ivan dontsov, andy phenix, maureen rottschaefer. project outline “the primary objective of this...
TRANSCRIPT
DISTRIBUTED TEAM COLLABORATION PROCESSES IIOMSE 555 MID-TERM (WINTER
2012)
Ivan Dontsov, Andy Phenix, Maureen Rottschaefer
Project Outline
“The primary objective of this OMSE 2012 Practicum Project is to extend and refine the process specification tool (developed during the 2010 Practicum) and address some of its limitations.
In particular, the project will address the ‘most obvious extension’ to provide a more user-friendly interface and easier administrative support.”
Team Members
Ivan Dontsov – Software Architect Andy Phenix – Project Manager Maureen Rottschaefer – Requirements
Manager
Roles OMSE 555
Software Project Manager (SPM)(Andy Phenix)
Software Architect (SA)(Ivan Dontsov)
OMSE 555 / 556Project Team
OMSE Customer(Stuart Faulk)
Requirements Manager (RM)
(Maureen Rottschaefer)
OtherOMSE 555 / 556Project Teams
Roles OMSE 556
Software Project Manager (SPM)(Andy Phenix)
Software Architect (SA)
(Ivan Donstov)
OMSE 555 / 556Project Team
OMSE Customer(Stuart Faulk)
Requirements Manager (RM)
(Maureen Rottschaefer)
OtherOMSE 555 / 556Project Teams
Software Developer / Tester
(Andy Phenix)
Software Developer / Tester
(Ivan Donstov)
Software Developer / Tester
(Maureen Rottschaefer)
Primary Role
Secondary Role
Project Management
Phased ApproachWaterfall Process for OMSE 555Transition to Iterative for OMSE 556
Jan-12 Jun-12Apr-12
Jan-12 - Mar-12Phase 1 - Base-lining
Mar-12Baseline Requirements CompleteCandidate Architecture Complete
Mar-12 - May-12Phase 2 - Core Functionality
May-12 - Jun-12Phase 3 - Enhancements, Revisions
May-12Core Functionality Complete
Jun-12Final Delivery
OMSE 555 OMSE 556
Key Deliverables - Status Project Proposal
Published
SPMPDraft Issued for Review
SRSDraft Issued for Review
SADIn Progress
Requirements Process
Existing Process Tool Analyzed Past Process Project Analyzed Initial Requirements Documented Review of Requirements by OMSE 555
students Final Requirements Documented
Software Architecture
Web-Based Application PSU Hosting Linux Platform Mono Development Framework MySQL Database (likely)
Challenges
ResolvedInter-Team CommunicationRoles & ResponsibilitiesRedmine
OutstandingQA Role
What’s Next Project Plan
WBS, Estimates and Schedule for OMSE 556
RequirementsComplete SRS for Primary FunctionalityPaper Protoypes for Web UI
Architecture‘Hello World’ Application on Target PlatformModule Design
Project Website