ISLAMIC CENTER OF KENT (ICK) 2013 Annual Financial Report and Project
update
Prepared by:
ICK Executive Committee
November 24, 2013
1
Mission of the Islamic Center of Kent
Create physical, educational, and spiritual environment to facilitate development of a vibrant Muslim community in the city of Kent and South Puget Sound Region.
2
Goals of the Islamic Center of Kent
To develop infrastructural facilities that meets the growing needs of the Muslim community in the City of Kent and surroundings
To provide religious, educational, social, and recreational services for all strata of the community;
To develop the Center as place of meetings and deliberations for the Community
3
Objectives of the Islamic Center of Kent
To Plan, Design, and Implement the New Multi-purpose Building project by 2020 that can cater services to about 600 Musullees and 200 students;
To acquire and possess the neighbor’s land and building by 2015 and pay-off the installments by 2018.
To start a pre-elementary school (Pre-K & Pre-School) by 2015 and gradually upgrade to elementary school by 2020;
To triple the religious, educational, social, and recreational programs for the community from its existing level by 2018
To initiate and form a forum of the Leadership of the local Masjids in the Puget Sound to coordinate events of common interests by 2014.
4
Islamic Center of Kent, where is it?
• Name: Islamic Center of Kent
• Location: 20857, 20859, & 21009 SE 108th Ave SE, Kent, WA 98031
• Land Coverage: Approx. 2.25 acres (98,000 sft)
• Land Zoning: Commercial (72%) and Single Family Residential (RA-6) (28%)
• Future Zoning: Required RA-6 plot to rezone into Church Services Area
• Debt on Land & Building: $925,000
5
Islamic Center of Kent (Main Building) 6
Islamic Center of Kent (Women Building) 7
8 Islamic Center of Kent (Parking Lot)
Newly Bought Neighbor’s Property
9
Parcel View of the ICK Properties and Neighbor’s (Digital Music
System) Property
10
$807,000 $216,400
$40,000
Total: $1,063,600
FINANCIAL REPORT- 2013
11
ICK Income-Expense Statement (January – October)
12
Particulars Debit Credit
Gross Recipts : Donations/ charity Revenue $295,770.81
Total Revenue Collected $295,770.81Expenses:
Taxes and permits $3,798.94
Utilities $8,614.02
Repair & Maintenance $37,430.82
Salaries & Wages $32,855.14
Bank Fee $1,592.14
Supplies $2,282.70
Insurance $2,000.00
Funeral Exp $450.00
Masjid Khidmat Services $4,080.00
Zakat Distribution $20,064.34
Ramadan Affairs Exp $1,052.93
Fundraising Exp $13,419.17
Event Expenses $4,715.01
Planning & development Exp $51,482.07
Dishonored Checks $865.00
New Property Purchase $275,965.56
Total Expenses $460,667.84
Retianed Income ($164,897.03)
Income-Expense statement, 2013
ICK Balance Sheet as of October 31, 2013
13
Balance Sheet
Particulars
AssetsFixed AssetsOld LAND AND BUILDING (20857 & 20859) $535,000.00
New Land and Bulding (21009) $1,200,000.00
Less Depreciation @2.5% $43,375.00
Total Fixed Assets
$1,691,625.00
Opening cash with bank $300,308.33
Retained earning at the end of October'13 ($164,897.03)
Total Current Assets $135,411.30
Total Assets $1,827,036.30
Liabilities and Equity
Total Liability (New Land and Building) $925,000.00
TOTAL EQUITY WITH ORGANIZATION $902,036.30
Total Liabilities and Equity $1,827,036.30
ISLAMIC CENTER OF KENT
Period :01/01/2013 to 10/31/2013
2013 Budget Performance Analysis
14
Budget Items2013 Target
Amount ($)
Actual ($)
(Jan - Oct)
2013
Projected
Amount ($)
Actual
Perf. (%)
2013 Projected
Perf. (%)
Friday & Donation
Box Collection$50,000.00 $36,421.31 $43,705.57 72.84% 87.41%
Lunch Sale $15,000.00 $10,934.00 $16,719.01 72.89% 111.46%
ACH and Members
Contribution$20,000.00 $17,340.00 $21,768.00 86.70% 108.84%
Fund Raising in
Ramadan at ICK$100,000.00 $22,229.00 $22,229.00 22.23% 22.23%
Fund Raising from
FR events and
Masjid Visits
$300,000.00 $190,739.50 $215,229.10 63.58% 71.74%
Zakat Fund $20,000.00 $17,307.00 $20,768.40 86.54% 103.84%
Funeral Services
Fund$2,000 $800.00 $960.00 40.00% 48.00%
Grand Total: $507,000.00 $294,970.81 $340,419.08 58.18% 67.14%
DEVELOPMENT PROJECT REPORT- 2013
15
New Multi-purpose Building Project Goals
• Construct a medium size multipurpose Islamic Center for about 600 mosullees
• Project that expresses community identity
• Medium construction cost with a low life cycle cost materials
• Local funding source as much as possible
• Also seek funding from external sources
• Building in a shortest possible time (6-8 years) (2012-2020)
16
Major Functionalities Items Capacity Unit Space Total
Space (sft)
Prayer Hall with a mezzanine floor for ladies
600 mosullee 10 sft/person 6,000
Class Rooms (10)- 20’x 15’ 200 students 15 sft/student 3,000
Community Hall – 75’x 40’ 250-300 person @10-12 sft 3,000
Library & Conf. Room Office + Meeting/Counseling Rooms Imam’s Room Reception, Quiet, Lobby areas etc.
700 sft 650 sft 200 sft 1000 sft
3,000
Gymnasium/ Recreational Areas, Plus Other Facilities (Child & Elder Care, Funeral, Kitchen, Storage, etc.
2 units (Male and Female)
3,000 sft 1,000 sft
4,000
Surface/underground /Elevated parking space
150 (surface) 300 sft/car 45,000
Total Space required 19,000+45,000 = 64,000 sft 17
Islamic Center of Kent Site Layout Plan
18
Preliminary Cost Estimate Cost Items Area (sft) Unit
Rate ($) Total Estimated Cost ($)
Prayer Hall 6,000 $200 $1,200,000
Community hall/Class Rooms 6,000 $150 $900,000
Library, office & meeting rooms etc.
3,000 $200 $600,000
Gym & Recreational, Child care, Elder care, kitchen, Funeral, and other Facilities
4,000 $150 $600,000
Parking Stalls 45,000 $20 $900,000
Construction Contingency @15% $630,000
Total Construction Cost: ≈64,000 sft
$4,830,000 ≈5,000,000
19
Project Implementation and Cash flow Requirements
20
2013-14 2015-16 2016-17 2017-18 2018-19 2019-20
$650,000 $550,000 $1,600,000 $2,000,000 $1,000,000 $600,000
Conceptual Plan and Land Use
Permit
Detailed Design, Plan, and Specs, Building
Permit Construction
Bid Documents
Construction
Phase 1
Construction
Phase 2
Down payment for Neighbor’s
Property
Construction
Phase 3
Installment for Neighbor’s Property
Installment for Neighbor’s Property
Project Phasing (Planning and Design Phase)
Major Tasks
Plan & Designing Milestone Schedule
Estimated Expenditure
Task: 1 Feasibility study, Conceptual plans & design, internal space plan, geotechnical study, rezoning, pre. cost estimate. Land Use Permit
2012-13 $100,000
Task: 2 Marketing materials for fund raising, artist’s model, Rendering , Documentary, and Marketing website
2013-18 $50,000
Task 3 Acquisitioning of the Neighbor’s Property 2013-20 $1,200,000
Task: 4 Preliminary Design Plans and Specs (60% level)
2014 $150,000
Task: 5 Detailed Design Plans and Obtaining Building Permit
2015-16 $200,000
Total Cost (Planning & Design Phase ): $1,800,000 21
Project Phasing (Construction Phase)
Constn. Phases
Construction Details Milestone Schedule
Estimated Expenditure
Phase 1 Renovating the newly bought building into a pre-elementary school
2014 $100,000
Phase 2 Construction of Main prayer hall , Library, and office facilities
2016-17 $2,000,000
Phase 3 Construction of community/class rooms, Gym. & recreational facilities
2018-19 $1,700,000
Phase 4 Construction of surface parking space and access roads
2019-20 $1,200,000
Total Cost (Construction): $5,000,000 22
Consultants at Work
• Studio Senbel Architect + Design – PRIME
– Sub-Consultants
• David A. Clark Architects, PLLC : Associate Architects
• Pacific Land Engineering, Inc : Civil Engineering & Permit
• OTAC, Inc : Landscape Designer
• Heath and Associates Inc. : Traffic Consultant
• Other Consultants hired by ICK
– H&S Consulting : Wetland, Fisheries, and Wildlife Specialist
– Tayee Surveyors : Civil Surveying
– S.S. Geotechnical Services : Geotechnical Services
23
Jazakallahu khair for your time and patience!!
24
For Questions and comments, please contact:
Mizanur Rahman President, Executive Committee, ICK
[email protected] Cell: 206.432.6284