  • 7/27/2019 James Wight 1

    1/28

    ACI Building Code: Operationsand Discussion of Recent &

    Coming Changes

    James K. Wight

    Chair of ACI Committee 318Dept. of Civil & Env. Eng.

    University of Michigan

  • 7/27/2019 James Wight 1

    2/28

    ACI 318: Philosophy for

    Committee Operation

    Consensus Document Based on Practical EngineeringPrinciples

    Membership: 53% Practicing Engineers, 33%Academics, and 14% Trade or Govt. Associations

    Goal is for continuous improvement in safety andusability of the code, not just simplification

    New items for the code need a reason statement tojustify the proposed change and must containexample(s) to show the impact on current designpractice

  • 7/27/2019 James Wight 1

    3/28

    ACI 318 Code Committee

    Code organization: 22 Chapters

    4 Appendices

    Committee organization: 8 Subcommittees

    Technical change proposals are developed by

    subcommittees and approved by main committee. Each chapter/appendix is the responsibility of a

    different subcommittee.

  • 7/27/2019 James Wight 1

    4/28

    Whats new in 318-05

    Consistent notation Alternative torsion design procedure

    Use of spiral reinforcement with fy of 100 ksi

    for confinement Limits on reinforcement spacing for crack

    control and skin reinforcement

    Need for shear reinforcement at slab-columnconnections of structures in high seismicperformance categories

  • 7/27/2019 James Wight 1

    5/28

    ACI 318-02 Notation Issues

    Angle of inclination of inclined stirrups(shear - chapter 11)

    Modification factor for top bars(anchorage chapter 12)

    Ratio of flexural stiffness of beam toflexural stiffness of slab (two-way slabs

    chapter 13)

  • 7/27/2019 James Wight 1

    6/28

    ACI 318-02 Notation Issues

    Reinforcement ratio for vertical web

    reinforcement in walls (ordinary

    systems) Chapter 14

    Reinforcement ratio for horizontal web

    reinforcement in walls (specialsystems)- Chapter 21

    n

    n

  • 7/27/2019 James Wight 1

    7/28

    Notation and Terminology Task

    Group

    Task group formed to reduce the number ofconflicts and duplicate definitions in 318-05.

    Task group recommendations were sent

    directly to the main committee and were notballoted by any of the eight subcommittees.

    Task group generated more than half of thechanges to 318-02 that were released forpublic comment.

  • 7/27/2019 James Wight 1

    8/28

    Approach Taken

    Each term used in the code should have aunique definition.

    Consolidate similar terms where possible.

    Add or revise subscripts to distinguish amongterms and give meaning to them.

    Existing terms were not modified unlesschanges were required to avoid duplication ofnotation.

  • 7/27/2019 James Wight 1

    9/28

    Consolidation of Terms

    318-02 fy yield strength (most chapters and appendices)

    fyh yield strength (11, circular hoop)

    fyh yield strength (21, all transverse reinf.)

    fy yield strength (11, longitudinal steel)

    fyv yield strength (11, transverse steel)

    fyt yield strength (12, transverse steel)

  • 7/27/2019 James Wight 1

    10/28

    Consolidation of Terms

    318-05 fy specified yield strength of reinforcement

    fya specified yield strength of anchor steel

    fyt

    specified yield strength of transverse reinforcement

    =

    v y

    s

    A f d

    V s =

    v yt

    s

    A f d

    V s

    =

    g c

    s c y

    A f

    . A f0 45 1

    =

    g c

    s ch yt

    A f

    . A f0 45 1

    ACI 318-02 ACI 318-05

  • 7/27/2019 James Wight 1

    11/28

    Development Length

    318-02 reinforcement location factor (12)

    coating factor (12)

    reinforcement size factor (12)

    lightweight aggregate concrete factor (12)

    A

    3

    40

    yd b

    c t r

    b

    fd

    f c K

    d

  • 7/27/2019 James Wight 1

    12/28

    Development Length

    318-05: factor used to modify development lengthbased on

    reinforcement location reinforcement coating

    reinforcement size

    A

    3

    40

    y t e sd b

    c t r

    b

    fd

    f c K

    d

    t e s

  • 7/27/2019 James Wight 1

    13/28

    Text Versus Notation

    The possibility of using only notation within theCode text was discussed.

    11.1.3 Computation of maximum factored

    shear forceVu at supports ...

    11.1.3 Computation of maximum Vu at

    supports ...

  • 7/27/2019 James Wight 1

    14/28

    Defining of Terms in Code

    A limited number of common terms are not defined eachtime they are used:

    Terms are defined the first time that they are used in asection, and only the notation is used subsequently.

    yf

    cf

    d b wb hn nV uVnM uM

  • 7/27/2019 James Wight 1

    15/28

    Alternate Design Procedure

    in Torsion

    Section 10.6.7 permits an alternate torsion designprocedure for deep thin members where the equivalenttube analogy leads to very unconservative designs

    h/bt 3

    bt

    h

  • 7/27/2019 James Wight 1

    16/28

    Alternate Design Procedure

    in Torsion

    Permitted to use method given in PCI Handbookand/or method given in paper by Zia and Hsu,PCI Journal, May-June 2004. Tn is taken equal toTc plus Ts and for the concrete contribution in

    torsion they use:

    ( )20.8 2.5 1.5

    101

    c c

    e

    g c

    T f x y

    P

    A f

    =

    = +

    y1x1

    x2

    y2

  • 7/27/2019 James Wight 1

    17/28

    Use of High-Strength Steel for

    Spiral Reinforcement

    Section 10.9.3 permits the use of steelwith a yield strength, fy, up to 100 ksi (690MPa) for spiral reinforcement.

    fy 100 ksi

  • 7/27/2019 James Wight 1

    18/28

    Use of High-Strength Steel for

    Spiral Reinforcement

    In Chapter 21 (earthquake-resistantdesign), the value of fy permitted fordesign is limited to 60 ksi (21.11.5). Note:this limit is to be enforced when checkingthe shear strength of spiral columns, butthe higher yield strength (100 ksi) ispermitted when designing spiral as

    confinement reinforcement.

  • 7/27/2019 James Wight 1

    19/28

    Limits on Bar Spacing for

    Crack Width Control

    Section 10.6.4 Applies to reinforcementnearest to the extreme tension fiber.

    s

    ss

    cc

    or

  • 7/27/2019 James Wight 1

    20/28

    Limits on Bar Spacing for

    Crack Width Control Limiting equation was changed to reflect

    potentially higher working stresses resultingfrom changes in load factors and phi factors.

    40,00015 2.5

    40,00012

    c

    s

    s

    s cf

    sf

  • 7/27/2019 James Wight 1

    21/28

    Spacing Limit for Skin

    Reinforcement in Deep Beams

    In 2002 Code, thelimit was based ond, not h.

    Also, the spacinglimit was given asa function of the

    size of the bar.

    s

    s

    s

    s 36 in.

    h/2

    cc

  • 7/27/2019 James Wight 1

    22/28

    Spacing Limit for Skin

    Reinforcement in Deep Beams

    Research has shown that the size of the bar isnot important, so the code was simplified andthe spacing limit is the same as that for crack-

    control reinforcement.

    40,00015 2.5

    40,00012

    c

    s

    s

    s c

    f

    s

    f

  • 7/27/2019 James Wight 1

    23/28

    Need for Shear Reinforcement

    at Slab-Column Connections

    Although not designed as part of the systemfor resisting lateral loads, transfer momentscan be developed at these connections due

    to lateral drift of the building during anearthquake.

    If connection area is already subjected to

    high shear stresses for resisting gravityloads, displacement-induced transfermoments can cause a punching shear

    failure.

  • 7/27/2019 James Wight 1

    24/28

    Need for Shear Reinforcement

    at Slab-Column Connections

  • 7/27/2019 James Wight 1

    25/28

    Need for Shear Reinforcement

    at Slab-Column Connections

    Section 21.11.5 requires a minimum amount ofshear reinforcement as a function of gravityinduced shear and expected story drift.

  • 7/27/2019 James Wight 1

    26/28

    Potential Changes for ACI 318-08

    Modification (modernization) of analysisportions of the code.

    Include in-plane design of structural walls in

    Chapter 14. Use of steel studs as shear reinforcement at

    slab-column connections.

    Include adhesive and grouted anchors inAppendix D.

    Simplify the analysis and design procedures

    for slender columns.

  • 7/27/2019 James Wight 1

    27/28

    Potential Changes for ACI 318-08

    Modification of the stress block for usewith high-strength concrete.

    Include the size effect for shear strength

    contributed by concrete in deep beams. Include seismic design categories within

    Chapter 21.

    Seismic design requirements for foundations,including concrete piles.

    General reorganization and reduction of

    textbook material included in the Code.

  • 7/27/2019 James Wight 1

    28/28

    Summary for ACI 318-05

    Primary change was to achieve consistentnotation throughout the code.

    Limited number of technical changes.

    Expect more technical changes in 2008edition of the Code.