iv.a recent planning studies€¦ · stability studies typical time for ibrs from initial planning...

19
IV.A Recent Planning Studies Shun Hsien (Fred) Huang February 24, 2020 ERCOT GTC Workshop

Upload: others

Post on 24-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

IV.A Recent Planning

Studies

Shun Hsien (Fred) Huang

February 24, 2020

ERCOT GTC Workshop

Page 2: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Most Common Stability Challenges

2

2018 LTSA Stability Assessment

Long Distance

Large Power

Transfer

Weak Grid

Page 3: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Long Distance Large Power Transfers

3

1900.0

300.0

2BUS 2

0.9316.4

SW

-336.4

3BUS 3

1.0355.3

-900.0

36.4

927.1

358.8

463.6

179.4R

463.6

179.4RA Typical 345 kV

Circuit in West Texas

Significant reactive

losses and system

reactive need.

Continue adding

reactive support

may not be the best

solution.

300 600 900

Line Q Losses -60 80 395

Angle Separation 8.5 17 29

0

5

10

15

20

25

30

35

-100

0

100

200

300

400

500

An

gle

Sep

arat

ion

(d

egr

ee)

Lin

e Q

Lo

ss (

MV

AR

)

Line Flow (MW)

Large angle

separation limits the

transfer capability.

Page 4: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Long Distance Large Power Transfers

4

Generator speed (Hz)

Time (sec)0.00 2.00 4.00 6.00 8.00 10.00

60.00

60.40

60.80

61.20

61.60

62.00

Syn. Gen

Syn. Gen

Angular instability Inter-area Oscillation

Robust exciters

improve the angular

instability.

Power system

stabilizers improve

the damping.

Page 5: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Weak Grid

5

PMU measurement of a wind

plant connect to a weak grid in

West Texas.

Fault

location

Broader and larger voltage dips during

and after faults. Challenges for voltage

recovery.

Page 6: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Weak Grid

6

Steady State Voltage Instability Dynamic Voltage Instability

Voltage Collapse

point above 0.95 pu

Tools/Models Adequacy?

Page 7: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public 7

• Algebraic equation with no time step

• Solved in < 1 sec

• 60 Hz, steady state

• Tools: PSS/e, Powerworld, PSAT

• Parameters: ~tens• Differential equation with time step of 1 ~ 4 ms

• Simulation finished in 1 ~ 10 mins

• Tools: PSS/e, Powerworld, TSAT

• Parameters: tens ~ hundreds

• Differential equation with time step of

10 ~ 50 us

• Simulation finished in 10 mins ~

hours

• Tools: PSCAD

• Parameters: tens ~ hundreds

Steady StateDynamic

(Electromechanic)Transient

(Electmagnetic Transient)

12

00

21

BB

SE

S_

UN

IT1

1.1

19

.3

L1

27

0.0

23

5.6

R

-26

9.7

-21

4.2

1

1

27

0.0

23

5.6

12

00

22

BB

SE

S_

UN

IT2

1.1

19

.2

AL

0.0

0.0

27

0.0

23

5.6

R

33

80

BIG

BR

N_

_5

1.0

35

6.0

31

33

RIC

HL

ND

2_

5

1.0

35

6.3

31

34

RIC

HL

ND

1_

5

1.0

35

6.0

29

3.0

-12

.7

-29

2.7

8.3

All the GTCs are identified in the dynamic studies.

Accurate and good quality models are critical.

Page 8: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Recent Planning Studies

• 2018 Panhandle and South Texas Stability and System

Strength Assessment

• 2018 Dynamic Stability Assessment of High Penetration of

Renewable Generation in the ERCOT Grid

• 2019 Panhandle Regional Stability Study

• 2020 Panhandle Regional Stability Study (ongoing)

• 2020 Dynamic Stability Assessment of High Penetration of

IBRs in West Texas (ongoing)

• 2019 RTP GTC Exit Alternatives Evaluation

8

Page 9: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Panhandle Studies

9

4300

55365182 5223

126

1356

3174

4992

0

1000

2000

3000

4000

5000

6000

2016 Study 2018 Study 2019 Study 2020 Study

Gen

erat

ion

Cap

acit

y (M

W)

IBRs Capacity (MW) Met PG6.9

Panhandle IBRs (MW) Nearby Panhandle IBRs (MW)

Inverter-Based Resource (IBR): A Resource that is connected to the

ERCOT System either completely or

partially through power electronic

converter interface. For example, wind,

solar PV, and battery.

Page 10: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Nearby

Panhandle WGRs

5182

MW

SCs

ERCOT

Grid

3174

MW

• Identified stability limitations in Panhandle

– Oscillatory/angular stability in normal operation (no planned outages)

– Voltage stability under planned outage condition (modified thresholds)

• Key takeaways:

– Nearby Wind Generation Resources (WGRs) provide voltage support

along transfer path

– Nearby WGRs drive larger angles in Panhandle

– Lubbock integration improves the stability issues

10

2019 Panhandle Study

Panhandle WGRs

Page 11: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Aggregated MW in

Panhandle/Nearby Panhandle

MW of a synchronous

generator in the Coast region5MW

~180MW

Out ofPhase

Observed Oscillation

• Oscillatory responses are observed during high power

transfer

• Synchronous condensers identified as primary participant

11

Page 12: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

2018 Study: High Penetration of IBRs

• Based on studied 2031 LTSA scenario

• ~70% Penetration of Inverter-Based

Resources (IBRs, like wind and solar)

• Significant active and reactive power

losses

• IBR controls require sufficient system

strength for reliable operation or more

robust inverter control capability is

required, grid forming (?)

• Synchronous condensers are subject to

synchronous machine instabilities (inter

& intra area oscillations & angular

instability)

• Additional Transfer Paths between West

Texas and Central Texas Were

Beneficial

12

Page 13: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

2020 Study: High Penetration of IBRs

• 2022 DWG HWLL case with the inclusion of planned IBRs

(met PG 6.9) in West Texas.

• Average IBR Dispatch: 83%

• IBR Penetration: ~58% (historical penetration record)

13

Area IBR Capacity (MW) IBR Output (MW)

West Texas 2,4373 20,166

South Texas 6,841 5,615

Total 31,214 25,781

Page 14: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

2019 Regional Transmission Plan (RTP)

• The 2019 Regional Transmission Plan

(RTP) economic analysis enforced the Lobo

to North Edinburg GTC (N-1 conditions)

• The Panhandle GTC was not enforced in

the 2019 RTP based on the results from

updated Panhandle stability studies

– These updates were presented at the August

2019 ROS meeting

14

Page 15: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

2019 Regional Transmission Plan (RTP)

• The Lobo to North Edinburg GTC was modeled and

enforced in the 2019 RTP economic analysis

• The interface did not experience enough congestion to

justify the multiple 345-kV system improvements that make

up its GTC exit alternative

15

Study YearCongestion

Rent ($M)

% of Hours

Congested

2021 3.8 1.6

2024 6.7 2.4

Page 16: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Ongoing Evaluation of GTC Exit Alternatives

• As appropriate, ERCOT will continue to evaluate GTC exit

alternatives against the economic planning criteria during

the RTP process

• Based on recent stability studies, ERCOT expects that

more GTCs will be modeled in the 2020 RTP

• ERCOT will consider the viability and usefulness of

processes for the economic review of GTC exit alternatives

outside of the RTP

16

Page 17: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Takeaway: Evolving stability challenges

• Example

17

PanhandleNearby

PanhandleWest Texas

Export

Synchronous Generators

Wind Plants PV Plants Battery/DER…

Location and technology are important

Page 18: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Takeaway: Dynamic model availability, accuracy,

and quality are critical

18

Dynamic Models

Manufactures/Consul

tants

Resource Entities/Developers

Utilities/

System Operators

Stability Studies

Typical time for IBRs from

initial planning to physical

interconnection

18-24

MonthsNumber of IBRs

currently planned

beyond 2022

0

2.6

1.61.1

2.6 2.8

1.3

0

0.5

1

1.5

2

2.5

3

2017 2018 2019T

ime D

iffe

rence (

Year)

Year of Meeting Modeling Requirements

Wind Solar

Average duration of planned projects

between meeting modeling requirements and

projected commercial operation date

Dynamic models can be available only ~8 months prior to COD

Page 19: IV.A Recent Planning Studies€¦ · Stability Studies Typical time for IBRs from initial planning to physical interconnection 18-24 Months Number of IBRs currently planned beyond

Public

Takeaway: Mitigation Considerations

• Better stability management

• Dynamic performance review and improvement

• Better reliability support

– damping support, robust control under weak grid,…

• Grid enhancement

– AC circuit, DC circuit, reactive support, synchronous condenser,

FACTs,…

19