izvoarele 38 mw pv plant

11
38 MW PV PLANT IZVOARELE - Giurgiu County - ROMANIA Photovoltaic Engineering BORRA BORRA Energy Plant Energy Plant Srl Srl January , 2012 Presentation to Potential Investors

Post on 20-Oct-2014

344 views

Category:

Investor Relations


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: IZVOARELE 38 MW PV PLANT

38 MW PV PLANTIZVOARELE - Giurgiu County - ROMANIA

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

January , 2012

Presentation to Potential Investors

Page 2: IZVOARELE 38 MW PV PLANT

Opportunity Background The Big Picture

Capitalize on Government-backed Green Certificate (GC) incentive scheme with top prices achievable for early entrants (estimated top GC trading price at least 3 years from Renewable Energy Law publishing)

Tap in to high demand for renewable energy created by Romanian Government undertaking targets vs. EU green energy policy.

For the next 2-3 years at least, the revenues from green energy projects (MWh price plus GC price) will slightly increase vs. the current price situation (no external market factors are considered). Application of GC subsidies system is covered by a MWh price increasing (until 2020 it is estimated a MWh price increasing up to 30%)

Romania rated as the 3rd fastest growing country in the EU for gaining planning permission for wind turbine developments (according to European Wind Energy Association); After the coming into force of Renewable Energy Law it is expected a similar growth for PV developments.

Since launch of trading platform, GCs have been traded at the maximum price, i.e. 241.04 Ron. GC are fully traded.

Renewable Energy Law is applicable starting October 2011 (Government Order 88/12.10.2011)

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

1

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 3: IZVOARELE 38 MW PV PLANT

Tariff Review

Romanian Government undertaking for renewable energy, including hydro, concerns an increasing of renewable energy production vs. gross internal energy production at 38% by 2020

Renewable energy, that benefits of GC system subsidies is set at 20% from total energy production by 2020 (from 10% in 2011 and 12% in 2012)

GC tariff schedule will operate for 15 years from commissioning date, providing project starts no later then 2016

Solar generated power will receive 6 GCs per MWh;

GC prices: min. €27 to max. €55; starting with 2011, the GC price will be EU inflation-indexed at set up in Ron based on average Eur/Ron at the BNR exchange rate established in December, “previous” year.

Current average electricity price €50 per MWh (average price for interval 1-24 h for 2011); tariff used in the financial modelling, also.

Penalties of €110 per non-purchased GC, payable by non-compliant electricity suppliers -> twice the price of purchasing Green Certificates. The penalty is also EU inflation-indexed

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

2

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 4: IZVOARELE 38 MW PV PLANT

Project’s Specifics

The Project has an installed power of 38 MW, being developed over a land with a surface of over 75 ha, divided in 3 plots interconnected with 20 kV underground power lines (see layout in page 6).

The current use of land is agricultural; it is plane and free of any type of constraints (environmental etc).

The land is privately owned; the rights are secured for a period of 35 years, starting December 2011.

The location is conveniently placed along a county road and within the close proximity of a railroad

station.

There is a double 110 kV overhead power line crossing one of the 3 plots of land covered by the project, owned by the local power distribution company (ENEL Muntenia); this line will be used to connect the PV plant to the national power grid.

The fixed ground-mounted PV panels will be of premium quality, supplied by REC Group – Norway (type REC 235 PE), with an efficiency of up to 14.2%, a 10 year product warranty and a 25 year linear power output warranty (max. degression in performance of 0.7% p.a.).

The invertors will also be of premium quality, from SMA – Germany.

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

3

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 5: IZVOARELE 38 MW PV PLANT

Solar Resource

Over 210 sunny days per annum

1450-1500 kWh / sqm is the yearly sum of global irradiation

The figures are submitted in kWh (per mp/year), on optimally – inclined PV modules, the most used calculation method for energetic application.

Photovoltaic Geographical Information Systems (PVGIS) is a software approved by the Centre for Renewable Energy Sources

The solar map related for Giurgiu area is developed and offered by Energy Research Institute – Italy, entity under coordination of the EU

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

4

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 6: IZVOARELE 38 MW PV PLANT

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

5

Solar Resource

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 7: IZVOARELE 38 MW PV PLANT

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

6

Project’s

layout

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 8: IZVOARELE 38 MW PV PLANT

Permitting process – general overview:

According to the Romania laws, there are two key-permits to be obtained:

1. The Construction Permit, as a result of a land use change procedure and an application file including different additional permits (including Environmental Permit) and basic designs (civil works and technical design) of the project;

2. The Connection-to-the-grid Permit, following a procedure that includes, among getting few other additional permits, a Connection Solution Study performed by an authorized consultant.

Permitting process – project’s status:

The procedure for the change of the land destination was initiated; civil works design and technical designs are in progress already; the Construction Permit is expected to be issued in April 2012.

The Connection Solution Study was contracted and initiated; the Connection Permit is expected to be issued in March 2012.

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

7

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 9: IZVOARELE 38 MW PV PLANT

Financial figures for a ..... years investment :

Estimated revenues: EUR ..... per year,

Total investment costs: EUR .....,

Estimated operation and maintenance costs per annum - 5% from total income

Estimated debt / equity ratio: ....

Recovering investment period: ..... years

Other financial indicators: IRR project – .....%, EBITDA margin – .....%, Net margin profit – ......%, ROE – ......% (yearly average ROE – ......%), NPV – EUR ....., (@ assumed cost of capital ...% p.a.) ...... ......

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

8

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 10: IZVOARELE 38 MW PV PLANT

Assumptions for revenues’ estimation:

Green Certificate price Considered the current price of EUR 56.16 (equiv. of RON 241 at an exchange rate of 4.25) Yearly adjusted with inflation rate (EUROSTAT data), estimated at 2.50% p.a. (average for 2005-2010 was

2.70%; for 2011 estimated at 2.70%) No changing negative adverse pricing up to 2015 (included) Starting with 2015 until 2020, we’ve considered a GC price decreasing of 30%, constantly distributed during

the analysed period.

Electricity Price 2011 MWh price considered is EUR 50 (based on 2011 quantity electricity statistics, for 0-24h intervals; for

2011 the average price was EUR 51.75) From 2012 (included) to 2020 we estimate a price increasing of 27,5% (according to ANRE’s publication, the

price increasing of 30% is considered until 2017/2018), constantly distributed during the analysed period ; No external factors market considered which might affect the internal price energy No Romanian’s commitment considered to EU for market liberalisation of energy price

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

9

IZVOARELE PV PLANTIZVOARELE PV PLANT

Page 11: IZVOARELE 38 MW PV PLANT

Proposed Selling Structure

.... ....

Photovoltaic Engineering

BORRABORRA

Energy Plant SrlEnergy Plant Srl

10

IZVOARELE PV PLANTIZVOARELE PV PLANT