it tetra tech nus, inc. · 'it tetra tech nus, inc. 0 600 clark avenue, suite 3 king of prussia. pa...
TRANSCRIPT
-
TETRA TECH NUS, INC. 'It 600 Clark Avenue, Suite 3 King of Prussia. PA 19406- I433 0 Tel 6 10.49 1.9688 Fax 6 10.49 1.9645 w . t e t r a t e c h corn PHIL-I9226
June 10,2005
Project Number 7673
Mr. Robert Prince United States Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, Pennsylvania 19406-1415
Reference: RAC 3 Program EPA Contract No. 68-S6-3003
Subject: Health and Safety Plan (HASP) EPA Work Assignment No. 059-RICO-03DG Safety Light Corporation (SLC) Site Remedial Investigation/Feasibility Study (RVFS)
Dear Mr. Prince:
Enclosed please find one copy of the HASP for the subject site. The HASP was prepared by Tetra Tech NUS, Incorporated (TtNUS) under contract to the United States Environmental Protection Agency (EPA). Linda Dietz, EPAs remedial project manager for this site, has directed TtNUS to provide this plan to you.
If you have any questions, please do not hesitate to contact me at 610-491-9688.
Sincprely,
;kndrew /e- bowitz l L 1 I . Project dfanager
C: Linda Dietz (EPA Region 3) File 6.3
NMSSIRGNl MATERIALSOOZ
-
HEALTH AND SAFETY PLAN
REMEDIAL INVESTIGATION / FEASIBILITY
STUDY
SAFETY LIGHT CORPORATION
BLOOMSBURG, COLUMBIA COUNTY, PENNSYLVANIA
EPA WORK ASSIGNMENT NUMBER 059-RICO-03DG
TETRA TECH NUS PROJECT NUMBER 7673
RAC 3 PROGRAM
CONTRACT NUMBER 68-S6-3003
MAY 2005
TETRA TECH NUS, INC.
-
HEALTH AND SAFETY PLAN
REMEDIAL INVESTIGATION / FEASIBILITY
STUDY
SAFETY LIGHT CORPORATION
BLOOMSBURG, COLUMBIA COUNTY, PENNSYLVANIA
EPA WORK ASSIGNMENT NUMBER 059-RICO-03DG
TETRA TECH NUS PROJECT NUMBER 7673
RAC 3 PROGRAM
CONTRACT NUMBER 68-S6-3003
MAY 2005
-
HEALTH AND SAFETY PLAN
REMEDIAL INVESTIGATION / FEASIBILITY
STUDY
SAFETY LIGHT CORPORATION
BLOOMSBURG, COLUMBIA COUNTY, PENNSYLVANIA
EPA WORK ASSIGNMENT NUMBER 059-RICO-03DG
TETRA TECH NUS PROJECT NUMBER 7673
RAC 3 PROGRAM
CONTRACT NUMBER 6866-3003
MAY 2005
-
HEALTH AND SAFETY PLAN
REMEDIAL INVESTIGATION / FEASIBILITY
STUDY
SAFETY LIGHT CORPORATION
BLOOMSBURG, COLUMBIA COUNTY, PENNSYLVANIA
EPA WORK ASSIGNMENT NUMBER 059-RICO-03DG
TETRA TECH NUS PROJECT NUMBER 7673
RAC 3 PROGRAM
CONTRACT NUMBER 6846-3003
MAY 2005
-
HEALTH AND SAFETY PLAN
REMDIAL INVESTIGATION/FEASIBlLlTY STUDY
SAFETY LIGHT CORPORATION BLOOMSBURG, COLUMBIA COUNTY, PENNSYLVANIA
EPA WORK ASSIGNMENT NUMBER 059-RICO-03DG EPA CONTRACT NUMBER 6846-3003
TETRA TECH NUS PROJECT NUMBER 7673
Tetra Tech NUS, Incorporated 600 Clark Avenue, Suite 3
King of Prussia, Pennsylvania
MAY 2005
SUBMITTED BY: APPROVED gY:
TETRA TECH NUS, INC. PITTSBURGH, PENNSYLVANIA
TETRA TECH NUS, INC. KING OF PRUSSIA, PENNSYLVANIA
-
TABLE OF CONTENTS
.
I
.
_-
.
..
SECTION PAGE
1 . 0 INTRODUCTION ........................................................................................................................... 1.1 SITE HISTORY AND BACKGROUND ............................................................................. 1-2 1.1
1.2 KNOWN WASTE/DISPOSAL ........................................................................................... 1-2 1.2 SUMMARY OF PREVIOUS INVESTIGATIONS .............................................................. 1-4
2.0 SCOPE OF WORK ........................................................................................................................ 2-1
3.0 PROJECT TEAM ORGANIZATION .............................................................................................. 3-1 3.1 3.1 . 1 TtNUS Project Manager 3-1 3.1.2 3.1.3 3.1.4 3.1.5
KEY PROJECT PERSONNEL AND ORGANIZATION .................................................... 3-1
TtNUS RAC 3 Health and Safety Manager ...................................................................... 3-1 TtNUS Field Operations Leader ....................................................................................... 3-2 Site Safety Officer ............................................................................................................. 3.2
...................................................................................................
TtNUS and Subcontractor Personnel ............................................................................... 3-3
4.0 TRAININGMEDICAL SURVEILLANCE REQUIREMENTS ......................................................... 4-1 4.1 INTRODUCTORY/REFRESHER/SUPERVISORY TRAINING ........................................ 4-1
4.2 SUBCONTRACTOR EXCEPTIONS ................................................................................ 4-1 4.3 SITE-SPECIFIC TRAINING .............................................................................................. 4-2 4.4 OTHER TRAINING ........................................................................................................... 4-2 4.5 MEDICAL SURVEILLANCE ............................................................................................. 4-2
4.1.1 4.1.2
Requirements for Tetra Tech NUS Personnel .................................................................. 4-1 Requirements for Subcontractors ..................................................................................... 4-1
4.6 MEDICAL DATA SHEETS ................................................................................................ 4-3
5.0 HAZARD ASSESSMENT .............................................................................................................. 5-1 5.1 5.1.1 5.1.2 5.2 5.2.1 5.2.2 5.2.3 5.2.4 5.2.5 5.2.6 5.2.7 5.2.8 5.2.9 5.3 5.3.1
CHEMICAL HAZARDS ..................................................................................................... 5-1 Site Contaminants ............................................................................................................ 5-1
Heavy Equipment Hazards .............................................................................................. 5-2
Slips, Trips, and Falls ....................................................................................................... 5-3
Drum Handling .................................................................................................................. 5-5
Severe Weather ............................................................................................................... 5-7 Heat and Cold Stress ....................................................................................................... 5-7
Fauna ............................................................................................................................... 5-9
Chemical Used On Site .................................................................................................... 5-2 PHYSICAL HAZARDS ...................................................................................................... 5-2
Energized Systems ........................................................................................................... 5-2
Heavy or Awkward Lifting ................................................................................................. 5-3 Portable Power Hand Tools .............................................................................................. 5-3
Compressed Gases .......................................................................................................... 5-6
BIOLOGICAL HAZARDS .................................................................................................. 5-9
5.3.1.1 Venomous Snakes .......................................................................................................... 5-9 5.3.1.2 Insects and Spiders ........................................................................................................ 5-10 5.3.1.3 Other Animals ................................................................................................................. 5-11 5.3.2 Flora ............................................................................................................................... 5-12
ii
-
.
. TABLE OF CONTENTS CONTINUED
..
.
..
.
SECTION PAGE
6.0 AIR MONITORING ........................................................................................................................ 6-1 INSTRUMENTS AND USE ........................................................................................... 6-1
HAZARD MONITORING FREQUENCY ....................................................................... 6-1 INSTRUMENT MAINTENANCE AND CALIBRATION ................................................. 6-1
6.1
6.2 6.3
6.1.1 Photoionization Detector ............................................................................................... 6-1
7.0 PERSONAL PROTECTIVE EQUIPMENT .................................................................................... 7-1 7.1 LEVELS OF PROTECTION ......................................................................................... 7-1 7.2 SELECTION OF LEVELS OF PROTECTION .............................................................. 7-1 7.3 RESPIRATORY PROTECTION PROGRAM ................................................................ 7-2 7.4 DECONTAMINATION .................................................................................................. 7-2
8.0 SITE CONTROL MEASURES ...................................................................................................... 8-1 8.1 EXCLUSION ZONE .......................................................................................................... 8-1
8.2 CONTAMINATION REDUCTION ZONE .......................................................................... 8-1 8.3 SUPPORT ZONE ............................................................................................................. 8-2 8.4 SITE VISITORS ................................................................................................................ 8-2 8.5 SITE SECURITY AND ACCESS ...................................................................................... 8-3 8.6 SITE MAP ......................................................................................................................... 8-3 8.7 BUDDY SYSTEM ............................................................................................................. 8-3 8.8 MATERIAL SAFETY DATA SHEET (MSDS) REQUIREMENTS ..................................... 8-4 8.9 COMMUNICATION .......................................................................................................... 8-4 8.10 SAFE WORK PERMITS ................................................................................................... 8-4
8.1.1 Exclusion Zone Clearance ................................................................................................ 8-1
9.0 SITE HEALTH AND SAFETY STANDARD OPERATING PROCEDURES ................................. 9-1 9.1 GENERAL SAFE WORK PRACTICES ............................................................................ 9-1 9.2 DRILLING OPERATIONS - SAFE WORK PRACTICES ................................................. 9-3 9.2.1 Before Drilling Operations ............................................................................................... 9-3 9.2.2 During Drilling Operations ................................................................................................ 9-3 9.2.3 After Drilling Operations ................................................................................................... 9-4
10.0 EMERGENCY RESPONSE / CONTINGENCY PLAN ................................................................ 10-1 10.1 INTRODUCTION ............................................................................................................ 10-1 10.2 EMERGENCY PLANNING ............................................................................................. 10-1 10.3 EMERGENCY RECOGNITION AND PREVENTION ..................................................... 10-2 10.3.1 Recognition ..................................................................................................................... 10-2 10.3.2 Prevention ....................................................................................................................... 10-3 10.4 EVACUATION ROUTES, PROCEDURES, AND PLACES OF REFUGE ...................... 10-3 10.5 DECONTAMINATION PROCEDURES / EMERGENCY MEDICAL TREATMENT ....... .1 0-4 10.6 EMERGENCY CONTACTS ............................................................................................ 10-4 10.7 EMERGENCY ALERTING AND ACTION/RESPONSE PROCEDURES ....................... 10-8 10.8 PPE AND EMERGENCY EQUIPMENT ......................................................................... 10-8 10.9 INJURY/ILLNESS REPORTING .................................................................................... 10-9
iii
-
TABLE OF CONTENTS CONTINUED
SECTION PAGE
11 .O SPILL CONTAINMENT PROGRAM ........................................................................................... 11-1 11.1 SCOPE AND APPLICATION .......................................................................................... 11 -1 1 1.2 POTENTIAL SPILL AREAS ............................................................................................ 11-1 1 1.3 CONTAINMENT AREAS ................................................................................................ 11 -1 11.3.1 IDW ................................................................................................................................ 11-2 11.3.2 Flammable/POL Storage ................................................................................................ 11-2 1 1.4 MATERIALS HANDLING ................................................................................................ 11-2 1 1.5 LEAK AND SPILL DETECTION ..................................................................................... 11-3 11.6 PERSONNEL TRAINING AND SPILL PREVENTION ................................................... 11-3 1 1.7 SPILL PREVENTION AND CONTAINMENT EQUIPMENT ........................................... 11 -3 1 1.8 SPILL CONTAINMENT/CONTROL RESPONSE PLAN ................................................ 11 -4
12.0 CONFINED SPACE ENTRY ....................................................................................................... 12-1 13.0 HAZARD COMMUNICATION ..................................................................................................... 13-1 14.0 MATERIALS AND DOCUMENTS ............................................................................................... 14-1
14.1 MATERIALS TO BE POSTED AT THE SITE ................................................................. 14-1
15.0 GLOSSARY ................................................................................................................................. 15-1
ATTACHMENTS
ATTACHMENT I - INJURYALLNESS PROCEDURE AND REPORT FORM ATTACHMENT I1 - MEDICAL DATA SHEET ATTACHMENT 111 -TICK CONTROL AND LYME’S DISEASE INFORMATION ATTACHMENT IV -TASK HAZARD ASSESSMENT SUMMARY TABLE ATTACHMENT V - CHEMICALS/RADIONUCLIDES OF CONCERN TABLE ATTACHMENT VI -SAFE WORK PERMITS ATTACHMENT VI1 - EQUIPMENT INSPECTION CHECKLIST ATTACHMENT Vlll - SOP FOR UTILITY CLEARANCE ATTACHMENT IX - SOPS FOR RADIOLOGICAL INSTRUMENT USE
TABLES
NUMBER PAGE
10-1 Emergency Contacts ................................................................................................................... 10-7
iv
-
TABLE OF CONTENTS CONTINUED
FIGURES
NUMBER PAGE
4-1
6-1
8-1
10-1
10-2
Site-Specific Training Documentation ......................................................................................... ..4-4
Safe Work Permit .......................................................................................................................... 8-5 Emergency Response Protocol ................................................................................................... 10-5 Bloomsburg Hospital ................................................................................................................. 10-1 0
Documentation of Field Calibration ............................................................................................... 6-3
V
-
1 .O INTRODUCTION
This Health and Safety Plan (HASP) has been developed to provide practices and procedures for Tetra
Tech NUS, Inc. (TtNUS) personnel and subcontractors engaged in site activities related to the Remedial
Investigation / Feasibility Study at the Safety Light Corporation (SLC) Site in Btoomsburg, Columbia
County, Pennsylvania. This HASP has been developed to comply with Title 29 Code of Federal
Regulations (CFR), Part 1910.120 (29 CFR 1910.120) and 29 CFR 1926.65.
This HASP contains the following general information:
Identification of tasks and potential hazards associated with soil, groundwater, surface water and
sediment, ecological and air investigation activities as well as site reconnaissance, topography
surveying, ecological characterization, and multimedia sampling tasks;
Listing of contaminants of concern and the associated hazards;
Required personal protective equipment (PPE), depending on the activity being performed and the
nature of the identified contaminants and physical hazards;
Employee health and safety training requirements;
Emergency response information;
Medical surveillance requirements;
Site control measures;
Confined space entry requirements;
Spill containment requirements;
Frequency and types of air monitoring and exposure monitoring, and;
Decontamination procedures.
This HASP has been developed using the latest available information regarding known or suspected
chemical contaminants and potential physical hazards associated with the proposed work at the Safety
Light Corporation Site. Modifications or updates may be deemed necessary based on expanded scope
or work, updated chemical contaminant information, TtNUS policy or procedural changes, revised
emergency contact information or emergency response procedures, or other conditions that justify
modification of this document. Changes to the HASP will be made with the approval of the TtNUS Project
Manager (PM) and RAC 3 Health and Safety Manager (HSM). Any requests for modifications of this plan
based on field observations will be directed to the HSM, who will determine if the changes are necessary.
1-1
-
--
x
As a supplement to the HASP, the Tetra Tech NUS, Inc. Health and Safety Guidance Manual provides
additional information on many health and safety related topics and provides various company-specific
Standard Operating Procedures (SOPS). This document is referenced throughout this HASP, and will be
available for use by field personnel performing work at the site.
1.1 SITE HISTORY AND BACKGROUND
The SLC facility is located at 4150-A Old Berwick Road, Bloomsburg, Pennsylvania, within the South
Centre Township of Columbia County in central Pennsylvania, about 6 miles east of Bloomsburg and 6
miles west of Berwick. The north site boundary is the Old Berwick Road and the south site boundary is
the Susquehanna River. The site is completely fenced on all sides. SLC owns the Vance-Walton property
located along the southeast corner of the site. Other residential tracts of land are adjacent to the east and
west boundaries of the site. The site is about 10-acres in extent and contains numerous structures and
contaminated areas, including lagoons, dumps, an abandoned canal, and buildings. SLC utilizes a 2-acre
area of the site for its current manufacturing operations. In the 8-acres not under NRC license, third party
companies, USR Metals, Inc. and Multimetals Products Corporation, conduct nonradiological
manufacturing processes that include metal finishing and plating.
Activities at the site have varied over time and involved a number of different radionuclides including, but
not limited to, radium-226 (=Ra), tritium (3H), strontium-90 (%r), americium-241 (241Am), and cesium-
137 (137Cs). Fuel oil, solvents, and heavy metals were also used at the site. During site operations,
buildings, soils, and groundwater at the site have become contaminated with radionuclides. There is also
evidence of vinyl chloride contamination in groundwater. A detailed site history including results of
previous investigations may be found in the Site-Wide RI/FS Work Plan (TtNUS, 2005).
1.2 KNOWN WASTE/DISPOSAL
Wastes generated at the SLC facility include solid and liquid waste streams contaminated with radioactive
materials, including =%A, %r, 137Cs, 241Am, and 3H. Contaminated laboratory glassware was buried on the
property. Contaminated solids were placed inside two old silos buried in the ground (refer to building number 14 on Figure 1-2). According to groundwater analytical data collected by Foster Wheeler in 2000 and
Monserco in 1995, the old silo shows a wSr and '37Cs plume going towards the Susquehanna River.
Concentrated liquid wastes were allowed to evaporate, and the dry residuals were transferred to the
Radiological Services Company. Additionally, plant effluent was discharged into the abandoned canal,
located adjacent to the Susquehanna River. These canals were a series of about five individual
impoundments that were all part of the former river bed. The canals were filled with river water, allowing the
wastes in them to be diluted prior to discharge into the Susquehanna River.
1-2
-
From 1948 to 1954, the east lagoon was used for the disposal of sewage and process wastewater from the
radium laboratory in the main building. In 1960, the contents of the east lagoon were pumped into the west
lagoon. During the May 2001 NRC site visit, an oily spot was observed in the middle of the base of the east
lagoon. Also, an 8 or 10-inch diameter outfall was observed in the east lagoon; origin unknown.
The west lagoon was used for the disposal of liquid waste including silver plating wastes and anodizing
solutions from USR (before 1982) and SLC (after 1982) operations (Figure 1-2). Low-level radioactive waste
reportedly was buried in the west lagoon. Also as noted above, in 1960 the east lagoon was pumped into the
west lagoon.
The east and west lagoons are located in the 100-year floodplain and were reportedly flooded in 1972, mixing
with flood waters. Contents of the lagoons were dispersed on the site property and in the Susquehanna
River.
Three disposal areas are located on the facility; the abandoned canal, and two disposal pits (east and west
plant dumps) (Figure 1-2). The abandoned canal was used for the disposal of =RA contaminated ductwork
and liquid waste from radiological production activities. The east plant dump encompasses areas between
the east and west lagoons, and was identified in 1972 during a storm sewer installation. The west plant
dump is adjacent to the western property line and fence. During a May 2001 NRC site visit, the east plant
dump contained piles of pallets, old chain-link fences, old pipes, windows, cinder blocks, and sheet metal. In
1948 and 1949, the west plant dump was used for the disposal of solid waste. The west plant dump also
was used for the disposal of =RA dials and wSr deck markers.
_-
Four 2,400-gallon aboveground storage tanks (ASTs) housed in the Liquid Waste Building contain 3H
contaminated wastewater from the Tritium or Nuclear Building (refer to building number 11 on Figure 1-2).
The wastewater is transported through a below-grade drain line and enters a concrete sump that is about 7
feet deep. The wastewater is then pumped into one of the 2,400-gallon ASTs for dilution. The 3H
contaminated wastewater is diluted to a concentration of 3 x l o 3 pCi/mL, then is released to the North Branch of the Susquehanna River. According to groundwater analytical data collected by Monserco in 1995,
a VOC plume containing vinyl chloride, 1,1,1 -trichlorethane, 1,l -dichloroethane, and cis-l,2-dichloroethane
emanates from the area of the Liquid Waste Building and flows toward the Susquehanna River.
Another potential source for onsite contamination is an underground storage tank (UST) formerly used to
store 3H contaminated wastewater. Prior to 1972, 3H contaminated wastewater was previously contained in
below-ground tanks in a vault in the basement of the Liquid Waste Building. In 1972, the North Branch of the
Susquehanna River flooded the building and a tank containing 3H contaminated wastewater was uprooted
1-3
-
from its location and dispersed in the flood water. Before the flood, the tank contained about 500-gallons of
H contaminated wastewater. The flood water was sampled and detected 3H contamination. The remaining
tank was subsequently filled and the vault was capped. The remainder of the building was filled with soil and
covered with a concrete slab.
1.3 SUMMARY OF PREVIOUS INVESTIGATIONS
3
Since the 1960 time frame, the company has undertaken various clean-up efforts including decontamination
of buildings, backfilling of on-site lagoons and removal of soils contaminated with =RA. These clean-up
efforts are not well documented.
According to site documents, eight environmental investigations of the SLC site have been conducted since
1978. Six environmental summary reviews were also prepared from available data. These investigations
and environmental reviews are further described below.
1978 Giles Drilling Corporation, on behalf of USRC, initiated groundwater monitoring with the installation of
monitoring wells 1, 2, and 3 located in the southern portion of the facility south of the underground silo area. Soil and groundwater from these wells provided initial data on contamination levels and
suggested that additional monitoring was required. No investigational report or initial groundwater
monitoring data is available from this investigation; however boring logs for these wells are included
in the Meiser & Earl Report discussed below.
1979 Meiser & Earl Hydrogeologists, on behalf of USRC, conducted a hydrogeological investigation, including installation of thirteen monitoring wells and three wells for background (wells 4 through 19).
The thirteen monitoring wells were located around the abandoned canal, the east and west lagoons,
and the disposal pits. Investigation activities commenced on January 29, 1979, and were completed
in March 1979. Objectives of the investigation were to determine the depths to groundwater, water-
table gradients and flow directions, existing water quality, extent of any radiological contamination
from abandoned disposal areas, and to propose appropriate pollution abatement techniques.
Investigation activities included the collection of interval soil samples for textural classification and
radioactivity analysis and the construction of screened or cased wells from which water samples
could be collected. The investigation activities revealed hydrogeological information at the site; the
site is underlain by fluvio-glacial deposits and static water levels revealed that water flow across the
site is essentially from the north to the south (towards the Susquehanna River), except during limited
periods when flooding occurs and flow is temporarily blocked locally by a groundwater mound.
1979 Radiation Management Corporation (RMC) conducted a radiological investigation in conjunction
with the Meiser & Earl Investigation. RMC reportedly used soil and groundwater collected both
by Meiser & Earl and by themselves for radiological analysis. This report concluded that
1-4
-
although Contamination was evident, no significant public health hazard was present and
remediation was neither appropriate nor justified at that time. However, continued and additional
environmental monitoring was suggested.
1981 Oak Ridge Associated Universities (ORAU) performed an environmental survey under contract
to the NRC. ORAU conducted survey activities at the SLC site in June and August, 1981. This
survey reviewed the SLC’s program for controlling and monitoring radiation and radioactivity
levels. Data were collected to confirm measurements performed by the licensee, to evaluate the
adequacy and accuracy of environmental controls and monitoring procedures, and to determine
if environmental contamination was occurring. Survey activities include the measurement of
direct radiation levels in unrestricted areas around the entire property, monitoring routine
releases of tritium in stack air and liquid effluents from SLC activities and measurement of
radionuclide concentrations in the environment as a result of present and previous operations of
SLC and USRC. Boreholes were drilled for the collection of subsurface soils; however no
monitoring wells were installed. Media sampled were surface and subsurface soil, groundwater,
vegetation, surface water, and aquatic organisms, both on and off -site.
The main conclusions of this study were that direct radiation levels were above the regional
background levels at the site, but were below federal guidelines for unrestricted use. However,
on-site soil sampling indicated elevated levels of =%A, wSr, and 13’Cs and groundwater
sampling showed levels of 3H and ?3r exceeding NRC and EPA guidelines for unrestricted use.
The study concluded that contaminants were migrating into soil and groundwater, but did not
appear at that time to be accumulating off-site although ORAU indicated this to be a potential
future concern.
1988 NRC performed an environmental evaluation of the site using available monitoring data. The
objective of this evaluation was to compile information about on-site contamination, to assess
the hazards to nearby residents, and to make recommendations about further remediation
actions. The NRC concluded that the disposal of radioactive wastes at the SLC site had caused
extensive contamination of groundwater on and off-site, and of soil on-site. The study identified
areas where decontamination work should be focused. Decontamination efforts should focus on
cleanup and control of the disposal silos, open dumps, and contaminated soils in order to
minimize further contamination spread. The NRC evaluation also identified that further
characterization work was necessary, covering both radiological and non-radiological hazardous
constituents.
1990 Chemical Nuclear Systems, Inc. (CNSI) conducted a hydrogeological and radiological evaluation
of the SLC facillty in June and July 1990. This study was a response to a Partial Interim
1-5
-
Settlement Agreement between USR Industries and the NRC. This settlement required partial
studies of the nature, scope, location, and movement of radioactive contamination at the SLC
facility. This evaluation was also intended to provide characterization data required to be
collected by the NRC according to the settlement agreement. The evaluation was not
considered comprehensive in scope. The primary objectives of this study were to assess the
hydrogeologic flow regime and the potential for off-site radiological migration from the site.
Activities conducted include soil coring, installation of 9 monitoring wells (wells A through I) and
groundwater and rainwater sampling.
The study indicated that groundwater flow is in a southerly direction toward the Susquehanna
River, and confirmed the presence of radioactive contamination within the soil and groundwater.
Off-site wells showed evidence of 3H and the highest level was measured at the Vance-Walton
well. Groundwater samples also showed evidence of %3r from adjacent properties to the east
and west of the SLC site. Levels of radionuclides detected were below drinking water standards.
The study recommended further environmental monitoring and site characterization work.
1991 NUS Corporation Superfund Division prepared Preliminary Assessment (PA) for EPA using all existing SLC reports. This document concluded that the soil and groundwater remained
contaminated primarily with =RA, ?3r, 13’Cs, and 3H as a result of waste disposal practices
employed during the history of the site.
1993 In 1993 and 1994, Roy F. Weston Technical Assistance Team (TAT), tasked by EPA Region 3, conducted soil and groundwater sampling at the SLC property and vicinity. The TAT
recommended the following upon completing the sampling activities: clean out a tub full of blue-
colored residue with standing liquid, pH equal to 0, in the Metal Etching Building, remove empty,
rusting drums scattered along the west lagoon edge, check state regulations for applicable laws
regarding tank removal due to a tank overfill located east of MW11, and recommended that a filterkcreen be placed at the outlet of a compressor exhaust in the Carpenter shop. The soil
samples detected some contaminants, however none met or exceeded EPA action levels.
1994 Ecology and Environment, Inc. (E&E), tasked by the NRC Region I office, conducted a file
review in support of the Hazard Ranking System (HRS) Package which was being prepared by
E&E. The file review found that several inspection reports, two in 1980 and one in 1986,
prepared by NRC indicate elevated 3H concentrations in the neighboring residential wells,
including the Vance Walton and Murphy wells; however, levels detected were below drinking
water standards. It was also noted that NRC inspection reports reveal that 3H, nsRA, and %r
have been detected consistently in on-site groundwater at concentrations exceeding NRC
guidelines for unrestricted area.
1-6
-
1994 In 1994, Monserco Limited prepared a Characterization Plan for SLC to quantify the physical and
radiochemical characteristics of radiological contamination and it's distribution, assess non-
radiological constituents and their effect on radiological constituents, evaluate environmental
impacts, assess associated hazards from existing and potential future radiological contamination
under the conditions of unrestricted use, and finally to provide sufficient information to develop a
closure plan for the site. This plan outlined the methods and technologies to be used as part of
the site survey and detailed each survey location in regards to area to be sampled and quantity
of samples to be taken.
1995 SLC commissioned Monserco Limited to conduct a site characterization. These activities were
conducted between May 1995 and December 1995. Objectives of the site characterization were
to determine the extent of radiological contamination on ground surfaces, determine whether radioactive contaminated items are buried under the SLC grounds, gain access to the two
underground silos and obtain information on their contents, drill new boreholes and wells (wells
M1 through M13), sample and analyze the subsurface soils and waters, and determine the extent of radiological contamination inside the buildings.
Monserco conducted electromagnetic surveys at the site. Four anomalies indicating large
metallic objects were detected using the survey: two underground silos, an anomaly located east
of the Well House indicative of an underground storage tank, and linear anomalies located in the
same vicinity that may be buried pipes associated with the underground storage tank. Two
anomalies representing large metallic objects were located south of the Etching Building and
west of the Pipe shop. Numerous anomalies associated with isolated buried objects were
detected. The highest density of these anomalies was located south of the Solid Waste Building
and Liquid Waste Building in the abandoned canal. A number of linear anomalies identified
across the property may indicate buried pipes or cables.
Eight trenches were excavated revealing the canal bottom, metal debris, and glass. Thirteen
boreholes were drilled at various locations on the SLC site to assess the radiological and non-
radiological condition of the subsurface soils and to install additional groundwater monitoring
wells. Cored material was monitored every two feet for radiation using a contamination probe.
Positive radiation readings were recorded for soils from boreholes M2, M3, M4, M5, M6, M7, M9, M10, M11, M12, and M13. Hydrocarbon odors were reported by field crew during drilling at
boreholes M1, M8, M9, and M13. Organic vapors were monitored using a photo ionization
detector (PID). Positive results were obtained from boreholes M1 and M7.
1-7
-
... .
Results from monitoring well sampling showed elevated levels of radionuclides, most notably
Cs, in groundwater near the buried silos (M9, M13) and in a southerly (downgradient) direction
at wells M4 and M5. Vinyl chloride (up to 30 ug/l) was also detected in monitoring wells in the
vicinlty of the Liquid Waste Building in wells Mi, M8, and M1 1 .
137
2000 A Health Consultation Report documenting past sampling data was issued by the Agency for
Toxic Substances and Disease Registry (ATSDR) in April 2000. The report concluded that
radioactive materials, specifically %A, %r, 13Cs, 3H and 241Am, have been used and
disposed in silos, lagoons, and holding tanks associated with the SLC. From these disposal
practices, radioactive material has contaminated the on-site areas of the SLC and perhaps
nearby off-site residential wells (3H only). The contaminants in the residential wells are not at
levels of public health concern. The amount of land contaminated has been exacerbated by a
flood of the Susquehanna River in 1972.
ATSDR reviewed environmental sampling data collected during three characterization events
from 1980 until 1996. The results indicated that surface soils are contaminated with and
Cs and that the contamination has apparently seeped from the soils to the groundwater. Soil
contamination is mostly to the south and southeast of the main buildings. Although the
contamination has not yet reached the river, data strongly suggest the contamination is migrating
in that direction. Additional contamination associated with the site is predominately between the
main site buildings and the river but external exposure to ionizing radiation is localized along the
outside of the buildings.
1 37
2000-
2001 The Pennsylvania Department of Environmental Protection (PADEP) implemented a Hazardous
Sites Cleanup Act (HSCA) funded assessment of the SLC property. Foster Wheeler
Environmental Corporation was contracted to conduct the site assessment activities, which were
completed in August 2000. The primary objectives of this assessment were to perform sample
collection and analysis of surface water and groundwater in and around the site. Activities
included collection of groundwater from monitoring wells, collection of surface water from the
adjacent Susquehanna River, and collection of water from nearby residential wells. Sample
results indicate that the groundwater and potentially the surface water at the SLC site are
impacted by previous site activities.
Analytical results indicate that groundwater is impacted by radionuclides and some inorganic
analyies. The majority of groundwater sample results confirm the presence of radionuclides
above non-detect levels. Comparison of the groundwater analytical results indicated that many
samples exceeded the EPA drinking water maximum contaminant levels (MCLs) for gross
1-8
-
alpha, gross beta, %A, 228RA, and %3r. The highest concentrations of radionuclides were
found in the groundwater collected from the monitoring wells closest to the location of the
underground waste disposal silos, wells M9 and M10. None of the residential well sample
results were found to exceed the EPA MCLs for radionuclides. There were inorganic analytes
detected above the PADEP Act 2 Medium-Specific Concentration (MSCs). Some of these
exceedences may be attributed to the elevated level of suspended solids in the groundwater
samples. Lead and copper exceeded the PADEP Act 2 MSCs in one of the residential well
water samples. As copper was not detected in other groundwater samples, the elevated copper
levels may be attributed to the residential plumbing system.
Low-level organic contaminants were detected in the groundwater samples collected from the
site. Vinyl chloride and bis(2-ethylhexy1)phthalate were the only organic contaminants to exceed
the PADEP Act 2 MSCs, and were detected in samples from only one monitoring well, M9.
None of the residential well samples exceeded the PADEP Act 2 MSCs for VOCs or SVOCs.
Analyses for radionuclides in surface water collected from the Susquehanna River show that low
concentrations are present. Standards for radionuclide concentrations in surface water were not
used for data comparison, as none were determined applicable for this event by PADEP. All
surface water sample results were below the inorganics Water Quality Criteria for Toxic
Substances and surface water samples were not analyzed for VOCs or SVOCs.
2001 ICF Consulting submitted a Review and Evaluation of Characterization Data for SLC in October
2001. This report was prepared under contract to the NRC. The report presented prior
characterization data, an evaluation of the completeness of the data, and suggested where
additional data could increase the current understanding of the site and refine future cost estimates. The ICF report concluded that operations have resulted in the radiological
contamination of every building (except for the Old Radium Vault) at the site. It should be noted that, although it is believed that radioactive sources have been removed from the Old Radium
Vault, access to the building was not possible due to a collapsed roof. Due to structural damage
at some buildings, remediation is most likely not possible due to entry restrictions. Many
buildings still contain contaminated waste, equipment, and source material. The majority of the
surface soils at the site are contaminated with at least one radionuclide at levels exceeding the
Derived Concentration Guidance Levels (DCGLs) as reported as either actually detected
concentrations or presumed by analytical detection limits in excess of the DCGLs. The DCGLs
were calculated in the Monserco report using guidelines in effect at that time. The DCGLs were
considered remediation goals to achieve acceptable levels of radiological levels to return the
property to unrestricted The primary radioactive isotopes of concern in surface and subsurface
soils are 226RA, 13’Cs, 241Am, and ?3r. The primary radioactive isotopes of concern in
1-9
-
1
groundwater are 3H, =RA, 13’Cs, 241Am, and ?3r. Daughter isotopes of 226RA, such as 214Pb
and 214Bi, have also been found in the surface and subsurface soils and groundwater.
2002- 2004 A 1994 settlement by NRC with SLC required SLC to remove and dispose radioactive wastes
stored in the underground silos. By June 2000, SLC had removed the waste and placed it in 176
55-gallon drums and 26 containers each containing approximately 3.55 cubic yards of material.
These waste drums and containers; however, were placed in the floodplain of the Susquehanna
River approximately 200 feet from the river. In 2002 EPA conducted a removal assessment of
these materials and entered into an administrative order of consent with SLC to relocate the
waste in a secure area on the property outside the floodplain and arrange for disposal at an
NRC-licensed facility. SLC did not comply with the consent order and EPA commenced
implementation of a RA. The drums and containers were moved to a secure location outside
the floodplain in December 2004 and are waiting for transport and disposal at a licensed facility.
2004 Lockheed Martin Services, under contract to EPA, submitted an Aerial Photographic Analysis of
SLC in December 2004, showing site conditions from 1938 until 1999. Significant site features,
including lagoons and dump areas are shown, although resolution of several of the photographs
is poor.
1-10
-
2.0 SCOPE OF WORK
This HASP addresses health and safety issues associated with field activities related to the RI at the SLC
Site. Detailed information on planned site activities is provided in the Field Sampling Plan (FSP). Site
activities addressed within this plan include:
0 Mobilization/Demobilization and Site Reconnaissance including topographic surveying and
residential well inventory
Groundwater Investigation including refurbishment of existing and installation of new groundwater
monitoring wells, groundwater and effluent water sampling.
0
0 Equipment Cleaning/Decontamination
0 Investigation-derived wastes (IDW) Management
This HASP will be modified if additional site activities are to be performed by TtNUS personnel, or if other
site conditions change (new information on contaminants of concern, changes in how work is going to be
performed, personnel changes, etc.). or this his HASP discusses many of the hazards associated with
these site activities as well as safe work practices that will be used to mitigate the hazards and to protect
site personnel, the environment, and site property.
.- .
2-1
-
3.0 PROJECT TEAM ORGANIZATION
3.1 KEY PROJECT PERSONNEL AND ORGANIZATION
This section defines responsibility for site safety and health for TtNUS employees engaged in onsite
activities. Personnel assigned to these positions will exercise the primary responsibility for onsite health
and safety. These persons will be the primary point of contact for any questions regarding the safety and
health procedures and the selected control measures that are to be implemented for onsite activities.
3.1.1 TtNUS Proiect Manaqer (PM)
The TtNUS PM is responsible for the overall direction of health and safety for this project including the
following functions:
I.
II.
II.
iii.
iv.
V.
vi.
3.1.2
Providing pertinent site information (scope of work, available analytical data, personnel
assignments, etc.) to facilitate preparation of the HASP.
Approving the HASP.
Monitoring field documents to ensure adequate health and safety practices are employed.
Coordinating with the project personnel to implement necessary emergency response procedures.
Verifying corrective actions are implemented.
Ensure that project personnel receive this HASP and that provisions for conveying information
contained within the HASP and other site documents to site workers are provided.
Providing for appropriate monitoring, personal protective equipment, decontamination materials,
and other project necessities.
TtNUS RAC 3 Health and Safetv Manaqer (HSM)
The HSM or authorized designee is responsible for developing this HASP in accordance with applicable
OSHA regulations. Specific responsibilities include:
i. Developing the implementing project health and safety documents including the HASP.
ii. Reviewing information regarding site contaminants and physical hazards associated with the site.
ii. Establishing air monitoring and decontamination procedures.
1 1 1 . Assigning personal protective equipment based on task and potential hazards.
iv. Determining emergency response procedures and emergency contacts.
...
3-1
-
v. Stipulating training requirements and reviewing appropriate training and medical surveillance
certificates.
vi. Providing standard work practices to minimize potential injuries and exposures associated with
hazardous waste work.
vii. Modifying this HASP, as it becomes necessary.
viii. Auditing project sites to ensure compliance with this HASP and other applicable OSHA
regulations or TtNUS H&S
3.1.3 TtNUS Field Operations Leader (FOL]
The TtNUS FOL is responsible for implementation of the HASP with the assistance of an appointed Site
Safety Officer (SSO). The FOL manages field activities, executes the work pian, and enforces safety procedures as applicable to the work plan. Additional duties include:
i.
I I .
Ensuring and enforcing compliance with the HASP.
Coordinating site activities such that they may be performed in an effective and safe manner
consistent with the HASP.
Enforcing the buddy system on-site.
Controlling site entry of unauthorized personnel.
Assuring availability of all safety equipment.
Inspecting the site for safety hazards and proper posting
iii.
iv.
V.
vi.
3.1.4 Site Safetv Officer (SSO)
The SSO supports site activities by advising the FOL on the aspects of health and safety on site. These
duties may include:
I.
II.
Coordinating health and safety activities with the FOL through implementation of this HASP.
Selecting, applying, inspecting, and maintaining personal protective equipment, air monitoring
instruments, and other site equipment and materials.
Confirm that site personnel meet appropriate training and medial requirements.
Conducting site-specific training, daily safety meetings, and weekly inspections.
Verification of decontamination procedures are being implemented.
iii.
iv.
V.
vi. Implementation of Hazard Communication, Respiratory Protection Programs, and other
associated health and safety programs as they may apply to site activities.
Conducting site inspections to identify potential hazard and to implement corrective actions vii.
3-2
-
viii.
ix.
Coordination of emergency response procedures and follow-up.
Notification of appropriate contract representatives and TtNUS Project Manager in the event
of an emergency.
Investigation of accidents and injuries (see Attachment I - Illness/lnjury Reporting Procedure
and Form).
Providing input to the HSM regarding the need to modify, this HASP, or applicable health and
safety associated documents as per site-specific requirements.
Observing field team members for symptoms of exposure or stress.
X.
xi.
xii.
Compliance with the requirements stipulated in this HASP is monitored by the SSO and coordinated
through the TtNUS HSM and the TtNUS Corporate Health and Safety Manager.
Note: In some cases one person may be designated responsibilities for more than one position. For
example, at the site, the FOL may also be responsible for SSO duties. This action will be performed only
as credentials, experience, and availability permits.
3.1.5 TtNUS and Subcontractor Personnel
TtNUS and subcontractor employees are responsible for:
1. Understanding and following direction provided in this HASP, and other project plans and as
provided under the direction of the SSO and/or FOL.
Reporting unsafe conditions or incidents to the FOL and/or SSO.
Providing necessary training and medical surveillance information to SSO.
Attending site-specific training and daily safety meetings.
ii.
111.
iv.
...
3-3
-
4.0 TRAINING/MEDICAL SURVEILLANCE REQUIREMENTS
4.1 INTRODUCTORY/REFRESHER/SUPERVlSORY TRAINING
4.1.1 Requirements for Tetra Tech NUS Personnel _--
Prior to performing site activities at SLC, TtNUS field personnel must complete 40 hours of introductory
hazardous waste site training. Additionally, TtNUS personnel who have had introductory training more
than 12 months prior to site work must have completed 8 hours of refresher training within the past 12
months before being cleared for site work. In addition, 8-hour supervisory training in accordance with 29
CFR 191 0.120(e)(4) will be required for site supervisory personnel. Documentation of TtNUS introductory,
supervisory, and refresher training as well as site-specific training will be maintained at the project site.
TtNUS will conduct a site-specific training session prior to initiating site work. Additionally, a brief safety
meeting will be held daily to discuss operations planned for that day and to review applicable Safe Work
Permits. These daily meetings may also be used to discuss completed operations, scope of work
variances, and any problems that were encountered.
4.1.2 Requirements for Subcontractors
TtNUS subcontractor personnel will have completed introductory hazardous waste site training or
equivalent work experience as defined in OSHA Standard 29 CFR 1910.120 (e). Additionally, personnel
who have had the introductory training more than 12 months ago, are required to have 8 hours of
refresher training meeting the requirements of 29 CFR 1910.120 (e)(4) prior to performing field work if
required. TtNUS subcontractors will certify that each employee has had such training by sending TtNUS a
letter, on company letterhead, containing the necessary training information and by providing copies of
certificates for subcontractor personnel participating in site activities.
4.2 SUBCONTRACTOR EXCEPTIONS
Subcontractors who will not enter the exclusion zone during operation, and whose activities involve no
potential for exposure to site contaminants, will not be required to meet the requirements for
training/medical surveillance other than site-specific training as stipulated in Section 4.3. Exceptions to
the training and medical surveillance requirements stipulated in Sections 4.1 and 4.5, respectively, will
only be granted through prior approval by the RAC 3 HSM.
4-1
-
.-
4.3 SITE-SPECIFIC TRAINING
TtNUS will provide site-specific training to site personnel who will perform work on this project. Site-
specific training will also be provided to personnel [EPA, DEP, etc.] who may enter the site to perform
functions that may or may not be directly related to site operations. Site-specific training will include:
Names and roles of designated personnel and alternates responsible for site safety and health
Site activities and operations planned at the site
Safety, health, and other hazards present on site
Use of personal protective equipment
Work practices to minimize risks from hazards
Medical surveillance requirements
Signs and symptoms of overexposure
Contents of the Health and Safety Plan
Emergency response procedures (evacuation and assembly points)
Spill response procedures
Review of the use of Safe Work Permits
Site-specific documentation will be established through the use of the Site-Specific Training
Documentation Form (Figure 4-1). Site personnel and visitors must sign this document upon receiving
site-specific training.
4.4 OTHER TRAINING
TtNUS incorporates other OSHA required training as part of annual 8-hour refresher training. This
additional training includes but is not limited to hearing conservation and protection (29 CFR 1910.95),
hazard communication (29 CFR 191 0.1 200), and personal protective equipment (29 CFR 191 0.1 32).
Training provided as part of site-specific training or daily safety meetings on project work sites
supplements this training. It should be noted that in some situations, additional training for TtNUS or
subcontractor personnel will be necessary (confined space operations, use of respiratory protection, fall
protection, energy control, etc.).
4.5 MEDICAL SURVEILLANCE
Tetra Tech NUS and subcontractor personnel participating in project field activities will have had a
physical examination. Physical examinations shall meet the minimum requirements of paragraph (f) of
OSHA 29 CFR 1910.120. The physical examinations will be performed to ensure all personnel are
medically qualified to perform hazardous waste site work using respiratory protection.
4-2
-
Documentation for medical clearances will be maintained at the job site and made available, as necessary. Subcontractor personnel may use the "Subcontractor Medical Approval Form" to satisfy this
requirement, or a letter on letterhead stationary from an officer of the company. The letter should state
that the persons listed in the letter participate in a medical surveillance program that meets the
requirements contained in paragraph (f) of Title 29 of the Code of Federal Regulations (CFR), Part
1910.120, entitled "Hazardous Waste Operations and Emergency Response." The letter should further
state the following:
0 The individuals listed have had physical examinations under this program within the frequency as
determined sufficient by their occupational health care provider
Date of the exam
The individuals identified have been cleared, by a licensed physician, to perform hazardous waste site
work and to wear positive- and negative- pressure respiratory protection.
A sample Subcontractor Medical Approval Form and form letter is provided to eligible subcontractors in
the Bid Specification package.
4.6 MEDICAL DATA SHEETS
Each field team member (including visitors entering the exclusion zone) shall be required to complete and
submit a copy of the Medical Data Sheet found Attachment I1 of this HASP. This shall be provided to the
SSO prior to participating in site activities. The purpose of this document is to provide site personnel and
emergency responders with additional information that may be necessary in order to administer medical
attention.
4-3
-
FIGURE 4-1
satisfaction, and that the dates of my training and medical surveillance Site- 40-Hour &Hour
(Printed and Signature) Training (Date) Training Name Specific Training Refresher
Date (Date)
SITE-SPECIFIC TRAINING DOCUMENTATION
indicated below are accurate. 4-Hour
SUperViSOry Medical Training Exam (Date)
My signature below indicates that I am aware of the potential hazardous nature of performing investigation activities at Safety Light Corporation, and that I have received site-specific training which included the elements presented below:
Names of designated personnel and alternates responsible for site safety and health Site activities and operations planned at the site Safety, health, and other hazards present on site Use of personal protective equipment Work practices to minimize risks from hazards Medical surveillance requirements Signs and symptoms of overexposure Contents of the Health and Safety Plan Emergency response procedures (evacuation and assembly points) Spill response procedures Review of contents of relevant Material Safety Data Sheets Review of the use of Safe Work Permits
4-4
-
5.0 HAZARD ASSESSMENT
Site-specific hazards are identified through hazard analysis to determine the appropriate safety and health
procedures needed to protect workers from the identified chemical, physical, and biological hazards. This
section provides information on most commonly encountered hazards associated with planned field
activities at SLC and lists generally practiced mitigation procedures. Tasks, hazards and associated
control measures are identified in detail in Attachment IV.
5.1 CHEMICAL AND RADIOLOGICAL HAZARDS
Site activities associated with hazardous waste sites bring field personnel into possible contact with
hazardous chemicals in the form of site contaminants, cleaning/decontamination fluids, sample
preservatives, calibration gasses, and products used to operate or maintain site equipment. This section
of the HASP serves to identify those chemical hazards and provide guidance to prevent or minimize
potential for exposures or contact with these chemicals. A list of chemical and radiological contaminant
properties can be found in Attachment V
5.1.1 Site Contaminants
The site consists of locations where radioactive materials and chemicals were used in manufacturing
processes. Numerous sampling and remedial activities have been performed over a period of years that
provide a good characterization profile of site contaminants. The primary radioactive isotopes of concern
associated with subsurface soils are Ra-226, Cs-137, Sr-90, H-3 and Am-241. These contaminants would most likely be encountered during direct push sampling and monitoring well installation/construction and
testing activities. The possibility also exists for the presence of vinyl chloride in subsurface soils. These
same radionuclides, as well as vinyl chloride, represent contaminants of concern for associated
groundwater processing activities. These contaminants could be encountered during monitoring well
redevelopment, monitoring well sampling, water level measurements, and pipe discharge sampling. There
is a minimal potential that these contaminants may be observed during residential well sampling.
It is not expected that these contaminants will pose an inhalation hazard. However, safe work practices
such as avoiding the generation of site dusts, avoidance and collection of potentially contaminated soils,
and exposure monitoring to evaluate potential exposure (vinyl chloride) to site personnel will be
implemented during the performance of site activities. Periodic monitoring of equipment, work areas and
personnel using portable radiation detection instruments will be performed to verify radiological conditions.
5- 1
-
5.1.2 Chemicals Use on Site
Site investigations may require the use of chemicals (sample preservatives, decontamination solvents,
fuels, etc.). Manufacturer Material Safety Data Sheets (MSDS) will be maintained and be available for
review by site personnel to determine potential hazards, protective measures, and other information
regarding the potential hazard of the chemical. Safe work practices and the use of protective equipment
to prevent exposure to potential site contaminants will also be used to prevent exposure to chemicals that
may be used or encountered during site operations.
5.2 PHYSICAL HAZARDS
Potential physical hazards associated with fieldwork are described below, along with TtNUS policy and
general procedural guidelines to minimize these hazards.
5.2.1 Heavv Equipment Hazards (Pinchkompression points. rotatinq equipment. etc.)
Often the hazards associated with drilling operations are the most dangerous to be encountered during
site activities. The SSO will discuss safe drilling procedures as part of site-specific training and/or during
daily safety meetings. The following rules will apply to drilling operations:
- -
Site personnel will be aware of the location and operation of this equipment. Each drill rig must be equipped with emergency stop devices which will be tested daily to ensure
that they are operational.
Long handled shovels or equivalent shall be used to clear cuttings from the borehole and rotating
equipment.
-
0 Additional requirements during drilling activities are discussed in Attachment IV. The SSO will
thoroughly discuss safe drilling procedures during the pre-activities training session and all equipment
(drill rigs, excavators, backhoe, etc.) will be inspected using the Equipment Inspection Form
(Attachment VII).
5.2.2 Eneraized Svstems (Contact with Underaround or Overhead Utilities)
Underground utilities such as pressurized lines, water lines, telephone lines, buried utility lines, and high
voltage power lines may be present throughout the facility. Therefore, subsurface activities must be
conducted following the requirements of the Tetra Tech NUS SOP for “Utility Locating and
Excavation Clearance (HS-1.0)”. A copy of this SOP is provided as Attachment VIII. Drilling operations will
5-2
-
be conducted at a safe distance from overhead power lines as discussed in Attachment VIII. In certain
cases, utility personnel may need to de-energize electrical cables using facillty lockouthagout procedures to
insure electrical hazards are eliminated.
5.2.3 Slips, Trips, and Falls
All work sites contain potential slip, trip, and fall hazards, such as:
0 holes, pits, or ditches;
0 open manholes to sewers
0 slippery surfaces;
steep grades;
0 uneven grades; and
0 sharp objects, such as nails, metal shards and broken glass.
Personnel will be instructed to look for potential safety hazards and to immediately inform the SSO or the
FOL about the hazards. If the hazard cannot be immediately removed, action such as marking or
barricading the hazard will be taken to warn site workers.
The SSO will determine the severity of any injury incurred during a slip, trip, or fall. If a person becomes
contaminated because of a slip, trip, or fall, the victim should obtain prompt medical attention.
Decontamination shall be provided to the extent necessary.
5.2.4 Heavv or Awkward Lifting
Precaution shall be exercised when lifting heavy or awkward objects (sample coolers, sampling
equipment, IDW containers, augers and other drilling equipment, etc.). Personnel should know and
practice proper lifting techniques and not lift more weight than can be handled comfortably, regardless of
load weight. Help should be obtained for lifting loads greater than 50 pounds. Mechanical equipment
should be used for lifting heavy materials when possible.
5.2.5 Portable Power Hand Tools
Environmental site activities occasionally require the use of portable hand tools. Any such equipment
(e.g., wrenches, wedges, chisels, hammers, pneumatic tolls, drills, welding equipment, etc.) used in the
work area must have appropriate guarding, interlocks, or controls to ensure safe operation, in accordance
5-3
-
with 29 CFR 1926.301 through 302. Machinery and equipment must be inspected for defects in the
guarding and operation before each use.
The following specific precautions will be used to help prevent injuries and accidents:
Never remove, make inoperative, or reduce the effectiveness of any equipment or machine guard.
Never override any safety interlock or attempt to operate any piece of equipment or machinery
without guards or other required safety devices in place and fully functional.
Never operate any piece of equipment or machinery when it is functioning improperly or at any
time when operation would constitute a hazard. Any piece of equipment that does not meet this
requirement must be repaired immediately or will be removed from the premises.
Occasionally, during installation of equipment or demolition of an existing area, there may be
times when a piece of equipment must be left in an incomplete state. It may be potentially
hazardous to operate the equipment or to enter the area during this time. When such situations
occur, the equipment must be locked out or the area must be identified with yellow tape that reads
"Caution - Do Not Enter".
In addition, the following general precautions should be considered:
Do not use electrically powered tools near flammable materials or within an explosive atmosphere, unless they are of the explosion-proof type meeting the National Electrical Code
(NEC) for explosive areas. Employees operating the equipment should be aware of sparks and/or
metal fragments when using this equipment.
At no time will electrical power equipment be operated without proper grounding. All electrical
cords and cables, including extension cords, shall include a third wire ground.
Prohibit operations of electrical tools in wet or damp areas except in unusual emergency
circumstances.
Limit use of tools to the purpose for which the tool is intended (e.g., wrenches will not be used as
hammers). Defective tools (e.g., with mushroomed heads or split or defective handles) shall not
be used.
Do not use conducting (Le., metal) tools around electrical facilities. Insulated tools, approved for
electrical work, shall be tested frequently for proper insulation.
Select the correct size and type of wrench for each job. Wrench handles shall not be extended
with a pipe or cheater because the jaws will spread.
Repair mushroomed punch, drift, and chisel heads. Mushroomed heads represent
fractured/stressed/crystallized metal that will break and fly off when struck.
5-4
-
Wear eye protection at all times.
Wear leather or heavy cotton work gloves when using tools to protect against blisters, cuts, or
other hand injuries.
Wear eye protection (safety glasses with side shields) to protect the eyes from twigs, sticks, or
flying debris.
Wear long pants and long-sleeved shirts to protect against abrasions.
Wear hard hats if work will involve areas with overhead hazards (e.g., overhanging branches).
Wear sturdy work boots.
Inspect all hand tools [i.e., shovel handles (cracks, splinters, etc.), brush hook handles and blade
attachment points, etc.)
Use the proper tool for the intended purpose. This to will avoid potential injury possibly created
through improper use.
Drum Handling
The following general guidelines shall be followed:
Use only drums and containers that meet the appropriate U.S. Department of Transportation
(DOT), OSHA, and United States Environmental Protection Agency (USEPA) regulations.
Be aware of the potential hazards of the contents of drums or containers before handling. Only
trained personnel should open drums containing unknown materials.
Bulging drums or containers are an indication of pressure buildup. Open all drums or bungs
extremely slowly to determine the presence of vapors or pressure inside the drum. If the
possibility of fire or explosion exists, a protective shield and/or remote opening devices should be
used.
Consider any unlabeled drum or container as containing a hazardous substance and leave it
alone until contents are properly identified and labeled. Do not assume that exterior labeling
properly identifies the contents or potential hazards of drums and containers.
Label and identify drums and containers when moved to the staging areas to safely identify and
classify their contents. Segregate incompatible drums.
Staging areas shall be provided with adequate ingress and egress routes. Use secondary
containment at staging area for all moved drums.
Inspect the integrity of the drum or container before moving. Any drum or container lacking
integrity shall be overpacked.
5-5
-
0
0
0
0
0
0
5.2.7
When
Organize site operations to minimize the amount of drum or container movement. Have a clear
view of the available pathway when moving drums. If needed, an additional person should be
available to provide guidance.
Utilize drum container handling equipment whenever possible. The equipment utilized should
have a sufficiently rated load capacity, and should be able to operate smoothly on the available
surface.
Use proper lifting and moving techniques to prevent back injuries, if handling equipment is not
available.
Never stand on drums or containers.
Use non-sparking tools.
Cease site operations immediately if site activities uncover buried drums or containers. The SSHS
must be notified. The SSHS will evacuate the area. All unknown situations must be evaluated
before site activities are resumed. The services of a specialized contractor trained in handling
unknown contaminants may be needed. If, after evaluating the situation, only a portion of the site
is affected, that area shall be barricaded and work may continue at other portions of the site.
working with compressed gases (e.g., calibration gases for monitoring instruments,
oxygen/acetylene cylinders for welding), the following general precautions should be taken:
Chain or secure cylinders in an upright position at all times whether in storage or use.
Move cylinders only when they are chained to a handcart; never drop, role or slide them across
the ground or floor.
Keep the protective cap in place at all times when the cylinder is not in actual use. Cylinder must
be properly labeled with contents and hazard warnings.
Always use the proper regulator for each cylinder. Don’t use an adaptor or other connections to
attach a regulator to a gas cylinder. If it is the correct regulator, it will fit easily on the existing
connection.
Store and properly secure cylinders in a well ventilated location. The use and storage of
flammable or combustible gases is restricted in the facility.
All cylinders utilized onsite shall be free of corrosion and inspectedhested per DOT requirements.
Any cylinder that does not meet DOT inspection requirements must be tagged “Do Not Use” and
removed from site property.
Keep oxidizing gases separate from fuel gases.
5-6
-
I
e Cylinders should be tagged and capped when empty. It is recommended that full and empty
cylinders be stored separately
5.2.8 Severe Weather
Project tasks under this Scope of Work will be performed outdoors. As a result, inclement weather may
be encountered. In the event that adverse weather conditions arise (electrical storms, heavy winds,
hurricanes, etc.), the FOL and/or the SSO will be responsible for temporarily suspending or terminating activities until hazardous conditions no longer exist.
5.2.9 Heat and Cold Stress
The most severe heat-induced illnesses are heat exhaustion and heat stroke. If left untreated, heat
exhaustion could progress to heat stroke and possible death.
The symptoms of heat exhaustion include:
headaches;
dizziness or lightheadedness;
weakness;
mood changes such as irritability, confusion, or the inability to think straight;
upset stomach;
vomiting ;
decreased or dark-colored urine;
fainting or passing out; and
pale, clammy skin.
In the event that these symptoms are observed, the following actions should be taken:
0
Act immediately. If not treated, heat exhaustion may advance to heat stroke or death.
Move the victim to a cool, shaded area to rest. Don’t leave the person alone. If symptoms include
dizziness or lightheadedness, lay the victim on his or her back and raise the legs 6 to 4 inches. If
symptoms include nausea or upset stomach, lay the victim on his or her side.
Loosen and remove any heavy clothing.
Have the person drink cool water (about a cup every 15 minutes) unless sick to the stomach.
5-7
-
--
0 Cool the person’s body by fanning and spraying with a cool mist of water or applying a wet cloth to
the person’s skin.
Call 91 1 for emergency help if the person does not feel better in a few minutes. 0
The symptoms of heat stroke include:
0
0
0
0 seizures or fits; and
0 unconsciousness with no response.
dry, pale skin with no sweating;
hot, red skin that looks sunburned;
mood changes such as irritability, confusion, or the inability to think straight;
If these symptoms are observed, call 91 1 for emergency help immediately and follow same actions listed
above.
If the SSO requires personnel to wear chemically impervious clothing, heat stress monitoring will be
required. The safe duration of workhest periods will be determined based on the suggested schedules in
the current American Conference of Governmental Industrial Hygienist (ACGIH) Threshold Limit Values
for heat stress. These workhest periods will be adjusted based on the:
0 anticipated work rate;
0
0
0
ambient temperature and other environmental factors;
types of personal protective equipment; and
individual worker characteristics and fitness.
The workhest periods may be further adjusted when the temperature reaches 70 degrees Fahrenheit or
above.
Heart rate will be measured for 30 seconds using the radial pulse method, and as early as possible in the
rest period. If the heart rate exceeds 11 0 beats per minute, the work period will be shortened by one third.
If at the beginning of the next rest period, the heart rate is still greater than 110 beats per minute, the work
period will again be shortened by one third.
Temperatures may be taken orally at the end of the work period. If the body temperature is greater than
99.6 degrees Fahrenheit, the next work period will be shortened by one third. If oral temperature still
exceeds 99.6 degrees Fahrenheit at the end of the shortened work period, it will be shortened again by
one third. A worker will not be allowed to wear a semi-permeable or impermeable garment if hisher oral
5-8
-
. .
temperature is greater than 100.6 degrees Fahrenheit. If deemed necessary by the SSO, heat stress
monitoring will be performed.
Cold stress is also an important factor in employee health and safety. On days with low temperatures, high
winds, and low humidity, anyone can suffer from the extreme cold. Severe cold temperatures can be life
threatening. Several factors increase the harmful effects of cold: age (being very young or very old), wet
clothing, wounds or fractures, smoking, fatigue, emotional stress, and certain diseases and medications.
Cold weather injuries may be either local or systemic. Local cold weather injuries include chilblains
(chronic injury of the skin and peripheral capillary circulation) and frostbite. Frostbite occurs in three
progressive stages: frostnip, superficial frostbite, and deep frostbite. Systemic cold injuries, due to
hypothermia, are these that affect the entire body system. Hypothermia is caused by exposure to cold and
is aggravated by moisture, cold winds, fatigue, hunger, and inadequate clothing or shelter. The objective is
to prevent the deep body temperature from falling below 96.4"F (36°C) and to prevent cold injury to body
extremities.
5.3 BIOLOGICAL HAZARDS
Many environmental investigation activities bring site personnel into areas that are natural habitats for
many indigenous plants and animals, including snakes, rodents, and insects. When working in the field,
TtNUS personnel and subcontractors must be aware of their surroundings and recognize the hazards
associated with the wildlife around them. Field workers must remember that these animals are wild and
should be left alone.
Fauna - 5.3.1 5.3.1.1 Venomous Snakes
Although not considered a significant concern at most sites, venomous snakes may be present. Field
workers must maintain awareness of their surroundings. In most instances, these animals, when left
alone, will eventually retreat to preferred habitats away from people, Site personnel must be made aware
of the potential presence of these animals.
Venomous snakes which may be found in Pennsylvania include:
5-9
-
0 Eastern Diamondback Rattlesnake - 7-4 feet in length; found in almost any habitat, but most commonly in pine woods, abandoned fields or brushy/grassy areas; aggressive.
0 Cottonmouth (Water Moccasin) - Exceeds 5 feet in length; variable color pattern; characteristic
whitish mouth lining shown when in a defensive posture; found along stream banks, in swamps
and margins of lakes; unpredictable disposition.
If a venomous snake is observed, the following protocol should be followed:
0 Move!
0
0
Notify the SSO or Field Manager.
Notify others in the area.
If bitten by a snake, the patient should be transported immediately to the nearest medical dispensary,
which, depending on the severity and nature of the bite, may transfer the patient to an offsite medical
facility. The absorption of venom should be retarded by placing the victim at rest and splinting the
extremity that was the site of the bite. The affected limb should be kept below heart level. If possible, place
a wide constriction band above the bite. This should be just firm enough to allow a finger to be placed
between the band and the skin. The goal is to impede lymph flow, not venomous return. As the area
begins to swell, the band should be loosened and re-applied away from the swelling. Never attempt to
suck the venom out of the patient.
5.3.1.2 Insects and Spiders
Caution should be used when opening the casings around monitoring wells as these areas are excellent
habitats for spiders. Any personnel with known allergic conditions to specific insects should notify the SSO
so that appropriate precautions can be taken. Notification of allergic conditions can be through the use of
a Medical Data Sheet as presented in Attachment II.
Ticks are small, round-shaped, dark colored insects that are the size of small seeds. Several diseases
(e.g., Lyme disease from deer ticks) may be transmitted from ticks. Therefore, bites from both wood and
deer ticks may present potential hazards to human health. Lightly colored clothing should be worn so that
any ticks present are more easily seen. In addition, site personnel should thoroughly inspect themselves at
the end of the day and remove any ticks that are beneath clothing and/or attached to skin. Additionally,
site personnel should tape pant legs to work boots and if necessary wear protective coveralls to minimize
the potential for tick to become attached. Commercially available insect repellents containing DEET may
5-10
-
be used according to manufacturer recommendations. Ticks can be removed with tweezers, taking care
to remove the head, then the affected area should be washed with soap and water, and an antiseptic
ointment should be applied. If the tick’s head cannot be removed or if a rash persists, medical attention
should be sought. A tetanus immunization may be recommended. Additional information of Lymes
disease and tick bite prevention is provided in Attachment Ill.
Black widow spiders and brown recluse spiders, both venomous, may also be present in and around
structures (e.g., buildings, well casings) or vegetation. Bites from these spiders can cause swelling and
intense pain in the bite area and in some instances have caused deaths. Site personnel will be made
aware of the potential hazards associated with venomous spiders and instructed to avoid contact with
them. Symptoms associated with a black widow bite include abdominal pain, dizziness, headache,
sweating, severe cramps, weakness, and difficulty breathing. Symptoms of a brown recluse bite may
include fever, chills, nausea, vomiting, itching, and brown urine that may develop within 36 hours. In either
eventuality, medical attention should be sought immediately.
Chiggers may also be present at the site. Precautionary measures against chiggers include tucking
clothing in pants and pant legs into boots.
Venomous insects include wasps, bees, hornets, and red ants. Most of these insects are not considered
to be dangerous. In the event of an insect sting, the following general procedures should be followed:
0
0 Wash the site.
Apply a cold pack.
Remove the stinger with the edge of a credit card or something similar.
If a stinging victim develops serious symptoms including shortness of breath, flushing, swelling of the face,
or severe swelling of a body part, medical attention should be sought immediately. A severe reaction
could mean that a life-threatening condition is developing.
5.3.1.3 Other Animals
Rodents carry diseases such as Hantavims Pulmonary Syndrome (HPS). Human infection may occur
when infective rodent saliva or excreta are inhaled as aerosols produced directly from the animal.
Transmission may also occur when dried or fresh materials contaminated by rodent excreta are disturbed,
directly introduced into broken skin, introduced onto the eye membrane (conjunctivae), or possibly
ingested in contaminated food or water. The disease begins with one or more symptoms including fever,
5-1 1
-
muscle aches, headache, and cough and progresses rapidly to severe lung disease. Medical attention
should be immediately sought if these symptoms are observed.
5.3.2 - Flora
Work sites may contain numerous irritant plants with toxins, including poison ivy, poison sumac, and
poison oak. Published research has shown that approximately 45% of those exposed to the resin of these
plants may develop an allergic reaction within 12 to 24 hours. Symptoms of this reaction could include
severe skin irritation characterized by redness, blisters, swelling, and intense burning and itching. Severe
allergic reactions may result in abscesses, enlarged glands, fever, and, infrequently, kidney problems