jenny k. harbine aurora r. janke earthjustice bozeman, mt...
TRANSCRIPT
![Page 1: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/1.jpg)
Jenny K. Harbine
Aurora R. Janke
Earthjustice
313 East Main Street
Bozeman, MT 59715
(406) 586-9699 | Phone
(406) 586-9695 | Fax
Counsel for Plaintiffs Vote Solar
and Montana Environmental Information Center
Michael J. Uda
UDA LAW FIRM, PC
7 West 6th Avenue
Power Block West, Suite 4H
Helena, MT 59601
(406) 457-5311 | Phone
(406) 447-4255 | Fax
Counsel for Plaintiff Cypress Creek Renewables, LLC
MONTANA EIGHTH JUDICIAL DISTRICT COURT
CASCADE COUNTY
VOTE SOLAR, MONTANA
ENVIRONMENTAL INFORMATION
CENTER, and CYPRESS CREEK
RENEWABLES, LLC
Plaintiffs,
v.
THE MONTANA DEPARTMENT OF
PUBLIC SERVICE REGULATION,
MONTANA PUBLIC SERVICE
COMMISSION, and NORTHWESTERN
CORPORATION d/b/a NORTHWESTERN
ENERGY,
Defendants.
Case No.
Judge: Hon.
PETITION
FOR JUDICIAL REVIEW
![Page 2: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/2.jpg)
1
INTRODUCTION
1. This case challenges the Montana Public Service Commission’s (the
“Commission”) July 21, 2017 Order and November 24, 2017 Order on Reconsideration that
together drastically and unreasonably slashed the rates that will be paid by NorthWestern Energy
(“NorthWestern”) to small renewable energy developers and reduced the duration of the
contracts for the sale of energy from these small developers to NorthWestern. See Final Order
No. 7500c, In the Matter of NorthWestern Energy’s Application for Interim and Final Approval
of Revised Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No. D2016.5.39 (July 21,
2017) [hereinafter “Initial Order”] (attached as Exhibit 1); Order on Reconsideration No. 7500d,
In the Matter of NorthWestern Energy’s Application for Interim and Final Approval of Revised
Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No. D2016.5.39 (Nov. 24, 2017)
[hereinafter “Order on Reconsideration”] (attached as Exhibit 2).
2. Federal and state law requires the Commission to establish standard rates and
contract lengths for independent energy projects with a generating capacity of three megawatts
or less. In the challenged decision, the Commission slashed standard rates for small solar
development projects by more than half—from approximately $66 per megawatt hour to
approximately $31 per megawatt hour. At the same time, the Commission reduced maximum
contract lengths for the sale of renewable energy to NorthWestern from 25 to 15 years, which
together with the reduced standard rate will severely limit the ability of developers to finance
renewable energy projects.
3. The Commission’s decision is a death knell for small solar development in
Montana at a time when demand for renewable energy is growing, the cost of producing
![Page 3: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/3.jpg)
2
renewable energy is at an all-time low, and NorthWestern has claimed a significant need for
electric capacity that solar and wind developers are well-positioned to supply.
4. Because the Commission’s decision is arbitrary, unreasonable, and unlawful, it
should be set aside.
JURISDICTION AND VENUE
5. This action is brought pursuant to Montana law governing small power
production facilities, Mont. Code Ann. §§ 69-3-601 et seq., and the Montana Administrative
Procedure Act, Mont. Code Ann. §§ 2-4-101 et seq. This Court has jurisdiction over plaintiffs’
claims pursuant to Mont. Code Ann. § 3-5-302(1)(b) (providing state district court jurisdiction
over all civil matters); Mont. Code Ann. § 2-4-702 (providing for judicial review of contested
cases); and Mont. Code Ann. § 69-3-402 (providing for judicial review of Commission
decisions). Because this action is brought pursuant to Mont. Code Ann. § 69-3-402, it “shall
have precedence over any civil cause of a different nature” pending before this court.
6. Plaintiffs exhausted their administrative remedies by seeking reconsideration of
the Commission’s decision consistent with the Commission’s regulations. See Mont. Code Ann.
§ 2-4-702(1)(a) (providing for judicial review of contested cases after exhaustion of available
administrative remedies); Admin. R. Mont. 38.2.4806 (Commission regulation on
reconsideration). The challenged decision is final and subject to district court review. See
Admin. R. Mont. 38.2.4806(6) (“A commission order is final for purposes of appeal upon the
entry of a ruling on a motion for reconsideration ….”).
7. Venue is proper in this District under Mont. Code Ann. § 25-2-126 because the
Commission’s decision will have “operative effect” in Cascade County, where numerous
projects subject to the challenged decision are proposed or sited. See State Consumer Counsel v.
![Page 4: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/4.jpg)
3
Mont. Dep’t of Pub. Serv. Regulation, 181 Mont. 225, 229–30, 593 P.2d 34, 37 (1979) (holding
that the cause of action arose in the county where the Commission’s decision would have its
“operative effect”); see also Mont.-Dakota Utils. Co. v. Pub. Serv. Comm’n of Mont., 111 Mont.
78, 107 P.2d 533, 534 (1940) (“It is not the mere making of the order, but the place where it is
put in operation, that determines where the cause of action arose. Operation of the order is what
is alleged will injure plaintiff.”), overruled on other grounds by Lunt v. Div. of Workmen’s
Comp., Dep’t of Labor & Indus. of State, 167 Mont. 251, 537 P.2d 1080 (1975).
PARTIES
8. Plaintiff Vote Solar is a non-profit grassroots organization working to foster
economic opportunity, promote energy independence, and fight climate change by making solar
a mainstream energy resource across the United States. Founded in 2002, Vote Solar engages at
the state, local, and federal levels to remove regulatory barriers and implement the key policies
needed to expand solar energy generation. Vote Solar has more than 70,000 members
throughout the United States, including members and supporters in NorthWestern’s Montana
service territory. Vote Solar and its members have an interest in promoting clean energy,
including the availability of renewable power for use in Montana, and preventing impairment of
the development and availability of renewable energy across the country.
9. Plaintiff Montana Environmental Information Center (“MEIC”) is a non-profit
environmental advocacy organization founded in 1973 by Montanans concerned with protecting
and restoring Montana’s natural environment. MEIC plays an active role in promoting Montana
clean energy projects and policies, including advocating for the expansion of responsible,
renewable energy and energy efficiency and supporting policies that insulate energy consumers
from fuel price risk. At the state level, MEIC leads the effort to pass policies that help expand
![Page 5: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/5.jpg)
4
clean, affordable, reliable, and efficient energy solutions for Montana. MEIC has approximately
5,000 members and supporters, many of whom are in NorthWestern’s Montana service territory
and seek increased access to affordable renewable energy.
10. Vote Solar, MEIC, their staff, and their members and supporters (collectively
“Vote Solar”) who are residential electric customers in NorthWestern Energy’s service territory
have direct and substantial interests in the challenged decision because the substantially reduced
contract length and significant rate decrease for small solar developers in Montana may impact
their electricity rates and diminish opportunities for expanding their use of clean energy from
wind and solar resources. Vote Solar’s interests are further demonstrated through their
commitment to the development of clean energy resources, particularly solar resources, in the
State of Montana.
11. The legal violations alleged in this complaint cause direct injury to Vote Solar and
its members’ interests in their electricity rates and the expansion of their use of clean energy
because the challenged decision will negatively impact the development of clean energy
resources in the state. Specifically, the contract-length reduction and rate decrease are likely to
affect opportunities for future renewable energy development in Montana and the availability of
renewable power for use by NorthWestern’s Montana customers. These are actual and concrete
injuries to Vote Solar caused by the Commission’s failure to comply with state and federal laws
that would be redressed by the relief requested in this complaint. Vote Solar has exhausted its
administrative remedies and thus has no other adequate remedy at law.
12. Plaintiff Cypress Creek Renewables, LLC (“Cypress Creek”), a Delaware limited
liability company, is a solar energy developer that, through and together with its corporate
affiliates and subsidiaries, develops solar-powered power production facilities across the United
![Page 6: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/6.jpg)
5
States. Cypress Creek has been actively involved in efforts to develop solar energy projects in
Montana for the past several years. Cypress Creek’s development affiliates include more than a
dozen entities each of which seeks (i) to develop a discrete solar facility in Montana that meets
the definition of and has registered with the Federal Energy Regulatory Commission (“FERC”)
as a “qualifying facility” under the federal Public Utilities Regulatory Policies Act (“PURPA”),
and (ii) to sell the electrical output of such facility to NorthWestern, which under PURPA is
obligated to purchase such output at its “avoided costs,” as discussed below.
13. Plaintiff Cypress Creek has a direct and substantial interest in the challenged
decision because the substantially reduced contract length and significant rate decrease ordered
by the Commission impacts the ability of Cypress Creek to finance and develop its planned small
solar energy projects in Montana. As a result, the challenged decision will have a severe adverse
effect on Cypress Creek’s development activities in Montana and, absent judicial relief, will
prevent Cypress Creek from constructing any additional solar projects in the state. Cypress
Creek has exhausted its administrative remedies and thus has no other adequate remedy at law
with respect to the issues raised by this Petition.
14. Consisting of five elected Commissioners from throughout the state, Defendant
Montana Public Service Commission is a state administrative agency that supervises and
regulates aspects of the operations of public utilities, common carriers, railroads, and other
regulated industries. The Commission is responsible for setting avoided cost rates for the
purchase of energy from qualifying facilities by public utilities.
15. Defendant Department of Public Service Regulation is an administrative agency
of the State of Montana created pursuant to Mont. Code Ann. § 2-15-2601. The Commission is
the elected head of the Department.
![Page 7: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/7.jpg)
6
16. Defendant NorthWestern Corporation is a Delaware corporation doing business as
NorthWestern Energy in the State of Montana as the state’s largest public utility. As a public
utility in Montana, NorthWestern is subject to the jurisdiction of the Montana Public Service
Commission. NorthWestern is named as a defendant pursuant to Mont. Code Ann. § 69-3-
402(1) because it is an interested party.
STATUTORY AND REGULATORY BACKGROUND
I. THE PUBLIC UTILITIES REGULATORY POLICIES ACT
17. Montana’s law governing utility purchases of energy from small power
production facilities, Mont. Code Ann. §§ 69-3-601 et seq., implements a federal law known as
PURPA, which is designed to promote independent generation of renewable energy. Whitehall
Wind, LLC v. Montana Pub. Serv. Comm’n, 2015 MT 119, ¶ 2, 379 Mont. 119, 120 347 P.3d
1273, 1274; see also 16 U.S.C. § 824a-3(f) (providing for state implementation of PURPA).
18. Congress enacted PURPA in 1978 in response to a nationwide energy crisis. See
FERC v. Mississippi, 456 U.S. 742, 745, 750 n.12 (1982). In passing PURPA, Congress sought
to reduce American reliance on fossil fuels by encouraging diversification of energy resources.
Id. at 750–51; Indep. Energy Producers Ass’n Inc. v. Cal. Public Utils. Comm’n, 36 F.3d 848,
850 (9th Cir. 1994). To that end, PURPA encourages the development of small power
production facilities by requiring utilities to pay a fair rate to small power production facilities,
including renewable energy facilities such as wind and solar. See FERC v. Mississippi, 456 U.S.
at 745, 750–51; Small Power Production and Cogeneration Facilities; Regulations Implementing
Section 210 of the Public Utility Regulatory Policies Act of 1978, Order No. 69, 45 Fed. Reg.
12,214, 12,215 (Feb. 25, 1980) [hereinafter Order No. 69].
![Page 8: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/8.jpg)
7
19. Prior to the passage of PURPA, small renewable generating facilities faced key
obstacles that inhibited their sale of electricity to utilities. First, the development of small
renewable generating facilities was impaired by the absence of any utility obligation to purchase
electric output from small renewable developers at an appropriate rate. See Order No. 69, 45
Fed. Reg. at 12,215. Second, even when utilities did purchase this electric output, utilities often
engaged in discriminatory pricing that inhibited the development of small renewable generating
facilities. Id. Congress specifically designed PURPA to overcome these obstacles to the
development of small renewable generating facilities. FERC v. Mississippi, 456 U.S. at 750–51;
see also Order No. 69, 45 Fed. Reg. at 12,215 (“Sections 201 and 210 of PURPA are designed to
remove these obstacles.”); see also Whitehall Wind, LLC v. Montana Pub. Serv. Comm’n, 2010
MT 2, ¶ 7, 355 Mont. 15, 16–17, 223 P.3d 907, 908–09 (“PURPA requires large utilities to
purchase energy from smaller qualifying facilities at rates that allow the small facilities to
become and remain viable suppliers of electricity.”).
20. Section 210 of PURPA embodies the statute’s goal of advancing renewable
energy from small power producers by requiring utilities to purchase electric energy from
cogeneration and small power production facilities known as “qualifying facilities” at rates that
are “just and reasonable” to the utility’s customers, are “in the public interest,” and do “not
discriminate” against qualifying facilities. 16 U.S.C. § 824a-3(a), (b). To meet these standards,
rates for purchase of electricity must reflect “the incremental cost to the electric utility of
alternative electric energy,” id. § 824a-3(b), & (d), otherwise known as “avoided costs,” 18
C.F.R. § 292.101(b)(6), Admin. R. Mont. 38.5.1901(2)(a) (defining “avoided costs”). In other
words, utilities must pay a rate for electricity from qualifying facilities that reflects the costs the
utility would otherwise incur to itself develop generation capacity and/or produce or purchase
![Page 9: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/9.jpg)
8
energy. This avoided cost standard is designed to ensure that ratepayers remain “indifferent as to
whether the utility used more traditional sources of power or the newly encouraged alternatives”
under PURPA. S. Cal. Edison, San Diego Gas & Elec., 71 FERC ¶ 61,269, at 62,080, 1995 WL
327268, at *8 (1995).
21. Recognizing that burdensome negotiations between small power producers and
statewide utilities could discourage the development of renewable energy, particularly from
smaller projects, PURPA requires state utility commissions to establish standard offer rates for
purchases from certain qualifying facilities. See 18 C.F.R. §§ 292.204(a), 292.304(c) (requiring
states to set standard rates for qualifying facilities of 100 kilowatts or less and allowing states to
set standard rates for qualifying facilities of up to 80 megawatts in design capacity, which is the
maximum power production capability of a facility); Order No. 69, 45 Fed. Reg. at 12,223
(stating that “the transaction costs” associated with individualized rates for small facilities
“would likely render the program uneconomic”).
22. The Commission’s establishment of standard offer rates for qualifying facilities in
Montana are at issue in the challenged decision. Admin. R. Mont. 38.5.1901(j) (defining
“standard rates”). Under Montana rules, qualifying facilities with a design “capacity not greater
than 3 megawatts [are] … eligible for standard offer rates” that are based on calculation of a
utility’s avoided costs. See id.; id. 38.5.1902(5). Qualifying facilities with maximum production
capability greater than three megawatts are not subject to the challenged decision and must
negotiate avoided cost rates through a contract with the utility or, if negotiation is unsuccessful,
petition the Commission to set the rates and conditions of the contract. Mont. Code Ann. § 69-3-
603; Admin R. Mont. 38.5.1902(5).
![Page 10: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/10.jpg)
9
23. In setting standard offer rates under PURPA, the Commission is required to
“determine the rates and conditions of the contract for the sale of electricity by a [qualifying
facility]” according to certain criteria, including that “[l]ong-term contracts for the purchase of
electricity by the utility from a qualifying small power production facility must be encouraged in
order to enhance the economic feasibility of qualifying small power production facilities.”
Mont. Code Ann. § 69-3-604(2). The Commission must also consider “[t]he terms of any
contract or other legally enforceable obligation, including the duration of the obligation.” 18
C.F.R. § 292.304(e)(2)(iii); see also Admin. R. Mont. 38.5.1901(1) (adopting and incorporating
by reference federal regulations implementing PURPA).
24. Standard offer rates set by the Commission must also account for both the
“aggregate value of energy and capacity from qualifying facilities on the electric utility’s
system” and “the shorter lead times available with additions of capacity from qualifying
facilities.” 18 C.F.R. § 292.304(e)(2)(vi), (vii).
25. Although standard offer rates must accurately reflect the utility’s avoided costs,
they do not require a “minute-by-minute evaluation of costs” to account for inevitable
fluctuations in energy prices. Order No. 69, 45 Fed. Reg. at 12,224. As FERC, the federal
agency tasked with implementing PURPA, has explained, “in the long run, ‘overestimations’ and
‘underestimations’ of avoided costs will balance out” over the course of the long-term contracts
between qualifying facilities and electric utilities. Id. Moreover, allowing for standard rates
over a single long-term contract ensures “that a qualifying facility which has obtained the
certainty of an arrangement is not deprived of the benefits of its commitment as a result of
changed circumstances.” Id.
![Page 11: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/11.jpg)
10
26. In essence, the economic design of PURPA seeks to simulate the outcome of a
free and open market by encouraging development of qualifying facilities that offer generation at
a cost equal to the incremental cost to the utility of building its own generation or procuring
power from other sources. PURPA generation purchased at the avoided cost price is reasonable
for the consumer because it is no more expensive than if the monopoly utility generates power
itself or purchases it from another source.
II. THE COMMISSION’S AVOIDED COST RATEMAKING PROCEDURES
27. This case arises from the Commission’s process for setting standard offer rates for
certain qualifying facilities. Commission rules require a utility to submit bi-annual updates to its
avoided cost information, based on the costs for any planned new resources identified in the
utility’s resource procurement plan, to allow the Commission to establish standard offer rates for
qualifying facilities. Admin. R. Mont. 38.5.1905(1).
28. Before the Commission may approve any change in the avoided cost rate, it must
first publish notice of the proposed change, announce a hearing on the proposed change, and
inform interested persons how to petition the Commission to intervene as parties to the hearing.
Mont. Code Ann. § 69-3-303.
III. COURT REVIEW OF COMMISSION RATEMAKING DECISIONS
29. The Commission’s ratemaking decision may be challenged within 30 days of the
final order in the district court of the proper county. Mont. Code Ann. § 69-3-402(1). If the
Commission’s order is found to be “unlawful or unreasonable” it can be vacated or set aside by
the court. Id.
30. Because the Commission is an administrative agency in the State of Montana, it is
subject to the Montana Administrative Procedure Act (“MAPA”). Under MAPA, the court “may
![Page 12: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/12.jpg)
11
reverse or modify [the Commission’s] decision if substantial rights of the appellant have been
prejudiced” because, among other things, the agency’s decision violates constitutional or
statutory provisions, exceeds its statutory authority, is based on unlawful procedure, is affected
by other error of law, is “clearly erroneous in view of the reliable, probative, and substantial
evidence on the whole record,” or is arbitrary or capricious. Mont. Code Ann. § 2-4-704.
31. Under MAPA, an agency action is arbitrary if the agency fails to consider relevant
factors, including the standards and purposes of the statutes the agency administers. Clark Fork
Coal. v. Mont. Dep’t of Envtl. Quality, 2008 MT 407, ¶ 21, 347 Mont. 197, 202–03, 197 P.3d
482, 487; see also Am. Paper Inst., Inc. v. Am. Elec. Power Serv. Corp., 461 U.S. 402, 413
(1983) (relevant factors include the purposes of PURPA). Moreover, courts should not
“automatically defer to the agency ‘without carefully reviewing the record and satisfying
themselves that the agency has made a reasoned decision.’” Clark Fork Coal., ¶ 21 (quoting
Friends of the Wild Swan v. DNRC, 2000 MT 209, ¶ 28, 301 Mont. 1, 7, 6 P.3d 972, 976–77).
FACTUAL BACKGROUND
I. SOLAR ENERGY DEVELOPMENT IN MONTANA
32. Montana faces an unprecedented opportunity to diversify its energy supply with
clean, solar-generated electricity. Over the past decade, the demand for solar energy in the
United States has sky rocketed. More than 14,700 megawatts of solar energy were installed in
the United States in 2016, nearly doubling the amount installed in 2015. In that same period of
time, the average cost of solar projects has declined dramatically. Utility-scale solar power now
in many cases is as affordable, or more affordable, than conventional, fossil-fueled electric
generating sources.
![Page 13: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/13.jpg)
12
33. Consistent with these trends, Montana was poised to experience substantial
growth in solar development prior to the Commission’s actions in this proceeding. In May 2016,
NorthWestern stated that it had nearly two dozen requests for power-purchase agreements from
developers of small solar energy projects with a capacity of three megawatts or less.
34. Solar energy could contribute tremendous benefits to NorthWestern and its
electricity customers. NorthWestern Energy has reported a shortage of capacity to meet its peak
customer demand, which increasingly occurs in summer months, when solar energy production
is greatest. Additionally, while solar energy is a significant summer-peaking resource, its
production characteristics complement local wind resources, which are most productive in winter
months.
35. Further, solar resources can be built more rapidly and in smaller increments than
larger fossil-fueled resources. Because of these characteristics, solar energy development can
match more closely the utility’s future load growth and capacity needs, with fewer shortages or
surpluses of capacity that can be detrimental to ratepayers. And in the case of NorthWestern,
which has identified immediate capacity needs, solar energy development can more quickly
rectify resource deficiencies that expose its ratepayers to the inherent risk of volatile market
prices for power.
36. Locking in long-term rates for affordable solar energy at current low prices also
provides a significant hedge against market volatility. The cost of natural-gas-fired generation is
heavily dependent on future natural gas prices. Not only are NorthWestern’s customers at risk of
paying high fuel costs for utility-owned fossil-fueled plants if natural gas prices spike, customers
pay the fixed capital costs of such utility-owned resources whether they are producing power or
not, including when those resources are out of service for repairs or because they cannot be
![Page 14: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/14.jpg)
13
operated economically. By contrast, for independently owned solar energy projects selling
electric power to NorthWestern—such as the small solar energy facilities that qualify for
standard offer rates—ratepayers pay only for the power that is actually produced. In addition,
ratepayers bear no risk of paying for construction cost-overruns of qualifying facilities, as they
do with utility-owned projects.
37. Solar energy development also yields significant local economic benefits. The
construction of each additional 100 megawatts of solar energy generation in Montana would
likely result in an investment of hundreds of millions of dollars in the state, including by
generating short-term and permanent employment and local tax revenue.
38. Notwithstanding these benefits of solar energy development and the ability of
renewable electric capacity to meet NorthWestern’s claimed need for new generating resources,
on information and belief, NorthWestern has not made any new commitments to purchase solar
qualifying facility power since the Commission suspended the pre-existing standard rate on June
16, 2016.
II. NORTHWESTERN’S APPLICATION TO REDUCE STANDARD RATES
39. Prior to the challenged decision, the Commission last modified standard rates for
small (three megawatts or less) qualifying facilities in 2012, finding such rates just and
reasonable, in the public interest, and not discriminatory. Order No. 7199d, In the Matter of
NorthWestern’s Application for Approval of Avoided Cost Tariff for New Qualifying Facilities,
Dkt. No. D2012.1.3 (Dec. 7, 2012). Consistent with its prior practice, the Commission
established these standard rates based on a 25-year contract length.
40. In January 2014, NorthWestern unsuccessfully sought to alter the 2012 standard
rates. See Order 7338b, In the Matter of NorthWestern Energy’s Application for Qualifying
![Page 15: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/15.jpg)
14
Facility Tariff Adjustment, Dkt. No. D2014.1.5 (May 4, 2015). After a full contested case
proceeding, the Commission rejected NorthWestern’s requested rate change based on the
utility’s failure to support its avoided-cost assumptions “with a comprehensive, long-term
resource planning analysis,” and its use of a potentially flawed method for calculating avoided
costs. Id. ¶¶ 19–21. Accordingly, the Commission determined it lacked a sufficient basis to
change the standard rates approved in 2012.
41. On May 3, 2016, NorthWestern filed its next bi-annual avoided cost application
with the Commission, proposing drastic reductions in standard offer rates for NorthWestern’s
purchases from solar, wind, and non-wind qualifying facilities. See NorthWestern Energy’s
Application for Interim & Final Approval of Revised Tariff Schedule No. QF-1, In the Matter of
NorthWestern Energy’s Application for Interim and Final Approval of Revised Tariff No. QF-1,
Qualifying Facility Power Purchase, Dkt. No. D2016.5.39 (May 3, 2016) [hereinafter “2016 Rate
Application”]. For solar qualifying facilities, NorthWestern’s 2016 Rate Application proposed a
standard rate that would be as little as roughly half the current rate—reducing it from an average
price of roughly $66 per megawatt hour to between $34 and $44 per megawatt hour. While
proposing dramatically reduced payments for solar electricity, NorthWestern’s application
maintained the 25-year maximum contract duration previously implemented by the Commission.
This 2016 Rate Application initiated the proceeding underlying the challenged decision.
42. Vote Solar and Cypress Creek intervened in the proceeding on or before the June
10, 2016 intervention deadline set by the Commission. The Montana Consumer Council and
New Colony Wind, LLC also intervened in the proceeding.
![Page 16: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/16.jpg)
15
43. As parties to the proceeding, Vote Solar and Cypress Creek engaged in discovery,
submitted expert testimony, participated in the hearing held by the Commission, and submitted
post-hearing briefing.
44. Vote Solar’s expert, Tom Beach, submitted testimony justifying an avoided cost
rate for solar qualifying facilities of between $60 and $73 per megawatt hour. This calculation
reflected the Commission’s historical practice of compensating non-carbon emitting facilities for
avoided costs associated with projected future regulation of such carbon emissions. Mr. Beach’s
calculation also relied on widely accepted methodologies for compensating solar energy
resources for their contribution to a utility system’s overall capacity to meet peak demands, in
this case, a value that reflected robust solar energy production during many of the hours in which
NorthWestern’s customer demand is high (NorthWestern’s “on-peak period”). Mr. Beach’s
calculations were based on a 25-year contract length, consistent with the existing standard offer
contract terms and NorthWestern’s 2016 Rate Application. In his testimony, Mr. Beach noted
that NorthWestern currently has a significant need for generation resources because it has a
substantial capacity deficit. As Mr. Beach explained, “[b]y any standard measure of resource
adequacy in the utility industry, NorthWestern needs to add generation capacity in order to
provide adequate resources to meet its customers’ long-term needs.” Pre-filed Direct Testimony
of R. Thomas Beach on Behalf of Vote Solar and MEIC, at 8, In the Matter of NorthWestern
Energy’s Application for Interim and Final Approval of Revised Tariff No. QF-1, Qualifying
Facility Power Purchase, Dkt. No. D2016.5.39 (Oct. 14, 2016).
45. Cypress Creek’s expert, Roger Schiffman, submitted testimony highlighting a
number of deficiencies in NorthWestern’s avoided cost methodology, including its lack of
transparency, its undervaluing of avoidable resource costs in certain situations, and its energy-
![Page 17: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/17.jpg)
16
price forecasting approach. Mr. Schiffman further testified that NorthWestern’s proposed
payments for capacity “substantially understat[ed] this value for solar resources.” Pre-filed
Direct Testimony of Roger Schiffman on Behalf of FLS Energy and Cypress Creek Renewables,
at 19, In the Matter of NorthWestern Energy’s Application for Interim and Final Approval of
Revised Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No. D2016.5.39 (Oct. 14,
2016).
46. On October 26, 2017, more than five months after NorthWestern filed its
application and over four months after the deadline to intervene, the Commission requested
additional issue testimony on two topics: (1) maximum contract length and (2) performance
standards for qualifying facilities. With respect to maximum contract length, the Commission
requested testimony on the following questions:
a. Does the current 25-year maximum contract length in
Schedule QF-1 impose undue forecast risk on customers? If
so, why?
b. Would a maximum contract length shorter than 25 years be
reasonable? If so, what would be a reasonable alternative
maximum contract length and why?
c. Would it be reasonable to limit the time period in a long-
term contract during which fixed rates are paid, with
market index-based payments thereafter? If so, why or why
not?
d. What maximum contract lengths are available in other
states?
Notice of Additional Issues, In the Matter of NorthWestern Energy’s Application for Interim and
Final Approval of Revised Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No.
D2016.5.39 (Oct. 26, 2016).
47. The Commission’s request did not solicit input from nonparties or provide notice
of any new opportunity to allow stakeholders interested in this new issue to intervene.
![Page 18: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/18.jpg)
17
48. In response to the Commission’s Notice of Additional Issues, Vote Solar
submitted testimony from Tom Beach stating that the Commission should maintain its 25-year
term for contracts. As Mr. Beach explained, other states recently addressed this issue and chose
to maintain the availability of long-term contracts for small qualifying facilities to avoid chilling
renewable energy development. Mr. Beach testified that long-term contracts are essential to
allow qualifying facilities to obtain necessary financing for their projects. Moreover, as Mr.
Beach explained, long-term contracts do not present an additional risk to ratepayers and, in fact,
may shield ratepayers by hedging against future volatility in fossil fuel prices.
49. Cypress Creek also submitted additional issue testimony on the importance of
adequate contract lengths for purposes of securing project financing. Specifically, Cypress
Creek witness Patrick McConnell explained that institutional lenders are generally unwilling to
take the pricing risk of financing a project beyond the term of a fixed-price contract. Because the
entire costs of the project must generally be paid during the term of the contract, projects with
shorter contracts do not make economic sense.
50. The Commission held a two-day hearing in January 2017. Following the hearing
all parties submitted post-hearing briefs.
51. On June 22, 2017, the Commission held a work session on NorthWestern’s 2016
Rate Application. At that work session, the Commission voted to adopt a 10-year maximum
contract length for qualifying facilities, with a mandatory rate adjustment after five years. In an
effort to comply with PURPA’s prohibition on discriminatory treatment of qualifying facilities,
the Commission voted to apply similar restrictions on contract lengths or cost-recovery periods
for new resources acquired by NorthWestern. The Commission also voted to adopt standard
![Page 19: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/19.jpg)
18
rates for qualifying facilities that were even lower than those proposed by NorthWestern and that
reduced previous rates by more than half.
52. During a break in the work session, a member of the Commission staff was
recorded saying that the Commission’s contract-length decision is “going to probably kill
[qualifying facility] development entirely.” In response, Commissioner Lake agreed, “actually,
the ten year might do it if the price doesn’t. And honestly at this low price, I can’t imagine
anyone gonna get into it. … [J]ust dropping the rate that much probably took care of the whole
thing.” Commissioner Lake, at 6:10, Commission Work Session 1358, In the Matter of
NorthWestern Energy’s Application for Interim and Final Approval of Revised Tariff No. QF-1,
Qualifying Facility Power Purchase, Dkt. No. D2016.5.39 (June 22, 2017). On July 21, 2017,
the Commission issued Final Order 7500c adopting the decision it made at its June 22, 2017
work session.
53. Vote Solar filed a motion for reconsideration on July 31, 2017, arguing that
reconsideration was warranted because, among other things, the Commission unlawfully and
unreasonably (1) adopted a 10-year contract length based on an insufficient record to
demonstrate that such a contract term was sufficient to encourage the development of qualifying
facilities; (2) adopted a shortened contract term without proper notice to interested parties; (3)
adopted avoided cost rates that failed to compensate qualifying facilities for avoided carbon
costs; (4) significantly undervalued total avoided costs based on the unreasonable assumption
that NorthWestern does not require new generating resources until 2025; (5) significantly
undervalued the contribution of solar resources to meeting NorthWestern’s capacity needs; and
(6) failed to account for shortened contract lengths in calculating avoided costs.
![Page 20: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/20.jpg)
19
54. Cypress Creek also filed a motion for reconsideration adopting Vote Solar’s
arguments and providing additional arguments against the drastic reduction in contract length.
Among other things, Cypress Creek observed “that shortening [the qualifying facility] contract
duration to ten years will deprive [qualifying facilities] of reasonable opportunities to attract
capital, will compromise the economic feasibility of [qualifying facilities] in Montana, and will
discourage [qualifying facilities] from entering into long-term contracts,” in violation of PURPA
and Montana law. Joint Mot. of FLS Energy, Inc. and Cypress Creek Renewables, LLC for
Reconsideration of Order 7500c, at 8, In the Matter of NorthWestern Energy’s Application for
Interim and Final Approval of Revised Tariff No. QF-1, Qualifying Facility Power Purchase,
Dkt. No. D2016.5.39 (July 31, 2017).
55. NorthWestern also filed a motion for reconsideration of the Commission’s
application of the 10-year term to NorthWestern’s cost-recovery for its resource acquisitions.
III. PRE-DECISIONAL STATEMENTS BY COMMISSIONERS
56. Although the Commission did not formally make a final decision in this docket
until its November 24, 2017 Order on Reconsideration, throughout the proceeding, individual
commissioners foreshadowed the outcome through numerous editorials in the press about key
issues and parties to the proceeding.
57. At the very outset of the proceeding, before all parties had submitted testimony,
Commission Chair Johnson authored an August 4, 2016 guest opinion in the Billings Gazette
that stated that “[s]ome corporate solar developers operating in Montana … appear[] content
with throwing ratepayers under the bus to boost their own profits” and characterized solar
advocates as “environmental activists.” Brad Johnson, Opinion, Montana PSC Sides with
Consumers on Solar Pricing, Billings Gazette, Aug. 4, 2016, http://billingsgazette.com/
![Page 21: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/21.jpg)
20
news/opinion/guest/guest-opinion-montana-psc-sides-with-consumers-on-solar-
pricing/article_907808ae-f5eb-5ba6-9501-a92eef5e4bb5.html (attached as Exhibit 3).
58. Later, Commissioner Koopman wrote a July 2017 guest opinion in the Billings
Gazette, Missoulian, and Great Falls Tribune stating that one party to the case, the Montana
Consumer Counsel, “has been arguing for years that long-term (up to 25 year) fixed-rate
contracts are unworkable, and place consumers at great risk. The commission has agreed in
principle, but hadn’t yet found a good solution” before issuing its initial decision in the
proceeding. Roger Koopman, Guest Column, Ratepayers Have Constant, Effective Advocate in
Montana Consumer Counsel, Missoulian, July 7, 2017, http://missoulian.com/opinion/columnists
/ratepayers-have-constant-effective-advocate-in-montana-consumer-counsel/article_ff2e1e17-
14ab-565e-8d96-b7966c933ab7.html (attached as Exhibit 4).
59. Shortly after the Commission issued its initial decision, Commissioner O’Donnell
authored a guest opinion in the Great Falls Tribune, the Montana Standard, Helena Independent
Record, Missoulian, and the Billings Gazette touting the Commission’s decision to drastically
reduce contract rates, which was still subject to reconsideration, stating that there is “no truth
whatsoever” to the claim that the Commission’s decision to drastically reduce contract length
would “‘kill’ wind and solar development in the state.” Tony O’Donnell, Opinion, Montana’s
Clean Energy Future Should Not Be Financed on the Backs of Ratepayers, Great Falls Tribune,
July 27, 2017, http://www.greatfallstribune.com/story/opinion/2017/07/27/montanas-clean-
energy-future-should-not-financed-backs-ratepayers/517727001/ (attached as Exhibit 5).
60. Further, while motions for reconsideration were pending before the Commission,
Commissioner Koopman authored a guest opinion published in the Bozeman Daily Chronicle
and the Helena Independent Record stating his belief that if renewable contracts of less than 25
![Page 22: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/22.jpg)
21
years “cannot attract financing” it “would only be because these projects are too risky in the first
place ….” Roger Koopman, Guest Column, Do We Really Want Solar Energy at Any Cost?,
Bozeman Daily Chronicle, August 2, 2017, https://www.bozemandailychronicle.com
/opinions/guest_columnists/do-we-really-want-solar-energy-at-any-cost/article_4a50b00e-e4e0-
504d-887f-e8e250b21e41.html (attached as Exhibit 6). Commissioner Koopman also praised an
earlier Commission decision in this proceeding that suspended standard rates for certain
qualifying facilities at a time when “[o]ut-of-state developers were perched at Montana’s
borders, ready to rush in and take advantage of these inflated rates, reaping windfall profits at
consumers’ expense.” Id.
61. These public statements on the merits of and parties to the proceeding pending
before the Commission demonstrate the apparent pre-judgment of critical issues by individual
commissioners before the parties had completed their presentation of evidence and argument. As
described below, the evidence did not support the Commission’s pre-determined outcome.
IV. THE CHALLENGED DECISION
62. On October 5, 2017, the Commission held a public work session on the motions
for reconsideration, and, on November 24, 2017 the Commission issued its Order on
Reconsideration. Despite Vote Solar and Cypress Creek’s arguments, the Commission retained
its decision to reduce the maximum contract length from 25 years, though it did increase the
maximum term established in its Initial Order only from ten to 15 years. The Commission did
not alter its initial decision to set an avoided cost rate that significantly undervalues both the total
costs avoided by solar energy and the capacity contribution value of solar.
![Page 23: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/23.jpg)
22
A. The Commission’s Decision on Contract Length
63. While reducing maximum contract lengths for the purchase of electricity from
qualifying facilities to 15 years, the Commission did not satisfy its obligation to ensure that such
contracts were sufficiently “long-term” to “enhance the economic feasibility” of qualifying
facilities as required by state law, Mont. Code Ann. § 69-3-604(2), or make any findings
regarding the combined impact of the Commission’s decisions to dramatically reduce the
standard rate for qualifying facility power and shorten contract lengths. Indeed, the Commission
did not solicit testimony on either of these issues.
64. As a state agency, the Commission must support its decisions with substantial
record evidence. See Mont. Code Ann. § 2-4-704(2)(a)(v). However, during the Commission’s
October 5, 2017 work session, three of the five Commissioners acknowledged that the
evidentiary record on this point was “weak.” Commissioner Koopman, at 1:00:52, Commission
Work Session 1131, In the Matter of NorthWestern Energy’s Application for Interim and Final
Approval of Revised Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No. D2016.5.39
(Oct. 5, 2017); see also id., Commissioner Kavulla, at 1:09:24 (relaying concern from
Commissioner O’Donnell that “the evidentiary record in this proceeding on contract length was
frustrating to him”); id., Commissioner Kavulla, at 1:09:41 (“[D]espite of noticing it [contract
length] as an additional issue and trying to engage in a real investigation of this, I don’t think,
frankly, but for a couple of, a bit of, testimony from parties and other jurisdictions findings on
this, I don’t think actually there’s much of an evidentiary record.”). As the Commission
acknowledged in its Order on Reconsideration, neither NorthWestern nor the Montana Consumer
Counsel (“MCC”) offered testimony regarding the impact of shortened contracts on the ability of
qualifying facilities to obtain financing.
![Page 24: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/24.jpg)
23
65. In responding to arguments that the Commission should refrain from changing
qualifying facility contract lengths in light of this record, Commissioner Koopman stated:
The argument that there was no proof given that it wouldn’t affect
financing is a weak argument. There was not good evidence either
way. I wish, you know, I wish that there was more evidence on the
record… And so the Commission unfortunately has a weak
evidentiary record to go with in this area. … Sure it [a 10-year
contract length] may affect financing. It may affect the, you know,
the interest rate. It may not. We don’t know.
Commissioner Koopman, at 1:00:20, Commission Work Session 1131, In the Matter of
NorthWestern Energy’s Application for Interim and Final Approval of Revised Tariff No. QF-1,
Qualifying Facility Power Purchase, Dkt. No. D2016.5.39 (Oct. 5, 2017).
66. The viability of any particular contract length for purchases from a qualifying
facility depends on the price at which the output of the facility will be purchased under the
contract. Where the purchase price is lower, decreasing annual revenues, developers need longer
contract lengths to obtain financing for energy development projects. The Commission totally
failed to consider this relationship between contract length and contract price.
67. Despite the absence of evidence showing that 15-year contracts under the present
rate would be sufficient for projects to secure financing, the Commission concluded that “record
evidence supports setting a 15-year maximum contract length.” Order on Reconsideration ¶ 30.
B. The Commission’s Decision on Avoided Cost Rates
68. In addition to its decision to reduce maximum contract lengths for purchases of
electric power from qualifying facilities, the Commission cut by more than half the standard
offer rate for such purchases. Among other things, the rate established by the Commission: (1)
eliminated compensation to qualifying facilities for avoided carbon costs; (2) failed to
compensate qualifying facilities for total avoided costs in years before 2025; and (3) failed to
![Page 25: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/25.jpg)
24
consider the impact of its reduction of NorthWestern’s cost-recovery period to 15 years on
NorthWestern’s avoided energy and capacity costs.
69. First, the Commission ignored the recommendation of its own staff to maintain a
carbon cost adjustment to the standard rate and unreasonably reversed its long-standing practice
of compensating non-carbon emitting, renewable energy facilities for avoided regulatory costs
associated with carbon emissions. As Vote Solar observed, the Commission previously required
NorthWestern’s customers to pay the utility a premium of $21/metric ton of carbon emissions
avoided through its acquisition of hydroelectric resources. Since then, the Commission required
compensation to numerous renewable energy developers for avoided carbon emissions,
recognizing that non-carbon emitting resources help to insulate NorthWestern’s customers from
the projected costs of future carbon regulation.
70. The Commission’s about-face decision to omit compensation for avoided carbon
costs was based on its “assessment that the political forces that once indicated environmental
regulatory action at the federal level was likely in the reasonably foreseeable future has
diminished [after the 2016 Presidential election] and, accordingly, the likelihood of carbon
emissions regulation has decreased.” Initial Order ¶ 77. However, the Commission’s prior
actions undermined this rationale. Specifically, prior to the challenged decision, the Commission
had already considered changes in the political landscape after the 2016 Presidential election
affecting potential carbon regulation and nonetheless determined that compensation to a non-
carbon emitting qualifying facility (Crazy Mountain Wind) was appropriate. The Commission
did not identify any record evidence to justify its changed position in the challenged decision or
otherwise demonstrate that carbon costs will not exist during the standard rate contract period.
![Page 26: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/26.jpg)
25
The Commission also disregarded evidence of regulatory risk associated with carbon emissions
that is independent of national “political forces.” Id.
71. Second, the Commission underestimated NorthWestern’s total avoided costs by
basing its estimate on a combination of the costs of NorthWestern’s planned construction of a
combined cycle combustion turbine in 2025, and the lower projected costs of market purchases
in the years before 2025. Although avoided costs may properly be based on market prices for
electricity when a utility does not have any need for new generating resources, that is not the
case here. NorthWestern’s resource procurement plan identified an immediate need for new
generating resources because it currently lacks sufficient capacity to meet customer demand.
Accordingly, NorthWestern plans to add new resource capacity in 2018, well before its planned
construction of a combined cycle combustion turbine in 2025. By basing NorthWestern’s
avoided costs on market prices before 2025, the Commission underestimated costs that solar
qualifying facilities could displace as soon as 2018. Indeed, “the shorter lead times available
with additions of capacity from [solar] qualifying facilities” (as opposed to the more extended
schedule to plan, permit, and construct a combined cycle combustion turbine) make solar energy
resources particularly valuable to help meet NorthWestern’s immediate resource needs. 18
C.F.R. § 292.304(e)(2)(vii) (identifying “shorter lead times” as a factor the Commission must
consider in determining avoided costs). The Commission’s calculation of total avoided costs
overlooked these factors.
72. Third, the Commission’s calculation of total avoided costs did not account for the
Commission’s contemporaneous decision to limit NorthWestern’s cost-recovery term for its own
resources to 15 years. In calculating avoided costs, the Commission relied on the costs of
NorthWestern’s planned construction and operation of a combined cycle combustion turbine
![Page 27: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/27.jpg)
26
spread out over 25 years. When the Commission decided to limit NorthWestern’s cost-recovery
term to 15 years, the Commission did not reevaluate avoided costs based on the much higher
annual cost for a combined cycle combustion turbine when the total cost is spread over a shorter
term. Nor did the Commission consider whether the shorter recovery term may affect whether
NorthWestern would identify a resource other than a combined cycle combustion turbine as the
most-economical resource on which the avoided cost rate should be based. As Commission staff
observed, “[t]he planned resources that form the basis for the avoided costs and rates approved in
[the Commission’s Order] may not be preferred resources” given the Commission’s decision to
limit NorthWestern’s cost recovery to a 15-year term. Mike Dalton et al., Memorandum re
Motions for Reconsideration, at 25, In the Matter of NorthWestern Energy’s Application for
Interim and Final Approval of Revised Tariff No. QF-1, Qualifying Facility Power Purchase,
Dkt. No. D2016.5.39 (Oct. 2, 2017). Without information about NorthWestern’s resource
portfolio under the newly adopted cost-recovery term for utility-owned resources, “it is not
possible to confirm that the approved [standard] rates are reflective of NorthWestern’s avoided
costs under [the symmetry] finding and, therefore, whether those rates are just and reasonable to
NorthWestern’s customers.” Id. In other words, Commission staff expressed concern that the
Commission lacked evidence to confirm that the standard rates approved in the challenged
decision accurately reflect NorthWestern’s avoided costs under the utility’s shorter cost-recovery
term. The Commission’s Order on Reconsideration did not acknowledge or respond to concerns
raised by Plaintiffs and the Commission’s staff about the accuracy of the Commission’s avoided-
cost calculation.
![Page 28: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/28.jpg)
27
C. The Commission’s Decision on the Contribution of Solar Energy Resources
to NorthWestern’s System Capacity
73. The Commission’s decision also failed to fully compensate solar qualifying
facilities for their contribution to NorthWestern’s system capacity to meet its customer demand.
74. Under PURPA and Montana law, the Commission must set avoided cost rates that
fairly compensate qualifying facilities for both energy and capacity costs that the qualifying
facility allows the purchasing utility to avoid. 18 C.F.R. § 292.304(a), (b), (e); Admin. R. Mont.
38.5.1901(1). “Capacity costs are the costs associated with providing the capability to deliver
energy; they consist primarily of the capital costs of facilities.” Order No. 69, 45 Fed. Reg. at
12,216. Once a qualifying facility’s contribution to a utility’s capacity needs is calculated, the
facility receives capacity payments based on that value for its output during the utility’s period of
peak demand, or “on-peak” hours. NorthWestern’s 2016 Rate Application identified the utility’s
“on-peak” hours as high-demand hours in January, February, July, August, and December.
75. In the challenged decision, the Commission assumed that solar qualifying
facilities will contribute just 6.1% of their capacity to NorthWestern’s overall capacity needs, in
stark contrast with solar capacity values ranging from 28% to 51% for other utilities in the
region. In rejecting these much higher solar capacity values, the Commission distinguished them
as applying to utilities with summer-peaking capacity demands as opposed to NorthWestern’s
winter-peaking capacity demands. However, the Commission conceded that peak demand on
NorthWestern’s system occurred during the summer in nearly half of the years it evaluated.
Further, the Commission acknowledged that record evidence demonstrated that demand for
electricity throughout the region—which the Commission identified as more relevant in
ascertaining the capacity value of new resources than demand solely on NorthWestern’s
system—is projected in future years to occur primarily in the summer. Nevertheless, the
![Page 29: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/29.jpg)
28
Commission did not attempt to reconcile NorthWestern’s projected summer needs with the
Commission’s conclusion that NorthWestern is exclusively a winter-peaking utility.
76. Further, the Commission calculated solar capacity contribution based on only a
narrow subset of NorthWestern’s on-peak hours, thereby disregarding solar resources’ capacity
contribution in the vast majority of hours during NorthWestern’s “on-peak” period.
77. The Commission’s decision was additionally flawed because it failed to account
for the “aggregate value of energy and capacity from qualifying facilities on the electric utility’s
system,” 18 C.F.R. § 292.304(e)(2)(vi)—in particular, the significant synergies of winter-
peaking wind resources and summer-peaking solar resources. The Commission dismissed
evidence of the complementary production characteristics of these two resource types, claiming
that data were not available to allow the Commission to calculate their aggregate contribution.
But the Commission was not required to quantify the aggregate value of wind and solar
resources; it was simply required to account for the combined benefit of such resources “to the
extent practicable.” Id. at § 292.304(e). The Commission failed to do so by isolating its
analyses of wind and solar resources and assigning capacity value only for a very small number
of peak-load hours predominantly in the winter, thereby under-compensating each resource type
even while NorthWestern reaps the combined capacity benefits of the two.
78. The Commission’s methodology is irreconcilable with NorthWestern’s stated
capacity needs, particularly as NorthWestern’s highest load hours increasingly occur in the
summer and not the winter months. NorthWestern’s current resource portfolio is inadequate to
meet NorthWestern’s peak summer demand in every year since 2011, let alone future, higher
forecasts of summer loads. Yet, the Commission’s methodology fails to recognize the valuable
contribution of solar qualifying facilities to meet NorthWestern’s growing summer demand.
![Page 30: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/30.jpg)
29
79. For these reasons, the Commission unreasonably and arbitrarily undervalued the
significant contribution that solar qualifying facilities resources make to NorthWestern’s system.
FIRST CAUSE OF ACTION
Arbitrary, Unreasonable, and Unlawful Reduction in Contract Length
(Mont. Code Ann. § 69-3-604(2), § 69-3-402, § 2-4-704)
80. Plaintiffs hereby reallege and reincorporate Paragraphs 1 through 79.
81. Montana law requires the Commission to establish “long term” contract rates that
are sufficient to “enhance the economic feasibility” of qualifying facilities. Mont. Code Ann.
§ 69-3-604(2).
82. The Commission’s decision unreasonably reduced the maximum duration of
standard-offer contracts from 25 years to just 15 years. In so doing, the Commissioners failed to
determine based on record evidence that 15-year contracts are sufficient to “enhance the
economic feasibility” of qualifying facilities as required by Montana law, Mont. Code Ann. § 69-
3-604(2), and failed to evaluate whether longer contracts were necessary in light of the
Commission’s contemporaneous decision to reduce by more than half the standard rate available
for purchases of electric power from qualifying facilities. The record evidence would not
support any finding that 15-year contracts satisfy the requirements of Mont. Code Ann. § 69-3-
604(2), particularly in light of the combined impact of dramatically reduced standard rates.
83. By adopting a shortened contract length based on insufficient evidence to ensure
that the shortened contract length would “enhance the economic feasibility” of qualifying
facilities, id.; 16 U.S.C. § 824a-3(a), the Commission violated the requirement that its decisions
be reasonable and lawful. See id. §§ 2-4-704, 69-3-402.
![Page 31: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/31.jpg)
30
SECOND CAUSE OF ACTION
Arbitrary, Unreasonable, and Unlawful Avoided Cost Rates
(Mont. Code Ann. § 69-3-402, § 2-4-704; Admin R. Mont. 38.5.1901(1); 16 U.S.C.
§ 824a-3; 18 C.F.R. § 292.304(a), (b), (e))
84. Plaintiffs hereby reallege and reincorporate Paragraphs 1 through 83.
85. Under PURPA and Montana law, the Commission must set avoided cost rates that
fairly compensate qualifying facilities for both energy and capacity costs that the qualifying
facility allows the purchasing utility to avoid. 18 C.F.R. § 292.304(a), (b), (e); Admin. R. Mont.
38.5.1901(1).
86. These rates must be “just and reasonable to the electric consumers of the electric
utility and in the public interest” and “shall not discriminate” against qualifying small power
producers. 16 U.S.C. § 824a-3(b); 18 C.F.R. § 292.304(a); Admin. R. Mont. 38.5.1901(1).
87. The Commission’s determination of avoided costs in its Initial Order and its
Order on Reconsideration were unlawful and unreasonable because (1) the Commission
arbitrarily and unlawfully eliminated compensation for qualifying facilities for avoided carbon
costs; (2) the Commission failed to fully compensate qualifying facilities for total avoided costs
in years before 2025; and (3) the Commission arbitrarily failed to consider the impact of its cost-
recovery constraints for NorthWestern’s future resource acquisitions on avoided costs.
88. The Commission acted arbitrarily in setting avoided costs by failing to consider
all relevant factors, see Clark Fork Coal., ¶ 21, and failing to provide a reasoned analysis to
justify its departure from its prior precedent, see Waste Mgmt. Partners of Bozeman, Ltd. v.
Montana Dep’t of Pub. Serv. Regulation, 284 Mont. 245, 257, 944 P.2d 210, 217 (1997).
89. Accordingly, the Commission’s decision was arbitrary, unreasonable, and
unlawful in violation of Montana law. See Mont. Code Ann. §§ 2-4-704, 69-3-402.
![Page 32: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/32.jpg)
31
THIRD CAUSE OF ACTION
Failure to Compensate Solar Qualifying Facilities for Full Capacity Contribution
(Mont. Code Ann. § 69-3-402, § 2-4-704; Admin R. Mont. 38.5.1901(1); 18 C.F.R.
§ 292.304(b), (e))
90. Plaintiffs hereby reallege and reincorporate Paragraphs 1 through 89.
91. Under PURPA, the Commission must set avoided cost rates that fairly
compensate qualifying facilities for both energy and capacity costs that the qualifying facility
allows the purchasing utility to avoid. 18 C.F.R. § 292.304(a), (b), (e); Admin. R. Mont.
38.5.1901(1).
92. The Commission’s decision unreasonably adopted a 6.1% capacity contribution
value for solar resources that fails to fully compensate solar qualifying facilities for their capacity
contribution to NorthWestern’s system. Specifically, the Commission ignored NorthWestern’s
need for capacity resources during summer months when solar energy production is greatest.
The Commission’s methodology of calculating the capacity value of solar resources based on
demand in a narrow set of hours primarily in the winter is irreconcilable with NorthWestern’s
immediate, year-round capacity needs. The Commission’s methodology further failed to account
for the aggregate value to NorthWestern of wind and solar resources.
93. Accordingly, the Commission’s calculation of solar qualifying facility capacity
contribution was arbitrary, unreasonable, and in violation of Montana law. See Mont. Code Ann.
§§ 2-4-704, 69-3-402.
![Page 33: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/33.jpg)
32
PRAYER FOR RELIEF
THEREFORE, plaintiffs respectfully request that the Court:
1. Declare that the Commission’s decision was arbitrary, unlawful, and
unreasonable;
2. Set aside the challenged aspects of the Commission’s decision;
3. Direct the Commission to immediately reinstate 25-year contract lengths for small
qualifying facilities as established in Order No. 7199d, In the Matter of NorthWestern’s
Application for Approval of Avoided Cost Tariff for New Qualifying Facilities, Dkt. No.
D2012.1.3 (Dec. 7, 2012);
4. Direct the Commission to immediately establish standard offer rates for small
qualifying facilities that: (1) compensate qualifying facilities for avoided carbon costs; (2)
compensate qualifying facilities for total avoided costs based on the costs of resource additions
in 2018; and (3) account for the impact of a 15-year contract or cost-recovery term for
NorthWestern’s future resource acquisitions;
5. Direct the Commission to immediately establish capacity payments to small solar
qualifying facilities that compensate such facilities for their production throughout
NorthWestern’s on-peak period;
6. Enjoin the Commission from adopting future rates or contract lengths inconsistent
with this Court’s order;
7. Award plaintiffs their reasonable fees, costs, and expenses, including attorneys’
fees, associated with this litigation; and
8. Grant plaintiffs such additional relief as the Court may deem just and proper.
![Page 34: Jenny K. Harbine Aurora R. Janke Earthjustice Bozeman, MT ...meic.org/wp-content/uploads/2017/12/Montana-Solar... · Tariff No. QF-1, Qualifying Facility Power Purchase, Dkt. No](https://reader033.vdocuments.net/reader033/viewer/2022060215/5f05d68c7e708231d414f637/html5/thumbnails/34.jpg)