JCB INDIA LTD
Robin Singh Bhinder
40707028
INE-MBA 3rd Year
Projects Undertaken Project 106 (A new backhoe loader designed in India
for India) Introduction of Health Cards/ Health Management
System in JCB Introduction and Implementation of ANDON System
based on supervisory control and data acquisition (SCADA)
Designing and commissioning of a new King Post Carriage assembly line
Kaizens/ Improvements
Project 106
• Preparation of Elementary Process Sequence sheets for every part of the machine
• Preparation of Standard Operation Procedures for every part of the machine
• Fixture/ tackle design, testing and installation• Tool identification and commissioning of the
same
Elementary Process Sheet - EPS
• I was involved with the formulation of the Elementary Process Sheet (EPS) of P-106.
• It states the smallest possible amount of work done during the process• It deals with part numbers, quantities of the parts, TAKT times, method of
operation and the process of production being followed.• It lays down the basic procedure of production. • It also gives details about the tooling required for the process.• Used only for reference at managerial level• The details of EPS are very helpful for formulation of Standard Operation
Process , Work Combination Charts and in time studies.• It is also very useful in dividing the work content between the workers at
a stage
Standard Operation process-• I formulated the Standard Operation Process (SOP) for P-106• Standard Operation Process gives the exact step by step procedure to be
followed by the workers during a procedure/process• It is formed by analyzing the drawings of various assemblies • It gives all the details like part names, numbers, their quantity• It also gives various key points to be followed during the process like use
of proper safety equipments, proper handling and quality issues.• It gives the critical torque values to be used in the process (if any)• It reduces the time required for a new worker to get accustomed to his
work.• The visitors can use this sheet to understand the process without any
enquiry• An example of SOP is shown in the next slide.
Fixture Design, Testing & Installation
• The P106 is a compact machine as compared to the normal 3DX machine . Therefore all the dimensions are different.
• Thus all the fixtures, tackles and trolleys to be used on M Line, Assembly Line and paint shop were to be designed.
• In all a total of 6 Tackles, 3 Sub Assembly Trolleys and 5 component Trolleys and 4 Fixtures were designed
• I was involved in the designing and testing process of all the fixtures, tackles and trolleys.
• This was done with the help of drawings of different components. • The software used was AUTO CAD 2010.
BOOM DIPPER SUB ASSEMBLY FIXTURE
Tooling Analysis• I analyzed the EPS and SOPs made previously to find
out the types and quantity of tools required.• Ergonomic and safety points were also considered
during selection of tools so that human effort is minimized
• State of the art DC tools and Oil Pulse tools were procured where the torque values were critical like Rear Axle to Mainframe mounting, Yoke Plate mounting, Cab Fitment and Tyre mounting.
• In case of bulky tools gravity balancers were employed to reduce the amount of force required to carry/ lift the tool
Health Management System• I was involved in the process of improving the health
of the workers.• The basic aim of this system was to reduce the
complaints regarding high fatigue levels• For this movement of every worker was captured
along with the amount of weight and the amount of bending he has to do using a Health Card and Movement Chart
• Stage wise concerns were then developed and actions taken through Problem Counter Measure approach
Sr. No. Description Permissible Actual
1 Maximum Lifting of Weight 8 Kg.
2 Body Posture while working
Walking
Sitting Nil
Bending < 60 Deg
Stretching
3 Working Temp. 32-35 Deg. C
4 Drinking Water Access Point 25 Mtr
5 Kaizen Cell Point 25 Mtr
Health Card
Movement Chart
Assembly Line - Movement Chart (Feb'10)
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Stages/Operator
Dis
tanc
e (m
m)
Health Card Summary A Line
0
100
200
300
400
500
600
700
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Stages
Sco
re
January
February
March
• The health cards were then analyzed and the stages with high values were tackled first
• For example-
ANDON System
• I was involved in implementing and installing the new ANDON system which unlike the previous system is based on Supervisory Control and Data Acquisition (SCADA)
• That is anyone at any place in the plant can find out about the production status instantly using his workstation or by looking at the display board
• Thus any kind of problem is notified instantly thereby decreasing the time required to rectify the problem
ANDON Work Station
King Post Coupling (KPC)• Since the demand of JCB 3DX model has been
increasing continuously, therefore to meet the demand a new KPC assembly area is required.
• The new assembly area is designed while keeping in mind that the amount of manual lifting required is minimum and that the problems faced in the current system are not present
• Special care has also been given to the fact that the worker does not have to bend in order to reach the tools, parts
• The new system is designed to be safer and is easy to maintain
• To make the system easier to maintain, the cranes are only eight feet above ground level
• The whole conveyor set up is on ground level. Thus the breakdown time is considerably reduced
• The new system is more spacious, thus there is more room for the worker to maneuver in and the various tools to be used can be placed within the reach of the worker
KPC Layout
Kaizens & Improvements
• Improvement is a continuous process in JCB• I was involved in various kaizens implemented
in the company• Some of the Kaizens implemented are-
1. Installation of new axial fans on the shop floor
Advantage- Better air circulation and flow on the shop
floor. Eliminates the problem of low air pressure in
the ducts
Axial Fan
2. Developed new light weight tackle to lift king post
Advantage- Reduces operator’s fatigue level while lifting
the king post