itdg-micro-hydropower in nepal (guidelines)
DESCRIPTION
micro-hydroTRANSCRIPT
Contents
3 DMRSION WORK5 ....
3.1 Overview...
3.2 Generol princi
3.3 Intoke locotio
3.3.1 Charocteristics
3.3.2 Exomple
77
77
77
18
18
20
3.4 Intoke types
vll
1
tf't,'
66
vll l
5.6 Checklist for grovel trop, settling bosin
6.5.4 Quick method for smoll schemes with crossflow turbines ................ ............. 95
ix
7.
1 0
11
APPENDICES
Appendix A
Appendix B
Appendix C
LIST OF PHOTOCMPHS
Ph0t0 2.2 0bstructions coused by debris folling from on unstoble slope ......... ..................... 9
Photo 3.2 Side intoke of the Golkot micro-hydro scheme, Boglung, Nepol .........22
Photo 3.3 Where on intoke is lioble to ottroct flooting debris, o troshrock moy be necessory (Sri Lonko) .............22
Ph0t0 3.5 Timber plonks ploced horizontolly in grooves provide o low-cost gote in q chonnel (Mhopung) ...........25
Ph0t0 3.11 Gobion wolls ot the heodworks of the 30 kWJhorkot micro-hydro scheme, Mustong, Nepol ................. 35
Ph0t0 4.3 Stone mosonry in cement mortqr heodrqce ccnql of the 50 kW Golkot MHB Gqlkot, Boglung, Nepol ..................... 38
Photo 4.4 Reinforced concrete cover slobs provide protection from folling debris (Bolivio) ................... 38
Photo 4.6 Timber conol with brocing supporting the sides, Thuptenchuling ........ .............. 39
Photo 4.11 Overflow from the foreboy dischorged over o rock cliff, Dhoding micro-hydro, Nepol .......... 50
Photo 4.12 Spillwoy on o crossing where the excess flow is dischorged into q gully,
Photo 4.13 HDPE pipes provide qn overflow from o timber chonnel (Mhopung) .................... 53
Ph0t0 4.15 Ghqndruk micro-hydro heqdroce crossing, Ghondruk, Nepcl ............ 54
Photo 4.u Flush-outs should be provided qt low points in pipelines so the heovy debris cqn be
Photo 4.18 HDPE heodroce pipe olong unstqble olignment, Ghondruk micro-hydro scheme, Nepol ...... 56
Photo 4.19 Bend prepored by cutting ond welding the HDPE heodroce pipe ot Ghqndruk ...................... 56
xl
Photo 4.21
Photo 4.22
Photo 5.1
Photo 5.2
Photo 5.3
Phoro 5.4
Phoro 5.5
Photo 5.6
Photo 5.7
Photo 5.8
Phoro 5.9
Phoro 5.10
Phoro 5.11
Phoro 5.12
Photo 5.11
Phoro 5.14
Photo 5.15
Photo 6.1
Photo 6.2
Phoro 6.3
Photo 6.4
Phoro 6.5
i'iroto 6.6
Phot0 6.7
Phoro 6.8
Photo 6.9
Photo 6 .10
Photo 6.11
Photo 6.12
Photo 6 .11
Photo 6.14
Phor0 6 .15
Photo 7.1
Ph0t0 7.2
Phoro 7.3
Photo 7.4
Photo 7.5
Photo 7.6
Joining HDPE pipes by pushing
Collors used to join HDPE pipes
th€m while hot
57
colkot grovel trop .... ' . . . ' ' , , . . . . . . . . . . . . . ' ' ' ' ' . . . . . . . . 71
Sliding got€ ot settling bosin entronce, Peru ....___........... ?5
Jhorkot setti ing bosin ....... . . . . . . . . . . . .76
se( l ing Dosrn o t Jhorkor . . . . . . . . . . . . 1'7
sqll€ri Chioiso setl l ing bosin
chondruksef i l rng bq) in . . . . . . . . . . . . . . . . . . . . . 78
81
8l
84
crovel trop. settling bosin ond foreboy ofJhonhe mini'hydro ................
A dry stone mosonry foreboy showing the connection with the penstock .........,..............
A cem€nt mosonry chonn€l qnd foreboy ot the top ofo ste€p slope (DhqdingJ .............
82
. . . . . . . . . . . . .8 l
Cleoning con be difiicult with horizontol bors
submerged troshrock, Solleri Chiolso mini-hydro scheme............
overflow weir for the settl lng bosin qt Jhorkot .................................
An expqnsi0nj0int should b€ locotedjust below qn onchor block to protect the block
from forces which mqy Ilot be designed to resist (Siklis) ..................
chondruk peoking reservoir during construction ............. ................. . . . . . . . . . . . . . . . . . . . . . . 85
Ghondruk DeokiD0 reservoir ofter construction .............................
P€nstock qlignment of the 36 kW Jhorkot micro-hydm sch€me, Mustong, Nepol ........................................................ 87
Pen( toLk . Purong. . .
84
85
Penstock olignmert ofthe 50 kW Borpok micro-hydro scheme, Corkho. Nepol
Excovotion to reduc€ the cost oflh€ penstock ond reduce the need foronchors {Siklis) ..... .............. ......... ....... ... 88
Penstock instollotion is often chollenging ond requires sofe ond cor€ful work .... ................ 89
Penstock oiignment high obove the ground to ollow occess for people 0nd cottleJhonlre mini-hydro ................... 89
HDPE-mild ste€l c0upling. Jhong micro-hydro sch€me, Mustong, N€pol .................. .................................................. 9i
Penstock ot Ghondruk with vil log€ in the bqckground ............
Temporory suppon for site welding work,Jhonl(Ie minihydro, Nepoll08
A strolqht p€nsrock with four suppons cnd on onchor block before th€ power house.....
Jhonkre minihydro onchor block for on upword verticol bend
slrdlng expqn5ion jornt, Jhonkre mrni.hydro
crocking 0f the upper surfoce of on unreinforced oDchor block......
U5e o l d ry s tone wo l l fo r fo rm work , JhunLre mrn1.hydr0 . . . . . . . . . . . . . . . . . . . . . . . . . . .
droinqge ond prevelting corrision betwe€n the block ond the pipe (Kiomche) ............................
104
105
106
108
l l l
u 1
l l 2
1 1 3
I l lstone mosonry suppoft piers,lhonkre mini'hydro scheme ...........
The use ofon exlension t0 the concrcte supp0n lifts the pipe cleor 0l on block, ollowirlg
Photo7.7 Wooden support piers ot Komche micro-hydro scheme, Nepol ....................... ........................... I16
Photo 8.2 Powefhouse ond loilroce oi the solleri Chiolso mi[i 'hydro scheme . . ... . . ..... .... ..... 130
Phot0 9.1 Unsroble slopes (re o thr€ot l0 schemc. This polvefhouse wos destroyed by o londslide ........................................... 119
Photo 9.2 Mosonry steps for entrgy dissipotion ond contr0l 0f spil lwov woter ............ ........................... 140
x I
;))l
I
t
6
J
0
Ph0t0 9.4 Stone mosonry con provide slope stobilisotion olong the route of the penstock (Barpok) ......... ........ 141
LIST OF FIGURES
Figure 1.2 Heod is the verticol height through which the woter drops ................ 3
Figun 2.1 Viewing the site from o vontoge point gives the opportunity to ossess the options for
Figure 3.7 A temporory weir proposed for the 18 kW Thorong Phedi micro-hydro scheme, Monong, Nepol .............................26
Figure 3.8 Heodworks orrongement of the 500 kWJhonkre mini-hydro scheme, Nepol .............. ........................27
Figure 3.10 A stone mosonry permonent weir proposed for Ghomi micro-hydro scheme, Mustong, Nepol ................................ 29
Figure 3.11 A plum concrete permonent weir proposed for Ghqmi micro-hydro scheme. ............ 30
Figure 3.15 Heodworks orrqngement of the 80 kW Bhujung MHP, under construction in Lomjung, Nepol ................................. 36
Figure 4.3 Buried membrone lining proposed in Design Mqnuols for Irrigction Projects in Nepol ..................... 4l
Figure 4.11 Heqdworks of the 100 kW Siklis micro-hydro scheme (Siklis, Nepol) ........................... 62
Cqnol lining with stone mosonry in cement mortor 66
72
57
81
83
An ideol settl ing bq\rn
Foll velocity ofquonz spheres in woter
A typicol settl ing b0sin ond its components ..............
Exponsion 0nd controction rolio in s€t0ing bosit
Flushing o settling bosin using th€ verlicol flush pipe method
V€rticol flush pip€ section in o settiing bosin
Flushing system of jhqnkr€ minihydm
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ?4
Foreboy
Figure 4.13
Flgure 5.1
Figurc 5.2
Figure 5.3
Figure 5.4
Figure 5.5
Figurc 5.6
Figure 5.7
Figurc 5.8
Figure 5.9
Figure 6.1
Figurc 6.2
Ilgure 6.3
FrguIe 6.4
Figure 6.5
Figur€ 6.6
Figur€ 6.7
Figur€ 6.8
FiguI€ 7.1
Figure 7.2
Frgure 7.3
Figure 7.4
Figur€ 7.5
Flgure 7.6
Figure 7.7
Figure 7.8
Fjgure 7.9
Figurc 8.1
Figur€ 8.2
Flgur€ 8.3
Figur€ 8.4
Flgure 8.5
Figun 8.6
Figure 9.1
Figure 9.2
Figure 9.3
Fiqure 9.4
Fiqure 10.1
tiqure 10.2
Figur€ 10.3
Figure 10.4
Table 3.1
Tqble 3.2
Wolls ood floon ofwot€r retqining structur€s
Typicol penstock profile
..... 142
90
9l
93
to2
105
106
107
108
112
112
4
1 1 5
1 1 9
122
125
127
127
131
133
133
133
135
136
142
142
144
149
lypicol HPDE mild steel pipe coupling
Surge pressures
Jhonkre mini-hydro p€nstock olignment ot downstrcom end
Tronsition from buried to exposed penstock, jhonkre mini-hydro
Sliding rype exponsion joint
Thermol exporsion ofo p€nstock pipe
Setting out rh€ c€$tr€lin€ ofth€ pensto(k 6lignm€nt
Anchor block s€ction.
Composit€ onchor block section
Arrangement ofweor plote ot a suppon pier
Typicol s€ction through o support pier
Diston(es ond ongl€s used in onchor block ond support pier equotions
Proposed onchor block shope
Force diogrom on th€ qnchor block
Suppon pier for smoll schemes with ground height ofless thon 1 m
Suppon pier for smoli schemes with ground height of 1 m to 2 m
Powerhouse floor plon ofth€Jhonk€ mini'hydro scheme
Mochine foundotion section
Mochine foundotion plon......
Resolution offor€s on the mqchine foundotion ...........
Proposed mochin€ foundotion section for Exomple 8.1
R€inforced concrcte toilroce chonnel
Gobion retoinirg w011..............
Stone mosonry r€toining woll................
T€rrocing ond dry stone wolls to retoin slop€s ....
A gobion check dom 0t the intok€ ofjhorkot micro-hydro scheme
A Coondo intoke scr€en ..........
Propos€d orrongemenr for bursting disc instollotion in micro-hydro s(h€mes
Flexible steel suppon pier forJhorkot micro-hydro scheme
Foundotion for theJhorkot f lexible support pier...........................
145
'150
LIST OF TABLES
Toble 1.t
Toble 2.1
Tobie 2.2
Dillerenc€s between micro'hydro ond lqrge hydro schemes
Indicotors of slope instobility
Possibl€ use 0fsoil & rock in micro-hydropower .......... 10t2Tqble 2.3 Cqnol se€pdge loss€s......
cot€gories of Nepolese rivers
Selection criterio tor side qnd bottom inrcke
19
Toble 4.1 Roughness
Toble 6.1 Advontoges ond disqdvontoges of different penstock moteriol .......... 90
Toble 7.3 Unit weight (y), ongle of friction (Al ond ollowoble beoring pressure for diflerent soil types .......... 121
UST OF WORKED OUT EXAMPLES
UST OF BOXES
Box 3.1 Composite gobion concrte PVC sheet
Box9.1 Use of mosonry grid to stobilise theJhonke mini-hydro powerhouse orec slope ........743
1. Introduction
1.1 Hydropower ond micro-hydropower
Hydropower is the generotion ofpower (mechonicol ond/or
electricol)using the foll ofwoter In the cottext ofN€poi, o
hydropower scheme with on instolled copocity ofless thon 100
kW is clossified os micro hydro. Schemes in the rong€ 100-1000
kW ore clossi{led os mini hydro, ond shore some ofthe choroc-
teristics 0f micro-hydropower schenes. Apqft frorn the power
output ofschemes, some 0fthe mojor differences between lorge
ond micro hydro cre shown below in Tobie Ll.
SOMI DENNITIONS
. Civil engineering is the opplicotion ofscience to the
pr0ctic0lbuildirg ofsofe ond cost effective structufts.
. A structure is on ossembly of motencls which serves the
pueose for lvhich it is designed (occommodote people,
conv€y Ilou trofi ic, etc.) ond c0rries the ossocioted
loods . A c rv r l e r ,g rnecr ing s r ru , ru re r ' spr r . f i co l l y
designed to fulfil o purp0se ond/0r pe orm o function qt
0n opprop ore quolity ond to qn occeptoble time scole
ond cost.
r Civil rvorks are cll octivities necessory for the building of
structures.
. Sforoge schemes moke us€ ofo dom to stop river flow
building up q reservoir 0fwoter behind th€ dom. The
wotrr is then reLeosed through turbines when power is
n€eded.
r Run-oiriyer sche mes do not stop the river flow, but
insteod divert p0n ofthe flow vio o heodroce ond
Toblt l.l Differenc€s b€tween micro-hydro ond lorge hydro schemes
The design ond construction 0fcivil €ngineering works hove
some important chorocteristics:
They ore depeodent 0n conditi0ns ot the site. No two
sltes orc the some.
They olwoys involve structures thot ore in contoct with
the ground. Design engineers moy hcve controloverthe
mot€riols used in corstruction, but hove li lnited conrr0l
over the ground on wh i , h lhe \ t ru ( lu re s l0nds . They
must therefor€ toke occount ofthe ground conditions,
ond moy hove to consider olternotive sites to ovoid
stobil ity probleIns
They oiten involve o number 0fpeople working on
design, supervision ond constructi0n ot the site. Vorious
skills ond moteriols ore involved, usuolly over o period
of severoi months. Therefore plonning, communicotion
ond occount0bility ore very importont.
Foilure ofcivil works con be very dongerous ond very
expensive. Similorly, poor performonce or over-design
ore uneconomicol.
On€ importont point should b€ recognisedi complete
stondordisotion 0fcivil works is not possibl€ due to the
vori0tion in site conditi0ns. Insteod, stondord 0pprooches to
penstock to q turbine. Micro-hydro schemes qre olmost
olwoys run'of-th€-river.
1.2 Aspects of civil engineering worlc
DESCzuPNON MICRO HYDRO SCHEMES LARCE HYDRO SCHEMES'IYpe
Pow$ generotion
Noture oi intoke
funnels & underground structuri,s
Penstock oliqnment
surge shoft
Distribution system
Unlined conol
N'lostly run-ol:river
Electricol ond/or rnechonicol
Usuolly t€mporory 0r semi-permonent
Rore
Verticol & Irorizontol bends
Rore, fbreboy octs os surge tqnk
Isolot€d (i.e. not coonected to then n r i ^ f n 1 o l , . f r , . , r v n r i . l r
Cor0rnon
Both run'of'r iv€r ond storoge
Electricolonly
Pefmonent
CoII]mon
Fewer verticol bends ond usuolly no h0nzontol
bends
Comrnon
Ilostly grid connected
Rqre
I
II
design ore used. providing methods ond crireriq thot enoble o
design to b€ odopt€d to conditions ot o site
Of course, scfe. occurote ond economic design is essenti0l
in civil engineering but, becouse ofsite voriotions, o procticol
understonding ofdesign is olso cruciol. Fqilures in civil engi-
neering do not usuclly 0ccur through on error in colculotions
but becouse of o seemingly nrinor €vent or cjrcumstonce lvhich
drd not s€€n1 imponont. A thoiough understqnding is needed of
which elemenls ore crit icql.
1.3 Components of micro-hydro schemes
Alth0ugh no two micro hydro sites 0re sirl l iLqr, oll ofthem
require specific common components ofdifferent dimensions to
convey the streom w0ter to the power generoti0n units ond
bcLk r i lo t :? s l reom :he 'c io r : :ponent ' oD 'sho l ln rn Frgure
1.1. Thc civil conponents or€ briefly discussed below:
HEADWORI(s
Structures ot the ston oithe scheme or€ collectiv€ly cqlled the
heodworks. In micro-hydro schemes, the heodriorks ohvoys
include the diversion weir, intoke ond grovel trop. A spillwoy
ond o settling bosin ore qlso usuolly ot the h€odworks.
DIVERSION WEIR
A diversion weir is o low structure (smqll dqm) ploced ocllss
the river which diverts some ofthe dv€r flow into the
hydropower scheme. The weir con be of o permonent, semi-
permon€nt 0r temporory n0ture.
INTAJC
This is ot the riverborlk upstreom from the diversion weir
where w0ter is init iolly drown into o c0nduit (conol or o pipe).
Usuolly 0 flow contrcl structuI! ond o coorse troshr0ck 0rc
incorporqted ot th€ inroke.
GMVEL TRA"P
This is 0 bosin (pond) clos€ to the intoke wherc grovel 0nd oth€r
coorse mot€riols ore tropped ond then remov€d. In the obs€nce
ofthis structur€ grovel con s€ttle olong the gentler s€ction of
the heodroce or in the settling bosin.
SETTUNG BASIN
Thl5 LS qLso o bosin where sqnd 0nd 0lher Iine 'uspended
porticl.s present in the river woter ore sertied ond then
renoved. lf ollowed t0 enter the p€nstock. such porticles wordd
obrode lhe penstock pipe ond the turbine 0nd hence shonen
thcir opLrqtl()n0l l i \ ' fs.
HEADRACE
This is o conql or o pip€ thot conveys the woter ftom the
heodworks to the foreboy structure. The heodroce olignmenl is
usuolly on even to gently sloping ground; o heqdroce pip€ is
generolly not subject to srqnificont hydrculic pressure.
FOREBAY
This is o tonk ot th€ entronce to the penstock pip€. ihe foreboy
tonk ollows for fl0w tronsiriorI from open chonnel to pressure
flow ond provides storoge wh€n there ore flow fluctuotions in
the turbine. It con olso serve os o finol settling bosifl. ln fqct,
sometimes the settl ing bosin ond the foreboy structur€s om
combined.
SPILLWAYS AND ESCAPES
Spillwoys orc openings in h€odroce conols thot divert €xcess
flows ond 0nly ollow the design flow d0lvnstr€qm. Note thot
some literoture moy us€ th{ terms spillweir 0r overflow t0 r€f€r
to the spillwoy. Escopes ore similor structures but their function
is t0 diven flows from the heqdrqce conols in cose the upstrcom
sectjons get blocked such os if there ore l0ndslides.
CROSSINGS
Thes€ ore structur€s thot convey the flow over streoms, gullies
or ocross unstoble telloin subject to londslid€s ond €rosion.
Aqueducts. culverls dnd susp€xded crossings ore examples of
such structures.
PENSTOCK
This is o pipe thot conveys wot€r und€r pressur€ from the
foreboy to the turbine. Th€ penstock pipe usuqlly storts wher€
the grcund profile is steep.
ANCHOR BLOCI(
An onchor block {thrust block)is on encosement of o penstock
design€d to constroirl the pipe m0vem€nt in qlldiltctiors.
Anchor blocks ore ploced ot oll shorp horizonrol orld verticol
bends, since there ore forces ot such bends thqt will t€nd to
move the pip€ 0ut ofolignment. Anchor blocks 0re olso
required to resist oxiolforces in long strcight sections of
penstock.
SUPPORT PIER
suppon piers (olso colled slide blocks or soddles) orc structures
thot ore used olong stroight runs ofexpos€d perutockpip€
(betwe€n onchor blocks), to prevent the pipe from sogging ond
becoming overstressed. They need to resist oll verticol forces
such os the weight ofthe penstock pipe ond the wot€r. However,
they should ollow m0vement poroliei to the penstock olign-
ment, which occurs during thennol exponsion und controction
Pr0cesses.
POWERHOUSE
This is o building thot oc(omrnodotes ond proteds the el€ctr0-
mechonic0l equlpment such os the turbine, generotor ond moy
include oqro'plocessing units. Thc electro nechonicol equip-
ment in the powerhouse convens the potentiol 0nd kinelrc
energy 0Iwoter int0 €lectficol power
TAILMCE
Thrs is 0 chonnel 0r o pipe thot conveys rvoter lr0m the turbine
(0fter p0wer g€neroti0n) bock int0 the streqm; g€nerolly the
s0m€ str?0m lronl wirich water wos init iolly withdrown.
Det0iled d€s.riptions of th€se comp0nents includinq
selection, design qnd c0nstruction lneihod0logy 0rc discussed in
subsequent chopt€.s.
A
Toilr oce
l)oul? l.l Components ofo micrc hydro saheme
1.4 The power equotion
'Ilte powerovoiloble from c hydropower scheme is dep€ndent
on the volume llowing in the system ond ils drop jn heighr. The
Rloti0nship ls exprcssed by lhe po!ver equotr0nl
P = 0 x o x h x €
rvhere:
t ' is the power produced in kw
Q is the flow in the penstock pDe in mr/s
g js the occeleration due t0 grovity = 9.8 m/s':
hq,,,, is the gross heod ovoiloble in m
e is the overoll s!'st€rn eiliciency
Gross heod, h,, ,., is the dilference bet!\r€en the lvoter level
ot the f0reb0y ond the turbjne centreljne level (or toilroce woter
surioce ifo drqft tube is uscd). This is shown schemoticolly in
F igure 1 .2 .
Nel h€od, h , is the pressur€ heod ot the entronce to the
lurbjne. Thot is lhe gr0ss head mirus conveyonce losses in lhe
penstock. For micr0-hydropower schemes the penstock 1s
generolly designed such thoI the net heod is 90'95q,r ofthe gross
heod meosured from the Ibrcboy (reier to Secti0n 6.4 for
penstock sjzing).
The 0veroll systeln ell iciency, e", is the rotio ofuselul
po$,er output t0 hydr0ulic power input. It is the prOduct of
s€pqrate effl. iencies for severol components ofthe system. i.e.
e : € i r e L e q e , ,
wherc:
er is the pensto.k efficrerrcy. rypicoliy 0.90 0.95
i h = h e )
e, is the turbine efl)ciency. typic0lly 0.65 - 0.80 depending on
rurDlne ryp€
er ls the generot0r efl iclency, typicolly 0.65 0.90 depending
on s izepL is thr lronsmissi0n emciency rncluding trcrnsforners i l
used, typicolly 0.85 0.90
F0r preliminory plonning of rnicro-hydropower schemes
in Nepol it is comm0n to ossume on overoll system efficiency 0f
0.5 to 0.6. However, it moy be os low as 0.3 lor very smoll
instollotions ond os high os 0.7 f0r lorger schemes. Therefore ot
detoil€d desiqn stoge it is imponont to recolculote the power
output bosed on the octuol design 0nd monufocturcrs' doto for
the proposed equipment.
F i g , . r p l l H c o d . r h e \ e r t o l h . g l . l r h r c u ! h w h . , l | , h d r p r d r o p .
l rap/^ / )
a'/'/
z\{],,'<\,
l Anchq
2. Site selectionond planning
2.1 0verview
Th€ selection 0fon 0ppropriote sjte in m0st micro-hydropower
schemes is on iterotive process. In the Nepolese context, usuolly
some community members rvho hove hod previous exp0sure to
micro-hydrgpolver tcahnology oppiooch fundrn g ogenIies.
consultqnts or monufocturers dependinq upon their f lnonciolps0urces ond the size 0fthe scheme. Thf r€chnicions ofthe
ogency concemed undertoke o sire visit to ossess whether the
site is feosible f0r a micro hydro irstollotion. Bosed on the
feosibil i ty report submitled by th€se tecirnicions, th€ commu.
nity members ond others involved ln the process decjde
whether t0 pr0ceed f.rf l l ief with I ne di\ / lJpmpnr of rhe
scheme.
0nceth€ decisi0n is mode to proceed wjth the scheme,
ond if it is in the upp€r ronge 0f Dicro hydro (soy obove 20 kw)
then 0 detoiled survey ofthe protect or€q is undcrtoken ond a
detqiled design rcpon is prcpored. Th€ sor)cti0n oi loons,
subsidy ond grcnts by funding crgencies ond bonks ore bosed on
this repoft. Thrre ore frequent m€etings between the concernedporties during this stoge. F0r the lower el]d oi micro hydr0 (soy
iess thon 20 kW). usuolly the monufocturers undertake both the
design ond instoLlotion.
Apon from socio econornic foctors such cs the need 1br
electricity, 0lI0rd0bil ity, ond supply 0nd demond, technjr0lly
the selection ofon 0pproprioie site depends on the foll0wing
two foctors:
. Streom ilolv
. Topogrophy
As mentioned in Chopter I, the power ovoiloble from o
micro'hydroporver scheme is o functjon 0fboth the flow ond
the heod. The heod depends on the topogrophy i\,ficro'hydro
becomes technic0lly vioble oniy ifthe combinotion ofhead ond
flow ore such thor the demond of the rorgeted conrnrunity con
be met. Urdsr n0rmol circumstqnces. Ihe low scoson florv r,i the
III
nv( rs l r0u ld be u5ed wh i le (01 ,u l l l rng Ihepowpr 0 - lpu l I l
should be n0ted thot designers hove ll le c0ntrol over the l low
ovoiloble in the streonl. Horveve( they h(ve s0me conlr0lover
lht'topogrophy. They con choose dil lerent olignnents for lhe
intoke, heodroce ond penst0ck. l hey con olso modify the locol
topogrophy through excovotion, building 0fstructures ond by
undertqking s0il stobil ity enhoncemenl meosures.
Although the plonning ofDricro hydro civil works does
not rBquire the detoiled work oflorge projects, the principles orc
tht s0De 0nd core needs to be token to foll0w some bosic rules.
Proper plonning ond co-0rdinoti0n in th€ init iol stoge ofthe
proj€ct will keep costs to o mirrimum ond reduce deloys.
Meosurement ofheod ond flow ore beyond the scope of
thpse guidelines but full desc ptions 0fthe methods used con be
found in o number oftexts including Rei 1.
2.2 Principles of site investigation
Site rnvestigotion is the preliminory work c0rried out t0
estoblish the suitqbil ity for construction ofthe vori0us options(or the most fecsible option rI rt is opporentr t lrrough the
rnvestigotion of soils, slope stobjl ity, f lood l€v€ls, surfoce woter
movenent qnd subsidence. This is discussed loter in this
chopter
In most civil €ngineering work, the unexpecred hcppens.
Sit€ inv€stigotion oims to predict whot this might be so thot the
engineer con prepore o design thot wil l deol with it.
It should b€ noted thot th€ meosurement ofheod ond
flow serves to estoblish the 0pti0ns ov0iloble for development of
the site f0r micro'hydro. The site investigotion then qssesses the
suitobil jty ofthe site f0r eoch olternotive. The site invesrigotion
process helps to choose the optinlunr loyoul where more thon
on€ opti0n opp€ors to be teosible. Site condrtions ore ols0
recorded during the site investigqtion stoge so thot there is
odequot€ informotion for the detoiled design phose.
Ther€ is usuolly o limit t0 th€ time ond funds ovciloble
for site investigotions. lt is olwoys dimcult to know wh€n
odequote work hos been comp)eted. Thekeyistowork
efficielltly ond to think corefully 0bout where mor€ thorough
invesiigqtion is required. The principles ofsit€ investigotjon 0re:
. Take your time and be thorough. A return visit to coll€ct
informotion missed th€ first time is costly, ond inod-
equote civil d€sign ev€n morc so
. walk oll over the sire. Goin o fulloppreciotion ofthe
options ovoilqble.
. Tolk to local peopla especiol)y those who hove corried
out construction work in the or€o. Since most ofthe
riv€rs in th€ mountoins ond th€ middie hil is ofN€pol
hove not been gouged, streom flow dqto ore not usuollyqvqiloble. Therefore, it js imponont to tolk to l0c0l
people t0 get o l ir€l ofth€ flo0d lev€Ls for rore l lood
everts (soy 20 yeors t0 50 yeors return period).
. Overoll, oim to rqise the understonding ond oworeness
ofchonges in the site over time.
2.3 Selection of olternotive lovouts
2.3.1 AN OVERVIEW OF THE SITE
This will involve viervlng the site from o physicoLvontoge point
os shown in Figure 2.1, ond toking tim€ to consider the procti-
coldesign qnd construction ofthe olternqtive loyouts (i.e.
selected potentiol sites). Eoch possible loyout will require
construction work on diflerent pqrts ofthe potentiol site ond
the surveyor should th€rcforc note on which pon eoch compo-
neni ofthe scheme will be locctsd. The overview should note
feoturcs thot moy 0ffect the d€sign ofth€ scheme, such os slope
stobility, ond lond us€ ond ownership. A sk€tch mop of€och site
plon should be mode os shown in Figurc 2.2.
23.2 LOCATION OF COMPONENTS
For eoch ofthe olternotive loyouts selected du ng ihe site visit,
locotions ofeoch component should be identif ied ond th€n
included in rhe site plorl os shown in Figure 2.2. Nore thot
generolly the locotion of th€ intoke is the key cornpolrerlt in
determining the site loyout, sinc€ th€r€ is usuolly only one most
oppropriote intoke locotion. Ther€fore the intoke lo(otion moy
determine the locotions qnd qligrlments ofother components.
lntoke selection is covercd in Chopter 3.
once oll olternotives hove been identif ied, the most
suitnble loyout shou)d b€ chos€n. Ap0rt from the project cost.
the followirrg ore (he nlqLo criterio thot should be used to select
the most suitoble loyout:
. The combinotion ofheod ond flow ofeoch olt€rnotive
should b€ such thot the required minimum power
output is feosjble.
o Preference should be given to the simplest loyout in
terms ofdesign ond construction.
. The shoner rhe qlignment ofthe scheme is, the less the
requirement for construction moteriols. H€nce, such q
scheme con be constructed f0ster ond ot o low€r cost.
. The powerhouse should be os close os possible to the
lood centre. It is odvisoble to keep the tronsmissiol line
length less thon 2 kilometrcs.
. Finolly, techDic0l porometers such os overo)l slope
stobil ity, f lood risks, ond other site-specific issues should
be consider€d.
Y'r.{ t l u f t\ l \ ,
[ ..r
f d 6dr.-
##a.-)\ ,
r)n k t 1 /
4Flgurc 2.1 Viewing the site frotn o vontoge point glves the opportunity t0 ossess the options for the loyout ofo scheme
Y i l l q g eoo
q reqar o Ea a
Trqnsmiss ioa l j
PoWerlrouse- Qve\oc,F, Q,li!n
Rive r tzr rq.a spillrrzo
l r r i q q { i o a c - q n q
Tqi lrq.'
. ! Fore-bqv
Corn f isld
Corn F i
Sgt t t : "_g !SS;n
S P i l l w a
l leqdrc<.e. C-qnqlG r a v a - l { t
Figur€ 2.2 Atypicol site plon
_5lT E Pt,qN
r l
2.4 Geotechnicol considerotions
2.4.7 GEOLOGY
The geology ofthe site is crit icol to the design, costs ond future
performonce of the civil works of micro-hydro schemes.
Geologicol mops ofcertoin qreqs ofNepol ore qvoilqble qt the
Deportment of Mining cnd Geology or Tribhuvon University's
geologicol librory. It is worth checking whether such o mop is
ovoiloble for the oreo of interest since this will indicote the
generol geologicol condition ofthe site.
Geologicol chorocteristics ofo site con be grouped in the
following woy:
c Major weakness zones -Lorgeoreos ofgeologicol
instobility in the oreqs where the clvil structures ore to
be locqted.
o S/ope stability - The degree ofstobility ofthe hillsides of
the site.
. Sorl and rock fypes - Foundotion conditions ond liobility
t0 seepoge undermining ond subsidence oround
structures plonned for the site.
2.4.2 MAJOR WEAKNESS ZONES
The moin tectonic zones of the Himcloyos generolly correspond
to the physiogrophic divisions ofthe country ond run in
northeost-southwest direction. Mojor weokness zones such os
thrusts or fqults seporote these zones from eoch other. Inqddition there ore mony other "minor" weokness zones which
could significontly impoct the project. If qvoiloble, o geologicol
mop of the oreo where the micro-hydro scheme is proposed
should be consulted to ovoid plor:ing civil stmctures 0n these
mojor thrusts ond foults. If circumstonces dictote the inevitobil-
ity ofplocing the scheme in such zones, expert help from o
geologist should be sought.
2.4.3 SLOPE STASILITY
In geologicol terms, the hil ls ond mountoins of Nepol ore young
ond unstqble. They could be likened to o pile of sond in thot the
excovotion olong o slope eosily results in the sliding ofthe lond
obove, especiolly when o further triggering mechonism occurs
(porticulorly during the monsoon). Common triggering
mechonisms ore the followino:
. Surfqce woter
r Ground woter
r Undercutting ofslope by excovotion
The stobility of slopes will qffect the design of oll
components of o micro-hydro scheme qnd should therefore be
onolysed thoroughly, porticulorly in the following key oreos:
o Above ond below proposed conoi routes.
o Below the proposed locotion ofo settl ing bosin or o
foreboy tonk.
o Along the proposed penstock olignment.
r Above ond below the proposed locotion ofthe power-
house.
Threots in these oreos will either toke the form of
weokening ofthe support oround the foundqtions through lond
slipping owqy 0r collopsing, or domoge t0 structures through
folling debris, os shown in Figures 2.3 ond 2.4 ond Photogrophs
2.1 ond 2.2. tndicqtors ofslope instobii ity ore presented in
toDIe z. I .
figure 2.3 Threot to structures from below due to londslip
Figure 2.4 Threot t0 structures due to folling debris from obove
Photo 2,1 Tension crocks olong oslope Photo 2 2 Obstructions coused by debris follrng from on unstoble slope
tlbk 2.1 Indicotors ofslope instobility
sEcnoN 0F sroPE INDICATOR OF INSTABILITY
LJpper, middle or lower hillslopes Tension crqcks qlong slope (Photogroph 2.1), ground shelves shorply, trces leoning downslope
or bending upwords from the bose, woter springs or seepqge qt bose ofslope, displocement
of pqths, fence or posts.
Fresh rock foces exposed, presence ofsoft, weotheroble rock, openjoints in rock, tension
crocks, overhongs qnd loose rock, woter springs or seepoge ot bqse ofrock foce,
Frcsh d€bris ot bose ofslope, tree roots exposed,loose debris which moves underfoot,
profiles steepen towords bose ofslope, debris littered with deod or ovenurned woody plonts
ond oross clumDs.
Bpos€d foces of londslides
'lle followilg feotures ofthe slope or rock foc€ indicot€ slop€
stobilitf
. complete vegetotion cover, including trees stonding
verticolly
. Stroight, even, slope prolile
I Rock surfoc€s covered with moss, lichen or 0 weotheR
skin
. Hod, impemeobl€ rock
. Rock with no or fewjoints
. Closed mckjoints
. W€ll.pock€d d€bris, especiolly with fin€ moteriol
p0cked into voids between coorse moteriol
. Well-estoblished trees ond shrubs
. No octive gullying (olthough o stoble gully system
moy be present)
The incRosed Imowledge ofthe sit€ goined ftom 0 thorough
investigotion ofthe slopes will influ€nce the design ofthe
whol€ scheme, poniculorly the locotion ofprincipol
srruclurEs.
The recommend0ti0ns frOm thp rnvesligotion ofsl0pe
stobrlity 5hould iollo!\, rwo bcrsic rules:
. Never construct on fi l l , thot is, lond \,vhich hos beerl
builr up or f i l led using excovot€d moteriol.
. Avoid the locoli0D of structLrrcs close t0 londslide zones
2.4.4 SOIL AND ROCK TYPES
The surveyor should investigote whot locol a0nstrLrction
moteriqLs such os soil ond rock ore ov0iloble ot site. Possible
uses 0fsuch moteriols 0re preserted in Toble 2.2.
The type of soil or ro(k olso oflecls thf lourdotion oi
\ r f l r t u r e . 0 n d l l - p L u n 0 l t y p e . f o r p x o n r p l , . . f h e . o i ) t 1 p e , .
sondy loom, o lorger tbundoti0n depth is .equired. 0n the
oth€r hond, structures moy be built directly on hord rock
with0ut ony excovoli0r). Similorly, l ining nl0v not be requjred
for heodroce ccnol if rhe soil type is cloy HDw{rv€r, l ining wil l
be required ifthe oLgnmcnt rs through sondy soil.
Subsidence is coused by the locotion 0fqcid substonc€s
in the locol groundwoter octing on solubl€ rocks such cs
limest0ne. by the presence of rocks which ore l ioble t0 spli lt ing
ond l0liotioir, oi bV undcrEround cdverns \rhich cre prone to
coLlopsc. The presence of thick loyers of loo!c sqndy soil (Ioy
olso Leod to subsidence.
These chorocteristics qre identilled by coreful observo-
ti0n 0fthe site. Limesione 0utcrops, sinkh0les (holes of 2-10 nr
in diom€ter which lorrrl when the i im€storle beneoth diss0lVeJ,
cousing the s0ilobove t0 collopse), the oppeqronce olstreoms
or other seepoge from depressions or crocks in the ground
surfoce ore excmples 0l choroctri istics ro look for.
Undermining refers 10 the octj0n of surfuce woter on the
tbundqtions 0fsrrucrures. The iDtoke ofthe scheme ond the
penstock ore porticulorly prone to undcrminlng where surloce
woter threqtens the structures, but the h€odroce conol is olso
vulnerqble.
Toble 2.2 Possible use ofsoil qnd rock in micro.hydropower
2.5 Hydrology ond wster ovoilqbility
2.5.1 PRf,DICTION METHODOLOGIES
Hydrology dictotes the size ofvorioLrs micro-hydr0 conponents
like the turbine, chonnelond the penstock.lt olso hos gfeot
influence on the schene being designed over or under copocity.
The g€ncrol pro(tice jn Nepol tor mlcro-hydro sch€m€s is t0 visit
th€ sjte dufLng dry secson ond meosure the flo!v. The scheme is
then designed bosed 0n thjs flow This moy leod to situotions
wherc the l lows ore less thon the design flow ond consequently
turbines orp pr0ducing less porver thon expecled The foct thot
nro ny n lc ro hyd ro . h rnr?5 . rL Nepo l repon grnr ro r lon woy
below the iostolled copocity is strong evidence of this. It is
imperotive t0 understond whether the flow wos meosured in o
drier thon riyeroge yeor or in on overoqe yeor, becouse ofthe
influence th0t this hos on selecting the design florv. To be oble to
produce o design flow os occurqlely os possible. o prediction
study must be undertoken.
Most potentiol micro hydropower sites orc locoted on
ungouged cotchments where site specific hydrologic doto is
lo.king. To estim0te yield from ung0uged corchmerts, two
techniqLles qre currently ovoilqble to predict f l0ws. These ore
known os th€ WECS/DHM ond lhe MIP methods, and qre
present€d in the subsequent discussions to predict f lows in
ungouged cotchments in Nepol.
f iow€v€r, o( o rcgi0noi troining workshop on low flow
meosur€ment ond onolysls orgqnised by ICllr{OD in April 1999
in I(othmondu, Nepol, it wos reported thot both the WECS/DHM
ond MIP methods for estimotrng yield from ungouged cotch-
ments hod mojor drowbocks, ond use ofthese methods hod to
be ex€rcised with extro ccutlon- It was recommended thot rhe
WECSiDHM sludies be revielved, ond estimotion ofthe porom-
eters be updoted from time t0 time. In this regord, DHN'I is n0w
colloboroting with WECS Io rsview the pr€vious studies, ond
improve 0nd updot€ the por0nleters by using more stotions
with Longer records ofdcto. [t wos stressed rhot with Nepo]
focing blg problems in estimoting the d€sign low flows for o
N'IE OF SOIL
OR ROCK
POSSIBLE USE IN
Ii'IICRO.HYDRO CIVIL WORKS
TRIATMENT BI]FOR-L USE
Sond Concrcte
Ag!reg0te in concrete
Bed moteriolin droins
Cdbions ond masonrv
Conoll ining
Musr be selected or thoroughly woshed to be free from orgonic motter, fine
ponicles, cloy lumps 0Dd excessive mico.
Musl be corefully soned ond woshed.
Must b€ wosh€d.
N{usl be selected for c0rr€ct type of rock, density ond size.
Testing ofcloy content required to ensur€ thot it wil l serve os on
impermeoble loyer
crovel
Rocks
Clov
10
v0riety of opplicotions including micro-hydropower, o Ielioble
method wos urgently required. In this c0ntext, the lnstitute of
Hydr0logy, U.K. is undertoking 0 project titled 'Regi0nol Flow
Regimes Estimotion f0r Smoll-scole Hydropower Assessment
(REFRESIiA)" in coilcboroti0n with ICIIUoD ond DHII from 1999,
which oims to provrde o relioble method for estimoting the
hydrologicoiregime ot ung0uged sites in the Hrmoloyon r€giOn
0fthe country RIFRISHA is scheduled to b€ rtody in obout fivo
ye0rs trme.
WhcslDepotr|Jfjent of Hydrotogy and
Meteorolry pHMl method
The woter qnd Energ-v conlnrissi0n Sccretoriot (wECs) cud DHN{
(Rel4) method ls b0sed 0n 0 series of regression equ0tions thot
orc derived from onolvses ofoll the hvdrologi[ol records ir0m
Nepol. The findings ofthis l"gfession onolysis hov€ b€en used to
produce €quotions for predicting different hydrologic poronr-
eters such os the l0!v flols, flood flows qnd floiv durotion
rurves.lt js beyond the scope ofthis boQk to exploin in det0il
the WICS/DHIVI meth0d. Reodels ore odvised to consult the
Rfercnce. detoils 0f \\ hr.\ ore provrded in Chop'er I L Appen-
dix Adescribes this method with qn exomple.
lledium lrrigation Project method (MIPI
lh€ MIP method pre5€nts o technique ibr €slimcting the
distributloi, 0f nont hly ilows throuqhout 0 yeor'for ung0uged
l0t0tions. Th€ lvllP m€thod0lOgy uses o dut0hqse consisting of
DHM spot meosurenenrs. The 0ccosionol wddjng gougings
conducted by DHM include only 1ow llows ond these flows d0
not rPpresent the noturol c0ndjtions since they ore residuol
llows amoining ofter obsrroction ior different purposes like
iriq0tion. MIP pr€sents non-dimensionol hydrogrophs of meqn
rnonthly fl0ws for seven difierent physiogr0phic regi0ns. These
hydrogrophs present nonrhly fl0ws os o rotio ofthe flow in
April (0ssumed IOwest onnuol flow). For opplicotion to
ungoug€d sites, it is necessory r0 obtoin o I0w flow dischorge
e5tim0te by gouging ot a pofticulor site. Th€ m€osurcd flow is
then used with ih€ r€gionoL non dimensionol hydrogroph t0
synlhesise on 0nnu0l hydr0gr0ph for the site. Appendix A
describes this method rvjth on exomple.
Comryisons of the WECSIDHM s,,d the MIP opprooches
IIDCSIDHM: D€lio€otion 01 droinoge bosins qnd elevati0n(ontours oR oft€n distcfird on rhe cv0rlobl€ mops: olso
ngmsions wen derived 0n lhe bosis ofobserved 0ows for
c0tdlments ronging in size fr0m 4 up t0 54,100 kTn'. Therefore,
fol llows in smoller cotchments the results would prov€ to be
unnlioble.
MIP: The MIP method opprooch bosed on wodrng meosure.
ments tak€n 0n on int€rmittent b0sis connot be expected to
give 0 good estimotion oftot0l f low in the monsoon months, it
con, however, give o reosonoble opproximotion ofthe divertoble
flows in these months. In the rvet seoson months, NllP would be
expecred to underestimole WECS tlqures, which should more
0ccurotely represent totol f low In the dry seosor l i l lP ond
!VECS should both provide rotol f low estimotes. The MIP
prOcedure, which €xplicit ly odvocot€s the use 0floc0l doto to
odjust the regionol hydrogroph, should give r€osonobly
occurote estimotes through rhe dry seoson months thot ore
crit icol in ossessing micr0 hydro projects.
Not€ drot neither the WECS/DHM nor ihe MIP n€thOds
rvere derived from doto for high oltitude snow'fed cotchments.
F0r such cotchments, more weight should be given to the results
of site meosurem€nts.
It must be €mphosi5ed that one con get o fe€l for 0nnuol
i loods by meosuring f)ood lev€ls ot sjte. Silt ond debns depos-
ited olong the river bonks or l€veljust below th€ vegerction
growlh 0re irdicoti0ns ol l lood depths. By meosuring flood
deprh, width ond overoge gr0dient ofthe river ot the intoke
orco, it is possible to calculote the flood flow using I ' lonning's
equotion, described in 4.3.2. I l is beyond the scope ofthis book
to dcscribe the different methods ofriver gouging: pleos€ s€e
Re[. I or Rel. 2 fbr guidonce.
2.5.2 PROCEDURX TO ESTABLTSH fiE DESIGN FLOW
l. C0ndLr( | 0 flow n.eosurement ol srle during the dry
Jeo\on rNov( mber \1oyJ. Pr|.fcrobly rn February lor
snow-fed rivers ond li{orchiApril for 0ther rivrrs. Note if
the yeor is drier thon overog€, overoge or wettcr lhon
overoge This con be estoblished by tolkiog to rhe locols.
Consider ifthere orE sjgnificont obstroctions by 0ther
wqter users, such os jf igoti0n ond drinking woter
schemes upstreom ol the p0int where th€ gouging wos
conducted.
2. Colculote :
. Averoge nlonthly flows by using WECS/MIP methods.
. Flow durotion curve using WECs.
. lnstontoneous flood 0ows ofdifferent return periods
using WECS.
L compore the dry seqson rneon monthly flows obtoined
by IVECS ond N{lP method. lfthe tlow meosur€d ot site is
0bout overoge occordjng to the locol people, romp0re
the dry seoson meon moDthly flow obtoined by the
WICS method with thot obtoined by the lr'llP method,
ond use the lower volue. Ifthe fl0w wos meosured ot
11
sit€ du ng elther o wetter thon qverqgr yeqr or o drier
thon overoge yeor, then use the volue obtoined by th€
WECS melhod.
Use the llow durorion curve (FDc) to estoblish theprobobil ity of exceedonc€ ofthe volue fron step 3. The
FDC is useful becouse the power €quivolent ofthe flow
con be superimposed onto it, so thot it is p0ssjble lo reod
ofl the omount oftirne eoch ye0r thot certoin power
levels con be obtoired. This is o useful plonning tool,
oJlowing o choice ofsize ofturbine t0 be mod€, together
v,/ith 0n indic0ti0n 0frcquired vorioble flolv perform-
once ofturbine 0nd on indjc0tion ofthe plonl f0ctor
constroints which wil l result from ony portjculor choice
oftu.bine siz€. S€e R€f. l fordetails.
Decide on whct perc€ntoge ofthe l low es(qblished in
st€p 3 cqn be div€fted for power generotion. lfusing a
temporory weir ossum€ thot 50% ofrhe 1l0w corl be
divened. lfthe rive! preselts farmidoble dimculties,
ossume less thon 500/0. If using o permqnent w€ir
founded on bedrock ossume 954/0 ood for weir bosed on
olluvium foundotion, ollow for seepqge losses ond
ossume thot 90olo of the flow c0n be drvened.
Toble 2.3 cqnql seepoge losses
N PE OF SOIL SEEPACE LOSS, (lh/1000 n'
OF WETTED AREA)Rock
Impervious cloy loom
Medium cloy loom
cloy loom or silty soil
crovelly cloy loom or sondy
cloy or grovel cen€nted with cloy
Sondy loom
Sondy soil
Sondy soil with grovel
Pervious grove)ly soil
Grcyel wrth some eorth
<0.5
0.8 - 1.2
1 .2 - t .7
1 .7 ,2 .7
2 .7 ,3 .5
3.5 5.2
5.2 6.4
6.4 8.6
8.6 - 10.4
10.4 20.8
5.
6. c0lculote seepoge losses f0r the w0ter conveyonce
structures. Th€se iosses must be deducted fr0m the flow
estoblished jn step 5. Ssepoge colculotion is covered jn
Section 2.5.3.
7. Consider iftherc are other rvoter users such os jrdgotjon
ond drinking water dowlstreom ofth€ diversion works.
Estobiish th€ omount of flow that hos to be r€leased
downstrrom ond deduct this omount lr0m the 0ow
ifom st€p 6. This is the design IIow.
A design exotiple is inciuded in Appendix A.
2.5.3 SEEPAGE
It i. imperolive ro exomine lhe soil olong the r0ute o[the
proposed conol ond estimote the omount ofseepoge thot o
cqnol mqy suffer, on imponont issue thot is often overlo0ked by
Dicro-hydro designers. Thls is especiolly trut for micro-
hydropower schemes with long unlined conols. Toble 2.3 gives
conol seepoge losses for djffer0nt soil tvpes. By colculoting th€
wetted oreo for o given cross section ofthe conol, seepoge con
be colculofed using doto from the toble. [x0mpie 2.1 i l]ustrotes
this method.
2.6 Otherconsiderotions
2.5.I FLOOD RISK
In site investig0li0n, the concern is for the selection ofthe b€st
option for the desjgn ofthe scheme. Therefore know)edge of
flood levels is imponont ot the two extremes ofthe micro'hydro
scheme, the intoke ond the powerhouse, 0r ot other pons ofthe
A 500 metre lorlg unlined heodroce conol is to be con-
structed in sondy cloy to convey o design flow ofO.l m?/s.
A stondord tropezoidol s€ction is pmposed with o depth
of0.2 m, o bonom width of0.6 m ond side slopes of1:2(V:H). Colculote the seepoge loss in rhe conol.
Solution:
The wetted perimet€r (P) ofth€ ccnol con be colculoted
using the following equotion:p = s + 2 x H x {ifM(see chopter4)=o.o+zxo.2xVi iTZT= 1.49m
The wetted dr€o: P x L
= 1..19 x 500= 747 ml
From Tobi€ 2.1, seepage loss ir sqody clcy is 3.5 lA/1000
m'z ofwetted oreo. Th€ seepog€ loss is giv€n by:
q.,! = 3.5 x wett€d or€oi 1000= 3.5 x 747 /1000= 2.6 Vs
Which is 2.6% of the designed flow of the conol.
12
scheme thot moy be lulneroble to flood domoge from the river.
Flood l€vels moy be pr€dicted by hydrologicol colculotion
from ovoiloble doto to give the 20 yeor or 50 yeor 0ood level, 0r
by ronsulting locol people. ldeolly, both methods should be used
t0 give 0 relioble estimote. Alwoys cllow o morgin oferror so
thot o rore llood event is ollowed for, ond think rorefully obout
how the floods will olTect eoch ofthe prcposed loyouts for the
proJect. The locotion ofthe poweftouse higher oD o slope will
rcduce the ovnilobie heod ond therfore hcve on importqnt
unpoc on the.opoory ond the economrcs ofthe prqect.
2.5.2 CROSS DMINAGE
Sometimes, because 0fthe n0tur€ ofthe topogrophy, the
he0dmc€ conol ond/or the pgnstock olignments will n€ed to
cr0ss gullies ond smoll streoms. Note thot dry slopes ole more
stobl€ thqn soturoted slopes. Surfoce woter con be diverted by
conslructing v0rious t)?es of cross droinoge works. For
exomple, cotch droins con be constructed uphill from the
rnicro-hydro olignment to divert th€ surfoce runoff. Cotch
droins ore smoll chonnels thot divert surfqce runoff(thus cotch
it)qnd diveft it int0 neorby gullies or noturol drqinqge.
Another exomple ofcross drqinoge works is the use ofo
superpossoge. This is o covered heodroc€ conol orrongement
sudr thot the surfoce runoffllows over it whereos the design
flow is sofely conveyed in the conol.
2.6J WATER RIGHTS
Sometirnes there con be woter use conflicts betw€en the
pmposed micro-hydro sch€me ond other prior uses oFthe source
stnon. For €xomple, ifthep is on irrigotion scheme down-
stn0m 0fthe proposed micro-hydro intoke thot moy r€ceive less
wot€I {once the micro-hydro plqnt js commissioned), thelt will
be conflicts. Such w0rer righrs issues should be rcsolv€d beforc
inplementing the micro'hydrc sch€me.
It sh0uld b€ not€d thqt irrigqtion ord micro-hydro ccn be
c$ordjnoted ifon cgrc€ment with oll conc€rned porties is
Rodred in the initiol stoge. This is b€cqus€ inigqtiorL woter is
not ltquind throughout the yeor orld thercfore woter cqn b€
us€d for power production ot other times. This moy resuit in
less or even no power ovoiloble during peok irrigotion period.
fiow€ver, ifthe elertdcity users or€ olso owners ofthe irrigot€d
lond, they con prioritise their needs, such os by irrigoting in the
oftemoons ond nights ond producing power duriDg mornings
ond evenings.
2J.{ tiND OWNEnSHIP AND LqND USE
T1I€ surveyor should note down the issues conceming lond use
ond ownership. Ifthe olignment trqvers€s thrcugh o form€r's
poddy neld, the lond moy hove to be boughr by the prcj€ct.
Another €xomple is thot on open chonn€l heodroce moy be
technicolly feqsible but the designer m0y hove to choose o
buried pipe ifthe heodroce olignment is r.rlong cultivoted lond.
Similorly, sediment flushing ond spillwoy flows need to be
sofely diverted owoy from cultivoted lond. It is importont to
note down londowners whose lorld will be used for structures,
so thot ogreements such os leose orrongements cqn be negoti'
oted. These foctors will offect the design ofth€ schene.
2.5,5 HIGH AITITUDE SITES
These guid€lines ore g€n€rolly opplicoble to micro-hydropower
in Nepol, but some porticulor m€osurcs n€ed to be tok€n for
high oltitude sit€s to ovoid ill'efffects fmm fr€eziDg tempero-
tur€s.
To 0void frost dom0ge to concrele ond mosonry, th€
following meosurcs ore necessory:
. Keep the woter to cement rotio os low os possible,
pr€ferobly not mole thon 0.50.
. Avoid oggregot€ with o lorye moximum size, or o lorge
proportion of fl ot porticles.
. Use o woter reducirg oir entrqining ogent (plosticiser).
. Ensure good compoction.
. Do not build while night temperutufts ole below
freezing. Surfoces must be prevented from drying out
for ot leost three weel6 ifthe ombient temperoture is onqverog€ 5oC or less.
To ovoid ice domoge to conols ond structurcs, the woter
foce of wolls should b€ smooth concrete or plost€red mosonry
oDd inclined ot 0pproxrDotely l:1. The exponding ice con then
ise between the wolls, inst€od ofpushing the wolls aport.
Heodrqce c0nols should be designed for o minimum
velocity 0f0.6 m/s. Ev€n though the surfoce mcy frceze, woter
will flow under the ice.
The rop ofrroshrqcks should be below ony exp€cted ice
lev€1, to ovoid ice forming oround the troshrock bors. Timb€r
trsshrock bors moy b€ less lioble to icing thqn steel bors.
Th€ foundotion l€vel of structures should be below the
deprh of ground freezing. This is )ikely to be obout one metr€
depth.
2.7 Plonning
Th€ plqnning ofcivil engjn€ering works lor lorg€ projects is 0
complex process ond the skills Iequired ore considered to be o
seporote disciplin€ within the fi€ld ofcivil enginee ng. The
reqson thot plonning is given so much importonce ir th0t the
project construction cost con be significontly brought dowr by
13
emcient co-ordinqtion of lobou! €quipment ond mot€riols. This
eruur€s thot the Esources orc used ot their moximum prcduc-
tlury
As mentioned eorli€r. the plonning ofmicro'hydro civil
work does not rcquire the detoiled work oflorge prcjects-
However, the principles orc the sqme ond corc needs to be tqken
to follow some bqsic rules. The pmcess ofconstructing micro-
hydro civil works hos three ports:
. Unde$tandingwhot hos to be built
. Estoblishingthemethod, €quipment ond the p€ople
required
. Corr!'ng outthework sof€ly, economicolly ond to the
quolity r€quircd to sotisry th€ cli€nt.
"Ihe undentondingpqrt ofthe prcc€ss sounds stroightfor-
word, but it should not be overlook€d. civen the likely number
ofpeople involved, effective commumcotion ord cleor demqrco-
tion of responsibilities ore essentiql in plonning. Everyone
needs to lanow whot they ore occountoble for ond to whom.
There orc a number offoctors offecting hoq when ond in
whot order the work con be corried out. A checklist of these
foctors is os follows:
. Performonce ofstoff, €quipment ond moteriols.
. Avoilobility of stoff, equipment ond moteriols.
. Holidoys ond festivols.
. Access to the site.
. Weother, seosons.
r Avoilobility oftunds.
. Sit€ geology qnd topogrcphy.
. Existing use ofthe site qnd its boundories.
. Public relotions.
PRporing o "Project Implementotion Chort" in the
initiol stog€ is olwoys helpfr.[ since it will indicote whot
octivities ore in th€ criticol poth ond ollow for plonning qheod.
Undoubtedly, such o chort wiU undergo frequent revision
du ring the construction phose- However, it is stil helpful to
formulote o chort ord moke chonges os necessqry since it con
be used to monitor the progress of work ond plon for futurc
octivities such os procul€mellt ofconstruction moteriols ond
lobour orlqngements. A typico] implementotion chort is
showninFigure 2.5.
Activity Durqtion in months
1 2 3 4 5 6 7 8 9 10Public relotionsi oworeness roisino il D
Site survey including lowflow
meosurement & dotq processingI
Detoileddesign sFinoncing
Tendering ond oword of
construction contrqct @6weeks
A n
Fobricotion & supply ofsteel ports
(penstock, troshrocks, flush pipes etc.)
construction of heqdroce cqnql o N
Construction of settlino bosin & forebov N
Construction of mosomy wol & gully crossing s F T
Insto.llotion ofp€nstock & construction of
onchorblocks & support pie$
o E
Fobricotion & supply oftuftine. beh drive
ond otierelectrGmechonicol eouiDment
s
Instollotiol of tronsmission Iine N T A
Powerhouse construction T I
Electrcmechonicol instollotion qt powerhouse
Testing & commissioning A
Proj€ct hondover to the client L
Figure 2 5 A rwicol Prolect lJnplemcnlohon Chon
74
2.E Checklist for site selection
IAND OWNERSHIE LAND USE A,I!D WATER RIGIITS
H0ve 0ll issues conc€rning lond use ond owlership been duly
recorded during the srte visit? Does the olignment troverse
through o former's poddy field or is jt olong bqmn lqnd? Hove
woter rights issues such os irrigotion use b€en odequot€ly
oddressed?
INTAXE
Moke sure woter con be diverted qwqy from tie river ond
towqrds the heodroce. Does the river course oppeor stoble or
does it look like it will meonder? Think obout floods ond flood
levels. Does lhe riv€r corry l0rge boulders? Ifso, think obout
temporory diversion works r0ther thon o permonent w€ir.
GRAVU, TRAP
Does the river c0rry o sigflificont omount ofgrovel during the
monsoon? If so provid€ 0 grov€l trop os close to the heodworks
0s possible. Con rhe grovel be eosily flushed into the stl€om or 0
neorby gully from the grovel trqp?
SETruNG BASIN'this
stucture should be locoted qs close to the intoke qs
possible. The e0rlier the sediment is removed the less rhe
mohtenonc€ in the heodrqce. Ifthe source river is not for owqy
tle sedimenr c0n be dischorged bock into ir.
IIEADRAG
Il generoJ the heodroce olignment should be on level to slightly
doping ground. Ifthe olignm€nt is ste€p, corsider using o
h€odroce pipe insteod ofo conol. Try to get the olignment owoy
ftomtbe river os eorly os possible to minimis€ llood domog€.
Pmvide escopes upstreom oforeos where the conol might be
blocked by lorddides. tfseepoge fiom the heodroce cqnol con
trigg€r londdides, think obout hning the conol or using pipes.
FONBAY
Allowonce shonld be mode for finol settling ofsediments.
G€nerolly. this structurc should be locqted just uphill ofthe
tr0nsition 0reo whete the ground profile chonges from Ievel to
ste€p, ts th€Ie o possibility to sqfely dischorge the €nt[e flow
ftom o spillwoy in cose ofsystem m0lfunctiol?
PE{STffX
Tle p€Ntock olignmenr should stort where the ground profil€
gets steeper. An ideol ground slope would be between 1:1 ond 'l:2
lV:H). The Ilqtter the ground slope, the less economrc is rhe
p€trsto&.lt is dimcult to mqnuolly loy penstock, construct
support piers ond onchor blocks ifthe slope is greqter thon 1:1.
Also try to minimise bends since th€se will require odditionol
onchor block.
POWERIIOUSE
Moke sule thot ther€ is enough spoce for o powerhouse with the
requiftd dimensions (to fit the electro-mechonicol equipm€nt)
ot the loc0tion sel€cted. Excqvotion con be minimised by
locoting the powerhouse on l€v€l grcund. Think obout wher€
the toilwoter con be dischorg€d (i.€. tolhoce olignment).ls thepowerhouse high enough obove the river to be sofe from floods?
IAII,RACE
Moke sur€ thot th€ t0ilroce is protected fiom the streom into
which woter emerging from the turbine is dischorged. The
toihoce should be oriented downstreom to prevent floodwqter,
debris, ond bed lood from being funnelled into it toword the
powerhouse.
TR,qNSIItrSSION UNES
ls the vlllqge situoted owoy from the powerhouse site? lfso,
tronsmission lines 0re requipd. The cost oftronsmission lines
Photo: 2 3 A Stroight p€nstock run keeps costs to o mininum
15
qdds significondy to the overcli cost ofo scheme. Consult R€i I
for d€ioiis.
AVAII.IIBIIIIY OF COI{STRUCTION
MATERIALS AND IIAOUR
Constructiorl mdt€riols for micro-hydro schemes thot m0y be
fould at site ore sond, cagregote ond ston€s. Arc thes€ mcte -
ols eosily avoilobl€ 0t site or brought fronl outside? AIe skilled
lobourers such os mosons cnd carpenters ond ulskilled
lobourcrs ovoilabl€ at site?
The unit rotes for such construction moteriols ond lobour
should be obtoined while ot site for esrimoting quonritjes ond
cost ofthe scheme duing the design phose. It is more Ielevontto use prcvail ing rotes rother thon distrjct rotes, which orenorrnol]y lower thon the prev0il ing r0tes.
STAB!UTY
Apon from the obove criterio, it is very impofiont for the entire
scheme to be 0n stoble ground. Ifonly o smc)l length ofthe
0lignment is unstobie it m0y be possible to stobihse ir. Refer to
S0ct ron 2 .4 0nd Choprer 9 ro 0sseqs lh is j ssue.
3. Diversion works
3.1 0verview
The div€fiion works for o micro-hydropower sch€me control
the flow 0fr{oter frcm the source river into the heqdroce.
ThE c0mp*€ o diversion weir (usuolly). on intoke, ond
s0metunes nver troiDing works. The diversion works ore pqrt
oftheheodworks, qnd serve the foLlowing functions:
. m0intoin the design 0ow with nominol heod losses
during both monsoon ond dry seosoDs;
. !rcv€nt, or 0t leost minimise, th€ bed lood ond other
flo0ting moteriols (ice, timber, leqves etc.) entering th€
conol;
. sofely cont0in pe0k flows ir the iver ond owoy from
th€ micro-hydro syst€m so thot domoge is not coused
to th€ structures.
'Ihe principol mointenonce t0sk ossocioted with cjvil
works is oftenthe removql ofsediment orld debris conjed by
$e incoming woter, which con couse domoge to the turbines
should itbe pemifted t0 enter rhe penslock. It is therefore
tlsgltiol th0t the odapted intoke design prevents sqnd, bed
lood ond debris irom entering the intoke os much os possible.
one ofthe p ncipol couses ofproblems in the operotion
ofhydroporver schemes is o poorly designed intake which moy
permit oper0tion ofth€ schem€ in the shon'term but beyond
thot. cous€ serious domoge to the system. The design ofon
oppropriote intok€ structure for micm-hydrc in Nepol requires
on odequoi€ understonding of Himoloyon riven since theyh ' v , < ^ m , , , n i . ' , , f , n r ' , r , c
3.2 Generol principles forselecting intqke locqtion
The mojor considerqtions requir€d to select 0ppropridte intok€
locotiols ore disaussed in this section. It is imponqnt for the
design engine€r to r€olis€ thst much con b€ l€omed from
observing the irrigotion intoke sites selected by locol formers.
The forDers ore fomili0r with the rivem ond hove the odded
odvontoge thot they hove observed them over c long period of
tine. In foct, some of the former monoged irrigoti0n schemes
in Nepol or€ more thon 100 yeors old ond the intokes ofsuch
1 7
sites hove foced most problens brought qbout by Himoloyon
rivers.
The following princrples should be considered whiie
selecting oppropriote intoke locotLons:
Minimol disturbs,ncc to the nstursl stste ofthe iver
Construction ofhigh ond permonent weirs 1lo!g€r thqn 1'2 m)
ocross the totol width ofthe dver is g€nerolly ufldesiroble,
becouse domming hos the eflect 0fropid sedim€nt deposition
ond chonge ofpresent river course,leovlng the lntoke dry ond
useless. The design ond construction of weirs requires coreful
considerotion to qvoid preserltinq on obstocle to flood flow in
the roiny seoson. F0r diversion from o noturol pool, no weir is
required ond woter con be conveyed through HDPE pipes 0r o
covered mosonry flume t0 o heodroce conol.
For this reoson, ottempts should be made to locote
intokes such thot the noturol woter level ot low flow in the
strcom is suitoble for the intoke level ofthe con01. This will
ollow the conol intok€ structure to be built ot stream level ond
the onJy meosures nec€ssory within the streom or river bed
itselfore meosures for th€ stobilisoti0n ofthe present stote of
the streom.
Locotion in on srea which offers nsturol prctection
When withdrowing wot€r from o streom whose level moy
increose morkedly dudng roiny periods, it is desiroble to locote
the intoke behind or under lorge, permonently ploc€d boulders
or rcck, these limit the woter thot con enter the intoke, ond
deflect flood flows ond river borne debris owoy. Advontoge con
olso be roken ofstoble bonl<s 0nd rock outcrops.
Lnation on the oubide ofo bcnd
Therc is o noturol tendency ofthe ver to deposit sediment on
the inside ofbends olong th€ ive. At bends, the direction 0lrh€
flqw clos€st to the river bed chonges compored wjth the sudoce
flow. A spircl flow forms, which tronsports the bed 10od to the
inner side ofthe river bend. On oll streoDs ond rivers it c0n be
observ€d thot grovelond sand bonks form ot the inside bend,
i.e. the bed loqd is dive(ed from the deflecting bonk. As o rcsult
ofthis when the river flow d€creoses, the river width decrcos€s
from the inside ofthe bend. Therefore cn intoke should not be
sited on the inside ofo bend. To minimise sediment loqd ond to
ensure flow (tvoilqbility during the dry season, on intqke should
be sited on the outside ofo bend. The best location is about 2i3
t0 3/4 ofthe distonce oround the bend or lhe outside qs shown
in Figur€ 3.1. Shorper bends orc more effective in preventing
ihe entry of sediment, and the omount 0fbed lood tronsported
into the conol decreoses os the diverted proponio[ ofthe totol
flow ln the dver decr€oses.
FLgure l-1 Locoting intoke oround o b€nd
other considerations
In stroight sections of0 iver, the water flows poro)lel to the
bonks qnd the bed lood is transported olong the bottom.
Thefelore iIl stroight sectians the locqtion of the intoke is
governed by foctors such os bcnk stability and heodroc€
ollgnment.
Ih€ locqtion ofqn iltcke structure must be so chosen
thot th€ lorgest p0ssible ponion afrhe bed load remoins in the
river ond is not dive(ed into the hecdrcce. How€vec even c
good intoke lvill not exciude oll sediment; lhe grovel trqp cnd
seltl ing bosin [unher olong the conql (ompl€te this.
3.3 tntoke locqtion in relotionto river chqrocteristics
3J.1 CHARACTERISTICS OF HIMAJ.AYAN RIVERS
In Nepol, most micrc'hydropower schemes ore locoted in the
foothills ofthe Himolqyon Ronge. This includes the High
Mountoins, Middle Mountoins ond the Siwqliks os shown in
Figure 3.2. It is essentiol to hqve q cleor understonding ofthe
chorocteristics of these Himolqyon rivers beforr opprooching
tbe design ond construction ospects ofdiversion works. These
rivers flow in geologicolly young mountoin structuEs ond con
be choroctedsed os follows:
steep river grodient ond steep slopes olong both river
bonks;
High degrce ofcontinuing ercsion 0nd sediment
rr0nsporT;
Sm0ll€r streqms of steep ond unstoble noture with o
bouldery ol)uviol bed;
Ii0ble to tronsport consideroble quontit ies ofsedirnent
rnc lud ing bou lders dur ing lhe monso0n; .
A significont flow ond s€djment incrcose in the rivers
du ng the monsoon.
Due to these u!ique choroct€ristics, development of
hydropower from the Himoloyon rive$ pr€sents grcot chol
Figur€ 3.2 Feosible locotions of mrcro-hydro schemes in Nepol
lenges. Design ond c0nstruction ofoppropriqte structures to
cope with movement 0f lorge boulders qnd high sediment
loods ore two ofthese chollenges. River intokes used elsewhere
in nlotively flot ond stoble rivers including the Teroi ore
inoppropriote in the cose of mountqin rivers of Nepol.
Ioble 3.1 Cotegories of Nepolese rivers
Rivers in Nepol con be categorised occording to the woy
in which they ore influenced by vorious chorocteristics. The
types of river thot sre mostly utilised in micro-hydro ore shown
in Tqble 3.1.
TYPE GMDIENT
(MArN LOCATToN)
VALLEY SHAPE BED MATERTAT CHANNEL PATTERN SEDIMENT MOVEMENT
(N: NORMAL, F: FLOOD)
1A very steep(Mountqins)
Norrow volley no
flood ploinsRocks, very lorge
boulders
Single N - Sond in suspension
F - ravel. cobbles qnd boulders
IB Steep (Mountoins
ond hill regions)
Norrow volley,
irregulor norrow
fiood pioins
Rocks ond bouiders,
grovel ond cobbles
in shools
One moin plus flood
byposs chonnel
N - Sond ond grovel
F - Includes cobbles qnd smqll
boulders.
ic Steep (Mountoins
ond hill regions)
Norrow volley,
irregulor norrow
flood ploins
Rocks ond boulders,
grovel ond cobbles
in shools
Severol octive chqnnels
os well os floodwoys.
N - Sqnd ond grovel
F - Includes cobbles ond smqll
boulders.
A
,${
ry Intermediote
(Hill regions)
Outwosh river,
confined by
volley sides
Some boulders,
moinly grovelqnd cobbles
Single plus limited
floodwoys
N - Sand ond fine to medium
grovel
F - Includes coorse grovel,
cobbles, perhops smqll boulders.
28. Intermediote
(Hillregions)
Ditto but less
confined volley
Some boulders,
moinly grovel
ond cobbles
24 octive chonnels
with floodwoys
N - Sand qnd fine to medium
grovel
F - Includes coorse grovel,
cobbles, perhops smoll boulders.
2C. Intermediate
(Hill regions)
Ditto but wider
volley
Some boulders,
moinly grovel
ond cobbles
Broided, severol octive
floodwoys.
N - Sond ond fine to medium
grovel
F - Includes coorse grovel,
cobbles, perhops smoll boulders.
Soune: Ref.5
19
33.2 EXAMPLE INTAXf,S'typicol intoke locotions for some ofth€se rivers ore shown in
Figures 3.3 ord 3.4. It should be noted thot these ligures
illustrote only possibl€ locotions for iltok€s, not the prefened
rype ofintoke.
fijver type 1A
Mountoin rivers of Type 1A prcvide fovouroble conditions for
intokes in t€rms ofpermonence qnd lqck ofinterference from
s€diment irl normol conditions.
Iigure 3 3 Slung ofinlokes rn mountoin rive6 ofType lA(Soufte: ReL 5)
Nver We 1B
Int0kes on Type 1B rivers con olso be locoted similor to 1A.
However. these riv€6 provide o greoter choice ofintoke site, ond
p€rmit more permon€nt irtok€ structurcs, either ftom the side
ofthe chqnnel or os qn ongl€d or frontol inroke built inro the
chonnel It is often possible to protect the intoke behind o rock
0utcr0p.
fjver We lC
Intoke selection in these riv€n differs from 1A ond 18 oDly in
rcqui ng contrcl of one or more of the chonnels in order to
ensur€ thqt sumcient flow reoch€s the intoke. A possible
orrong€ment is shown in Figurc 3.4.
Figure 3-4 Siting ofintoke in mouDtoin or ste€p hill rivers ofType lC.(Soufte: Ret. 5)
crsvel bed rtvers
These or€ cotegory 2 rivers (2A, 28 & 2C) which hqve less steep
chonnels compor€d to cotegory 1 types. The riverbeds ore
moinly ofcobbles ond grovel, tog€ther with some boulders.
Intoke siting follows the some generol principles os in cotegory
]. However, these vers provide more flexibiliry For exomple, it
is posslbl€ t0 use morc permonent river control structures such
os concrete or mos0nry werrs ond liver rroining wolls.
Post,ua
l
t_tr00d I
' \
Flow dircdim
R o c l c l i f f ,loce
Route offeeder cqlol O
Phoro 3 I Ar?o olrnrole in o rype 28 river (Dhoding)
20
3.4Intqke types
3.4.1 DESCRIPTION
lypes 0fintoke structure ore chiefly distinguished by the
method used to divert wqter from the river. In micro-
hydropoweq moinly two types of intoke qre used os follows:
r Side intqke
o Bottom intoke
Toble 3.2 Selection criteriq for side und bottom intoke
Aport from the obove types, qn innovotive intqke colled"Coqndq intoke" hqs olso been field tested in o micro-hydro
scheme in the UK. This is discussed in Chopter 10 (lnnovotions).
3.4.2 SELECTION CRITERIA
Tqble 3.2 oids the choice between side ond bottom intokes for
grven conditions.
SEI^ECTION CRITERIA SIDE INTAKE BOTTOM INTAKE
Amount ofwoter: Fqvouroble site selection necessory
(outside ofo bend, or qn qrtif iciol bend
by groins) if the omount of diverted
woter is greoter thon 50% of the woter
supplied.
The bottom screen drqws off the river wqter up to the
copocity limit of the screen (i.e. oll river flow if
screen is lorge enough).
Grodient ofriver:
r very high (i > 10%)
tohigh(1070 >i >10lo)
o meon grodient
(tVo >i > 0.0170)
Fovouroble: mointenonce free operotion
ol'the intoke structure should be ensured^ ^ f ^ - ^ ^ ^ ^ - ^ : L t ^u ) l u l u ) P U 5 ) l u l ( .
Fovouroble
Fqvouroble for very high grodient; con be
mointenonce-free, if properly designed.
Unfovouroble ifi < 10o/o.
Unfovouroble: fine bed lood into the initiql heodroce
conol results in difficulty in flushing.
Plqn of river:
o stroight
r winding
o brqnched
Possible
Very fovouroble ifthe river chonnel is
stoble; when orronged on the outside
bend.
Unfovouroble; donrrning of the river
is required.
Very fovouroble, qs bottom screen is uniformly
looded.
Unfovouroble, os bottom screen is not uniformly
looded.
Unlovouroble.
Suspended sediment
c0ncentr0ti0n:
r high
o low
Suitoble in combinotion with very
ell lcient settl ing bosin.
Well suited
Less suitoble
Well suited
Bed lood tronsport:
. strong
r w€ok
Suitoble os long os sulflcient qmount of Less suitoble
woter remoins in the river for flushing.
Well suited Well suited
Nopted fromRef. 3.
z l
3.5 Side intoke
3.5,I DESCRIPTTON
Side intokes ore simple ond less exPensive thon oth€r tyPes of
intqk€. They ore eosy to build, operqte ond mointoirl Side
intokes ore similor to formers' troditionol intokes for irrigolion,
ond hence the form€rs con qurckly leorn the principles of
operotion ond mointenonce ofthese intokes The slde int0ke of
the 50 kw Golkot micro-hydro scheme con be seen in Photo-
groph 3.2. Note thot to mintmise flood flows in th€ conol, the
intoke is design€d os on extension of the heodroce conol lt wos
felt thot the intoke could be vuln€roble to flood domqge ond
therefore the coorse troshrock is locoted further downstreom
Phoro I2 Srde intote ofthe Coltot mrcro hydrc s.h€me Boglung NPpol
{se€ Appendrx C for lh€ dro!t'ing)
side intokes must be s0fe ogqinst boulder impoct ond
floodwqter entry. They ore m0sr effective when built on the
out€r bend 0fthe river (to minimise the omount ofsediment
drqwn inro the inrqke), neor norurol Pools or sit€d ln such o
wqy thot they ore protecled os much os possible from river
floods (e g behind o permoDent rock outcrop) Side intokes con
b€ used with or without o w€ir
side intoke without web lnotursl Pondl
I[ some coses, orl €xposed intoke structure moy be ovoided by
exrrocting woter ftom behind the shelter ofo r0ck outcrop ln
other coses, therc moy be 0 notur0l cleft ln o rock spul 0r on
opeling b€tween o very lorge boulder 0nd o rock woll' thot c0n
be used os o notur0l intoke. wherever Possible, this type of
intok€ should be preferred, slnce it is the most economlcol one,
ond scfe from the domoge offloods ond debris moteriols. It olso
mointoins the principle of "minimol disturbonce to Ih€ nqturol
stote of ver".
A side intoke withour 0 weir is unLkely to be suitoble for
river lypes 1C, 2B ond 2C, due to the strong possibil i ty ofthe
river course shifting in the future.
side intske with weir
The function ofo weir is to rolse the woter level in old€r to
ensule o constont minimum depth ofwqter uPstreom ofthe
weir This ollows the required flow to be div€rted to the
heodroce os long os there is sufncient woter in the river' Types
ofweir ore desc bed in Secrion 3.6.
3.52 TMSHRACKS FOR SIDE INTAXES
The troshrocks for side intqkes con be mo[ufoctured from flot
steel, ongles, tees or rould bors welded together ot flxed
intervols. The trqshrock qt the intok€ is qlso }clown os'coorse
troshrqck" since the bor spocing is wider hele compored to the
troshrqck ot rhe foreboy. For side intokes, Ihe functiol ofth€
troshrock rs to stop boulders, cobbles, flooting logs ond
bronches from entering the heodroc€ Coorse troshrocks for side
intokes ore Dot designed to exclude grovel ond sedrm€nt This is
thejob ofthe grqvel trqp ond the settl ing bosin.
Th€ size ofthe troshrock should be such thot th€ woter
v€locity is opproximqtely 0.6 m/s (o lower velocity is uneco-
nomic, whereos o high velocity tends to ottroct b€dlood ond
d€bris, ond results in increosed heodloss)
Photo.3.3 wh€re on intoke is lioble to ottroct llooting debris
o troshrock moy b€ necessory (Sn t.onlo)
22
Since boulde$ con frcquently impoct the coorseuoshrock, it n€eds to be robust, i.€. thick steel s€ctions shouldbe used. Depending on the length ond width ofthe opening,notur€ ofthe sediment lood ond the required flow o cleorspocing of50 mm to 200 mm con be used. The side intokecoorse trcshrock ofth€ Golkot Micro-hydro Scheme is shown inPhotooroDh 3.4.
Ptoto3.4 Coors€ troshrock for 50 kW Golkor MHq Boglung, Nepol. 55 mm x l0nI! 00ts ot 75 mm centre to centlP. (S€e App€ndix C for rhe drowingl
3J3 ORItrCE DESIGN
Aside intoke normolly includes on orifice domstpom of theElihrock ot th€ riverbonl, thrcugh which woter is iniriolly
d$wn hto the heodroce. Sometimes, the side intoke isjust ocontinuotion ofthe heodroce conol up to the riverbonk.
However, 0s for os procticoble, on orifice should be incorporotedto limit excessive flows during floods. with qn intoke thot isjust o continuotion ofthe heodroce conol to the riverbonl,€ress flow connot be controlled during floods. Such excessfow col domoge the heodroce conol ond other structurestlowastreom. Howev€r, the orifice need not be 0t the intoke0n0{i.e.0t the riverbonk). If it qppeors th0t rhe intqke is or o
ploin or susceptible to domoge from boulders, then thefiiEce con b€ locqted downstr€om. In such coses the conol
ofthe orilice ond the intoke would be temoororv ondnoy ltquft repoir ofter every monsoon.
An orific€ is on opening (Figure 3.5) ir the intoke from
which the river woter is conveyed towords the heodroce. Theorifice ollows the design flow to poss thrcugh it under normolconditions (i.e.low flow) but restricts higher 0ows duringfloods. The dischorge through on orifice for subm€rgedcondition is:
q = nc fi(r'; rt)
v : c \E(4-hJ
where:
Q is the dischorge thmugh the orilice in m3/s
V is the velocity thmugh the orilice
A is the oreo oforifice in m,
dotum.hh is the woter Ievel in the heodroce cqnol meosured iiom thesome dotum os h,.g is the occelerotion due to grqvity = 9.8 m/s,
Figure 3.5 Side intoke
C is the coemcient of dischorge ofthe orifice ond isdependent on th€ shope of orifice. The volue ofC decrcoses withthe omount ofturbulence induced by the intoke. For o shorp
edged ond mughly finished concrete or mosonry orilice
structure this volue is 0s low os 0.6 qnd for corefullv hnishedoperture it con be up to 0.8.
(h, - hh)will vory occording to the dischorge in the river
since o higher woter level in the ver will produce o gr€oter
heod ot the orifice.
The moximum velocity for o well constructed concrete/mosonry orifice is 3 m/s: ifthe velocity exceeds this volue. theorifice surfoce will be scour€d. For micro-hydro, the recom-mend€d velocity (V) through the orifice during normol flow is1.0 - 1.5 m/s. Stortirg with o smoll orince opening for normolflow (i.e. high velocity) will limit excess flow during floods,
since th€ dischorge through th€ orifice is proportionql to the
hh
h n
23
squore root ofthe difference between the wcter level in the river
ond the heodroce conol (h. - hn). However, if the orilice is
directly ot the river (without o troshrock) the velocity should be
less thon 1.0 m/s to ovoid drowing bedlood into the intoke.
The size of the orifice is colculqted qs follows:
r Assuming o moximum velocity of 1.5 m/s through the
orifice, colculote the required oreo of the orifice opening
u s i n g Q = V x A .
r Fororectonguloropening,A = WxHwhereWisthe
width ond H is the height ofthe orifice. Set H occording
to the river ond ground conditions ond colculote W.
. To ensure submerged condition, orronge the orifice
opening such thot the woter surfoce level ot the
heodroce conol is ot or slightly higher (scy up to 50 mm)
thon upper edge ofthe orifice. Note thot the design of
heqdrqce cqnol is covered in Chopter 4. Hence the
design of different micro-hydro components ore interde-
pendent.
Now colculote h, for the design flow conditions.
The h, is the woter level thot needs to be mointqined in
the river during normol conditions. If the octuol level in
the river is less, repeot the colculotions with lorger
width qnd smqller height of the orifice. If the sctuql
river level is still less provide o weir with weir crest level
ot h,
o Cclculote the flow through the orifice for flood condition
(h, = design flood level). The excess flow (i.e. flow
during flood less the design flow) will hove to be spilled
bqck into the river or neorby gullies in the initiql reach
ofthe heodrqce. This is discussed in the next Chqoter.
An exomple of on orifice sizing is shown in Exomple 3.1
ii,l lIi'l.I
I,ll
ffI;I r
II
Choose c suitoble size of on orifice for o design flow of 250 l/s. The normol woter level in the river is
0.8 m obove the bed level. The design flood level is obout 0.7 m obove the normol woter level. Whot
is the dischorge through the orifice during such o flood?
Q = 0.250 mr/s
Set V = 1.2 m/s :
- o 0.25Orifice oreo (A) =
i: LZ = 0.21 mz
set orifice height (H) = 0.20 m oni'*iArn of orifice (U =* = ** = t.os m' H 0.20
Set bottom of orifice 0.2 m obove the river bed level. This will minimise the bed loqd. Also, set the
dotum ot the river bed level.
Set wqter level ot heodroce conol, hn = 0.5 m with respect to the dotum os shown in Figure 3.6 (i.e.
100 mm above the upper edge of orilice to ensure submerged condition). Note thot loter the heodrace
canol will hsve to be designed occordingly.
q = 6g \Dsq- hJAssume C = 0.6 for roughly finished mosonry orifice.
Q = 0.2t x 0.6ffi3466- ss)= 0.31 m3/s or 310lls
Q *ouioo = 250 l/s: Therefore orifice size is 0K.Discharge through the orifice during flood flow:h, - hn : 0.8 * 0.7- 0.5 = 1.0 m;
Qn*o = 0.21 x 0.6 {2x9.8x1.0 = 0.56 mrls
Qn*o = 550 l/sThe dimension of the orifice ond the levels cre shown in Figure 3.6. Note thot the excess flood flowcon be dischorged vio o spillwoy st the grovel trop or onother suitoble locotion. A second option is toinstoll onother orifice {double orifice system) downstreom.
24
Flood level (1.50 m)#
Oriflco
Not to scalo
Normal wator levol (0.80 m)s
0.40 ms7
0.20 m
Rlver bed lsv€l (0.00 m) / Datum
Fioupl6 Dimensions ofth€ orillce ond levek
Plloro 1.5 Timber plonks ploced horizonrolly in grooves pmvide o low-cost gote in o chonn€l In this cose,
th€ dnb€rs hove b€€n lift€d to oct os o restricting orillce (Mhopung)
whether the river is eroding (o generol lowering ofthe river-
bed), oggroding (o generol building up ofthe riverbed), or
shifting its course. The heodworks design, ond in pqrticulor the
choice of weir, must toke occount ofpossibl€ future chong€s.
When it becomes qpporent thot o weir is required, the
following foctors should be considered for both permonent ond
temporory weirs:
. lf0 weir ocross port ofthe river l€ngth is sumcient, then
it should not b€ ext€nded 0crcss the €ntirc width. Aport
from 0dding extro cost it olso encourog€s sediment
d€position upstreom ofthe weir-
. The w€ir h€ight should be os low os possible (i.e. weir
cr€st l€vel = h,, just sumcient to m0intoin the w0t€r
level in th€ intoke). This mokes the structur€ more
stoble, less susceptible to flood domoge ond olso
minimises sediment deposition.
3.5.2 TEMPOMRY WEIRS
A temporory weir is typicolly con-
structed using boulders plcced octoss
pon or oll of the river width. A diqgonol
olignm€nt mcy r€duce the Rquircd
height ofthe w€ir obov€ the riv€rb€d.
This is the tr0ditional method used by
Nepoli formers to feed irrig0tion conols
or woter mills (ghqttos). ond is used
quite extensively in micm-hydro schemes
in Nepol. For micro.hydrc schem€s in the
lower ronge such os those used for ogro-
processing only, this type of weir is often
oPProPnqte.
Though q temporory weir is
simple and low cost, it hos o few
Iimitotions: for example it is not possible
to divert oll ofthe river f low even in the
dry seoson. Therefore this t]?e ofweir is
b€st suited to situotions where the dry
seoson flow ofthe river exceeds the plont's design dischorge.
3.6 Diversion weirs
3.5.I GENEMI.
A weir is Rquired ifthe flow cqnnot be diverted towqds the
side intole without roising the river woter level, especiolly
during the low flow seoson. Th€ weirmoybe oftemporory
semi-permonent or permonent construction, A temporory weir
is the prefened option for micro-hydro schemes.
In pl0millg o weir, ottention must be given t0 the
geomorphology ofthe river, ond ony chcnges tiot moy be
toking ploce. Alwoys consult with locol people ro esroblish Photo 3 6 A lemporory weirin o Type 28 river{Dhqding)
During the high flows, even if the weir is woshed owoy, it moystill be possible to divert the required flow towords theheodrqce since the woter level in the river is high.
A proposcl lor c temporory weir constructed ofstonemqsonry in mud mortor is shown in Figure 3.7. This isintended to ollow diversion ofo higher proportion of the dryseqson flow, but would still get woshed owoy during theqnnuol floods. Constructing temporory weirs with bouldersos lorge qs con be hqndled monuolly ond including cut-offwqlls and riprop con minimise flood domoge. As con be seenrn Figure 3.7, cut-off wolls ore downword extensions of theweir ct th€ upstreom ond downstreom foces thot reduce
seepoge post the weir. Riprop is on engineering term used todenote the plocing ofo loyer ofboulders for scour protection.
The omission of scour protection would result in scouring ofthe riverbed, eventuolly leoding to the foilure of the weir itself.
Once the river dischorge decreoses, o temporory weir
con be usuolly reconstructed ot l i tt le cost. The repoir ondmointenonce work on o temporory weir con be minirnised bybuilding the weir using rock outcrops, Iorge boulders ond
other noturol protection ofthe river. Good monogement ofcosh for the onnuol weir "rebuild" is required.
ln rnost coses, o temporory weir is suitoble only for thediversion of flows below 1 nrr/s. This fits well into the mrcro-hydro dischorge ronge, since the moximum flow in micro-hydro schemes rorely exceeds 500 l/s. For micro-hydro
schemes, o temporory weir is the preferred option over more
permqnent structures. This is becquse most rivers flowingthrough the mountoins ond the middle hil ls of Nepol corrylorge boulders during the m0ns00n ond therefore onystructure built ocross such rivers is not likelv t0 survtve.
3.6.3 GABION WEIR
Gqbions hove been used extensively in the post, for bothmicro-hydro ond irrigotion intoke weirs, but the result hosnot been very encouroging. The gobion wires ore vulnerobleto domoge by boulders moving during floods, ond ofter o fewqre broken the entire gobion structure moy collopse.Gobions ore therefore unsuitqble in river Types 1B qnd 1C.
However, if there is no significont boulder mov€mentolong the river stretch ot the intqke oreo o gobion weir moybe possible. Ifproperly designed qnd constructed, theodvontoge ofo gobion structure is thot, unlike concrete ondmosonry structures, it con tolerote some ground movementwithout significont domoge. TheJhonkre mini-hydro weir ison exomple of o gobion weir structure (see Figure 3.8 ondBox 3.i). The weir design should include checking:
o sofet! ogoinst scour (by founding 0n rock or lcrge
boulders, or by constructing o 'counterweir' down-
streom to lorm o stilling pool)
seepoge control (by using on impermeoble mem-
brone)
st0bility ogoinst overturning ond sliding
sofety on beoring copocity ofthe foundotion.
a
a
Temporcyweir, stone
Locolion of-0225-cb-ssT--rc
All dimensions ore in mm.
Figure3.7 AtempororyweirpfoposedforthelSkWThorongphedi micro-hydroscheme,Monong.NepolNote the cut'olfwqlls ond ripr(p at downstreom foce.
LO
@o(9
o{(ot \o
M M O M S
HDP f lush o i
140fflnfr HDPEfor irrigotionFore b
G rovel t ro
I n t oke
Poo lG ob ion we i r
i i i g u r e 3 ' 8 [ l e o d w 0 r k s o f r o n g c n ] e n t 0 | t h e 5 0 0 k W J i l 0 n k r e n l i n j I t y d r o s c 1 t e m e , N e p o l . N o t e t h o t t h e i n t o k e , s e t t l i n g b c s i n
structure ond there is no hecrdroce. the topogr0phy is such thct 0 pel)stock olignnlent could be storted ri itht 0t the heodworks.
II
I
, \€r\
Qt
lti7/
4,
27
Figure 3-9 Cross section ofJhonke Mini'hydro drversion welr
ll tr rl E&(
Photo 3.7 Diversion weir of rhe Jhonlce Mini-hydro Sch€me
The 500 kW Jhonlar Mini'hydropow€r Sch€me, locot€d 0n theJhonlqe river, Dolokha, Nepol, wos designedjointly by BPC
Hydroconsult qnd Development ond Consulting Services (DCS). The construction wqs undertoken by DCS. As con be seen in the
section through the weir, to minimise seepoge in the dry seoson, o heovy grode polFhene sheet hos been fixed qt the upstEom
foce of the gobion w€ir' T0 pr€v€nt the sheet ftom being punctured by boulders ond other debris, stone bockfll hos be€n
incorporoted in front ofit. Also to prevent the gobion wires from being nicked by rolling boulders, 150 mm ofploin concrete isploced olong oll exposed surfoce ofthe w€ir.
Dudng o 1995 monsoon flosh flood (esdmoted to b€ o 1:30 yeqr return period flood), this weir wos portiolly domoged. It wos
then repqired. Since then, the weir hos foced two onnuol floods without ony repoirs. occosionql repoir ofthe concrete topping
ondtlle gobionwires oreexpected (i.e. during the onnuol mointenonce period.
2 8
3.6.4 PERMANENT WEIR
Sometimes if there is o scarcity 0f woter, especiolly during the
low flow seoson, ond the river does not corry lorge bouiders, o
permonent weil moy be built ocross the river. Micro-hydro
schemes in the higher ronge (50 kW or obove) ond mini-hydro
schemes (100 kW to 1000 kW) often hove permonent weirs.
Permonent weirs ore generolly c0nstructed of moss
concrete (1:1.5:3 with 400/o plums), or stone mosonry in 1:4
cement mortor. A reinforced concrete surfoce loyer moy be
considered to protect the weir from domoge by boulders moving
in flood. A permonent weir should only be considered if oll of
the following conditions ore met:
r Lorge boulders do not move in the river ot the weir site.
r The river bed is stoble (not eroding, oggroding or
shifting course)
o There is o scorcity offlow, especiolly in the dry seqson.
r Skilled mosons ore locolly ovoiloble for both construc-
tion ond mointenonce.
r There ore suflicient funds for both construction ond
future mointenonce work.
Even if qll of the obove conditions ore met. further
considerotion should be given for remote sites (3-4 doys wolk)
becouse of the cost ond difliculty involved in tronsporting
cement ond reinforcing steel. Besides considering the foctors
mentioned eorlier (use of lorge boulders, weir ocross port 0f the
river if possible ond low weir height), lor permonent weirs
scour protection should olso be provided. The toe ofthe weir
(i.e., downstreom foce of the weir) is most susceptible to
scouring since there is o drop from the crest ofthe weir.
Protection ogoinst scour is provided by cut-offwolls ond
plocing boulders (such os stone soling) or riprop downstreqm of
the weir cs shown in Figure 3.10. The cut-offwolls olso reduce
seepoge under the weir, which con increqse the flow ovqiloble
t0 the intoke during the dry seoson. Figure 3.11 shows onother
option for 0 permonent weir in cose bedrock is found qt the
proposed site. When the weir is on bedrock, deep cut off wolls
ond riprop ore unnecessory. As shown in Figure 3.11, shollow
cut olf wolls ond onchor rods con be used to fix the weir on the
rock surfoce: the anchor rods should be grouted into the rock.
An ulternotive design is described in Box 3.2.
200rhk. Rc cT 12 @ ZOOdc tbothways
12C-V
-2.OOV
o.45v
I lmo I 3560 | tooo I
Note: All dimensions ore in mm. levels ore in m.
Figure 3.10 A stone mos0nry permonent weir proposed for Ghomi microtydro scheme, Mustong, Nepol. The 1:3 slope ollows rolling boulders to tr0vel dOwnstreomthroughthewcirondtheRCCblonkethelpstostrengt l ientheweirsurfoceogoinstobrosionduetorol l ingboulders. Alsonotethecutol fwol lsondr ipropotdownstreom foce.
Stone cement mosorry (
29
Figure I 11 A plum concrete permonent weir proposed for chdmi micro.hydro scheme The lil slope ollows rolling boulders to trov€l downstreom rhrough thew€r ond th€ RCC blonket helDs Io str€nath€n Ih€ weif surfoce oooinsr obfosion due to rollino boulders
Ph.rm concrele ( | : 3 : 6, 4OoloPlums)
2OO lhk RCC (t : 1.5:t500,r-1
Tl2 @ 2OOczc bof hwoys
€A.,.-3-v
t20v
o.@
16 onchor rodlonS @ 3 OOc,t,gortedwith l : I :O.4(cement,sond
Note: All dimensions ore in mm, levels ore in m.rvoler) qrot | .
lnPeru, rTDG hosbeenusing on opprooch to design
ofintokes which uses plonks slotted in piers
perpendiculor to the dil€ction offlow ofthe riv€r
Short reinforc€d con(ete piers or€ constructed ot o
spocing of2 metres. Eoch pier hos verticol grooves
olong its full depth. Then timberplonls ore ins€fted
betweenthe pi€rs by inserting th€ ends ofplonks
onto the slots. During the roiny s€oson, one or more
spons con be removed to regulqte the flow ot the
intoke orilice qnd to ollow river-bome debris to llow
olong it without cqusing domoge to thewhole
stntcturc.
Photo 3 8 slort€d conrrere piers
3 0
I
3.6.5 HEAD OVER WEIR
As stoted eorlier, plocing q weir ocross the river roises the woter
level. Any excess flow thqt is not withdrown into the intoke
flows over the weir. The dischorge over the weir is given by the
iollowing equotion:
Q = C* x L *., x (hou.noo)t t
where:
Q = Dischorge over the weir in mr/s
L *", = Length of weir in m
hou.nop = Heqd over the weir crest level in m
C* = Weir coeffrcient which vories occording t0 the weir profile.
C* for different weir profiles is shown in Tqble 3.3. In micro-
hydro, the weir is usuolly brood with round edges qnd therefore
C* is 1.6..
Table 3.3 C... for different weir profiles
The weir equotion is olso useful in colculoting the flood
levels ot the intake ifthe flood dischorge is known or cqn be
calculotedbosed on the river hydrology. Once the flood levels
ore known, the flood protection wolls ot the riverbonk con be
designed. For hrown dischorge over the weir, the heod over the
weir (ond hence the woter level ot the intoke) con be colculqted
by rewriting the weir equotion os follows:
. lQ f " '! : I - - l"ovef,op
\ c* x L*",, I
Colculotion of heqd over o weir con be seen in Exomple 3.2
3-Z Bottom intokes
3.7.I DESCRIPTION
The bottom intoke, qlso known os o Tlroleon or trcnch intoke, is
o grille-like opening thot coptures woter from the b€d ofthe
river ond drops it directly into the heqdroce. The flow generolly
posses through on opening in o wing woll of the intqke
structure ond owoy from the river. in some coses the grille moy
cover o smsll chomber, but generolly the bottom intqke is
designed os o trench, perpendiculor to the direction of the river
flow.
The bottom intqke is most oppropriote in Iocotions where
there is no opprecioble sediment movement olong the riverbed,
becouse it withdrows bottom woter in preference to surfoce
woter. This type of intoke wos first used for smoll hydro ond
irrigotion systems eorly this century in olpine oreos ofEurope.
Ptofile of crest of welr cw
nlnA
_rh
broad; sharp edges
broad; round edges
round ovedall
sharp-edged
rounded
rool-shaped
1 . 5
1 .6
2.1
1 .9
2.2
2.3
A brood crested weir hos been ploced ocross o river for a
micro-hydro intqke os shown in Figure 3.12. The weir
height is 0.5 m snd the length 5 m. How high should the-flood protection woll be for o 20 yeor return flood of 11
*,/j?_ ,C* = 1.6 for bmod crested weir
Flood level
Figure 3.12 Brood crested weir
h -/ a J*'"ovenop \ c. x Lr.o ,
Note thot C* is 1.6 for brood crested rveir
t 7l \0'657h"""n"o =(--i;Fl = 1.24 m
Height offlood protection wolls from river bed level = 0.5
m + ho",noo * 0.3 m (ollow 300 mm of freebootd) = 2.Oa
31
Worldwide proctice shows thot it is 0pplicoble in smollrivers in
mountoinous ond hil ly regrons, where the followrng conditjons
exlst:. steep river bed ofbore rock or boulders whjch ror€ly
move (they or€ suitoble for f low velocil ies €xce€ding 3
m/s);
. Minimol bed lood ofsond qnd grovel:
. surplus Ilow ovoiloble for continuol flushing To dote
oniy o few bottom intokes hov€ been constructed in
Nepol, s0 Nepqlese formers ore not lom ior with them.
The d€sign ofbottom rntokes must be done corefully to
ovoid becoming blocked with sediment. Bottom intokes
for Thome ond Jhong micro-hydro scheme ore shown ill
Photogroph 3.9 ond 3.10.
3.7.2 TRASHRACKS FOR BOTTOM INTME
Srmilor to side intokes. the troshrocks of bottom intokes con be
monufqctured from flot st€el, ongles, tees or round bors welded
together ot intervols. The sectlon chosen must be strong
enough to withstond impoct by ony bed lo0d moving dunng
floods. lrs shope is olso very imponont, stnce this qff€cts the
chonces ofclogging. Round bors, for exqmple, ore more Prone
to clogging, b€couse the opening in the middle ts smqller thon
on the top. From the point ofview ofclogging, th€ secti0ns
listed below ore orronged in the order ofbest to worstl
Tees
Angles
Chonnels
Flots
Round bors
The recommended cleor spocrng between these flots,
ongles or bors is 6 to 15 mm ond o commonly used sPocilg is
12 mm. The rcoson why these bors ore closer thon those ofthe
side irltoke troshrock is thqr grovel olso needs t0 be exc]uded
from the bottom intake. Since the init iol heodr0ce for this type
ofintoke is covered, it would b€ dimcult to r€move ony grovel
thot obstructs the flow. It should therefor€ be excluded The
spqcing ofthe flots or qngles dep€nds on the prtdominont
porticle siz€ ofthe sedlm€nts coffied by the river flow (i.e. bed
lood) ond the provision for o settling bosin ln the conol
syst€m. The lorger the spocing (oPening), the lorger the
pofticl€s thot will enter the heodroce. on the oth€r hond, if
the Openilgs ore too norrcw, theP is o high chonc€ of
clogging necessitoting frequent cleoning ofth€ troshrock. It
is 0lso importont to ploce rhe troshrqcks such thot the bors
or€ olong the dircction offlow This mlrumises the risk of
clogging.
Phoro 310 Bottom intok€ wrth the gnu rPmoved (Jh0n9)
on€ ofthe drowbocks ofthe bottom intoke is the
clogging oftroshrock by pebbles ond dry leov€s. EsPeciolly
during the dry seoson, the river moy corry q lot ofl€oves,
which become tropped in the trqshrqck ond reduce the flow
through lt Therefor€ the troshrock needs to be cleoned
periodicolly during the dry seoson During morlsoon, this is
not o problem; the river Ilow sweeps the grqvel ond leoves
before th€y con clog rhe troshrocks.
3.73 DESIGN OF BOTTOM INTAJG
The foilowing equotion is used for the design ofo bottom
intok€:
cpbr.fih
where:
Q^ = design dischorge into the intoke in mr/s,
b = width ofthe bottom intoke in m.
L = l€ngth ofthe rroshrock in m. ln proctice, it is recom-
mend€d thqt the troshrock length (L) be incEosed by 20%, i.e.,
L=1.2xL.".,r,,.d. Thiswil l ensur€ thot there wil l be odequc te
flow when the troshrock is portiqlly block€d by wedg€d
stones ond brcnches.
2
w
Photo I9 Botronr intoke ofThome mkro hydro schem€, N€pol
Bottom intok€ with the griu rPmoved (Jhong)
32
.>L -
" , k
1 "Tqble 3.4 1 vclues for p
ho = Initiol woter depth in m in the river upstreom of the
intqke.
h, = ho * vo'/29. Note thqt os con be seen in Figure 3.13 h, is
cctuolly the initiol woter depth in the river plus the velocity
heod ofthe river (v"'/2g). For steep rivers, the flow velocity
should be meosured since the velocity heod con be high.
X, = 0 function ofthe inclinotion ofthe troshrqck (p) cs shown
in Tqble 3.4.
c = Conection foctor for submerced overfqll.
0 = cleqr spocing of the troshrock bors in m.
d = centre t0 centre distonce between the troshrock bors in m,p = ongle ofinclinotion ofthe troshrock with respect t0 the
horizontol in degrees.
p = c0ntroctiOn coefficient for the trqshrock, which depends on
theshope ofthe bors os shown in Figure 3.12. Also in the figure,
Q is the river flow upstreom of the intoke ond Q. is the excess
flow in the river downstreom of the intoke.
Note thot to solve the bottom intoke equotion, either thelength or the width ofthe intoke opening needs to be set qnd
the other dimension con then be cqlculoted. The selection of
one ofthese dimensions depends on the site conditions. For
exomple, if the length of the trashrock is too smqll, the
heodroce ccnol will require deeper excovqtion in the riverbed,
which moy be difhcult. Generolly, the length of the bottom
intqke should be equol to the width of the heodroce canol, ond
the width should motch the river chonnel.
It is importont thot the culvert beneoth the trosh rock is
steep enough t0 convey the moximum conceivoble sediment
lood to the grovel trop: o grodient ofot leqst 1:20 is recom-
mended. The grovel trop moy require continuous flushing,
which meons thot sufhcient heod ond surplus flow hos to be
ovoiloble. The design must be oble to corry ond spili bock to
0o
20
40
6o
8o
100
720
1.000
0.980
0.961
0.944
0.927
0.910
0.894
140
160
180
200
220
240
260
0.879
0.865
0.851
0.837
0.825
0.812
0.800
= 0.6 , cosrj20
l l l o.zs-o es
\ t ???loso_oeofooz-
ooa t
J o 6s gqg o ?o-o esconlrrctlon corf f lcirnt g
fin'IIITTTITI
Figun 3.13 Symbols used in the bottom intoke equ0tions
the river the moximum flow entering the intoke r.rnder flood
conditions.
Enoineers desioninrt o botton intoke should refer t0
References 3 ond 5 for further informotion.
A suitoble site hos been locoted for o bottom intoke. The river width ot this oreo is 5 m ond the depth is 0.5 m (i.e. h. :
0.5 m). A velocity of 3 m/s wos neosured ot the intoke site. The design flow (Q^) required for power generotion is 0.40 mr/s.
Select on qppropriote size for the bottom intoke.
Design cqlculotions
Choose 20 rnm diometer round bors for th€ troshrock.
p = 0.85 for round bors (from Figure 3.i2) Set the cleor spacing between the bors,
o = 1 2 r n m
Centre t0 centre distonce between bors,
d: 32 mnt
Set the inclination ofthe trcrshrack 0 : 8" (The inclination ofthe troshrock should be equol to or slightly greoter thon ther i r t o r n r n A i o n l \
For p = 8u,X =0.927
2h -_ .y .h
3 ' " t '
h, = 0.5 + 3'z129 = 0.96 n'-
20rh -- x0.927 x0.96 : 0.59 m
3
oc : 0.6 ;* cos'tf)
0
I 0.012 \c = 0 . 6 x 1 _ l x c o s ' j ( 8 ' 1 : 9 . 2 2
\ 0.032 I
Now use lhe bot tonr in toke equot ion:
2n - - - , , k r E - , -Y a -
3 L f t u L \ l g n
2Q. : ^ x0.22x0.85xb*L . ,E igS*OSS\ 4 3
Q ^ = 0 . 4 2 x b x LWith QA = 0.40 Inr/s:
0.40b x l = 0 . 9 5 m r
0.42
0,95^ F I - -u t L *
rD
Select the width ofthe troshrock, b = 2 m L = 0.9512 = 0.48 m.
Increose the length by 200/o: L= 0.48 x 7.2 = 0.57 m. The
proposed dimensions of the bottom intoke ore os follows:
Width of the opening, b = 2.0 m (0t right ongles to the flow)
Length of the opening, L = 0.6 m (porollel to the river f low)
Troshrock bor size = 20 mm diameter round bors
Bor sPocing = 32 mm centre tO Centle
The plon of this proposed bottom intake is shown in Figure 3.14.
ffi ----1 rBot f c rn i n t r ke-
u Do rs qf p iTtri c,'c
Figure 3.14 Dtnreusions for th0 bol torn intoke of t ix t rmple 3.3
t /
Note thot in this exqmple the width ofthe troshrock is less
thon the river wrdth, which is occeptoble becouse only 50lo 0fthe
river flow is required. Where most of the flow is to be diverted,
the troshrqck width should be €quql to th€ mv€r width.
3.8 River troining works
A flood protection woll olong the riverbonk moy be required if
there is c high probobrhry offlood domoge to the inrliol heqdroc€
ond 0ther structures such os th€ grovel trop ond settling bosin.
Such wqlls ore qlso cqll€d river lroining structurcs since they
confin€ the river chonnel. The woll height should be gr€oter
th0n0rot leost equol lo the design flood level.
The foundotion ofony ver troining wolls must be
protected from undermining by the river. This con be done by
one ofthe foilowing methods.
(o) Founding the wqll on rock or lorge boulders. For gobi0l
wolls it mqy be necessqry to first build up o level bose
using stone mosonry or moss concrete.
ft) Founding the woll below possrble scour depth.
(c) Using o gobion mottress olong the dver side ofthe woll.
This method is not opprcp ote in dv€rs corrying o he0vy
bed lood, becouse the gobion wires will be domoged by
boulders moving during floods.
0n olluviol dvers (i.e. deep deposition ofsond ond cobbles),
gobion flood protection wolls ore usuolly more oppropriote for
micm-hydro sch€me. This is becouse the grould ofolluviol fivers
tends to chonge ond fl€xible structures con cope better in such
conditions Gobion wolls moy require onnuol mqintenonce
(especiolly ofter monsoon) therefore skilled mcnpower should
either be qvoiloble ql site 0r some locol peopl€ should be troined
du ng the consrruction phose.
Gobion wolls con olso seNe the function ofretoining wolls
ond stobilise the slopes behiDd it. Ifslopes ot lhe olluviol
riv€rbonk ore unstobl€, th€n gobion wolls con olso be designed
os ntoining wolls. Photogroph 3.11 shows the use ofo gobion
woll to stobilise the bonk slope. Refer to Section 9.4 for rctoining
woll design.
on stqble riverbonks, such os exposed bedrock, o mosonry
woll cqn be built provided thot rhe river do€s not corry lorge
boulders thot could domoge mosonry structurcs. In lorge
hydopower ond irrigotion projects even concrete flood boder
w0lls ore used but usuolly such solurions ore economicolly
unjustifi obl€ for micro-hydro schemes.
Figure 3.15 shows the use ofo gobion woll to prevent the
riverbypossing the diversion weir ond domoging the heqdroce
pipe during floods.
Photo 3.11 Gobion wqlls ot $e heqdworks ofthe 30kwJhorkor micro-hydroscheme, Mustong, Nepol
3.9 Checldist for diversion works
Refer to Toble 3.1 qnd find out whqt cotegory the
source river folls in.
Refer to Tqble 3.2 ond decide on whether o side intoke
or o bottom intoke is suitoble.
Is o weir r€quired or is it possible to divert the dver
wot€r without one? Remember the concept of"minimol disturbqnce to the nqturol stote ofthe
wot€r".
Does the river course opp€or stoble or does it look like
it will meonder? Think 0bout flood ond flood lev€ls.
Also, ifthe river cqrries Iorge boulders during the
floods, qnd o weir is requiEd, think obout temporqry
diversion works rother thon o permonent weir
To minimise flood dqmqge the intoke locotion should
be such thot it is possible to set the heodroce olign-
ment immediotely owoy from the ver course.
Ifo side intoke hos been selected qlong o river bend,
Iemember to locote it on the outside ofthe bend.
Hove the flood levels ond history ofthe river course
been discussed with the locol community members?
Firlolly, consider th€ cost ofdifferent options. Is it more
economic to construct temporory diversion works qnd
incur some onnuql lobour chorges or to choose more
permonent diversion works?
35
- Efiq. . t ]l Ii , l
Weir
lntoke
GobionFro
@ 4oOnrn closs II
Figure3. lS Heodworksorrongement0f the80kWBhujungMHP,underconstruct ioninLomjung,Nepol . Not icethef loodpmtect iongobionwol lsondr ipropot
downstrcom foce of the weir.
36
4. Hecdrace
4.1 Overview
The heqdroce ofo micro'hydropower scheme is o conol or opip€ th0t conveys woter from the inloke to th€ foreboy. The
heodroce olignment is usuolly on even to gendy sloping ground
ord the flow is coused by grovity. A h€0droce pipe is generolly
not subjected to significont hydr0uhc pressurc.
Since c0nols ore generqlly less expensiv€ th0n pipes, they
on used more often for heodroces in micro-hydro schemes. The
generol rule is to use conols os ofterl os possible ond ro use pip€s
ordy for the dimcult stntch ofth€ heodroce olignment, such os
t0 n€go(i0te cliffs or unst0ble oreos.
Micro.hydro heodroce conols qre similor to fqrmer
m0n0ged smoll irrigotion conols in thof they ore designed to
keep s€ep0ge, friction ond erosion to q minimum. Howev€r,
thett 0r€ olso some bosic differrnces os follows:
. lnigotion conols ore used only 3-6 months in o yeor
whereos micro-hydro schemes rcquire woter throughout
the yeor
. In inigotion conols, some voriotion in flows does not
crcote problems, ond temporory repqirs (e.9. plocing of
bronches ond leqves ot o leoking section ofo conol) con
be mode, The heodroce conol in o micro'hydro scheme
needs to be mol€ relioble.
r The loss ofheod ov€r th€ l€ngth ofthe heqdroce should
b€ minjmised so thot power output cqn be optimised.
Some micro-hydro texts use lhe term power c0n0U
conduit for €ither the length belween rhe intoke ond the
sdtling bosin (when thrs structure is seporote from the foreboy)
0rfor the €ntire heodroce. ln this rext the term heodroce is used
in ollcoses.
The velocity in th€ iniriol heodroc€ l€ngrh r€eds to be
high enough to corry grovel ond sedimert up to the grovel rrop
ord settling bosin respectively. where thel€ is o s€porote
seftling bosin ond for€boy, the velocity in the heodroce between
these structures con be lowered since it will corry sediment free
Ilow.
Photo: 4 1 Eorth Chonnel(Dhoding)
4.2 Conol types
Heodroce cqnols con be clossified occording to the moteriols
used to construct them. Vorious types ofheadroce conol used
in micro-hydro schemes ore os follows:
4.2.1 EARTH CANAIS
Th€s€ ore constructed by simply excovoting the grcund to the
required shope. Such conols ore used on stoble ond gently
sloping ground. seepoge con be high in such conols depending
on soil rype If therc ore signs ofinstqbiliry in o heodrace
section, or ifseepoge from the conol is Iikely to contribute ro
slope instqbilily such os londslides, this type ofcqnol should not
b€ s€l€cted. However, for heodroce olignm€nts on stoble ground
where seepage is not likely to couse instobiliry eorth conols ore
the most economic option.
Where cloy is locolly ovoiloble it could be considered qs q
lining to reduce seepoge from eonh conols. How€ver, o scheme
in Syongjo successfully used o cloy Iiring protected by sronepitching for the peoking reservoir (which wos fenced off) but in
th€ heodrqce cqnol the Iining wos destrcyed by cottle.
4.2.2 STONE MASONRY IN MUD MORTAR CANAIS
Ifon eorth c0nol does not oppeor to be feqsible, the s€cond
option to be considered should be stone mosonry in mud monor
type. Compored to 0n €onh conol, there will be less seepoge
from this type ofconal. For similor llows, the cross s€ction of
this type ofconol c0n be smoller thon the eqrth con0l becouse q
higher velocity is occ€ptobl€ (without cousing erosion) os will
3?
be discussed lqter An exomple ofo stone mosonry conol in
mud monor con be seen in PhotooroDh 4.2.
4.2.3 STONE MASONRY IN CEMENI MORTAR CANAIS
In terms ofcost, this is usuolly the leost preferobl€ option for o
heodroce conol. Th€ odvontqge with this type ofconol is thot
seepoge is minimol (i-e. significontly l€ss th0n stone mosonry in
mud mortor conols). A stone m0sonry in cement mortor conol
should be used ot locqtions where the soil type is porous
(leoding to losses ofunocceptoble omounts offlow) ond/or
s€epoge is likely to trigg€r londslides. For micro'hydr0 sites
locoted 3-4 dqys wolk from the roodhe0d, the need for o long
cement mortor conol con mok€ o micro-hvdro scheme uneco-
nomic due to the high cost ofcement.
An exomple of o sron€ mosonry in cement mortor
heodroce conol con be seen b€low ilr Photo0roDh 4.3.
Photo 4-4 Reinforced concrpte cover dobs provide protection from folling debds(Eol iv io)
4.2.5 OTHER TYPES OF CANAI
ln certoin or€0s there moy olso be other typ€s ofconol thon
thos€ mentioned qbove. For exomple, on irrig0tion c0nol in
Ecuodor construct€d ofused oil drums cut into two semi-
circulor holves con be seen in Photogroph 4.5. Such o conol moy
be useful for short ond diflicult sections or for oqueducts where
used drums ore €0sily ovailoble ond economicol.
Another exomple is the use oftimber conol os con be
seen in Photogroph 4.6. This requir€s the use ofhordwood ond
skill€d lobour Similor to oil drums, timber cqnols con bepossible for shon crossings ond oqueducts or where timber is
obundont ond inexpensive.
Exompies ofother types ofconol or€ pEsented in Boxes
4.1 to 4.5.
4.2.4 CONCRETE
CANAI.s
Most micro-hydro
schemes do not hove
heodroce conols
construct€d of
concPte since they
orc very exPenslve.
Th€re is virtuolly no
seepoge through
such conols. some-
times, rcinforced
concrete conols ore
used for short
crossings. Generolly,
HDPE heodroc€ prp€s
ore more economlc
thon concrcte conols.
Photo 4 3 Stone mosonry in cement mortorheodroce conol ofthe 50kw colkot MHBColkot, Boglung, Nepol
Photo 4 2 A rorsed mosonry chonnel supplying o mill (Mustong)
38
Photo 4 5 An oil drum rrrigotion conol, Ecuodor Photo 4 6 Timber conol with brocing supporting the sides, Thuptenchuling
39
Ferrocement pilot projects hove been promoted by the
Andhi Kholo Idgotion Pmject (A(IP) ond the Internotionol
Lobou Orgonisotion (lLO). Fefiocemetrt structures ore
mode of thin cement sond mortor (1:2 to 1:3)with thin
steel mesh os reinforcement. ILO hos used ferrocement for
Iining frigotion conols in th€ SindhuD nood Rehobilitotion
Proj€ct.
Th€ ILO ferrocement conol cost wos US$ 31 per lineor
meEe ond the cement mosonry desigl of similor copocity
wos US$ 28 (1989 prices). The tlo justifies the odditionol
cost by ottributing it to befter durobility snd little
mointenonce whidr fe[ocement conols requA€. other
odvontqges ore smooth finishing which reduces heod
losses, resistonce to obrosion, ond very low seepoge
Iosses.
The f€rrocement flum€ used in AKIP (designed by BPc
Hyftoconsult)is shown in Photogroph4.6 ond Figure 4.l.
colvonised sh€ets with intermediote steel fromes werc
used for the formwork. Multiple loyen of 10 mm to 15
mm thick, 1:3 cement sond mortor were ploced onthe
formw0rk. The Enol inside loyer (i.e. woter retoidng
surfoce) wos prepored using o mix of 1:2 cement sond
mortor. Golvonised thin wiE mesh (olso }amwn os chicken
wire mesh)wos ploced between ecchloyer os
reinforc€m€nt.
The Andhi Kholo ferrocem€nt flume hos been functioning
w€U since its commissioning in 1993. This design wos
more economicol thqn the conventionql stone mosonry in
cement mortor co[ol with drop structufts. However, it
should be not€d thot the construction off€nocement
conols requir€s skilled ond well troined monpower
(mqsons) to ochi€ve the requir€d quolity of work ond
therefore moy only bejustified where o very long ccrol is
to be instolled in poor soils. Furthermore, ifskilled lobour
is expensive, ferrocement conols moy cost more thon th€
conventionol design, osinth€ cose ofSindhuli Flood
R€hobilitqtion Proiect.
Fioure 4l Andhi Kholo Proiect fermcem€nt llume
I:2 CEMETTT SATO, MORTAR
Y ' 3 . 5 X 2
40
ln the Andhi Kholo ldgotior Project (AKIP) designed by BPC Hydroconsult, soil-cement wos tested os on option for ir gotion
conols. Th€ soifcement wos pr€pqred using o mix ofone pon cemelt ond one port sqnd to ten ports oflocol red coloured
cloyey silt soil. The red colour of the soil indicotes o high iron content, which r€octs with cement to form o hord loyer on the
excovoted surfoce ofthe conol.
1^,/o opplicotions of soil-cement werc tested in 1990 ond 1991. The first test used sorl which wos grqded using o 4-mm
sleve, with l0rg€r lumps ond soil broken up with o tomper After mixing the dry ingredients ofcement, sond ond soil, woter
wos odded ond rnixed thoroughly until the mortor reoched the desired consistencyforplostering. The excovoted surfoce ofth€
corol which contoined permeoble soil ond grovelwqs first modemoistby sprinkling woter ondthen the mix wos opplied
firrr y to o thicleess of
40 mm qnd pocked
tightly to eliminot€ oir
pockets. The surfoce wos
trowelled smooth qnd
therl cured for q week.
In 1991, o 15 mm
si€ve wos used to grode
the soil over o test
section of 140 mu Loter
moredemonding
conditions were used for
o furth€r test over o
section of25 m length, o
grcdient of 1:20 qnd q
velocity ofopprox. 1.3
m/s. A section of the
Andhi Kholo soil cement
conol ccn be s€en in
Photogrqph 4.10.
To dqte, the
performonce ofthe soil-cem€nt linilg ot Andhi Kholo hos been good. The 1990 test section developed some crocks ofter o
week. oppor€ntlydueto on excess ofwqterin the mix, whichthen coused crqcking qs the soil-cement dried up ondhordened.
These crocks hove not worsened. The 1991 section hos not shown oly crocking. The lining inst0lled irl th€ st€ep conol section
hos olso been performing well.
Th€ odvontqge ofthis technique is thqt it is low cost. Befween 20yo ond 40% ofthe cement requted for o conventionol
concrete mix is reploced by soil. The procedures qre eosy to leorn oIId ore similor to those used for troditionol houses con-
structed in the Andhi Kholo oreo. How€v€r, one pr€pquisite for this typ€ ofcorol is the ne€d for high iron content ir the soil
usedto pr€pore the mix.other soils will not perform well. Arother conclusion thqt hqsbeen drown fiom th€ Andhi Kholc
expeience is thot soil-cement conols ore not oppropriote for turbulent flows. Th€y ore suitobl€ where seepoge controlis
required ond the grodient is gentle {velocity limited to -1.0 m/s.)
Photo 410 Soil c€m€nr lined conol s€ction ot AndhiKholo, Nepol
42
The method developed by IT Peru ond d€scribed here is generolly known os th€ 'formers m€thod' for constructing conols,
The formers method p€rmits sovings in time ond moteriql in constructing concrete chonnels by reducing the need forpouring concEte into conventionol formwork. Precis€ plocement of formem ond lines tied betwe€n them enoble the
concrpt€ to be ploster€d to the insides ofthe trench ond lirished with o trcw€l {se€ Figup 4.4).
Th€ method involves plocing o loyer ofconcret€ on the bottom ond sides ofthe conol to form o uniform thickness ond
o smooth finish. L€v€llirg ond finishing th€ surfoce is done occording to th€ former.
Procedutt
. Setting out for the forme$.
Locqte pegs €very 10 metrcs ul
stroight sections ond every 5
metPs in curv€d secttons, toking
into occount the slope ofthe
d€sign. It is preferoble to use o
builder's level to ochieve the
Iequircd precision.
. Fixing the formers. Locote formeE on eoch peg ot right ongles to the centreline ofth€ conol, verticol ond exoctly in line.
They or€ fixed to th€ pegs using No. 16 goug€ wil€ ond noils, ofter which intermedidte formers oI€ locot€d every 2.5
metr€s in stroight sections, the requir€d slope b€ing checked with d pipe lev€l to give 5 mm drop ev€ry 2.50 metres (o slope
of 2 ir 1000). Eoch former is checked for lin€, Ievel, thot it is p€rp€ndiculor to the conol centreline ond fixed firmly.
. Lining the conal. PRpore o 1:1.5:3 concrete mix
After mokirg the dry mix, tuming the mix o minimum of thrc€ times to mix thoroughly, odd woter, which should
hqve o quontity no gRoter thon on€'holfof th€ totol weight ofth€ c€ment (i.e. for mix with 1 kg ofcement put % litre of
woter). Next the sides ofthe conol ore plosteRd ond compocted. The pegs ore tok€n out ofter the linish is completed.
TheB Iine sond is sprinlded with cem€nt to give o mix of 1:3 ond o plosterirg bo0rd is used to give o smooth, impermeoble
firish to the lining. When the sides ofthe conol ore completed the some procedup is followed for the bottom. To finish the
€dges, corc is r€quired to ensure thot the formers rcmoin in line, They should be checked using o cord or rule.
. L\trscting the foBn€rs. Form€rs sre tsk€n out oft€r 24 hours io cold climotes. To moke extroction eosy, o loyer of oil or
petro) is ploced 0n the formers before c0rrying out the Iining. This olso 0ssists with the pRservotion oftbe formers. CoIe
should be token to ovoid domoge to the €dges ofthe lining when the formers ole token out.
. Curing the concrefe. To r€och the required strength ond durobility, fresh concrete should be cured. This is ochieved by
filling rhe suffounds with woter so thot the linings remcin sooked for o p€riod ofo minimum of 10 doys. Thisiseosyto
c0rry out by locoting runs or eorth bonks ot eoch end, which retqin the woter. During r0iny periods 0 spjllwoy con be
formed to ollow excess wot€r to €scope, which will olso offer o check on the slope. The curing of concrete is very impor-
tont ond should not be overlooked.
. Exponsion joints. Exponsionjoints ore required i[ the spoces thot or€ left when the form€rs or€ tok€n out - €very 2.5
metrcs in sroight sectiOns orld vorioble in curved sections. Thes€ permit the concrete to expond ond controct without
crocking the linings. To fill th€joints the following work is required:
o) Cleon thejoints ofdebris ond unwonted moteriols with on ongulor polette whose dimensions ore suitobie for the
width ofthejoint.
b) Prime th€ iBside surfoce 0f th€ joint with o solution of tor with kerosene ln propc ions l:3 so thot it hos the
viscosity ofpoint. This solution should be opplied with o brush.
c) Ploce o hot mix oftor with line sond, in proportions ofl con oftor to 4 cons ofsond. First heot the tor ond then
groduolly odd the sond while mixing until it hos rhe consist€ncy ofblock sugor This mixture is pldc€d first ot th€
sloping sides ofthe chonnei ond then ot the bottom. lt is plqced in loyers ond compoct€d with th€ angulor pol€tte.
The finished level ofth€joint should not exceed the level ofthe conol liring.
Figure 4.4 Formers method oflining conols
{I .{ l il t j
iIl i ,; ti,r i f r' {'t
i l il i
4.3 Conoldesign
{.3.1 DESIGN CRITERJA
The following criterio ore used for the design ofheodroce
ccnolsi
Cspocity
The heodroce c0Dol should be oble to corry the design flow with
odequote freebocrd. Fr<ebood is th€ dillsrerce in elevotion
between the conol botlk t0p ond tir€ d€sigr wcter l€vel.
During monsoon, the river woter levelis high ond
therefore l lows higher thon the design l low con enter the
intoke. Spillw0ys and €scopes cr€ required to dischorge the
excess flows. Similorly if fqll ing debris or other obstructions
block the conol, the entire flow needs to be soleLy dischorged
into o neorby gully or stl loIn before it induces funher jnstobjl
ity problems.
Velocity
The velocity shou)d be Iow enough to elsure th0t ths bed ond
the wqlls 0fthe conoiore not eroded. The rec0mmended
moxlmum velocity f0r different types of conol is shown in Tcbie
4.1. Ifthe velocity is too low 0quotic plonts ond moss wil l stort
i0 grow on the conol ond reduce the cross sectiono) 0reo. A
mininum velocity 0f0.4 m/s should be mointqined to prevent
the growlh ofoquotic plonts. Also, the veiocity in the heqdroce
coaol up to the settl ing bosin needs to be high enough to
pr€v€nt sedirnent depgsition.
Eeodloss ond seepsge
As meotioned eorlier he0dloss ond seepoge need to b€ mini
mised. Heodloss is governed by the conal slope. Seepoge cor be
controlled by choosing the construction nloteriois (eorth, mud
or cement monor conols etc.) oppr0priole for rhe ground
conditions.
Side slopes
Theoreticolly, the optimum cross sectionol shope for o conol is o
semi-circle, since it ccn convey the moximurn flow for o given
tross sectronol oreo. Since lt rs dlmcult (o (onstruct o 5€nli.
circulor conol. in proctice, o tropezoidol sh0pe (which is close to
o semi-circ)e)is used. F0r mosonry conqls in cement moftor or
ploil concere concls thot qre continuous, Iertongulor shopes
(i.€., verticol wolls) ore rccommended unless the bockfill con be
well compocted or excovoting the required tropezoidol'shope is
possible. This is becouse tropezoidol cement mosonry ond pioin
concrete conqls'sid€ wolls wil l hove to depend on the bockfl l l
for support. The wolls moy crock 0t lhe conoi b€d level
(cousing seepoge) since it moy be difncuh to conpoct th€ .
F L r r r . l s l d J J r | " u l ) , o c h r r l i . r o r f l g ) d l . L l p T . r d u l o n o l s
bockfi l lproperly behind the wqlls, os showr in Figur€ 4.5.
Recommended side slopes for different conol types 0re shown
in Toble 4.2.
Stobility
Not only should the conol be on stoble ground but the or€os
obove 0nd bel0w the olignment 0lso !eed to b€ stoble. when
det€rmininq theconcl route ot site, the signs ofstobjl ity ond
instoirility discussed in Chqpt€r 2 should be referred to.
The conol design should qddress stobility issues such
os prot€ction ogoinst rocl'folls, londslides ond storm runoff.
covering conols by plocing concr€t€ slobs (or flot ston€s) ond
some soil cover (to obsorb the impoct offolling rocks) con b€
on oppropriote solution ifo smoll length ofthe conol is
vulneroble to rocHolls. Exomples of concrcte slobs con be
seen in the superpossoq€ drowings ofthe colkot sch€me in
Appendix C.
Economics
similor to ony orher engin€edng strucrure, the design ofth€
conol should be such thot th€ cost is minimised. This is
especi0lly importont in the cose of o long heodroce conol
sinc€ optimising the design wil l result in substontiol soving
in the totol project cost. Design optimisotion or minimisirtg
costs requires k€eping lhe conol olignmelt qs short ospossible lunless longer lengths ore needed to ovoid unstqble
oreos ond crossings)os w€ll ds minimising excovotion ond
the use 0fcorstruction moteriols, €speciolly cement ond
stones. FOr exomple, in 0 mjcro-hydro schem€, cement
masonry canol could be used only ot sections where the sojl
is porous ond/'or s€epoge is likely to trigger landslides. ln the
sqme scheme, eorth ond stone mosonry in mud monor
conols could be used ot sections wh€re probl€ms qssociot€d
with seepoge oI€ not expected.
43.2 MANNING'SEQUAIION
The design ol 0 heodroce conol is bosed on Monning's
equqtion. Monning's €quotions for flow ond velocity ore os
follows:
' . 1
l ;
l ,
AR4'VS
wher€:
Q is the flow in th€ conol in mr/s
V is velocity in the conol in m/s
is the roughness coeflicient ofthe conol (olso colled
Monning's n)which is d€pendent 0n the moteriols ofthe
cqnol. The vqlue ofn for differ€nt typ€s ofconol is given
in Toble 4.1.
is the cross sectionol oreo up to the woter surfoce l€vel
in m'?.
is the slope ofthe energy grode line. The invert slope of
the conol is used for s since it is porqllel to the energy
grod€ lin€ 0t loog€r lergths. For exomple i:500 (1 in 500)
irv€rt slope is I m ofdrop in l€vel in 500 m ofhorizontol
conol length.
Sometimes percentqge (0/o) or froctions orc olso used to
denote the slopes. For exomple o slop€ of 10lo meons thot th€r€
will be o difference in lev€l of I m every 100 m of horizontol
distonce.
The equivolents ofthe slop€ in froctions or decimols ore
given by the following exomples;
2 % = 2 l 1 O O = 0 . 0 2 = 1 i n 5 0
2 in 1000 = 2/1000 = 0.002 = 1in 500
1.50 ,6 = 1 .5 /100 = 0 .015:1 in67
3.5 in 1000 = 3.5/1000 = 0.0035 = 1 in 286
is the hydroulic rodius. R = A/P
is the w€tted p€rim€ter in m. This is the totol length 0f
the bottom ond th€ two sides ofth€ conql up to the
woter surfoc€ level.
n
R P l FI1
R
P
{3J SEDIMENT DEPOSMON IN CAI{AIS
The velocity in eoch s€ction ofthe heodroc€ conol should be
high enough to trcnsport ony sediment entering thot section.
Betwe€n the intoke ond the grovel trop o velociry of 1.5 - 2.0 m/s
is recommended. Between the grovel trop ond the settlipg
bosirl o lesser velocity is possible, but the sediment tronsport
copobility should be checked usirg o simplified version of
Shield's formulo: d= 1lRs
where:
d is the size ofporticle tronsported in o conol, in m
R is the hydroulic rodius, in mc i c r h , . n h ^ l h d < l ^ n ,
Ifthe grovel trop is designed to settle porticles lorger
thon 2 mm, then th€ conol downstftom ofthe grovel trop must
b€ oble to tronsport pofticles up to 2 mm.
Tqble 4.1 Roughness co€mci€nt qnd o-llowqble mqximum velocity
See note below for advice an chanftels where the water dcDth is less tha7 one metrc.CHANNELTYPE DESCRJPTION MA)C
vELOcITY (mlslEorth chonnel Clay, lvith stoles ond scnd. ofier ogeing
Grovelly or scndy looms, mqintoined with mtnimum vegetotion
lired wjth coors€ st0nes, mointolned with rninlmun vegetotj0n
For cqnols less thon 1 metr€ deep, use the equotion in N0te '1.1 for n e.g.:Vegetated (us€ful to stobil ise soil); woter depth 0.7 nl
rvoter depth 0.3 m
Heoviiy ov€rgrown, woter depth 0.1 metrcs
0.020
0.030
0.040
0.050
0.070
0.150
0.8
0.4
1 . 0
0.8
0 .8
1 . 0Rock cut 0.015
0.045
0.060
Smooth ond uniform
Jogged ond irregulor
Very jogg€d ond ifngulqr
1 .5
1 .5
1 . 5Mosonry qnd
concreteStone mosonry in mud morto( dry st0ne mosoory
Stone mosonry in cement mortor using rounded ston€s
1:4 cement scnd mortor
1:3 cement sond mortqr
Stone mosonry in cement rnort0r using split stones (drcssed)
1:4 cement scnd mortor
1:3 cem€nt sond mortor
wlth l:2 pointirlg
Concrete (occording to finish)
1:3:6 ploin concrete
1i2:4 ploin concrete
1:1.5:l reinforc€d concrete
1:l :2 reinforced concrcie
Cement pl.rster
0.015
0.030
0.020
1.0
l . l
2.0
3.0
5.0
1 . 5
2.0
1 .0
5 .0
3 .0
5 .0
0.013 - 0.017
0.013
1 : l
1:2wooden conols Ploned, well jointed boords
I l n h l n n p a h ^ ^ r / (
Older wooden conols
0 .011
0.012
0.015
3.0
3 .0
1.0M€tol conols Ail types
Mountoin str€oms DominoDt bed moteriol :
Crovel (up to 60 mm)
Cobbl€s {up to 200 mnr)
Boulders (up to 600 mm)
Lorge boulders (> 600 mm)
Note 4.I Roug,ilrl€ss efi:ct [or shoi]ow channels
Resecrch ot Wogeningen University in th€ Netherl0nds demonstroted thot the roughness is increqsed for chonnels under 1 metrc in
depth, becouse oi rhe turbulence creoted by the side ond b€d suifcces. The rcsecrch showed thot the follorving equotions con be
used to hnd rhe roug\ness coriirii.,r. i.\i\\,i dt!'.f. cl\cler
0.020
0.03
0.04
0.05
0.07
3.0
n - o . o 3 i \ E H < 1 mn = 0 . 0 { / \ F H < 1 n rn = 0 . 0 8 / { F H < l m
well tnointoinrd channels u'ith l i tt le veget{rtio!:
Chonnels with siron vegetotlorl:
Heovily overgrolvn chonnels:
Ii,l,
In proctice it is sensitrle t0 l l lointoin short veg€totion ir o er t0 protect the bonks of conols.
Toble 4.2 Re(omm€nded sidc slopes for heodroce conolsCANAL MATERIAI stDE sLoPE (N = h/vlR0ck/conglomerqre (hord t0 loose)
Iirm cloy
Loom
Sondy cloy, scndy locnr
Silty sond, sondy eofth
loose sordy €orth. porous eorth
Grovely e0rth, sri lTor loose conglomercte
Grovelond boulder mixed wIh eonh (soft ond Ioose)
Stone mosonry in mud rnortor
Stone mosonry in cement mortdr
P lo in Ionr rP ie
Notesl
1. These volues orc for conols excovoted in s0il ofl0w nl0isture cortent with woter toble below conal bed. slopes need to beflottened ifthese condirions or€ not ochiev€d.
2. The sides ofl ined conols rtlcy b€ v€nicol (designed qs r€tcining wolls)or ot the slop€ reronmended for the uDderlying so)l
0 (verticol) to 0.5
0.25 rc 4.5
1 .0 to 1 .5
1 .5 to 2 .0
2.0 to 2.5
2.5 to l
0 .5 to l
1..5 ro 2
Sec Not€ 2
S€e Note 2
5(e Note 2
43.4 DESIGN PROCEDUR"E
the heodroce canoldesign procedul" is os follows:
L Decide on coDol type os per sile condrtious ie.g. eorth
corol, st0ne mosonry in mud monor or stone mosonry
rn cement mofior).
2. Choose o suitqble velocity (V) such lhot it is less thon the
mcxinurn velocity given in T0ble 4.1. N0te lh0t
unoccept0ble heodl0ss moy result ifchosen velocities ore
close to m0ximum velocity Also choose the correspond
ing roughness coell lcient (n) fron Tobie 4.1.
lhen colculote cross sectionolorpo (A) from theo
following equotion: A =f
Free boord
lel
Figurp 4.6 Symbols used rn conol sizing
3. Using Table 4.2 decide 0n the side slope (N). Note rhot N
is th€ ratio 0fth€ horizontol length divrded by th€
verticol height of tbe sjde woll (i.e. N = h/v os sholvn ir)
Figure 4.6).
Colculcte the optin]um conolheight (H). conol bed widrh
(B), ond th€ conol top widrh (T)using the iollowing
equotions:
x = 2 \ ' [ + N j 2 N
r - A, , V X + N
B = H X
T = B + ( 2 H N )
Note thot in cose of o rectongulor conol, N = 0 ond
X = 2 , s 0 :
i ^H = / , ! o n d T = t = 2 1 H
\ 2
I{ence, for o rectongulor conol the hydroulicolly
optimum shop€ is wh€n the width is twice the height.
These symbols ore schernoticolly shown Ln Figure 4 6
lfon optimunl cor)ol shope is not possible due to
site specil ic conditions (such os norrow width olong o
clif l) then either the width or th€ height should be
selected to 5uii the sit€ conditions. Then the other
dunension con be colculoted.
To ensure stoble ond uniform flow in o long conol, the
velocity must be less thcn 80% ofthe "crit icol velocity
l ^ "l imir" V, =J '=
, where V. rs lh€ crit iLclvel0ciry
thot for o rectongulor cqnol V. = fit
Ifthe conol vrlocity js greoter thon 0.8V then rcpeot
colculqtions with Low€r velocity.
6. Colculote the wetted p€rimeter (P)using rhe following
equotion:
P = B + 2H .', i1 1,11 , note thot for recrcngulor conol,
P = B + 2 H
7. Colculote the hydroulic rodius (R)os fo)lows;
8. The slope (S) cot now be found from Monning's equo-
tion:
/ n t \ 'S = I I
Now oll dimensions required f0r the c0nstruction ofthe
ranol ore knorvn.
9. Heodloss = L S (L is the length ofthe conol section).
Sometimes S is f ixed by th€ conolroute, which hos
oireody been decrded ond surv€yed. Another €xornpie of
fixed slop€ (S) situotion is when on existing inigoti0n
conol is proposed to be used for o miclo hydro scheme(ond higher flows 0s well 0s l€ss leokoge orc requir€d).
In such situotions different cr0ss sectio!l01 0reos should
be ossumed (i.e. triol qnd error) such that the v€locity is
less thon the ollowoble moximum velocjty for the
design flow ond ihe type 0fronol proposed. This con be
done by r€writ ing Molroing's equotior) os follows:
^ (BH + NHl" \!v - r - x l
n [(B + 2]r \ (r +N1 I
with o known design flow (Q), select the oppropdote
side slope (N) 0ccording to the typ€ ofconol chosen.
Then fix either B or H ond colculote the 0ther using the
dbove equotion. Finolly from Tobl€ 4.1, check thot thevelocity (V = Q/A) is l€ss thon lh€ moximum velocity for
the conol type.
10. Col(ulqte rhe size of the lorgest pq(icle rhor wil l betrqnspolted in th€ conol:
d = 1 1 R S
Ifthis is less thon the possible size in the conol, repeqtthe design using o higher veLocity.
11. AlLow o freeboord os follows:
300 mm for Q < 500 lis
400 mm for 500lls < Q < 1000 iis (such flows oreunusuol ior micro'hydro schemesJ.
Such freeboord ollows for:
. Unc€rtojDties in the design {e.9. the vo)ue of n'moy
diff€r by 5olo to t0% from estimote).
. Woter level being obove the design level due to
obstructlon rn the conol or durrng emergenr ies.. D€t€riorotion of th€ conol embonkment.
12. Check thqt possible flood flow in conolcon be occommo'
d0ted without using more thon 5070 ofthe freeboord.
13. Find the totol h€od loss. If this is too high or too smoll,
repeot the colculorion( with o dlferenr velocLty.
Consider using different typ€s ofconol keepiug the
overoll cost in mind.
Avoid o conol width ofless thon 300 mm os n0rrow
c0n0ls con b€ eosily blocked. Also fbr stone mqsonry conols,
smoller sizes ore diff icull Io construct.
Th€ existing irrigotion conol ot Colkot needs to be modilled qs o heodrace conol for o pow€r outpur of 50 kW The exist inginigotion conol's cornmond ol€o is 20 hectots. The community hos requ€sted thot the conol be sized such thot it would b€possible to ir g0te the fi€lds ond produc€ 50 kW simultoneously.
The following informotion wqs coll€cted through site inv€stigqtion ond d d€toiled survey:
Gross heod {h) = 22 m {forebgy to powerhouse)
lntoke to 130 m downstreom: 1:50 slope (s) with on€ drop srructur€.
131 m to 231 m downstreom: 1:92 slope.
232 m to 405 m downstreom: 1:365 sl0pe.
406 m to 730 m downstreom: l:975 slope with 3 crossings.
731 m to 1119 m dowostredm {for€boy)r 1:400 slop€ with on€ crossing.
48
site conditions dictote thot the entire heodroce olignment be constructed out ofstone mosonry in cement mortor_Note thot I m goP hos been provided ot chonge o[slopes. This is the tronsitionol length thot connects the rwo diflerertslopes.
ln this exomPle, the lequired design 0ow will be colculoted 0nd the heodroce conol from chojnoge 406 m to 730 m will b€slz€d.
D€sign fl ow colculotions:
Assume 550/0 overoll €mciercy (e" = 0.55)P = Q g h€, (power equotion)
Q = P / ( s h e " )= s0l{9.8 x 22 x 0.55) = 0.421 mr/s
Therefore flow required for pow€r gen€rotion is 421 l/sAssum€ on ir gotion rcquirement of1.5 i/s/ho for existing i lr ig0t€d lond.kdgotion d€mond (Q) = 1.5l/s/ho x 20 hq
= 30 l is
Tot0i d€sign flow for the hecdroce cqnol = 4zl Us + 30lls = 451 lls. Thertfore use o d€sign llow of455 lls to size tlleheqdrqce conol.
conol sizing
c0n0l type: srone mosonry in cement mortorn - 0.020 for dRssed stone mosonry {from Toble 4.1)
Q = 0.as5 mr/s
s = l/975
From Toble 4.2 choos€ N = 0.5 (1h/2v)
Set lh€ botlom widih {B) = 0.450 m which is the size of the existing irrigotion conol. This miDimises excovotion works.Now use the foll0wing form ofthe Monning's equotion where only the woter depth, H. is unknown:
^ (BH+NHz)5',\ i;Y r , - t r 3
n l (B+2H! ( l +N1 l
10.450ii +0.5H11 rx\tiE75u,r')) = - -=-
o.o2o[o 4so+2H ''(r +051 ]"By triol ond €rror meth0d, the obov€ equotiot is bolonc€d when H = 0.268 m for o flow 0f455 lh.Therefore, the wqter depth will be obout 768 mm. N0w check thot rhe velociry is less thon the moximum ollowoble velocityof 2.0 m s ffom Toble 4.t.
v= Q/n \
0.455
(BH+NH1
0.455(0.450x0.768 + 0.5x0.768')
or V = 0.7 m/s < 2.0 mis OK.
The drowing qnd dimensions for this concl sertion con be se€n in Drowing 420/04/2A01 (Conol type B) ofAppendix C. Not€thot the originol design wos bqsed on on ossurned volue of0.()17 for Monning's n, giving o woter depth ofZ05 mm, rhereforeoctuol fr€eboord mqy be less thon recomm€od€d. The oth€r conol s€ctions ofthis scheme con be verilled by simiior colculo-tions.
3.4.1 IOCATION OF SPIIIWAYS
As mentioned eorlier, spillwoys ore required in heodroce conols
to spill excess flows during the monsoon ond in cose ofobstruc.
tion in the conols. Similorly, spillwoys ore olso requir€d ot the
foRboy to spill the entire design flow in cose ofsudden volve
closure ot the Dow€rhouse.
Note thot when the conol olignment hos oL€ody been flxed (i.e. fixed conol b€d dope, s) os in the c0se of the C,olkot schem€,there is little control in the velocity. The velocity con be slightly modified by chonging the cmss sectionol oIPo but it will b€difficult to moke significont chonges. For exomple, the velocity in the U92 slope conol section ofthe C,olbt scheme is obout2 m/s. However, this wos found to be mol€ economicol (i.€. reshoping the existing conol) thon r€oligning the conol olignmentto reduce the slope. This impli€s thot the steeper sections ofthe conol moy require more mointenonce work thon the gentlersections. This is one Eoson for plostering the inside surfoces of th€ conol.
Also, note th0t earth inigotion conols or€ gmerolly ste€per since lf (mughness coefficient) is higher. when such conols or€
modified os heodroce, they become smoother (use ofcem€nt mortor, ploster, better shope, etc.) ond hence con hove highervdocities.
3.4 Spillwoys The exc€ss flows rhot ore dischorged vio o spiliwoy
should be sofely diverted into the streom or neorby gully such
thqt they do not couse ony ercsion or dqmqge to other struc-
tures. Sometimes, this moy requiR the construction ofo
chonnel to the noturol woter cou$e. Locoting spillwoys close to
o gully will sove the cost ofchonnel construction os con be seen
in PhotooroDhs 4.11 ond 4.12.
Photo412 spillwoyon o crossing where the excess llow is dischorged intoogully, Colkot micm.hydro schem€, Boglulg. NeDol
4.4.2 SPTIIWAY DESIGN
Where woter is ponding ot o downstr€om regulotor such os in o
foreboy, the design ofspillwoys con be bosed on the weir
equotion discussed in Chopter 3.
0 = C t . . ( h ) ' sPhoto4.1l overflow from the forpboy dischorc€d overo rockdiff, Dhoding
micro-hydrc, N€pol
50
where:
Qpir.oy = dischorge over the spillwoy in mr/s
L,pir*oy = length of the spillwoy in m
hou.noo = heod over the spillwoy in m (i.e. height of wcter
over the spillwoy)
C* : o coefficient (similor to weir coeflicient) which
vories occording to the spillwoy profile. C* for different weir
profiles is shown in Toble 3.3 (Chopter 3).
The design steps qre os follows:
o Colculote the flow through the intqke during floods os
discussed in Chopter 3. The spillwoy should be sized
such thot the entire flood flow con be diverted owoy
from the conol. This is becquse the micro-hydro system
could be closed during flood or there could be on
obstruction in the conol.
r Choose o spillwoy profile ond determine C*. In the
Nepolese context, o brood, round edged prohle (C* =1.6)
is suitoble since it is eosy to construct.
r Spillwoy crest level should be 0.05 m obove normol
cqnol woter level. No more thon 500/o of the freeboord
should be used. Therefore, with o generolly used
freeboard of 300 mm, the ovqilqble hou"no, is 0.5 x 0.30 -
0.05 = 0.10 m. The required length con then be colcu-
loted for the chosen hou.noo ord flood flow.
Where there is no ponding immediotely downstreom,
such os in the heodrqce conol, the spillwoy length colculoted
using the weir equotion should be multiplied by 2: this occounts
for the groduol decreqse in heqd over the spillwoy, until the
required level is reoched at the downstreqm end of the spillwoy.
ln this cqse only the excess flow (Qn"o, - q.,,nn) should be used
for Qp,u,oy. Note thot in such coses, locoting the spillwoy
immediotely upstreom of on orifice will increose the flow
through the weir. The design of o spillwoy is presented in
Exomple 4.2.
Design o heodrqce conol to convey o flow of 285 l/s. Site conditions indicqte thot the conol would be stoble if stone mosonry
in mud mortor is used. The expected flow through the intoke during o Z0-yeor return flood is obout 480 lis. Design an
odequote spillwcy.
Design procedure:
Ccnol type: stone mosonry in mud mortor
Q = 0.285 m3/s
From Toble 4.1:
Roughness coeflicient n = 0.035
chooseV = 1.0m/s
From Tqble 4.2, for grovelly eorth, select side slope, N = 0.5, (1h/2v).
Cross sectionol sreo, A = 0.285/1.0 = 0.285 mz
x = 2{ff i -2*X = 2{ i1"r-gfr) -2x0.5
X = 1.236
Cqlculcte the woter depth in the cqnol, H:
,r= fT-." { ( x+N)
u = f__Q285_" { (1.236+0.5)
H : 0.405 m
Calculote the bed width, B:
B = H X
' I
i
B = 0.405 x1.236
B = 0.50m
Colculcte the top width up to the design woter level, I
T: B + (2HN)
T = 0.50 + (2x0.405x0.5)
T = 0.905 m
Check if V < 0.8 V,
.. tTo- | o285xe3-v I r
- = r -c \ i T v 0 . 9 0 5
V, = 1.76 m/s
0.8 V. = 1.41 m/s > V : 1.0 m/s OK
Colculote the wetted perimeter, P:
P: B * ZxH{ f f iP = 0 . 5 + 2 x 0 . 4 0 5 \ F + O y )
P = 1.406 m
Colculote the hydroulic rodius, R:
A 0.285R = _ - = - = 0 . 2 0 3 m
P 1.406
Colculote the required consl bed slope, S:
/ nv \ 'q = f - l- \ R0f67 I
/ 0.035x1 \'s - | _ t\ o.2o3o*' I
S = 0.0103 or 1:97 (i.e. 1 m ofdrop in 97 m ofhorizontol
ccnol length)
Finolly ollow 300 mm of freeboord. The cancl dimensions
con be seen in Figure 4.7.
Check the flow depth for maximum flood flow in the
canol.
(BH+NH1t3{;a-
n[to+zHr4r+r.r1 ]"'
0.480 =(0.sH+0-51x3 xfi-Oto:
[ , - I2 , ro.o3s [o.s + 2H v(1 + 0.51 J
By triol ond error method, the obove equotion is balanced when H = 0.55 m. Therefore, the flood flow occupies 500/o of thefreeboqrd (the moximum qllowed, os discussed eorlier) ond the heod 0n the spillwoy (hou,noo) wiil be 100 mm.
Check the size of porticle thot will settle in the canal ot o velocity of 1.0 m/s.
Figure 4.7 Proposed internol canol dinlensions for Exomple 4.1
52
D = 1 1 R S: l l x 0.203 x 0.0103= 23 mm
I.e. porticl€s lorg€r thorl 23 mm would settle in this heodroce cono]. Therefore, to ovoid deposition upstrcom ofthe settling
bosin, the grovel trop must be designed to remove oll porticles grcoter thon 23 mm.
Design of spillwoy
Note thot 2 conditions need to be ch€cked os follows:
1. The spillwoy must be oble to convey the entire flood flow of480l/s in cose the h€odroc€ conql downstrcom gets obstmcted
{ponding cose).
2. The spillwoy should be obl€ to spill the excess flow (48014 - 2851/s) when there is no obstruction downstr€om.
The colculoted m0ximum spillwqy length should be used in the design.
cqlculotions
Choose q bro0d crested weir with round €dges profile, so C, = 1.6
Cose 1: qe,[*"y = 480 l/s
h",.""e = 100 mm colculoted eorlier
Now colculote lhe length ofthe spillwoy,
. Qp'rr*vL,p,rr*oy = [1fr--p
. 0.480"rpr [eoy l .6x{0.1)rr
Cose 2: qoijr""y = 480 - 285 = 0.195 lh
20
c x{h
2x0.195l.6x(0.1)r5
LTherefore o spillwcy l€ngth 0f9.5 m is requiEd for the
obove conol {Cose 1).
Pholo 4 l3 HDPE prpes provide 0n overflow from o timber chonn€l (Mhopung)
4.5 Crossings
Sometimes the heodroce or rhe penstock olignm€nt mqy n€ed to
cross guli ies ond smoll slreonrs. Crossings ore such structur€s
thot conv€y th€ flow over streoms, gullies or qcross unstoble
te oin subject to londslides qnd erosion
The cqlkof crossing wirh o spil lwoy wos shown in
Photogroph 4.10. This is o 1.2 m long oqueduct thot is con'
structed from reinforced concrete. Its size ond slope ore similor
to the upstreqm heodroce conol. In micro-hydro sch€mes,
reinforced concret€ crossings moy be feosible ifthe l€ngth is
short. Such structures ore expensive ond complicoted for longer
lengths.
53
The Jhonke mini-hydro penstock crossing cqn be seen in
Photogroph 4.14. ln this cose the penstock olignment hod to
troverse o 12.6 m wide gully This gully is octive only in the
monsoon ond 0t other times it is dry. A series of mosonry wolls
wele designed to support th€ penstock (similor to the suppon
piers) olong the gully. All ofth€se wolls rest on o continuous
foundotion pod. During the monsoon, the surfoce runoffflows
between the wqlls.
Photogroph 4.15 shows the chondruk cmssing. The 50kw chondruk micro-hydrc scheme hos o long HDPE heodrocepipe (see Box 4.6) ond ot one locotion, the olignment hod tocross o gully. As con be seen in the photogroph. 0 mild steel
Phbto415 Chondruk micm-hydm heod roce crossmg.
chondmk, N€pol
pipe wos used for the crossing with onother verticol pipe
supPorting it.
Aport from the types ofcrossings discussed obove,
inverted siphons ole olso sometimes used ocross gullies,
Invert€d siphons qre pipes thot ore buried ocross the gullla They
trqverse down to the lowest point ofthe gully ond then come
up ot the other side (hence the nome inverted siphon). As long
os there is suflicient heod ond the pipe is below the hydroulic
grqde line, the flow con be conveyed through such siphons. A
Ilush out volve must be incorporqted ot th€ low point ofthe
siphon (since sediment con be deposited ot the low poinr).
4.6 Heodrcce pipe
4.5.1 GENERAL
Pipes moy be rcquipd olong the heodroc€ olignment where
slop€s ole unstoble ond wher€ londslides moy occur Although
mosonry ond concrete conols con minimise seepoge induced
londslides. they ore rjgid structures ond in the event ofslope
foilures, such conols con be swept owoy- These conqls will olso
crock ifth€re ore sm0ll slope movements. Where soil instobility
prcblems ore expected, flexible pipes moy be 0n oppropriote
solution prcvided thot the required pipe length is not too long
(s€e Box 4.6). Anotherc0se for the use offlexible pipes is when
the entip hillside is slowly sliding (i.e. moss movement is
occurring)ond port ofthe heodroce olignment needs to
troverse it.
In Nepol HDPE pipes ore often used to oddress th€ obove
pmblems. These pipes ore flexible enough to occommodote
some ground movement ond con bejoined by heot welding,
which is described in Box 4.7. HDPE pipes should be buried to
protect them from sunlight, cottle ond vond0lism.
The reoson why PVC pipes hcve not been used for
heodr0ce in N€p0l is b€couse olthough they ore eosy tojoin
(with o PVC c€ment solution), they ore olso very gid. Therc-
fore, they connot occommodote ground movement.
Appendix B includes doto on stondod pipe sizes ovoil-
oble in Nepol.
4.62 DESIGN CRITERIA
The design criterio for heodroce pipes ore similar to those of
heodroce conols. specificolly, the design should oddress the
following issues:
. The pipe diometer should be such thot for the ground
slop€ ofthe olignment, it should be oble to convey the
design flow. Ifthere is o possibility offlood llows
entering into th€ pipe, moke provision for spilling srlah
exc€ss flows.
Phoro 4 14 Jhqnlce mlni hydro penstock crossing, Dolokho, Nepol
54
The inlet to eoch section ofheodroce
pipe should be protected with o
troshrock, so thot debris does not get in
ond block the pipe. The spocing ofthe
troshrqck bqrs should be no more thon
one third ofthe pipe diometer, ond the
velocity through the troshrock should
not exceed 1 m/s.
Wherc o section ofheodroce pipe ends
in on unlined conol, o mosonry
tronsition strucNr€ is recommended, to
ovoid scour by the high velocity flow.
Heodroce pipes qI€ emcient when they
orc flowing full, but ifthe heod on the
pipe exceeds the roted pipe heod (i.e.
ollowoble heod on the pipe) breok
pressur€ tonks ne€d to be provided. Such tonl6 dissipote
the heod over the pipe ond ovoid the need to use o
higher pipe roting. Howeve4 in proctice, repeoted use of
bEok pEssure tonks hos sometimes induced cyclic surge
(i.e. periodic chonge in heod ond hence the llow).
Another option in such coses is to sel€ct o lorger pipe
diometer such thqt open flow condition prcvqils. Br€ok
prtssule tonls should be provided with lockoble covers,
so thot debris connot g€t in ond block the pipe.
Photo 4.15 BlPoI prEssuR tonk with ice orcund lhe wols (Jhonq)
o As for os possible, th€ pipe olignment should be such
thot it is olwoys sloping downhill. This ensures thot
therc is olwoys o positive heod ov€r the piPe qnd the
chonce ofit being blocked is olso reduced.
. Ifthen is o need for inv€rted siphons (or the piPe ne€ds
to go uphill for some length due to the gmund profile),
oir Eleose volves should be provid€d qt high points
olong the olignment. similorly, flush volves should qlso
be pmvid€d 0t low points to flush sedim€nt from the
pipes qnd henc€ pr€vent them ftom being dogged.
Photo 4 l7 Flush-outs should b€ provided ot low points in pipeliner sothot hedvy debris cdn be p€riodicoly rEmoved (Siklis)
Note thot the setting out ond preporotion ofthe bendl for
heodroce pipe is similor t0 the heodroce conol discussed in
Section 4.4. As mentioned eorlier, HDPE pipes should olwoys be
buried. A minimum buried depth ofl m with sieved soil
150 nun t0 300 mm oround the pipe is Ecommended os shown
in Figun 4.8. The use of sieved soil ensuRs thqt the pipe is not
punctuEd by pointed rocks during compoction, distributes the
loods evenly ond prevents futurc diffeftntiol settlements obove
the pipe. The 1 m depth minimises the overburden loods over
the pipe such os when people or coftle wolk over it. Also, in
ol€os wher€ freezing is expected during mid-winter, 1 m is
usuolly sumcient to be below the ftost line.
At inlet ond outl4 sections ofo heodroce pipe, it is
Rcommended to provide ir et ond outlet structur€s ofstone
mosonry or conc€te.
55
The 50kW Ghondruk micro.hydro scheme wos one ofthe first micrc-hydropower projects thot fmc Nepol wos involved in
HDPE pipe hos been used successfully for the long heodroce through forest, but lessons shouldbe leomed from the Problems
exP€n€nced:
. Sticks ondleoves entering the piPe qt the heodworks
get wedged ot the weld beods, cousing pipe blockoge.
. Vondols thrcwing stones into thebreokprcssul€ tonks,
. Pipe collqpse du€ to negotive pressure ot o high point
(where th€ pipeisbelow the hydroulic grode line).
. Surging flow due to oirbeing drown intothe pipe ot
breok pressure tonks.
At one short locotion, th€ hillsid€ wos not very stoble qnd
the HDPE pipe hos been supported by golvodsed wires tied
to trees os con be s€en in PhotogroPh 4.18. A.lso notlce
thot the HDPE pipe con be bent wher the bend rodius is
loJge. However, it would hove beentechnicolly sounderifo
gobion woll hod beer built downhill of the PiPe 0lignment
ond the pipe covered with soil qs shown in Figure 4.8
Photogrqph 4.19 shows o mitred b€nd on the chondruk
HDPE heodroce pipe. This wos mode by cutting piPe
sections ot on ongle ond them by heot welding. It hos storted leo]cing ot the bend ond the villogers hove wroPPed it with
plostic sheets ond golvqnised wire. Bends tiot ore constmcted by cutting ond welding pipe sections require core during the
?hoto 4 18 IIDPE heodroce pipe olong unstoble oligrunmt, Chondruk
mrcro-hydro scheme, Nepol
joining process (i.e., the more joints, the higher
the likelihood ofleotoge). fthere is some
h€qd over the heodroce pipe, then there con be
significqnt forces ot the bend os will discussed
in Chopter 7. Such forces cqn weoken the
joints ond couse leol<oge. Also note thot tI€
pipe section shown in the photogroph should
hove been buried.
Photo 4 19 B€nd prepored by cuning ond welding
the IIDPE h€odroce pipe ot Ghondruk
IIDPE pipes ore ovoiloble in th€ mqrket in fixed lengths (e.g.46 m pieces)qnd need to be joined ot site. Unlike pvc pipes, thereis not o liquid solution thot con be used to join HDPE pipes. The only economicol method ofjoining thes€ pipes is by heotwelding them. This involves heating the ends (thot need to be joined) sucl thot they become soft ord molleoble ond then
ioining them by applying force from close to both ends ofthe pipes, This joining temperqture is reoched qt obout 200"C. Thefollowing steps orer€commended whenjoining HDPEpipes otslt€:
. First heqt the welding plot€ until the required temp€roture
is reoched. The welding plote (olso lglown os the heotingplote) is o mild steel disc with o rod welded ot the edge ondq wooden grip ot the end ofthe rod. Heoting the w€ldingplote con be done by either using o kerosene burner (os
shown in Photogroph 4.20) or by heoting the plote over ochorcool fire. A speciol chqlk colled tiermo-croyon con b€used to ensure thot tlrc plote hos reodrcd th€ requiredjoining temperoture. A few lines should be mork€d on theplote while it is being heated. When the plote reoches thejoining temperotue the dlolk colour tums blue t0 blockwithin one second.
. The welding Plote should then be removed and ploced inside o Teflon bog (the bog con be mode by stopling Teflon fobric).The Teflon bog ensults thot the heoted I-IDPE pipe ends do not stick to the heoting plote ond distort the slnp€ ofthe pipe.Teflon is o speciol fobric thot cqn withstond higher temperotuj€.
. Th€n with the heoting plote inside the T€flon bog, the pipes should b€ pushed together until thet is o uniform beod oroundthe outsideioint surfoce. The heoting plqte olong with bag should then be removed ond the pipes quickly pushed ogainsteoch other. This Pquircs ot leost thr€€ people (one t0 hold the plote ond two to push the pipes.) os shown in Pbotogroph4.21. once the plote is placed betw€en the pipes. the entire process should be completed within 15 minutes since the plotetemperoture will stort decreosing. One prcblem in ttris metlod is thot th€ two pipes moy not be straight sinc€ it will bedifficult to opply uniform forces orould the pipe circumf€Enc€ monuolly- An olt€rnotive is to use collot flonges os shown inPhotogroph 4.22 These flonges ore mode in two ho.lves such thot they fit on the outside circumference ofthe pipe. In thismethod, th€ collo$ ore fitted obout 50 mm to 100 mm from the heoting mds ofthe pipes, b€fore inserting t}re heoting
Plote. As soon os the required temperoture is met, the heoting plote is tolen out, ond bolts ore inserted olong the flongesond tighten€d everdy. This ensures thot the two pipes oft stroight. Once thejoint cools, tle collors ore removed byunbolting them. As Gn 0lternative to tlle obove methods, o mechonicol j ig is commoDly used, which serves both to olign thepiPe ends ord to opply the requiredjoining force. The pipe monufocturers con odvise the requir€d force for different pipediometers ond grodes.
Refer to Oopter 10 (lnnovotions) section 10.3 concerning o de-becder tool to ftmove the ctcumfer€ntiol beod corrsed by heotwelding. photo 422 Collors used rojoiD ItDpE pipes
Phoro 4.21 JoiningHDPE pipes by pushingthem while hot- Noticethe Tellon bog.
Ph0t0 4.20 Heotitrg the w€iding plote
Generol bockfi | | cornpoctedin 25O mm loyers
Sieved bckfill morirnm srze 5mm)conpocled In mm hyers
Pipe
Drystone mosonryto retoin bockfil l
I
\z
cEooI
II
I
[5dmn-Tr
Generol bocKill
Sieved bockfil l
Pipe
hsd mn-1-l--
58
i
{I
4.63 DESIGN PROCEDTJRE
The design procedure (i.e. selection ofon oppropriote pipe
diometer) for o heodroce pipe is os follows:
1. Choose o stondord pipe size from Appendix B, such thqt
the velocity V is less thon 3 m/s (to minimise woll
obrosion ond to ovoid excessive heodloss) ond greoter
thon 0.5 m/s (to ovoid sediment being deposited in the
pipe). In generol, for HDPE pipes o velocity of 2.5 mls to
3.0 m/s is found to be economicol.
2. Colculqte the octuol velociw:
40r t - . -
rId,
where:
V is velocity in m/s
Q is design flow in m3/s
d is the pipe internol diqmeter in m.
3. At the entronce ofthe heodroce pipe set the submer-
gence heod os follows:
. 1.5v'zn ) -s - 2 9
where h, is the submergence heod in m os shown in
Figure 4.9. Note thot this is the heod from the crown of
the pipe. If the submergence heod is less thqn required,
then the pipe will not be oble t0 convey the design flow
(Q becouse oir will be drown into the pipe.
Figun 4.9 Submergence heod for o pipe
4. Cqlculote the heodloss in the pipe length bosed on the
inlet, woll friction, bends, volves ond exit losses os
follows:
Totol heod loss = woll loss * turbulence losses
The woll losses result from the friction between the flow
and the pipe woll. Woll losses ore colculoted os follows:
First determine the roughness volue, k in mm from Toble
4.3. Note thot the values of k iq this toble ore bosed on
normql oge (5-15 yeors) or condition.
Then use the Moody Chort in Figure 4.10 to find
the corresponding friction loctor ffor the selected pipe
mqteriol, diometer ond the design flow.
The wqll loss cqn now be colculoted from the foilowino
equotion:
LV2h = f _"woll loss
dX2O
In terms of the flow, diometer ond length, this equotion
con qlso be rewritten cs:
, fLQ.n ='^wqll loss 12d5
furbulence losses qre colculoted os follows:
h = V ' z l 2 s ( K + K + K + K )tu rD lo \s I v ' en l ron(e Dand (on l rocuon vo lve?
where heqd loss coeflicients, K, ore qs shown in Tqble 4.4.
Note thot HDPE pipes cqn be bent (by hond) without
cousing ony domoge if the bend rodius is qt leost 50
times the pipe diometer. This should be done wherever
possible, becouse:
o) it ovoids the need for mitred bends;
b) it ovoids the need for onchor blocks to restroin bend
forces (discussed in Chopter 7); ond
c) ot such Iorge rodius, \"n, becomes negligible.
Where o long rodius bend is not possible, o shorper bend
is required, ond the volue of \.no should be tqken from
Toble 4.4. Mitred bends will normolly be used for steelqnd HDPE pipelines: these qre fobricoted by cutting the
pipe ct on ongle (moximum 15") qnd then welding the
ends together to creote o bend ofup to 30". For bends of
more thon 30", two or more mitre joints ore required.
Check if the totol heqd loss for the design flow is less
thon the loss in heqd due to the pipe grodient (S) ond
thot the pipe profile is below the,hydroulic grode line
everywhere. If not, repeot cqlculotion with lorger pipe
diometer.
Determine the woter level ot the control structure ot the
end ofpipe such os the breqk pressure tonk, grovel trop
III
II
6.
59
or the settling bosin. Allow 100/0 morgin by ossumingthot the totql heod loss is 10%o higher thon colculoted(i.e. woter level is l0%o lower thon colculoted). This is toollow for uncertqinties such os the woll losses beinohigher thon ossumed.
7. Repeot colculotions with higher submergence heod dueto flood flows ond colculote the corresponding losses ondpipe flow. The excess flow will hove ro be spilled from ocontrol structure (grovel trop, settling bosin etc.) ot theend ofthe pipe.
Tqble 43 Roughness volue for differrnt pipe moteriols
MATERIAT ROUGHNESS VALUE, k (mm)Smooth pipes
PVC,HDPE, MDPE. Glqss fibreConcrete 0.15Mild steel- Uncooted- Gqlvqnised
0.06
0.06
u . l )
(I
i
i
I
;
I
1 . 2 O / m 3 / s , r
; \ , " /. 2 . 5 t 2 l 0 20 5 0 1 0 0
6(o
't()
ll_
0 l
. 09
.08
. o7
U O
. 05
.04
.03
.025
.o2
.0r 5
0. I
.09
.08
0 7
.06
.05
.03 s.9
.02s 6LL
.02
.01
.o09
.008
.01 .02 .05 . t .2
1 .2
.5 I
*(#)2 s / r o \ z o s o roo
rvd - 000.00t ud-.999.005
Figure4.l0 Moodychort
60
Tqble 4.4 Turbulence losses in pipes
Heod loss coefficient for intokes lK-*jEntronce prohle
z7
kvK-c** 1.0 0.8 0.5 0.2
Head loss coeffici€nts for bends (Ko..of
Bend profile
r/d MITR-ED-
{o l0 = 20'lk-o l0 = 45"1k".", l0 = 90"|
Q.20
0.400.75
0.15
0.30
0.50
0.120.250.40
0.10
0.20
0.30
0.100.220.45
.Mitred bends with 4d : 1.5, maximum 30 per mitred joint
Heod loss coemcients for sudden controcrtions lK_.*.*lControction profile
5.0) \2.01 .51.0d,ld,0.500.400.35
Heod loss coefficients for volves (\",.f
K .
SPHERICAI.
0.1
o t
BUTTERFLYTYPE OFVALVE GATE
Ii
I
Flood lrvcl
J$.m3BodioHDpE160 Us in 2r?8O
GRAVEL TR.Aq
l{ol fo rcolc
rivcr levrl
Figur€ 4.ll Heodworb of the tffi kW Siklis micro-hydm scheme (Siklis. Nepoli
A sketch of the heodwork of the existing 100 kw Siklis micro-hydropower scheme is shown obove in Figure 4.11. colculorethe following:
1. Heodloss in intoke pipesZ. Design woter level in grovel trop3. Flood flow through intoke pipes4. Spillwoy length ot grovel trop
l. Hecdlocs in lntake pipes ct design 0ow
nl Pinp frictinn
For 280 mm di0'meter, Closs II HDPE pipe monufocturcd in Nepal, internal diameter = 262 mmFIow perpipe (Q = 160/2 = 80 l/sFrom thble {.3, sssurne k = 0.06 mm
k 0.06mm't;-=Em;- = o'ooo23
l.zQ 1.2x0.08;--= fll6z
=0.356
.'. f = 0.0166 (from Moody Chort, Figure 4.10)
. fLtr" h m u r o s : l 2 d i -
_ 0.0166x40x.0.08, = Ol9 m
12x0.2625
b) Inlet heodloss
K** = 0.8 for this cose (Tcble 4.4)
62
I
I
I
I
v2. ' . h . . - K xror( toss emmftc
29
Check velocity;
40 ,1x0.08V = i - = - = 1 . 5 m r s-
fld2 nx0%t
0.8x1.52of hintnl., =
Z*9f = 0'qLE
c) Exitheodloss
- \lzh . = l ( . 1 -
srr6r &t Zg
1.0x1.5'zz-9f
= o'11 m
.'. Totol heodloss tn intok€ pip€s= 0.29m * 0.09m * 0.11 m = 0.49 m
2. Ilesign water levd in grovel trcp
This should be ot leost 0.49 m * ltl% (sofety mcrgin) i.e.0.54 m below the low river level ot the intoke, or "o" = 0.54 m inFigure 4.11.
3. Flood flow through tntala pipes
Flood level is 1.5 m obove low river level.Allow 0.2 m heod over grovel trop spillweir (i.e. b = 0.2 m in Figure 4.ll).Then net heod on intoke pipes = 0.54 + 1.5 - 0.2 = LE4_8., or 'c" = 1.84 in Figure 4.11.
fiol ond error solution for flow:
o) TrY Q = 200 l/s in eoch pipe
7.20 7.2x0.2-
a : i .262- =o'916
+ f = 0.0152 (from Moody Chort)
0.0152x40x0.20'?t i-^...^,,,-.:-::--:-:-::--- = 1.64 mwour*s 72x0.2625
v = 4Q - 4xo'2 = 3.71 m/slld'z llxQ%:t
Inlet & exit losses (0.8 + 1.0) + = 1.26 m' 2 9
Totol heod loss = 2.90 m
This is more thon 1.84 m (net heod on intoke pipes for flood level), .'. ossumed flow is too high.
Try interpolotins: 2oo U, - (# )"= ,r, U,
OJ
b) Check for Q = 159 l/s in each pipe.
l.zQ 1.2x0.159*a =Tff i ' - =0.?30
-+f = 0.0i54 (from Moody Chort)
0.0154x40x0.15fJh*otrrorr=
l17p1AZG2t =l'05m
40 4x0.159v=fr, =
;oo%z, =2'95mls
Inlet ond exit losses (0.8+1.0) *
: *rn
Totqlheodloss = 1.E5 m
This is neor enough to 1.84 m
Therefore flood flow through the two intoke pipes is: 2 x 159I/s = 31E Us
4. Spillwcy length ot grovel ftop
Weir equotion:
Qpimoy = C* x Lrpitt*oy x (ho"rno/t t
Required spillwoy weir length,
- Qoittwovl _ =-spuwoy
c*x(ho""noo)rt
Toke C* = 1.5 ond Qp'rwoy : 318 Us to ollow the entirc flood flow to be spilled over in cose the turbine needs to be closed
during such floods.
hou.noo = 0.20 m (heod over weir, ossumed eorlier)
0.318. . . L . . = -=2 .22m
spurwoy 1.6x0.20,.t
or'd" = 2.22 m inFigure 4.11.
Note the following:
1. To limit the inlet velocity, two porallel pipes hove been used from the intoke to the grovel trop. Downstr€om of the
grovel trop there is only one pipe and the veiocity is doubled. The rroson for using a lower velociry in the initiol pipe
length wos to lower the submergence heod so thot excovotion work ot the intoke could be minimised. With lower inlet
velocity there less chonce of ottrocting flooting debris which could block the inlet.
2. The spillwoy weir length is reosonoble, but note that on olternotive ossumption for heod over the weir would give o
di{Ierent onswer. The wolls oround the grovel trop must be high enough to contoin the flood flow over the spillweir.
3. The grovel trop hos to be locoted sufliciently for downstreom ofthe intoke to ensure thot the grovel trop spillweir isqbove the moximum river flood level ot thqt point: in this cose the 40 m intoke pipe Iength is more thon enough to meet
this criterion.
4.7 Construction of conols
4.7.1 DESCRIPTION
Once the conol type hqs been selected ond the design corriedout, there qre four stoges in the octuol construction os follows;
. setting out ofthe course ofthe conol,
. preporing the bench for the conol,
. excovoting the conol, qnd
o lining the conol.
These secticns describe 0 g€nersl nethod 0lc0nclconstruction ond offer exomples of other proven methods thotmoy be suitoble under certoin conditions.
4.7.2 SEIIING OTII
Setting out the conql requires the following equipment ond
sto{I
r Bosic equipment:. Level mqchine (or Dumpy level). Meosuring tope. Tripod. Wooden pegs. Mqchetes. Mqllet. Pick. Hoe. Point. Pqintbrush
o Stqff:. Surveyor. Chcinperson (ossistont to surveyor). Helper to cleqr vegetotion qnd pr€pore pegs
The setting out ofthe cqnql is done by plocing pegs olong
the olignment. Depending on the topogrophy, such pegs shouldgenerolly be ploced ot 5 t0 20 m intervols olong the olignment.
Pegs should olso be ploced qt bends, structures such os drops,
ond the beginning ond end of crossings ond superpossoges.
Some intermediote pegs or reference pegs should beploced just outside the conql olignment using o level mochine(or o Dumpy level). With the use of the level mochine, the
difference in levels between these pegs con be cqlculoted. Suchpegs will serve os reference levels for the excovqtion work. An
olternqtive to this is to point morks ot exposed rocks just
outside the olignment ond colculqte their levels.
4.73 BENCH CUT
The bench of q conol is like o rood of uniform width ond slope,see Figure 4.12. The bench is prepored by excovoting o strip oflond ofeven width olong the pegs ploced eorlier on the conqlolignment.
The bench width should be the top width of the conqlplus on ollowonce for berms on eoch side of the conol. On thehill side, q berm of 300 mm is recommended. so thot moteriqlwoshed down by rqin from the slope obove is not depositeddirectly in the conol. A 1.0 m wide berm is recommended on thentt tSlde nf thq henrh tn rpdrrCp sppnnnp thrnrrnh thp rnnnl hnnlz
! r . r v g 5 ^ ^
ond to provide occess for construction ond mqintenonce. Alesser berm should only be used in conjunction with verticolcement mosonry wqlls founded on rock. Note thot q bermwidth less thon 500 mm is diflicult to wolk olong.
The slope ofthe bench should be the some os the slope (S)ofthe conol section. Therefore, where there is o chonge in theconol slope (in the design) the bench slope should olso chonge
occordingly. The levels of the cqnol ond the bench ot differentlocotions con be verified using o theodolite or o level mochineqnd the intermediote pegs thqt were ploced outside the conololignment eorlier.
Once the initiql level ot the intoke is fixed, the subsequentlevels cqn be colculqted bosed on the slopes. The initiol level
con be estimoted bssed on the contour mops of the oreo or byon oltimeter. Another method is to use the trigonometric points
estqblished by the survey deportment, but this moy toke longerond require more resources.
The initiol level does not hove to be very occurote (i.e. theexoct elevotion from the seo lwel) but the differences betweenintermediote pegs should be occurote, since it is these differ-ences thqt determine the slope ofthe conol.
An exomple of o level colculotion is presented below:The designer hqs recommended o slope of 1.520 for o
certoin cqnol section. The topog rophic mop of the oreo
indicotes thqt the elevotion ot the intoke is qround 1600 m
obove meon seo level (MSL).
In this cose the first peg thot is ploced ot the intoke oreocon be ossumed t0 be ot o level of 1600 m qbove MSL. Ifthesecond peg is to be ploced 20 m (horizontol length) downstreqm,the bench level here should be:
20 m x 1.5/100 : 0.30 m down from the intoke or 1600 m - 0.30m = 1599.70 m obove MSL.
The subsequent reodings between intermediote pegs (i.e.
reference points) con be noted in sequence with similorcalculotions.
65
a
{
exceeding the top width ond meeting the bottom width ot the
required depth. Thus, the required tropezoidol shope con be
orrived ot. This method of excovotion minimises the use of
construction moteriols ond the need to bqckfill. Note thot, os
mentioned eorlier, the side wolls of o tropezoidol cement
mosonry conql ore more likely to crqck if constructed on
bocklill.
It is qlso helpful to prepore q wooden "former" to check
the cross sectionol shope ofthe cqnql for tropezoidol shopes.
This involves constructing o wooden frome (using rectongulor
sticks) ofthe required tropezoidcl shope.
The cqnol invert slope should be constontly checked
using o level mochine. Note thot on inqccurote slope con be
very costly: if the slope is less thqn required, the conol will not
hove the copccity to convey the design flow; ifthe slope is
steeper thon required, the velocity moy exceed the mqximum
vqlue for the conql type ond stort eroding it.
4.7.5 CANAI. UNING
Once the excqvotion work has been completed, the octuol
construction ofthe cqnol con commence. The construction of
the cqnol depends on the type thot hos been chosen. For- . . ^ * - l - : f ^ - ^ ^ + L ^ ^ - - l L - - L ^ ^ - - L ^ ^ - * ^ t l . L - . : - - - ^ - - : - - jcxul l lp l t , l l u l . l tu lL l l Lul lur l luJ uccl l L l ruscl l , u l l urur , t5 lcqut lcu
is to trim the side wolls qnd bottom width qt some ploces where
the excovqtion work hos been poor. However, if o mosonry
cqnol hqs been chosen, then this will require collecting stones,
dressing/sizing them ond then plocing them ot the excovqted
surfqce occording to the design.
For stone mosonry in cement mortor, the following is
recommended:
o The minimum thickness for bed ond side wolls should be
300 mm, since thinner wolls require more stone work
(dressing ond sizing) ond moy not hove the required
strength. This olso opplies to stone mosonry in mud
mortor conqls. Recommended designs ore shown in
Figure 4.13.
r Sond used for preporotion ofthe mortor should be clean
I
I
1
Figurc4.12 Conolbench
4.?.4 CANAL EXCAVATION
0nce the conol bench hos been prepored, the excovotion lines
need to be set out os follows:
o Plqce pegs olong the centreline ond the top ond bottom
widths of the conol. The centreline is on imogincry line
thot posses through the centre ofthe conql ond porollel
to the sides. Note thqt the top ond bottom widths should
include the side woll thickness os well (i.e. outside edges
ofthe finished cqnal).
r Join the pegs using thin ropes. Then mork seporote lines
for the top qnd bottom widths (for tropezoidol sections)
using powdered lime or qshes so thot they ore indicoted
on the ground. Note thot for rectangulcr sections, the
top ond bottom widths ore equol ond two porollel linesqre suflicient for the excqvqtion work.
o Check the dimensions ogoinst the design specificotions.
Once the excovotion lines hove been prepored the conol
should be excovoted to the required shope ond slope os per the
design. For o rectongulor conol, the excovotion should stqrt
from the sides down to the required depth. For tropezoidol
sections, the excqvotion should stort ot the centrql port without
exceeding the bottom width lines verticolly down t0 the
required depth. Then the sides should be excqvqted without
1.00
h>
0
min,
' o ) Woll height <0.46
Note: All dimensions ore in metres b )woll heighr >0.46
Figur€ 4.13 Conol lining with stone mosonry in cement mortor
66
ond free from orgonic moteriols qnd fine porticles. Thesond porticles should be gronulcr (like ordinory sugor)ond not floky. Sond mixed with fine porticles should bethoroughly woshed before use.
The rotio ofthe mortqr should not be less thon 1 portcement t0 4 ports sond by volume (1:4 cement/sondmortor). This opplies to qll wqter retoining structuressuch os the settling bosin ond the foreboy tonk. Thestones should be wetted before construction (dry stonesobsorb wqter from the cement mortor, stopping it reochfull strength).
1:3 cement sqnd mortqr moy be used for plosterwork inthe heqdroce conol ond other wqter retoining structuressuch os the settling bosin ond the foreboy. plostering theconol lining is normolly unnecessory, but could be usedto reduce hydroulic losses (refer to Tqble 4.1) or whereseepoge is occurring in bodly constructed mosonry. Thethickness of the ploster should be obout 12 mm (1/2
inch).
Immediotely ofter the construction of o cement mo-sonry portion ofthe conol length, it should be kept moistfor ot leost four doys. This is colled curing ond is doneby gently pouring woter on the wolls of the conql. Theuse of hession (wet socks) to cover the mosonry helps toretoin moisture cnd cures the cqnql structure better. Anuncured conol will not goin full strength. During hotond dry weother pouring woter on the mosonry conolwill be required frequently to ensure thot the conol wollsremqin moist ond reoch their full strength. Curing ismore importont for plosters since they ore thin surfqcesond con eosily crock ifthey dry up quickly. Note thot ifthe ploster is done ot o loter stoge (ond not immediotelyqfter the mosonry work), it will require further curing
for ot leost onother 4 doys. Also, the mosonry should be
wetted before opplying the ploster.o For ploin concret€ lining, use 80 mm thickness. A
minimum curing period of Z doys is recommended.o For reinforced concrete see Section 8.5.2.
4.8 Checklist for heodrqce works
o Check the heodroce olignment for stobiliry. Is the oreaobove ond below the heqdroce olignment stoble? Referto Chopter 2 for signs of instobility. Remember thoteorth conols ore the most economic option where theheodroce olignment is on stoble ground ond seepoge isnot likely to contribute to slope instobility.
o To minimise costs, stone mosonry in cement mortorcqnals ond heodrqce pipes should only be used clong thedifficult stretches of the olignment.
e While fixing the heodroce olignment do not moke theinvert slope steeper thon necessory since ony loss inheqd here leoves less heqd for power generotion.
Minimise the length unless longer length is required toovoid costly crossings. \ different options so thedesign is economicql ond the construction is procticol.
r Hqs the heodrqce cqnol or the pipe size been colculotedbqsed on the ovoiloble site doto? Ifon inigotion conql isbeing refurbished into o heodrqce, note thot there moynot much control over the invert slope. Decide on therype ofconol by trying different cross sections ondcolculoting the corresponding velocities such thot theyqr€ within the limit shown in Toble 4.1.
r For HDPE heodroce pipes, be sure to follow Figure 4.g forpipe buriol detqils. HDpE pipes should not be exposed.
r For the construction work refer to Section 4.7.
+ -
b l
5. Grovel trop, settlingbasin ond foreboy
5.1 Overview
5.I.1 THE SEDIMENT PROBLEM
Most rivers corry o substontiol quontity of sediment in the
form ofgrovel, sond or f iner rnotericl depending on the river
chorocteristics, geology ofthe cotchrnent oreo ond the dis-
chorge. Steeper rivers such qs those thot originote from the
Iiimoloyos corry cobbles ond even move lorge boulders during
onnuol f loods. Intokes ore locoted ond designed to l imit the
omount of sediment entering the micro-hydr0 system, but such
sediment connot be entirely eliminoted. Intokes con only
prevent boulders ond cobbies from entering into the system
ond minimise the influx of grovel ond finer sediment.
l-orge porticles con block the heodroce ond reduce its
copocity. Suspended sediment con couse severe weor on the
turbine runner, seols ond beorings, since the flow velocity ot
the runner is high. Such weor couses o reduction in the
efhciency of the turbine ond eventuolly leods to its complete
foilure. In either cose, mointenonce is necessory, requiring
high expenditure in terms of reploced ports, mon-hours ond in
loss ofpower production. There ore obundont exomples of
turbine runners completely destroyed within o few yeors ofter
instollcrtion ot micro-hydro plonts thot locked settl ing bosins.
The rote of weor of turbine ports due t0 sediment
obrosion is governed by the following foctors:
o Concentrotionofsuspendedparticles
r Hordness ofporticles
r Size of porticles
o Shope ofporticles
o Resistonce ofturbine runner
r turbine heqd
It is not necessory to exclude oll sediment ot the settling
bosin. This is virtuolly impossible ond would not be economi
colly vioble, especiolly for micro-hydro schemes. A smqll
concentrotion of fine sediment is often permissible os will be
discussed lqter. The design should be such thot the size ond
concentrotion of sediment possing the settiing bosin qre within
occeptoble limits.
5.1.2 FUNCTION OF THE STRUCTURES
Grovel trcps, os the nome denotes ore designed to trop grovel
thot enters the intoke olong with the diverted flow. If o river
only corries fine sediment ond not grovel (even during floods),
then this structure is not required. However, most mountoin
rivers in Nepol corry grovel, especiolly during floods. In the
obsence ofo grovel trop, grovel wil l settle olong the gentler
sections ofthe heodroce or in the settling bqsin, where it is
difficult to flush out.
A settling bqsin is o bosin whose function is to settle the
suspended porticles present in the diverted river flow. Since
rivers qre never free from sediment, oll micro-hydro schemes
should hove o settling bqsin. For smoll schemes, this moy
simply be a widened section of the conol. The flushing mecho-
nism moy be rudimentary, which is occeptoble provided thot
domoging sediment does not reqch the turbine.
A foreboy is o tqnk locoted qt the end of the heodroce ond
the beginning of the penstock pipe. It is o structure thot ollows
for the trqnsition lrom open chonnel to pressure flow condi
tions. The woter Ievel ot the foreboy determines the operotionol
heod of the micro-hydro scheme.
5.1.3 LOCATION OF THE STRUCTURES
Whenever possible the grovel trop, settl ing bosin ond loreboy
should be combined. This minimises the construction cost.
Sometimes, either the grovel trop ond the settling bosin or the
settling bosin ond the loreboy ore combined, but the topo-
grophic conditions ore rorely oppropriote to be oble to combine
oll three structures. The Jhonkre mini-hydro is q rore exomple
where it wos possible to combine oll three structures os
described in Box 5.1.
Selection ofon oppropriote settling bqsin site is governed
by the following criterio:
o The locqtion should be such thqt it is possible to flush
the sediment ond spill excess flow from the bqsin
without cousing erosion problems or damoge to other
structures. There must be suflicient heod to flush the
sediment qnd druin the bosin.
r The settling basin should be locoted qs close to the
heodworks os possible, especiolly ifit is seporote from
69
the foreboy. The eorlier the sediment is removed the less
the mointenonce of the heodrqce. Furthermore, the
heodroce olignment downstreom of the settling bosin
con be gentler (hence less loss in the cvoiloble heod)
since the flow will be sediment free. A locotion close to
the intoke ollows ecsy dischorge of sediment bqck to the
river. From on operotionol viewpoint, it will olso be
eosier for the operotor/helper to combine work ot the
intoke, such os cleoning the coqrse trqshrock, qnd
flushing ofthe settling bosin.
r There needs t0 be odequote spoce to construct this
structure os designed. Note thot it cqn be o relotively
wide ond long structure. Therefore, locoting this
structure on foirly level ground minimises the excovo-
tion costs.
The foreboy is locoted immediotely uphill of the
tronsition oreo where the ground profile chonges from
level to steep. The following odditionol foctors should be
considered before decidino whether o site is suitoble for
o foreboy:
r It should be possible to spill the entire design flow from
the foreboy without cousing erosion or instobiliry
problems. Ideolly if this structure con be locoted close to
o gully, it moy be possible to sofely divert the spillwoy
flows into it.
o Similqr to the settling bosin there needs to be odequote
spqce to construct this structure os designed. However,
the foreboy is usuolly smqller in size.
5.2 Grovel trap
A grovel trop is recommended for oll micro-hydro schemes in
Nepol. In the obsence of o grovel trop, the settling bqsin must
be close to the intqke ond qble to flush the grovel thot enters the
bosin. Grovel trops differ from settling bqsins in thot they
hondle coorse moteriql thot enters neor the bed, rother thon
suspended moteriql thot needs to be settled. The moin design
principle for o grovel trop is thot the velociry through it should
be less thon required t0 move the smollest size of grcvel to be
removed. The lorgest size ollowed to enter into the intoke con
be controlled by the spqcing of the coorse troshrock bors. In
generol grovel trops should settle porticles lorger thon 2 mm
diometer. Smoller sized porticles will be settled ond removed in
the settling bosin. The following criterio should be used for the
design ofthe grovel trop:
o To be oble to trop porticles down to 2 mm diometer, the
velocity in the grovel trop should be limited to 0.6 m/s.
o lfthe grcvel trop is hopper shoped, the floor slopes
should be obout 30" (1:1.7). Such on orrongement will
focilitote eosy flushing ofgrovel. Ifit is not possible to
construct such o shope, the floor should siope towords
the flushing end, with o longitudinol slope of 2-5%0.o JIq lgnglh of the grovel trop should be ot leost three .
times the width of the heqdroce colol or 2 m, whichever
is lorgg. With this fixed length ond o velociw of 0.6 m/s.
the required width of the trop con now be determined. .Note thqt this is o generol rule of thumb, but if a
significont bed lood con enter the intoke, then o longer
length moy be required. Since studies regording the
movement of grcvel in rivers ore rore (rorer thon
sediment studies), it is usuolly diflicult to estimote the
storoge required in o grovel trop. Note thqt the storoge
must be provided below the normol flow depth.
o To minimise blockoge of the heodrqce or domoge due to
obrosion in the heodrqce, grovel trops should be locoted
os close to the intoke os possible.
Crovel trops con be emptied vio flushing gotes or by
lifting stoplogs (i.e. wooden plonks). Since grovel enters the
intoke only during high flows, incorporoting stoplogs isgenerolly more convenient qnd economic.
The Golkot grovel trop is shown in Photogroph 5.1 ond in
Drowing 42010/.12C02 of Appendix C. Although o grovel trop,
this structure hos oiso been designed os o primory settling
bosin. This is becouse the heodroce conol is long (1.1 krn) ond if
significont sediment lood con be tropped in the grovel trop, the
mqintenqnce requirement will be less fqr downstreom in the
heodroce conol. Furthermore, once the sediment is removed.
the heodroce conol slopes con be gentler os discussed in Chopter4. Since this is o combined structure, the colculotions ore
presented ofter the discussion on settling bosins.
Note thot os con be seen in Drowing 420lCF.l2A0l(Appendix C), the Golkot grovel trop is locoted 35 m down-
streom from the intoke. This is becouse the initiol length of the
intoke wos felt to be vulnerqble to flood domoge. For the somereoson the coqrse troshrock is ploced qt the end ofthe orovel
Irop.
In the Golkot micro-hydro scheme, significont grovel lood
is not expected for the following reosons:
o The diversion weir is of o temporory noture ond does
not extend throughout the river width.
r The intoke is locoted on the outside ofo bend.
70
53 Settling bosin
53.T DESIGN CRITERJA
Suspended sediment thot is not settled in the grovel trop is
tropped in the settling bosin. The bosic principle ofsettling is
thot the greoter the bosin surfqce or€q ond the lower the
through velocity, the smoller the porticles thot con settle. A
settling bosin hos o significqntly lorger cross sectionql or€o
thon the heodroce conol ond therefore the flow velocity is lower
which ollows the settling ofthe suspended moterioJs.
A settling bosin must sotisry the following thr€e c terio:
Scttling copocity
The length ond width ofthe bosin must be lorge enough to^rr^Lr. r^mo noronr.^o ^. rh6 nno .o.r i .ne-t tC f0] loul Cfu ' w r r e r u r 9 ! l l l ! r ' r r u g L u . r r l r r u r l I u r
suspension ond be deposited on the bed. The sediment concen'
trotion pqssing the bosin should be within occeptoble limits.
The geometry ofth€ ir et, the width ofthe bosin ond ony
curvotur€ must be such os to couse minimum turbulence.
which might impoir the effrcienry
Stomge corcity
The bosin should be qble to storc the settled pqrticles for some
time ur ess it is designed for continuous flushing. continuous
flushing mechonisms ore however not incorporot€d in micro-
hydro schemes due to the complexity ofthe design ond the
sconity of woter during the low flow seoson. H€nce, the
stomge copocity must be sumciently lorge thot the bosin does
not require fr€quent flushing.
Flushiry cspcity
The bosin should be oble to be operoted so os to rcmove the
stored porticles from it. This is don€ by opening gotes or volves
ond flushing the sediment olong with the incoming flow in the
bosin. The bed grodient must be ste€p enough to cl€ot€
v€locities cqpoble ofremoving oll the sediment during flushing.
532 THE II'EAL SETruNG BASTN
The theory behind the design ofo s€trling bosin is derived onthe bosis ofon ide0] bcsin. Therefore, before proceeding tothe
design phose. the concept ofthe ideol bosin needs to b€ under-
stood. Such on ideol bosin is shown in Fioure 5.1.
tuint X Plon oreo A
FigurE 5.1 An ideol s€ttling bosin
Consider o porticle entering the'ideol settling bosin" on
the woter surfoce ot point x (i.e. beginning ofthe settling zone)
os shown ill Figurc 5.1. In this figure:
L = length ofthe setrling zone (m)
B = width ofthe settling zone (m)mpnn wntpr dpnth in thp <p t t l inn znno lm l n lcn
colled hydroulic depth
t = time for porticle to trovel the length L {s)vp = horizontol velocity component ofthe ponicle (m/s)
w: v€rtico.l velocity component ofth€ porticle (m/s), i.e..'foll velocity" which is discussed loter
Q: dischorge (mr/s)
Then the following equotions must hold for the pqrtide
to reoch th€ end ofthe seftling bosin (point Y):
y : w t ( o l
L = v p t ( b )
Q : B v p y ( c )
substituting for y, vpond t ftom (o) ond (b) into (c) Rsults
i n : q : 9 1 *
Phoro 5.1 Colkor grovel trop
71
Therefore, for o given dischorge Q, the plon oreo ofthe
settling bosin con theoreticolly be determined for sedimentotion
of o porticle with foll velocity w However, in prcctice, o lorger
bosin qr€o is required beccuse of the following foctors:
r the turbulence of the woter in the bosin;
o imperfect flow distribution qt the entronce; ond
o the need to converge (sometimes curve) the flow
towqrds the exit.
Therefore in 'reol bosins" the through velocity is limited,
to reduce turbulence, ond the required plon oreo is obout twice
the oreo colculqted for the "ideol bosin".
533 FAII VETOCITY OF SEDIMENT AND PARTICI.E SIZE
The foll velocity, w, chqrocterises the obility of porticles of
vorlous sizes to settle out under grovity. For o discrete pqrticle,
this volue depends on its size, density, ond shope, os well os the
temperoture of woter.
Figure 5.2 shows the foll velocity in woter, w, os o
function ofthe porticle diqmeter for reference quartz spheres.
This figure con be used to estimote w for the colculqtions
required in the design ofthe bosin. Note thqt the temperoture
effect becomes less for lorger diometer pofticles.
In micro-hydropower schemes, the settling bosin is
designed to trop 1000/6 ofporticles greoter thon o certoin size,
d,,,n. 0nly o proportion of smoller pqrticles will be tropped, but
d, ., is set so thot the smoller porticles possing though the bosin
will not couse significont obrosion domoge to the turbine.
For micro-hydro schemes the following procedure is
recommended for the selection of d,,.u:
r Low heod schemes, h < 10 m:
4,.n: 0.3 to 0.5 mm
o Medium head schemes. 10 m < h < 100 m:
d,,,, = 0.2 to 0.3 mm
r High heod schemes, h > 100 m
d,,, : 0.1 to 0.2 mm
where h is the gross heod.
The current proctice in Nepol is to use dr..., of 0.3 mm
regordless of the heqd of the scheme, which is somewhot
orbitrory. The opprooch outlined in this section is more logicol.
This is becquse for o given ponicle size, the higher the heod, the
more the domoge is to the turbine.
Th.4,-, ronge given obove os o function of heod ond
flow ollows the designer some flexibility in deciding the porticle
size to be settled.
J1ll tI I III z rrfI I
TT aII t vzv
1 _-Ternpelof--ilrn -C -7
r-//, .-/
2 7 7-
t o
aaoE=E.s3
e.Yoo l
oo l I lo looFo l l Vc loc i ty , In cent lnct r r pe lecond ( Rouse,1937 )
oo l o l rooo
Figun 5.2 Foll velocity of quortz spheres in woter
72
.II
ItIt
The following foctors should be used while deciding on
the volue of d,,.u:
o If most porticles ore highly cbrosive (quortz sond or
minerols), then the lower limiting volues should be used.
Ifthe pcrticles qre softer less obrosive substqnces, then
the higher limiting volues moy be occeptoble.r Crossflow turbines ore relotively less sensitive to soft
impurities such qs siit ond cloys. Other types such os
the Froncis turbines ore m0re sensitive to ony kind of
suspended motter. Pelton turbines ore intermediote.
r For exomple, d,,.u : 0.2 mm should be selected in q cqse
where: h = 50 m, suspended porticles are mostly pure
quortz or similor minerqls, ond o Frqncis turbine is
used.
5.3-4 SETruNG DESIGN
The oreo required for the settling bosin ond its plon shope ore
colculoted os follows:
1. Using the criterio discussed in Section 5.3.3, determine
what the ronge of the scheme is (i.e., low, medium or
high heod) ond decide on the corresponding minimum
porticle size to be settled, i.e. d,*,,.
2. Using Figure 5.2, for the selected d, n,,,, determine the fqll
velocity, w.
3. Colculote the required bosin surfoce oreo (A) using the
following equotion.
) i
A- -::w
Note thot o foctor of 2 hos been used to ollow for
turbulence in the bosin.
4. With the bosin qreo colculoted obove, fix either the
length, L, or the width, B, occording to site conditions
ond colculote the other dimension such thqt 4 < t/B <
10.
5. Check thot the horizontsl velocity (V
0.44 \q;, i.e. V < 0.24 m/s
=*," less rhqn
where d,,,, : 0.3 mm. If not, increose the cross sectionol
oreo (B or y) to meet this condition.
53.5 STORAGE DESIGN
The concentrotion ofsuspended porticles in the flow con be
expressed os lollows:
Concentrction (C) =kg of suspended motter
m3 of woter
Unfortunotely, there hove not been ony studies regording
the concentrotion of sediment in smqll mountoin rivers of
Nepol thot ore oppropriote for micro-hydro instollotion.
Therefore, in the Nepclese context, the designer hos to rely on
doto ovoiloble from lorge hydropower projects. The recom-
mended proctice in Nepol is to use C = 2 kg/m3 for the design of
settling bosins for micro-hydro schemes
The sediment storoge requirement in o settling bosin is
colculoted qs follows:
1. Colculote the sediment lood using the following equotion:
S , -o = QTCwhere:
S,*o : sediment lood in kg stored in the bosin
Q = dischorge in m3/s
T = sediment emptying frequenry in seconds
C = sediment concentrotion of the incoming flow in kg/m' .
A ressonoble emptying frequency (T) in the Nepolese
context could be obout once to twice doily during high floW
which results in less thon once q week during the low flow
seoson when the sediment concentrotion is low.
2. The next step is to colculote the volume of the sediment,
using the following equotion:
\l / _
- lood
' r e d r m e n t - S . X P -
oansnv tof,or
where:
V,.di..m = volume of sediment stored in the bosin in m3.
Sd"n,iry : density of sediment in kg/mr, obout 2600 kg/mr. Unless
other doto ore ovoiloble this volue should be used for So.*,r.
Prono, : pocking foctor of sediment submerged in woter.
When submerged in woter, porticles occupy mor€ spoce
thon when dry. This is meosured in terms of pochng foctor,
which is the ratio of unit volume of dry sediment to unit
volume of wet sediment (i.e. volume of 1 m3 of dry sediment
divided by the volume of this sediment when submerged).
Pocking fuctor for submerged sediment is obout 0.5 (i.e. the
volume of dry sediment is doubled when submerged).
Beiow the settling zone must be the copocity to store the
colculoted volume of sediment, \.ain.nt. This storoge spoce is
ochieved by increosing the depth ofthe bosin os follows:
t ioaoqa
-
Where Yuo,on.is the storoge depth in the settling bosin
below the hydroulic depth (y) discussed eqrlier, ond A is the
plon oreo. The hydroulic depth ond the storoge depth ore olso
shown in Figure 5.3.
53.6 COMPONENTS OFA SETruNG BASTN
The settling bosin hos three distinct zones; the inlet, settling
\/sedlment---;-
lt
i
i
i
\1l
1
It
Freeboord
TYPICAL CROSS-SECT lON
' tvPrcAL Lor{GrruotuL sEcrro}J I
lnlet zonc Sellling zonc Oulht zone
Freeboord
f low+
-!-
f l ow ' ,
N S.for.o99 zI
Figure 5.3 A typicol s€ttling bosin ond its components
ond outlet zones. These ore discussed below ond shown in
Figures 5.3 ond 5.4.
Inlet zone
This is the initiol zone where the tronsition from the heodroce
to the settling bqsin occurs ond there is o groduol exponsion in
the bqsin width.
The design of the inlet is importont to the efliciency of
the bosin. For high hydroulic efliciency ond effective use ofthe
bqsin, the inlet should distribute the inflow ond suspended
sediment over the full cross sectionol oreo ofthe settling zone.
Vorious reseqrch doto show thot horizontol velocity
voriotions qcross the width of q rectongulor tonk offect the
hydroulic efliciency considerobly more thon velocity voriotions
in depth. Therefore, ottention needs to be given t0 uniform flow
distribution in the horizontal plone. The following methods ore
used in the inlet zone t0 ochieve o good flow distribution:
o Grqduql exponsion of the iniet chonnel. This is the most
commonly used method in micro-hydro schemes. To
determine the length of the inlet zone, set the horizontol
exponsion rotio ot obout 1:5 (cr = 110) os shown in
Figurr 5.4. This will ollow on even flow distribution ot
the beginning ofthe settling zone. The verticol expan-
sion rotio con be higher ot qbout 1:2 (a = 27) os shown
in Figure 5.3.
o Another option is to incorporote o weir os con be seen in
the Golkot settling bosin (Drowing 420/04/3C01).
r ftoughs with slots or orifices in wolls or bottom.
. Bofile wolls
Note thot orifices or boffle wolls ore often used in woter
treotment focilities where extremely low velocity is required but
these methods ore rorely used in micro-hydro schemes.
In some schemes in Peru, o sliding gote is instolled in
front of the settling bqsin os shown in Photogroph 5.2. During
flushing, the gote is initiolly closed, impounding woter behind
it. When the settling bqsin is emptied, the gote is opened ond
the sudden rush ofthe impounded woter flushes out ony
sediment thot hos remqined inside the bosin.
a^
Fiqure 5 4 Exponsion ond controction rotio in s€ttling bosin
Settling zone
The b0srn rcoch€s the required width ot the beginning ofthis
zone. Pofticles or€ settled, stored ond flush€d in this zon€. The
length ofthis zone is longer thon th€ ir et or the outlet zones. It
should be noted thot long norrow bosins perfom better thon
shQft wLde bosins. A ronge of 4 to 10 is rccommended for the
r0 0 ofthe length Io width (L/B). Bosin shqpe con olso be
improved by subdrvision with q longitudinol divide wcll, since
thrs d0ubles the L/B rotio for q given bosin length. Also, the
longitudinol divide woll cqn ossist in the operotion ofthe
scheme. For exomple, the sediment in one sub-bosin con be
flushed while the oth€r is in operotion, producing holfthe
power 0utput. Without the subdivision, the pl0nt w0uld hove
to b€ closed during flushing.
Provision for flushing the stored s€diment should be qt
the end ofthe settling bosin. A floor slope of1:20 to 1:50 in the
settling zone focilitotes flushing.
Outlet zone
This forms the trqnsition from the settling zone to th€ h€odroce.
The tronsition con be more obrupt thqn the inlet exponsion (i.e.,
horizontolly 1:2 or P = 26.5"os shown in Figur€ 5.4, ond
verticolly 1:1 os shown in Figure 5.3). Note thqt ifthe settling
bosin is combined with the foreboy, then this zone is not
necessqry: the for€boy structure con be dir€ctly downstreom of
The operoting woter level of the settling bosin is gener-
olly contrclled ot th€ outl€t. som€times by o weir which moy be
design€d to operot€ 0s submerged in oder to conserve h€od.
53.7 FLUSHING ARMNGEMENTS
verticsl flush pipe method
There ore vorious woys ofremoving the stored s€dim€nt from
the settling bosin. An qppropriote method for micro-hydro
settling bosins is the'v€rticql flush pipe". This us€s o detoch'
oble venicol mild steel pipe over o hole in the bosin floor A
droin pipe is lued below the bosin floor to convey the flow out
of the bosin. when the verticol flush pipe is lifted, the w0ter
stored in the bosin ond the incoming 0ow olong with the
sediment ore droined through the hole. Aport from being
simple, th€ other odvontoge ofthis system is lhot it con spil l
some excess flow such os during floods when the wot€r lev€l in
Pno o 5 2 SIdrn9 gor p or \et lhng bosrn enl ionce, Peru
Figurp 5 5 nushino o settling bosin using the venicol flush pipe method
?5
the bosin is qbove the normol level. This verticol flush method
is shown schemoticqlly in Figurc 5.5. The colkot settling bosin
is bosed on this method os con be seen in Drowing 420/04/3C01
ofAppendix c- similorly, theJhqrkot micro-hydro scheme olso
uses this method for flushing os con be seen in Photogrqph 5.3.
Photo 5.3 Jhorkot settling bosin
The diometer of the flush pip€ is governed by the
following criteriol
o) overflow copocity
It needs to spill the excess flood flow thot enters the bosin os
shown in Figurc 5.6. This is governed by the weir equotion,
where the perimeter ofthe pipe is used for the length cs follows:
0" . : fI dC h^ .r1?
where:
Qn""d is th€ expected flood flow in the bosin
hn""dis the depth ofwoter obove the verticql pipe during
Qn*d This is the heighr between the top ofthe verticql flush
pipe ond the top ofthe settling bosin woll.
C" is the weir coemcient for o shorp edged weir, which is
1.9 (see Tqble 3.3, Chopter 3). The reoson for using the shorp
edged weir coefhcient is becous€ the pipe thickness is smollr^mnnrod r^ rh , h ' ^ ,1
In terms ofthe pip€ diometer, the obove equotion con be
rewritten os follows:0" .
/ i = 41.9nh_ 3i,
To ensure droining ofexcess flow ond to prevent spilling
ofthe design flow the height 0fthe verticol flush pipe should be
such thot the top lev€l is 50mm obove the design woter level.
Also note thot ifthe settling bosir is combined with the foreboy,
it moy be mole importont to size the flush pipe diometer such
thot it is oble to spill the design flow. This is becouse ifthe
turbine volve is closed during emergencies, the entire design
flow will hove to be spilled from the foreboy until the operotor
reoches th€ intoke or other control structurcs upstreom ofthe
forebola
b) Flushing cqpocity
The pipe should be obl€ to divert both the incoming flow ond
the woter volume in the bosin, thus emptying it. This is bosed
on the following equotionsl
l .s0. = c,c \6 + tL
or O. = CAril{6i9i
where:
Q.,in" is the design flow. q.,ir" is multiplied by 1.5 in the
first €qu0tion to ensurc thot therc is 0 drow down in the w0ter
Ievel inside the bosin during flushing {i.e., both the incoming
flow qnd the flow in the bcsin con be droined).
C is the orifice coefficient : 2.76 (oppli€s or y wh€re the
totol pipe length is less thon 6 m).
tL,t"is th€ depth ofwoter in the b0sin during the design
flow prior to flushing.
ho",n is the flushing heod when bosin is empty. This is the
diff€r€nce in level betwe€n th€ floor ofthe bosin ond the flush
pipe outlet os cqn be seen in Figurc 5.6
A is the oleo ofthe pipe section.
Th€ second €quotion ensures thot the design flow con be
dischorg€d through th€ system wh€n the b0sin is empry lt is
importqnt to check this condition especiolly ifthe hn",h is low.
Photo 5 4 Lifting the {lushing mec}onism 0hong)
76
In terms ofthe pipe diometer, the obove two equotions
con be rewritten os follows:
, - / 6a" ' . ' \ ' '"
- \ l lc.rG-+h /
^ . , - / 4 Q ' ' '
\ '" ' " - \ncVn I
Not€ thot these equotions 0ssum€ thqt there is free pipe
flow ot the outlet ond the plpe dtonteter is constont {verticolond horizonrol pipes ofthe system hove the some diometer).
All of the obove three equotLons should be used ro size the
drqmeter ofrhe flush pipe. The pipe should be siz€d using the
equotron rhot results in the lorgest diqmeter lfthe totol pipe
length is m0re thon 6 m, the flow should be colculoted using theguidelines given in Chopter 4.
Sluice gste
Another convention0l m€thod offlushing includes the use 0f
sluicing gotes. This is more common in minr- ond lorge
hydrcpow€r schem€s. In this system, gotes ore lifted either
monuol)y or mechonicolly, to droin the bosin. Th€ Solle
Chiolso mini-hydro scheme is bosed on such conventionol
flushing system os con be seen in Photogroph 5.6.
53.8 OTHER CONSIDERATIONS
Spillwsy requirement
Ifexcess flows con not be spill€d from the upstreom heodroce
portion such os du€ to lock of o suitoble oreo (or if o pipe is
used), 0 spillwoy should olso be incorporqted ot the settling
bosin. The spillwoy should be sized to spill the entire llow
expected during the high flow seoson. This is becous€ the plqnt
moy need to b€ shut during high flows for rrpoir work. The
spillwoy should b€ locoted upstr€om ofthe bosin to ovojd
excess flow (ond sedim€nt) through the bosin. Note thot the
design ofspillwoys w0s coveRd in Chqpter 4.
However, in the cose where there is o verticol flush pipe
sized to divert the expected high flows, o seporote spillwoy is
not necessory
Cover
Sometimes th€r€ con olso be site specific considerotions thot
need to be oddressed du ng lhe design ofthe settling bosin. For
€xomple, th€ Ghondruk sertlirlg bosin is locoted in o forest oreoqnd lorge tree leoves were constontly blocking the troshrqck.
This problem wos overcome by plocing wirc mesh over the
bosin os con be seen in Photogroph 5.7.
Phoro 5 6 Solleri Chroko serrhng bosin
Figure 5 6 venicol {lush pipe scction in o serrling bosrn
Photo 5 5 Sert lng bosrn or lhor l rot
77
7
Ploto 5 7 Chondruk serdrng bosin
The Golkot grov€l tropiprimory settling bosin is designed for q llow of455l/s. Noteth0t the gross heod ofrhe scheme (h)is 20m.
As grovel trop or y. the minimum dimension should be os follows:
crcss sectionol ol€o requircd for V = 0.6 m/s to trop porticle size down to 2 mm.
0 ' 0 .455A: - - - : = - =0 .758m2
v 0.6
With o flow depth = 0.5 m:
Width B = 0.758/0.5 = 1.52 m, soy 1.5 m.
Using L = 3 x heodroc€ conql width (B' = 0-6 m)= 1.8 m. Use 2.0 m minimum length.
Therefore ifthis structure werc designed hs o grovel trop only the dimensions would hove been os follows:B = 1 . 5 m
L = 2.0m
As o settling bosin, the dimensions r€quired ore os follows:
since 10 m < h < 100 m, the scheme is clossified os medium heod. Recoll thot the turbine is o cmssflow type. Therefore, d,-,: 0.3 mm.
With o meon river temperoture of15 0C during the high 0ow seoson. fiom Figup 5.2, the foll velocity w = 0.037 m/s for
78
rl .r, = 0.3 mm
LB = 2Q/w = 2x0.45510.037=24.6m2t
SetB = 2.5m
L = 24.61?.5 = 9.8 m, Set L= 10.0 m
LIB=+Inlet profile due to spoce constroints set o = 260,
B_B'I = _ --islet
2 ton(a)
2.5-{.6
(2 ton 260)
= 1,94 m. Set Lnr"t = 2.0 m
Check required depth ofsettling zone, y:
Msximum horizontol velocityv = 0.aa {Irr*
= 0.44i6-.3 = 0.24 m/s
a 0.445
" 'Y=Tt=--rE; ,T=0.76mSediment storoge r€quircment:
Assume sedimentconcentrotion,C = 2kg/mrg. = 2600 ko/m3qorny
P- = 0.5loaIor
Flushing frequency, T = 8 hours wos chosen for this scheme (but 12 hours is recommended). 8 hours = 28,800 s
S , * o = Q x T x C= 0.455 x 28,800 x 2= 26,208 kg
rr - Slooa
v sediment -
sd.nrny x Pfo.,o,
= 26,208 / (2600 x 0.5) =29.16 *3
Actuol bosin oreo = LB : 10 x 2.5 = 25 m2
Required storqge d€pth,Y,,o,on. = 20.16125=0.81 m
Requireddepthofbosin = Freeboord * Y * Yuo,n"= 0.3 * 0.76 + 0.81 = 1.87 m
Therefore, os con be seen in Drowing aZ0l0Al2C02 in Appendix C, the actuol internol dimensions of the basin sre os follows:
L : 1 0 . 0 msfiillng
B . = 2 . 5 mqruD9
79
Depthofbosin = 1.9mL** = 2.0 mLoou* = 1.25 m
Since the heodroce conol is long, o secondory settling basin has been incorporoted upstreom ofthe foreboy os con be seen in
Drowing 420/0413C01 in Appendix C. As con be seen in this drowing, the settling bosin hos the following dimensions:
L . : 7 . 8 msetutno
B*,,* = 2'4 m
Depth ofbosin = 1.7 m (ovJ
L,r., = 4.4 m including the weir length
Lou,r. = 0 m (outlet into foreboy)
Note the following:
Qesisn = 421 l/s in the secondory settling bosin/foreboy. Recoll from Chopter 3 thot the flow required for power production
wqs 421 l/s ond the heodroce conol wos designed for 455 lis to provide extro irrigotion woter.)
As discussed eorlier, o weir hos been incorporoted ot the inlet zone to ensurc on even distribution of flow. Since the settling
bosin is combined with the foreboy, the outlet zone hos been omitted. Also notice the submerged weir ot the end of the bosin
which controls the velocity through the bqsin and provides sediment storoge depth. Since the grovel trop is expected to
settle most of the sediment, there hos been o compromise in the rotio of L/B (3.25) in the settling bosin: in this cose the weir
ond porollel sides upstreom ofthe settling zone give o good flow distribution ocross the bosin.
As discussed eorlief, note the flushing orrongement where sediment is flushed by removing the verticol pipe. The sizing of
this pipe is os follows:
Since there ore o number ofspillwoys along the heodroce conol (upstream ofthe settling bosin/forebay), flood flow is not
expected. Therefore, the criterion is to ensure thot the flush pipe is oble to divert both the incoming design flow and the
woter volume in the bosin, thus emptying it during flushing
Check the flush pipe diqmeter using the following two equotions:
Note thot cs con be seen in the Golkot drowing $2010apC01) h*,,n = 1.3 m ond hnu,n :1.7 m
,_{ 6q.*n" l "d = \ R C . ,
= 0 . 4 1 0 m 0 r 4 1 0 m m
, - f 4Q. . " \ " 'd = t n111;- ,l
= o.rt6 m or 386 mm
Therefore, o diometer of 410 mm is required for the flush pipe.
The octuol flush pipe diometer thqt wos used for the Golkot scheme is 400 mm (slightly smoller thon colculoted). This wos
occepted becouse it motches the penstock diameter ond wos eosier to fobricote.
TheJhonke mini-hydro scheme is o rore exompl€ where it wos possible to combine the grovel trqp, settling bosin ond foreboyinto on€ structure os cor be seen in Photogroph 5.8 ond Figup 3.8 (Chopter 3). The intoke is locot€d ot the left bqrk of o widepool and there wos odequote spoce to combine qll three structures herc. Also, the topogrophy wos such thot it wos possible tostort the penstock olignm€nt right ot the intqke.
The grovel trcp is ploced ot the curved
section imm€diqtely behind the intoke.
The stroight s€ction behind the grovel
trop work os o settling bosin ond th€
tqnk behind this is the foreboy Since
the initiql penstock qlgnment is buriec
it cqnnot be seen in the photogrqph.
Also note tlot os discussed eqrlier, the
structure hos been divided into two
bosins so thqt th€ plont need not be
completely shut during flushing.
Plotforms hqve been incorporoted ot
the end ofthe grovel trop, settling
bqsin qnd obove the foEboy to
focilitot€ flushing os well os deoning
of the troshrock. The flushing system for both grov€l ond sediment is q modilicotion of th€ 'v€rticol flush pipe" method. As
shown in Figure 5.7, insteod ofo flush pipe o cylinder (top€red ot the bottom) is used which fits snugly into the hol€ on the
bosin floor. Since the woter depth is high, the cylinders ole lifted witl spindle wheels (thus gaining mechonicol odvortoge)thot rest on the slobs. However, note thqt with thls system, th€ excess flow cqnnot be diverted viq the cylind€rs since they oreclosed on top.
The troshrock qt the foreboy is cleoned by roking thrcugh th€
bors (flot plotes) with o speciql steel roke. To prevenr
vondolism th€ spindl€ wheels ore stor€d seporotely ond
instolled only du ng flushing. lnthe photogroph the
threoded ends (where the spindles ore insert€d)conbe s€en on
the grov€l trop ond settling bosin plotforms
Figure 5.7 nushing system ofjhoDke miln hydro
Photo 5 E Grovel trop, settling bosin ond for€boy ofJhonlae mini'hydro
n
8 1
5.4 Foreboy
5.4.1 GENEML
The foreboy ofo micro-hydro scheme serves th€ following
functions:
. It ollows for the tronsition from open chonnel to
pr€ssurc fl ow conditions.
. It regulotes th€ flow into the penstock, porticulorly
through the releose ofexcess woter into o spillwoy.. It releoses the surge pEssure os the wove trovels out of
thp npn(tn.k n inp
. It con qlso serve os o secondory/fnol settling bosin ond
trop some porticles thot enter the heodroc€ downstr€om
of the settling bosin.
. Although very rore in micro.hydro schemes, the foreboy
con olso provide woter storoge for use during peok
power demond period os discussed in Box 5.2.
Structurolly, the for€boy tonl is similor to the settling
bosin €xcept thot the outlet uonsition is reploced by o troshrock
ond the entronce into the penstock pipe
t i
Photo 5 9 A dry stone mosonryforeboy showing the connection with thepenstork
5.4.2 PIPE IJVEL
The foreboy ollows for th€ tronsition from open chollnel to pipe
flow by providing odequote submergence for the penstock pipe.
As discussed in Chopter4, ifthe submergence heod is nor
sumcient, the pipe will drow in oir ond be unoble ro convey the
design flow Similorly, r€coll from Chqpter 4 thot the minimum
submergence heod rcquired for the penstock pipe is os follows:1 qlrz
h > _i::' 2 9
whel€:
h, is the submergence heod, ond
V is the velocity in the penstock.
5.43 I'ESIGN OF A FOREBAY
If the length ofthe heodroce conol between the settling bosin
ond the foreboy is long. tlen sediment con enter the conol, such
os when debris folls from uphill ofthe heodroce olignment.
Similorly ifon eorth conol (or stone mosonry in mud mortqr)is
constructed between the settling bosin ond the for€boy,
sometimes high velocity in the conol, such os during the
monsoon, con couse emsion ond cqrry sediment to the for€boy.
In such coses the foreboy should olso be designed to sewe os o
secondqry settling bosin ond the design method used for sizing
o settling bosin should be used. However, o lower sediment
concentrotion (soy C = 0.5 kg/mr) con be used since onlyporticles thot hove escoped the s€ttliq bosin or those thot hov€
been eroded from the heodroce conol oIe exDected in the
foreboy
Ifthe heodroce upstreom ofthe foreboy consists ofHDPEpipe or ofcement mosonry conol ond the settling bosin is
functioning well, there will not be ony need for secondory
settling. Howeve! os o pr€coution, some storoge depth below
the pipe invert should be ollowed for. A depth 0f300 mm or
€quol to the pipe diom€ter, whichever is lorger is r€commended
for this purpose.
5.4.4 FOREBAY SIZE
The minimum size ofthe forcboy should be such thot o person
con get in ond cleon it. The minimum cleor width r€quircd for
this is I m. Even ifth€ sediment lood is not expected in the
foreboy, it moy sometimes reoch this structure such os when
the s€ttling bosin is filled in quickly during the monsoon or
there is 0 smoll londslide. lfo pe$on con get into the foreboy
ond deon it occosionolly or during the onnuol mointenonce
period,limited sediment occumulotion will not be o problem. A
storoge depth below the invert ofthe penstock should beprovid€d for this, os con be s€en in Figure 5.8.
lfpossible, the foreboy should olso be sized such thot 15
seconds ofthe design flow con be sofely storcd in the tonk
82
obove the minimum pipe submergence level. This is more
imponont ifthe scheme consists ofo h€odroce pipe insteqd ofq
conol. There con be smqll tronsient surges in the heodroce pipe
which r€sult in uneven flow. The 15 s€cond storoge copqcity
h€lps to bolonce such uneven flows.
0.6 m/s, but o moximum of 1 m/s cou]glgllgl-
It should olso b€ not€d thot the troshrockbors should beploced v€rticolly since horizontol bqrs ole dimcult t0 deon os
shown in Photogroph 5.11. The spocing between the troshr0ck
bors should be obout ho.lfthe nozde diomet€r for Pelton
turbines ond holfthe runner width for
crossflow turhine. This Prevents the
turbines from being obstructed by debris
ond minimises the chonces ofsurge.
Cl€qning ofthe troshrock con be
minimised by fixing it such thot it is
submerged during the design flow os in
th€ cose ofthe Soll€ri Chiolso mini-hydro
(Photogroph 5.12.). Here the top level of
th€ troshrock is below the d€sign woter
level. Any flooting debris such os leoves
orr woshed by the flow obove the
troshrock ond spilled viq the spillwqy
Although this type ofqrrqngement
focilitotes self-cleoning of the troshrock,
some 0dditionol flow (thon the design
flow) will be constontly required.
Photo 511 Cleoning con be d'fficult wirhhorizontol bors.
FigurP 5 8 ForPboy
5.4.5 TRASHRACK
The troshrock qt the foreboy should be plcced qt 1:3 slope for
both emcient hydroulic performonce ond eose ofcleoning (such
os by roking) os shown irl Frgure 5.8. To minimis€ heodloss ond
blockoge, the recommended velocity through the troshrock is
II
Photo 5.10 A cemenr mosonry chonnel ond foreboy ot the rop ofo st€ep dope (Dhoding)
83
7
5.4.5 SPilIWAY
As discussed eorlier, o spillwoy should qlso be incorporoted ot
the foreboy. The spillwoy should be sized such thot it con
releose the entire design flow when required. This is becouse if
the turbine volve is closed during emergencies, the entire design
flow will hove to be spilled from the foreboy until the operotor
reqches the intoke or other control structures uDstreom ofthe
foreboy.
5.4.7 GATE AND VENT
Incorporoting o gote ot the entronce of the penstock will moke
the mqintenqnce work of the turbine eosy. The gote con be
closed, thus emptying the penstock qnd work cqn be done in the
turbine. However, o ropid closure of this gote will creote o
negotive pressure (i.e. vocuum) inside the pipe ond could couse
it to collopse. Plocing qn qir intake pipe os shown in Figure 5.8
will prevent such o situotion since oir con be drown through
the oir intoke pipe ond into the penstock.
The required size ofthe oir vent is given by:
A 2 -
where:
d = internol diometer of oir vent (mm)
Q = moximum flow of oir through vent (l/s)= moximum flow of woter through turbine
E = Young's Modulus for the penstock (N/mm'z,
see Toble 6.2)
D = Penstock diometer (mm)
t.n.,iu. = effective penstock wqll thickness ot upper
end (mm) (refer to Section 6.6)
F = sofety fqctor,5 for buried pipe or 10 for
exposed pipe.
+(#lPhoto 5.12 Submerged troshrock, Solleri Chiolso mini-hydro scheme
Consider o 300 mm steel penstock of 3 mm woll thicknessconnected to o turbine thot con toke 250 lis. Thepenstock is obove ground.
Q = 250 l/sE: 2.0 x 105 N/mm'z(from Toble 6.2)D : 3 0 0 m mt = 3 m mt.r..tiu. = 7.27 mm (from Section 6.6)F : 10 for obove ground pipe
0r, d = 80 mm, i.e. the minimum internol diometer of
the oir vent should be 80 mm.Photo 5.13 0verflow weir for the senling bosin otJhorkot
84
Th€ d€sign flow ofthe 50 kW Ghqndruk micro hydro scheme is 35l/s but the dry seoson flow is 0nly 201/s. Hence during th€dry seoson the power output wos obout 39 kW untll o p€qkrng reservoir wqs bullt in 1994. Such q peqking reservoir b€comenecessory becouse ofthe demond for firll power (50 kW) ln the !'rllage during the morlings ond evenings. Th€re is nominolpower demond rn the ofternoon ond even less du ng night time.
A suitoble site for the reservoir wos iocoted on the te[oce immedrote]y downstreqm ofthe old foreboy. Photogrophs ofthepeoking reservoir dudng cnd ofter construction con be seen below.
The wolls ond the floor o[the reservoir were constructed ofstone mosonry in ceme[t mortqr. The reservolr hos been sized suchthot it cqn provide the design flow ol35l/s for ot leost six hours (3 h0urs in the morning ond 3 houn in th€ evening). Thecolcuiotions ore os followsl
Storoge volume required - (D€sign flow - dry secson flow) x 6 (hr ) x 60 (min/hr) x 60(s/min)= (35 20) x 6 x 60 x 60 - 324,000 litres 0r 324 mr.
Hence o reservoir wrth o minimum storoge copocity ofl24 mr is r€quired to b€ qble t0 provide 50 kW for su hours. The octuoldimensions ol the reservoir ore qs follows:. Length = 20 m
. Width = 20 m
. Depth = 1.2 m
Hence, the st0roge volume is 480 mr, obout 48rl0 lorger thon lhe minimum required voiume. Note thot th€ old foreboy hosnow bec0me redundont. Also, since the peoking reservorr is downstreom 0fthe old ibreboy, o ferv metres ofheod orc lost.This is cOmpensoted by slightly increosing the dcsign flow
Any sedrment deposifed in the res€rvoir is monu0lly cleoned du ng the onnuol moint€nonce period. A flushing focility wosnol instolled becouse 0fp0tentiol erosion ond londslide problems due to the lqrge volume ofwoter involved.
At preselt the power plont is shut when there is n0 demold for po',ver, then the reservoir is o]lowed t0 fill.
Ph0to 5 i4 Chondruk peohng reseruoir dudng construcrion Pho, 5.15 Chondruk ppoh. lg rcseryoir o l lpr con.rrucrron
8 5
5.5 Construction of woterretoining structures
Once the size ofthe grovel trop, settling bosin qnd foreboy hove
been colculoted, the type qnd dimensions of the wolls ond floors
need to be determined. For micro-hydro schemes, stone
mosonry in cement mortqr is generolly the most opproprioteqnd economic option. The construction detoils ond procedures
for this type of structure ore os follows:
o The ground should first be excovoted occording to the
bosin shope qnd then be well compocted using o
mqnuol rom.
o Since these qre woter retoining structures, 1:4 cement
sond mortor should be used for the wolls ond floors qs
discussed in Chopter 4.
r The wolls should be built such thot they ore o minimum
of 300 mm thick ot the top ond increose with depth os
shown in Figure 5.9. Note thot in this figure, the woll
surfoce 0n the woter retoining side is verticql. This
increoses the stobility ofthe structure since for o
cOnstont depth the woter pressure is Iorger thon the soil
pressure. Ifthe verticql foce is towords the soil, the
woter volume in the bosin will increose but structurol
stobility will be slightly reduced.
o The internol surfoce (woter retoining surfoce) ofthe
wolls ond the surfqce ofthe floor should be plostered
using 1 :3 cement sond mortor to o thickness of 12 mm.
This significontly minimises the l ikelihood of seepcge.
r Finolly, the wqlls ond the floor should be cured os
discussed in Chopter 4.
Another option is to use reinforced concrete for the floor
ond wolls. However this is more expensive ond olso requires
skilled lobour, so is not generolly recommended for micro-hydro
schemes.
5.5 Chechlist for grovel trop, settlingbosin ond foreboy work
r Con the grovel trop, settling bosin ond the foreboy or ot
leost two of these structures be combined together?
o Are these structures locoted such thqt excess woter con
be spilled sofely, without cousing erosion or stobility
problems?
r Is the settling bosin sized such thot the emptying
frequency is once to twice doily during high flows? Also,
does d,uun correspond t0 the heqd ond turbine type?
Refer to Section 5.3.3.
o Is secondqry settling required ot the foreboy? Is the
foreboy lorge enough for mqnuol cleoning ond is o
spillwoy incorporoted in this structure? Hos the
submergence heod been checked?
r Once these structures hove been sized, refer to Section
5.5 for the construction detqils.
lsoomtnn.iilf
Stone mosoni n ' l :4 cen ien lrDr to r
Compocted eorth
l2 inm th ick o losterl :3 cement morfor
figure 5.9 Wolls ond floors ofwoter retoining structures
86
5. Penstocks
6.1 Overview
A penstock is o pipe thot conveys the flow from the foreboy tothe lurbine. The penstock pipe stqrts wherc the ground profileis steep os shown in Photogrqph 6.1.
Phoro 6l Penstock olignm€nr ofthe 36 kWJhorkot micro-hydro scheme,Mustong, Nepol
The potentiol energy ofthe flow qt the foreb0y isc0nverted into kinetic energy ot the turbine vio th€ penstockprpe. Since the flow is conveyed under prcssure it is importontfor the pipe design to be sofe. Coses hove be€n reported whelethe penstock pipes hove burst. Since the pensrock is on steepground slopes, such pipe burst con instqntoneously couse
londslides ond other stobility problems. Furthermorc, penstock
instollohon is ofren chollenging ond requires sofe ond cqEfulwork os shown irl Photogroph 6.2.
Photo6.2 P€nnock o lig nment of the 5r0 kw Borpo} micrD-hydro scheme,C,orkho, Nepol
The penstock pipe usuolly constitutes o significontportion ofthe totol micm-hydro construction cost. Therefor€ itis worthwhile optimising the design. This irvolves o cor€fuIchoice of: pipe moteriol, such os mild steel or HDPE; on economi-col diqmeter such thot the heod loss is within occeptoble limits;ond woll thickness so rhe pipe is sofe for the design heod ondony surge effect thot moy result from sudden blockoge oftheflow.
6.2 Selection of the penstock clignment
6.2-1 SrTE WORK
Selection ofth€ penstock oliglment ot site should be bosed onthe following criterio:
87
r
Fottbsy fio{.otion
The penstock storts ot the foreboy, for which locotion criterio
ore given in Section 5.1.3. In oddition, the foreboy locotion
should be chosen to optimis€ the lengths ofh€odroce ond
penstock whilst ochieving the required power output from the
sch€me. Penstock pipe is generolly more €xpensive thon
heqdrqce conql, thereforc in most coses th€ for€boy locotion
should be chosen to give the minimum penstock length.
How€ver, sometimes o longer penstock moy be economic, to
ovoid the need for the heodroce to crcss 0n unstoble sloD€.
Procticol ground slope
An ideol ground slope for the penstock olignment is between l:1
ond 1:2 MH). The flotter the ground slope the less economic is
the penstock since o longer pipe l€ngth is r€quir€d for o low€r
heod.
Although o ste€p slope minimises the penstock length, it
will be difficult to.monuolly loy the penstock, construct suppon
pi€rs ond onchor blocks ifthe slope is greoter thon 1:1. There-
fore, for penstock olignments on slopes steeper thon 1:1, the
Photo 6-3 Excovotion to rEduce the cost of the p€nstock ond reduc€ the need fol
oncho$ (Siklis)
odd€d site instollqtion cost moy outweigh the sovings mode on
the pipe costs.
Avoid o penstock pmlil€ thot storts ot o gentle slope ond
then becomes steepe! becouse ofthe risks ofnegotive surgeprcssures cousing sub-otmospheric pressurc. See Section 6.5.
For micro-hydro schemes with l€ss thon 20 kW of
instqlled copocity, the ground prof e ofthe p€nstock olignment
cqn be meosured using on Abney Level os discussed in Miclo-
hydro Design Monuol (Ref l). For lorger micro-hydro schemes.
the use ofo theodolite ond o pmfessionol surveyor is r€com-
mended. This is becouse ifthe pRfobricot€d b€nds do not frt ot
site due to survey efiors, odditiono] cost ond time will be
required to omend these, especiolly ifthe sit€ is locoted for fmm
the roodheod ond the pipes ore flonged. Note thot som€ slight
odjustment con be mode ifthe pipes ore w€lded ot site.
Errors in the design heod colculotion (due to survey
elron)will result in eith€r oversizing or undersizing the electro-
mechonicol units, which will olso incrcose the project cost,
either in terms oflost power production or in €xtro cost for the
oversized units.
Minimum numfur of D€nds
Bends increose the heodloss ond require odditionol onchor
blocks. Th€r€forc the selected olignment should be os stroightqs possible, both in plon ond elevqtion. Note thot smoll bends
con be ovoided by vorying the support pier heights for the
exposed section ond the trench depth for the buried section.
Spoce for powerhouse qr"s
The chosen oligrment should be such thot it is possible to
construct o powerhouse ot the end of the penstock. A river
terroce w€ll obove the flood l€vel is ideol for the powerhouse
oreo. A route thot is otherwis€ suitoble for the penstock
olignm€nt but do€s not ollow for the construction ofthe
pow€rhous€ is inopprcpriote.
Stsbihty
since th€ penstock olignment is on steep ground slopes ond the
pipe is under pressure, it is importont for the olignment to b€
on stobl€ grcund. Any gmund movement cqn domoge the pip€,
support piers 0nd onchor block, qnd in cose ofpipe bursts
unstoble slopes will couse further emsion ond londslides. slope
stobility is discussed in detoil in chopter 9.
88
Photo6.4 Penstock instollotionis oft€n chollenging ond ftquir$ sole ondcorcful work
Other site qncifrc conditions
Aport from the obove criterio. there moy be other site specilic
conditions thot dictote the p€nstock olignment. For €xomple, if
the olignment cmsses o locol troil, this section should either be
buried or high enough obove the grcund such thot people ondcottle cqn wolk undemeoti.
Th€ Jhonlce mini-hydro penstock olignmenr is on
exomple where o site specific condition govemed the penstock
olignment. Th€re is cultivot€d lond between the intok€ ondpowerhouse ofthis scheme, so the penstock wos oligned mostly
olong the edge ofthe culrivoted lond. At on€ section this wosnot possible ond the olignment hod to troverse the cultiv0ted
fields. Since it wos not possibi€ ro bury the pipes ot this section
{due to downstr€om olignmenr), o few ofthe support piers were
sized to be 2 m high qs shown in Phorogroph 6.5. This rcsultedin q cleor spoce ofobout 2.5 m under the penstock, which
ollows formers ond cottle to w0lk undemeqth.
6.2.2 PROFII,J OF THE SELECTED ALTGNMENT
Bosed on the site survey. o plon ond pmfile ofthe penstock
olignment should be plepored ot the design office os follows:
The ground profile should firsr be drown using on6<-
oppmpriote scole. Some scqle should used for bothhorizontol ond verticol lengths so thot the bend onglesore true ongles, which minimises the likelihood ofermrs. Ifthe olignment olso hos horizontol bends, theno plon view should qlso be pl€por€d to show horizontol
bend ongles.
Once the grcund prcfile hos been prepored, the penstockpipe should b€ drown on it such thot the number ofbends is kept to o minimum. In g€nerol for oboveground olignment the support pier height should beminimised unless some ofthem need to be incnqs€d toovoid smoll 0ngl€ bends. Similorly. excovotion shouldbe minimis€d for the buried section unless deepertftnch€s or€ r€quired ot short s€ctions to ovoid smoll
ongle bends. Optimising the olignment will requiresome iterotions. An exomple ofo penstock profile isshown in Figur€ 6.1.
For obove ground penstock sections, o minimum ground
cleoronce of300 mm is r€commended ro keep the pipe
dry ond for ease ofmointenonce such os pointing.
For buried penstock s€ctions, o minimum soil cover of1
m is r€commended os in the cose ofHDPE heodroce pipe,
ond th€ trcnch detoils should be similqr to those shownin Figure 4.8 (Chopter 4).
Photo 5.5 ttnrtock olignmenr high obove th€ ground to 0llow oc(ess for peopleond (otrle, Jhonkl? mini-hydro
89
Trorhrock
nd lrvrl
mo3onrY lnl:.1 c.nont mortsr
3OO min. round c l rorcncr
d 3 mmlh l ck m i l d r t cc l p rn r toc t
Ponrhouse
- 2 O 2 4 6 m
Sco lc
io in l
A nc ho rbloc k
Figun 6.1 'l)rpicol penstock prohle
6.3 Pipe m0tefi0ls Peru (see chopter 10, Innovorions) cnd Sri Lqnkq, but hqs
not yet been used in Nepol. Toble 6.1 compores these three pipeIn Nepol the most commonly used penstock pipe moteriols ore moteriols.
mild steel qnd HDPE. Rigid or unplosticised PVC (uPVC) is
onother option thot hos been used in other countries such qs
lioble 6.1 Advontcges ond disqdvontoges of different penstock moteriols
MATERIAL OCCURRENCE ADVANTAGES DISADVANTAGES
Steel Most common o Verv widelv ovqiloble o Heovy, tronsport cost con be higho Pipes con be rolled to olmost ony size o Rigid, bends hove to be speciolly fobricoted oto Con go up t0 olmost ony thickness workshop
o Eosy to join ond con withstond high r Hos corrosion problems
pressure r Cqn be expensive
o Con hove high surge requirementHDPE Foirly common r Does not corrode o Diflicult to join (solvent not ovoiloble)
o Light ond hence eosy to tronsport r Avoiloble in discrete diometers, moximumo Flexible (occommodates smoll bends) diqmeter ovqiloble in Nepol is 315 mm OD.o Low surge requirement o Must be buried (due to ultro violet (W) ond
thermol degrodotion) ond corefully bockfilled.
Limited pressure rotings ovoiloble in Nepol (up to
10 kg/cm'Zwhich is 100 m heod)
More expensive thon mild steel for lorge diometers
ond high pressures
90
PVC common in
other countries
but not y€t used
in Nepol
Does not conode
tight
Eosy to instoll (solution ovoiloble
tojoin pipes)
Brittle, con b€ domoged during tronsportotion
Must be buried (due to W ond thermol
d€gr0dotion) ond coEfully bocldilled.
Unsuitoble in fl€ezing conditions
Not ovoilobl€ in diometers lorger thon 250 mm in
Nepol
Limited pr€ssure rotings ovoilobl€ in Nepol (up to
10 kg/cm'z = 100 m heod)
More expensive thon mild ste€l ot high pressures
The decision os to which pipe moteriol to use for the
penstock con be bosed on Toble 6.1, esp€ciolly in Nepol. When in
doubt, it is recommended thot the design€r undenoke prelimi-
nory designs for oll pipe moteriols ovoiloble ond compore the
c0sts.
To minimise costs, for long penstock olignments HDPE
pipes con be used for the upstreom length where the heod is
Ielotively low (see Box 6.1). Stondod couplings orc ovoiloble tojoin HDPE ond mild steel pipes os shown in Photogroph 6.6 0nd
Figure 6.2.
Photo 6 6 HDPE-mild neel coupling Note thqt exc€pt for rhe finol lenqrh. rheHPDE pipe isburied,Jhong micro-hydro scheme, Mustong, Nepol
Although steel pipe for micro-hydro in Nepol h0s
normolly been speciolly monuf0ctured locolly, stondord steelpipes moy be ch€oper in some cqses. Detoils ofsuch pipes olegiven in Appendix B.
6.4 Pipe diometer
Orce the penstock olignment ond pipe moteriol hove b€en
decided on, the design involves choosing the diometer ond pipe
thiclaress. Selecting on opprcpriote pipe diometer is discussed
in this section ond the woll thickness is discussed in Section 6.6.
Note thot with o few exceptions th€ sizing ofthep€nstock diometer is similor to thqt ofo heodroce pipe dis.
cussed in Chopter 4. For simpliciry the entip penstock diom-
eter selection Drocess is included in this section.
Choos€ o pipe size such thot th€ veiocity, V is between
2.5 mF ond 3.5 m/s. In gen€r01, o v€locity lower thon
2.5 m/s results in on uneconomicolly l0rg€ diometer
Similorly, ifthe velocity exceeds 3.5 m/s, the heodloss
con be excessive ond hence uneconomic0l in the long
run due to loss in pow€r output. Furthermore, higher
velocities in the p€nstock will rcsult in high surge
pressure os will be discussed loter.
Note thot compored to the heodroce pipe, higher
velocities con be ollowed in the penstock pipe since it
conveys sediment fite woter
For steel penstocks, it moy be economicol to
choose the diometer so thot ther€ is no wostoge fiom
stondord size steel sh€ets. For HDPE or PVC. ovoiloble
sizes must be selected. Pipes ole normolly specilled by
outside diomete! so 2 times woll thickness must b€
subtroct€d to obtoin the intemol diqmeter Stondod
pipe siz€s orc given in Apperdix B.
Colculote the qctuol velocity:
Figure 6 2 Typicol HPDE-mild steel pipe coupljng
4 it, _ --::-' - nd ,
9l
I
r t 2
where:
V is velocity in m/s.
Q is design flow in mr/s.
d is the pipe internol diqmeter in m.
Colculqte the heodloss in the pipe length bosed on the
inlet, woll friction, bends, volves ond exit losses os
follows:
Totol heod loss = wqll loss * turbulence losses
Wqll losses ore colculoted qs follows:
First determine the roughness volue,'k'in mm from
Toble 4.3 (Chopter 4).
Then use the Moody Chort in Figure 4.10 (Chopter 4) to
find the corresponding friction foctor ffor the selected
pipe moteriol, diometer ond the design flow.
The woll loss con now be cqlculoted from either ofthe
foilowing equotions:
LV2h = f - ^r"woll loss d X 29
"'
. f L x Q 'n ="woll loss
l}ds
furbulence losses ore colculoted os follows:
1 " -turD loss
t K + K . + K + K . ). entronce ueno conlrocuon votve,
where loss coefficients, K, ore os shown in Toble 4.4.
4. In generol ensure thot the totql heod loss for the design
flow is between 50lo ond 100/o of the gross heod, i.e.95o/o
to 90olo penstock efliciency.
5. Ifthe heod loss is higher thon 10%o ofthe gross heod,
repeot colculotions with lorger diometer. Similorly, if
the heod loss is less thon 50lo the pipe diometer moy be
uneconomic, therefore repeot colculotions using smoller
diometers.
Note thot in exceptionol coses o less efficient penstock
moy be more economic, such qs when the power demond is
limited, the penstock pipe is long qnd there is qbundont flow in
the river even during the low flow seoson. In such coses, o
higher flow con be qllowed in o smoller diometer pipe ollowing
o higher heod loss, which is compensoted by the flow. Hence
sovings con be mode in the cost ofpipes os discussed in Box 6.1.
However, this opprooch should be justified by o detoiled
economic onolysis.
29
The 80 kW Bhujung micro-hydro scheme (Bhujung, Lcmjung, Nepol) designed by BPC Hydroconsult for Annopurno Conservo-tion Areo Project (ACAP) is currently under construction. The design dischorge ofthe scheme is 150 l/s, the totol penstock
length is 860 m and the gross heod is 104 m. Since it is o long penstock, HPDE pipes ore used for the initiol length ond mildsteel pipe for the downstreom end os follows:
PENSTOCKTYPE IIIICT{NESS lmmf3
315 mm diometer. Closs III HDPE 16.1
300 mm diometer, mild steel 3
300 mm diometer, mild steel 4
Totql heodloss
% heodloss
Note thot the totol head loss is obout 120lo: though more thon 10%0, in this cose o higher heodloss wos found to be economic.
This is becouse the estimoted power demond for the villoge is 80 kW ond the source river (Midim Kholo) of the scheme hos
significontly higher flows, even during the low flow seoson (minimum flow of 0.5 m3/s in April) thon the required design
dischorge.
92
If the penstock pipe diometer wos sized for less than 10% heodloss (i.e. by increosing the diometers cnd decreasing the design
dischorge such thot power output = 80 kW), the pipe cost including loying ond tronsportotion would hqve increosed by 15%.
Similorly if mild steel wos used for the entire olignment (for heodloss = 72o/o), the pipe cost would hove increosed by about
30026. Note thot settling bosin ond hesdroce costs need to be included in the optimisotion.
6.5 Surge colculotion
5.5.1GENERAL
The thickness of the penstock pipe is determined by the gross
ond surge heods of the scheme. It is therefore importont to hove
some understqnding ofthe c0ncept ofsurge before colculoting
the pipe woll thickness.
A sudden blockoge ofwqter or ropid chcnge in velocity in
the penstock (or ony pipe thot hos pressure flow) results in very
high instontoneous pressure. This high pressure is known os'surge' pressure or often referred to os "woterhommer". Surge
pressure trovels qs positive ond negotive woves thrOughout the
length ofthe penstock pipe.
Wqter hommer occurs os the surge wove trqvels lrom the
source 0r the origin ofthe disturbonce, olong the pipeline until
it strikes some boundory condition (such os q volve 0r other
obstruction) ond is then reflected or refrqcted. Ifthe pipe is
strong enough to withstond the initiol surge effect, the pressure
will ultimotely dissipcte through lriction losses in the woter
ond pipe woll os well os through the foreboy. The speed of the
surge wcve (wove velocity) is dependent on such foctors os the
bulk modulus of wqter, flexibility of the pipe ond the rotio of
pipe diometer to woll thickness.
ln hydropower schemes, positive surge chorocteristics
ore different for different types ofturbines. Surge heod colculo-
tions for the two most common turbines used in micro-hydro
schemes qre discussed here. Note thqt these colculotions ore
bqsed on the initiol (i.e. undompened) positive surge heod.
In proctice there will be some domping of the surge
pressure os the wove trovels olong the pipe, ond whilst the
pressure fluctuotion is uniform in the lower portion it dimin-
ishes groduolly t0 zero ot the foreboy, os shown in Figure 6.3.
However, the pipe is normolly designed for stqtic heod plus
constont positive surge over the full penstock length.
Note thot the negotive surge con produce dongerous
negotive (sub-otmospheric) pressure in o penstock if the profile
is cs in Figure 6.3. Once the negotive pressure reoches 10 metres
the wqter column seporotes, ond subsequent rejoining will
couse high positive surge pressure sufficient to burst the
penstock. Sub-atmospheric pressures less thon 10 metres cqn
cquse inword collopse of the pipe wqll, so should olso be
ovoided. Ifthere is ony possibility ofnegotive pressure the pipe
wqll thickness must be checked for buckling (see Section 6.6.2).
To ovoid negotive pressure, move the foreboy to Point A
in Figure 6.3. Alternotively toke meqsures to reduce the surge
pressure.
"Bursting disc" technology could provide o reliqble meons
ofsofely releosing excess heqd in cose ofsurge pressure without
increosing the pipe thickness (which is the convention). This is
discussed in Chopter 10.
Figur€ 6.3 Surge pressures
6.5.2 PELTON TUNBINE
For o Pelton turbine use the followino method to colculqte the
surge heod:
1. First colculote the pressure wcve velocity 'o'using the
equotion below.
1M0m/s
f{elwnere:
E is Young's modulus in N/mm'z. The volue of Young's
modulus for mild steel. PVC ond HDPE con be seen in
Toble 6.2.
d is the pipe diometer (mm)
t is the nominql wqll thickness (mm), Dot t.n.,iu.
tL
93
2. Then colculote the surge heod (h,,*"), using the following
equotlon:
where:
n is the totol no. of nozzles in the turbine(s).
Note thot in o Peiton turbine it is highly unlikely for
more thon one nozzle to be blocked instontoneously.
Therefore, the surge heqd is divided by the number of
nozzles (n). For exomple if o penstock empties into two
Peiton turbines with two nozzles on eqch turbine.
n = 4
The velocity in the penstock (V) is:
. , 4Qv - -
no'
3. Now colculqte the totol heqd:
h : h + hlotol grc1s surge
4. As o precoution, cqlculote the criticol time, T., lrom the
following equotion:
T. = (21)/o
where:
T, is the criticol time in seconds,
L is the length of penstock in m,'q'is the wove velocitv colculqted eorlier.
lf the turbine volve closure time, T, is less thon T,, then
the surge pressure wove is significontly high. Similorly, the
longer T is compored to T , the lower the surge effect.
Note thot this colculotion is bqsed on the ossumption
thot the penstock diometer, moteriol ond wqll thickness ore
uniform. If ony of these porometers vory, then seporote
colculotions should be done for eoch section.
Also note thot when the T = T,, the peok surge pressure
is felt by the vqlve ot the end ofthe penstock. lfo pressure
gouge is not instolled upstreom ofthe volve, o volve closure
time of ot leost twice the criticol time (i.e., T > 2T") is recom-
mended.
The design engineer shouid inform the turbine monufoc-
turer of the closure time (T) so thot if possible the monufocturer
con choose the threod size ond shoft diqmeter such thot it will
be dillicult to close the vqlve in less thqn twice the colculoted
closure time. The operotor ot the powerhouse should be mcde
owore of this closure time ond the consequences of ropid volve
closure.
If the gross heod of the scheme is morc thon 50 m, it is
recommended thot o pressure gouge be ploced just upstreom ofthe volve. Compored to the cost of the turbine ond thepenstock, the cost ofsuch o device is low (obout US$50 in Nepol)
ond is worth the investment. When the operotor closes or
opens the vqlve, his speed should be such thot there is no
observqble chonge in the pressure gouge reoding.
6.5.3 CROSSFLOW TURBINE
In o crossflow turbine, instontoneous blockoge ofwoter is notpossible since there is n0 obstruction ot the end of the monifold(i.e. crossflow turbine hos o rectongulqr bore opening insteod of
o nozzle). Therefore, surge pressure con develop only ifthe
runner vqlve is closed ropidly.
For o crossflow turbine use the followinq method to
colculqte the surge heod:
1. Cqlculote the prcssure wove velocity 'c' (using the sqme
equotion os for Pelton turbine).
2. Now colculote the criticol time l, similor to the Pelton
turbine cose:
r. : (zr)/o
3. Choose o closure time, T (in seconds) , such thqt: T > 2T "
Similor t0 the Pelton turbine cose, the design engineer
should inform the turbine monufocturer of the closure
time (T) ond the operotor ot the powerhouse should be
mode owqre of this closure time.
4. Now cclculote the porometer 'K' using the following
equotion:
K: IColculote surge heod by substituting the volue of'K' in
the equotion below:
h 'u* ' = [ ; '
If 'K'is less thon 0.01 (i.e. closure time (T)is long
enough), then the following simplified equotion con olso
be used:
hru*, : hnr*{ K
Note thot ifthe vqlve is closed instontoneously, the entirelength ofthe penstock will experience o peck pressure os
o v lsurge g n
*i*r-l'
v.l
follows:
h,u,r. : ov/g (i.e., some os in the cose 0f Pelton turbine
with one nozzle).
However, in proctice it wiil take 0t ieost five to ten
seconds for the operotor t0 close the volve, therefore in o
crossflow turbine instontoneous surge pressure is not o
problem.
If the gross heod of the scheme is more thon 50 m, q
pressure gouge should be ploced upstreqm 0fthe volve to
control its closing/opening speed, os in the cqse ofo Pelton
turbine.
6.5.4 QUICK METHOD FOR SMALL SCHEMES
WITH CROSSFI.OW TURBINES
For smoil micro-hydro schemes using crossflow turbines (such
os milling schemes) where the power output is less thon 20 kW
ond the gross heod is less thon 20 m, this quick method moy be
used.
Add20o/o to the gross heod to qllow for surge heod, i.e.
h,u", : 1.2 x hq,.,. This results in o more conseryotive volue for
the surge heod but its contribution t0 the increqse in the
thickness would be insignificont since the h0.,, is iow.
6.6 Pipe wall thickness
6.6.1 POSITTVE INTERNAL PRESSURE
Once the surge heod hqs been determined, the nominql woll
thickness (t) con be colculoted os follows:
1. If the pipe is mild steel, it is subject to corrosion ond
welding or rolling defects. Its effective thickness (t.o..,,u,)
will therefore be less thon the nominol thickness.
Therefore, for mild steel, ossume q nominql thickness (t)
ond to colculot€ t.,T,,,,u, use the following guidelines:
o) Divide the nominql woll thickness by 1.1 to ollow
for weldina defects.
Divide the nominol woll thickness by 1.2 to ollow
for rolling inoccurocy ofthe flot sheets.
Since mild steel pipe is s_ubject to qoryo1ion,
for 10 yeqlr ofplont life: subtrocl 1 mm onq:_
for 20 yeors of plont life: subtroct 2 mm
The recommended uenstock desion life is 10 veors for
-lehemes up t0 20 kl^L+s yeors fo!$b9!Sgsa&9l9.IyLsld20-yeors for schemes of 50-100 tE.f!g!e_!S!-nes-mql.be odiusted -olglsygqgryfglonolys is.
For exomple the effective thickness of o 3 mm thick mild
steel pipe designed for o 10 yeors life is:
3t _ = - - _ 1 : 1 . 2 7 m meuec l rve
1-1 x 1 .2
From this exomple it is cleor thot if o mild steel pipe used,
the nominol woll thickness (t) should be qt leqst 3 mm.
Note thot this does not opply for HDPE pipes: their
effective thickness is the nominol woll thickness of the pipe. A
low temperoture c0rrection foctor moy opply to PVC pipes, refer
t0 the pipe monufqcturer: if the temperqtures ore sub-zero,
t"n".,iu" froy b€ os low os 0.5t. Aport from protection from ultro-
violet degrodotion, this is onother reoson t0 bury PVC pipes ot
high oltitude.
2. Now colculote the sofery foctor (SF) from the following
e0uoti0n:
2 0 0 x t x S5 f =
h,u,o, X d
where:
t,r.,,,u" is the effective thickness ond d is the internol
diqmeter of the pipe. Note thot some units (m or mm) should be
used for both t.n"oiu. ond d since they concel out in the obove
equotion.
S is the ultimote tensile strength of the pipe moteriol in
N/mm2. Volues of S ond other useful porometers ore shown in
Toble 6.2.
h,o,o, is the totql heod on the penstock os follows:
h ,o to , : hg . r r+h ru * .
3. For mild steel or PVC pipes:
IfSF < 3.5, reject this penstock option ond repeot
colculotion for thicker wolled option. However, SF > 2.5
con be occepted for steel pipes ifthe surge heod has been
colculoted occurotely ond sll of the following conditionsqre met:
o) There ore experienced stoffot site who hove
instqlled penstock pipes of similor pressures ond
moteriols.
b) Slow closing volves qre incorporoted ot the
powerhouse qnd the design is such thot o sudden
stoppoge ofthe entire flow is not possible.
Domoge & sofety risks ore minimol. For exomple
even if the pipe bursts, it will not couse londslides
or other instobility problems in the short run.
Coreful pressure testing to totol heod hos been
performed before commissioning.
b)
c,
d)
I,lr-
95
for f lrJt t DtDes:
HOlf pipes ore qvqiloble in discrete thicknesses bqsed on
the pressure rotings (kg/cm'z) 0r stotic heods. The designer
should set SF > 1.5 ond cqlculote t.r.,,u" (tot€ thot t : t.r.,,iu" f0f
HDPE). Then from the monufocturer's cotologue the qctuol
thickness should be chosen such thot it is equol to or lorger
thon the colculoted t.'.,,u,. Thc Sofety Foctor should then be
checked using the octuql thickness. For HDPE pipes, it is
recommended thot the Sofety Foctor olways be ot leost equal
to 1.5.
6.6.2 NEGAIIVE INTERNAL PRESSURE
Check the pipe woll thickness for buckling ifthe negotive surge
con produce negotive internol pressure in the pipe. N0te thot
the negotive pressure must not exceed 10 metres heqd, see
Section 6.5.1. The shope ofthe negotive surge pressure profile
Toble 6.2 Physiccl chqrocteristics of common mqteriols
connot be occurotely determined: ossume it is horizontol in the
lower half of the penstock, ond diminishes groduolly in the
upper holfto zero qt the foreboy, see Figure 6.3.
In order to provide on odequote foctor ofsofety ogqinst
buckiing, the minimum pipe woll thickness is given by:
/ p D t o l l
t ^ > d l ' ^ lerr€((ve - \ze I
where:
t"n.tiu. is the effective pipe woll thickness, mm
d is the pipe internol diqmeter, mm
F is foctor of sofety ogoinst buckling (2 for buried penstock ond
4 for exposed penstock)
P is the negotive pressure, N/mm'z(10 m heod = 0.1 N/mm'z)
E is Young's modulus for the pipe mqteriol, N/mm' (from Toble
o .z l .
MATERIAL YOUNG'S
MODULUS lEf Nfmmz
COEFFICIENT OF UNEAR
EXPANSION lctlfC
ULTIMATE TENSII^E
STRENGTH (S)Nfmm'z
UNIT WEIGHT lylkNlm'
Steel (ungroded)
Steel to 15226175
or IS 2062/84
PVC
HDPE
2.0 x 10s
2.0 x 10s
2750
1000
12.5 x 10 {
12 .5 x 10 -6
{ 2 0 - 6 0 ) x 1 0 *(140 - 240) x 10 {
320
410
3 5 - 5 5
20 -35
77
77
14
9.3
lfthe steel quality is uncertain it rs besr b ask for samples and have them independently tested at laboratories. Properties of PVC and HDPE vary
considerably: they should be confirmed from manufoctures' catalogues or by laboratory tests.
The requined doto for the design ofthe Golkot penstock ore os follows:
. Q = 421 l/s (colculoted in Exomple 4.2)
t hnror, = 22m
r two verticol bends, n : 200 & 420, both mitred.r Penstock moteriol: uncooted mild steel, 35 m long ond flonge connected.
r turbine type: crossflow
Refer to Drowing 42010413A01in Appendix C for the ground profile ond bend ongles.
Pipe dicmeter cqlculation
S e t V : 3 . 5 m / s
Colculote the internol pipe diometer:
96
d =- V n V { [ x 3 . 5
Calculote woll loss:
From Table 4.3 choose k = 0.06 mm for uncooted mild steel.
k 0.06
d =
391 =0.00015
1.2Q 1.2x0.421_ : _ = t - . 2 ,
d 0.391
f = 0.013 (Moody Chort, Chopter 4)
LVz 35 x 3.52h = t _ = O O l ?-'wolr ross dxag 0.391 x 29
h*o,, tor, = 0'73 m
Inlet loss:
K,n,*n.. = 0.5 for this case (Toble 4.4)
- V, 0.5 x 3.52h,nln lorr
= K.n,.n..X -;- = L-
= 0.31 mzg zg
Note thot Exit loss = 0 since the flow at the end ofthe penstock is converted into mechonicol power by rototing the turbinerunner.
For mitred bends. from Toble 4.4
0 = 220, \.no = 0.11
0 =420 , \ . no=0 .21
Bend losses = (0.11 + 0.21) * T'- = 0.20 mzg
Totol heod loss = 0.73 m + 0.31 m * 0.20 m= 1.24 m
1.24% heod loss =
;;- x 100 %= 5.60/o < l0% OK.
Although the colculoted pipe diometer wos 391 mm internol, Drowing 4}olo4l3cozin Appendix C shows the outside pipediometer to be 388 mm, i.e. internol diometer 388 - 2 x 3 = 382 mm. This wos chosen to correspond to o 1200 mm stondodplote size (1200/n = 382). In proctice, however, the monufocturer proposed 400 mm internol diometer pipes for the somecost, becouse this corresponded to the plote size thot he hod.
Pipe woll thickness cslculqtions
Colculote the pressure wove velocity 'o'
1440
E : 2.0 x 105 N/mm'zfor mild steel (Toble 6.2)
97
v
d : 4 0 0 m mt = 3mm
14400 r o :
-*(-rttno-,-ro_r,J6 - \ 2oro = 923 m/s 3
Now colculote the criticol time:
2L 2 x35T. :; =
Sr3 : 0.08 s. Note thot it would be
impossible to dose the volve in the powerhous€ in 0.08 secondsl
Choose closu€ time T = 10s > 2T. = 0.16s
-:[-'*-l t.**-lorK = 0.003. Since K is less thon0.01
h*r. : hn^,, x 6K = 22 no.oo3orh = 1.20 m
h . = h + h = 2 3 . 2 mq6 snr!.
The pipes were monufoctured by welding (1 .1) rolled llat ste€l
plotes (1.2). 1.5 mm hos been subtrocted to ollow for ot leost 15
yeqrs of lif€.
t.-". = 3/(1.1 x 1.2) - 1.5 - 0.Z/ mm
Now check the sofety foctor:
2 f f i x1 . xs
h . x d
S : 320 N/nunz for ungroded mild steel (Toble 6.2)
2@x0-nx32OS F =
23.2x 400
or SF : 5.3 > 3.5 OK.
Not€ thot the sof€ty foctor is higher thqn required but the
minimum recomm€nded thicleess for flot rolled mild steel pipe is
3 mm.
The Golkot p€nstock olignment before ond ofter pipe instollotion
con be se€n in Photogrophs 6.7 ond 6.8 r€spectively.
Photo 6.E Penstock olignment, colkor
Photo 6.7 Excovotion for penstock olignment, Colkot
98
The required dota for the design of the thonlcre penstock are os follows;r Q = 4 5 0 U st hn*r, = 180 m
. ten verticol bends, 0 = 690 , 230, 260,310,400, 20, 30, 120, g0 & 30, all mitred.r Penstock moteriol: mild steel, flot rolled ond site welded, 550 m long. High quolity steel plotes were bought ond tested for
tensile strength ot the loborotory. Minimum tensile strength, S = 400 N/mm':wos ensurcd through the tests.r furbinetype3PeltonturbineswithZnozzlesineochturbine,thereforen = 3x2 = 6.
Colculqte the required pipe dicmeter qnd woll thickness. Note thot since the penstock is long, it will be economic to decreosethe thickness ot lower heqds.
Pipe dicmeter cqlculation
Since the pipe is long set V = 2.5 m/s to minimise heodloss.
Colculote the internol pipe diometer:
. fT tux0-150-d : \ ' / n i =
J I I - 25 =o '479m
Colculote woll loss:
From Toble 4.3 choose k = 0.06 mm for uncooted mild steel.
k 0.06
d 479
1.2Q 0.450
o 0.479
f = 0.0014 (Moody Chort, Figure 4.7)
LV2 550 x 2.52h : f - = 0 0 1 4"worr ross d x 29 0.479 x2g
h . : 5 . 1 3 mwon loss
Inlet loss:
Kun,,on., : 0.2 for this cose (similor to fourth entronce profile in Toble 4.4)
vz 0.2x2.5'zh . . = ( x - - - : -
rnre( ross enrron(e zo 29h . . = 0 . 0 6 m
lnlel loss
Exit loss : 0.
For mitred bends, interpolote from Toble 4.4:
for0 = Of ,q"o = O.:e
f o r 0 = 2 3 0 , \ . n o = 0 . 1 1
f o r 0 : 2 € c , K o . n o : 0 . 1 3
for 0 = 37r, eno: 0.18
for0 = 4or , \ *no = o.2o
99
for0 = 20,\.*= 0.02
fo rO =30 , l f und=0 .02
for0 =120, l tnd=0.06
fo rO =80 , l q .nd=0 .04
fo r0 =30 ,Q"o=0 .02
Bendlosses = (0.34 + 0.11 + 0.13 + 0.18 + 0.20 + 0.02 + 0.02?-52
+0.06 +0.04 +0.02)* U
=0.36m
Total heqd loss = 5.13 m + 0.06 m * 0.36 m- \ A m
5.6% heod loss = -:-- x 10070 = 3.7oh <5c/0,
180
Therefore, the diometer can be mode smoller. The odopted diometer of theJhonlce penstock is 450 mm, which gives 4.10lo
heodloss, thmugh o repeot ofthe obove colculotions.
Pipe woll thickness cclculotions
First colculote the thickness required 0t the downstreom end of the penstock (i.e. h,,0,.. = \*, = 180 m) using d = 450 mm.
Tryt = 6mm
0ro =
oro=1071 m/s
40 4 x 0.450V = -i: --:------- = 2.83 mls.
ndz zx(0.450)'?o v 1
h - _ x _surge g n
1071 x 2.83 1i . - - - - = 5 2 m"rurg.- 9,8
^ 6
h . = h + h : 1 8 0 * 5 2 = 2 3 2 mrdot qrcss surle
6t _ = _ _ 1 . 0 = 3 . 5 5 m meilectrve
1.1 x 1.2
(1.1 for welding, 1.2 for flot rolled, qnd 1 mm for corrosion sllowonce: the corrosion allowance is less than previously recom-
mended for lorger schenres becouse Jhonkre wcs designed to provide construction power to o lorger project).
Colculqte the sofety foctor:
2 0 0 x t - x Seilcdtve
SF: -_-----.-n . x 0
rotol
200 x 3.55x 400
232x450
.(-**u1
100
SF = 2.72 > 2,5, olthough SF is less thon 3.5, it is occeptoble in this case since:
1. There were experienced stoff at site. The site staff hod instolled penstock pipes in vorious other micro-hydro projeas.
2. The volves ot the powerhouse ore of slow closing type.
3. The pipes were pressure tested os follows:
Tensile test of steel plotes wos performed ot o loborotory ond on ultimote tensile strcngth of 400 N/mm'z wos ensured os
mentioned eqrlier.
Rolled pipes were pressure tested ot the workshop ot h,o,or using o hydroulic pump'
Finolly, the pipes were olso pressure tested on site sfter installotion by simuloting h,u*. ot the entronce (foreboy) using o
hydroulic pump.
4. The olignment wos ossessed to be foirly stoble. In cose of pipe burst it wos not expected to instontoneously cause
Since the Jhonkre penstock is long, to optimise the design, it wos decided to decrcose the pipe thickness ot lower heods {i.e.,
upstreom) using the some sofety foctor (SF).
Colculotions of the stqtic heod ot which the penstock thickness con be decreased by t mm (i.e. thickness = 5 rnm) using the
some sofety foctor (SF = 2.721ore os follows:
t440n = : = i 0 2 7 m r S-
l,-l z-Eqrqg_\Jt ' t -ZTxlT'xT/
Note thot t = 5 mm in this case
V = 2.83 m/s, (some Q & d)
ov l 1027 x2.83 ih - - x - = - - := - X - - =49m- - 5 u r s e o n 9 . 8 6
)t - = - 1 . 0 = 2 . 7 9 m m€lrecrve 1.1 x 1.2
2 0 0 x t - x s€IecItve
\ t s = - -h . x d
I0 t0 l
or rewriting this equotion in terms 0f h,o,ori
2@ X t"o..,,""X SL _ -r r lo to l -
SFxd
200x2.79 x400^ - k = 1 8 2 mvr 'froror -
2.72x 450
h = h - h = 1 8 2 - 4 9 : 1 3 3 mqroJs to(01 surg€
Therefore the pipe thickness wos reduced to 5 mm ot o stotic heod of 133 m inJhonlcre, keeping the some foctor of sofety (i.e.
2.72\ osshown in Figure 6.4. The Jhonkre penstock olignment for the lost section con olso be seen in Photogroph 6'7. These
calculotions were repeoted for lower stotic heads ond o wall thickness down to 3 mm hos been used to reduce the cost.
101
Photo5.9 JhqnlsE mini.hydro pensl ock olgnment
qPe,
t tur b incp6ntlock
Figurp 6.4 JhoDkp mini-hydm penstock olig nment ot downstreom end
between the flonges for tightness ond to prevent leokoge. Th€
colkot penstock (Photogroph 6.8) is offlonge connected type.
A comporison ofthese two methods oJong with generol
rccommendotions ore Dr€s€nted in Toble 5.3.
5.7 Pipe jointing
6.7.1 GENEMI.
Individuol mild steel penstock pipes con bejoined ot site by two
conventionol methods, nomely site w€lding ond vio flonges.
Eoch ofthese methods hqs its own odvontoces ond disodvon-
toges os discussed in Toble 6.3.
6.?.2 Sm WEU)ING
This involves tronsporting q welding mochine ond diesel or
petml to site, then joining the pipes by welding together the
ends os shown in Photogroph 6.10.
6.73 FI.ANGE CONNECIION
This involves welding flonges (thot hov€ bolt holes) ot both ends
ofthe pipes in the workshop, thenjoining them 0t site by
bolting th€m together A rubb€r gosket should be ploced
Photo 6.10 site welding ofpenstock pipes, Jhonla€ minihydro
102
Toble 63 Comporison between site welding ond flonge connection
PIPEJOINING
METHOD
ADVANTAGE DISADVANTAGE GENEMI. RECOMMENDAIIONS
AND COMMENTSSite welding Eosy to fobricote ot
workshop since flonges
do not hqve to be welded
ot pipe ends.
A properly welded pipe
will not leqk ond requires
less mointenonce.
Higher degree ofprecision work requiredqt site to weld the pipe ends. Improper
welds con couse leoks cnd pipe burst othigh heods.
Need to trqnsport o welding mqchine
ond 0 generot0r ot site. Also requires
supply ofpetrol/diesel to site.
Diflicult logistics if the site is more
thon o doy's wolk from the rood heod.
Generolly not economic for smoll
schemes ond/or short penstock lengths.
Select this option only ifthe site stoff
ore experienced, site is less thon o doy'swolk from the roodheod ond penstock
length is more thon 50 m.Flonge
connection
Eosy to instqll qt site.
Site instollqtion work
involves plocing o gosket
between the flonges ond
hn l t inn thpm
Fqbricqtion cost is high since flonges
need to be welded ot ends. Also there issome wostoge since the flonge isprepored by removing the centrol disc of
o diometer equol to the externol pipe
dicmeter.
The pipe o\ignment ond the bends connot be odjusted qt site.
Con leok if the bolts qre not well
tightened or if gaskets ore of poor quolify.
Higher risk ofvondolism since the bolts
con be removed.
Flonge connection is oppropriqte for
schemes thqt ore locoted more thqn odoy's wolk from the roodheod ond/or
hove q relotively short penstock length.
Minimum flonge thickness should be
ot leost twice the penstock wo.ll
thickness or 8 mm whichever is lorger.
A minimum bolt diometer of t2 mm is
recommended.
A minimum gosket thickness of 5 mm
is recommended.
Should be obove ground.
6.7.4 HDPE AND PVC PIPES
For HDPE pipes the best method of joining them is by heot
welding os described in Chopter 4 (Box 4.7). Aithough speciol
flonges ore ovoiloble to connect HDPE pipes, they ore gener-
olly more expensive thon the cost incurred in heot welding
them. HPDE pipes ore ovoiloble in rolls for smoll diometer (up
to 50 mm) ond for lorger diometer they ore ovoilqble in
discrete lengths (3 m t0 6 m in Nepol)
PVC pipes with smoll diometer (up t0 200 mm) hove
socket ot one end such thot onother pipe con be inserted
inside ofter opplying the solution ot the ends. Lorger
diqmeter PVC pipes ore joined with o couplet which is o short
pipe section with inside diqmeter equol to the outside
diometer of the pipes to be joined. The solution is opplied on
the connecting surfoces ofboth the coupler ond the pipes ond
thenjoined together.
6.8 Pipe lengths
Mild steel pipes con be mqnufoctured ot the workshop in qlmost
onylength required. PVC ond HDPE pipes ore ovoiloble in fixed
lengths (3 m t0 6 m in Nepal). Although, shorter pipes cre eosy
t0 tronsport, odditionol costs will hove to be incurred in joining
them ot site (more flanges or welding work). it should be noted
thot, unlike cement bogs, onimols (mules ond yoks) do not
usuolly corry penstock pipes becouse of the shopes ond lengths
involved.
Sometimes, due to the weight involved the only option
for trcnsporting the generotor qnd turbine to remote site is by o
helicopter. In such cqses, it moy be possible t0 tronsport the
penstock pipes in the some trip becouse the current tronsport
helicopter ovoiloble in Nepol con corry up t0 three tons
(depending on oltitude). The combined weight of the generotor
snd turbine hordly ever exceeds one ton ond the helicopter
103
chorge is dependent on the flying hours ond not on loods.
When this is the cose longer pipes {up to 6 m l€ngths) con be
tronsport€d to site qnd hencejoints con be minimis€d.
Recommendotions for pipe lengths und€r vorious
conditions oIe discussed below:
MiId steel pipe
The following foctors should b€ consider€d while sizing mild
steel pipes.
1. In generol pipes long€r thon 6 m should not be morlufqc-
tured since they wjll b€ difficult to tronsport 0n trucks.
2. lfth€ pipes ne€d to be corried by porters from the
roodhe0d, the weight should be such thot on individuol
length con be c0rried by 1-2 porters. For exomple, ifthe
pipe weight is obout 50 kg, usuolly one port€r con co y
it. Similorly two poners moy b€ oble c0rry up to 90 kg.
Therefore, ir is optimum t0 size pip€s occordilgly,
esp€ciolly ifthe penstock length is long ond the site is
locoted more thon o doy's wolk from the ro0dheod.
3. For flot rolled pipes the monufocturing costs will be less
ifthe pipe length rs o multiple ofth€ 0voiloble steel plote
width. For exomple if pipes ore rolled from 1.2 m wide
plotes,lengths 0f1.2 m,2.4 m 0r3.6 m etc. wil l lower
monufocturing costs.
HDPE an.l PvC pipes
As mentioned eqrlier, these pipes ore monufoctured in the
loctory qt f ixed lengths. but they con be cut in holfor one third
ofthe length for eose oftronsportqtion. However, o PVC p'pe
with 0 socket ot one €nd should not b€ cut since IejOining wil l
not be possible without o specicl co)lor The following foctors
should be considered while determining the length ofHDPE 0nd
PVC pipes.
L in Nepol the moximum ovcilcble length of these pipes is
6 m Even if longer pipes become ovoiloble, such lengths
should nor be used for micro-hydro sch€mes. Gen€rolly
it is eosier to corry two 3 m pipes rother thon one 6 m
pipe ofthe sonre type.
2. lfthe prpes need to be c0rried by porters from the
roodheod, then the crit€rio outl ined in No 2 for mild
steelolso opply.
6.9 Exposed versus buried penstocl(
HDPE qnd PVC prpes should alwoys be buried. This minimises
lherm0l movemenr o r rd p ro tec ts the p ipe oqo ins t lmpoct ,
vondolism ond ultro-violet d€gr0dotion
Flonged steel pip€ should be obove ground. This is
b€cous€ the goskets moy need to be repioc€d durrng the life of
the scheme.
Mild sreel penstock with welded joints con be either
buried or obove ground. However, mointenonce ofburied pipe
is difncult. therefore the originol pointing ond bocktrlling must
be c0refully supervised to ensure thot corrosion does not reduce
the l ife ofth€ penstock.
Sometimes port ofth€ penstock olignment moy be oboveground ond pon buried. In such coses. it is best to moke the
tronsition ot on onchor block, otherwise coreful detoiling is
required. An exomple ofsuch detoiling ot the tronsition is the
use of o retoining mosonry woll with 0 l0rger diqmeter mild
steel pipe through which the p€nstock comes out ond con
occommodote thermol exp0nsion ond controction, see Figure
6.5. An exponsionjoint should normolly be used immediqtely
downstreom ofthe retaining woll. Not€ thot the design ofqnchor b,ocks is covercd in Chopter T.
Toble 6.4 compor€s the 0dvontoges ond disodvontoges of
buried penstock pipes.
Phoro 6ll P€nstock, Purong
r[
104
Tobl€ 5.4 Advontoges qnd disqdvqntqges ofburied penstock pipe
ADVANTAGES DISA"DVANTAGES
Protects the penstock ogqinst odverse €ffects 0f
temperoture vonoll0ns.
Protects the woler irom lieezing due to low 0lr
tempetotures.
Protects the pipe from folling d€bris ond trees.
Prorects the pipe from t0mpering 0nd vondollsm.F l i m i n n r o . c , , n n ^ d n i a r (
Smoll bends do not need onchor blocks.
Does not chqng€ the londscope.
Pip€s or€ less 0cc€ssible for rnspection, ond foult frnding
becomes dimcult.
Repoir ond mointenonce ofthe pipes is dif l icult.
Instollotion is exp€nsive in rock ond where soil cover is thin
Improcticobl€ on steep slopes (>30").
F.gule65 I ronsr ' .on f tomLuned topx|ovdppn,to, l ' ,Jhonkrtmrnr l "ydrc
5.10 Expansionjoints
Penstock pipes ore subjected to t€mp€roture vo qtions due to
chonges in the ombient temperoture. When the ombient
temperotur€ is high the pipes wiJl expond ond when it drops,
the pip€s will contr0ct. Such th€rm0l exponsion couses str€ss€sin th€ pipes ifthey ore not free to expond.
Photo 6 l2 An exponsionjoinr should b€ locoredjust below ononchor block ioprotect the block from fon€s whr(h it rnoy nor be designed to rpsNt (S*tis)
For buried pipes, o minimum cover of 1 m should be
provided in ollcoses (i.e. HDPE, PVC ond mild steel pipes) See
Iigure 4 8 Ibr trench detoils.
Buried pipes do not require support piers, ond he sovings
m0de 0n the pi€rs moy equol or even exceed the cost ofexcqvo-
tion ond bockll l l . Since this ts o site specific c0s€, q c0st
colculotion should be done ifbuned mrld steel pipe is being
considered.
Both €xposed 0nd buried p€nstock pipes Iequire onchor
blocks ot significont bends. However, for relotively low heod
ond flow, qs well os smollbend ongles, lhe I m depth of well
compocted sorlcover on buried pipe moy be odequote (see
Chopter ?, Anchor blocks ond support piers).
The norure ofthe terroin ond the sotldepth moy olso
govern whether to bury 0r expose the penstock pipe. Buried
penstock is not pr0cticoble on roures steeper thon 30o b€couse
the bocl1il l wil l be unstoble Where topsoil is thrn or rock is
exposed, the costs involved in excovoting the rock moy mqke
buriol ofthe pipe impossrble
105
rAn qbove grcund penstock is subjected to gr€oter
temperotuE vqriotions rcsulting in high€r thermol exponsion.
The thermol exponsion or controction is high€st when the
penstock is empty, such os during instollotion or repoir work.
The temperotur€ voriotion is relotively low when the pipe is full
since the flow ofwoter witl foirly constont temperoture
prcvents the pip€ ftom ropidly heoting up.
As long 0s pipes ore free to move ot one end, thermql
exponsion does not cous€ odditionol strcsses. However, o
penstock pipe section between two qnchor blocks is kept fixed
0t both ends. In such o cose thermol exponsion could couse
odditionol stresses ond the pipe con even buckl€. Ther€fore,
provision must be mode for the penstock pipe to expond ond
controct, by instolling on exponsion joint in o penstock pipe
s€ction betw€en two onchor blocks.
The most common type of exponsion joint used in Nepol
is ofsliding type. This is shown in Figure 6.6 ond Photogroph
6.13. Such on exponsionjoint is ploced between two cons€cu-
Figure 6.6 Sliding type expo$ionjoint
tive pipe lengths ond bolt€d to them. The stoy rings orc
tightened which compresses the pocking ond prevents leoking.
Jute or othff similor type of fible is used for pocking. When the
pipes expond or controct, the chonge in lengths is occommo-
doted insid€ th€ joint section since there is o gop between the
Prpes.An odvontog€ ofon exponsionjoint is thot it r€duces the
siz€ ofthe onchor blocks since they will not need to withstand
forces due to pipe exponsion. Another ddvontoge is thot they
con 0ccommodote slight ongulor pipe misolignment.
Exponsion joint rquirements for vqrious penstock
conditions ore discussed below.
Mild steel pipes
An exponsiorjoint should olwoys be incorporoted imm€diotely
downstrcom ofthe forebcy ond immediotely downstreom of
eoch onchor block, for both obove ground qnd buried steel pipe.
One is olso recommended immediotely downstrcom ofo
tronsition from buried to obove ground pipe.
HDPEPiPfs
Exponsionjoints orc not necessory for HDPE penstock pipes
pmvided thot they ore buried (which should qlwoys be the
cose). This is becouse HDPE pipes ole flexible ond con bend to
occommodote the expqnsion effects due to the differences in
temperqture b€tween instollotion ond operotionol phoses.
PVC pipes
PVc pipes with gluedjoints require provision for exponsion, ot
the some locotions 0s for steel pipes.
Sizing of expsnsion joints
The sliding surfoce of the exponsion joints should be mochine
fi shed (such os in o lqthe mochin€) to o toleronce of obout I
0.1 mm. The recommended thickness ofthe steel pofts (Etqiner
ond stoy ring)is qbout twice the thiclaless ofo well-designed
penstock pipe,
The gop in the exponsionjoint should be obout twice the
calculoted moximum pipe exponsion lergth.
The moximum exponsion length is co]culoted using the
following equodon:
A = cr{t -T ..)L
where:
A L = pipe exponsion length in m os shown in FiguR 6.7.
o = coefficient oflineor exponsion in m/m "c ofthe pipe.
which depends on the pipe moteriol. This coemcient r€lotes to
the length thot q moteriol will expond per 1oC increose of
temperoture. Different moteriols expqnd ot differcnt rotes. The
106
Photo 5.13 Slidng exponsion joint, Jhonlxe mini_hydro
volues of this coe{Iicient for mild steel, HDPE ond PVC ore shown
in Toble 6.2.
Tno, = highest temperoture in'C thot the pipe will experience.
Note thot this con even be during mid-summer qfternoon when
the pipe is empty (either during instollotion or repoir wor$.
T,o,o = lowest temperqture in'C thot the pipe will experience.
This cqn be during winter when the woter temperoture is just
obove the freezing point. Note thot iffreezing temperotures ore
expected, the pipe should either be emptied or provision should
be made for constont flow. If the woter in the penstock
stognqtes during freezing temperoture, ice will form inside the
pipe ond could burst it, becquse when wqter freezes, the volume
exponds.
L = pipe length in m.
Since it moy be difficult to determine when the expon-
sion joint wiil be instoiled ot site, the monufscturer should be
qsked ollow on exponsion gop of 2AL. Then, during instollo-
tion, the temperoture should be noted ond the gop left occord-
ingly.
Exomple 6.3 shows on opplicotion of this equotion.
figure 6.7 Thermdl exponsion ofo penstock pipe
5.11 Pointing
Since mild steel pipes ore subjected to corrosion, oppropriote
coots ofpoint should be opplied before dispotching them to site.
Proper pointing of mild steel pipes significontly increqses their
useful lives.
The pipes should be sond blqsted ifpossible, otherwise
they should be thoroughly cleoned using o wire brush qnd o
piece ofcloth. Prior to pointing, the pipe surfoce should be
cleqn from oil, dust ond other porticles. When opplying
subsequent coots ofpoint, the previous coot must be dry. .The following coots of point ore recommended:
Ou*ide swfsce of obove ground mild steel pipes
First two coots of primer should be opplied on the pipe surfoce.
Red Oxide Zinc Chromote primer is qppropriote for this purpose.
Then onother two coots of high quolity polyurethone enomel
point should be opplied on top of the primer.
Outside surfoce pipe of which will be buried 0r cost into
onchor blocks'lwo coots of primer similor to qbove ground pipe should
be opplied. Then, onother two coots othigh-build bituminous
point should be opplied over the primer. Provide on extro coot
of bituminous point ot tronsition qreos, which ore more prone
to corrosion (see Figure 7.1).
Inside surfsce ofpipes
For smoll diometer pipes it moy not be possible to point the
inside surfoce. However whenever possible, the inside surfoce
should be pointed with two coots of good quolity red leqd
primer.
A mild steel penstock pipe is 45 m long betrveen theforebay ond the first cnchor block. The steel temperotureduring instollotion wos 40"C, ond the expected lowesttemperotur€ during the operotional phose is 40C duringwinter. Whot exponsion gop should be recommended to
the monufocturer? AIso, if the temperoture duringinstollotion is 2ffC, whot gop should be provided?
a = 1 2 x 1 0 { m / m o CTno, = 40 oC
T . . : 4 o Cc0ld
L = 4 5 mAL = u(\",-\",u)Lo r A L = 1 2 x 1 0 { ( 4 0 - 4 ) x 4 5or AL = 0.019 morAL - 19mm
Therefore minimum recommended exponsion gop= 19.4 x 2 = 38.8 mm, soy 40 mm.lf the temperoture during instollotion is 2dc
AL = 12 x 10 -5(40 - 20) x 45or AL = 0.011 morAL = 11 mm
Therefore, during instollotion qn exponsion gop of 11
mm x 2 = 22mm should be provided.
107
If therc is o doubt obout the quolity ofpoint, the suppli-
er's speciflcotions should be checked prior to its use. Note thotpointwork is not requiEd for HDPE or PVC pipes.
Any pointwork domoged during tronsport ond instollo-
tion must be mod€ good, so thot the full number ofcoots ispRsent everywher€. This is especiolly importont for bu ed
DiDes.
6.12 Instqllqtion
The following procedure should be used.
o The centreline ofthe penstock should be s€t our using q
cord ond pegs olong the selected route os shown in
Figuft 6.8. For micro-hydro schemes obove 20 kW of
insto]led copociry o theodolite should olso be used to
ensuR thot the bend ongles comspond to the fqbricoted
oioe bends.
4i#
Figurp 68 Sstthg out the centrEline ofthe p€nstock olignment
A line should be morked by spEoding lime on the
surfoce ofthe gmund t0 pploce the cord. Then thepositions ofondror block ond support piers should bemorked t0 the r€quiftd spocing for exposed pipes ondexcovotion corried out olong this line os l?quil€d.
For buried pipes, the penstock is instoll€d in the
excovoted trench ond bocldrlled os shown in Fioure 4.8.
The bocldll should be rornmed in loyersond o slight hump obove the level of theground helps to keep the olignment dryAn improperly bocldlled penstockoligment con quickly become theroute for droinoge woter down thehillside. However, note thqt bocK lshould be completed or y ofter the pipehos be€n pressure tested.. For exposed pipes, the onchors ondsupports should be consuucted os willb€ discussed in Chopter T. The pipeshould be cost into the onchors ondploced on one support pier ot o time.No further supports or onchors shouldbe built until the pipe is secured to theprevious onchor block or suppon pier
For both site welded ond flong€ connected pipes, the
end should pmtrude from the lost support block with
odequote morgin (- 300 mm) so thqt either the flonge
or the weld line does not lie on the support pier during
thermol expqnsion or controction. If mor€ thon one
pipe section n€eds to be welded between the supportpiers, temporory supports should be used os shown in
Photogroph 6.15. Flonge connected pipes should bejoined ond the bolts tightened os the instollotion
Progresses.
l
Photo6.15 ltmporory support for sit€ v{elding worhJho_Dhe minihydro, Nepo.l
.108
Photo 6 14 Penstod ot Cbondruk with villqge in the bqckground
The instqllqtion of the penstock should stort
lrom the mochine foundqtion ond proceed upstreom.
This qvoids ony misolignment between the penstock
ond the turbine housing. Since the turbine needs to be
firmly fixed to the mochine foundotion, there is olmost
no toleronce at this end qfter the mqchine foundotion
hos been constructed. Furthermore, the pipe sections
below the exponsion joints con slide down if instollo-
tion proceeds downstreom from the foreboy. Minor pipe
deviotion ccn be odjusted ot the foreboy wqll, but such
odjustment is not feosible ot the mochine foundotion.
For micro-hydro schemes, loying of penstock in discrete
lengths is not recommended since this cqn leod to
misolignments of the pipes.
r Penstock pipes should be pressure tested 0t the foctory
before tronsport to site. For schemes where the heod is
more thon 15 m the completed penstock should olso be
pressure tested during the commissioning phose. lf
feosible such pressure test should include the surge
heod (i.e., pressure test ot hror..). This con be done by
simuloting the expected surge heod ot the foreboy
using o mqnuol pressure purnp. If ony leokoge is
noticed, the section should be repoired such os by
tightening the bolts, chonging foulty goskets or
welding. For buried pipe olignment, the bockfill should
only be completed ofter successful pressure testing;
however, if there ore ony minor bends without qnchor
blocks, these must be bockfilled before pressure testing.
once the pipe trench is bockfilled, it will be difficult ond
time consuming to re-excovote ond identify the leoking
sectlon.
6.13 Mointenonce
Above ground mild steel penstocks should be repointed every 3
to 4 yeors depending on the conditions. Nuts, bolts ond goskets
offlonge connected mild steel pipes should be checked qnnu-
olly, loose bolts should be tightened ond domoged goskets
should be reploced. A visuql check for flonge leoks should be
corried out monthly.
For buried penstock sections, signs ofleokoge such os
the sudden oppeoronce ofsprings olong the olignment
(especiolly during winter) ond moist ground where the qreq
wos previously dry should be checked. Ifony leokoge is
noticed, the penstock should be droined ond corefully exco-
voted for repoir ofthe leoking section.
6.14 Checklist for penstock work
Refer to Toble 6.i ond decide on the penstock moterial.
When in doubt compore the costs of qll ovoiloble
options.
Is the olignment on procticol ground slope? Is there
odequote spoce for the powerhouse oreo ot the end of
the penstock olignment? Hqve the bends been mini-
mised?
For mild steel pipes refer to Tqble 6.3 to decide on flonge
connection or site welding. Also be sure to specifo
oppropricte coots of point.
If o buried penstock olignment is being considered, refer
to Tobl€ 6.4 to compore the odvqntoges qnd disodvon-
toges, ond Figure 4.8 for the trench detoils.
Is the pipe diometer such thqt the heqdloss is between
5o/o snd 70o/o?
Hqs ollowqnce been mode for surge effects while sizing
the penstock woll thickness?
Is the sofety foctor sufficient os discussed in Section 6.6?
Are the pipe lengths ond weights such thqt they ore
tronsportoble ond porteroble?
Refer to Section 6.12 for pipe instollation ot site.
a
a
109
7. Anchor blocks andsupport piers
7.1 Overview
Ar qnchor block is on €ncosem€nt of0 penstock d€signed to
rcstr0in the plpe movem€nt ln oll drr€ctlons. Anchor blocks
sh0uld be ploced ot 0ll shorp horizontol ond venrcol b€nds,
since there ore forces ot such bends which will t€nd t0 move the
pipe out of oligrlm€nt. Anchor blocks ore qlso requir€d to resist
oxiol forces in long stroight sections ofp€nstock.
Support piers ore short colLlmns thot ore ploced between
onchor blocks qlong stroight sections ofexposed penslock pipe.
These strucrurcs prevent the pipe from sagging ond becoming
overstressed. However, the suppon piers need to ollow pipe
movement porqllel to the penstock olignment which occurs du€
t0 thermol expqnsion ond controction.
7.2 Anchor blocks
72.I GENERJqI
Locoti0ns ot which onchor blocks ore required ond their
construction orc described in this section.
7.2.2 LOCATION OF ANCHOR BLOCrc
Anchor blocks ore required ot the following locotions:
At verticol or horizontol bends ofthe penstock os shown
in Photogroph 7.2. A filled p€nstock exefts forces ot such
bends ond th€ pipe needs to be properly 'onchored'.
lmmediotely upstreom of th€ powerhouse. This
minimises forces on the turbine housing.
At sections ofthe penstock where the stroight pip€
lengrh exceeds 30 m. This is to limit the thermol
exponsion ofthe pipe since on exponsionjoint will be
ploced downstreom ofthe onchor block.
723 CONSTRUCIION OF ANCHOR BLOCXS
A[ch0r blocks should normolly be constructed of 1:3:6 concr€te
(1 poft cemenr, 3 pqrts sqnd. 6 ports oggregote)with 400/0
plums ond nomrnol reinforcernent. Plums ole boulders thot ole
distributed ever y oround the block such thot they occupyqbout 40% ofthe block volume. The boulders odd weight to the
block ond therefore incrcose stqbility while decr€osing the
PhotoT'l A stroight penstock with four suppons ond ononchor block befoR the powerhouse
Photo ? 2 Jhonhe mni'hydro onchor block for on upword venicol bend
1 1 1
. r m , n r r , ^ 1 " m , . e n " i r D l
Hoop reinforcement is required 0round the pipe lo resist
crocking ofthe concrete due t0 tensile forces from the pip€.
Three l0 mm bors ore generolly suincient, os shown in Figure
7.1. The hoop b0rs sh0uld be opproximotely 150 mm cleor of
the pipe, cnd should exrend to 100 mln from the b0se, so thot
rhe whol€ weight ofthe block cqn be nobil ised without
crocking Ifthe reinforcement is inodequote, the block con
crock. os shown in Photogroph 7 3. A collor 0r metol togs moy
be welded to th€ prpe to eusure thot rhe pipe does not slide
within the onchor biock
For downword bends, the onchor block is moinly in
compression, therefore o st0ne mosonry structure (1i4 cement
monor)con be considered ifcosts con b€ brought down.
Composite onchor blocks c0n ols0 b€ considered to sove
cost os shown in Figure 7.2. Foundotion ports ond centrol
portion ofth€ block con be mode of lr1.5r3 reinforced concrete
ond outer poftion ofthe block con be mad€ ofstone mqsonry rn1 . 4 l . p m o n r ' c . n d ) m n r l n r
Note: All dimensions
ore ln mmh d i n g ( 1 , 3 : 6
Figu.e 7 I Anchor block seclion
The cement requirements [or plum concrete 0nd cementm n c ^ n r u . r D . c f ^ l l ^ u , c .
. 1:316 concrele with 40% plums: 132 kg ofcement per ml
ofblock volume.
. 1t1.5:3 concretet400 kg 0fcement per ml
. Stone mos0nry in 1:4 cemenl moffor 159 kg ofcemenl
per m ' .
Although more cem€nt ls required for cement mosonry
blocks, sovings moy be mode by ov0iding the cost of formwork
Photo 73 Crocking otthe Dppcr sudoce o[on unrcinforc€d onchor block
(where wood is expensive) ond crushing ofstone to preporc
oggreg0tes. Th€r€fore, whether pluln concrete or cement
mosonry rs economicol is site sp€cil lc but this issue should be
investigoted ifthere ore o number ofdownword venicol bends.
Cost con qlso be reduced by using permonenr dry stone
wqlls os formwork for the bu ed portion 0fthe onchor block os
shown ln Photogroph 7 4 At sires where wood is expensiv€ this
opprooch is worth considering.
Both ploin concrete or stone mosonry in cement mortor
\(
f -
Stone mosonrY in l :4 c/m
_ _i-- * ___j___<*--|-z-F=i- |
------
t : t5 :3
Note: Alldlmensions
ole ln mm.
Ir{,1
t12
lholoT4 useof drynonerv(r1 l forkr fD$ork.J l r (Lnk|c
blocks shoLrld be cured os discuss€d in Ch0pt€r I by keeping
them noist for ot leost o week.
The design oionchor blocks is covered rn s€ction 7 4.
Toble 7.1 Suppon pier spocing lcentre to centrc horizontol length in metresl
7.3 Support piers
?.3.1 GENERAL
l.ocotions ot which suppoft piers or€ required ond their
construcrion ore described in this sectiol|
7.3.2 LOCATION OF SUPPORT PIERS
Suppon piers ore requrred 0lorg thc stroight sections ofexposed
penstock betrveen onchol blocks. The moximum spocing of
support piers to ovoid overstressing the pipe is given in Toble
7 l. Pleose reod the notes under rhe toble'lhin-lvolled ploin pipe con buckle ot the suppon piers
with relotively short spons. In this cose the permissible spon
con be increosed by welding o w€qr plot€ to the pipe at e0ch
supp0n, see figure 7.3. This nroy be economicol for pipes lorger
thon 300 mm diomeler Corners ofweor ploles should be cut
with o rodius, to ovoid stress concentrolions Not€ thot o weor
plote is olso requir€d where the pipe leoves on onchor block, if
the spon t0 the first suppon pier exceeds thot ollowed for ploin
prpe.
It is usuqlly n0t economicol ro increose the pipe woll
thickness in ord€r to increose the support prer spqcing, but this
should be considered where the cost ofsuppon piers rs signrll
c0 n t .
PLAIN PIPE PIPE WITH WEAR PLAIESIFFECTIVE PIPE WAIL
THICKNESS, t,r.., ".
(mm):
320 Nimrnr STLEL
410 Nimmr STIEL
1 3
1.0
1 9
1 5
2.6
2.0
3.9
3 0
1.3
1 . 0
1 .9
1 5
3 93.0
2 6
2.0
h,,. < 100 r1r
100 mm dio
200 mm dio
300 mm dio
400 mm dio
500 mm dio
4.0 4.7
?.3 8.38.6 10.59 1 11.?
9.3 12.0
2 A
4 l
2 5
I 4
3 2
6 0
5 7
2.6
2 1
4.0
7 3
8.6
5.8
3.7
4 .7
8 .1
10.5
11.7
8.7
2 0
4 t
4 .9
5 1
4.1
3.2
6.0
? 0
7.4
7 5
(b) 100 < h,",", < 150 m
100 nnl dio
200 mm dio
100 mm dio
400 mm dio
500 mm dio
1 9
3.9
2 .5
1 4
3.1
5 8
5.7
2 6
2 T
4.0
7.1
8 2
5.8
3 7
4.7
8 .3
1 0 5
1 1 2
8 7
1.9
3 .9
4.4
4.4
4.0
1 .1
5 .8
6 .7
6 9
6.8
4 . 0 4 7
7 . 7 8 3
8.2 10 5
8 .6 11 2
8 .7 11 .5
1 1 3
. Continued
...Continued
rc) 150 < h,dor < 200 m
100 mm dio
200 mm dio
300 mm diq
400 mm diq
500 mm dio
2.7
2.5
l . a
2.35.05.72.6z . r
3.5
6.5
7.6
5.8
3.7
A A
8.3
10.1
10.6
8.7
2.7
3.2
3.0
z-u
2.3
5.0
5.8
6.0
5.8
3.5 4.7
6.5 8.3
7.6 10.r
7.9 10.6
7.9 70.7
(d) 200 < h,otor < 250 m
100 mm dio
200 mm diq
300 mm dio
400 mm diq
500 mm dio
1 .8
2.7
1 .8
4.4
5.2
2.6
2.1
J . l
6.07.05.83.7
9 . t
8.3
9.7
10.1
8.7
1.8
2.1
1 .8
a . a
J .Z
5.1
, . t
J . t . t . t
6.0 8.3
7.0 9.7
7.2 10.1
7. t 10.1
i,
Notes:
1. Applies only to steel penstocks welded or flonged to British Stqndord (minimum flonge thickness : 16 mm). In other coses
use one support pier for eoch individuol pipe length, with the pier in the middle.
2. Weor plotes to be of some thickness os pipe woll, ond welded on oll edges, covering bottom 180" of pipe. The length should
be enough to extend ot leost 0.5 times the pipe diometer beyond eoch side of tire support pier. See Figure 7.3.
3. For the colculqtioD 0ft"u".,u. reler to Section 6.6.
4. Interpolote between the obove volues for intermediqte pipe diometers, wqll thicknesses or steel grodes.
SECTION A.A
Figure.7.3 Arrongement ofweor plote ot o support pier
114
733 CONSTRUCTION OF SIJPPORT P|ENS
Support piers ole generolly constructed out ofstone mosonry in
1:4 cem€nt moftor. Dressed stone should be used for the outsid€
surfoces ofthe pi€r A 140'beoring oreq from the centft ofthe
penstock di0meter should be provided to support the penstock
pipe os shown in Figurc 7.4. Plocing o steel soddle plote obove
the support pier wh€re the penstock pipe rests olong with o 3
mm thick tor poper os shown in Figure 7.4 minimises friclionol
effects ond increoses th€ useful life ofthe pipe. c-clomps mqy
olso be provided to protect th€ pipe from vqndolism ond c
sidewoys movement. but there must be o gop between the
surfoce ofthe pipe ond th€ C-clomp, so thqt oxiol forces ore not
tronsferred to the support pier. stone mosonry support piels
wilh c-clqmps con be seen in Photogroph 7.5.
Wooden support piers hove occosionolly been used in
micro-hydro schemes, os con be seen in Photogroph 7.7.
Howev€r, wood is generolly expensive ond olso requips
frequent mointenonce such os pointing.
Ste€l support piers con olso be used qs on oltemqtiv€ to
srone m0sonry especiolly ot sites where cement is expensive or
the soil is weok in beoring. An exqmple ofsteel support piels is
rncluded in Chopter 10 (lnnovotions).
3 mm thickpaper
with steelsaddleplateundemeath
frgurp 7.4 T'?icol secrion rhrough o support pier
Photo 7 5 Stone mosonry support piers, JhonkP mini hydm scheme
Photo 7.6 The use ofon extension toth€ concrEte suppon lifts the pipe cleoro[on block, qllowinq droinoge ond preventing cormsion between the block ond
the pipe (ftomche)
1 1 5
7.4 Design ofqnchor blocksond support piers
7.4.1 GENERAI
The design ofonchor blocks ond support piers requires resolving
some common forces, which are therefore discussed together in
this section. First the structurcs orc tentotively sized orld the
vorious forces thot oct on them ore resolved. The minimum
colculqted block size thot is sofe ogoinst beoring, sliding ond
overtuming is occepted. It should be not€d thot the designpr0cess involves o few iterotions.
Vorious forces thot con oct on onchor blocks qnd supportpiers ore summorised in Toble 7.2 ond discussed ther€ofter
Photo 7 7 Wooden support li€rs ot Komche micro.hydro scheme, Nepol
Tqble 7.2 Forces on onchor ond slide blocks
FORCE lkNl DIRECIION OF POIENTI,AI MOVEMENT OF
ANCHOR BLOCK OR SIJPPORT PIER
COMMENTS
SYMBOLS ARE DEFINED AT THE END OF
T1IIS TASLE
F,
Fr = combinotiol ofFr, ond F,d
F,,: (We+w*) 1," cos ct
Frd = (Wp+W*)Lrd cos 0I f n i n p i < c r r n i n h r
F, = {w"+ w,.,)(1,,,+ 1,,)cos G
Uphill portion Downhill portion Fr is the component ofweight ofpipeond woter perpendiculor to the pipe.
Applies to both support piers ondonchor blocks
F,
F?,
F,o
= f (We+ W*)1,. cos cr= f (wp+ w*)Ld cos cr
Fz Expqnsion: onchor
below ond exponsionjoint obove
controctionr onchorbelow
ond expqnsion joint obove
Direcfions for forces on support pier
{t
F, is the frictionol force due to the pipe
sliding on the support pi€rs.
Applies to support pien ond onchor
blocks. The force octing qt on onchor
block is the sum offoEes octing 0n the
support blocks betw€en the onchor
block ond exponsion joints, butnnn^ . i rp in d iF . t i ^n
F,,
r, = zy*",.,h,",",x l{'r (?
=15.4h,"dd'zsin(?)
F, is the hydrostotic forte on bends th0t
octs olong the bisector ofthe bend.
0r y opplies to onchor blocks thqt
hove horizont0l ond/or verticol bends
if $rr
1 1 6
F, = combinqtion of Fou ond Foo
F = W L s i n u .4 u p 4 u
F = W L . s i n B4 d p 4 0 l
Uphill portion
F..,
Downhill portion Fo is the component of pipe weight
octing porollel to pipe.
Applies to onchor blocks only.
Colculqte only ifthe cngles (a or p) ore
lorger thon 20".
' 5
F s = i 0 0 0 E o T n ( d + 0 tSee Toble 6.2 in Chopter 6 forvqlues of E ond o
Uphill portion Downhill portion
\ - -
F, is the thermolly induced force
restroined by the onchor block in the
obsence oI on exponsion joint.
Applies to onchor blocks only.
Colculote only if exponsion joints ore
not instolled between onchor blocks.
F6
Fu=1oodF, directions os F, Fu is the frictionol force in the
exponsionjoint. The F6 force is felt
becouse the joint will resist sliding.
Applies to qnchor blocks only.
F7
F - = y h t l ( d + t ) t/ ! wo le r lo to l
: 31 h,o,o, (d + 0 t
Usuolly insignificont
Uphillportion X Downhill portion- - - -
\-.......-- ---.-
Fru- \
F, is the hydrostotic force on exposed
ends of pipe within expcnsion joint
Applies to onchor blocks only.
F8
\=(ftsJ""(T)=,5(sJ,'"(?)Usuolly insignificont
F, dirrctions os F, F, is the dynomic force ot o bend due to
chonge in direction of moving woter.
Velocities ore usuolly low in penstocks
so this force is smoll.
Applies to onchor blocks only.
F, n . ,
Fn = Y*o,.,h,o,o,X i(do,o' - d'..r,')
= 7 . 7 h ( d ' z - d ' z )l o lo l \ Drq snro l l '
F, is the force due to reduction in pipe
diometer from { n to d,.orr.
Applies to onchor blocks only.
F,o
u , r= !Fcos i xKoxw
F,o is the force due to soil pressure
upstreom ofthe block.
Applies to both onchor blocks ond
support piers
Colculote Fro if (hl - hr) is more thon
1 m. The force octs ot 113 of the height
(h,) from the bose ofthe block.
L
lii
W.D
W . = V o l . . . . x Y . .D Dloak I Dtftt
DEFINITION OF SYMBOIS USED IN TABI}7.2
cr = Upstreom penstock ongle with respect t0 the
horizontol.
B = Downstreom penstock ongle with respect t0 the
horizontol.
y : Unit weight in kN/mr
v - 9.8 kN/mrI wotPr
v : 22 kN/mlr concEle
y = 20 kN/mlr mos0nry
y see Tqble 6.2' p rpc moleno l
Y,o,r see Toble 7.3
O = Soil ongle offriction, see Toble 7.3q = Coeflicient of lineor exponsion ofpipe (oC r), see
Toble 6.2 in Chopter 6 where o is the symbol
used.
ADlg
E
I
sh
h")h
t0l0t
I
K"
Ko
I" l d
= Pipe internol diometer (m).= Internol diometer of lorger pipe in cose of
reduction in pipe diometer: Internol diometer of smqller pipe in cose of
reduction in pipe diometer.= Young's modulus of elosticity, see Toble 6.2 in
Chopter 6.: Coeflicient offriction between pipe ond support
piers: occelerotion due to grovity : 9.8 m/s'z: Buried depth ofblock ot the upstreom foce.: Buried depth ofbiock ot the downstreom foce.: Totol heod including surge.: Uphill ground slope (Figure 7.5). Note thct i moy
not olwoys be equol to a.: Active soil pressure coefficient qs follows:
_ cosi - l to tz i - .o tz 0cos i +\6sri - cos, O
= Hqlfthe distonce from onchor block centreline to
the centreline ofthe first downstreom support pier
Loo
L ,u
r"2d
Lru
I4U
aJ
AT
Wp
W
Wo is the weight of block.
Applies to onchor blocks ond support
piers.
(Figure 7.5).
Holfthe distonce from onchor block centreline to
the centreline of the first upstreqm support pier
(Figure 7.5).
,istonce between two consecutive support piers
downstreom ofthe onchor block.
Distonce between two consecutive support piers
upstreom ofthe onchor block.
Distonce from the onchor block centreline to
the downstreom exponsion joint (Figure 7.5).
Distqnce from the onchor block centreline to the
upstreqm exponsion joint (Figure 7.5).
Flow in the penstock pipe (mr/s).
Wqll thickness of penstock (m).
Moximum temperoture chonge ("C) thqt the pipe
will experience ofter being fixed ot onchor blocks.
Width of the onchor block in m.
Weight of pipe in kN/m
t l ( d + t ) t vr prpe n0(efl01
Weight of woter in kN/m
(Pipe oreo in m2) x y*o,",
118
Figure 7.5 Distdnces qnd ongles used in onchor block ond support pier equotions
7.4.2 DESCRIPIION OF FORCES
F, - F, is the component of the weight of pipe ond enclosed
woter perpendiculor to the pipe olignment. If therr is a bend qt
the onchor, however, both the upstreom ond downstreqm
lengths ofpipe contribute sepqrotely, eoch force perpendiculor
to the centreline of the pipe segment which contributes t0 it.
Fr-F, is the frictionol force ofpipe 0n support piers. Ifthe
penstock moves longitudinolly over supp0rt piers, o friction
force on the pipe is creqted ot eqch pier. A force'Fr", equol to
the sum of oll these forces but opposite in direction, octs on theqnchor. This force exists only where one or more support piers
ore locoted between the onchor block qnd on exponsion joint.
For exomple, if on exponsion joint is locoted immediotely
downhill of the qnchor, friction forces on the downhill length of
pipe will not be tronsmitted to the qnchor block from thqt side.
The friction coeflicient, f, depends on the mqteriql
ogoinst which the penstock slides ond is os follows:
steel on concrete, f: 0.60
steel on steel, rusty plotes, f : 0.50
steel on steel, greosed plotes or tor poper in between,
f : 0.25
F, - F, is the force due to hydrostotic pressure within o bend.
The hydrostotic pressure ot o bend creotes o force which octs
outword for upword bends ond inword if the bend is down-
word. This is o mojor force which must be considered in
designing onchor blocks. However, the block size con be
significontly reduced if the bend ongle (B-a) con be minimised
while fixing the penstock olignment.
F. - Fo is the force due to the component of the weight of pipe
porollel to the pipe olignment. On o slope, the component of
the weight of the pipe which is porollel to the pipe tends to pull
it downhill ond exerts o force on on onchorblock. The sections
ofpipe both upstreom qnd downstreom ofon onchor block moy
hove to be considered. The lengths 'Lou'ond'Loo'in the equotion
for the force "F," qcting on qn onchor block ore the lengths of
the upstreom or downstreom section of the penstock which is
octuolly to be held by thot block. The upstreom section moy
begin ot the foreboy 0r, more usuolly, ot on exponsion joint. The
downstreqm section usuolly ends qt on exponsionjoint. Ifthe
exponsion joint downstreom of on onchor block is locqted neor
the onchor, os it usuolly is, the force crising from the weight of
the downhill section of pipe between the onchor ond the joint is
insignilicont ond is usuolly neglected. Also, the onchor block
will not experience this force if the penstock is buried since the
ground friction will resist this force.
F, - F, is the force thot is tronsmitted t0 the onchor block due to
thermolly induced stresses in the obsence of on exponsion joint.
Ifon exposed section ofo rigid pipe does not incorporote on
exponsion joint, thermolly induced stresses build up in the pipe
and oct on the onchor block. The ossocioted force "Fr'moy
push ogoinst the onchor block (with increosing temperoture) or
119
illl
pull the onchor block (with decreosing tenperoture).
F. - Fu is the force due to friction within the exponsion joint. To
prevent leoking, the pocking within qn exponsion joint must be
tightened sufliciently. However, this tightening olso mqkes it
more diflicult for the joint t0 occept ony longitudinol move-
ment of the pipe. Friction between the pocking ond the
concentric sleeves in the exponsion joint creotes o force "Fu"
which opposes ony exponsion or controction 0fthe pipe. This
force is dependent on pipe diqmeter, tightness ofthe pocking
glond ond smoothness ofsliding surfqces. lfthere is not o
chonge in the pipe direction (cr = F) upstreom ond downstrecm
ofthe onchor block, the forces (from upstreqm ond downstreom
exponsion joints) concel out.
F - F, is the hydrostotic force on exposed ends ofpipe in
exponsionjoints. The two sections ofpenstock pipe entering
on exponsion joint terminote inside the joint; therefore, their
ends ore exposed to hydrostotic pressure, resulting in o force
"F," which pushes ogoinst the onchors upstreom qnd down-
streom of the joint. This force usuolly contributes minimolly to
the totol forces on on anchor since the rotio 0fpipe thickness to
the diometer is low. However, this force con be significont ot
mild steel-HDPE joint sections (since HDPE pipes ore thicker).
Note thot h,o,o, is the totol heod ot the exponsionjoint.
F, - F, is the dynomic force ot the pipe bend. At the bend, the
woter chonges the direction ofits velocity ond therefore the
direction of its momentum. This requires thot the bend exert o
force on the woter. Consequently, on equol but opposite
reoction force "F." octs on the bendl it octs in the direction
which bisects the exterior ongle of the bend (some os F,). Since
velocities in penstocks ore relotively low (< 5 m/s), the mogni-
tude ofthis force is usuoliy insignificont.
F, - Fn is the force exerted due to the reduction of pipe diometer.
Ifthere is o chonge in the diometer ofthe penstock, the hydro-
stotic pressure qcting on the exposed oreo creotes o force "Fr"
which qcts in the direction of the smqller-diometer pipe. if the
penstock length is long (os in the cose of Jhonkre mini-hydro),
then the pipe thickness is increqsed with increqsing heod.
However, the effect of chonging the diometer by o few mm does
not c0ntribute significont forces ond can be ignored.
Fro - F,o is the force on the onchor blocks or support piers due t0
the soil pressure octing on the upstreom fqce. Ifthere is o
significont difference between the upstreqm ond downstreom
buried depth (h, - h, > I m) of the block then o force will be
exerted on the onchor block due to soil pressure. In such cqses,
this force should be considered since it hos o destqbilisino effect.
Note thqt the resultqnt ofthis force octs ot 1/3 h..
7.4.3 DESIGN PROCEDURE
Once oll of the obove relevont forces hove been cqlculoted the
design procedure for onchor blocks ond support piers requires
checking the three conditions 0f stobility os follows:
Safety against overturning
The forces octing on the structure should not overturn the block.
For structures thot hove rectongulor boses, this condition is met
if the resultqnt octs within the middle third of the bqse. This is
checked qs follows:
r First toke moments obout one point of the block olong the
loce porollel to the penstock olignment.
r Find the resultont distonce qt which the sum ofverticol
forces oct using the following equotion:
/ I M \, . 1 _ I _ I" - \ I v /
where:
d is the distqnce qt which the resultont octs.
Itr,t is the sum o[ moments obout the chosen point of
the block.
IV is the sum ofvertical forces on the block.
r Now colculqte the eccentricity ofthe block using the
following equotion:
l r Ie : I
o o t t - d lt 2 I
r For the resultont to be in the middle third of the block, the
eccentricity must be less thon 1/6 of the bose length os
follows:
Finolly check thot e < €orowobre
Safety on bearing
The lood trqnsmitted to the foundqtion must be within the sqfe
beoring copocity limit of the foundotion moteriol. If the trons-
mitted lood exceeds the beoring copociry limit of the foundotion,
the structure will sink. The beoring pressure ot the bose is
checked using the following equotions:
p . =
where:
P. : moximum Dressure tronsmitted to the foundotion.mta
L&s€-ollowot l. 6
* ( ' . * - )
flri
r20
the sum ofverticol forces octing on the block.
length ofthe bose.
the bose oreo ofthe block.
eccentricitv colculoted eorlier.
The colculoted Pbo,, must be less thon the ollowoble
beoring pressure (Po'o,our,) for the type ofsoil ot the foundotion
level. Allowoble beoring pressure for different types ofsoil is
shown in Toble 7.3.
Toble ?3 Unit weight |7f, ongle of friction lOl snd ollowoble beoring pressur€ for difierent soil types
S r r -/ r v -
T -mse
A =ms€
r -
SOIL TYPE UNIT WEIGHT, y (kN/m') FRICION ANGrc(Aol AttOwABLE BEARING PRESSURE (kN/m')
Soft cloys ond silts
Firm cloys ond firm sondy cioys
Stiffcloys ond stiffsondy cloys
Very stiffboulder cloys
Loose well groded sonds ond
scnd/grovel mixture
I b
t7
20
20
18
22
25
30
32
31
50100200350100
Safety against sliding
The structure should not slide over its foundotion. The follow-
ing equotion is used to check this condition:
uIv' - > 1 . 5 :Itl
where:
I H = sum ofhorizontol forces
u =Friction coeflicient between the block ond the foundotion.
A volue of p : 1on ,, but not exceeding 0.5, is recommended for
friction between mosonry or concrete on soil.
lV = Sum ofvertical forces octing on the block
Design for one of the Jhonkre mini-hydro onchor blocks. The following information is provided:
Pipe diometer = 450 mm,
Pipeth ickness:4mm.
hntr, = 6o m'
\o*. = 48 *,
6 1 = i = 1 3 o , p = 2 5 '
Distonce to upstreom support pier, = 4 m,
.'.L,u = 2 m
Distance to downstreom support pier, = 4 t
" 'L 'a = 2 m
Distonce to upstreom expcnsion joint = 30 m.
" 'L* = 30m
There ore 8 support piers ot 4 m centre to centre spccing (L^ = 4 m) up to the upstrcam onchor block. To reduce friction, oll
support piers ore provided with steel shaddle plotes ond tor poper on top ofthe plotes os in Figure 7.4.
An exponsion joint will be locoted just downstreom of the block.
The soil rype is stiffcloy.
72r
CALCULAnONSh . = h + h
rorot gffi srge
= 6 0 m + 4 8 m = 1 0 8 m
Consider the block shope shown in Figure 7.6.Block volume excluding volume of the pipe =
{(2.2s x r} *(+- :x i.os)} x 2- 1 x fIx0.4582
/4 cos 13o - 2 x fl x 0.458'? /4 cos 25o = 16.12 m3
Unit weight of concrete, (y.oo.*.)= 22 kN /m3Weight of block, Wr = 16.12 x 22= 354.64 kN
Weight of pipe,
Wo =il (d + t) t y,,*r= f[ x 0.454 x 0.004 x 77= 0.,14 kN/m
n (0.4sorW* = ----;- x9.8 = 1.56kN/m
Wp+W, = 2.00 kN/m
Colculote the relevont forces:
3.00 mWdth = 2.00 m
Figure 7.6 Pmposed onchor block shope
1. F,u = (Wo * W*) L,ucos cr= (2.00) x 2 x cos 13' = 3.9) kl,f
2. F,o = (Wo*W*) L,ocos P= (2.00) x 2 x cos 25o = 3.63 kN
3. Frictionol force per support pier:= + f (Wp* W,)L^ cos cr
f = 0.25 for steel on steel with tor poper in between,= "r 0.25(2.00) x 4 cos 13o= -r 1.95 kN per support pier
Since there ore 8 support piers
F^onAnchorblock = t 1.95x8 = t 15.6 ld,{
Note thot F, is zero since on exponsion joint is locoted immediotely downstream of the anchor block
4. F, = 15.4h,o,o,0'r* (?)
= 15.4 x 108 x (0.450), r* (tt;- tt"
)= 35.20 kN
5. F.u = Wolru sin u: 0.44x 30 x sin 13'= 2.97 kN
122
Note thot Fou is insignificont since a is less than zff and could have been ignored cs discussed in Toble ?.2. F* hos beencolculated here only t0 show how it is done. F* is negligible since on exponsion joint is ploced immediotely downstreom ofthe onchor block., i.e., L* - 0 and therefore
F .=0 .
6. Fu =100xd = 100x0.450 = 45kN
7 . F I = 3 1 h , o , r ( d + 0 t
F7u = 31 x (108 - 30 sin cr) x 0.454 x 0.004= 5.70 kN
Fro = 31 x 108 x 0.454 x 0.()04 = 6.08 kN
Note thot os disclssed eorlier the rrsultont ofthese forces is insionificant.
/ Q ' \ / p - c \8 . F8 : t . t I
a , / s i n [ , /
^ _ 1 0 . 4 5 0 ' z \ . / 2 s " - 1 3 " \: 2's I o3so'? /th t z /
: 0.26 kN
Note thot os discussed eorlier, this force is insiqnificont.
9. F, = 0 since the pipe diometer does not chonge.
10. Soil force, F,o.
From Toble 7.3, y,o' = 20 kN/m3 ond
0 = 3oo for stiffclay.
Reco l l t ho t i =13o
. _ cosi - . , /coszi -coFI
K" = cosi +mffi =o'371
v . h 2F ,o= eXLcos i xKoxw
zJ x r.a'= -T- cos 13o x 0.37txz
= 23.45 kN
This force octs ot U3 ofthe buried depth ot upstrcom fqce ofonchor block from point o asshown in Figure 7.7, which is (U3 x 1.8) = 0.6 m.
123
Resolution of forces
c r = 1 3 " , b = 2 5 "
Forces (kN) X - component (kN) ++ Y - component (kN) + +
l u
F- l d
* F[cos a= *3.80
F,o cos P= * 3.29+ Fzusin cr= + 3.51
Positive during exponsion O
Negotive during contrcction @
/B+0 \- f r cos \
, /= -33.29
* Fou sin cr= * 2.97 sin 13o= * 0.67+ Fu (sin p - sin ct)= t 45 (sin 25" - sin 13")= -r 8.90
Positive during exponsion O
Negotive during controction @
* F^ sin cr: 5.70 sin 13"= * 1.28- Fro sin P= * 6.08 sin 25o= - 2.57
/0+cr1- r ,cos \ 2 /
= - 0.25
f F,o sin i= 23.45 sin 13'= * 5.28
+ 354.@
= 3.90
= 3.63
= - + 15.6
' 4 u
= 35.20
= 2.97
Fru : 5'70
Fro: 6'08
F, : o'26
F,o : 23.45
Wr: 354'64
* F,u sin cr: - 0.88- F,o sin B= - r - l j
-f F2u cos 0.
= -r 15.20
Positive during exponsion O
Negotive during controction @
/ p+cr\* F , s i n \ , ,= f l l .4 t )
+ F4u cos ct= * 2.97 cos 13o= * 2.89+ F, (cos a - cos B): +45 (cos13 ' - cos25 ' )
: -{- 3.06
Positive during exponsion O
Negotive during controction @
* F^ cos cr= 5.70 cos 13"= *5.55- Fro cos B= - 6.08 cos 25o= - 5.51
/ F+41*F rs i n \ , I
/ 250+ 130\= 0.26 sin | -l
\ 2 |
: * 0.09
* F,o cos i= 23.45 cos 13o- * 22.85
0
' a r
F' 3
= 4 5
Iv:345.26OExponsionIV = 320.44 @ Controction
l H = + 5 3 . 1 8 O E x p o n s i o nIH = + 16.66@ Controction
SUM
Note thot forces ore positive in X-direction is towords the right ond Y-direction downwords.
Colculote the centre of grovity of the block from the upstreom foce of the block toking the moment of moss. The eflect of the
pipe possing through the block is negligible, so need not be colculoted.
{(3x2.25)3 12 + | 1 /2x3x 1.05) 1 /3x3 } x2
{ (3x2.25]t + (Uzx3x 1.05) } x2
124
= 1.41m
.'. the weight of the block WB octs 1.41 m from point 0.
Sum ofhorizontol forces thot oct ot the bendI s - n
O Exponsion case 53.18 -22.85: 30.33 kN -r
O Controction cose 16.66 -22.85 = - 6.19 kN +-
Sum ofverticql forces thqt sct qt the bend
Iv -F ,oy -wBO Exponsion cose
345.26-5.28-354.64 = - 14.66 kN t
@ Controction cose
320.44-5.28*354.9 = * 39.48 kN T
Now drow q force diqorom on the block os shown in Fioure 7.7.
Check ifstructure is sofe ogoinst overturning:
O -+ Exponsion cose
Tqke sum 0f moments obout point 0 with clockwise
moments os positive:
I u@r o = 30 .33x2 .15 * 22 .85x0 .6
+ 354.& x 1.41 - 14.66 x 1.0= 564.30 kN-m
, /:r,r\ 564.30o: \ - tu /= i f i : 163m
t 3 |e = l - - 1 . 6 3 l = 0 . 1 3 m
I'IL 3
P - = 0 . 5 m'o l lowohle
6 6
. ' . e < e . O Kon0woDte
@ + Controction cqse
Tqke sum of moments obout point O with clockwise moments os positive:
IM@ 0 = -6 .19x2 .15 * 22 .85x0 .6
+ 354.64 x 1.4i - 39.48 x 1.0: 460.96 kN-m
, /ru\ +oo.sod = l - l = - = 1 . 4 4 m
\ Iv I 320.44
l : Ie : l - - 1 .44 | : s .96 m
l ' l
39.48014.660 e
@Expansion
Contrac{on
Penstock
Figurc 7.7 Force diogrom on the onchor block
Recoll thot €ouo*obl. = 0.5
. " e < e . . . . 0 K .otowoDt€
Since e < eo,,*ob,. for both coses, the structure is sofe ogoinst overturning.
Check if the structurc is safe on beoring copocity:Note thot for stiffcloy ollowoble beoring pr€ssure is 200 kNlm'? (Toble 7.3).
O -r Exponsion cose:
= Iv / t *6 f )mre 4.," \ Lb""I
,*..= 44 (r + $r:) = 72.5 N/mzm 5 € 3 x 2 \ r l
@ + Controction cose:
p = l ' v ( r + !s - , )'bose
A*r, \- q",./
P. -320'44 /r + -6Iq'06) : 5e.8 kN/m2d * 3 x 2 \ r l
In both coses P*," ( Pouo*orr. = 200 kN/mz. .'. the structure is sofe ogoinst sinking.
Check ifthe block is scfe ogoinst sliding:
O -+ [xponsion cose
I H < p I V
p = 0.5 for concrete/mosonry on soil
53.18 kN < 0.5 x 345.26 kN
53.18 kN < 172.53 kN OK.
O + Controction cose
T H < p ' V
16.66 kN < 0.5 x 320.,14 kN
i5.66 kN < 160.22 kN 0K.
Since I H . p I V in both coses the structure is sofe agoinst sliding.
.'.The onchor block is stable. The colculotions could be repeoted to justiff using o smoller, more economicol block.
7.4.4 STZNG OF ANCHOR BLOCKS FOR SMAI.L SCHEMES
For micro-hydro schemes with o gross heqd less thon 60 m qnd
on instqlled power copocity less thon or equol to 20 kW the
following guidelines cqn be used to determine the size of on
onchor block:
o At o stroight section, locote one onchor block ofter every
30 m distonce (os discussed eorlier) by plccing 1 m3 of
plum concrete for eoch 300 mm of pipe diometer. For
exomple, if the pipe diometer is 200 mm, then:
/ 2 0 0 \t
" f1*, = 0.67 m3 of concrete volume is required.
r At o penstock bend, where the bend ongle is less thon 450
(i.e., 0 - a), double the concrete volume thon whot is
126
required for o stroight section. For exomple ifthe pipe
diometer is 200 mm ond the bend is 20'. then:
/ 2 0 0 \2 xl--:=- | = 1 .33 m3 of concrete is required for
\ 3 0 0 /the qnchor block.
r Similorly, if the bend ongle is lorger thon 45', then the
required concrete volume should be three times thot for
o stroight section. For exomple if the pipe diometer is
350 mm ond the bend is 500, then:
, - (-:+) = 3.5 mr of concrete is required for the\ 3 0 0 /
onchor block.
John Bywoter hos developed o more sophisticoted
method of sizing onchor blocks for smoll schemes. This is
ovqilqble through ITDG.
7.4.5 SIZNG OF SUPPORT PIERS FOR SMAII SCHEMES
For smoll schemes (gross heod less thon 60 m cnd power
copociry limited t0 20 kW) Figures 7.8 qnd 7.9 con be used osguidelines to size for support piers.
If the penstock olignment is less thqn 1 m qbove theground, Figure 7.8 cqn be used os o guide for the shope ofthe
support pier. The minimum length ond width ot the bose
should be 1 m x I m ond the top width porollel to the penstock
olignment should be 0.5 m. The width qt the top perpendiculor
t0 the penstock pipe route should be kept 1 m ond the uphill
woll surfoce should be perpendiculor to the penstock pipe. A
minimum foundotion depth of 300 mm should be provided.
Similorly, if the penstock pipe is 1-2 m obove the ground, Figure
7.9 con be use qs o guideline. Note thqt the structure is similor
t0 Figure 7.8 except thqt the bose length ond width ore 1.5 m x
1.5 m.
For lorger schemes qll relevont forces should be resolved
ond conditions ofstobility should be checked qs discussed
eorlier.
Note: All dimensions
qre in mm
Figure 7.8 Suppon pier for smoll schemes with ground height of less thon 1 m
Note: All dimensions
ore in mm
Figure 7.9 Support pier for smoll schemes with ground height of I m to 2 m
7.5 Checklist for onchor blockond support pier works
o Hove onchor blocks been locoted ot exposed penstock
length intervols exceeding 30 m even when there ore no
bends?
o For onchor blocks, hos o minimum cover of 300 mm
oround the pipe been provided? Is odequote reinforce-
ment included?
o If there ore o lot of downwords bends qnd wood is
expensive ot site consider using mosonry onchor blocks.
Also for the buried sections, dry stone wolls con be used
os permonent formwork.
r Hos odequote foundotion depth been provided for both
support piers ond onchor blocks? Be sure to include steelplctes ond tor poper on support piers to minimise
friction.
o Hove oll relevont forces on both support piers ond
onchor blocks been checked os discussed in Section 7.4?r Finolly reler to Chopter 9 for issues concerning stobiliry.
127
E.l Overview
the powerhoust occommodotes electr0 nlechonic0l equlpment
such 0s the turbine, generotor, ogro processlng units ond
controlponels. The morn luncti0n ofthls butlding is to protect
the electro-mecllonicol equipnrenr fronr odverse weother os
well0s possible rnisllondlin0 by un0uthonsed persons. The
powerhouse should hove cdequote spoce such thot oll equip-
menl con fit in 0nd be occrssed without dimculty. Costconb€
bmught d0wn if the c0nstrLrction is simil0r to other houses in
Itr€ Communrty.
The powerhouse ofthe Borpok rriclo'hydro scheme r..,r
h seen in Phot0gr0ph 8 1 This buildrng is similor to other locol
hous€s in the community. Note thot the tronsformer is f€nced
t0pr€vent occidents due to unouthorised occess.
Th€ g€nerot0rs, Iurbines 0nd rhe belt drives need ro be
$cuRly lixed on the mochine I0undotion in the powerhouse.
Il is Rquires 0 cqreful oesrqrsln.r lhe equiDment generores
8. Powerhouseond tailrace
129
Photo 8 I Powerhous€ oflhe Eorpok micro.hydm schem€
dynomic forc€s ond even q slight displocement con cous€
excessive strcsses on vorious ports ofthe €quipment ond leod to
equipmerIt molfunction.
The toilroce is 0 chonnel or o pipe thot conveys woter
from the turbine (ofter power generotion)bock into the str€qm;
generolly the sqme str€om from which the woter wos initiolly
withdrown.
The powerhouse ond toilroce ofthe S0ll€riChiolso mini-
hydro scheme con be seen in Photogroph 8.2
PhotoE2 Powerhoute ond toilroce ofthe SolleriChnlso minr-hydro scheme
E.2 Locotion ofpowerhouse
The locotion ofthe pow€rhouse is govemed by th€ penstock
olignment since this building must be locoted ot the end ofthe
penstock. Aport from this, the following crit€rio oIe recom-
mended for locoting the powerhouse:
o The powerhouse should be sofe from not only onnuol
floods but olso rore flood events. Discussi0ns should be
held with the locol community members to ensuE thot
floodwoters hove not rcoched the proposed pow€rhouse
site within ot leost the post 20 yeors. For micro.hydro
schemes of5G100 kW it is r€commended thot the
powerhouse be obove the 5Gyeor flood level.
. It should olso be possible to dischorge the toilwoter
sofely ftom the powerhouse bock to the streom.
. Ifpossible the powerhouse should be locoted on level
ground to minimise €xcovotion work.
o The proposed locotion should be occessible throughout
the yeor. At some ploces this moy r€quire constructing o
new foot troil.
o The powerhouse should be locoted close to the commu.
nity thot it serves, prcvided thot the penstock qlignment
ond other porometers or€ feosible ond economicol. This
will Rduce the tronsmission lin€ cost. ond ifo0ro.
pmc€ssing units ore olso instoll€d in the powerhous€,
the community will not hove to corry their groin for o
long distonce.
. Oth€r stobility issues discussed in Chopter 9 should olso
be oddr€ss€d.
E.3 Design of powerhouse
83.1 GENERAI
A powerhouse thqt is similor to other locol houses in the
community is generolly economicol ond oppropriot€. The
community m€mbers \a'ill be oble to construct such o building
with nominol supeffision.
Ifo decision is mode to construct tie powerhouse similor
to oth€r locol houses, then the civil design input requircd is to
size th€ plon oreo ofthe building ond design the mochin€
foundotion. The olto inside the powerhouse should be well lit
ond ventilqted with sufficient windows. Plocing o few trons-
porcnt fibrcgloss sheets (skyligh0 in the roof will pmvide
odditionol illuminotion os con be seen in Photoorooh 8.3.
832 SEE OF TIIE FOWENfiOUSE
The plon oreo ofthe powerhouse should be determined os
follows:
. The siz€ ofthe electm-mechonicol equipment should be
obtoined from the monufqcturer.
. All l€quil€d equipment should be drown to scole ond
ploced on the proposed powerhouse plon oreo. This moy
requir€ o few t ols to determifle the optimum loyout.
r30
Photo 8.1 Powerhouse of the Fonlcc minF hydlo
-\
833 POWERHOUSE WAII AND OTHER DETAII.S
Most houses in the hills of Nepol ore constructed of stone
mos0nry in mud mortor. Wooden truss with corrugoted iron
sheet (CGI), slotes or strow thatching ore used for the roofs. A
similor building is recommended for the powerhouse structure
with the following considerqtions:
o The minimum woll thickness of the stone mosonry
wolls (mud mortor) should be 450 mm. If funds ore
ovoiloble ot leost the externql surfoce of the wolls
should be plostered in cement-lime mortqr (12 mm
thick, 1:1:6 mix) to keep owoy moisture from roin.
r The penstock pipe should not normolly be built into the
powerhouse woll, otherwise the wqll could be domoged
by vibrotion from the turbine. The recommended
solution is to leove on oversized opening in the woll; on
olternotive is to ploce o bigger pipe outside the penstock
pipe where it posses through the wqll. At Jhonkre mini-
hydro the wqll wqs locolly thickened to act os o support
pier for the penstock pipes entering the powerhouse.
o The cleor height of the building should be 2.5 m t0 3 m.
r For lorger schemes, provision must be mode for liftingpnt r in rnpnt t \n t rnnnnt \2 l ; f tgd hy hnnd y ' r rnng i "
. 1 . . / . . . - . . . " J
, , " . , _ . 1 . r / u t l | t J
,' ,"r' slo(,c5
r3200
Figun 8.1 Powerhouse floor plon of the Jhonkre mini-hydm scheme
Adequote spoce should be provided such thot oll
equipment is eosily occessible. There should be q cleor
spocing of ot leost 1 m oround eoch item of equipment
thot hos moving ports (such os the generotor, turbine
ond the belt drive). Noted thot ifogro-processing
equipment is instolled, the community members will
regulorly visit the powerhouse (to process their groin).
Therefore odditionol spoce is required so thot the
powerhouse does not become overcrowded ond o
potentiol oreo for occidents. It is recommended thot
such qdditionol spoce is provided os o lobby ct the
entronce ond the equipment is ploced beyond it. A lobby
lorge enough for five people to woit with their groin
(obout 3 m x 3 m) moy be odequote in most coses.
Adequote windows should be provided for lighting ond
ventilotion. Note thot the door ond windows need to be
locoted such thot they do not obstruct occess to the
equipment. This requires co-ordinoting the locotions of
the equipment, windows qnd the door.
The powerhouse loyout of the Jhonkre minihydro
scieme i-s .rhou/.r,, in Fitrr 8 t
131
,7-
expensive; m0re oppr0pri0te is o block ond Iockle
supp0rted by o beom or lemporory A-fromc.
CGI sheets should be used Ibr the ro0llng, since th€y 0re
relotively fire resistont ond leok prooi
Th€ lloor ofthe powerhouse should be 300 mm to 500
mln obovc the 0ulside ground surlirce to prevent
dompness ond roinwoter entering Drqins should olso
be provjded outside the powerhouse
Doors ond windows should open outwords for scfety in. . .p ^ f f i rp ^ r f l ^^ . l in .
8.4 Design of mochine foundotion
The design ofthe mochine f0undotion is similor to thot ofon
onchor block, but simpler. The m0st significont Ibrces thot the
mochine foundqtion con experience ore os follows:
. The thrust due t0 hydrostohc force when the volve ot
the powerhouse is closed or Ihe totol heod Lncluding
surge due to sudden blockoge offlow lfthere is on
exponsionjoint upstreom ofthe volve, the entire h€od
will be tronsferred to the m0chine foundoti0n from the
turbine housing
r The venicol force due to the weight oflhe foundotion
block, thc turbine qnd lhe gener0lor
Soil forces do not need to be considered becouse rhey ore
bolonced on eqch side ofthe foundotiorr.
Since o homogeneous 0nd rigid srructure is required the
mochine found0tion shou]d be constructed ofreiuforced
concrete. Th€ design process is to t€nlotively size the mochine
Photo 84 Construct ion ofJhonkre mini 'hydro mochlne foundot ions
foundotion ond then ch€ck the structure 0g0rnst ov€fturning,
sliding ond sinking os in the cose ofonchor blocks.
The Jhonkre mini-hydro mochine foundotion pits cor be
seen under construction in Photogroph 8 4. Th€ mochine
fourld0tion ofthe colkot scheme cqn be seen in Drowing 420/C/
3C03 ofAppendix c. Plocing the turbine pit f loor 0.3 m below
toihoc€ invert level h€lps to r€duce obrosion by the woter
leoving the turbine.
Exomple 81 i l lustrotes th€ design principles ofo mochine
foundotion.
: \ :
Design o mochine foundqtion to support o directly coupled rurbine ond generotor. The following informotion hos been
provided:
Penstock pipe diometer - 300 mm, mild steel.
The pipe centreline is 300 mm obove th€ powerhouse floor
0 . = 150 Us
cross hecd (h0.,,) = 51 m
Expected moximum surge heod (h,"_.) - 50 m
Woter l€vel in the toilroce chonnei = 0.25 m
Weight ofturbine {Wr) = 300 k9
W€ight ofg€nerotor (W") = 350 k9
Site conditions reveol thol the f0undoti0n needs to be constructed on soil.
--l
Calculotions:Try a reinforced concrete structure with dimensions as shownin Figures 8.2 ond 8.3.h . = h + h = 5 1 m * 5 0 m = 1 0 1 m :
totd grcss surge
Force due to h,o,o,, F") = (Pipe oreo) x 101 m x unit weight of
w0ter
ilo.3,m2 x 101m x 9.8 kN/m3
4
orF, = 59,960N:70.0kN
Weight of turbine (Wr) : 300 kg = 300 x 9.8 = 2910 N = 2.94
KN
Weight of generotor (Wo) : 350 kg : 350 x 9.8 = 3430 N = 3.43
Ploce oll forces on the mqchine foundotion ond divide the
block in three sections W,, W, cnd W, cs follows:
Colculote the weight of three sections of the block using 22
kN/mr for unit weight of concrete.
W, = 0.4x 1.5m x 2.5mx 22kN/m3=33.00 kN
W, = [ ( 0 .45x 1 .5x2 .5 ) - (0 .45x 1 x0 .5 ) * (0 .a5x0 .5x 1 ) l x
22 = 27.23kN
W, = 2.35 x 1.5 x 2.5 x 22 = 193.88 kN
Check whether the block is sofe ogoinst overturning:
Toke sum of moments obout point B (counter clockwise
moments os positive):
tM@B
10 .4 \= *,* (i + o.4s + 2.35) + (w, + wr) x
1 0 . 4 5 1 / 2 . 3 s \[;
* 2.35) + (wc + w3) t;/
- FH x 1.8
= 33.00(3.0) + (27.23+2.94)(2.575) + (3.43+193.88)( 1 . i 7 5 ) - 7 0 x 1 . 8
or XM@B = 282.5 kNm
Note: All dimensions ore in mFigurc 8.2 Mochine foundotion section
Id,I
+IIII
l l
r I I O l l fOCO
l l
Note: All dimensions ore in m
Figurt 8.3 Mochine foundotion plon
Sum of verticol forces, IV : W, *Wr*W3+Wr+Wc Figure 8.4 Resolution of forces on the mochine foundotion
= 33.00 + 27.23 + 193.88 + 2.94 + 3.43
Note All dimensions ore in m
or IV = 260.5 kN
Equivolent distance ot which XV octs fmm point B:
d = & - ? . 8 ? . 5 = 1 . o B mry 260.5
[t^ Ieccentricity, e = l+-*d I" t, J
lz.z Ie = l__ 1.08
IL J
e = 0.52m
L 3.2€q'owobrc=
f= a =0.53m
Since e is less thon €orowobre, eccentricity is in the middle third.
.'. The structure is sofe ogoinst overturning.
Check bearing pnessure:
p**=* (,.tJ
=#('.s'n)
= &., n ,
< 180 uf
(mox. ollowed for soil)
.'. The structure is sofe ogoinst sinking.
Check sliding:
Assume thot the friction coeflicient between block ond soil, p = 0.5
X H = F r = 7 0 k N
F !V = 0.5 x 260.5 = 130.2 kNFoctor of sofety 0goinst sliding:
= pIv = -P9.2* = 1.g6 > 1.5 oKIH 70
.'. The structure is sofe agoinst sliding.
Hence, t}te structure os designed is odequote. The finol design including the reinforcement bors con be seen in Figure 8.5. A1:1.5:3 mix concrete with reinforcement pottern os shown in the figure is recommended for the mochine foundotion since thestructure must be rigid cnd strong enough to lvithstond the forces. A 50 mm cover (cleor spocing between the bors ond theedge of the concrete surfoce) should be provided for the reinforement bors. Such cover provides pmtection for the rcinfonement bcrs ogainst corrosion ond other odverse effects.
IjI
\,"
Note thot os con be seen in Figure 8.5, a 100 mm width of sand ond gravel hos been ploced ot the periphery of the mochinefoundation down to the depth of the powerhouse floor. This will structurolly isolote the mochine foundotion from thepowerhouse floor so thot the dyncmic forces (such os vibrotions) ore not tronsfened to the floor ond wclls. Crocla olong thepowerhouse floor ond walls have been observed where the mochine foundations hove not been structurolly isoloted. The 50mm thick bituminous surfoce prevents the grovel ond sond from being compocted (ond hence the possibility of tronsfeningforces to the powerhouse floor). This is done by pouring hot bitumen (os used in block topped roods). The 50 mm thickconcrete blinding provides on even surfoce for reinforced concrete work ofthe mochine foundotion.
AIso note thqt, if o belt drive system is required, the mochine foundotion should be extended to cover it. However, the depth offoundotion for the belt drive con be lowercd to 300 mm but with similqr reinforcement pottern.
Bose f rome (dimensims ore to be
- l tl l
' l l
l lt lI tl lr l'r==J
2 .. l
t . , .- t
. t
5Omm thick biluminous srrfoce
5Omm thickb l i nd ing ( l : 5 : 6 ) Anch bol ts
450
Notes
1. All dimensions ore in mm.
2. A minimum of six 20 mm diometer, 700 mm long onchor bors ore to be used to fix the bose frome
foundotion.
3. 10 mm diometer Tor steel bors ore to be used for reinforcement. Moximum spocing to be 150 mm
mm on other foces. Lop length sholl be 400 mm minimum.
4. Minimum reinforcement cover sholl be 50 mm.
5. Structurql concrete shqll be 1:1.5:3 mix.
to the mqchrne
in turbine pit ond 200
Figure 8.5 Proposed mochine foundotion section for Exomple 8.1
135
E.5 Tqilrqce
E.5.1 GENEn TTh€ toilroce is the finol civil structuft thot conveys the designflow. Similor to the heodroce, op€n chonrel or pipes con beused for the toilroce section. Toihoce chonnels of the ftonlcemhi-hydro ond Solleri Chiolso schemes ore shown in Photo-grophs 8.5 ond 8.6 Rspectively.
often, inodequote ottention is given to tie design ond
construction ofthe toilroce since the flow ot this stoge does not
contribute towods power production. However, such o
proctice con result in inodequote depth ofthe tqilroce pit or
erosior ofslopes, which could threoten the powerhouse
structul€,
8.52 I'ESIGN OF THE TAIIRACE CIIANNEL
Design of the toilroce chqnnel is similor to thot of the heodloce
csnol discussed in chopter 4. However, since heodloss does not
need to be minimised o higher veiuciw con usuolly be ollowed,
within the limits giv€n in'lbble 4.1. Not€ thot ot higher
velocities o strong€r grode ofmortor or concrete is r€quired to
resist erosion. Reinfored concrcte moy be economic for o steep
dnnnel os shown in Figure 8.6.
Note thot the downstr€om end of the toihoc€ must be
orronged so thot thel€ is no donger oferosior either by the river
or by the flow from the toilr0ce. Id€olly the dischorge point
should be orto mck or large boulde$. In erudible moteriol o
sti.lling bosin moy be required to dissipote the energy ftom o
steeD toilroce chonn€I.
E.53 DESIGN OF IAIIIACE PIPElfdue to site conditions, o pipe is rEquired for the toilroc€, thedesign procedur€ discussed in Section 4.5 (Heodrocr pipe,chopter 4) should be used t0 size the pipe. similor to o toihocechonnel. o higher heodloss con be ollowed for the pipe.
f HDPE pipe is used, the velocity should be limited to3 m/s ond the pipe should be loid t0 o uniform grodient. Higher
Phoro 8.5 Toilmc. dlonnel ofthe Jhonlae mini.hydm sdeme Photo 8.6 Toilroce dnruIel of the soleri chiolso mini-hydm scheme
mincorer:5Omm
Fioull E.6 R4info@d concrrte roillo(e chonftl
136
velocities 0r non-uniform grodient con result in oir entenoln_ment ond surge problems.
Ifpossible, the toilrqce should empty onto lorge rocks qtthe riverbonk so thqt there is no erosion qt the confluence.
E.6 Checldist forpowerhouse ond toilroce
ls the powerhouse locoted obove the oppropriote flood level?(Refer to Section 8.2)
Is the powerhouse oreo stoble? Refer to Chopter 9 forfurther detoils on stobility.
Hos odequote spoce been ollowed inside the power-house such thot oll equipment con fit in ond permit occesswithout difliculty?
Hos the mochine foundqtion been sized such thot it issofe ogoinst overturning, beoring cnd sliding? Also, be sure tostructurclly isolote the mochine foundotion.
o Is o chonnel or o pipe odequote for the toilroce? Hovethe velocity limits been checked?
r Is the toilwoter likely to couse erosion ot theriverbonk?
737
9. Slope stabilisqtion
9.1 Overview
Nepol's mountoin slop€s, porticulorly the slopes ofthe Middle
Mountoins, ore undergoing ropid chonges due to riv€r cutting,
weothering, ond soil erosion. The rote ofsoil erosion is very
iltense in the Middle Mountoins becouse ofthe subtropicol
clim0te ond intense rqirfqll (2000 to 2500 mm per yeor folling',,dthh 3 to 4 months). This oreq is qlso widely cultivoted using
i[igoted terroces ond heovily deforested due to populotion
pressuRs. Poor woter monogement ond forest mismonogement
h this oreo hov€ l€d to further d€cline of the hill slopes. The
n0turcl processes coupled with mon s influence hove led to
Iordslid€s, ond degrqdotion ofhill slopes offecting the
sustoinobility ond durobility of irrigotion chonnels, wqter
supply systems, micro-hydro schemes ond other development
work.
It is not possible to completely ch€ck these nqturol
processes, however it is possible to conuol them by oppropriote
choice ofmonogement, design ond construction pructices. The
underlying principle behind slope stobilisotion meosures is to
stQbilise hill slopes 0nd river bonks so os t0 protect th€ micrc-
hydm schemes.
Most slope stqbilisotion prcblems con be €ffectively
t0cki€d by moking sure thqt th€ hill slopes ore dry 0y diverting
th€ surfoc€ w0ter from the slopes), constructing retoining wolls
0s well os und€rtoking bio-engine€ring m€osur€s such os
plonting oppropriote vegetotion. Note thot dry slop€s on more
stobl€ thon soturoted ones ond londslid€s oenerolly occur on
wet slopes.
Photo 9 I Unsrobl€ dop€s orc o thrEot lo schemes.This powerbouse wosdestmyed by o londdide.
Retoining structures such os dry stone mosonry wolls,
gobions 0nd teffocing ore the most common method used to
stobilise slopes in mico-hydro schemes. In most micm-hydro
schemes constructing r€inforced concRte r€toining wolls is not
feosible due to their cost.
In the long term, prcventive bio-engineering meqsurcs
would be more effectiv€, sustoinqble ond cheoper thon I€mediol
works. These m€0surcs will often need the continued mointe-
nonce commitment ofthe community
9.2 Implicotions of noturolgeologicol processes
Soil erosion, river cutting, weothering, ond slope foilur€s hove
implicotions for d€sign, construction, operotion ond mqinte-
nonce of micro-hydro schemes.
fuv€r cutting cqn qllect intokes in severol woys, besides
triggering slope foilures, thot moy domoge o portion of
heodroce conol, foundotions ofsettling bosin, crcssings ond
powerhouse. For exomple, meqndering vers con leove intokes
high ond dry Similorly, degrading rivers con r€nder intokes
useless.
When heodroce cqnols ore built on hill slopes where
surfoce erosion hos qdvonced to o stoge where gullies hov€
olr€ody formed, there ore greqter sks ofconol foilure due to
d€ep€ning ond €nlorgement ofthe gullies.
The moin couse ofgully formotion is excessive run-off
due to deforestotiorl, overgrozing cnd burning ofthe vegetotion.
Excovotion work con olso trigger soil emsion. The
following is recommended to reduce the risk ofslope foilum due
to €xcovotion work:
cotch droins c0n be constructed obove the top ofon
excovotion, diverting surfoce woter to o sofe oreo.
When excovoting for conol construction, to prevent
surfoce erosion fresh hill cuts ond exposed slopes of
chonnel bonks must be quickly cover€d with topsoil so
thot vegetotion cqn be re-estoblished.
Spoil from excovotions should be corefully disposed ofso
thot soil erosion is not initioted.
Wherever possible conols should hove b0l0rced cut ond
fill sections to ovoid too much excovotion ond exposurc
offrogile loyers.
ii l: t' ! l
139
. Provide odequote berm width on the hillside ofheodroce
c0nols, to stop sh0llow londslips blocking the flow ond
cousing overtopping, which leods to erosion ofdownhill
slop€s.
9.3 Bio-engine€ringworks
All engineeriDg meosurcs such 0s ptoining wqlls ond check
doms should be well suppl€mented with bio-€ngineering
meosures os for os procticoble.
Plqnting gross or shrubs on the freshly cut hill or the
londslide oreo qre exomples ofbio-€ngine€ring meosul€s. Fost
growing, d€ep rooted orld dense cover type ofvegetotion thot is
oppropriote to the locol environment should be used for such
Purposes.only deep-rooted trces should be used for bio-engineering
purposes, ond they should not be plonted so close to conols or
structurcs thot their roots could cous€ piping or structurol
domoge. At leost 3 metres cleororlce is recommended. Fost
growing trees thot do not h0ve intens€ root systems should be
ovoided since they moy foll due to their own weight during
stoIIns.
once the slopes hove been stobilised, cole should be tol€n
to ensure thqt thele is no funher overgrozing.
9.4 Retoiningstructures
Retoining wolls ore stmctur€s thot support the bockfi.ll ond
surchorge lood fmm the odditionol conol width or plotform
over the wolls in hill sections. Though the per metre cost of
conol construction rrquiring retoining wolls is mon thon
constructing the some length by cutting inside th€ hill, the use
of retoining wolls sometimes becomes essentiol.
The most common types ofrctoining wqll used in micro-
hydro schemes ore grovity wolls ofgobions or cement mosonry
These depend on the moss of the structure to r€sist overturning.
Their design dep€nds on the woll densiry soil pqrometen,
droinoge ond looding conditions, typicolly Esulting in o bose
width of0.40 to 0.65 times the h€ight. The designs shown in
Figurps 9.1 ond 9.2 0re therefor€ sofe, but conservotive in mony
conditions.
For high or long wolls it will b€ economicol to design for
the sp€cifrc site conditions. site specific designs should olso be
mode wherc the bockfill is inclined rother thon horizontol.
The wolls should be checked for overturning, sliding ond
beoring pressure, os described for onchor blocks in Chopter T.
Altemotively rtfer to stondord cMl engineering texts such os
Photo 9.2 Mosonry stepr for energy dissipotion ond contml of spillwoy woterAlthough costly. eloborote contlol is essentiol wheR slop6 ore vuinemble toemsion {Siklis)
Ref. 7. (The unit weight offilled gobions is 1+18 l(N/nr,
dep€nding on the unit weight ofthe rock fill ond ossuming 3G
35% voids).
Woll foundotions must be deep enough to be sofe ogoinst
ercsion: normqlly qt leost 0.5 m below ground lev€I, but see
Section 3.8 for river worla. Lined toe droirs moy be used in
erodible oreos to corry seepoge woter sofely cwoy from the woll
foundotion.
C,obion l?toining wolls should be constructed with on
inclinotion 0f 1096, seeFiguE 9.1. Where gobions or€ to be built
on sond or flne soils, o loyer of filter cloth should be ploced
between the foundotion ond the gabions. The gobion boxes
should be loced together olong oll edg€s ond stptched beforc
filling with roclc The rock should be pocked with the minimum
ofvoids.
Stone mosonry wolls con be constructed in l:4 c€ment/
sond mortor os shown in Figur€ 9.2. Such wolls or€ suitoble for
retoined heights ofup to 2 to 3 m. The slop€ ofthe front foce
moy be steepened ifnecessory prcvided thot the bose width is
mqintoined. Tte reqr foce of the woll should be left rouoh to
140
ho9.SGrbion ot the ioe of on unstoble slope
hcrcqse friction with the bockfiil. Weepholes must be provided
to rclieve woter pressure behlnd the w0ll, ond their mouths
should be protected with ccrefully ploced stones. Bockfill
behind the woll should be free'droinrng grovel or stones; ifthe
Rtoined soil is fine, o filt€r cloth should be ploced os shown to
pEvent the soil ponicl€s blocking the drqinoge.
, O a . 6 .
9.5 Terrocing ond dry stone woll
Lock ofeffort in looking for oltemote woll types. such os
teffocrng 0nd dry stone wolls often rules out the dev€lopment
ofoth€r techniques thot ore mor€ economicol and duroble.
Minor londslid€ oreos con be stobilised by constructing
dry ston€ t€rroces as con be seen in Figure 9.3. The overoll slope
ofsuch terroces should be l imited to 30'(i.e. terroce widrh
should be twice its height). 500 mm thick dry stone wolls
should b€ used for the verticol foce of the rerroces. Such dry
stone wolls retoin the soil behind ond ollow the su oce woter
to droin out.
Constructiog smollcotch droins on the terroc€s helps to
reduc€ soil erosion by droining the surfoce woter
An olternotrve method used to stobilise the steeper
Jhonkre mini-hydro powerhouse slope is discussed in Box 9.1.
Pioto9.4 Stone mosonry con provid€slope
rlobilisotion olong th€ mute oflhe penstock (Borpok)
ri5
IIil
":i
h , f f i 8 , f f i
1.0 1.02.0 1.53 .0 2.04.0 2.55.0 3.5
Figure 9.1 Gobion retoining woll
,300 ,F+;+l
lmrn.l
75 dia.weep holes@2mdc
Figurc 9.2 Stone m0sonry retoining woll
Note:
1 . Cqtch drqins often lined with imperme'
oble lining mqteriols (i.e. stone
mosonry) to ovoid infiltroti0n. Woter
collected from cqtch droins needs to be
droined to neorest nqturol droin.
Londslide
Figure 9.3 Terrocing ond dry stone wolls to retoin slopes
tqz
In order to increqse the gross heod ofthe Jhonkre minihydro scheme, it wos decided to excqvote o 20 m depth ot the power-
house oreq. This required stobilising the hill slope behind the powerhouse oreq. This qreq qlso hod to droin ground woter due toseepoge from the cultivqted terrqces (paddy fields) obove. When irrigotion woter wos provided for the poddy frelds significontseepoge wos observed ot the powerhouse oreo. After considering vorious olternotives, it wos decided to use o grid of mosonrybeqms ond columns infllled with dry stone ponels.
Photogrophs 9.5 ond 9.6 show the hillside during excovotion
ond ofter the construction ofthe mqsonrv orid.
The hill slopes were frrst excqvqted qt 2:1 to 3:1 slopes (V:H) with two intermediote berms olong the hillslope qnd one ot the
sides. Then the grid of stone mosonry (in 1:4 cement: sand mortor) beoms ond columns with dry stone mosonry infill ponels
wos constructed olong the excovqted slopes. The beoms ond columns ore 500 mm wide ond 300 mm deep. The distqnce
between the columns is 2 m ond the verticol distonce between the beoms is 1.5 m (moximum). The dry stone infill soved the
cost of cement qnd focilitqtes drqinoqe. Cqtch droins hove been nrovided ot the berm levels.
To dote this 16 - 20 m high structure is stoble. During the monsoon ground woter thot hos seeped from the poddy fields obove
con be seen droining out from the weep holes qnd the dry stone ponels.
Photo 9 6 Mosonry grid ot powerhouse slope
9.6 Check doms ond gully control
Gullies thot ore octive or smoll streoms where scouring of the
riverbed is prominent con be controiled by constructing check
doms. Check dqms ore smoll wqlls thqt prevent further erosion
on the wqtercourse ond qlso qllow deposition ofbed loqd
upstreom ofit qt o stoble grodient.
For smoll gullies thot ore oniy octive during the m0ns00n,
the check dom could consist of o simple dry stone woll. For
smoll streoms, bed erosion cqn be controiled by using gobion
check doms.
Gobion check doms hove been used to control riverbed
scouring ot theJhorkot micro-hydro scheme. The riverbed ot the
Jhorkot intoke oreo hod been scoured by more thqn 3 m ot
143
some plqces ond the scour depth wos g€tting deeper. It was felt
thot further scouring olong the riverbed would cquse totql
foilure of the existing gobion woll olong the left bqnk of the
river. A series of gobion check dcms wos constructed ot the
intoke oreo to prevent further scouring and to fccilitote the
deposition of bed lood. The first check dom is shown in Figure
9.4. Note thot to prevent the gobion wires from being broken by
rolling boulders, 100 mm thick ploin concrete wos provided ot
the top surfoce of the gcbion woll. A minimum foundqtion
depth of 1 m from the lowest streombed level hos been provided
for oll check doms.
These check doms were constructed by the end ofJune
1998. They hove survived the first monsoon floods ond
culrently their conditions ore being monitored.
9.7 Maintenqnce
Retoining woils, check doms ond other slope stqbilisotion
structures should be inspected regulorly; specificolly before qnd
ofter every monsoon. Remediol works should be done os soon
os ony problems ore noticed. For exomple, the gobion crotes, if
broken, should be repoired soon. Similorly, if stones ore missing
from the dry stone mosonry retoining wolls or check doms,
they should be replcced.
The droinoge system ofthe stobilised slope should be well
mqintoined. Deposition of boulders, grovel or soil in the droin
should be removed. If the ploster or mosonry is broken, it
should be repcired. Note that stcbility problems con occur in
even o well stobilised slope ifthe droinoge system stops
functioning.
It is importont to note thot some structures such qs
gobion wclls ore not mecnt to be permanent on their own.
They moy deteriorote ond collopse. However, once oppropriote
vegetotion over these structures hos token root ond hos
mqtured repoir of these structures moy not be necessory since
the roots o[the vegetation will stcbilise the soil moss.
In the cose ofbio-engineering meosures, ony plonts thot
ore missing should be reploced. If possible, newly plqnted oreos
should be fenced to prevent grozing of qnimols.
l O O m m t h i c k P C C ( 1 . t . s r J )
lnloke cdnol 5000
Dry woll
G o b i o n s Note: All dimensions ore in mm.
Figure 9.4 A gobion check don ot the intoke ofJhorkot micro-hydro scheme
144
10 Innovctions
10.1 Generol
A ru.mb€I of innovotive ideos, I€seolth, opplicotions ond pilotpmjects Rlevort to micm-hydro technology thot hove not yetbem fully field tested, especiolly in the Nepolese context, orEdiscussed in this chopt€r. some opplicotiors orc in the reseolthood development stoge, others hove beetr successfully impleE€nted in other countries or corded out os "pilot pmjects' inNep0l.
102 Cosndqintoke
A Coondo intok€ hos o speciol screen thot utilises the tendencyoffluids to follow o surfoce. This is krown os the "coondo
d€ct'. As shown in Figup 10.1, th€ Coondo scR€n is instoll€dolong the crest of the diversion weir ond is shoped in the ogeecrlrv€ configurotion. A curve occelerotion plote qt the top of thessrm stobilises ond occelerotes the flow. As the flow posses
ovs tfu srE€n surfoce, th€ sheoring oction of t}Ie bors com-Din€d with the Coondo effect seporotes the flow. Cleon woterp6ses down thmugh the screen wh€r€os sediment ond d€bris
Fss ov€r the screen to rejoin the woter couBe below the weir.0n dvers corrying cobbles snd boulders dudng flood, the
Cmfllo int0le must be cor€firlly locoted s0 thot heovy bedloodnot p0ss over the scRen ond domoge it.
The potmtiol odvontoges of th€ Coondo intoke or€ onportio or sites which sufrer ftom exposure to high silt lood orwhich offer scope for cost sovings in the heodroce. In the n$tcose, the intola con Educe the need for lorge or multiplesettling bosins. In the second cose, wher€ o site loyout issuitoble, it moy b€ possible to commmce the penstocl rundinctly ftom the Coondo, goining heod ond ovoiding the needfor o heodroce conol. 0f course, this might imply thot thepenstocl is longer thon other potentiol loyouts or thot it runsclose to t]rc river. A thorough frnonciol ond technicol onolysisof the options is l€quil€d beforE msking o decision on thesuitobility of the C0ondo for o porticulor site.
The Coondo scEens ort fobricoted to o high tol€ronc€from stoinless steel. The supplier ofthe Coondo scr€ens (olso
colled "Aquo Sh€or ScEens") in Europe, Du.los Limited, Woles lX,doims t}lot scEens con be pmduced with 0.5 mm to even 0.2mm deor spccings, whidl diminote 90% of 0.25 mm ond 0.1mm portides Espectively. Both types of screen diminote oll1 mm pqrticles. In most micm-hydro systems this would olsoeliminote the need for o settling bosirl
The flow copocity of these ss?ens is 1,10!/s per metre ofweir length. A scRen with o flow copocity of40 Us (0.3 mwidth) costs obout Us$ 1380 (197 price).
A Coondo intola hos been test€d ot 0 mioo-hydro site inWoles by Dulos Ltd., in conjunction with nDG, UK The designflow of this micm-hydrc scheme is ,10 l/s ond the intoke isshown in Photogroph 10.1.Wcir
werf lorv
Rou topowerptonl
l0l A Coondo intol(e scrEen Photo 10.1 Coondo intole ofo micrchydlo scheme in Woles, uX
Over o six.month period, the performonce ofthe screenhos shown the following chorocteristics:
r Around 90% of sediment between 0.5 mm ond i mm
diometer wos excluded.
o Some build up ofdlgoe wos noted, but this did not
inhibit flow during th€ triol p€riod.
. The effect on performonce due to ice wos not noticeoble.
even ot temperotuEs 12'C below freezing point.
Tests ore rtquircd over o longer period to check for
corrosion ofthe screens ond effect ofcontinued olgoe growth,
porticulorly in wormer temperotures.
More informotion on Coondo screens con be obtoined
from:
DUI"qS Limited,
Mochyr l€th, Powys sY20 8sX, Woles, UK
Fox: +44 (0)1654 781390
e.moil: [email protected]
10.3 De-beqder for HDPE pipes
As discussed in Chopter 4 (Box 4.7), HDPE pipes or€joined by
h€ot wdding which melts ond fuses the ends together. This
Ieods to rois€d "beods" on the inside 0nd outsid€ ofth€ pipe os
shown in Photogroph 10.2. The extemol beod is not o problem
but the internql beod promotes blockqges ond significont heod
loss. An effective de-beqder would reduce the rcughn€ss volue
for HDPE from 0.06 mm (Toble 4.3) t0 0.03 mm.
A "de-beoder" tool hos beer designed (for IT Nepol)torcmove the intemol beods ftom HDPE pipes while the joints qre
still hot [i.€., hot de-beoding). This equipment hos been de.
signed to rcmove beods for pipe diometers up to 250 mm. lt is
still in the experimentol phsse ond l€quiles some developrnent
for use in the field.
As shown in Photogroph 10.3, the de-beoder consists ofo
mild steel shoft with o sleeve on which o bush spring looded to
o locking collor (vio on ,tllen key) is ploced. There ore three
horden€d steel blodes (cutter orms) thot oI€ pin connected by
Rctongulor steel bors to the bush. By unlocking the bush the
connecting pin con be slid up the sleeve to incl€ose the cutting
diometer
Photo I0.3 De-beoder tool
De-beoding with this tool is done by first unlocking the
bush so thot th€ tool con fit inside the pipe. A mild steel md
with 0 hondle is connected to the de.beoder such thot the
hondle sticks out ofthe pipe. The rod is supported byo number
of mild steel discs inside the pipe (smoller thon the HDPE pipe
diometer) for loterol stobility. The de-beoder is then ploced
inside ofthe pipe such thot it is obout 100 mm in front ofthe
prcposedjoint. Th€ rodius 0fthe cutting orms orc then
onong€d by sliding the bush such thot the blodes ole in contoct
with th€ inside pipe surfoce. once the blodes snugly fit on the
pipe surfoce, thel€ is o clicking sound indicoting thot the
cutting orms hove been locked. As soon qs the two pipe ends
orejoined by heot welding os discussed in Chopter 4, the de-
beoder is push€d forword till the blodes come in contoct with
the beods. The hondle is then tumed ond the de-beoder is
pushed forword which rcmoves th€ b€od.
Photo 10.2 weld beods on llDP! joint surfoce
146
This de-beoder wos tested ot Nepol Yontro sholo Energ]1Kothmondu, on o 200 rnm pipe os shown in Photogroph 10.4.De-beoding wos tried on o joint obout 2 m from one end 0f thepipe. the test wos portiolly successfi:1. It wos not possible toItmove the entir€ strip of the beod. Port of the beod ond somethin stronds were left on thejoint, qs con be seen in Phorogroph10.4.
Photo 10.4 HDPI pip€joint debeoded using the de-b€oder
The following observotions w€I€ mode in the workshop:
The mojor constroint wos thot the rodius ofthe cutter
blodes is nxed ond the blod€s do not work eouollv well
on oll pipe diomders within the ronge.
f d€-beqding is not stqrted immediotely ofter the pipes
oI€ joined (i.e. within 30 seconds), the beods connot be
Rmoved,
The tuming ofthe hondle ond pushing ofthe de-beoder
hos to be contmlled. A suddenjerk pushes the de-beoder
beyond thejoint.
The de-beoding process is olso homp€rcd ifthe pipe ends
ore not totolly circulor.
Hence, design improvements ore rcquird befoE tNs de-
beodercon be used in the field.
Commeftiol de-beoders ore olso ovoiloble but they ore
expensive. Some such commemiol de-beqders con olso remove
beods oft€r thejoints hove cooled (i.e. cold de-beoding). Photo-
gmph 10.5 shows q section ofon HDPE pipe which wos cold de-
beoded usino q commerciol de-beoder.
Photo 10.5 HDPE pip*joint deb€oded using o conmeniol deb€od4 fte smollring in fiont ofthe piF scction is rhe b€od.
turth€r informotion on commerciol de-beoden con beobtoined from:
Fxsion Gmup PLCChesterfield Troding Estote,chesterfield S41 9Pz,Englond, (JK
Faxt + aApl7246 4fi472
10.4 Bursting disc
As discussed in Chopter 6, p€nstock pipes for micm-hydroschemes ore designed to occommodote the surge heod whensetting the pipe thicloess. An incftose in th€ pipe thicknessolso increoses the cost 0f the pipe. Funhermore, depending onthe locotion of the site, drc tronsportotion cost olso incposes.In o high heod scheme with o long penstock olignment, theincl€ose in cost to cccommodote the sume heod con be sionifi-cont.
TheR or€ mony wdys to guord ogoinst surge domoge butmost involve significont cost (whm, for sofety I€osons the llowhos t0 b€ constroined) or involve greot colt in instollotion ondmointenonce.
The "bursti4 disc' technology moy pmvide o plioble
m€ons of sofely r€leosing the excess heod in cose ofsurgepressure. A "bursting disc" is q commerciolly ovoiloble over.pnssurc sofety device mqde fiom o bdttle moteriol such osgrophite or 0n oppropriote metol, or o suitoble metol which isd€signed to ruptuE extEm€ly quickly once o criticol pl€ssul€ isexceeded, such os the surge heqd induced inside the penstockpipe in the event of o j€t blockoge. Such discs or€ connmiollyused in the chemicol industry to protect pipdines ond pressure
147
Y
vessels (thqt conveygqs ond petroleum fluids) from high surge
pressure. Pipes thot hove bursting discs do not n€ed to be
designed to occommodote surge plessules. Photogrqph 10.6
shows o commerciolly ovoiloble bursting disc (including the
bu$t plote). Note thot scrotch lines qre mode in th€ plote
during monufocture to introduce weql:nesses in th€ plote such
thot it bursts occording to the pottern shown in Photogroph
10.6 once the Dresc bed pressure is reoched.
Photo 10 6 A commerdolly ovoiloble bursting disc
Most grophite discs ore flot, deform very slightly under o
pressurc differcntiol ond becouse oftheir physicol pmperties, ot
the set plessule sh€or instontoneously oround the periphery of
the disc octive orco giving imm€diotely full bore venting. Such
discs orc suitoble for verting ofboth liquids ond goses. The disc
is monufoctured to burst within its toleronce onJy when
instolled in o suitobly designed ond monufocturcd holder
some ofthe moin odvontoges ofgrophite bursting discs
ore thot they ore not odversely offected by misoligned pipe
work or ov€rtorquing ofpipe flonge bolts. Due to the sum-
ciently high burst pressure, this type ofdisc does not requirc
bockpressure support to withstond full vocuum pressure. The
discs hove 0n operoting rotio of90% qnd ore guoronteed to
rupture within o moximum of30 milliseconds.
The discs ore qlso inexpensive ond in cose ofrupture due
to surge pressure, oll thqt is pquired to recommission the pipe is
to Rploce the grophite plot€. Henc€, this technology could be
highly suitoble for micro-hydro schemes including those locoted
ln remote oleos.
Theoreticol res€orch on the opplicobility ofbursting discs
for micro-hydro schemes hos been undertoken by Dulos in
conjunction with worwick Universiry The bursting disc
orrongement proposed by th€ study is shown below in Figure
10.2.
FigurE 10.2 Proposed orrongement for buNting disc instollotion in micrc-hydmschemes
Note thot in cose ofthe rupture ofthe disc, the flow
would dischorge inside the turbine cssing. such on orronge-
ment is well suited in micro-hydro schemes since o seporote
flow control structur€ is not required.
The comlusions ofth€ obove study werc os foUows:
. The disc could reduce surge pressure by 60% - 70% ifthe
subsequ€nt flow rote through the bronching orronge-
ment is only moderotely reduced. The rroson why the
entirc surge heod connot be eliminoted is becouse the
diometer ofthe disc is usuolly smoller thon the penstock
diometer ond hence the flow is reduced.
r The penstock sofety fqctor could be Educed from 3.5 to
2.5.
These theoreticol findings need to be thoroughly verified
by octuolly instolling the discs in existing micro-hydro schemes
ond monitoring the rcsults. ITDG Nepol hos plons to field test
the bursting discs in some existing micro-hydro schemes.
More informotion on the opplicobility ofbursting discs
for micm-hydm schemes cqn be obtoined from Dulos Limited
(some oddrcss os obove).
Informotion on commerciol bursting discs con olso be
obtoined from the following manufocturer:
IMI Moffton Limit€d
Woboston Rood, Fodhouses,
Wolverhompton WV10 6QJ
Englond,lx
Fox: + 44 l0) 7902 397?92
10.5 Flexible steel supportpier for Jhorkot micro-hydro
The 36 kWJhorkot micro-hydro scheme is locqted in Mustong
District, Nepol. This is o community owned scheme ond is
monoged by the Jhorkot Elect ncotion committee. ITDC Nepol
hos been involved in providing technicol support for refurbish-
ment work of this scheme for some time.
148
Similor to other oreos of Mustqng, the topogrophy of theproject oreo consists of frogile ond unstqble slopes ond is prone
to londslides. The intoke ond the initiql heqdrqce conol have
been domoged frequently by Iondslides ond floods.
Although the slope olong the penstock olignment is
relotively stoble compored to the intoke oreo, it is weok ond
0ls0 prone to lqndslides. The existing mosonry support piers
storted sinking due to their own weight os well os the weight of
the penstock pipe ond the woter inside it. Hence, the penstock
(flonge connected) storted to sqg qt vorious ploces.
As port ofthe preporotion ofthis text, o pilot project wos
corried out to design qnd instoll steel support piers for the
Jhorkot scheme with ossistonce from Mr. Shyom Roj Prodhon of
NYSE. The design criterio were os follows:
r The support pier hod to be light, to minimise self-weight.
r It hod to be fobricqted using ports thot could be corried
by porters or mules. Jhorkot is obout holf o doy's wolk
from the district qirport ond 5 dovs'wqlk from the
neorest roodheod.
r The design hod to sllow for the
sinhng of the foundotion. ln
cose ofsinking ofthe ground
below the foundotions, the piers
should not pull the penstock pipe
down olong with it.
The design ofthe support pier ond
the foundotion ore shown in Figures 10.3
ond 10.4 respectively. The totcl weight
ofq 2 m support pier is 60 kg (excluding
the foundotion work) whereos o
mosonry pier of simiior height would
weigh 4000 kg.
Note thot such support piers
should be instolled perpendiculor to the
penstock clignment (not verticolly) since
they ore only resisting force F, (see
Chopter 7).
Figup 10.3 Flexible steel support pier for
Jhorkot micro-hyd ro scheme
The top section of the pier consists of o chonnel which is
pin connected to two legs thot hove turnbuckles. The penstock
pipe rests on the chonnel qnd the pin connection ollows the
chonnel some rototion such thqt it is perpendiculor to thepenstock olignment. Two holes hove been provided on the
chonnel to clomp the penstock with o 12 mm diometer bor. The
turnbuckles con be odjusted to fine tune the height ofthe
support piers (up to 300 mm) during instollotion ond in cose the
foundction sinks in the future.
The bottom of the turnbuckles (40 mm rods) Iit inside o
hollow pipe os shown in Figure 10.3. In cose the ground
beneoth the foundotion sinks, the suppofi pier structurr below
the turnbuckles drops down olong with the foundotion ond
only the top port (up to the turnbuckle legs) hongs with the
penstock. Hence the penstock pipe is not drogged down with
the pier in cose ofsinking.
The bottom port of the pier consists of ongles which orr
bolted bock to bock (Figure 10.3). Bolt holes ot o distonce 0f150
mm ore provided for coqrse adjustment of the pier. The bottom
eaO arF
ffiE_
alcrDx A. a
. l O O E A l ! . O n
K
149
stclo|l t-A
t's€qnoN 8- B
Figure 10.4 Foundotion forthe Jhorkot fl exible supportpler
ongles orc pin connected to the foundotion so thot the moments
due to thermol exponsion 0fthe penstock pipe oI€ not token by
the support pier or the foundotion. During instollotion os well
os loter in cose the foundotion sinks, coo$e odjustment con be
mode using the bolt holes ofthe bottom ongles ond then fine
tuned using the turnbuckles ot the top.
The top ond bottom ports ofthe pier hove fixed heights.
The length ofth€ middle portion (ongles bolted to chonnels)is
voried such thot the totol pi€r height is €quol to th€ required
height. Note thor this support pier con be dismontl€d such thot
therE ore 12 individuol pieces (including the 12 mm stinup bor
to connect to the penstock).
18 support piers ronging fmm 1.0 m to 2.6 m height hove
been fobdcoted bosed 0n this design. To ensup thot the support
pier would function well. one (2.5 m totol height) wos tested ot
the mqnufqctuEr's workshop (iIYSE) os shown in Photogrophs
10.7 ond 10.8. About 500 kg ofoxiol lood (moximum
compressive lood expected on the pier) wos opplied on the pier
There wos no observqble effect on the pier (d€formotion or
deflection of ongles) during the test of obout 2 hours. lt wos
even possible to roise the height ofthe pier by rctoting the
turnbuckles with the full test lood 0f500 ka.
As ofJu.ly 1998, oll 18 support piers hove be€n instolled otthe Jhorkot scheme. Th€ir p€rformonce is currently beingmonitored.
Photo 10.7 Lood test ofsteel support pier (side el€votion)
150
$I
10.6 PVC pipes
PVC pipes ore fr€quently us€d by Intermediote Technology forp€nstocks in its micro-hydro progromme in the northem Andes.one ofthe first schemes to benefit wos Choldn. This projecthoso copocity of25 kW ond o heod of96 metr€s. The p€nstockdiometer is 200 mm. Connection of pipe lengths wos throughglued spigot ond socketjoinrs. On commissioning, it wos foundthot pinhole leoks oppeored in thejoints. o prcblem thot wos0ddressed through the qpplicotion ofodditiorql resin. Thewhole length ofthe penstock wos buried for protection fromsunlight, onim0ls ond oth€r potentiol sources ofdomoge.
10.7 Anchor block design
'lhe stobility colculorions for onchor block design ore rime
consuming. A spr€odsheet progrom for the stobility onolyseshos b€en written byJohn Bywoter to spe€d up rhe pmcess.
To dqte there is no monuol to occompony the progrom,nor evid€nce thot it hos been verified. However, the progromwos used to veriry th€ guidelines given in S€ction 7.4.4. forsizing 0nchor blocks for smoll schemes.
Photo l0E toqd test ofsreelsuppon pief (front elevotion)
151
11. References
1. Adom Horvey et.cl. (1993), Micro-Hydro Design Manual, A 5. Design Manuals for lrrigation Projects in Nepal (1990),
guide to small-scale water power schemes, Intermediote Plonning ond Design Strengthening Project (PDSP), His
Technology Publicotions, ISBN 1 85339 103 4. Mojesry's Government of Nepol, Ministry of Woter Re-
2. Allen R. Inversin (19861, Micro-Hydropower Sourcebook, A sources, Deportment of lrrigotion. Unit€d Notions Develop-
Practical Guide to Design and Imflementation in Develcp- ment Progromme (NEP/85/013)/World Bonk.
ing Countries, NRECA Internotionol Foundotion, 1800 6. Salleri Chialsa Small Hydel Project (1983), Technicol Report,
Mossochusetts Avenue N. W., Woshington, DC 20036. DEH/SATA, rmco.
3. Helmut Louterjung/Gongolf Schmidt (1989), Planning of 7 . PN. Khonnq (lffil, Indian Practical Civil Engineer's
Intoke Structures, GATEIGTZ, Vieweg. Handbook, l5'h Edition, Engineer's Publishers, Post Box 725,
4. Itethodologies for estimoting hydrologic charscteistics of New Delhi - 110001.
ungouged locations in Nepol (1990), HMG ofNepol,
Ministry of Woter Resources, Woter ond Energy Commis-
sion Secretqriot, Deportment ofHydrology ond
Meteorology.
153
Appendix A - Flow estimation
A.1 WECslDeportment of Hydrology andMeteorology (DHMI method
41.1 PROCEDURE FOR ESTIMATING INSTANTANEOUS
FLOOD PEAK
i. From ovoilqble topogrophic mops, find out the cotch-
ment oreo (km'z)below 3000 m elevotion.
2. In the following equotion, input coefficients from Toble
A1.
Q = o (Areo below 3oo0m * 1) m3/s
where subscript o is either 2 veor or 100 veor return
period.
Toble A1 Prediction coefficients for instqntsneous flood
flows
RETURN PERIOD (YEARS) CONSTANT
COEFFICIENT (a)
POWER (B)
I
1
100
3. Flood peok dischorge, Q", for ony other return period con
A.I.2 PROCEDURE FOR ESTITUATING FLOW DUMTION
CURVE
1. From ovoiloble topogrophic mops, find out the cotch-
ment oreo below 5000 m elevotion.
2. Use the following equotions to colculote the flows. The
volues of monsoon wetness index cqn be reod from
Figure A3. Q* is the dischorge (m'/s) for the specified
probobility of exceedence.
hq* - -3.5346+0.9398.In (Areo below 5000 m*1) +0.3739.
In (Monsoon wetness index)
lnQro. = -3.4978+0.9814. In (Areo below 5000 m* 1) +0.2670.
In (Monsoon wetness index)
lnQ,* : -5.4357 *0.9824.In (Areo of bosin) *0.4408. In
(Monsoon wetness index)
lnQ* : -5.9543+1.0070. In (Areo of bosin) *0.3231.In
(Monsoon wetness index)
lnQ** : -6.4846*1.0004.In (Areo of bosin) *0.3015.In
(Monsoon wetness index)
lnQ** = -4.8508f 1.0375.In (Areo below 5000 m+1)
ln%rru = -5.4776*1.0776.1n (Areo below 5000 m+1)
.61 = -o.oe8e2 +0.0814e. @'xtcrnr
AI3 PROCEDURE FOR ESTIMATING IONG TERM
AVEMGE MONTHTY FTOWS
1. From ovqiloble topogrophic mops, find out the cotch-
ment oreo below 5000 m elevotion.
2. In the following equotion, input coeflicients from Toble
A3 ond the volues of monsoon wetness index from
Figure A3.
Q,.on,on,h: C. (Areo of bcsin)Ar. (Areo below 5000 m*1)Az.
. (Monsoon wetness index)t
where subscript month denotes one of the months from
jonuory to December. A power of 0 indicotes thot porticulor
porometer does not enter into the equotion for thot month.
7.8767
14.630
0.8783
0.7342
i':'fiI'll"ii'"n'.(Ln &2T s'c..qr)where S is the stondord normol voriqte for the chosen
return period, from Toble A2, ond
, / Q , * \r n r - I\ Q , t
-rnqF - 2.326
Toble A2 Volues of stondqrd normal voriate for vsrious
return periods
RETURN PERIOD (T) (Yrs) STANDARD NORMAL VARTATE (S)
2
5
10
z050
100
200
500
1000
5000
i0000
0
0.842
1.282
1.645
2.054
2.326
2.576
2.878
3.090
3.540
3.779
155
Table Al Ptediction coefficients for long t€rm qvercge monthly flows
MONTl{ CONSTANT
COEFFICIENT
POWER, AREA OF
BASIN (km1
Ar A2
POWER, AREA OF BASIN
BELOW 50fi) m +1 (km1
POWEROFMONSOON
WEINESS INDEX
4JonuoryFebruoryMorchAprilMoy
JuneJulyAugustSeptember0ctoberNovemberDecember
0.01423
0.01219
0.009988
0.007974
0.008434
0.006943
0.02123
0.02548
0.01677
0.009724
0.001760
0.001485
0
0
0
0
0
0.9968
0
0
0
0
0.%05
0.9s36
0.9777
0s7ffi
0.99r8
1.0435
1.0898
0
1.0093
0.9963
0.9894
0.9880
0
0
000000.26100.25230.26200.28780.25080.39100.3607
Note: units of flow ore m3/s
A.2 Medium lrrigation Projectmethod IMIPI
Procedure for estimoting meon monthly flows of o selected
cqtchment.
1. ln the low flow period from November to April, visit the
cqtchment in question ond moke one flow meosure-
ment. Ensure thot there hos been no heovy roinfoll
during the preceding few doys ond thot the woter level
is not fluctuoting ropidly.
2. Ascertoin ifthere ore significont upstreqm obstrqctions,
ottempt t0 quonriry them ond odd this omount t0 the
meosured flow
3. Estqblish in which hydrologicol region the cotchment
lies, from Figure A2. Divide the mecsured flow by the
non-dimensionol hydrogroph ordinote (Toble A4) for the
oppropriote month ond region. If the flow mecsurement
wos conducted ot the beginning or the end of the month,
it moy be necessory to interpolote between the two
relevqnt ordinotes from Toble A4. The result represents
the meon April flow to be expected in thot cotchment.
Tqke the April flow colculoted in step 3 ond multiply it
by eoch non-dimensionol ordinote from Toble 44. The
result is the hydrogrcph of meon monthly flows.
It is usefirl to compore the hydrogroph colculoted in step
4 with the oppropriote regionol hydrogroph depicted
omong Figures A4 to A10. To do this, divide eoch
ordinqte ofthe cotchment hydrogroph by the cotchment
oreo. Normolly, the colculoted hydrogroph will corre-
spond to the regionol hydrogroph within the limits
indicqted. The limits mcy be used os c rough guide to
the reliobility of flow in the cotchment. If the
hydrogroph lies outside the limits then it is not typicol,
due perhops to unusuol lond use or o typicol detoil of
topogrophy ond geology.
156
Tqble A4 Non.dimensioncl regionol hydrogrophs
MONTH RECION
JonuoryFebruory
Morch
April
Moy
June
JulyAugust
September
0ctober
November
December
2.40
1.80
1.30
1.00
z.ov
6.00
14.50
25.00
16.50
8.00
4.10
3.10
2.24
L . ( V
1.33
1.001 ) 1
7.27
18.18
27.27
20.91
9.09
3.%
3.03
2.77
1.88
1.38
1.00
1.88
3.13
13.54
25.00
20.83
70.42
5.00
3.75
2.59
1.88
1.38
1.00
2.19
3.75
6.89
27.27
20.97
6.89
5.00
3.M
2.42
t.82
1.36
1.00
0.91
2.73
77.27
13.94
10.00
6.52
4.55
3.33
2.03r.627.271.002.576.0824.3233.7827.035.083.382.57
3.30
2.20
1.40
1.00
3.50
6.00
14.00
3s.0024.N
t2.N
7.50
5.00
ttI
tfi
A3 Design exomple
Cotchment nome
Cotchment locotion
Hydrologicol region
Bqsin qreo
Areq below 5000 m
Areo below 3000 m
Monsoon wetness index
Month ofgouging
Flow meosured
Q,o = e (nroo+z.oN W)=362 mr/s
bl FIow dumtion anrveSolu Kholq
Solukhumbu
3
330 km'z
308.5 km'z
97.7 lglrr'z
1500
April
2.8 mr/s
052040608095100
PROBABILITY oF EXCEEDENCE (%) DISCMRGE (m3/s)
98.4559.3332.629.474.583.002.031.78
exomple:
lnQ*: -3.4978 + 0.98141n(308.5+1) + 0.26701n1500 =
4.083+Q=gr 'oer=59.33lnQo* = - 5.9543 + 1.00701n(330) + 0.3231 1n1500 = 2.248 ->
Qn= e22a - 9'47
ln%r*= -5.4716 * 1.0776 ln(308.5+1) :0.708+Qrr= eo",= 2.03
Q,* = [-0.09892+ 0.08149x r/1:ot.s+t112 = l.z8
Figure A1 shows the cqtchment mqp.
A3.l WECSIDHMPROCEDURE
alFTod flows
RETURN PEUOD (Yrs) INSTANTANEOUS FTOOD
DTSCHARGE (mr/s)
2
5
10
20
50
100
106
175
228
283
362
426
exomple:
q= L8767.(97.7+l;o.rar : 106 m3/s
Q,* = 14.63'(9?.7 * 7)oB2 : 426
t t l
cl Long term sverage discharges
MONTH LONG TERM AVEMGE DISCMRGE (m3/s)
JonuoryFebruory
Morch
April
Moy
Junejuly
August
September
October
November
December
Annuol
3.88
3.30
3.00
3 .17
4.37
I ) . t /
43.86
52.45.tu.v I
77.59
8.06
5.24
16.68
exomple:
Qn,"on j,ry = 0.02123.(330)0.(308. 5 + 1)' 0nq1{ I 500)0 ,5,r = 43.86 m3/s
4.3.2 MIP PROCEDURE
Estimcting the hydrogroph of meon monthly flows
tt!
I
I
II
I
NON.DIMENSIONAI
HYDROCRAPH
MEASURED FIOW
(m'/s)
PREDICTED APRIL FLOW
(m'/s)PREDICTED HYDROGMPH
(m'is)
JonucryFebruory
Morch
April
Moy
June
JulvAugust
September
October
November
December
2.71
1.88
1.38
1.00
1.88
3 .13
13.54
25.00
20.83
10.42
5.00
3.75
2.71 x23 : 7.59
5.26
3.86
2.80
5.26.
8.76
37.97
70.00
58.32
29.18
14.00
10.50
i,2.8 2.8/1.00 = 2.8
A33 RESUTTS
1. The dry seqson m€qn monthly flows colculoted by the
WECS ond MIP methods ore presented in the toble ond
figure below. WECS shows c slightly higher figure thon
MIP for the month of April. By definition MIP shows the
meosured flow. Experience shows thot results obtoined
by WECS ond MIP methods vory for different cqtchments
ond it moy not be olwoys true thot MIP yields lower
vqlue thon WECS. It is worth mentioning thot Solleri
Chialso mini-hydro scheme uses o design flow of 2.5 m3is(Ref.6).
iiL
158
WECS MEASURED FLOW
October
November
December
JonuoryFebruory
MorchAnril
Mqy
I I . )v
8.06
5.24
3.88
3.30
3.00
3.17
1 . ) I
29.18
14.00
10.50
7.59
5.26
3.86
2.80
5.26
2.80
HYDROGRAPH OFMEAN MONTHLY FLOWS
2. The design flow of 2.5 mr/s is exceeded 857o of the time,
occording t0 the WECS flow durotion curve.
FLOW DURAIION CURVE
Flow (m3/s
35 f -
,|\-*f\2 0 -
"f-I1 0 r -
sLs l -
0d
[ , w a - w ]
159
|{I,:
FiguTe A1 CATCHMEI,TT OF SOLU KHOLA ABOVE Tl{E SALLERI CHTALSA INTAKE
160
B.E6 >: r r ih 7
ts
a
Key:
1. Mountoin cotchments
2. Hills to north of Mohobhorots
3. Pokhoro, Nuwokot, Kothmondu, Sun Koshi tributories
4. Lower Tomur Volley
5. River droining Mohobhqrots
6. KqnkoiMoibosin
7. Rivers droining from Churio ronge to th€ Teroi
BItt
II
II
iII
IE\III
J gr { io - El r t iZ o "
o
5
IIIIII
IiIItt , - ._ - . . -_ -_- - - -
I
'i --l
Figure 43 Monsoon wetness index isolines
(Source Ref. 4)
,6
5
i ,I
Il .1, ,I
t )t \t )i : 'l J
l l. l i{ ;t ;; i. a
i lu a. l ;
l ri . l
_9
- i
H }{ *Z A ?
9 3 8
t
s tT !? !t - E
r62
AprMarFebJanDecNov0ctsepAugJulJUnMay
1000
N
=YDJo(l'(r= 100o
lJ-
->co=
10
MOUNTAIN
Mean
Flow
Mean
\ [ f
A
\o
Figure A4 Meon Monthly Hydrogroph - Regi0n l
(Source Ref.5)
TAIN CATCHMENTS
alHills to North otOlBivers
Inner I
r 000
q
=YaJ(D
(qE { ^ ^= t u votr
c,o=
10
th of Siv
I
I
\
Max
I
I
I
I
I
I
I
I
I
J-
) -
\ \)
l \
MrMrFI
-\J
an1SO0n
ivl
Mean ,I
Min
)
l
) :l \ f
a -
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Figure A5 Meon Monthly Hydrogroph - Regi0n 2
(Source Ref.5)
164
1000
N
=VaJ<1,(g
CE= 100Ilt
=co=
r0
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Aor
80%
Figure 46 Meon Month.iy Hydr€gfoph - Region 3
(Source Ref.5)
+- -
165
1 000
N
=YaJ(l,
(q(r=ou-=co=
100
10
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
(
Figur€ A7 Meon Monthly Hydrogroph - Region 4
(Source Ref.5)
166
1 000
N
=YU)Jo(g
CE= 100o
lJ-
=co=
10
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Aor
alRivers
20% /
Mean
Figure A8 Meon Monthly Hydrogroph - Region 5
(Source Ref. 5)
{ - -
167
KANKAIIMAIBA$IN
1 000
N
=:<aJ(D
oE=otrtEo=
100
10
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
- r \/ l \
\\
Mean
Flow
I 1l 1
I t
I
II
I
\ 1l 1l \
\\\ \20To
Mean
Figure A9 Meon Monthly Hydrogroph - Region 6
(Source Ref.5)
,t
L
_tbd
=--4--
)!
E
l/:\
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
TAIN
FarWestEast
A
i
lI
,-J'
May Jun
,/1
III
I
100
1 0 I
N
=Y(nJ<t,(q
E=ot L
-cco=
I - i.l 'l
- i . Ji /v
a,'l
I
I4/l ,t,'
TCHMENTS
Mean
Flow
\ r l
A
\o
Figur€ A10 Mecn Monthly Hydrogroph Region 7
(Source Ref.5)
i
169
Appendix B - Stqndqrd pipe sizesmsnufqcturers ond
suppliers
List of Tables los of March 19991
Nepothene HDPE pipe price l ist ond weight chort
Ponchokonyo HDPE pipes
Ponchokonyo PVC pipes
Hll 'CO/Hulos steel woter PiPesHll)COiHulos structurol steel pipes
B1
B3
B4
B5
B6
t71
-I
F A C T O R Y ; .
Ba la j u l ndus t r i a l D i5 t r i c t :
Ba la j u , Ka thn raodu , Nepa l .
Phone ; 350091
I
t
!
;I
IP'r. l LtJ.NtpdDEZruo
zuTPAt |JOLYITIIINE tI I)TASTII IruOtjSTftITSM a n u f a c t u r e o f H D P E P i p e s
TIF.AD OFFICE .
P o s t B o x N o . l 0 l 5
I ' r ipureswor . Kathmandu
P t r o n e : 2 6 1 > 0 1 , 2 6 1 1 4 9F a x N o . 0 0 9 7 ? - l - 2 6 1 8 2 8Te lax n 'o . 2365 KHANAL NP
Nepothene l- I igh Density Polyetbene Pipe Manufactured as per NS 40/010Price for H. D. P. E Pipes Manulactured as per NS 40/040
PR. ICE L IST
Outs ideDiamcter
( m m )
l 5 m m
S E R I E S
Working Prc2.5 Kgf/cm
W"ll Th',- Ikness I
M i n . M a x . I
I I
ssure. s q .
Price/Mt r .
Rs:. Ps.
SERIES I I t
Working Pressure4 Kgf.;cnr. sq.
_.-._--.-_.--.-Wall Thic- | Pricc
kness I /Mtr,Min . Max. I Rs . Ps .
SERIES IV
Working Pressure6 Kgficn. sq.
Wal l Th ic - | Pr icckoess | /Mt r .
M i n . M a x . I R s . P s .l -
S E R I E R
S'orking Prtl0 Kgf/cm
--.-Wal l Th ic - I
kness IM i n . M a x . I
- t .
2.0
v
rssu rc. s q .
Prl. ./Mt r .
Rs . Ps .
l t . l J
l0 inm i " 2 .3 2 .8 l o 2 l
2 5 m m i 2 . 8 3 . i 2 4 . 4 4
i 2 m m l " 2 . 3 2 . 8 27.35 3 .6 4 .3 40.4 I'
{c.;; l ,J' 2 .0 2 .4 30.37 2.9 3.4 42.35 4 . 5 5 . 2 6 7 . t 9
5Ornni l ) " 2 9 45.74 3 .6 4 .2 6s.5.8 5 . 6 6 . 4 96.32
b J M M Z
'2.0 2 .4 4 8 .76 3 0 3 . 5 70.7 ) 4 . 5 5 . 2 r02.85 7 l 8 . 1 I 5 3.55
/ f m m l (1 1 t Q 67.40 3 . 6 4 , 1 I 0 2 l 7 { 1 6 . 1 144. t I 8 . 4 o s 2r5.62
SOmm 3" l R 1 ' t 96.6S 4 . 4 ( ) 147.62 6.4 ' t .3 207.16 l 0 . l I t . 4 3 r 0 .71
l lOrnm 4" 3 .4 4 0 I 4 1 . 3 9 5 . 0 5 .8 206 06 7 . 8 8 8 30?-95 tz.41 3 . 9 459.9
l25rnrn 4|" 3 . 9 4 . 5 t s5I 3 6 . 0 6 . 8 276.97 E.9 l0 .E 398.45 l 4 . l 1 5 . 7 600.40
l4Onrnt 5" 4 . J 5 . 0 2.29.)4 6 8 351 .02 9.9 l l s02. I 5 15. E t7.6 7t5.29
l60mm 6" 4 .9 5 .6 296.8 r 7 8 8 . 8 4 5 6.53 1 l . l 1 2 . 7 64?.96 r8,020.0 917.56
J80mnr 7" 5 .6 6 .4 Jdu.y I 8.7 9 8 57 6.20 1 2 . El 4 . l 822.80 20.J 22,6 I 240.98
200mm 8" 6 .2 7 .1 q o d . 6 6 9 . 7 1 0 . 9 7t2.69 i r 1 I 5 . e l 0 l 22 5 25.0 I 527.02
225mm 9" 6 .9 7 .8 1 0 . 9 1 2 . 2 900.85 r 5.9 I t . t r 27 5.32 25.4 2S.2 937.69
250mm 10" 1 ; l 3 .8' t7 '1 .45 t ' ) I I 1 . 6 1 l 1 1 . 6 3 t7.'l 1 9 . 7 r 5 i7.96 28 .2 3 r . 3 2390.60
280mm l l 8 . 6 9 . 1 903.99 l l . 5 1 , 5 . 1 1386.06 19.8 22.0 l 975 .57 3 1 . 5 3 4 . 5 2989.6 7
3 l 5 n r m 1 2 " o ? r0.8 I I 39 .46 t 5 . 2 1 7 . 0 1 7 5 5 . 4 7 22.t 24.8 2501,97 36.4 J9.2. 3770.36
l 55mm t 4 t :
r00mm l6l;
10 .9 !2 .2--rL3
ll.s
I 446.80
l84rJ4
I 7 . t 1 9 . I
1 9 J ' l - s -
?224.22-?s24
J0
25.1 21 .9
283 3t .4
3 I 75.40
4010 39
39.9 44 . I
45 .0 40 .7
4'195.84
609 r .62
Ternrs & Cond_t t ig" t j -
l . l0% Tax rv i l l bc charge extra.
2. Thc pr ice are ex-factory pr ice excluding salcs tax & contract tax '
3 . Sub jec t t o Usua l ' Fo rce Ma jo r cond i t i on '
+. pr ice arc Subject to changc qi th out not icc, 25ld aclvrncc should bc peid at lhe t inte of order ing of goods and
balaoce should be paid before del ivery.
* Thase sizas arc not heina manttfacjttrad at nreqcnt
173
SERIES SERIES SERIES SERIESOutsideDiameter
Working Preszure2.5 Kdlcm sq.
Working Pressure4 Kef/cm so.
Working Pressure6 Ksf,/cm sq.
Working Preszuro10 Kef/cm sq.
rtm Wall ThicknessMin. Max. Weieht
Wall ThicknessMin. Max. Weieht
Wall ThicknessMin. Max. Weieht
Wall ThicknessMin. m&x. Weieht
16 rnm 2.0 2 .4 0.09220 mm 2.8 0 .13425 mm 7 .8 J . _ 1 0.20232 nnn 2 .3 2 .8 0.226 3 .6 4 .3 0 .33440 rnm 2.0 2 .4 0 .251 2 .9 3 .4 0 .350 4 .5 5 .2 0 .51450 rnm 2.4 2 .9 0.378 3 .6 4 .2 0 .542 5 .6 6 .4 0.79663 mm 2.0 2 .4 0.403 3 .0 3 .5 0.585 4.5 5 .2 0.850 7 .1 8 .1 r .26975 nun 2.3 2 .8 0 .557 3 .6 4 .3 0.846 5 .3 6 .1 i . t91 8 .4 9 .5 1.78290 mm 2.8 J . J 0.799 4.4 5 .2 I J 1 n 6.4 7.3 r .717 10.1 I 1 .4 2.568
110 mm 3.4 4.0 l . 185 5 .0 5 .8 1.703 1.8 8 .8 2.545 12.4 13 .9 3.801125 mm 3.9 A < 1.530 6.0 6 .8 2.289 8.9 10 .8 3.293 L4 I 15 .7 4.962140 nun 4 .3 5 .0 1 .897 6 .8 7.7 2.901 9.9 I t . r 4,1 50 I5.8 L ' t .6 6.209160 nrn 4 .9 5 .6 2.453 7 .8 8 .8 3.773 11 .3 12 .7 5 .355 18 .0 20 .0 8.079I80 mm 5.6 6 .4 3 . I 4 8 8 .7 9 .8 4.762 12 .8 14 .3 6.800 20.3 72.6 10.256200 mm 6.2 ' I ,T 3 .87 5 9 .7 10 .9 5.890 r4 .2 15.9 8 .391 22.5 25.0 12.620225 mm 6.9 7.8 4.822 10.9 12.2 7.445 l s .9 L7 .7 I 0 .544 25.4 28.2 r6 .014250 mm 7.7 8 .8 6.012 12.L 13 .6 9 .187 t7 .7 19 .7 13 .04 i 28 .2 31 .3 19.757
PANCHAKANYA PI-ASTIC IND. [P] LTD.I Manufaoturer of HDPE Pipes & Accessories ]
Pipes Manufacturored as per NS 40/040
IIEAD OFFICE: J3/12 Krishna Gallt, Lalitpu, P.O. Box. No. 2743I(othmandu, Nepal.Phone 52635'7,52511L Fax No. Slj.529.E-mail : [email protected] om.np
FACTORY: I-nmini Zane, Kotihawq Bhairahawa, NepalPhone (071) 60368. I 'ax: 605?d
I
174
I
PANCr{AKANYA ROTOMOULDS [PJ LTD.[ \4anufactr-u'er of uPVC Pipes & Aooessories ]
Pipes Manufactruered as per NS 206/046
IflAD OITICE: J3l12l(rishna Galli, Lalitpur, P,O. Box. No. 2743l(athmandu, N"pal.Phone 526351,52571L Fax No. 52.6529.E-mail: [email protected]
FACTORY: I-uminl Zone, Kotihawq Bhatrahawa, Nepal.Phone (0?1) 60368, Far: 6057{.
Class - I Class - 2 Class - 3 Class - 4OuGideDiameter
Working Pressure2.5 Keflcm so.
Working Pressure4 Kef/cm sq.
Worlcing Pressure6 Kpflsm sq.
Working Pressurei0 Kef/cm sq.
ln rnrn Wall Thickness\,Iirt. Max. Weielil
Wall ThicknessMin. Max. Weieht
Wall ThicknessMin. Max. Weieht
Wall ThicknessMin. max. Weielrt
20 rnm 1.1 1 .5 0.11 i25 mm t.4 1.8 0 .1 7032 mm 1 .8 2 .2 0.27040 rnm r .4 L8 0.28 i 1 ) , ) ' 1 0.41650 nu-n L - l 2.1 0 .418 28 J . J 0.64763 rnm 1.5 I .9 0.474 2.2 2 .7 0.668 3 .5 4 . t I .01075 rnm 1.8 2 .2 0.660 2.6 3. r 0.931 4 .2 4 .9 1.44390 rtun t a
L J t .7 0 .606 2..r 2.60.944 3 . i 3 .7 r .334 5.0 5 .7 2.&18110 mm 1.6 2 .0 0.894 2.5 3 .0 1 .369 3.7 4 .3 1 .938 6 .1 7 .0 3.077140 rnm 2.0 2.4 1 .413 3.2 3 .8 2.2?3 4.8 5 .5 3 .1 78 7.7 8 .7 4.955160 mm 2.3 2 .8 l.884 3.7 4 .3 7.94'l 5.4 6:2 4 .139 8 .8 9 .9 6.456180 mm 2,6 3 . r t . 5 5 3 4.2 4 .9 3.474 6. t 7 .0 4 .961 9.9 t 1 . r 7.830200 mm 2.9 3 .4 2.945 4 .6 5.3 4.563 6 .8 7 .7 6.464 11.0 t2 .3 1 0 .1 85
175
CtuGAs Steel Industries P. Ltd.G.P0.Box:4129, Kantipath, damal,Kathmardu, Nepal. Tel:977.1-253047, 228389,24U52,252475,252850, Far 9I/-1.22061 2Fac1ory: Simra, Bara, Tel: 977-53-20075, 20078,20170, Fax 977-53-20160
GATVANISED AND BLACKSl'El jL PIPES I 'OR ORDINARYUSES TN VATER, CAS AtR&STEAM LINtsS
TYPE NOTVIINALBORE
WALLTHICKNESS
APPOXOD
WEIGFT OFBLACK PIPEPLAIN EI{D
WEIGET OFGALVAMSI,D PTPE
THREADED &s(}rxx'.Tr'.D
CLASS M M TNCB M M MM KG/M MTR/T{.' KGIM MTR/II{.7
L IGHT' A '
1 5 1n 2.00 21.30 0.9? t050 1 .01 990
20 3t4 2.35 z o . w 1 _ 4 1 709 1 .48 o / D
z o J 33.70 2 .01 498 ? . 1 1 a74
32 l v , 2.65 4?.40 2.58 388 2.72 355
40 1 t a 48.30 3.25 308 3 . , 1 1 2812 9 0 60 30 4 1 1 213 4 3 3 222
65 2 t a 325 76 20 5 8 0 172 6 1 1 5 5
80 3 3.2s 88.90 6 . 8 1 117 7 .21 133100 4 3.65 1 1 4 . 3 0 9.89 1 0 1 10.49 9 1
I } lEDIUM' B '
1 5 21 .30 t . ?? E20 1 .28 7813t4 z o f , 26.90 t . 58 533 1 .65 o@
t < 3.25 33.70 2.41 4 1 0 2 5 4 394
32 - t 2 l 12 10 3 t 3 1 8 3.27 29240 1 , 4 3.25 48.30 ? A I 277 3.77 25150 3.65 60.30 5 .10 196 532 1 7 S
65 3.65 76.?O 6.51 154 6.82 110
80 3 rl 05 88.90 8.47 118 8.87 107100 4.50 1 14.30 12 .10 E3 12.69 75
4.85 139.70 16.20 62 16.95 55r50 6 I 4 8 s 16s 10 | 1s.20 | s2 l 20.00
IIEAVY'c '
20 3t4 J Z J 26.90 't.90 1 .97 508
25 4.05 33.70 2 .97 336 3 .07 3263Z 4.05 42.40 3.84 2& 3.97 23940 1 , 4 4.05 r18.30 .1.43 226 .1.59 201
)U 4.50 60.30 6 .17 t6? 6.39 1 4 E
65 2 ' a 4.50 76.20 7.90 127 8 .21 1 1 5
80 3 /t 85 88.90 10 .1 0 99 10.52 90
r00 1 5..10 1 1 430 14. /10 69 15 aa 63
125 5 5 4 0 139 70 17.80 56 t8 s2 5 1rso 5 r o 165 10 1 ) O A7 2 ) ? 2 12
200 mm (;Al,v^}'|lsl.:t) ^}{I) IILA(;K ST[tiL PIPTS (Detalled speclflc.tlon on requesl)
200 8 5.20 219 .10 27.71 36 29.20 3?2rn 8 5 0 0 2 1 9 1 0 31 82 31 aa2r] 28
Notee:1) Tenslle Strength: Tenslle slrength for water lubes when tested frorn etrlps, cut out from selected
tubes shall be more than 320 rVmm'.2) Tolerances: a) Thickness: Ught lubes: (+) not limited, C) 8% max.
Medium & Heavy prpes: (+) not limited, (-) 10% max.b) Weight: Single tubes: (+) 10%, G) 8%.c) Lengfh: Unless othenrlse specified 4 to 7 meters.
3) Pipes of hlgher tensile strengh and bigger diameter can also be manufac;tured as per requesl.
JorNr vFNruRE BFTwEEN---@mCeftr-
I
I
I
I
r { o
HiqGAS Steel Industries P, Ltd.G P O Eox l 1 29, Kantipath, Jamal.Ka ihmandu N epal Tel. 977.1 .253047. 228389, 243452, 25247: 2528n. F ax 9/7 '1'220612
F;: lory Srmra. Bara, Telr 977.53.20075, 20078, ?011A. F ax. 977'53'201 60
,--------..r f n nrr
/ t i l l t f l l t u t n Nu u " . u r r L t L _ ). - a d F B r € t i H F -
reSTRUCTURALSTEEL PIPES
f-nl fucturat steel pipes are manufactured in the same| \ | process as water pipes. However, the steel used is ofI U lhigher tensile/yield shength. We normally use highI grade steel with tensile sbengh of 42/55 kgs/cm as per
I
I
t
I
customers requirements. We normally use he steel as perJIS: G-3132, SPHT 2,3 or 4, or lS: 11513/1985 for he pur-poses. Structural pipes are basically used for manufactur-ing ples and welded sbuctures. Use of high grade stuc-fural steel reduces steel consumpton drastically Pipes ofstructuralgrade normally conform to lS: 1161/1979, JIS: G-3444/1993, BS: 1387/1985.
I I IPCO ST[TUCTIJFIAL' I - f ] ETESN q n i n
--;-l 5
al Bore
lu:rt--| /'),
9l*11"th q
2 l l 0
C l a s s
- t -T h i c k n e s a
g-m
2.00
vEr9nrB l a c k p i p e s
Area olCr. scllon
Mment o flnertl i
S e c t l o nM o d u l u s Gyra i ion
. x q m
0 9 6- AEl--
I a tc m .
0 5 7c m .
0 . 5 4C n r
0 6 9M 2 6 5 | 2 2 55 0.69 0.65 0 6'lil ) 5 l 4 i 84 0 . 1 1 0 . 7 1 0 .65
20 76 90 t L J l 4 l 8 l l 8 1 .02 0 8 7N,l 2 6 5 | 5 8 02 r 5 0 0 8 6H \ . 2 5 1 . 9 0 4 l | 7 2 1 2 8 0 8,1
t 7 0 2 6 5 2 0.1 5 8 t 4 1 8 6 l 0M f . 2 5 46 r 6 5 7 l t 0 8H 4 0 5 2.99 2 . 5 1 I 0 6
) / lv4 42.40 L 2.65 2 . 6 1 J I 6 5 7 I l 0 I l l
fvl 1 2 5 l 1 5 00 7 7 1 3 .64 l 9n ;1.05 1 . 8 6 4 8 8 9 0 7 4 . l 8 1 3 6
40 l 1 /2 4 8 l 0 L 2 9 0 J . ) I 1 . t 4 1 0 7 0 4 . 4 3 l 6 llvl 3 . 2 5 l 6 l 4 6 0 I t . 7 l 4 8 6 I 6 0
H 4.05 4 .43 5 6 1 l l 9 0 5 . 7 55 0 ) 60 l0 I I 2 9 0 4 . t 4 5 2 3 2 1 5 9 7 t 6 2 0 3
L2 j 2 5 4 5 7 5 8 2 23 7 . 8 9 2 0 2M 3 . 6 5 5 . l 0 6 5 0 2 6 t 7 8 .68 2 0 1H 4.50 6 . t 7 7 8 9 10 90 l 0 2 0 r 9 8
65 7 6 t 0 J .25 5 . E 4 7 .14 49 4.1 I 1 . 0 0 2 5 8M 1 6 5 6 5 1 E l I 54 65 t4.40 7 5 6H 4 5 0 7 9 2 l 0 l 0 6 5 t 2 7 t 0 2 5 4
80 88 90 L t 2 5 6 E O 8 7 4 8 0 l l 1 8 0 7 t 0 lM 4 0 5 8 4 8 t 0 8 0 9 7 ) 8 2 t .91 t 0 0H 4 8 5 1 0 . 0 1 l ? 8 0 I l l 4 6 25.53 2 9 8
t 00 l 4 . t 0 J . O ) 70 I Y q J ! 1 4 . 0 1 l 9 l2 . l 0 5 5 0 tJ4. t 4 1 .00 1 8 9
H 5 4 0 t 4 5 0 50 214 54 4E.O4 J E 6
t25 I 19 .70 L 4 .50 14.90 t 9 . 1 0 437.20 62.59 4 . 7 8M 4 8 5 16.20 20.50 467.64 66.95 4 . 7 7H 5 4 0 I ?.90 22.80 5 14 .49 7J .66 4 . 7 5
1 5 0 6 t 6 5 l 0 I 4.50 I 7 .80 22.70 7325 7 88.74 5 6 8M 4.85 t9. tu 14.40 1E4.49 95.0 5 .67H 5.40 2t.20 l 0 864.69 o1.7 ) . b )
175 7 t93.70 L 4 .85 22.60 28.70 284 00 31.00 6.68M 5.40 z) .w 90 416 .96 46 30 6.66H )_vu 21 .J0 34.80 516. I I 59.00 6.(A
200 E I t v . l v L 4 .U ) 2). tu 32.60 874.06 7 l . o 7 / . ) uM 5.60 t9.4U J I.OV z t4L.) , . 9) .4y / . ) )H 5 9 0 l t 00 2247 00 205. I t . >4
a n c e s :.) Thlctn.s: (+) nct l imled, C) 10% max b) lirrshr: (f) 1096, C) 8%
Q.8 mm., owr €.3 mm, (+) 1%c) outCda oimctcr : Up(o €.3 mm (+)0.4 trun.,
177
list of drowings
Appendix C Gqlkot drawings
Scheme lcyout
Itonsrnission l ine, route olignment
Heodworks ond heodroce generol orrongeluent, sheet 1 of2Heodworl<s ond heodroce generol orrongetnent, sheet 2 of2Fleodworks ond heodroce, intoke
Heo d'"vorks o nd heod roce, g rcrvel trop/overfl o',vHecdworks ond hccdroce, crossing nos. 1 ond 2Heodworks ond heodroce, crossing nos. 3 ond 4Penstock oreo, generol 0rrongement
Penstock oreo, settl ing bosinlforeboy
Penstock oreo, onchor block & support detoilsPenstock oreo, mochine lbundotion 0nd t0ilroce detoils
u r ( r v Y r r l q r
Drowing 2f i r r r r r r i n n I
Drowing 4
Drowing 5
Drowing 6
Drowing 7
Drowing 8
Drolvinq 9
Drowing 10
Drowlng l1
Drowing 12
179
I I jI Fi !
l ri t Il J l
i-lt lI ' I 'l l l !r ! [
l :!,iirf : : i i. l t "3 t r - . !
II
i(x
o
Drowing i Scheme Loyout
z4,---t-
3r i
I i3 g
:t,i l t
8 l i- l J
II
/III
!t
Ie
\IIt'+\ . \
\ \
tt
t!t
\ "1 \\ \\ \\ \
\ \\ \\ r\ \\\
tt
!t.rt
i iii
II
IIt r \ -
/\ \ l
\ \ /\ \
\ \\
I
II,
i . .tlrlfr,!ts
I
:o
a)
Et
o!
d
181
Drowing 2 Tronsmission line, route olignment
! tI! li!
ft
i ^: tl o
; !! r
t lt ol {i '
3 r r< t t
l 3 *
!
tt
I
S t .r l l
l : lo -
! t r! E f3 ; :
f i * *r l tl l rI a -
l i! o
i :
iliB
tI
s l !Et _
- : :r:, ii - 1 ' .; r ? ' i
, : i! 6 ;
;i!ii@-J
IfgtJ
-F
II
oe,o
I
ot!!J-Fo5(,
tl782
I
Drowing 3 heodwork ond heodroce generol orrongment, sheet I of2
. a b
: ? s 6
3 : l !
;i:ii;i;:rui
H'|lliiii;
co9
n
t 1
if;:l '
l r,1,' r t
:i"
i i, .i f it . [ : 'i i r i. I ,I l r , '
o l-T -l
JL iFi l3| il
EtEIl-----+;
l-l-Tt-/_N
pl
L I JI OCa rOOt I
+-tr F l r .r 6 l r o o t r d l
mJ ..l- llll- --l , t j l l , { l | l l -t t t l ll l \ r r I
-l--l---*---l-r "ll ' ' l l , , ,1 t l
trf-ffil ffll*J_F*
ffi-CFTaaT+
t---1
r-f-+
ln
i r. 1 , t
i "'+. r' - \ 1 4::. .. !i ;. I
iiiilr,
!
iE"o ! tg I :p t Et u 6
= UT
Drowing 4 heodwork ond heodroce generol orrongment, sheet 2 of 2
:l1l:a l ;
il,;il,:f ' :f l '
1
ilYz
!l;"
l!
I it \
. \ -
!i ri t !r l
r !' Et :
. ,: i: .l r! r
: . 1! o
' 9 !i t lt . l
I I ' ll l l l
,.rl
'h3l
-r-r. l l- t- l . l
I I Eli-]_-l :lr l I z l
t l < lu l
-t-q
-J-oql -
l ii ! i ,i iitiI l . t i
s i i ; :
IF'
Drowing 5 heqdwork ond heodroce, intqke
si:i i i ': ; I i ii : i ' i; i i i !i i : i ;
n, fiiiiF l i l E a r? l i a ,
il'il' =
et-(,aa
:l
fil;
;l'I
ir-! lt l
a lrtI
oof
:4:;/g
oodt}-- (
fl
rr!lii
Drowing 6 heodwork ond heodroce, grovel trop/overflow
a '
, i i i igg ! : ir 5 - i . I
iii:ii:itiiiiii
uiiliiiiil
F*i [*' l " 9 , t ll:\-l t -r lrl
Sgl-gi pl iFe i - g l "
v'l jr:ilr t ; l l ,:l ' .1,
?
-lllrrl .) l r
al!:url !tF
zl9 l
Fl=J I-l
il-f l1-^ltlr lt l
a-J-
1
il "EI ;Hl
ol' l
o l .z l tot JlEIl r lU'I
il'
&--T-
I
fl-
l'"-l Iu.
e-lr l - l L-l l""l i"*vlh'.sr
lrlJ# -r' r>
.l o'ry
:l;i lFliHI;t'
l - EL>,N_t
3
I
IF{t
Fox
3
H,< q! g (
?FgEr5< elr,7
| \ \l \
_ L _ \
- t."\\I
--;;i;--,,,
F__-_____r._____J
t t(o l
dli
t
: t .r 3 l\ : lv l\
Drowing 7 heodwork snd heodroce, crossing nos' 1 ond 2
:! i! if t: :r it !5 . 2
l !t l
i r o
, , i ! iL l ! i l :
o lZ l ; t i
;!= r?I . ; I :
I
l 1
l [ .:l '
;;;ii:iiiii'
tt#
LI
1
ta i I
l'l. ]I ' l
i_r . L l rr o o t t G ) r l 6 c l f6#6b=-#i
%J
f,lr;al-a+*'-+--#
-fo lo lelI
-l-0 l9 t
tII
o lo l'l
I;i-9 l-t
I
Io ,0 l0 t- l
-L
-tt
[-__5r1__..r_rc:
Hi29
H6x"I
u l
: lto t; l 'q!
Hl 'm
Gt)o
oL
Ftr{,F
o
g
U(J
C i
3 e= <c!2 6< P
E;xpa pH
a
I
!
t
I
I
E
! 5a !
e !
o
is?s
I Es lE 2
I
t
at
!I:EI
!
tt o
r ii i! 8
Drowing 8 heodwork ond heodroce crossinq nos. 3 ond 4
l---cri.a-l r-o*=n-ftlr+-er+a-t
"I-t:lo l z l3i 3lJ_3 li l ' l
;rxl
TI
o lo tf t l
IIF
o l
1L
I r i i
tI
- r la t iJ l t4 l !
I:
__l
Drowing 9 penstock oreo, generol orrongement
.1,: l
r ii .r 3: ct r! ?
f !; ;r tl lf i. 3 r
t ! i. i t ,
*iii;El :' :"
Drowing 10 penstock oreo, settling bosin/foreboy
\
\-,' Il)-7't 61,F FI'l '
g'
vEsE:F{-Fo56
r6t
I
Ic
- lnI
- ll ll ll l u
- H e
f , '- !
i' l, flaEsc; i; ii' ',,,,i i! ii ;tll;;i r i ' I
i i ;: i igEiiiii:i,ii!u
TI
J
1I
v,J
F
IzoFolr,,,oIJ
xIe.Io
EF
::' l l- x
^ i l t
u t ;I
I i z6 19
3l
fil;
tl
l , ilt; l i
:;it ! !
a, i
. ' ! ,
:l,
EF< gx iP 33t, ,-2 2r r t 7
u
-ffi*1d
190
ii 1
f i: r i i iE i i i i
iii: :
!a
, L Q
:t
t . !I I .
; t !
Eo h 'lrJ ,?
t e . -. x E !E ' r t :6 [ Iz i ,U >o - <
ol
Rg
o
F
I
6
Drowing 11 penstock oreo, onchor block ond support detoils
!t
r !+ :
! ii Ec !; t
: rI
l -
r . 3: x ,
t
€
E5
, I! r ' l lE l t l "
il;l'El a lo H l:
.elt z la
9 l ax l
t 9 n
nl =li ;I J t o -
--.1- o-l*
fil 'ar _ E
)5 l
r lt ir l
i li l
r lc o l
l uz t .
filuo l
N
o2
-1 - .Y u
n l : - l R .u l < l i a+- -rl o fi. l a l tg l , 9_r, I
{-r
J L I L - -oot I rooot tG
o l< l5 I ;F l '( J ltrjl(/,l
4wA,
19 i
Drowing 12 penstock oreo, mochine foundotion ond toilroce detoils
I
! l! lt i I
: l 'IT
t
. t
$ ;
I
Ita
at
I
: I . !t : E -
: , r ! ! g: i = E : : i
;;;;;i;r : ! i ; i ;
iijiii;*
; i! ri :t .
t :r :t .
1 !a . l
i i: :
9 t
6
o
o
I
taI
I
I.!
t!t
tIp
ta?
r a
! i- l
d ' !a .r il <
i :o l l !ujl ' !
El: '
o l;lz lo l
slt t l
?lrol
=l;lHl
:l8ll d lo l
< l
FaF
In
il3z l *o l a
Eliflc
t
-1-
I-lIEl
$:t{
r92
t,
@
tJ
Ltc
F
tF
o
3
oatso
Feo=FoxJ
3
I
< dU >
* ? sx 1 !8 E Eb 6z qU 6
3I
I
-1- Iq'
-t-
II
"l8l
I1 " .t 9 t
t r rqlf lo i lo t I. l l
I I-l- l-
ol I
l,L Ll-rl , /
tl {.1 tl $'
J 9 l
o l+
I
Index
AAir-releose volve, 55
Altimeter,65
Anchor blocks 2, 1 1 1
checklist, 127a n n c t r r l a f i n n 1 1 1
design, 116-127
exomple, 121
Iocot ion,1 l1 '
sizing,727
Anchor rod, 29
BBench cut,65
Bio-engineering works, 144
Bottom intqke
description, 31
design, 32
exomple, 34
troshrocks for, 32
Bursting disc,93, 147
Breok pressure tonk, 55
cConols
copocity, 46
concrete,40
construction, 67-69
crossrngs, 53
design,46-51
eorth, 39
economics,46
exomple, 50
excovotion,68
ferrocement,42
heodloss,46
lining,43, M,45,68
mosonry 46
oil drum,40
roughness,48
sediment tronsport,4T
seepoge,46
semi-circulor concrete, 41
setting out,67
side slopes, 46
stobiliry,49
stone mosonry in mud mortor,39
stone mosonry in cement,40
timber,40
types,39
velocity,46,48
Check doms, 147
Coondo intoke, 149
Components of micro-hydro, 2
Crossings, 2, 55
Cross droinoge, 13
Culvert, 33
Curing, 69
DDe-beoder, 150
Design flow
procedure to estoblish 11
Diversion weirs (see weirs)
Diversion works
checklist, 36
Droft tube, 3
Dry stone woll, 145
EEfficiency in power equotion, 3
Excovotion,68, 143
Exponsion joints, 109
Escopes, 2
exomple, 111
in HDPE pipes, 110
in mild steel pipes, 110
in in PVC pipes, 110
siz ing,110
Spil lweirs,2
Spil lweirs,2
Overflow 2
tt
*193
FFoll velocity of sediment, 74
Flood risk, 12
Flow
design colculotions, 51
estimotion, 10-11, Appendix A
FIow Durotion Curve, 1 1
Flume
ferrocement,42
Flushing
frequency, 81
verticql pipe method, 77
Foreboy 2,71,84
checklist, 88
design,84
pipe level, 84
size, 84
Forces
frictionol, 120
on onchor blocks, 120-124
Freeboord,50
Friction, 39,61-66
GGqbions,35
Gqbion weir, 126
Gobion retoining woll, 144
check dqms, 147
Cotes
penstock,86
sluice,79
Generotor efficiency, 3
Geology,8
Geotechnicol considerotions, 8
Grovel trop, 2,71,72
checklist,88
exomple,80
Ground woter, 8
HHeqd
gross, 3
net, 3
HDPE pipes
joining, 59
Heodroce (see conols ond pipes) 2,39-68
Heqdworks,2
Hydroulic rodius,47
Hydrology, 10, Appendix A
Hydropower, 1
IIntokes, 2
bottom (see bottom intoke)
Coandq (see Coondo intoke)
generol principles for selecting, 1Z
rypes, 21
side (see side intoke)
exomple,20
selection criterio, 21
Inverted siphons, 55-56
Irrigotion, 13, 39, 40, 42, 4
JJoints, rock,9
LLond ownership ond use, 13
Levels,3, 12,84
Limestones, 10
Lining
formers method,45
HDPE,43
soil cement,44
Locotion oIcomponents, 6
MMochine foundqtion
design, 135
exomple, 136
Monning's equotion,46
Mosonry, 10,26,40,42,48,49,50, 53, 56, 87, 116, 119, 135Micro-hydro, 1
comporison with hydropowe4 1
definition, 1
Moody chort, 62
oOrifice
design,23
exomple,24
I
I
194
PPeohng reservoir, 87
Penstocks (olso see pipes)
bosic loyout, 15
checklist, 113
description, 2
exomples,99-103
exposed versus buried, 108i n c t n l l n t i n n 1 1 ?
mointenonce, 113
moteriols,94
overview 91
point ing,111
selection of olignment, 9l-93
Pipes (olso see penstock)
buriol detoils,57,60
bends 58,61,63,92
design criterio, 56
design procedure, 61-66
diometer, 61,95
generol, 56
HDPE ond PVC, 58-59, 155jointing, 59,95, 106
lengths, 107
roughness, 62
stqndqrd size, Appendix B
submergence heod, 61
turbulence losses, 63
wqll thickness,99
Plonning,5, 13
Ploster,48,69,88, 135
Power,3
Power equotion, 3
Powerhouse
checklist, 141
definition,3
locqtion, 134
overview, 133
size, 134
Site investigotion, 6
Pressure
hydrostotic, 120-122
RReservoir pechng, 87
Retoining structures, 144
River troining works, 35
Rock types, 10
Roughness coefficient
conols,4748
pipes,62
Run-of-river schemes, 1
sScfety
ogoinst overturning, 124on beoring, 124
Sediment problem, 47, 71
Seepoge, 12,46
design colculotion, 12
Settl ing bosins,71,73
checklist,88
components, 75
design criteriq, 73
description, 2
exomple,80
flushing orrongements, 77-79
flushing copocity, T3
ideol,73
inlet zone,76
outlet zone, 77
settling copocity, 73
settling design,75
settling zone,77
storoge copocify, 73
storoge design,75
Shield's formulo,4T
side intqke,22
Sinkholes, 10
Site selection,5, 15
Slope stobility, 8, 143-747
Spillwoys, 79,86
definition, 2
exomple,53
locotion,52
Stobility of schemes, 16
Storoge schemes, 1
Support piers, 115
checklist, 131
construction, 1 1 9
description,2
design, 120
flexible steel, 152
locotion,117
Submergence heqd, 61, 84
Surge colculotion, 97-100
195
TTqilroce
checklist, 141
definition, 3, 140
design ofchonnel, 140
design ofpipe, 140
Tension crocks,9
krrocing, 145
Thermol exponsion, 115
Tlqnsmission l ines, 6, 15
Troshrocks, 22,32,57 , 85
wWoter ovoilobility, 10
Woter rights, 13
Woter retqining structures, 88
Weokness zones, 8
Werrs
diversion, 2, 25
gobion, 26, 28
heod over, 31
permonent, 29
temporory, 25
Wetted perimeter,4T
vVent plpe,61
Volves, 57,61
1 \ 1 r r
r i- r t / 'l l . -
, ) ,
r ' l l
" 1 ,! , 1 - ; A . t ' "
I
. " 1
VLt L?t a
. ^t",4' . - '
lIj
t196
P R A C T I C A L A N S W E R S
T O P O V E R T Y\ /
BPC Hydroconsu l t