IRTBA “STATE OF THE

INDUSTRY”

Will CountyFY 2012

Page 2: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

• 2008– Build Will unveiled

• 60 projects on County Highway System• $300 million program

– Funded with • RTA sales tax• Federal, State, & other Local funding sources

• 2009-Present– Additional 12 projects– Total additional cost $57 million– $100 million in bonds approved

by County Board

BUILD WILL UPDATE

Page 3: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

• Largest Overlay Program in History– Last 2 Years

• 84 Center-line Miles• 25 County Highways

– FY 2012• 36 Center-line Miles• 14 County Highways• Total estimated cost $10 million

– 3 Year Total• 120 Center-line Miles• 39 County Highways

BUILD WILL UPDATE (cont.)

Page 4: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

Road Construction $40.7 million

Structure Rehab & Reconstruction $11.9 million

Engineering $14.0 million

ROW Acquisition $14.8 million

Build Will Total $81.4 million

Maintenance $10 million

Program Total $91.4 million

FY 2012 PROGRAM

Page 5: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

• Weber Road @ Renwick Road

• 135th Street @ Il Route 171 (Archer Avenue)

• 95th Street Extension (Plainfield-Naperville Road to Boughton Road)

• Will-Peotone Road @ Old Chicago Road over Jordan Creek

• South Briggs over Metra & Hickory Creek

PROGRAM HIGHLIGHTS

Page 6: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

WEBER ROAD @ RENWICK ROAD

• Scope – Weber Road

• Widen to 6 lanes • Barrier Median

– Renwick Road• Widen to 4 lanes• Barrier Medians

• Total Cost: $ 14 million• Approximately $ 4 million in

Federal Funds (STP & CMAQ)• Quick Take approved for ROW

acquistion

Page 7: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

135TH STREET @ IL ROUTE 171(ARCHER AVENUE)

• Scope of Work– Realign

Intersection– New Structure over

Long Run Creek

• Total Cost: $ 7.1 million

Page 8: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

95TH STREET EXTENSION:PLAINFIELD-NAPERVILLE ROAD TO BOUGHTON

ROAD• Scope

– Approximately 2 miles of new Roadway

– New Structure over DuPage River

– Intersection Improvements at termini

– Noise Walls• Total Cost: $ 25.9 million• Funding: Over $10 million

in Federal Funds (STP & STR)

Page 9: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

WILL-PEOTONE ROAD @ OLD CHICAGO ROAD

• Scope– Turn Lanes on all legs– Reconstruction of

Structures over Jordan Creek on both roads

• Total Cost: $7.04 million

Page 10: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

SOUTH BRIGGS STREET OVER METRA & HICKORY CREEK

• Scope: Structure Rehabilitation

• Total Cost: $2.5 million

Page 11: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

• According to Labor Statistics – 42, 000 jobs are created – Per $1 billion in Construction

• Build Will FY 2012 Creates: 2210 jobs

JOB CREATION

Page 12: IRTBA “STATE OF THE INDUSTRY” Will County FY 2012

QUESTIONS?