 91 contiguous claims
covering 35 square kilometers of
prospective Abitibi geology about
25 km west of Val-d’Or
• Situated 10 km along strike to the
east of the Doyon–Bousquet-
LaRonde gold camp and 8 km
north of the Canadian Malartic
mine
• Potential for both quartz
carbonate vein gold deposits and
gold-rich VMS lenses and related
sulphide stockworks.
• One of the largest land positions
held by any junior mining
company in the camp
• Consolidation of these claims
allows for a systematic approach,
integrating geology with new
geochemical and geophysical
datasets to develop drill targets
on a wider scale
Chelopech Mine, Bulgaria
OPTIMIZATION OF EXISTING ASSETS
TSX:DPM
TSUMEB SMELTER
TSX:DPM 24
Tsumeb Smelter – Key Accomplishments
26
63
140130
44
1912-17
4.5
2011 2012 2013 2014 2015 2016 2017F Q1 2017
Reduced Total Capital Expenditures ($USM)
Significantly reduced SO2 levels
198 196 200
120
180159 152
2010 2011 2012 2013 2014 2015 2016 2017F
210-
240
Third Party con supplied to
smelter (‘000s t)
Chelopech concentrate
supplied to smelter
(‘000s t)
Increased Production
134 134 126
4138 46
22 7
94
123 118
2113
6242
311 0 3 80
40
80
120
160
2013 2014 2015 2016
Sewage Plant
Stadium Site
Hill site
Info Centre
NAMFO
3.0
18.5
6.8
9.7
(5)
2011 2014 2015 2016
Q1 20172012 2013
(2.5)
(7)
Adjusted EBITDA (US$M) (10)
2,10 See footnotes contained in Appendix on slide 34
2
TSX:DPM 25
(4) (4) (4)(4)(4)
(2)
(3),(4)
198 196 200
265-300
300-370
120
180
159152
312
341
420
479
394
418
440400-485
2010 2011 2012 2013 2014 2015 2016 2017F 2018F 2019F 2020F
The Tsumeb Smelter
• Unique ability to process large volumes of
complex concentrate
• Purchased to process the concentrate from
Bulgaria
• Major environmental upgrade capital
completed
Building on that success
• Completed the commissioning of the
sulphuric acid plant Q4 2015 and copper
converters Q1 2016
• Optimization gained traction in Q4 2016 with
record concentrate treatment
• Matte holding vessel opened process
flexibility and was commissioned in April
2017 ahead of original plans
• Smelter remains on target to demonstrate
consistent increased throughput in Q2 2017
as the smelter transformation project
continues to yield results
210-
240
240-
265
Third Party
con supplied
to smelter
(000s)
Chelopech
concentrate
supplied to
smelter
(000s)
Cash cost per
tonne of
concentrate
smelted (net of
by product
credits) (3)
Anticipated
future
capacity
Tsumeb Smelter – Optimizing Performance
2,3 See footnotes contained in Appendix on slide 34
2 2 2 2
465
425
370
TSX:DPM 26
Tsumeb Smelter - Expansion
Potential Expansion
• Expansion project considering the installation
of a rotary holding furnace has progressed to
a feasibility study
• Completed expansion feasibility study to
370,000 tonnes/year
• Completing environmental and social impact
assessment
• Remains a robust project subject to the
market timing of additional concentrate and
completion of the permitting for 370,000
tonnes/year
TSX:DPM 27
Growing Complex Concentrates Market
Mines In Operation Annual Tonnage As (%)
Chelopech 90,000 – 105,000 5.5%
South America 150,000 – 200,000 4.0% - 9.0%
Small Producers
(into blends)30,000 – 50,000 2.5% - 7.0%
Total Complex 270,000 - 355,000
Other Pyrite/Cu
Con/Antimony100,000 – 150,000 4.0% - 5.0%
Total Concentrate 370,000 – 505,000
Projects – Possible
ProductionAnnual Tonnage As (%)
Copper and Pyrite
Concentrates400,000 4.0% – 10.0%
SUMMARY
TSX:DPM
GROWTH OPTIMIZATION INNOVATION
TSX:DPM 29
Committed To Maintaining A Strong Balance
Sheet Supported With Sufficient Available Liquidity
$311 M in Available Liquidity
Top Down Financing Structure
• Utilize equity for vast majority of core funding requirements
• Maintain long term credit facilities with a core lending group
• Supplement with high yield bond, project debt, or equity
partner financing, where appropriate
Maintain financial strength and flexibility• Limit debt component of capital – Targeted Max. 20%
• Adhere to targeted credit metrics – Targeted Max 2.0 x
• Maintain sufficient liquidity – Targeted Min. $75 million
Selectively hedge exposures to manage risk• Provisional metal sales pricing
100% hedged
• Future production
92%/53% of 2017/18 Payable Cu production @ $2.40 / $2.62
30% of 2017 Payable Au production - $1,200/$1,497 floor/cap
• Foreign denominated operating costs
53% of balance of 2017 Nam$ costs hedged @ 13.98
21% of balance of 2017 Euro costs hedged @ 1.13
• Foreign denominated capital project costs
50% of Euro capital costs hedged @ 1.08
Net Debt (US$M) & Net Debt/EBITDA (x)
34
121 120(19)
0.1
1.081.67
0.56
0.0
0.6
1.2
1.8
-50
0
50
100
150
As of
March 31, 2017
RCF
$275M
Cash $36M
29
20162014 20152013 Q1 2017
0.04
TSX:DPM 30
Smelter • Expansion
detailed
engineering
• EIA approval
• Commercial
agreements
• Expansion
approval
• Commence
construction
• Start ramp-up
to operate at
expanded
capacity
• Production
at expanded
capacity
Krumovgrad • Construction • Q4 first
concentrate
production
Chelopech • Continue to
optimize
performance
• Zone 153
definition drilling
• Incorporate
Zone 153 into
mine plan
2017 2018 2019 2020
Key Value Generating Catalysts
TSX:DPM 31
5 Year Outlook – Growing Low Cost Producer
AuEq Production
by 2020
>351,000 oz
Complex
Concentrate
Smelted
t/year
370,000
2013 2014 2015 2016 2017F 2018F 2019F 2020F
Smelter Concentrate Throughput (kt) (2)
AuEq Production (000s oz) (2)
198
240-265
300-370
2013 2014 2015 2016 2017F 2018F 2019F 2020F
274
222 227243
295
351
271275Au Cu other
210-240200196
152
265-300
479394 418 440
400-485 450-485400-450
340-400
2013 2014 2015 2016 2017F 2018F 2019F 2020F
Smelter Cash Cost / tonne of concentrate smelted (net of by product credits) (2,3,13)
687747
610736
780-910
755633
498
2013 2014 2015 2016 2017F 2018F 2019F 2020F
All-in Sustaining Cost (US$/oz) (2,3,6)
2,3,6,12 See footnotes contained in Appendix on slide 34
TSX:DPM 32
Growth and Value Investment Opportunity
0.970.92
0.81
0.670.64
0.62 0.61 0.600.56 0.54 0.52
0.44
Roxgold TMAC Klondex Guyana Asanko Premier Alacer Argonaut Resolute Terenga DPM Primero
Avg. 0.66x
P / NAV(Cons. Est.) *
8.5x
4.4x
2.3x
2.0x 1.9x 1.7x
Alamos New Gold DPM Argonaut Primero Alacer
EV/2019F EBITDA (Cons. Est.)
Avg. 3.5x
* Source: RBC at June 9, 2017
Chelopech Mine, Bulgaria
APPENDICES
TSX:DPM
TSX:DPM 34
Footnotes and Disclaimers1. Includes payable gold in pyrite concentrate sold and related costs, when applicable
2. Forecast/guidance information is subject to a number of risks. 2017F is based on guidance issued in February 2017 and 2018 to 2020 forecast data is based on the completion of several growth
projects within currently contemplated time frames. See “Forward Looking Statements” on slide 2
3. A non-GAAP measure. Refer to the “non-GAAP Financial Measures” section of the Q1 2017 MD&A for reconciliations to IFRS
4. Data Source “Yahoo Finance”
5. Source: Capital IQ May 4, 2017 and RBC
6. AISC per ounce of gold represents cost of sales at Chelopech less depreciation, amortization and other non-cash items plus treatment charges, penalties, transportation and other selling costs,
sustaining capital expenditures, rehabilitation related to accretion expenses and an allocated portion of the Company’s G&A expenses less by-product revenues in respect of copper and silver
including realized gains on copper derivative contracts divided by the payable gold in copper and pyrite concentrates sold. Based on metals prices that approximate current rates. The assumed
copper prices reflect the impact of 92% of payable copper hedged at $2.40/lb in 2017 and 53% of payable copper hedged at $2.62/lb in 2018.
7. Chelopech figures as per 2016 public filings; AISC includes gold production in pyrites
8. Krumovgrad figures as per latest NI 43-101
9. Tsumeb figures as per 2016 public filings
10. Adjusted EBITDA represents earnings before income tax plus depreciation and amortization, finance costs, impairment charges, unrealized losses/gains on derivative contracts and investments at
fair value, minus interest income
11. Contained in the 2016 Annual Information Form dated March 28, 2017
12. Based on ZAR exchange rate of 14.0
Without limitation to the foregoing, the following outlines certain specific forward looking statements contained in this presentation and provides certain material assumptions used to develop such forward looking statements and material risk factors that
could cause actual results to differ materially from the forward looking statements (which are provided without limitation to the additional general risk factors discussed herein and in the Full Year 2016 MD&A). Sustaining CAPEX, Non-Discretionary
CAPEX and Discretionary CAPEX: assumes foreign exchange rates remain at or around current levels, and all capital projects proceed as planned and at a cost that is consistent with the budget established for each project. Subject to a number of risks,
the more significant of which are: technical challenges; delays related to securing necessary approvals, equipment deliveries, equipment performance, and the speed with which work is performed; availability of qualified labour; and changes in project
parameters, timing and decision to proceed with projects and/or any components there of and estimated costs, including foreign exchange impacts. Gold and Copper Production: projected levels of metal production assumes grades and recoveries are
consistent with current estimates of Mineral Resources and Mineral Reserves and DPM’s current expectations and construction of Krumovgrad project and decision to proceed with projects and/or any components there of; and ore mined/milled is
consistent with planned levels. Subject to a number of risks, the more significant of which are: lower than anticipated ore grades, recovery rates and ore mined/milled. Smelted Concentrate: assumes no significant disruption in equipment availability or
concentrate supply. Subject to a number of risks, the more significant of which are: unanticipated operational issues; timing and decision to proceed with expansion projects, including the holding furnace, and/or any components there of; and any further
expansion components including a holding furnace; lower than anticipated equipment availability; disruptions to or changes in the supply of concentrate; and toll rates lower than anticipated.
Technical Information related to slide 14 – Krumovgrad Project Economics
The Mineral Resource and Mineral Reserve estimates and other scientific and technical information which supports this presentation was prepared by CSA Global (UK) Ltd. (“CSA”), in accordance with Canadian regulatory requirements set out in National
Instrument 43-101 Standards of Disclosure for Mineral Projects, and were reviewed and approved by, as relates to Mineral Resources, Galen White, BSc (Hons) FAusIMM FGS, Director and Principal Consultant of CSA, and Julian Bennett, BSc ARSM
FIMMM CEng, as relates to Mineral Reserves. Both Galen White and Julian Bennett are independent Qualified Persons (“QP”), as defined under NI 43-101. The NI 43-101 technical report (the “Krumovgrad Technical Report”) entitled “NI 43-101 Technical
Report, Ada Tepe Deposit, Krumovgrad Project, Bulgaria” dated March 21, 2014, in respect of the study for the construction and operation of its Krumovgrad gold project disclosed herein, was filed March 31, 2014 on SEDAR at www.sedar.com. Simon
Meik, Processing, and Edgar Urbaez, formerly Corporate Director, Technical Services, both of DPM, who are QPs and not independent of the Company, have reviewed and approved the contents of this presentation. The Mineral Resource and Mineral
Reserve estimates contained herein may be subject to legal, political, environmental or other risks that could materially affect the potential development of such Mineral Resources. See the Krumovgrad Technical Report for more information with respect to
the key assumptions, parameters, methods and risks of determination associated with the foregoing Mineral Resource estimates.
Cautionary note to U.S. Investors concerning estimates of Mineral Resources. These estimates have been prepared in accordance with the requirements of Canadian securities laws, which differ from the requirements of U.S. securities laws. The terms
“mineral resource”, “measured mineral resource”, “indicated mineral resource” and “inferred mineral resource” are defined in NI 43-101 and recognized by Canadian securities laws but are not defined terms under the U.S. Securities and Exchange
Commission (“SEC”) Guide 7 (“SEC Guide 7”) or recognized under U.S. securities laws. U.S. investors are cautioned not to assume that any part or all of mineral deposits in these categories will ever be upgraded to mineral reserves. “Inferred mineral
resources” have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an “inferred mineral resource” will ever by upgraded to a higher category.
Under Canadian securities laws, estimates of “inferred mineral resources” may not form the basis of feasibility or pre-feasibility studies. U.S. investors are cautioned not to assume that all or any part of an inferred mineral resource exists or is economically
or legally mineable. Accordingly, these mineral resource estimates and related information may not be comparable to similar information made public by U.S. companies subject to the reporting and disclosure requirements under the U.S. federal securities
laws and the rules and regulations thereunder, including SEC Guide 7.
All-in sustaining costs: assumes metals contained in concentrate produced and cash cost per tonne of ore processed are each in line with planned levels; copper and silver prices remain at or around planned levels; concentrate deliveries are consistent
with DPM’s planned levels; general and administrative expenses and sustaining capital expenditures are consistent with current expectations. Subject to a number of risks, the more significant of which are: lower than anticipated metals contained in
concentrate produced, concentrate deliveries and metal prices; a higher than anticipated cash cost per tonne of ore processed; and higher than anticipated sustaining capital expenditures and general and administrative expenses.
Cash cost per tonne of complex concentrate smelted, net of by-product credits: assumes complex concentrate smelted is at planned levels; acid prices are at or around current levels; acid production and operating expenses are at planned levels; and
foreign exchange rates remain at or around current levels. Subject to a number of risks, the more significant of which are: complex concentrate smelted and acid production are lower than anticipated; acid prices are lower than anticipated; strengthening of
the ZAR relative to the U.S. dollar; and higher than anticipated operating and transportation costs due to a variety of factors, including higher than anticipated inflation, labour and other operating costs.
TSX:DPM 35
Market Cap, Major Shareholders and Analyst Coverage
Share Price (C$ per share) $2.31
Shares Outstanding – Current 178,440,698
Market Capitalization – Current C$412 M
52 week low – high (C$ per share) $1.87 – $4.14
Share Capital @ June 9, 2017 Analyst Coverage
Firm Analyst
BMO **In transition**
CIBC Capital Markets Jeff Killeen
Eight Capital Research Josh Wolfson
GMP Securities Oliver Turner
Paradigm Capital Don MacLean
Raymond James **In transition**
RBC Capital Markets Sam Crittenden
Scotia Capital Trevor TurnbullDundee Corporation 20.39%
GMT Capital 10.77%
EBRD 9.99%
Van Eck Associates 7.12%
Kopernik Global Investors 3.25%
Major Shareholders
TSX:DPM 36
2017 Full Year GuidanceUS millions, unless otherwise indicated Chelopech Tsumeb Consolidated (5)
Ore mined/milled (‘000s tonnes) 2,040-2,200 - 2,040-2,200
Complex concentrate smelted (‘000s tonnes) - 210-240 210-240
Metals contained in concentrates produced (1)(2)
Gold (‘000s ounces) 157-174 - 157-174
Copper (million pounds) 33.7-37.0 - 33.7-37.0
Payable metals in concentrate sold (2)
Gold (‘000s) 135-150 - 135-150
Copper (million pounds) 32.0-35.0 - 32.0-35.0
Cash cost per tonne of ore processed ($) (3)(4) 32-36 - 32-36
Cash cost per ounce of gold sold, net of by-product credits ($) (3)(4)(5) 670-810 - 670-810
All-in sustaining cost per ounce of gold ($) (3)(4)(5) - - 840-965
Cash cost per tonne of complex concentrate smelted, net of by-product credits ($) (3)(4) - 400-485 400-485
General & administrative expenses (3)(6) - - 18-22
Exploration expenses (3) - - 7-9
Sustaining capital expenditures (3) 13-15 12-17 25-32
1) Includes gold in pyrite concentrate produced of 42,000 to 47,000 ounces and payable gold in pyrite concentrate sold of 27,000 to 30,000 ounces.
2) Metals contained in concentrate produced are prior to deductions associated with smelter terms.
3) Based on foreign exchange rates and, where applicable, metal prices that approximate current rates and prices. The assumed copper price reflects the impact of 92% of 2017 payable copper
production being hedged at $2.40 per pound.
4) Cash cost per tonne of ore processed, cash cost per ounce of gold sold, net of by-product credits, all-in sustaining cost per ounce of gold and cash cost per tonne of complex concentrate smelted,
net of by-product credits, have no standardized meaning under GAAP. Refer to the “Non-GAAP Financial Measures” section of Q4 2016 MD&A for reconciliations to IFRS.
5) Includes the treatment charges, transportation and other selling costs related to the sale of pyrite concentrate, and payable gold in pyrite concentrate sold. Cash cost per ounce of gold sold, net of by-
product credits, excluding payable gold in pyrite concentrate sold and related costs, is expected to range between $640 and $790 in 2017. All-in sustaining cost per ounce of gold, excluding payable
gold in pyrite concentrate sold and related costs, is expected to range between $850 and $985 in 2017.
6) Excludes mark-to-market adjustments on share-based compensation.
Chelopech Mine, Bulgaria
THANK YOU
TSX:DPM
Corporate Head Office:
One Adelaide Street East, Suite 500
Toronto, Ontario, M5C 2V9
T: 416 365-5191
Investor Relations
T: 416 365-2549
TSX:DPM
www.dundeeprecious.com