ITEM 6.1.1 Cultural Centre Redevelopment Funding
Applications Update
Attachment 3
Margaret River Cultural Centre
Cost Comparison
Cost Report dated 15 Oct 2014 5,642,332.00$
Cost Report Rev. 1 dated 22 Oct 2014 6,852,767.00$
Difference 1,210,435.00$
Additional Items in Cost Report Rev. 1
Item 1 Removing existing asbestos roofing 135,000.00$
New Colorbond roofing to replace existing asbestos roofing 497,399.00$
632,399.00$
Design Contingency (6%) 37,943.94$
Contract Contingency (3%) 20,110.29$
Preliminaries (14%) 96,663.45$
Locality Allowance (5%) 39,355.83$
826,472.51$
Item 2 Additional Infrastructure and Theatre Equipment 293,800.00$
Design Contingency (6%) 17,628.00$
Contract Contingency (3%) 9,342.84$
Preliminaries (14%) 44,907.92$
Locality Allowance (5%) 18,283.94$
383,962.70$
Total of Item 1 & 2 1,210,435.21$
Total Cost for Asbestos Removal (including new Colorbond roofing) 891,655.00$
Total cost for Infrastructure and Theatre Equipment 625,000.00$
* Please note that all costs exclude GST.
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S1 MULTI USE SPACE (STAGE 1)
DEMOLITIONS & ALTERATIONSDEMOLITIONS & ALTERATIONSDEMOLITIONS & ALTERATIONSDEMOLITIONS & ALTERATIONS
Upper Floor
1 Remove mezzanine level and staircase to existing Squash court Item 5,335
2 Allow for making good to all affected surfaces and clean up on completion Item 500
Walls
3 Demolish existing asbestos wall to existing Sports Hall Item 6,804
4 Demolish existing external cavity brickwall Item 3,255
5 Remove part of external cavity wall to Passage for new emergency exit Item 360
6 Remove part of external cavity brickwall to existing Squash court for stackingdoor recess
Item 810
7 Remove part of internal brickwall to existing Squash court for new door Item 90
8 Demolish existing external brickwall Item 480
9 Demolish existing internal cavity brickwall Item 2,295
10 Demolish existing internal brickwall Item 9,600
11 Demolish existing glazed walls Item 4,000
12 Allow for making good to all affected surfaces and clean up on completion Item 1,500
Windows and Doors
13 Remove existing roller door Item 100
14 Remove existing glazed double doors and frames Item 450
15 Do., but with side lights Item 200
16 Remove existing timber single doors and frames Item 525
17 Remove existing timber double doors and frames Item 180
Roofing and Structural
18 Demolish existing asbestos roof and structural remains to Squash Court Item 11,178
19 Allow to demolish existing asbestos cement roofing from the roof structure tothe following areas:
20 Existing bar, foyer and existing verandah Item 11,000
21 Existing basketball courts and toilets area Item 38,200
22 Courtyard verandah roof to south of auditorium Item 2,500
23 Extra for vacuuming out the ceilings Item 4,200
24 Allow for protection to existing areas during demolition works Item 25,000
25 Allow for inspection for asbestos related materials Item 3,000
Cabinetwork
26 Remove existing benchtop / bench cupboard to Bar Item 630
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 1 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S1 MULTI USE SPACE (STAGE 1) (Continued)
27 Remove existing vanity top to Toilets Item 250
28 Remove existing lockers to Male and Female Changing rooms Item 750
Sanitary Fixtures
29 Allow to remove existing WCs Item 570
Floor Finishes
30 Allow to remove existing floor tiling and surface preparation for new finishes Item 1,372
31 Allow to remove existing floor finishes, and surface preparation to squash courtfor receiving new T&G flooring
Item 4,182
32 Allow to remove existing floor finishes and surface preparation for new finishes Item 1,207
33 Allow for any additional screed / self-levelling compund as required Item 1,100
External Works
34 Remove existing bitumen Item 144
35 Remove existing paving Item 355
36 Remove existing landscaping Item 216
NEW WORKSNEW WORKSNEW WORKSNEW WORKS
Site Preparation
37 Allow to form building pad Item 3,300
38 Allow for temporary entrance during refurbishment works Item 4,800
39 Allow extra for automatic opening device Item 9,300
40 Allow for temporary partitions during refurbishment works Item 2,000
Bar, Store and New Kitchen
41 New ground floor slab added to existing floor slab, including waterproofingmembrane and reinforcement, complete
247 m2 55 13,585
42 Allow to connect to existing ground floor slab Item 790
43 Allow for moisture barrier to achieve moisture content to suit carpet & vinylinstallation
Item 3,700
44 New internal brickwall - Maxi bricks 129 m2 65 8,385
45 Extra for HWP and painting 258 m2 40 10,320
46 Extra for splashback to Kitchen, approx. 200mm high (Tile P.C. Sum $50/=m2 supply)
18 m 38 684
47 New glazed wall 99 m2 750 74,250
48 Extra for columns to support new glazed wall Item 4,455
49 New wall in acoustic panels of plywood to existing Sports Hall 77 m2 275 21,175
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 2 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S1 MULTI USE SPACE (STAGE 1) (Continued)
50 Brick up existing cavity wall, including making good to all affected surfaces andclean down on completion
24 m2 145 3,480
51 Extra for HWP and painting 48 m2 40 1,920
52 Vertical sunshades to east facade 72 m2 1,050 75,600
53 New roof framing (msd. on plan) 506 m2 155 78,430
54 New Colorbond roofing (msd. on plan), including roof insulation and safetymesh
506 m2 72 36,432
55 Extra for roofing works to existing roof structure Item 10,000
56 Extra for polycarbonate roof skylights Item 1,400
57 Extra for strapping to existing roof structure Item 6,000
58 Allow for fascia capping Item 2,100
59 Allow for roof plumbing Item 10,200
60 New servery roller shutter to Bar, approx. 4100mm wide x 1000mm high 1 No. 2,000 2,000
61 New 'Concertina' glass doors to Bar, approx. 6000mm wide x 2400mm high 1 No. 14,000 14,000
62 New single timber doors, including steel frame, hardware and painting 5 No. 970 4,850
63 New double timber doors, including steel frame, hardware and painting 4 No. 1,425 5,700
64 New timber acoustic double doors, including frames, hardware and painting 2 No. 3,750 7,500
65 New counter to Bar 18 m 1,100 19,800
66 New wall cupboards to Bar 8 m 525 4,200
67 New underbench cupboards to Bar 18 m 950 17,100
68 Allow extra for Bar fitout PSum 20,000
69 New 5 tier shelving to Store 12 m 480 5,760
70 New benchtop to Kitchen, including underbench cupboards 18 m 780 14,040
71 New wall cupboards to Kitchen 18 m 525 9,450
72 New island bench to Kitchen 6 m 1,100 6,600
73 Allow for kitchen fitout PSum 50,000
74 Allow for Coolroom fitout, including all insulated panels to walls and ceiling andsingle door
Item 15,000
75 Extra for shelving to Coolroom Item 3,850
76 New plasterboard suspended ceiling to extended area, complete with allsupporting frames and insulation, including cornice
288 m2 92 26,496
77 Extra for moisture resistant plasterboard ceiling to Kitchen 36 m2 15 540
78 Extra for connecting to existing ceiling Item 750
79 Painting - Plasterboard ceiling 288 m2 16 4,608
80 Allow for 'Versilux' lining to Verandah 57 m2 70 3,990
81 Extra for painting 57 m2 18 1,026
82 New floor finishes to Kitchen - assumed ceramic tiling (Supply P.C. Sum $50/=m2)
36 m2 160 5,760
83 New floor finishes to Stores - assumed vinyl, including coved vinyl skirtings(Supply P.C. Sum $60/=m2)
21 m2 87 1,827
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 3 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S1 MULTI USE SPACE (STAGE 1) (Continued)
84 New floor finishes to extended Lobby area - assumed carpet (supply P.C. Sum$50/=m2)
182 m2 70 12,740
85 Extra for MDF skirting, including painting 95 m 20 1,900
86 New electrical services to extended area, to match new layout Item 67,000
87 Air conditioning to extended area Item 83,200
88 Allow to make good to all affected surfaces and clean up on completion Item 3,000
89 Allow to repaint existing surfaces PSum
90 Allow for storm water disposal system to suit new roof covering Item 7,600
New Multi Purpose Hall, Backstage and Toilets Area
91 New ground floor slab added to existing floor slab as New Store area, includingwaterproofing membrane and reinforcement, complete
50 m2 55 2,750
92 New wall in acoustic panels of plywood to New Multi Purpose Hall 168 m2 275 46,200
93 New internal brickwall - Maxi bricks 120 m2 65 7,800
94 Extra for HWP and painting 240 m2 40 9,600
95 Extra for new fire wall 38 m2 104 3,952
96 Allow to connect brickwall to existing Item 1,000
97 New external cavity brickwall, to new Multi Purpose Hall as stacking doorsrecess
29 m2 225 6,525
98 Allow for HWP and painting to brickwall 29 m2 40 1,160
99 Extra for louvred aluminium vents to brickwall, approx. 600 x 5600mm highoverall
4 No. 2,300 9,200
100 Allow to connect to existing brickwall Item 750
101 Brick up existing internal brickwall, including making good to all affectedsurfaces and clean down on completion
15 m2 80 1,200
102 Extra for HWP and painting 29 m2 40 1,160
103 New external timber stud walls, complete with plasterboard lining internally,selected weatherboard lining externally, sarking and insulation, to New Store
68 m2 190 12,920
104 Extra for painting 135 m2 14 1,890
105 Brick up existing external cavity brickwall, including making good to all affectedsurfaces and clean down on completion
5 m2 225 1,125
106 Extra for HWP and painting 5 m2 40 200
107 New roof framing (msd. on plan) 1,322 m2 155 204,910
108 New Colorbond roofing (msd. on plan), including roof insulation and safetymesh
1,322 m2 72 95,184
109 Extra for roofing works to existing roof structure Item 16,200
110 Extra for strapping to existing roof structure Item 7,000
111 Allow for fascia capping Item 3,276
112 Allow for roof plumbing Item 26,440
113 New 100mm thick solar span insulated roof panels, including all structuralframing, to New Multi Purpose Hall
267 m2 295 78,765
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 4 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S1 MULTI USE SPACE (STAGE 1) (Continued)
114 Allow for fascia capping Item 2,825
115 Allow for roof plumbing Item 5,350
116 New internal glazed aluminium double doors, including frames and hardware 2 No. 4,200 8,400
117 New internal single timber door, including steel frames, hardware and painting 1 No. 970 970
118 New internal timber double doors, including steel frames, hardware and painting 2 No. 1,425 2,850
119 New double fire door, including frames, hardware and painting 1 No. 3,950 3,950
120 No allowance made for mechanical operating devices for operable walls Note
121 New manually operated operable wall to New Multi Purpose Hall, approx. 6600x 5600mm high, including all necessary rails, tracks and hardware
1 No. 30,000 30,000
122 New stacking doors to New Multi Purpose Hall, approx. 17600 x 5600mm high,including all necessary rails, tracks and hardware
2 No. 77,000 154,000
123 New storage shelving to New Store, 5 tier 25 m 450 11,250
124 New vanity top bench to WC area fully prepared to receive basin 10 m 400 4,000
125 Extra for basin perforation 6 No. 110 660
126 Allow to install relocated retractable tiered seating Item 5,000
127 Considered all services to be connect to existing services, and no allowancemade for upgrade to existing mains
Note
128 New WC, including all necessary pipework and fittings 3 No. 3,400 10,200
129 Do., but to disabled WC 1 No. 3,500 3,500
130 New vanity basin including pipeworks and fittings 6 No. 2,425 14,550
131 New urinal, to Male WC 4 No. 2,050 8,200
132 New grab rails, to disabled WC 2 No. 110 220
133 New mirrors, to Toilets 6 No. 120 720
134 New toilet roll holders to Toilets 4 No. 45 180
135 New soap dispenser to Toilets 3 No. 65 195
136 Allow for new toilet partitions to Female WC 5 No. 2,100 10,500
137 New suspended ceiling with acoustic plywood panels to New Multi PurposeHall, including paint finish
246 m2 305.00 75,030
138 Allow to connect to existing ceiling Item 1,500
139 New suspended plasterboard ceiling to New Store, complete supporting framewith insulation, painting and cornice
50 m2 92 4,600
140 Allow to connect to existing ceiling Item 250
141 New T&G flooring to New Multi Purpose Hall (supply P.C. Sum $115/m2) 246 m2 290 71,340
142 New ceramic floor tiling to new Toilets area (supply P.C. Sum $50/m2) 5 m2 160 800
143 Allow for tiled skirting 9 m 32 288
144 New carpet flooring to Rehearsal/Breakout room and Backstage (supply P.C.Sum $50/=m2)
93 m2 70 6,510
145 Allow for MDF skirting + painting 57 m 20 1,140
146 Assumed floor finishes to rest of the area remains the same Note
147 Allow for acoustic wall treatment to new Multi Purpose Hall 253 m2 50 12,650
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 5 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S1 MULTI USE SPACE (STAGE 1) (Continued)
148 Allow to repaint existing walls, if required PSum 7,000
149 New electrical services, including infrastructure and theatre equipments Item 412,100
150 Air conditioning to new Multi Purpose Hall Item 72,000
151 Allow to make good to all affected surfaces and clean up on completion Item 2,500
152 Allow for storm water disposal system to suit new roof covering Item 7,875
External Works
153 Paving to new public walkway 27 m2 65 1,755
154 Extra for gate, complete with posts 1 No. 450 450
155 Bitumen to new walkway 70 m2 70 4,900
156 Allow for road drains Excl.
ON COSTON COSTON COSTON COST
157 Design Contingency Item 146,661
158 Contract Contingency Item 77,730
159 Preliminaries Item 373,623
160 Locality Allowance Item 152,118
ESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COST $$$$$$$$ 3,194,4783,194,4783,194,4783,194,478
ASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONS
ASSUMPTIONS
161 Unless indicated on the preliminary drawings, all specifications are assumed
162 No new finishes to existing areas considered in this cost report
163 Assumed no works done to the areas outside of the building lines indicated onthe drawings, except for replacing the asbestos cement roofing
GENERAL EXCLUSIONS
164 Goods & Services Tax. (G.S.T.)
165 Excavation in rock.
166 Window treatments
167 Sewer extension outside the site boundary
168 Power up-grade.
169 Transformer
170 Loose furniture & equipment
171 Architect's & Consutants' Fees
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 6 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S1 MULTI USE SPACE (STAGE 1) (Continued)
172 Disbursement (DA Fees, Building Licence Fee,Building Surveyor Fees,Independent Certifier Fees)
173 Q.S Fees - Cost Planning
174 Q.S Fees - Bill Of Quantities
175 Q.S Fees - Contract Administration
176 Escalation
GENERALLY
177 This Cost Indication is based on following drawings received from the Architecton 03-10-2014
178 Drawings SK3.1 to SK3.13
MULTI USE SPACE (STAGE 1) TOTAL 3,194,478
S2 AUDITORIUM (STAGE 2)
DEMOLITIONS & ALTERATIONSDEMOLITIONS & ALTERATIONSDEMOLITIONS & ALTERATIONSDEMOLITIONS & ALTERATIONS
Upper Floors
179 Remove existing staircases to Auditorium, approx. 4m high Item 1,500
180 Remove existing side and rear gallery level Item 10,300
Masonry and Walls
181 Allow to remove existing brick columns Item 1,700
182 Remove existing internal brickwall Item 3,250
183 Remove existing internal cavity brickwall Item 1,950
184 Remove existing external glazed wall Item 7,200
185 Allow to cut opening in existing internal cavity brickwall for single doors Item 790
Windows and Doors
186 Remove existing single door Item 300
187 Remove existing external double pivot doors Item 180
188 Remove existing window, approx. 2600mm x 1200mm high Item 210
Roofing and Structural
189 Allow to demolish existing asbestos cement roofing from the roof structure tothe following areas:
190 Existing fly tower and domed ridge vent Item 6,000
191 Existing Auditorium and projection box and domed ridge vent Item 13,000
192 Extra for vacuuming out the existing ceilings Item 2,100
193 Allow for protection to existing areas during demolition works Item 25,000
194 Allow for inspection of asbestos related materials Item 3,000
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 7 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S2 AUDITORIUM (STAGE 2) (Continued)
Cabinetwork
195 Remove existing benchtop / bench cupboard Item 280
196 Allow to remove all kitchen fitout (rangehood, stove, oven etc.) Item 550
197 Remove existing sink Item 270
198 Remove existing island benchtop Item 120
Floor Finishes
199 Remove existing floor finishes and surface preparation to receive new finishes Item 780
Services
200 Allow to remove ducts from existing toilets Item 220
External Works
201 Remove existing bitumen road Item 200
202 Remove existing landscaping Item 425
203 Remove existing paving Item 430
NEW WORKSNEW WORKSNEW WORKSNEW WORKS
Site Preparation
204 Allow to form building pad Item 4,700
205 Allow for temporary partitions during refurbishment works Item 1,400
Substructure
206 New ground floor slab, including waterproofing membrane, reinforcement, etc.,complete
188 m2 55 10,340
207 Extra for connecting slab to existing Item 1,425
Superstructure
208 New lighting platform - Steel framed 9 m2 345 3,105
209 Extra for balustrade to lighting platform 22 m 185 4,070
210 Allow for extra 3 risers to existing stairs, including making good to all affectedsurfaces
Item 1,350
211 New raised access passage to Projection Room 16 m2 235 3,760
212 Allow to connect to existing Projection Room slab Item 2,175
213 New staircase, approx. 4000mm high x 2000mm wide including steelbalustrades
2 No. 14,000 28,000
214 Do., but approx. 4000mm high x 1000mm wide 2 No. 9,000 18,000
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 8 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S2 AUDITORIUM (STAGE 2) (Continued)
Walls and Partitions
215 New internal brickwall - Maxi bricks 176 m2 65 11,440
216 Extra for timber cladding to wall, fixed on and including all supporting framing 32 m2 270 8,640
217 New internal cavity brickwall - Maxi bricks 12 m2 145 1,740
218 Allow to connect to existing brickwall Item 300
219 Brick up existing opening to existing cavity brickwall 20 m2 165 3,300
220 New toilet partitions, including doors, rails and all necessary hardware 3 No. 2,100 6,300
221 New internal glazed walls 8 m2 650 5,200
222 Extra for internal glazed double door 1 No. 2,800 2,800
223 New external cavity brickwall 15 m2 145 2,175
224 New glazed external wall 290 m2 750 217,500
225 Extra for columns to support new glazed wall Item 10,150
226 Extra for glazed single doors, including all necessary hardware 1 No. 1,800 1,800
227 Extra for glazed pivot double doors as entrance doors, including all necessaryhardware
2 No. 2,800 5,600
228 Vertical sunshades to east facade 111 m2 1,050 116,550
229 Timber battens to front of glass wall 130 m2 175 22,750
230 New timber stud partition to Control Desk and Access Passage, includinginsulation and plasterboard to both sides
12 m2 125 1,500
231 Allow to make good to all affected surfaces and clean down on completion Item 5,000
Doors and Windows
232 New internal single timber doors with steel frames, including all necessaryhardware
4 No. 970 3,880
233 New internal acoustic single timber doors and frames to form light and soundlock, including all necessary hardware
1 No. 3,390 3,390
234 Do., but double doors 4 No. 3,750 15,000
Structural Steel
235 Allow for roof framing and connect to existing Item 25,515
236 Allow for new brick columns Item 8,500
Roof and Roof Plumbing
237 New Colorbond roofing, including all insulation and safety mesh 818 m2 75 61,350
238 Extra for fascia capping Item 4,800
239 Extra for roofing works to existing structure Item 14,000
240 Extra for strapping to existing roof structure Item 18,600
241 Allow for roof plumbing and additional stormwater disposal system to suit newroof layout
Item 20,200
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 9 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S2 AUDITORIUM (STAGE 2) (Continued)
242 Roof arrestor system Item 10,000
Fitout and Equipment
243 Extend stage platform by 1000mm Item 8,800
244 Extra for junction to existing stage and making good to all affected surfaces Item 1,450
245 Extra for staircases to stage Item 900
246 Allow for staggered seating to Auditorium, approx. 308 number of seats (AllowP.C. Sum $500/= each chair - supply and install)
PSum 154,000
247 New vanity benchtop to Toilet, fully prepared to receive basin 3 m 400 1,200
248 New timber sitting bench to Toilet Lobby, approx. 600mm wide 7 m 525 3,675
249 New worktop to Control Desk, approx. 600mm wide 3 m 450 1,350
250 New drawer units to Control Desk 2 No. 600 1,200
Fitout to Toilets
251 New WC + services 4 No. 3,400 13,600
252 New vanity basin + services 3 No. 2,425 7,275
253 New urinals + services 4 No. 2,050 8,200
254 New toilet paper holder 4 No. 45 180
255 New soap dispenser 1 No. 65 65
256 New grab rails 2 No. 110 220
257 New mirrors 4 No. 120 480
Ceiling Finishes
258 New suspended ceiling with acoustic plywood panels to extended area,including insulation, all supporting framing and cornice
181 m2 300 54,300
259 New suspended ceiling with moisture resistant plasterboard lining to Toilet,including insulation, all supporting framing and cornice
7 m2 107 749
260 Existing ceiling over Auditorium to remain same Note
261 Allow for extra plywood panels over the Auditorium, including all supportingframing
304 m2 325.00 98,800
Wall Finishes
262 Hard wall plaster to brick walls (msd. gross) 429 m2 28 12,012
Floor Finishes
263 Allow for carpet to extended area (supply P.C. Sum $50/=m2) 159 m2 70 11,130
264 MDF skirting 114 m 12 1,368
265 Allow for vinyl to Toilet Lobby (supply P.C. Sum $60/= m2) 22 m2 87 1,914
266 Extra for coved vinyl skirting 21 m 22 462
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 10 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S2 AUDITORIUM (STAGE 2) (Continued)
Floor and Wall Tiling
267 Ceramic floor tiling to Disabled Toilet (supply P.C. Sum $50/=m2) 7 m2 160 1,120
268 Extra for tiled skirting 11 m 32 352
269 Allow to make good to all affected surfaces and clean down on completion Item 1,000
270 Assumed no wall tiling required Note
Painting
271 Painting to hard wall plastered walls 429 m2 12 5,148
272 Do., but to plasterboard ceiling 7 m2 16 112
273 Do., but to timber skirting, n.e. 250mm girth 114 m 6 684
274 Do., but to timber doors and frames - single 5 No. 335 1,675
275 Do., but to timber doors and frames - double 4 No. 445 1,780
276 Do., but to timber battens 130 m2 45 5,850
277 Do., but to plasterboard lining to timber stud walls 24 m2 12 288
Electrical Services
278 Allow for new lighting to extended building area Item 53,000
279 New electrical services, lighting and Audio Visual System to Auditorium Item 210,400
Mechanical Services
280 Allow for new air-conditioning to extended area Item 50,000
281 Do. but to existing Auditorium Item 81,000
Hydraulics Services
282 Allow for connecting to existing services Item 750
External Works
283 Bitumen to new walkway Item 3,100
284 Garden bed for climbing creepers Item 560
Generally
285 Allow to make good to all affected surfaces and clean down on completion Item 5,000
286 Allow to repaint existing wall, if required PSum 5,020
ON COSTON COSTON COSTON COST
287 Design Contingency Item 94,574
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 11 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S2 AUDITORIUM (STAGE 2) (Continued)
288 Contract Contingency Item 50,124
289 Preliminaries Item 240,930
290 Locality Allowance Item 98,093
ESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COST $$$$$$$$ 2,059,9492,059,9492,059,9492,059,949
ASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONS
ASSUMPTIONS
291 Unless indicated on the preliminary drawings, all specifications are assumed
292 No new finishes to existing areas considered in this cost report
293 Assumed no works done to the areas outside of the building lines indicated onthe drawings, except for replacing the asbestos cement roofing
GENERAL EXCLUSIONS
294 Goods & Services Tax. (G.S.T.)
295 Excavation in rock.
296 Window treatments
297 Sewer extension outside the site boundary
298 Power up-grade.
299 Transformer
300 Loose furniture & equipment
301 Architect's & Consutants' Fees
302 Disbursement (DA Fees, Building Licence Fee,Building Surveyor Fees,Independent Certifier Fees)
303 Q.S Fees - Cost Planning
304 Q.S Fees - Bill Of Quantities
305 Q.S Fees - Contract Administration
306 Escalation
GENERALLY
307 This Cost Indication is based on following drawings received from the Architecton 03-10-2014
308 Drawings SK3.1 to SK3.13
AUDITORIUM (STAGE 2) TOTAL 2,059,949
S3 CONFERENCE CENTRE (STAGE 3)
DEMOLITION WORKSDEMOLITION WORKSDEMOLITION WORKSDEMOLITION WORKS
Wall
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 12 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S3 CONFERENCE CENTRE (STAGE 3) (Continued)
309 Allow to carefully remove the timber screens and save it for re-use later Item 3,900
310 Allow to cut opening in existing glazed wall for new double pivot doors Item 900
External Works
311 Remove existing tree, large Item 2,200
312 Remove existing landscaping Item 6,690
313 Remove existing bitumen road Item 400
314 Remove existing paving Item 370
315 Remove existing kerbs Item 300
NEW WORKSNEW WORKSNEW WORKSNEW WORKS
Site Preparations
316 Allow for site clearance Item 6,500
317 Allow to form building pads including any filling Item 12,000
Substructure
318 New ground floor slab, including waterproofing membrane, reinforcement, etc.,complete
569 m2 55 31,295
319 Allow to form junction to existing slab Item 2,575
Wall
320 New glazed wall 231 m2 750 173,250
321 New external cavity brickwall 111 m2 190 21,090
322 Allow to connect to existing brickwall Item 1,050
323 Vertical sunshades to east facade 82 m2 1,050 86,100
Doors and Windows
324 New double timber doors and steel frames, including all necessary hardware 2 No. 1,425 2,850
325 New double pivot glazed doors to existing glazed wall 1 No. 4,800 4,800
Structural Steel
326 Allow for roof framing Item 88,660
327 Allow for columns Item 31,295
Roofing and Roof Plumbing
328 Allow for Colorbond roofing 572 m2 55 31,460
329 Anticon insulation on safety mesh 572 m2 20 11,440
330 Allow for fascia capping 103 m 42 4,326
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 13 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S3 CONFERENCE CENTRE (STAGE 3) (Continued)
331 Allow for roof plumbing Item 15,000
332 Roof arrester system Item 7,500
Joinery and Fitout
333 Allow for fitout to Conference Centre PSum 75,000
Wall Finishes
334 Hard wall plaster to brickwall (msd. gross) 221 m2 28 6,188
Ceiling Finishes
335 New suspended acoustic plasterboard ceiling, including all supporting framingand cornice
569 m2 115 65,435
336 Ceiling insulation 569 m2 15 8,535
Floor Finishes
337 Allow for carpet flooring (supply P.C.Sum $60/=m2) 569 m2 80 45,520
338 MDF skirting 103 m 12 1,236
Painting
339 Painting to HWP walls 221 m2 12 2,652
340 Do., but to ceiling 569 m2 16 9,104
341 Do., but to timber double doors + steel frame 2 No. 445 890
342 Do., but to timber skirting, n.e. 250mm girth 103 m 8 824
Electrical Services
343 Allow for electrical services Item 225,000
344 Audio Visual Services Item 50,000
Mechanical Services
345 Allow for air-conditioning Item 175,000
External Works
346 Allow for footpath 42 m2 60 2,520
347 Allow for ramp and landing 24 m2 65 1,560
348 Extra for painted galvanised steel hand rails and balustrades 30 m 225 6,750
349 Extra for tactile pavers 2 m2 425 850
External Services
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 14 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S3 CONFERENCE CENTRE (STAGE 3) (Continued)
350 No external serices considered in the costing (assumed existing servicesadequate for all stages)
Note
ON COSTON COSTON COSTON COST
351 Design Contingency Item 73,381
352 Contract Contingency Item 38,892
353 Preliminaries Item 186,940
354 Locality Allowance Item 76,111
ESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COSTESTIMATED TOTAL BUILDING COST $$$$$$$$ 1,598,3401,598,3401,598,3401,598,340
ASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONSASSUMPTIONS AND EXCLUSIONS
ASSUMPTIONS
355 Unless indicated on the preliminary drawings, all specifications are assumed
356 No new finishes to existing areas considered in this cost report
357 Assumed no works done to the areas outside of the building lines indicated onthe drawings, except for replacing the asbestos cement roofing
GENERAL EXCLUSIONS
358 Goods & Services Tax. (G.S.T.)
359 Asbestos removal
360 Excavation in rock.
361 Window treatments
362 Sewer extension outside the site boundary
363 Power up-grade.
364 Transformer
365 Loose furniture & equipment
366 Extension of School Insurance
367 Architect's & Consutants' Fees
368 Disbursement (DA Fees, Building Licence Fee,Building Surveyor Fees,Independent Certifier Fees)
369 Q.S Fees - Cost Planning
370 Q.S Fees - Bill Of Quantities
371 Q.S Fees - Contract Administration
372 Escalation
GENERALLY
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 15 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT DETAIL
ItemNo.
Item Description Quantity Unit Rate Amount
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S3 CONFERENCE CENTRE (STAGE 3) (Continued)
373 This Cost Indication is based on following drawings received from the Architecton 03-10-2014
374 Drawings SK3.1 to SK3.13
CONFERENCE CENTRE (STAGE 3) TOTAL 1,598,340
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 16 of 16
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
REPORT SUMMARY
Code Trade Description Trade%
Cost/m2 Total
Project: Wilde and Woollard
Building: Augusta Margaret River Cultural Centre
Details: Preliminary Cost Indication - Oct 2014 -Rev. 1
S1 MULTI USE SPACE (STAGE 1) 46.62 3,194,478
S2 AUDITORIUM (STAGE 2) 30.07 2,059,949
S3 CONFERENCE CENTRE (STAGE 3) 23.33 1,598,340
NOTE: ALL COSTS EXCL. GST
ESTIMATED PROJECT TOTAL 6,852,767
CostXJob No: 1597Cost Base Date: Date of Printing: 22/10/2014
Page 1 of 1
Merefield Wilde and Woollard Pty Ltd (ABN 31 009 414 902) trading as Wilde and Woollard (WA).Use of the Wilde and Woollard name and logo under Licence from Wilde and Woollard Australia Pty Ltd
WILDE AND WOOLLARD (WA)Unit 1 / Ground Floor
1008 Wellington StreetWest Perth, WA 6005
ITEM 6.1.1 Cultural Centre Redevelopment Funding
Applications Update
Attachment 4
Margaret River Cultural Centre Redevelopment Project - "Margaret River Needs a Strong Heart"
Discounted Cash Flow Analysis
Scenario Zero - No Business Events per annumRate Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Total
Capital Expenditure
Stage 1 - Multi-purpose space
QS Cost Estimate 3,200,000
10% Architects & Consulatants Fees 320,000
Fit out for Kitchen & Bar 150,000
Provision for Technical Fit Out 100,000
3,770,000
Stage 2 - Cultural Centre
QS Cost Estimate 2,060,000
10% Architects & Consulatants Fees 206,000
160 PVC Solar panels 60,000
Provision for Fit Out 50,000
2,376,000
Total Capital Expenditure 6,146,000 6,146,000
Funded by:
Royalties for Regions 5,000,000
Other Grants , Donations & Contributions 146,000
Shire 1,000,000
Total Capital Funding 6,146,000 6,146,000
Operating Revenue
Income from business events 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Income from current hires (provided to Arts M/R) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Estimated income from additional hires 3% Escalation 20,000 20,600 21,218 21,855 22,510 23,185 23,881 24,597 25,335 26,095 26,878 27,685 28,515 29,371 30,252 31,159 32,094 33,057 34,049 35,070 537,407
Estimated income from Kitchen hires 3% Escalation 15,000 15,450 15,914 16,391 16,883 17,389 17,911 18,448 19,002 19,572 20,159 20,764 21,386 22,028 22,689 23,370 24,071 24,793 25,536 26,303 403,056
Reimbursement of Utilities by Arts M/R 15,000 15,450 15,914 16,391 16,883 17,389 17,911 18,448 19,002 19,572 20,159 20,764 21,386 22,028 22,689 23,370 24,071 24,793 25,536 26,303 403,056
Total Operating Revenue 50,000 51,500 53,045 54,636 56,275 57,964 59,703 61,494 63,339 65,239 67,196 69,212 71,288 73,427 75,629 77,898 80,235 82,642 85,122 87,675 1,343,519
Operating Expenditure 3% Escalation
Arts Margaret River Contribution 236,900 244,007 251,327 258,867 266,633 274,632 282,871 291,357 300,098 309,101 318,374 327,925 337,763 347,896 358,333 369,082 380,155 391,560 403,306 415,406 6,365,592
Food & beverage staff, costs of goods 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Electricity 20,000 20,600 21,218 21,855 22,510 23,185 23,881 24,597 25,335 26,095 26,878 27,685 28,515 29,371 30,252 31,159 32,094 33,057 34,049 35,070 537,407
Rebate for Electricity Generated (5,000) (5,150) (5,305) (5,464) (5,628) (5,796) (5,970) (6,149) (6,334) (6,524) (6,720) (6,921) (7,129) (7,343) (7,563) (7,790) (8,024) (8,264) (8,512) (8,768) (134,352)
Other Utilities 1% of revenue 500 515 530 546 563 580 597 615 633 652 672 692 713 734 756 779 802 826 851 877 13,435
Fixed overheads - maintenance, cleaning, etc 7% of revenue 3,500 3,605 3,713 3,825 3,939 4,057 4,179 4,305 4,434 4,567 4,704 4,845 4,990 5,140 5,294 5,453 5,616 5,785 5,959 6,137 94,046
Depreciation 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 1,866,000
Refurbishment allowance 57,400 57,400 57,400 57,400 57,400 66,010 66,010 66,010 66,010 66,010 75,912 75,912 75,912 75,912 75,912 87,298 87,298 87,298 87,298 87,298 1,433,099
Total Operating Expenditure 406,600 414,277 422,184 430,329 438,718 455,968 464,868 474,035 483,476 493,201 513,120 523,437 534,064 545,009 556,283 579,282 591,243 603,562 616,251 629,320 10,175,228
Financing
Loan Principal Repayments 49,304 51,361 53,504 55,737 58,062 60,485 63,009 65,638 68,377 71,230 74,202 77,298 80,524 83,884 87,384 1,000,000
Loan Interest Repayments 4.13% fixed 41,364 39,306 37,163 34,931 32,605 30,182 27,658 25,029 22,290 19,437 16,465 13,369 10,143 6,784 3,283 360,010
Total Financing Costs 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 0 0 0 0 0 1,360,010
Funded by:
Developer Contribution Plan payments 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 1,360,005
Net financing costs to be funded by Shire 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5
Net Annual Result (356,600) (362,777) (369,140) (375,693) (382,443) (398,005) (405,166) (412,541) (420,138) (427,963) (445,924) (454,226) (462,776) (471,583) (480,654) (501,384) (511,007) (520,920) (531,129) (541,645) (8,831,714)
Net Annual Cash Flow (excluding Depreciation) 0 (263,300) (269,477) (275,840) (282,393) (289,143) (304,705) (311,866) (319,241) (326,838) (334,663) (352,624) (360,926) (369,476) (378,283) (387,354) (408,084) (417,707) (427,620) (437,829) (448,345) (6,965,714)
Net Present Value of Cash Flows 5.0% (3,945,864)
Margaret River Cultural Centre Redevelopment Project - "Margaret River Needs a Strong Heart"
Discounted Cash Flow Analysis
Scenario One - 6 Business Events per annumRate Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Total
Capital Expenditure
Stage 1 - Multi-purpose space
QS Cost Estimate 3,200,000
10% Architects & Consulatants Fees 320,000
Fit out for Kitchen & Bar 150,000
Provision for Technical Fit Out 100,000
3,770,000
Stage 2 - Cultural Centre
QS Cost Estimate 2,060,000
10% Architects & Consulatants Fees 206,000
160 PVC Solar panels 60,000
Provision for Fit Out 50,000
2,376,000
Total Capital Expenditure 6,146,000 6,146,000
Funded by:
Royalties for Regions 5,000,000
Other Grants , Donations & Contributions 146,000
Shire 1,000,000
Total Capital Funding 6,146,000 6,146,000
Operating Revenue
Income from business events 6 765,000 765,000 765,000 765,000 765,000 879,750 879,750 879,750 879,750 879,750 1,011,713 1,011,713 1,011,713 1,011,713 1,011,713 1,163,469 1,163,469 1,163,469 1,163,469 1,163,469 19,099,660
Income from current hires (provided to Arts M/R) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Estimated income from additional hires 3% Escalation 20,000 20,600 21,218 21,855 22,510 23,185 23,881 24,597 25,335 26,095 26,878 27,685 28,515 29,371 30,252 31,159 32,094 33,057 34,049 35,070 537,407
Estimated income from Kitchen hires 3% Escalation 15,000 15,450 15,914 16,391 16,883 17,389 17,911 18,448 19,002 19,572 20,159 20,764 21,386 22,028 22,689 23,370 24,071 24,793 25,536 26,303 403,056
Reimbursement of Utilities by Arts M/R 15,000 15,450 15,914 16,391 16,883 17,389 17,911 18,448 19,002 19,572 20,159 20,764 21,386 22,028 22,689 23,370 24,071 24,793 25,536 26,303 403,056
Total Operating Revenue 815,000 816,500 818,045 819,636 821,275 937,714 939,453 941,244 943,089 944,989 1,078,908 1,080,924 1,083,001 1,085,139 1,087,342 1,241,368 1,243,705 1,246,112 1,248,591 1,251,145 20,443,179
Operating Expenditure 3% Escalation
Arts Margaret River Contribution 236,900 244,007 251,327 258,867 266,633 274,632 282,871 291,357 300,098 309,101 318,374 327,925 337,763 347,896 358,333 369,082 380,155 391,560 403,306 415,406 6,365,592
Food & beverage staff, costs of goods 535,500 535,500 535,500 535,500 535,500 615,825 615,825 615,825 615,825 615,825 708,199 708,199 708,199 708,199 708,199 814,429 814,429 814,429 814,429 814,429 13,369,762
Electricity 40,000 41,200 42,436 43,709 45,020 46,371 47,762 49,195 50,671 52,191 53,757 55,369 57,030 58,741 60,504 62,319 64,188 66,114 68,097 70,140 1,074,815
Rebate for Electricity Generated (10,000) (10,300) (10,609) (10,927) (11,255) (11,593) (11,941) (12,299) (12,668) (13,048) (13,439) (13,842) (14,258) (14,685) (15,126) (15,580) (16,047) (16,528) (17,024) (17,535) (268,704)
Other Utilities 1% of revenue 8,150 8,165 8,180 8,196 8,213 9,377 9,395 9,412 9,431 9,450 10,789 10,809 10,830 10,851 10,873 12,414 12,437 12,461 12,486 12,511 204,432
Fixed overheads - maintenance, cleaning, etc 7% of revenue 57,050 57,155 57,263 57,375 57,489 65,640 65,762 65,887 66,016 66,149 75,524 75,665 75,810 75,960 76,114 86,896 87,059 87,228 87,401 87,580 1,431,023
Depreciation 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 1,866,000
Refurbishment allowance 57,400 57,400 57,400 57,400 57,400 66,010 66,010 66,010 66,010 66,010 75,912 75,912 75,912 75,912 75,912 87,298 87,298 87,298 87,298 87,298 1,433,099
Total Operating Expenditure 1,018,300 1,026,427 1,034,798 1,043,420 1,052,300 1,159,562 1,168,984 1,178,688 1,188,683 1,198,978 1,322,414 1,333,336 1,344,586 1,356,173 1,368,108 1,510,158 1,522,819 1,535,861 1,549,293 1,563,129 25,476,018
Financing
Loan Principal Repayments 49,304 51,361 53,504 55,737 58,062 60,485 63,009 65,638 68,377 71,230 74,202 77,298 80,524 83,884 87,384 1,000,000
Loan Interest Repayments 4.13% fixed 41,364 39,306 37,163 34,931 32,605 30,182 27,658 25,029 22,290 19,437 16,465 13,369 10,143 6,784 3,283 360,010
Total Financing Costs 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 0 0 0 0 0 1,360,010
Funded by:
Developer Contribution Plan payments 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 1,360,005
Net financing costs to be funded by Shire 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5
Net Annual Result (203,300) (209,927) (216,753) (223,784) (231,025) (221,849) (229,531) (237,444) (245,595) (253,990) (243,506) (252,412) (261,586) (271,034) (280,766) (268,790) (279,115) (289,749) (300,702) (311,984) (5,032,845)
Net Annual Cash Flow (excluding Depreciation) 0 (110,000) (116,627) (123,453) (130,484) (137,725) (128,549) (136,231) (144,144) (152,295) (160,690) (150,206) (159,112) (168,286) (177,734) (187,466) (175,490) (185,815) (196,449) (207,402) (218,684) (3,166,845)
Net Present Value of Cash Flows 5.0% (1,783,595)
Margaret River Cultural Centre Redevelopment Project - "Margaret River Needs a Strong Heart"
Discounted Cash Flow Analysis
Scenario Two - 12 Business Events per annumRate Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Total
Capital Expenditure
Stage 1 - Multi-purpose space
QS Cost Estimate 3,200,000
10% Architects & Consulatants Fees 320,000
Fit out for Kitchen & Bar 150,000
Provision for Technical Fit Out 100,000
3,770,000
Stage 2 - Cultural Centre
QS Cost Estimate 2,060,000
10% Architects & Consulatants Fees 206,000
160 PVC Solar panels 60,000
Provision for Fit Out 50,000
2,376,000
Total Capital Expenditure 6,146,000 6,146,000
Funded by:
Royalties for Regions 5,000,000
Other Grants , Donations & Contributions 146,000
Shire 1,000,000
Total Capital Funding 6,146,000 6,146,000
Operating Revenue
Income from business events 12 1,530,000 1,530,000 1,530,000 1,530,000 1,530,000 1,759,500 1,759,500 1,759,500 1,759,500 1,759,500 2,023,425 2,023,425 2,023,425 2,023,425 2,023,425 2,326,939 2,326,939 2,326,939 2,326,939 2,326,939 38,199,319
Income from current hires (provided to Arts M/R) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Estimated income from additional hires 3% Escalation 30,000 30,900 31,827 32,782 33,765 34,778 35,822 36,896 38,003 39,143 40,317 41,527 42,773 44,056 45,378 46,739 48,141 49,585 51,073 52,605 806,111
Estimated income from Kitchen hires 3% Escalation 20,000 20,600 21,218 21,855 22,510 23,185 23,881 24,597 25,335 26,095 26,878 27,685 28,515 29,371 30,252 31,159 32,094 33,057 34,049 35,070 537,407
Reimbursement of Utilities by Arts M/R 15,000 15,450 15,914 16,391 16,883 17,389 17,911 18,448 19,002 19,572 20,159 20,764 21,386 22,028 22,689 23,370 24,071 24,793 25,536 26,303 403,056
Total Operating Revenue 1,595,000 1,596,950 1,598,959 1,601,027 1,603,158 1,834,853 1,837,113 1,839,442 1,841,840 1,844,310 2,110,780 2,113,400 2,116,099 2,118,880 2,121,743 2,428,207 2,431,245 2,434,374 2,437,597 2,440,917 39,945,893
Operating Expenditure 3% Escalation
Arts Margaret River Contribution 236,900 244,007 251,327 258,867 266,633 274,632 282,871 291,357 300,098 309,101 318,374 327,925 337,763 347,896 358,333 369,082 380,155 391,560 403,306 415,406 6,365,592
Food & beverage staff, costs of goods 1,071,000 1,071,000 1,071,000 1,071,000 1,071,000 1,231,650 1,231,650 1,231,650 1,231,650 1,231,650 1,416,398 1,416,398 1,416,398 1,416,398 1,416,398 1,628,857 1,628,857 1,628,857 1,628,857 1,628,857 26,739,524
Electricity 52,000 53,560 55,167 56,822 58,526 60,282 62,091 63,953 65,872 67,848 69,884 71,980 74,140 76,364 78,655 81,014 83,445 85,948 88,527 91,182 1,397,259
Rebate for Electricity Generated (13,000) (13,390) (13,792) (14,205) (14,632) (15,071) (15,523) (15,988) (16,468) (16,962) (17,471) (17,995) (18,535) (19,091) (19,664) (20,254) (20,861) (21,487) (22,132) (22,796) (349,315)
Other Utilities 1% of revenue 15,950 15,970 15,990 16,010 16,032 18,349 18,371 18,394 18,418 18,443 21,108 21,134 21,161 21,189 21,217 24,282 24,312 24,344 24,376 24,409 399,459
Fixed overheads - maintenance, cleaning, etc 7% of revenue 111,650 111,787 111,927 112,072 112,221 128,440 128,598 128,761 128,929 129,102 147,755 147,938 148,127 148,322 148,522 169,974 170,187 170,406 170,632 170,864 2,796,213
Depreciation 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 1,866,000
Refurbishment allowance 57,400 57,400 57,400 57,400 57,400 66,010 66,010 66,010 66,010 66,010 75,912 75,912 75,912 75,912 75,912 87,298 87,298 87,298 87,298 87,298 1,433,099
Total Operating Expenditure 1,625,200 1,633,633 1,642,319 1,651,266 1,660,481 1,857,592 1,867,368 1,877,438 1,887,809 1,898,492 2,125,258 2,136,591 2,148,265 2,160,288 2,172,672 2,433,555 2,446,693 2,460,226 2,474,164 2,488,521 40,647,831
Financing
Loan Principal Repayments 49,304 51,361 53,504 55,737 58,062 60,485 63,009 65,638 68,377 71,230 74,202 77,298 80,524 83,884 87,384 1,000,000
Loan Interest Repayments 4.13% fixed 41,364 39,306 37,163 34,931 32,605 30,182 27,658 25,029 22,290 19,437 16,465 13,369 10,143 6,784 3,283 360,010
Total Financing Costs 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 0 0 0 0 0 1,360,010
Funded by:
Developer Contribution Plan payments 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 1,360,005
Net financing costs to be funded by Shire 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5
Net Annual Result (30,200) (36,683) (43,361) (50,239) (57,323) (22,739) (30,255) (37,996) (45,969) (54,182) (14,479) (23,191) (32,165) (41,409) (50,929) (5,348) (15,449) (25,852) (36,567) (47,604) (701,943)
Net Annual Cash Flow (excluding Depreciation) 0 63,100 56,617 49,939 43,061 35,977 70,561 63,045 55,304 47,331 39,118 78,821 70,109 61,135 51,891 42,371 87,952 77,851 67,448 56,733 45,696 1,164,057
Net Present Value of Cash Flows 5.0% 679,724
Margaret River Cultural Centre Redevelopment Project - "Margaret River Needs a Strong Heart"
Discounted Cash Flow Analysis
Scenario Three - 18 Business Events per annumRate Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Total
Capital Expenditure
Stage 1 - Multi-purpose space
QS Cost Estimate 3,200,000
10% Architects & Consulatants Fees 320,000
Fit out for Kitchen & Bar 150,000
Provision for Technical Fit Out 100,000
3,770,000
Stage 2 - Cultural Centre
QS Cost Estimate 2,060,000
10% Architects & Consulatants Fees 206,000
160 PVC Solar panels 60,000
Provision for Fit Out 50,000
2,376,000
Total Capital Expenditure 6,146,000 6,146,000
Funded by:
Royalties for Regions 5,000,000
Other Grants , Donations & Contributions 146,000
Shire 1,000,000
Total Capital Funding 6,146,000 6,146,000
Operating Revenue
Income from business events 18 2,295,000 2,295,000 2,295,000 2,295,000 2,295,000 2,639,250 2,639,250 2,639,250 2,639,250 2,639,250 3,035,138 3,035,138 3,035,138 3,035,138 3,035,138 3,490,408 3,490,408 3,490,408 3,490,408 3,490,408 57,298,979
Income from current hires (provided to Arts M/R) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Estimated income from additional hires 3% Escalation 40,000 41,200 42,436 43,709 45,020 46,371 47,762 49,195 50,671 52,191 53,757 55,369 57,030 58,741 60,504 62,319 64,188 66,114 68,097 70,140 1,074,815
Estimated income from Kitchen hires 3% Escalation 25,000 25,750 26,523 27,318 28,138 28,982 29,851 30,747 31,669 32,619 33,598 34,606 35,644 36,713 37,815 38,949 40,118 41,321 42,561 43,838 671,759
Reimbursement of Utilities by Arts M/R 15,000 15,450 15,914 16,391 16,883 17,389 17,911 18,448 19,002 19,572 20,159 20,764 21,386 22,028 22,689 23,370 24,071 24,793 25,536 26,303 403,056
Total Operating Revenue 2,375,000 2,377,400 2,379,872 2,382,418 2,385,041 2,731,992 2,734,774 2,737,640 2,740,592 2,743,632 3,142,651 3,145,876 3,149,198 3,152,620 3,156,145 3,615,046 3,618,785 3,622,636 3,626,603 3,630,689 59,448,609
Operating Expenditure 3% Escalation
Arts Margaret River Contribution 236,900 244,007 251,327 258,867 266,633 274,632 282,871 291,357 300,098 309,101 318,374 327,925 337,763 347,896 358,333 369,082 380,155 391,560 403,306 415,406 6,365,592
Food & beverage staff, costs of goods 1,606,500 1,606,500 1,606,500 1,606,500 1,606,500 1,847,475 1,847,475 1,847,475 1,847,475 1,847,475 2,124,596 2,124,596 2,124,596 2,124,596 2,124,596 2,443,286 2,443,286 2,443,286 2,443,286 2,443,286 40,109,284
Electricity 60,000 61,800 63,654 65,564 67,531 69,556 71,643 73,792 76,006 78,286 80,635 83,054 85,546 88,112 90,755 93,478 96,282 99,171 102,146 105,210 1,612,222
Rebate for Electricity Generated (15,000) (15,450) (15,914) (16,391) (16,883) (17,389) (17,911) (18,448) (19,002) (19,572) (20,159) (20,764) (21,386) (22,028) (22,689) (23,370) (24,071) (24,793) (25,536) (26,303) (403,056)
Other Utilities 1% of revenue 23,750 23,774 23,799 23,824 23,850 27,320 27,348 27,376 27,406 27,436 31,427 31,459 31,492 31,526 31,561 36,150 36,188 36,226 36,266 36,307 594,486
Fixed overheads - maintenance, cleaning, etc 7% of revenue 166,250 166,418 166,591 166,769 166,953 191,239 191,434 191,635 191,841 192,054 219,986 220,211 220,444 220,683 220,930 253,053 253,315 253,585 253,862 254,148 4,161,403
Depreciation 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 1,866,000
Refurbishment allowance 57,400 57,400 57,400 57,400 57,400 66,010 66,010 66,010 66,010 66,010 75,912 75,912 75,912 75,912 75,912 87,298 87,298 87,298 87,298 87,298 1,433,099
Total Operating Expenditure 2,229,100 2,237,749 2,246,657 2,255,833 2,265,284 2,552,144 2,562,170 2,572,498 2,583,135 2,594,091 2,924,070 2,935,693 2,947,666 2,959,997 2,972,698 3,352,278 3,365,753 3,379,632 3,393,928 3,408,652 55,739,030
Financing
Loan Principal Repayments 49,304 51,361 53,504 55,737 58,062 60,485 63,009 65,638 68,377 71,230 74,202 77,298 80,524 83,884 87,384 1,000,000
Loan Interest Repayments 4.13% fixed 41,364 39,306 37,163 34,931 32,605 30,182 27,658 25,029 22,290 19,437 16,465 13,369 10,143 6,784 3,283 360,010
Total Financing Costs 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 0 0 0 0 0 1,360,010
Funded by:
Developer Contribution Plan payments 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 1,360,005
Net financing costs to be funded by Shire 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5
Net Annual Result 145,900 139,651 133,214 126,585 119,756 179,848 172,604 165,142 157,456 149,540 218,581 210,183 201,532 192,623 183,446 262,767 253,031 243,004 232,675 222,036 3,709,573
Net Annual Cash Flow (excluding Depreciation) 0 239,200 232,951 226,514 219,885 213,056 273,148 265,904 258,442 250,756 242,840 311,881 303,483 294,832 285,923 276,746 356,067 346,331 336,304 325,975 315,336 5,575,573
Net Present Value of Cash Flows 5.0% 3,188,658
Margaret River Cultural Centre Redevelopment Project - "Margaret River Needs a Strong Heart"
Discounted Cash Flow Analysis
Scenario Four - 10 Business Events per annumRate Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Total
Capital Expenditure
Stage 1 - Multi-purpose space
QS Cost Estimate 3,200,000
10% Architects & Consulatants Fees 320,000
Fit out for Kitchen & Bar 150,000
Provision for Technical Fit Out 100,000
3,770,000
Stage 2 - Cultural Centre
QS Cost Estimate 2,060,000
10% Architects & Consulatants Fees 206,000
160 PVC Solar panels 60,000
Provision for Fit Out 50,000
2,376,000
Total Capital Expenditure 6,146,000 6,146,000
Funded by:
Royalties for Regions 5,000,000
Other Grants , Donations & Contributions 146,000
Shire 1,000,000
Total Capital Funding 6,146,000 6,146,000
Operating Revenue
Income from business events 10 1,275,000 1,275,000 1,275,000 1,275,000 1,275,000 1,466,250 1,466,250 1,466,250 1,466,250 1,466,250 1,686,188 1,686,188 1,686,188 1,686,188 1,686,188 1,939,116 1,939,116 1,939,116 1,939,116 1,939,116 31,832,766
Income from current hires (provided to Arts M/R) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Estimated income from additional hires 3% Escalation 30,000 30,900 31,827 32,782 33,765 34,778 35,822 36,896 38,003 39,143 40,317 41,527 42,773 44,056 45,378 46,739 48,141 49,585 51,073 52,605 806,111
Estimated income from Kitchen hires 3% Escalation 20,000 20,600 21,218 21,855 22,510 23,185 23,881 24,597 25,335 26,095 26,878 27,685 28,515 29,371 30,252 31,159 32,094 33,057 34,049 35,070 537,407
Reimbursement of Utilities by Arts M/R 15,000 15,450 15,914 16,391 16,883 17,389 17,911 18,448 19,002 19,572 20,159 20,764 21,386 22,028 22,689 23,370 24,071 24,793 25,536 26,303 403,056
Total Operating Revenue 1,340,000 1,341,950 1,343,959 1,346,027 1,348,158 1,541,603 1,543,863 1,546,192 1,548,590 1,551,060 1,773,542 1,776,163 1,778,862 1,781,642 1,784,506 2,040,383 2,043,422 2,046,551 2,049,774 2,053,093 33,579,340
Operating Expenditure 3% Escalation
Arts Margaret River Contribution 236,900 244,007 251,327 258,867 266,633 274,632 282,871 291,357 300,098 309,101 318,374 327,925 337,763 347,896 358,333 369,082 380,155 391,560 403,306 415,406 6,365,592
Food & beverage staff, costs of goods 892,500 892,500 892,500 892,500 892,500 1,026,375 1,026,375 1,026,375 1,026,375 1,026,375 1,180,331 1,180,331 1,180,331 1,180,331 1,180,331 1,357,381 1,357,381 1,357,381 1,357,381 1,357,381 22,282,936
Electricity 50,000 51,500 53,045 54,636 56,275 57,964 59,703 61,494 63,339 65,239 67,196 69,212 71,288 73,427 75,629 77,898 80,235 82,642 85,122 87,675 1,343,519
Rebate for Electricity Generated (12,500) (12,875) (13,261) (13,659) (14,069) (14,491) (14,926) (15,373) (15,835) (16,310) (16,799) (17,303) (17,822) (18,357) (18,907) (19,475) (20,059) (20,661) (21,280) (21,919) (335,880)
Other Utilities 1% of revenue 13,400 13,420 13,440 13,460 13,482 15,416 15,439 15,462 15,486 15,511 17,735 17,762 17,789 17,816 17,845 20,404 20,434 20,466 20,498 20,531 335,793
Fixed overheads - maintenance, cleaning, etc 7% of revenue 93,800 93,937 94,077 94,222 94,371 107,912 108,070 108,233 108,401 108,574 124,148 124,331 124,520 124,715 124,915 142,827 143,040 143,259 143,484 143,717 2,350,554
Depreciation 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 93,300 1,866,000
Refurbishment allowance 57,400 57,400 57,400 57,400 57,400 66,010 66,010 66,010 66,010 66,010 75,912 75,912 75,912 75,912 75,912 87,298 87,298 87,298 87,298 87,298 1,433,099
Total Operating Expenditure 1,424,800 1,433,188 1,441,828 1,450,726 1,459,892 1,627,118 1,636,842 1,646,858 1,657,174 1,667,800 1,860,197 1,871,470 1,883,081 1,895,040 1,907,358 2,128,716 2,141,784 2,155,245 2,169,109 2,183,389 35,641,613
Financing
Loan Principal Repayments 49,304 51,361 53,504 55,737 58,062 60,485 63,009 65,638 68,377 71,230 74,202 77,298 80,524 83,884 87,384 1,000,000
Loan Interest Repayments 4.13% fixed 41,364 39,306 37,163 34,931 32,605 30,182 27,658 25,029 22,290 19,437 16,465 13,369 10,143 6,784 3,283 360,010
Total Financing Costs 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 0 0 0 0 0 1,360,010
Funded by:
Developer Contribution Plan payments 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 90,667 1,360,005
Net financing costs to be funded by Shire 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5
Net Annual Result (84,800) (91,238) (97,869) (104,700) (111,735) (85,516) (92,979) (100,666) (108,584) (116,740) (86,655) (95,307) (104,219) (113,398) (122,852) (88,333) (98,363) (108,694) (119,335) (130,295) (2,062,278)
Net Annual Cash Flow (excluding Depreciation) 0 8,500 2,062 (4,569) (11,400) (18,435) 7,784 321 (7,366) (15,284) (23,440) 6,645 (2,007) (10,919) (20,098) (29,552) 4,967 (5,063) (15,394) (26,035) (36,995) (196,278)
Net Present Value of Cash Flows 5.0% (94,248)
ITEM 6.1.1 Cultural Centre Redevelopment Funding
Applications Update
Attachment 5
5 December 2014
Mr Gary Evershed
Chief Executive Officer
Shire of Augusta Margaret River
41 Wallcliffe Rd
Margaret River WA 6285
Dear Gary,
I write as Chief Executive Officer of the Perth Convention Bureau (PCB) to support your proposal to
expand the existing Margaret River Cultural Centre to include a Business Events Centre.
PCB is responsible for marketing Western Australia as a business events destination. It is an agency
funded by the State Government, City of Perth and the private sector through our 228 members.
Demand for corporate meetings, small conferences, and pre/post touring options in unique locations
is strong, particularly in the Margaret River Region, given the density of existing tourism
infrastructure. A dedicated Business Events Centre would be ideally placed there, and add
substantially to the region economically, socially and culturally.
During the 2013-2014 financial year, PCB secured 109 conferences and 84 corporate meeting and
incentive events with an estimated direct delegate expenditure of $107.9 million. These pieces of
business will materialise across 2014 – 2017.
In addition to conferences already secured for the Margaret River region, PCB is currently working
on a number of bids that could have the potential to be held in the region should the infrastructure
and standards meet the criteria set by our corporate and association clients.
With increased, dedicated meeting space, set in the unique Margaret River location, the proposed
development will enhance the offering the region can provide to business events clients.
A dedicated Business Events Centre would be ideally placed there, and add substantially to the
region economically, socially and culturally. To that end, being aware of the criteria and submission
process, its validity to access Royalties for Regions Funding is highly appropriate Yours sincerely
Paul Beeson
Chief Executive Officer
5 December 2014 Mr Gary Evershed Chief Executive Officer Shire of Augusta Margaret River 41 Wallcliffe Rd Margaret River WA 6285 Dear Gary, I write as Chief Executive Officer of the Perth Convention Bureau (PCB) to support your proposal to expand the existing Margaret River Cultural Centre to include a Business Events Centre. PCB is responsible for marketing Western Australia as a business events destination. It is an agency funded by the State Government, City of Perth and the private sector through our 228 members. Demand for corporate meetings, small conferences, and pre/post touring options in unique locations is strong, particularly in the Margaret River Region, given the density of existing tourism infrastructure. A dedicated Business Events Centre would be ideally placed there, and add substantially to the region economically, socially and culturally. During the 2013-2014 financial year, PCB secured 109 conferences and 84 corporate meeting and incentive events with an estimated direct delegate expenditure of $107.9 million. These pieces of business will materialise across 2014 – 2017. In addition to conferences already secured for the Margaret River region, PCB is currently working on a number of bids that could have the potential to be held in the region should the infrastructure and standards meet the criteria set by our corporate and association clients. With increased, dedicated meeting space, set in the unique Margaret River location, the proposed development will enhance the offering the region can provide to business events clients. A dedicated Business Events Centre would be ideally placed there, and add substantially to the region economically, socially and culturally. To that end, being aware of the criteria and submission process, its validity to access the Federal Stronger Regions Program is highly appropriate. Yours sincerely
Paul Beeson Chief Executive Officer