jan 31, 2005 community update. jan 31, 2005 thanks to the voters… measure r passed with over 63%...
TRANSCRIPT
![Page 1: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/1.jpg)
Jan 31, 2005
Community Update
![Page 2: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/2.jpg)
Jan 31, 2005
Thanks to the voters…
• Measure R passed with over 63% of the vote
• $3.87 billion for “the Safe and Healthy Neighborhood Schools Improvement Act of 2004”
![Page 3: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/3.jpg)
Jan 31, 2005
What did you approve in Measure R ?
1. New construction/Acquisition projects ($1.857B)
2. Repair, Upgrade, and Modernization projects ($1.563B)- Specified projects- Projects of certain types
![Page 4: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/4.jpg)
Jan 31, 2005
What we committed to…
• A Plan
• Engaging Stakeholders
• Strategic Execution Plan
![Page 5: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/5.jpg)
Jan 31, 2005
General Process
• Some Projects Already Identified
• Other Projects Need to be identified
![Page 6: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/6.jpg)
Jan 31, 2005
Project types:
1. Major repair ($315M)
2. Core Facilities ($300M)
3. Small Learning Communities ($88M)
![Page 7: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/7.jpg)
Jan 31, 2005
Identify the Remaining Projects
Possible Major Repair
Projects
Possible Core Facilities
Projects
Possible Small Learning Communities
Projects
Sorting Process
List
List
List
ConfirmPriorities
Community Review
Citizen’sBond
OversightCommittee
& Board of Education
June2005
StrategicExecution
Plan
![Page 8: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/8.jpg)
Jan 31, 2005
Methodical Process
• Assess the Needs
– Condition of Buildings
– Safety / Building Code Compliance
– Functionality
![Page 9: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/9.jpg)
Jan 31, 2005
1. Major Repair
![Page 10: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/10.jpg)
Jan 31, 2005
Prioritizing Major Repair Needs
• Assess the Condition of the Facilities
• Determine the Facilities Condition Index (FCI)
The Higher the FCI: The Higher the Repair Needs
![Page 11: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/11.jpg)
Jan 31, 2005
Facilities Condition Index (FCI)DISTRICT CLASSROOM BLDG
Building Needs: Cost of repair:
Re-roof $12,000
Re-Paint Exterior $2,500
New Energy Efficient Lighting $8,000
Total $22,500
Current Building Replacement Value $160,000
FCI =Cost of Needed Repairs
Current Replacement Value =
$22,500
$160,000 = 0.14
![Page 12: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/12.jpg)
Jan 31, 2005
Approach:
• Allocate funds to achieve consistent level of repair across District
• Projects selected per weighted scores in the following categories:– Immediate health and safety– Code compliance and liability– Asset safeguards and
deterioration– Age and aesthetics
![Page 13: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/13.jpg)
Jan 31, 2005
2. Core Facilities
Sanitary FacilitiesFood Service Kitchen / CafeteriaMulti-Purpose RoomsLunch SheltersLibrariesAdministrative OfficesGymnasiumsAuditoriumsPlaygroundsParking
![Page 14: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/14.jpg)
Jan 31, 2005
Campus Ranking by Need
Survey the Core Facilities
Compare Existing Facility to New School Facility
Prioritize the Needs by:Category of the Facility (cafeteria, library, etc.)Deficiency of the Facility (missing or too small)
![Page 15: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/15.jpg)
Jan 31, 2005
Category PrioritiesHigher Category – More Points
1. Code Compliance & Life-Safety Requirements
2. Sanitary Facilities, Food Preparation, Food Serving, Indoor Dining/Multi-Purpose Room
3. Library, Administration Space, Lunch Shelter
4. Gymnasium, Auditorium, Playground, Parking
![Page 16: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/16.jpg)
Jan 31, 2005
Deficiencies in FacilitiesLess Space / Greater Need – Higher Deficiency
Factor
Missing Core Facility – Maximum Deficiency Factor
100% of New School Facility - No Deficiency Factor
![Page 17: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/17.jpg)
Jan 31, 2005
Proposed Funding Distribution by Core Facilities Category
76%
12%
12%
• 76% for Missing or Extremely Deficient Core Facilities
• 12% for Food Services Modernizations
• 12% for Local District Determined “Needs-Based” Modernization
![Page 18: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/18.jpg)
Jan 31, 2005
3. Small Learning Communities
![Page 19: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/19.jpg)
Jan 31, 2005
Program Objectives:
• Conversion of existing High Schools and Middle Schools
• Personalized learning environments of 350-500 students
• Supports Autonomy of Space and Scheduling
![Page 20: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/20.jpg)
Jan 31, 2005
Potential Projects:
• Space conversions– Specialty classrooms (multimedia
production, performing arts) – Decentralized core curriculum
classrooms (science, computer labs)
– Teachers’ meeting/work rooms – Support Staff/Admin. space
• New buildings and additions
![Page 21: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/21.jpg)
Jan 31, 2005
Priority Criteria:
• Planned Instructional Programs• API Score• Program Improvement Status • Calendar • Student Population • Single-Track Capacity• New School Impact on Population • Number of SLCs planned
![Page 22: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/22.jpg)
Jan 31, 2005
Delivery Plan:
• Assessment / Scope Definition (Nov 04 – May 05)
– School conversion requests – Scope review, estimates, and prioritization– Approval by Superintendent– Bond Oversight Committee review– Board of Education approval
• Design / Construction
![Page 23: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/23.jpg)
Jan 31, 2005
In Conclusion…
![Page 24: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/24.jpg)
Jan 31, 2005
What will we accomplish?
• Continuation of Proposition BB & Measure K
• Will not fix everything
• These objective processes will address the most critical needs
• Other Critical Needs will Remain
![Page 25: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/25.jpg)
Jan 31, 2005
Next Steps…
• Identify specific projects• Brief Communities on the Results of the
Process• Identify Costs & Schedules• Incorporate in the Strategic Execution Plan• Bond Oversight Committee review• Board Approval• Design & Construct Projects
![Page 26: Jan 31, 2005 Community Update. Jan 31, 2005 Thanks to the voters… Measure R passed with over 63% of the vote $3.87 billion for “the Safe and Healthy Neighborhood](https://reader035.vdocuments.net/reader035/viewer/2022070409/56649e915503460f94b966da/html5/thumbnails/26.jpg)
Jan 31, 2005
For more information…
- List of new construction projects at: http://www.laschools.org/sep/
- List of existing facilities modernization and repair projects: http://www.laschools.org/efsep/