Progress Update Week ending 15th April

Page 2: ITS Bulding Project  - progress update April 2016

Programme Update - ITS For Period : Mon 14th March – Friday 15th April

- Completed new dormer construction within roof and associated external render

- Completed Bauder roofing to new build structure and continued works to existing re-roof

- Completed external brickwork to new-build structure & began stripping scaffold

- Completed floor screed pour to all floors and construction of internal lift shift

- Commenced internal partitions within new and existing buildings

- Commenced ceiling works to existing building & internal/external decorations

Page 3: ITS Bulding Project  - progress update April 2016

Progress Photos

Internal wall linings completed within new build structure

Page 4: ITS Bulding Project  - progress update April 2016

Progress Photos

Internal decorations commenced to all rooms in existing building (including cornice repairs)

Page 5: ITS Bulding Project  - progress update April 2016

Progress Photos

New roof dormer constructed and externally rendered

Page 6: ITS Bulding Project  - progress update April 2016

Progress Photos Roof to new-build structure complete and re-roofing to existing building ongoing – installation of new ‘Velux’ roof lights also commenced

Page 7: ITS Bulding Project  - progress update April 2016

Progress Photos

1st fix M&E continued to new build structure

Page 8: ITS Bulding Project  - progress update April 2016

Next Few Weeks………..A look ahead to works commencing within the next 4 weeks :

- Commence installation of new passenger lift

- Complete works to existing re-roof and associated areas

- Continue 2nd fix joinery including hanging the doors throughout the existing building

- Complete necessary sub-station cabling works to energise new mains panel board

- Commence the installation of lighting within the existing building

- Commence installation of curtain walling/glazing to new build structure

- Continue internal decorations and complete all external decorations