jane addams memorial tollway (i-90) rebuilding and

9
Jane Addams Memorial Tollway (I-90) Rebuilding and Widening Project Jason Wenberg, P.E., I-90 Corridor Construction Manager Illinois Tollway National Open House – August 20, 2013

Upload: others

Post on 17-Nov-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Jane Addams Memorial Tollway (I-90) Rebuilding and

Jane Addams Memorial Tollway (I-90) Rebuilding and Widening Project

Jason Wenberg, P.E., I-90 Corridor Construction ManagerIllinois Tollway National Open House – August 20, 2013

Page 2: Jane Addams Memorial Tollway (I-90) Rebuilding and

Jane Addams Memorial Tollway (I-90) I-90 West Corridor Overview Reconstruction and widening of a 54-year-old, 37-mile stretch

of I-90 between Elgin and Rockford Existing four lanes / PCC base / HMA overlay Proposed six-lane composite JPC (11.25”- 13”) 19 crossroad bridges

2

Page 3: Jane Addams Memorial Tollway (I-90) Rebuilding and

I-90 West Corridor Overview Schedule: Eastbound – March 2013 through November 2013 Westbound – September 2013 through November 2014 Crossroad Bridges – August 2013 through November 2015

Budget: $800 million

3

Page 4: Jane Addams Memorial Tollway (I-90) Rebuilding and

I-90 West Corridor Overview Green Initiatives 100 percent reuse/recycle of existing pavement section LED lighting Warm-mix asphalt Soil modification Permeable pavement Bioswales Composite concrete

4

Page 5: Jane Addams Memorial Tollway (I-90) Rebuilding and

I-90 Composite Concrete Composite Concrete Cross Section 8.25”- 10” thick lift of ternary concrete mix (black rock)

15 – 50 percent Fractionated Recycled Asphalt Pavement (FRAP)

3” Illinois Department of Transportation standard PV concrete mix

Placement Two belt placers

Two slip-form pavers Two belt placers

One slip-form paver (approved test section)

5

Page 6: Jane Addams Memorial Tollway (I-90) Rebuilding and

I-90 Composite Concrete Composite concrete vs. single-lift concrete Composite concrete is not practical for all applications

Ramps and interchanges Bridge approach and departures Crossover locations Gaps

6

Page 7: Jane Addams Memorial Tollway (I-90) Rebuilding and

I-90 Composite Concrete Composite concrete vs. single-lift concrete Large areas needed for:

Portable plants FRAP operations

7

Page 8: Jane Addams Memorial Tollway (I-90) Rebuilding and

I-90 Composite Concrete Lessons Learned: Coordination/communication

Concrete delivery Paving equipment (speed, delays, breakdowns)

Consistency Air Slump (2” black rock; 1.75” top lift)

Consolidation Slip-form paver with DBI Timing

Cover ternary mix 15 to 45 minutes

8

Page 9: Jane Addams Memorial Tollway (I-90) Rebuilding and

THANK YOU

9