is construction cost growth breaking your budget?

21
Is Construction Cost Growth Breaking Your Budget? APWA 2008 Annual Conference New Orleans 2 Who is PSMJ Resources, Inc.? Content Providers of Management Information Focused Exclusively on the A/E/C Industry More than 30 Years Newsletters Surveys & Books Seminars & Conferences Consulting Strategy 3 3 3 3 Marketing 3 3 3 3 Project Delivery 3 3 3 3 Finance 3 3 3 3 Human Resources 3 3 3 3 Transition 3 3 3 3 2

Upload: others

Post on 08-Jun-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Is Construction Cost Growth Breaking Your Budget?

Is Construction Cost Growth Breaking Your Budget?

APWA2008 Annual Conference

New Orleans

2

Who is PSMJ Resources, Inc.?• Content Providers of Management Information• Focused Exclusively on the A/E/C Industry• More than 30 Years

Newsletters Surveys & Books

Seminars & Conferences Consulting

Strategy

Marketing

Project Delivery

Finance

Human Resources

Transition

2

Page 2: Is Construction Cost Growth Breaking Your Budget?

Your Speaker

• Michael S. Ellegood, PE  (Mike)• Former Director of Public Works‐Maricopa County (retired)

• 22 years as a consulting engineer and project manager

• Published author• Associated with PSMJ since 2000

– Technical content leader, public works programs

• Member, APWA

3

The Problem

• Excessive construction cost growth

• In Maricopa County, construction cost growth exceeded 13% on average

• According to a recent AASHTO study:– On larger projects (>$5M)

• 82% exceeded original bid

• 30% exceeded over 10% of the original bid

• How does your agency perform?

4

Page 3: Is Construction Cost Growth Breaking Your Budget?

Why Do Projects Fail?

5

PSMJ’s Top 20 Excuses for Project Failure

1. The project team was full of incompetents.

2. I didn’t have enough time.

3. The customer kept making changes.

4. The budget was unrealistic.

5. I couldn’t get enough help.

6. Working for that client is impossible!

7. I couldn’t get the information I needed from accounting.

8. The schedule was unrealistic.

9. Everyone kept charging to the job.

10. _____ was taken off the job at the worst possible time.

11. I wasn’t given enough authority.

12. The designers wouldn’t stop           designing.

13. The contractor didn’t understand the               job.

14. This job was unique.

15. The building dept. is full of idiots.

17. The subs would not cooperate.

18. The word processing people kept getting pulled off my job.

19. ________ quit and left me holding the     bag.

20. The CADD operators didn’t know what they were doing. 

6

Page 4: Is Construction Cost Growth Breaking Your Budget?

Frank Stasiowski’s* Definition of Project Management

• “The art and science of guiding all of the stakeholders through a series of changes that we call a ‘project’”

*Frank is the founder and CEO of PSMJ Resources.  A highly respected architect , he  is widely respected as the developer of many of the project management protocols now in common use.

7

8

Page 5: Is Construction Cost Growth Breaking Your Budget?

“Change is inevitable, the trick is to  discover it early” (then manage it)!”

Managing Change

9

Change Effect Over Time

10

$

COMPLET ION

PLANNING PHASE

DESIGNPHASE

BID & AWARD

CONSTRUCTION PHASE

Time

The earlier in the project change is recognized, the easier and cheaper it is to manage.

Resolution Management Consultants

Page 6: Is Construction Cost Growth Breaking Your Budget?

11

Charter

PS&E

ManualsTraining

Phases of a Project

Change Management Begins Here

Project Charter AcceptancePrepared by :

Program Review:

Sponsor Approval:

Project Manager Acceptance:

Type name of assigned PM, Project Manager Date

Note:  A final signed copies of the project charter will be provided to the Program Office, Customers and Director.

12

Page 7: Is Construction Cost Growth Breaking Your Budget?

• Develop a Project Change Management Process• Determine project change threshold

– (Perhaps an aggregate change of 10%)

• Establish a structured review process– “Summit meeting”

– Project change control board

• Never authorize a change without:– Modifying the Scope, Schedule, Budget, WBS & PMP and a change to your supplier contract

– Obtain your client’s signoff

13

Change Management Plan

Recognize the Typical Causes of Change

• Changes in IT requirements

• Changes in codes

• Security concerns

• Adjacency (land use, tenants, etc.)

• “NFW” changes desired by the client

• Underground conditions

• Environmental and permitting changes

• Political / Public Acceptance

14

Page 8: Is Construction Cost Growth Breaking Your Budget?

Putting Change Management Together

• Develop and disseminate a project charter– Jointly developed with the client and signed off

• Develop a project change process

• Develop risk and quality management plans

• Do not short change the underground investigation.

• Conduct a proactive public outreach program

15

Tools to Manage Change

16

Page 9: Is Construction Cost Growth Breaking Your Budget?

News Flash: Projects Are Built in the Field!

Common Problems Ways to Avoid ThemWrong or outdated design references

Incorrect or differing survey datum

Utility interferences

Unchecked plans

Stale plans

Field conditions vary from design assumptions

Identify design references by edition and date, not “latest edition”

Reference adjacent facilities to your datum

Field reconnaissance with the PDT at the start of the project

Design staff required to field check during design

Construction Manager (or other experienced construction person) involved in all design reviews

Plan-in-hand review at 70%

Final field check just before IFB17

Forget this andstand by for changes!

How good are your plans?

“Bid spread is one of the most effective measures of the quality of a plan assembly (and the potential 

for change orders)”.

18

Page 10: Is Construction Cost Growth Breaking Your Budget?

What do we look for?

• Bid spread of ≤ 20% low to high

Or

• Bid spread of ≤ 15% among three close bidders

19

Storm Sewer Renovations

• Low Bidder  ‐ $193,100.00

• 2nd Bidder ‐ $276,300.00

• 3rd Bidder ‐ $283,200.00

• 4th Bidder ‐ $285,150.00

20

Page 11: Is Construction Cost Growth Breaking Your Budget?

Downtown Alley Parking & Lighting

• Low Bidder ‐ $1,052,839.13

• 2nd Bidder  ‐ $1,104,140.58

• 3rd Bidder  ‐ $1,221,183.60

• 4th Bidder  ‐ $1,362,120.00

21

Asbestos Abatement

• Low Bidder ‐ $339,181.00

• 2nd Bidder  ‐ $382,426.00

• 3rd Bidder  ‐ $414,880.00

• 4th Bidder  ‐ $599,957.00

• 5th Bidder  ‐ $610,000.00

• 6th Bidder  ‐ $773,057.00

• 7th Bidder  ‐ $827,162.00

22

Page 12: Is Construction Cost Growth Breaking Your Budget?

In Spite Of Our Efforts In The Planning And Design Phases, Changes Do Occur During 

Construction.  They Just Cost More!

Managing Construction Change

23

Impact of Change: #1 Cause of Conflict

If This Happens…Excusable delays

– Weather– Strikes– Acts of God

Owner delays– Late owner‐furnished equipment, 

material or information– Failure to make timely decisions– Denied access– Acceleration (directed or constructive)– Change in sequence– Formal changes– Suspension of work

Design professional delays– Over‐inspection– Late approvals– Deficient design

Contractor delays– Subcontractor delays– Failure to adequately staff the job– Defective work

The Result Could Be…• Increased Labor Rates• Additional Labor Hours• Increased Supervision (O.T., Shift Work)• Inefficiency• Material Escalation• Increased Material Handling• Extended Job Duration• Extended Field Overhead• Misallocation of Home Office Overhead• Additional Equipment• Idle Equipment• Assessment of Liquidated Damages• Termination for Default

24

TRANSLATES

I NTO

Resolution Management Consultants

Page 13: Is Construction Cost Growth Breaking Your Budget?

Categories of Construction Change

• Delays – owner, designer, contractor caused, act of god (force majeure)

• Scope Changes

• Condition Changes (actual conditions differ from design assumptions)

• Design Related Changes (Errors, etc)

25

Delay Related Changes

• The most common cause of claims• Often result of non‐responsiveness to RFI’s and contractor 

communications

Tips• Develop a process for managing contractor communications 

(RFI’s, submittals, etc)• Maintain communications – ask the hard question• Discuss contractor communications at every weekly meeting.• Determine schedule impact of contractor communications• Go over RFI’s & Submittals at every meeting and ask the hard 

question: “Do we owe you anything?”

26

Page 14: Is Construction Cost Growth Breaking Your Budget?

Scope Changes

Usually the result of:

• Customer requests after set milestone dates

• Not following the plan assembly

Tips• Don’t hesitate to inform the customer of increased cost

• Remember, the plans are more than a suggestion!

27

Changed Conditions

• The site conditions differ from the design assumptions (often underground conditions such as hidden utilities, rock outcroppings, etc.)

Tips • Investigate immediately, identify alternatives, act before it 

delays the project

• Flow chart the impacts – scope, schedule, budget

28

•Hindsight: Don’t skimp on the underground investigation even if you (think) you know what’s there.

Page 15: Is Construction Cost Growth Breaking Your Budget?

Design Related Changes

• Usually related to, if not caused by, design error

Tips

• Assess the alternatives

• Identify the impacts on scope, schedule, budget

• Make a decision  

29

•Hindsight: Thorough design review, documentation of plan check, field checks and a release for construction process will help prevent this from occurring.

For every Change Order:• Identify costs relating to change• Identify activity (or activities) affected by change• Require documentation showing whether a time extension is 

required (Is this on the critical path?)• Contractor should segregate change costs and hours from base 

work• Contractors should include all change‐related costs at the time 

the change is executed• Owners should attempt to close out change order (full and final 

settlement) by including all direct and indirect costs and any time extensions due

30

Change Order Management

Page 16: Is Construction Cost Growth Breaking Your Budget?

Remember …

• Change is inevitable, find it early and deal with it.

• Unlike fine wine, changes do not get better with age.

• Always consider the schedule impacts of change –scope, schedule (is it on the critical path?), budget.

• Move for quick resolution – contract modifications should include scope, schedule and budget. 

31

Not all identified claims will result in actual claims, contractors will use 

them as place holders in case of need.

Claims Management

32

Page 17: Is Construction Cost Growth Breaking Your Budget?

Protocols for Managing Claims

• Inspectors’ logs• E‐mails• Critical Path Items • Schedule and Review times• Documentation• Weekly Construction Meetings• Put a time‐limit on filing claims• Ask at each project meeting if any claims are pending

33

Conflict Resolution Policy

1. Issues will be resolved at the lowest level.2. Time and cost impacts will be identified immediately.3. Issues will be resolved or elevated before impact on cost or 

time.4. Elevate together – elevation is not a sign of failure.  Identify 

issues and elevate ASAP as indicated above.5. Inaction is not an option.6. Time available to resolve issues before impact will be 

allocated as noted.7. Once made, a decision is owned and known by all.

34

Page 18: Is Construction Cost Growth Breaking Your Budget?

Keys to Claim Avoidance

• Is it on the critical path?

• Rapid and effective claims management process

• Clearly Defined/Understood Contract Documents

• Timely Attention to Time/Cost Impacts of Change

• Manufacturer/Builder Input in Design Process

• Directions in Writing

• Quick Turn‐Around of Submittals, RFIs and Proposals

• Realistic Expectations

• Partnering

• Third‐Party Intervention When Communication Stops!

• Accurate Daily Logs/Schedule

35

COMMUNICATE - COMMUNICATE - COMMUNICATE

Claims Prevention Checklist

36

A. PRE-DESIGN 1. Adjacent Properties

a. Have all properties adjacent to the site perimeter been reviewed in detail?

___

___

b. Are there: ___ ___ • Seasonal watercourses? ___ ___ • Heavy traffic patterns? ___ ___ • Other independent construction

activities? ___ ___

• Other __________________________ ___ ___ • Other __________________________ ___ ___

2. Boring (Subsurface) Data a. Are boring depths inconsistent? ___ ___ b. Are boring locations erratic or unusual? ___ ___ c. Are boring locations relevant to

construction:

• Are borings provided outside the area? ___ ___ • Are gaps left within the building area? ___ ___

d. What time of year were the borings taken? ___ ___

Yes No

www.RESMGT.com

Page 19: Is Construction Cost Growth Breaking Your Budget?

Where to Get More Information

1. PSMJ Web Site:  www.psmj.com2. Project Management Institute:  www.pmi.org3. Resolution Management Consultants: www.resmgt.com4. Other Professional Societies 

(APWA, ASCE, AIA, ACEC, NSPE, CMAA, ASLA, etc.)5. PSMJ’s Monthly PM Newsletter: PM Tactics (Ask about 

organization‐wide electronic distribution)

37

Thank You For Coming

?

Page 20: Is Construction Cost Growth Breaking Your Budget?

Project Planning 

Project Charter Table of Contents 

 

 

 

Table of Contents 1. INTRODUCTION .......................................................................................................................................1

1.1. PROJECT CHARTER PURPOSE .................................................................................................................11.2. PROJECT OVERVIEW..............................................................................................................................1

2. PROJECT OVERVIEW AND SCOPE.......................................................................................................2

2.1. PROJECT OBJECTIVE..............................................................................................................................22.2. SCOPE...................................................................................................................................................22.3. MAJOR DELIVERABLES..........................................................................................................................22.4. PROJECT JUSTIFICATION ........................................................................................................................32.5. ESTIMATED PROJECT COST....................................................................................................................3

3. PROGRAM GUIDANCE............................................................................................................................3

3.1. PROJECT SPONSOR ................................................................................................................................33.2. DESIRED COMPLETION ..........................................................................................................................33.3. BUDGET................................................................................................................................................43.4. KEY ISSUES ..........................................................................................................................................43.5. OTHER GUIDANCE.................................................................................................................................43.6. OTHER AVAILABLE INFORMATION.........................................................................................................4

3.7   Signature Page ……………………………………………………………………………………………………………….… 5 

Page 21: Is Construction Cost Growth Breaking Your Budget?

PSMJ| Resources, Inc. ©

1.800.537.PSMJ www.psmj.com

“Ready for Construction” Verification

PROJECT MANAGER’S NAME: PROJECT NAME: WORK ORDER #: PROJECT #: DATE: Signature of the person who verified information.

1. Plans have been checked by design team in the field within the previous thirty (30) calendar days and any resulting issues have been resolved.

2. Design and construction references have been checked, are appropriate

and are specifically identified by date and/or edition number. 3. The spatial datum (benchmark) has been identified, properly referenced and

located in the field, and adjacent existing improvements are referenced to the same datum.

4. There is a set of check prints on file verifying that the plans have been checked. 5. Specifications are not in conflict with the plans. In those instances where plans need to

contain specifications for clarification of the design, the project manager will verify that the reference is identified with the specifications.

6. Issues raised and errors found in the review processes (40%, 70%, 90%, etc.) are

reconciled and/or corrected in the final documents. 7. Pavement design has been reviewed and approved. 8. The IGA, if any, has been fully executed. 9. Environmental issues have been resolved. 10. Utility issues have been resolved. 11. Right of Way has been acquired and issues resolved. 12. Possible need for updated public notice or involvement has been evaluated.