joint research activity 1 2nd generation adaptive optics ... · final design review may, 2007 phase...
TRANSCRIPT
![Page 1: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/1.jpg)
1st1st--2nd April ’04 GENT2nd April ’04 GENT OPTICONOPTICON--JRA1 KO N. JRA1 KO N. HubinHubin
Joint Research Activity 1Joint Research Activity 122ndnd generation Adaptive Optics for 8generation Adaptive Optics for 8--10 m 10 m
telescopestelescopes
N. N. HubinHubinEuropean Southern ObservatoryEuropean Southern Observatory
![Page 2: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/2.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 2Page 2
JRA1 CharterJRA1 Charter
DESIGN THE NEXT GENERATION OF ADAPTIVE DESIGN THE NEXT GENERATION OF ADAPTIVE OPTICS SYSTEMS FOR THE CURRENT OPTICS SYSTEMS FOR THE CURRENT EUROPEAN TELESCOPE FACILITIESEUROPEAN TELESCOPE FACILITIES
DEVELOP THE KEY TECHNOLOGY ENABLING DEVELOP THE KEY TECHNOLOGY ENABLING THE CONSTRUCTION OF THESE SYSTEMSTHE CONSTRUCTION OF THESE SYSTEMS
![Page 3: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/3.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 3Page 3
Future AO needs in the European Future AO needs in the European CommunityCommunity
AOAO--MCAO and XAO at the LBTMCAO and XAO at the LBT
AO and MCAO at the GTCAO and MCAO at the GTC
XAO with highXAO with high--contrast NIR instrumentcontrast NIR instrument VLT Planet FinderVLT Planet Finder
Low background XAO in MIRLow background XAO in MIR VISIR with VLT Adaptive M2VISIR with VLT Adaptive M2
Seeing reducer (6Seeing reducer (6--8’ FOV 8’ FOV –– NIR)NIR) HAWKHAWK--I with VLT Adaptive M2I with VLT Adaptive M2
Seeing reducer (1’ FOVSeeing reducer (1’ FOV––VisibleVisible--high SC)high SC) MUSE GLAO + multiMUSE GLAO + multi--laserslasers
Seeing reducer multiSeeing reducer multi--buttons (30’ patrol buttons (30’ patrol -- II--band)band) FALCONFALCON
“Significant” Strehl “Significant” Strehl --Sr(visSr(vis)=10%))=10%)-- in 5”in 5” MUSE GLAO + multiMUSE GLAO + multi--laserslasers
Large FOV medium Large FOV medium Sr(KSr(K)=60% )=60% MCAO Imager a la GeminiMCAO Imager a la Gemini
![Page 4: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/4.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 4Page 4
R&D for 2R&D for 2ndnd generation AOgeneration AOXAO GLAO MCAO
concept definitionPiezo DMPiezo DM41412 2 act.act.
JRA 2
QE: 90%
25625622 pixelspixels
0.5 -1.5 kfps
3-1e RON
WFS CCD
RTC Platform controlRTC Platform controlMCAO optimal controlMCAO optimal control
Front-EndAcquisition
CPU
CPU
CPU CPU
CCD Controller
192x192 active area
CPU
CPU
CPU CPU
CCD Controller
192x192 active area
CPU
CPU
CPU CPU
CCD Controller
192x192 active area
CPU
CPU
CPU CPU
CCD Controller
256x256 detector
192x192 active area
CPU
CPU
CPU
CPU
CPU
CPU
CPU
CPU
Tip/Tilt Sensor Deformable Mirror
100/1000 EthernetLCU
256x256 detector
256x256 detector
256x256 detector
VME64x
CPU
CPU
CPU
CPU
CPU
CPU
CPU
CPU
Reco
nstru
ctio
n
CPU
CPU
CPU
CPU
Con
trol
Statistics
1-2 KHz
~1300 act.
1.5kHz
VLT Deformable M2VLT Deformable M2
LETI-LAOG MOEM
800 µm pitch
![Page 5: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/5.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 5Page 5
WPsWPs description (1)description (1)
Design and prototype development of a Multiple FOV WFS for the LDesign and prototype development of a Multiple FOV WFS for the LBT BT telescopetelescope
MultiMulti--FOV WFS FOV WFS for LBTfor LBT
2.42.4
Design and prototype development of a multiDesign and prototype development of a multi--object WFS for the GTC object WFS for the GTC MCAO system (best effort)MCAO system (best effort)
MultiMulti--object object WFS for GTCWFS for GTC
2.32.3
Conceptual and preliminary design of a L/NGS MCAO system dedicatConceptual and preliminary design of a L/NGS MCAO system dedicated ed to large (1to large (1’’) FOV correction at short wavelength.) FOV correction at short wavelength.Feasibility and conceptual design of a very large FOV multiFeasibility and conceptual design of a very large FOV multi--WFS AO WFS AO system (FALCON)system (FALCON)
L/NGS MCAO L/NGS MCAO design for the design for the
VLTVLT
2.22.2
Feasibility studies and conceptual design for an Extreme AdaptivFeasibility studies and conceptual design for an Extreme Adaptive e Optics system dedicated to planet search science. Definition of Optics system dedicated to planet search science. Definition of the high the high level specification of all key components required for this systlevel specification of all key components required for this system and em and intended to be developed within this JRP (Deformable mirror, wavintended to be developed within this JRP (Deformable mirror, wavefront efront sensor, Real Time computer, control)sensor, Real Time computer, control)
XAO system XAO system conceptual conceptual
designdesign
2.12.1
This WP will concentrate mainly on the system study and design oThis WP will concentrate mainly on the system study and design of new f new AOAO--MCAO facilities for the current Infrastructures.MCAO facilities for the current Infrastructures.
System designSystem design22
This WP will mainly coordinate the JRA activities, prepare the kThis WP will mainly coordinate the JRA activities, prepare the key ey specifications for the other specifications for the other WPsWPs, organize study and design reviews, , organize study and design reviews, prepare the 18prepare the 18--months period reports and detailed work plans for the months period reports and detailed work plans for the OPTICON management.OPTICON management.
ManagementManagement11
DescriptionDescriptionTitleTitleWPWP
![Page 6: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/6.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 6Page 6
WPsWPs description (2)description (2)
Design and demonstration prototype of a Design and demonstration prototype of a PiezoPiezo stack deformable mirror stack deformable mirror control electronic able to drive the DM in WP3.3 will be developcontrol electronic able to drive the DM in WP3.3 will be developed and ed and tested. The prototype will not necessarily control the 1000 actutested. The prototype will not necessarily control the 1000 actuators.ators.
PiezoPiezo DM DM control control
electronicselectronics
3.43.4
Design and prototype of a Design and prototype of a PiezoPiezo stack Deformable Mirror with >1000 stack Deformable Mirror with >1000 actuators will be developed and tested.actuators will be developed and tested.
HighHigh--density density piezopiezo-- stack stack
DMDM
3.33.3
A theoretical study and experimental demonstration of an optimalA theoretical study and experimental demonstration of an optimal MCAO MCAO control will be performed on the ESO MCAO demonstrator.control will be performed on the ESO MCAO demonstrator.
Optimal control Optimal control for MCAO for MCAO systemssystems
3.23.2
22ndnd generation of Real Time Computer (RTC) platform for XAO and generation of Real Time Computer (RTC) platform for XAO and MCAO systems. A new H&SW RTC architecture will be designed and MCAO systems. A new H&SW RTC architecture will be designed and prototyped. Performance according to WP 2.1 and 2.2 will be prototyped. Performance according to WP 2.1 and 2.2 will be demonstrateddemonstrated
22ndnd generation generation RTC platformRTC platform
3.13.1
This WP contains all R&D activities required to support the abovThis WP contains all R&D activities required to support the above AOe AO--MCAO systemsMCAO systems
Technology Technology R&DR&D
33DescriptionDescriptionTitleTitleWPWP
![Page 7: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/7.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 7Page 7
WPsWPs description (3)description (3)
A Pyramid and Shack Hartmann high order wavefront sensors will bA Pyramid and Shack Hartmann high order wavefront sensors will be e developed and their performance compared on a dedicated test bendeveloped and their performance compared on a dedicated test benchch
High order High order WFS WFS
experimental experimental studystudy
3.83.8
2k act. & low order MDM R&D. A full design of a 2k act. and low 2k act. & low order MDM R&D. A full design of a 2k act. and low order order MDM will be performed and prototypes will be developed. CorrespoMDM will be performed and prototypes will be developed. Corresponding nding control electronics will be designed and prototyped. Testing of control electronics will be designed and prototyped. Testing of these these prototypes will be done on a best effort basis depending on remaprototypes will be done on a best effort basis depending on remaining ining funds for the test bench.funds for the test bench.
2k & low order 2k & low order MicroMicro--
deformable deformable mirrors R&Dmirrors R&D
3.73.7
Design, manufacturing and testing of a large (~1m) convex glass Design, manufacturing and testing of a large (~1m) convex glass shell shell for large deformable mirror will be performedfor large deformable mirror will be performed
Manufacturing Manufacturing of a large of a large
convex glass convex glass shellshell
3.63.6
Feasibility, conceptual and preliminary design of the VLT adaptiFeasibility, conceptual and preliminary design of the VLT adaptive ve secondary will be developed. Required subsecondary will be developed. Required sub--systems prototypes will be systems prototypes will be developed to overcome issues identified during the design phase.developed to overcome issues identified during the design phase.
VLT adaptive VLT adaptive secondary secondary
design studydesign study
3.53.5
DescriptionDescriptionTitleTitleWPWP
![Page 8: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/8.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 8Page 8
Interaction between Work packagesInteraction between Work packages
Planet FinderWP 2.1
ESO
1600 act. Piezo DM: WP 3.3-3.4RTC Platform R&D: WP 3.1
CCD R&D: JRA2 High Order WFS experiment: WP 3.8
![Page 9: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/9.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 9Page 9
VLT PLANET FINDER I: CHEOPSVLT PLANET FINDER I: CHEOPS
VLTNasmythPlatform
ZIMPOLPolarimeter
NIRIntegral
FieldSpectrogr.(R ~ 15)
FullSpectrum
TransmissionX-AO
~1600 Act.~ 2kHzSR~ 0.8 @ 1µm
2562 elementsR ~ 152k x 2k chip
simultaneouscharge shifting pol. switching@ ~ 1kHz
accuracy ~ 10-6
Courtesy MPIA
![Page 10: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/10.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 10Page 10
Nasmyth focus
Common Path
VisNIR
AO sensing
Visible Channel
Coronograph
NIR Imaging channel
Imaging Spectrograph
Courtesy LAOG
II
![Page 11: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/11.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 11Page 11
WP 2.1: Schedule and deliverablesWP 2.1: Schedule and deliverables
May, 2007May, 2007Final Design ReviewFinal Design Review
November, 2004November, 2004Phase A Conceptual design studyPhase A Conceptual design study
May , 2006May , 2006Preliminary design ReviewPreliminary design Review
May, 2005May, 2005Start of phase BStart of phase B
May, 2004May, 2004Mid Term Review: CCD, DM, RTC specsMid Term Review: CCD, DM, RTC specs
May, 2003May, 2003Feasibility KickFeasibility Kick--offoff
DateDateMilestonesMilestones
![Page 12: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/12.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 12Page 12
Interaction between Work packagesInteraction between Work packages
L/NGS MCAOWP 2.2 2.3 2.4
Optimal control MCAO: WP 3.2Adaptive secondary: WP 3.5-3.6
CCD R&D: JRA2 RTC Platform R&D: WP 3.1MOEMS R&D: WP 3.7
MAD
![Page 13: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/13.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 13Page 13
WP 2.2: MUSE Ground Layer AOWP 2.2: MUSE Ground Layer AO
MUSE Wide Field ModeMUSE Wide Field ModeEEx2 in 0.2”EEx2 in 0.2”
MUSE Narrow Field ModeMUSE Narrow Field ModeSr(R)~10%Sr(R)~10%
4 Sodium LGSsØ30”
Faint NIR TT-NGSScience
7.5”FOVScience1’ FOV
3’ FOV
4 Sodium LGSsØ140”
Faint vis. TT-NGS
Wavefront tomography using 4 sodium LGSsGround layer correction: one Deformable Mirror
![Page 14: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/14.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 14Page 14
WP 2.2: MUSE GROUND LAYER AOWP 2.2: MUSE GROUND LAYER AO
WFS Calibratio
n
2’ LGS Acquisition
Camera
On-axis IR NGS TT Sensor
Off-axis Vis NGS
TT Sensor
LGS FocusTrombone
VL
T A
DA
PTE
R
4 LGS Wavefront
sensors
VLT M1
M2 + DM
LGSs
Laser LaunchTelescopes
AO
RE
LA
Y O
PTIC
SMUSE
SPECTROGRAPH 3’ FOV
MUSE Calibration
1’ -7.5”FOV
MUSE + AO Calibration
PupilPupil
Field
![Page 15: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/15.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 15Page 15
WP2.2: MUSE GROUND LAYER AOWP2.2: MUSE GROUND LAYER AO
AO Structure 1
AO Structure 2
Adaptor-rotator
IR TT sensor
Calibration Unit
![Page 16: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/16.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 16Page 16
WP 2.2: ASSISTWP 2.2: ASSISTAAdaptive daptive SSecondary econdary SSimulator and imulator and IInstrument nstrument TTest bedest bed
Mimic spot elongation LGSElongatedLGS shape
Point likeNGS shapeSodium589 nmLGS wavelengthIR or VIS WFS0.45 – 2.5 µmNGS wavelength= MUSE to HAWK-I or KMOSFree within 1.5’- 4.5’LGS location= MUSE to HAWK-I or KMOSFree within 3’-8’NGS locationMedian seeing Paranal0.5-1”Seeing= f/# Nasmyth VLT focusf/15Output f-number>Temporal behaviour> 2 kHz (TBC)Operating frequencyOptionally 9’ x 9’ (TBD)3’ => 8’Field sizePattern equal to Adaptive Secondary~1300Number of act.MUSE 465-930, X-Shooter V+IR, HAWK-I0.45-2.5 µmWavelength Range
CommentOperating rangeRequirement
![Page 17: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/17.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 17Page 17
WP 2.2: ASSISTWP 2.2: ASSIST
Initial design based on MAD conceptInitial design based on MAD conceptVoiceVoice--coil actuated Deformable Mirrorcoil actuated Deformable MirrorInfluence functions of existing DSMInfluence functions of existing DSMDeveloped in Leiden AO Laboratory: LAOLABDeveloped in Leiden AO Laboratory: LAOLAB
![Page 18: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/18.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 18Page 18
WP 2.2 deliverablesWP 2.2 deliverables
To+9MUSE conceptual design study
To + 40MUSE-AO + DSM simulator FDR
To + 28MUSE-AO+ DSM simulator PDR
To + 16Trade-off review
To+10MUSE instrument KO
TimeMilestones
![Page 19: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/19.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 19Page 19
Mid-high-layer WFS
Ground layer WFS left
constant envelope collimator
Piston mirror
Fringe and flexure tracker
Dichroic wheel Science detector
F20 camera
WP2.3: LINC-NIRVANA
Ground layer WFS right
![Page 20: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/20.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 20Page 20
Pyramid sensoroptical co-adding 12 stars in GWS 8 stars in MHWS
2’
6’Mid and High Layer WFS 2’Ground Layer WFS 2’- 6’
WP 2.3: Multiple FOV WFS
![Page 21: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/21.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 21Page 21
GWS in detail
WP2.3: 6' FoV Ground Layer WFS
Star enlarger
GL WFS
![Page 22: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/22.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 22Page 22
2Q-04 3Q-04 4Q-04 1Q-05 2Q-05 3Q-05 4Q-05 1Q-06 2Q-06 3Q-06 4Q-06 1Q-07 2Q-07 3Q-07MfoV
Kick-offDesign phase
Design ReviewConstruction
Testing EuropeIntegration LBT
First LightSkytests
Final Report6 12 18 24 30 36
WP2.3: Deliverables/Schedule
• Design report: 07. 2004• First light on LBT: 01. 2007• Test Report: 10. 2007
![Page 23: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/23.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 23Page 23
WP 2.4: OBJECTIVESWP 2.4: OBJECTIVESIACIAC
Determine Determine whatwhat typetype ofof multimulti--objectobject wavefront wavefront sensor sensor willwill be be usedused in in thethe GTCAO dualGTCAO dual--conjugate conjugate modemode
Determine Determine viabilityviability ofof multimulti--objectobject curvaturecurvature sensingsensingcompare compare withwith ShackShack--HartmannHartmann//pyramidpyramid sensingsensing
DesignDesign a a laboratorylaboratory prototypeprototype, , togethertogether withwithmultimulti--layerlayer turbulenceturbulence simulatorsimulatorDevelopDevelop algorithmsalgorithms toto be be testedtested onon thethe prototypeprototype
![Page 24: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/24.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 24Page 24
WP 2.4: DEVELOPMENT PLANWP 2.4: DEVELOPMENT PLAN
2004 2005 2006 2007SpecificationViability studyViability study report (I&II)Conceptual designConceptual Design reportPrototype developmentLaboratory testsLaboratory tests report
![Page 25: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/25.jpg)
1st1st--2nd April ’04 GENT2nd April ’04 GENT OPTICONOPTICON--JRA1 KO N. JRA1 KO N. HubinHubin
WP 3: Key Component R&DWP 3: Key Component R&D
![Page 26: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/26.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 26Page 26
WP 3.1: AO Real Time platformWP 3.1: AO Real Time platformESOESO
Inputs: the AOInputs: the AO--RTC Platform grows around real projectsRTC Platform grows around real projects
AO RTCPlatformAO RTCPlatform
HAWK-IHAWK-I
Planet FinderPlanet Finder MUSEMUSE
OWLOWL
Others?Others?
![Page 27: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/27.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 27Page 27
WP 3.1: Implementation strategyWP 3.1: Implementation strategyThe AO platform serves several projects but does not end with themThe AO platform serves several projects but does not end with thThe AO platform serves several projects but does not end with themem
HardwareSpecification
CoreLibraries
Real-TimeCommunication
UserInterface
WP2.1
WP2.2
MUSE
Planet Finder
HAWK-I
Input Output
Platform
Impl
emen
tatio
nPr
otot
ypes
![Page 28: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/28.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 28Page 28
WP 3.1: FPGA development for WP 3.1: FPGA development for RTC platformRTC platform
COTS FPGA PMC module
Contribution from Durham
![Page 29: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/29.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 29Page 29
WP 3.1: Schedule & deliverablesWP 3.1: Schedule & deliverables
Milestone19.07.04Final Design Report7M22.01.07AO-MCAO RTC Platform Final Design
3 M01.01.04Specification of the 2nd generation AO and MCAO RTC Platform
10 M05.04.04Conceptual Design Study & Procurement
Milestone21.01.05Conceptual Design Review
2 M24.01.05Computational module testing
Milestone10.08.07Final Design Report
5M18.01.07AO-MCAO RTC Platform Design
Milestone26.08.06Test Report6 M04.03.06AO Platform Prototype testing11 M21.03.05AO Platform Prototype development (HW & SW)
Milestone18.03.05Performance and test report M1M1
M2M2
![Page 30: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/30.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 30Page 30
WP 3.2 MCAO optimal controlWP 3.2 MCAO optimal control
Optimal Control methods for MCAO Optimal Control methods for MCAO Theoretical study of the optimal control in MCAO: robustness to Theoretical study of the optimal control in MCAO: robustness to model model errors, simulation and performance with realistic enderrors, simulation and performance with realistic end--toto--end modelend modelDemonstration on Onera AO laboratory bench: single GS Mono Demonstration on Onera AO laboratory bench: single GS Mono Conjugate AO with offConjugate AO with off--axis optimizationaxis optimizationDevelopment & Test on MAD star oriented @ ESODevelopment & Test on MAD star oriented @ ESO
High performance WFS in MCAO High performance WFS in MCAO Theoretical studies and identification of key performance issuesTheoretical studies and identification of key performance issues: :
•• linearity versus corrected linearity versus corrected FoVFoV (e.g. GS separation…), (e.g. GS separation…), •• sensitivity versus dynamicssensitivity versus dynamics
Experimental validation: Experimental validation: •• Select key issues to be validated by experiment on MAD, Select key issues to be validated by experiment on MAD, •• Perform the validation with ESOPerform the validation with ESO
![Page 31: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/31.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 31Page 31
WP 3.2: Schedule and deliverablesWP 3.2: Schedule and deliverables
T0 + 36T0 + 36High High perfperf. WFS in MCAO: Experimental validation on . WFS in MCAO: Experimental validation on MAD; reportMAD; report
T0 + 24T0 + 24High High perfperf. WFS in MCAO: Criteria, key issues for . WFS in MCAO: Criteria, key issues for WFS devices; reportWFS devices; report
T0 + 12T0 + 12High performance WFS in MCAO: Concepts & key High performance WFS in MCAO: Concepts & key parameters; reportparameters; report
T0 + 36T0 + 36Optimal control experimental validation on MADOptimal control experimental validation on MAD
T0 + 20T0 + 20Optimal control demonstration on AO bench & test Optimal control demonstration on AO bench & test reportreport
T0 + 12T0 + 12Optimal control theoretical study reportOptimal control theoretical study report
TimeTimeMilestonesMilestones
![Page 32: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/32.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 32Page 32
WP 3.3 & 3.4: WP 3.3 & 3.4: PiezoPiezo DM R&DDM R&DESOESO
DM Top Level specificationsDM Top Level specifications40x40 rectangular 40x40 rectangular --> 1304 total> 1304 total5 mm spacing 5 mm spacing --> 200mm diameter> 200mm diameterActuator stroke: Actuator stroke: ±±55µµmmInterInter--actuator stroke: actuator stroke: ±±1.21.2µµmmResidual WFE: 10 nm Residual WFE: 10 nm rmsrms
DM Control electronicDM Control electronicUp to 1500 channelsUp to 1500 channels±±400 V400 V
Piezo DMPiezo DM41412 2 act.act.
![Page 33: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/33.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 33Page 33
WP 3.3 & 3.4: WP 3.3 & 3.4: PiezoPiezo--DM & control scheduleDM & control schedule
CfTCfT to be issued:to be issued: July 04July 04Start of contract:Start of contract: Nov 04Nov 04DM control electronic Specs:DM control electronic Specs: Jan. 05Jan. 05Design review, end of phase 1:Design review, end of phase 1: June 05June 05DM control electronic design review:DM control electronic design review: Sept. 05Sept. 05DM control electronic prototype:DM control electronic prototype: Feb. 06Feb. 06DM manufactured, end of phase 2:DM manufactured, end of phase 2: May 07May 07Test report, end of phase 3:Test report, end of phase 3: July 07July 07Provisional acceptance, phase 4:Provisional acceptance, phase 4: Oct.07Oct.07
![Page 34: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/34.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 34Page 34
Interaction between Work packagesInteraction between Work packagesESOESO
Adaptive secondary
WP 3.5
RTC Platform R&D: WP 3.1Thin convex shell: WP 3.6
DSM Simulator MOEMS R&D: WP 3.7
![Page 35: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/35.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 35Page 35
WP 3.5: VLT adaptive M2 designWP 3.5: VLT adaptive M2 design
Specifications preparedSpecifications prepared15 months feasibility/ conceptual design study (01.04)15 months feasibility/ conceptual design study (01.04)
Validate I/Fs with present VLT (volume, weight, dissipation)Validate I/Fs with present VLT (volume, weight, dissipation)Number of actuator & actuator spacing Number of actuator & actuator spacing Actuator response time Actuator response time Total and inter actuator stroke requirementsTotal and inter actuator stroke requirementsThin shell requirement and feasibility Thin shell requirement and feasibility WP3.6Calibration issuesCalibration issues
![Page 36: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/36.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 36Page 36
SHELL THICKNESS vs ACT.S SP. SHELL < 15 nm RMS WFMMT < 64 nm, P45 < 28 nm
MAGNET GLUING TEST (Phase 2)
CURRENT (LBT) ACT.S SPACING → 1015 ACTsNEW MAGNET DESIGN26.5mm PITCH → 1300 ACTs
LBT672 POWER = 2000 W(1300 ACTs → 3000 W)
WP 3.5: VLT Adaptive secondaryWP 3.5: VLT Adaptive secondary
![Page 37: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/37.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 37Page 37
WP 3.5: VLTWP 3.5: VLT DM2 coordinationDM2 coordination
• control system simulation
• control system design • embedded SW design
• HW design • HW prototyping (dynamic performance opt.)
• optimization of size & power consumption
• mechanical/thermal design • FEA
• actuators/magnet design
• handling, integration procedures + MGSE
• system & specs overview
• control law design
• optical claibration & testing
• engineering SW
![Page 38: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/38.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 38Page 38
WP 3.5: VLT Adaptive secondary PlanWP 3.5: VLT Adaptive secondary Plan
To+ 4M Phase 1: I/Fs analysis and straw-man design
5M ÷ 9M Phase 2: Deformable mirror surface quality and dynamical performance
10M ÷ 15M Phase 3: Conceptual design and analysis
16M ÷ 24M Phase 4: Preliminary design
25M ÷ 36M Phase 5: Final design
![Page 39: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/39.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 39Page 39
WP 3.6: Thin shell R&D plan
Demonstration of a large convex glass shell manufac 620 days 26-10-04Spec. of a ~1-m convex glass shell prototype 2 mons 26-10-04Manufacturing process and Test set-up study of a ~1-m glass 5 mons 21-12-04Study review 0 days 09-05-05Manufacturing of a ~1m glass shell prototype 15 mons 30-08-05Testing of the ~1m glass shell 5 mons 24-10-06Acceptance review 0 days 12-03-07
09-05
12-03
Task Name Duration Start
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H12003 2004 2005 2006 2007 2008
Call for tender will be issued
- Spec. of a ~ 1m convex glass shell prototype INSU/INAF/ESO
- Manufacturing process and test set-up study INSU
- Manufacturing of the ~ 1m glass shell prototypeINSU- Testing of the ~ 1m glass shell INSU
- Study review INSU
- Acceptance review INSU
![Page 40: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/40.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 40Page 40
WP 3.7: Specification of MOEMSWP 3.7: Specification of MOEMS
30nm?15nm30nm15nm15nm30nm30nm Best flat WFE rms
<500Hz?1.5kHz TBC
1kHz2kHz2kHz<1kHz<1kHzFrequency cut off
?1.2 µm1 µm1 µm1.1 µm
1.2 µm-Inter-actuator stroke
10-15µm10 µm2 µm2 µm10 µm10 µm10 µmMech. stroke
~1mm~2mm2mm<1mm1mm1 mm1mmActuator spacing
?Circular geometry
magnetic
electro static
electro static
electro static
magneticPrinciple? /Comment
~100130010040 000(200x200)
150010 000100# Actuators
Ophtamology(TBC)
MUSE M2 Simulator
VLTI-AT(1.8m)
X-AO forOWL-ELT
X-AO on 8m
OWL-ELT100m-60mButtons
VLT-8mFalcon AO Buttons
Micro –DM specification overview
![Page 41: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/41.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 41Page 41
WP 3.7: WP 3.7: towardtoward 2K MOEMS R&D2K MOEMS R&D
LAOG/LETI : LAOG/LETI : electrostaticelectrostatic mirrormirror64 64 actuatorsactuators2 kHz, 8um 2 kHz, 8um strokestroke
600µm
Prototype
![Page 42: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/42.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 42Page 42
WP 3.7: WP 3.7: VoiceVoice coilcoil MOEMS DMMOEMS DM
LAOG/LETI: LAOG/LETI: VoiceVoice coilcoil mirrormirrorSiliconSilicon membranemembrane2mm pitch 2mm pitch 52 52 actuatorsactuatorsStrokeStroke > 50um> 50um
![Page 43: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/43.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 43Page 43
WP 3.7: MOEMS control WP 3.7: MOEMS control electronicselectronics
DeveloppedDevelopped by LAOG:by LAOG:32 32 channelchannel modules modules includingincluding DAC DAC andand HV amplifier HV amplifier (200V)(200V)ScalableScalable to >2000 to >2000 channelschannelsDigital InterfaceDigital InterfaceFrameFrame update = 32usupdate = 32us
50mm
![Page 44: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/44.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 44Page 44
WP 3.7: MOEMS R&D scheduleWP 3.7: MOEMS R&D schedule
µDM SpecificationµDM Call for tenderµDM Preliminary DesignµDM Final DesignµDM ManufacturingElectronics design and prototypingElectronics manufacturingPackaging design and prototypingPackaging manufacturingTest bench definitionTest bench development
2004 2005 2006 2007
Contract1st Demonstrator
2k µDMTest Report+ 60 actuators magnetic DM (2005Q4)
![Page 45: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/45.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 45Page 45
WP 3.8: High Order WFS experimentWP 3.8: High Order WFS experimentINAFINAF
XAO systems will require very high accuracy WFSs. • 2 WFS candidates Pyramid and Shack Hartmann
• Simulation on-going at ONERA-MPIA and ESO.
• Experiment to cross check critical issues for high order WFS
• Open loop comparison then low temporal frequency (~2Hz)
![Page 46: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/46.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 46Page 46
WP 3.8: High Order WFS experimentWP 3.8: High Order WFS experiment
SH & PWFS design (ESO-INAF-Durham
Design of the test bench:1) Using the LBT672b unit (Sep05)2) Using Xinetics 349 DM in Heidelberg
WFSs characterization:Interaction matrix identificationMeasurements SNR and repetabilityAliasing contributions to WF error
Definition ofthe exp. study
![Page 47: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/47.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 47Page 47
JRA 1 OrganizationJRA 1 Organization
![Page 48: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/48.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 48Page 48
JRA1 Management tool: FTEsJRA1 Management tool: FTEsWORK PACKAGE
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total/Requested FTE (in pyear) to EC 116.60 17.65 36.9 6.25 8.50 1.00 9.00 4.50 25.10 2.00 20.10 0.00 3.80 1.90 11.4 2.00Total/Requested FTE (in k€) to EC 8551.10 1370.80 2952 500 425 50 454 227 1632 130 1407 0 608 304 912 160
Adaptive Optics JRP Management 3.40 3.00 3.4 3Proposal phase 0.00 0.00
AO-JRP Proposal Preparation 0.10 0.00 0.1 0AO-JRP consolidation with I3 OPTICON 0.10 0.00 0.1 0OPTICON I3 proposal evaluation by EC 0.00 0.00 0 0OPTICON I3 contract negociation with EC/partners 0.20 0.00 0.2 0
Joint Research Project management and follow-up 3.00 3.00 3 3
2nd Generation AO Systems Design 72.35 2.00 19.5 0 3.5 0 0 0 16.1 0 20.1 0 0 0 11.4 2XAO System design study 30.70 0.00 2.5 0 14.1 0 14.1 0
XAO Phase A Study specifications 0.00 0.00XAO Phase A Study 1 (2004) 4.10 0.00 0.1 0 4 0XAO Phase A Study 2 (2004) 4.10 0.00 0.1 0 4 0Review of Phase A Studies; Concept selection 0.30 0.00 0.1 0 0.1 0 0.1 0Specification for the XAO development 0.20 0.00 0.2 0XAO Design phase 22.00 0.00 2 0 10 0 10 0
L/NGS MCAO System design Studies 29.60 2.00 16.2 0 2 0 11.4 2AO Top level requirements 0.00 0.00L/NGS MCAO Simulation & Performance 0.00 0.00L/NGS MCAO Conceptual Design Study 0.00 0.00Conceptual Design Study review & evaluation 0.00 0.00 0 0 0 0N/LGS MCAO system specifications 1.60 0.00 0.2 0 1 0 0.4 0N/LGS MCAO system design 28.00 2.00 16 0 1 0 11 2
Multiobject WFS prototype for GTC 1.80 0.00Specification of the Multi-object WFS prototype development 0.20 0.00Feasibility study 0.40 0.00Multi-object WFS conceptual design 0.40 0.00Multi-object WFS prototype development 0.40 0.00Multi-object WFS prototype testing in the laboratory 0.40 0.00
Multiple FOV MCAO System with NGS 10.25 0.00 0.75 0 3.5 0 6 0MFOV-MCAO Simulation & Performance 1.00 0.00 0.5 0 0.5 0 0 06' FOV ground layer prototype design 5.00 0.00 0.25 0 0.75 0 4 06' FOV ground layer prototype manufacturing 1.00 0.00 0.5 0 0.5 06' FOV ground layer prototye AIT 3.25 0.00 1.75 0 1.5 0
ONERA NOVAINSU MPIAAO- JRP ESO INAF Durham
![Page 49: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/49.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 49Page 49
Status of Partner committed FTEs (2)Status of Partner committed FTEs (2)
Enabling Techno. for 2nd Gen./ELT AO Systems 40.85 12.65 14.1 3.3 5 1 9 4.5 9 2 0 0 3.8 1.9 0 0 0 02nd generation of AO Real-Time Computer platform 14.50 6.75 7.5 3.25 7 3.5
Specification of the 2nd gen. AO and MCAO RTC Platform 1.00 0.50 0.5 0.25 0.5 0.25Conceptual design study 2.00 0.50 1 0 1 0.5Computational module procurement & testing 2.50 1.25 1 0.5 1.5 0.75AO Platform prototype development (HW & SW) 3.50 1.75 2 1 1.5 0.75AO Platform prototype testing 2.50 1.25 1.5 0.75 1 0.5Test report 1.00 0.50 0.5 0.25 0.5 0.25AO-MCAO RTC platform Final design 2.00 1.00 1 0.5 1 0.5
Optimal control methods for MCAO systems 3.90 1.20 1.5 0 2.4 1.2Specification for MCAO Optimal control methods study 0.10 0.00 0.1 0 0 0Theoretical-experimental Study of the optimal control in MCAO 0.90 0.30 0.1 0 0.8 0.3Development of the optimal control for MAD 1.00 0.50 0.3 0 0.7 0.5Implementation of Recons. Method on MAD 0.70 0.00 0.5 0 0.2 0Testing of reconstruction method on MAD 1.20 0.40 0.5 0 0.7 0.4
2nd Generation Piezo DM 0.65 0.00 0.65 0Specification of the 1.5K-actuator piezzo stack DM 0.10 0.00 0.1 0Call for Tender for the design and prototyping 0.10 0.00 0.1 0Design of 1.5K-Actuator DM Prototype 0.10 0.00 0.1 0Development of 1.5K-Actuator DM Prototype 0.10 0.00 0.1 0Testing & evaluation of the 1.5K-Actuator Prototype 0.25 0.00 0.25 0
2nd generation Piezo DM drive electronics R&D 0.60 0.00 0.6 0Conceptual design study specifications 0.10 0.00 0.1 0Conceptual design study 0.00 0.00 0 0Specification of the 1.5K act.DM Drive electronics 0.10 0.00 0.1 0Call for Tender for the design and prototyping 0.10 0.00 0.1 01.5K act. Piezo DM Drive Elec. Design 0.10 0.00 0.1 0 DM Drive Electronics demonstration Prototype development 0.10 0.00 0.1 0DM drive electronics prototype testing 0.10 0.00 0.1 0
VLT Adaptive secondary design Study 2.85 1.00 0.85 0 2 1Spec. of the VLT Adaptive secondary feasibility study 0.25 0.00 0.25 0Feasibility/concept Study of VLT Adaptive Secondary 0.25 0.00 0.25 0Feasibility Study review 0.25 0.00 0.25 0Preliminary design of VLT Adaptive secondary 2.10 1.00 0.1 0 2 1
WORK PACKAGE
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
AO- JRP ESO INAF Durham GrantecanONERA NOVAINSU MPIA
![Page 50: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/50.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 50Page 50
Status of Partner committed FTEs (3)Status of Partner committed FTEs (3)
Large convex glass shell manufacturing demo. 2.90 2.00 0.4 0 2.5 2Spec. of a ~1-m convex glass shell prototype 0.20 0.00 0.1 0 0.1 0Manuf. process and Test set-up study of a ~1m glass shell proto 1.10 0.50 0.1 0 1 0.5Manufacturing of a ~1m glass shell prototype 1.10 1.00 0.1 0 1 1Testing of the ~1m glass shell 0.50 0.50 0.1 0 0.4 0.5
2K act. Micro- Deformable Mirror (MDM) R&D 7.05 0.00 0.55 0 6.5 0MDM subcomponent pre-studies and R&D (Patent) 0.00 0.00Preliminary specifications of a 2K act. & low order MDMs 0.00 0.00 0 0 0 0Preliminary Inquiry for the development of MDMs 0.00 0.00 0 0 0 0Final specification of the MDMs prototypes 0.35 0.00 0.1 0 0.25 0MDM-MDM control electronic I/F definition 0.35 0.00 0.1 0 0.25 0Call For Tender for a 2k act. MDM 0.05 0.00 0.05 0 0 0Preliinary design of 2K-Actuator MDM Prototype 1.55 0.00 0.05 0 1.5 0Final design of a 2K Act. MDM Prototype 0.55 0.00 0.05 0 0.5 0Development of 2K-Actuator MDM Prototype 1.25 0.00 0 0 1.25 0Design of a ~60 act. magnetic MDM prototype 0.00 0.00 0 0 0 01st ~60 act. magnetic MDM prototype and validation 0.25 0.00 0 0 0.25 02nd ~60 act. magnetic MDM prototype and testing 0.50 0.00 0 0 0.5 0MDM Control electonic conceptual design 0.55 0.00 0.05 0 0.5 0MDM Control Electronics Final Design 0.55 0.00 0.05 0 0.5 0MDM Control Electronics Prototype development 0.50 0.00 0 0 0.5 0MDM Test and Calibration plan 0.60 0.00 0.1 0 0.5 0
High-Order WFS Experimental Study 8.40 1.70 2 0 3 0 2 1 1.4 0.7Specification of the HOWFS Experimental Study 0.10 0.00 0.1 0 0 0 0 0 0 0HOWFS theoretical study and performance criteria definition 0.90 0.25 0.3 0 0.1 0 0.2 0.1 0.3 0.15Design of the HOWFSs (SH & P-WFS) & of the test bench 2.30 0.60 0.1 0 1 0 0.8 0.4 0.4 0.2Development of the HOWFSs and test bench 2.00 0.00 1 0 1 0 0 0 0 0HOWFSs performance testing and evaluation 3.10 0.85 0.5 0 0.9 0 1 0.5 0.7 0.35
WORK PACKAGE
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
AO- JRP ESO INAF Durham GrantecanONERA NOVAINSU MPIA
![Page 51: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/51.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 51Page 51
JRA1 Management tool: JRA1 Management tool: HWsHWs investmentinvestmentACTIVITY
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total/Requested (in k€) to EC 13450 4800 5715 2303 749 339 599 312 2969 1052 1653 246 621 317 922 170 223 61Total/Requested FTE (in k€) to EC 8551 1371 2952 500 425 50 454 227 1632 130 1407 0 608 304 912 160 162 0Total/Requested HW (in k€) to EC 4714 3244 2684 1724 310 275 130 70 1305 890 235 235 0 0 0 0 50 50
Total/Requested Travel (in k€) to EC 185 185 79 79 14 14 15 15 32 32 11 11 13 13 10 10 11 110 0
Proposal phase 0 0AO-JRP Proposal Preparation 0 0AO-JRP consolidation with I3 OPTICON 0 0OPTICON I3 proposal evaluation by EC 0 0OPTICON I3 contract negociation with EC/partners 0 0
Joint Research Project management and follow-up 0 02nd Generation AO Systems Design 710 430 270 0 130 120 0 0 25 25 235 235 0 0 0 0 50 50
XAO System design study 320 50 270 0 25 25 25 25XAO Phase A Study specifications 0 0XAO Phase A Study 1 (2004) 135 0 135 0 0 0 0 0XAO Phase A Study 2 (2004) 135 0 135 0 0 0 0 0Review of Phase A Studies; Concept selection 0 0 0 0 0 0Specification for the XAO development 0 0 0 0 0 0XAO Design phase 50 50 25 25 25 25
L/NGS MCAO System design Studies 0 0AO Top level requirements 0 0L/NGS MCAO Simulation & Performance 0 0L/NGS MCAO Conceptual Design Study 0 0Conceptual Design Study review & evaluation 0 0N/LGS MCAO system specifications 0 0N/LGS MCAO system design 0 0
Multiobject WFS prototype for GTC 50 50 50 50Specification of the Multi-object WFS prototype development 0 0 0 0Feasibility study 0 0 0 0Multi-object WFS design 0 0 0 0Multi-object WFS prototype development 40 40 40 40Multi-object WFS prototype testing in the laboratory 10 10 10 10
Multiple FOV MCAO System with NGS 340 330 130 120 210 210MFOV-MCAO Simulation & Performance 0 06' FOV ground layer prototype design 40 40 0 0 40 406' FOV ground layer prototype manufacturing 300 290 130 120 170 1706' FOV ground layer prototye AIT 0 0 0 0 0 06' FOV ground layer on sky testing 0 0
GrantecanMPIA ONERA NOVAINSUAO- JRP ESO INAF Durham
![Page 52: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/52.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 52Page 52
Status of Partner committed Status of Partner committed HWsHWs (2)(2)
Enabling Techno. for 2nd Gen./ELT AO Systems 4004 2814 2414 1724 180 155 130 70 1280 865 0 0 0 0 0 0 0 02nd generation of AO Real-Time Computer platform 410 265 310 225 100 40
Specification of the 2nd gen. AO and MCAO RTC Platform 0 0Conceptual design study 150 95 100 75 50 20Computational module procurement & testing 200 140 150 120 50 20AO Platform prototype development (HW & SW) 60 30 60 30AO Platform prototype testing 0 0Test report 0 0AO-MCAO RTC platform Final design 0 0
Optimal control methods for MCAO systems 115 0 115 0Specification for MCAO Optimal control methods study 0 0Theoretical-experimental Study of the optimal control in MCAO 115 0 115 0Development of the optimal control for MAD 0 0Implementation of Recons. Method on MAD 0 0Testing of reconstruction method on MAD 0 0
2nd Generation Piezo DM 1200 850 1200 850Specification of the 1.5K-actuator piezzo stack DM 0 0Call for Tender for the design and prototyping 0 0Design of 1.5K-Actuator DM Prototype 150 100 150 100Development of 1.5K-Actuator DM Prototype 1050 750 1050 750Testing & evaluation of the 1.5K-Actuator Prototype 0 0
2nd generation Piezo DM drive electronics R&D 230 190 230 190Conceptual design study specifications 0 0Conceptual design study 0 0Specification of the 1.5K act.DM Drive electronics 0 0Call for Tender for the design and prototyping 0 01.5K act. Piezo DM Drive Elec. Design 90 90 90 90 DM Drive Electronics demonstration Prototype development 140 100 140 100DM drive electronics prototype testing 0 0
VLT Adaptive secondary design Study 589 474 559 459 30 15Spec. of the VLT Adaptive secondary feasibility study 0 0Feasibility/concept Study of VLT Adaptive Secondary 100 0 100 0Feasibility Conceptual design study review 0 0Preliminary design 489 474 459 459 30 15
Large convex glass shell manufacturing demo. 385 220 385 220Spec. of a ~1-m convex glass shell prototype 0 0Manuf. process & Test set-up study of a ~1-m glass shell proto. 105 30 105 30Manufacturing of a ~1m glass shell prototype 280 190 280 190Testing of the ~1m glass shell 0 0
ACTIVITY
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
GrantecanMPIA ONERA NOVAINSUAO- JRP ESO INAF Durham
![Page 53: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/53.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 53Page 53
Status of Partner committed Status of Partner committed HWsHWs (3)(3)
2K act. Micro- Deformable Mirror (MDM) R&D 895 645 895 645MDM subcomponent pre-studies and R&D (Patent) 0 0Specification of a 2K act. MDM 0 0MDM-MDM control electronic I/F definition 0 0Call For Tender for a 2k act. MDM 0 0Preliinary design of 2K-Actuator MDM Prototype 270 150 270 150Final design of a 2K Act. MDM Prototype 200 160 200 160Development of 2K-Actuator MDM Prototype 270 235 270 235Design of a ~60 act. magnetic MDM prototype 0 0 0 01st ~60 act. magnetic MDM prototype and validation 20 10 20 102nd ~60 act. magnetic MDM prototype and testing 30 15 30 15MDM Control electonic conceptual design 40 10 40 10MDM Control Electronics Final Design 20 20 20 20MDM Control Electronics Prototype development 45 45 45 45MDM Test and Calibration plan 0 0 0 0
High-Order WFS Experimental Study 180 170 150 140 30 30Specification of the HOWFS Experimental Study 0 0HOWFS theoretical study and performance criteria definition 0 0Design of the HOWFSs & of the test bench 0 0Development of the HOWFSs and test bench 180 170 150 140 30 30HOWFSs performance testing and evaluation 0 0
ACTIVITY
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
Total
Requested
GrantecanMPIA ONERA NOVAINSUAO- JRP ESO INAF Durham
![Page 54: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/54.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 54Page 54
Financial contractual Financial contractual situation before the last situation before the last change recommended change recommended
by ECby EC
Organisation short name
RTD activities
Direct cost 5223of which subcontracting 2524indirect cost 492Total eligible costs 5715
2303Direct cost 724of which subcontracting 0indirect cost 26Total eligible costs 749
339Direct cost 523of which subcontracting 0indirect cost 76Total eligible costs 599
312Direct cost 2697of which subcontracting 820indirect cost 272Total eligible costs 2968
1052Direct cost 1395of which subcontracting 0indirect cost 258Total eligible costs 1653
246Direct cost 384of which subcontracting 0indirect cost 237Total eligible costs 621
317Direct cost 922of which subcontracting 0indirect cost 0Total eligible costs 922
170Direct cost 196of which subcontracting 0indirect cost 27Total eligible costs 223
61Direct cost 12062.7of which subcontracting 3344.0indirect cost 1387.1Total eligible costs 13449.8
4800.0
FINANCIAL INFORMATION- WHOLE DURATION OF THE PROJECT (K€)
ESO
INAF-OAA
Estimated eligible costs and requested EC contribution
Durham
INSU
MPIA
ONERA
NOVA
GTC
TOTAL
Eligible costs
Requested EC contribution
Eligible costs
Requested EC contribution
Eligible costs
Requested EC contribution
Eligible costs
Requested EC contribution
Eligible costs
Eligible costs
Requested EC contribution
Requested EC contribution
Requested EC contribution
Requested EC contribution
Requested EC contribution
Eligible costs
Eligible costs
Eligible costs
![Page 55: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/55.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 55Page 55
Financial situation Financial situation for the first 18for the first 18--
months (before EC months (before EC modification)modification)
Organisation short name
RTD activities
Direct cost 2831of which subcontracting 1689indirect cost 187Total eligible costs 3018
1353Direct cost 354of which subcontracting 0indirect cost 12Total eligible costs 367
184Direct cost 271of which subcontracting 0indirect cost 30Total eligible costs 301
151Direct cost 1393of which subcontracting 350indirect cost 142Total eligible costs 1534
468Direct cost 747of which subcontracting 0indirect cost 135Total eligible costs 883
159Direct cost 198of which subcontracting 0indirect cost 119Total eligible costs 317
165Direct cost 442of which subcontracting 0indirect cost 0Total eligible costs 442
90Direct cost 101of which subcontracting 0indirect cost 12Total eligible costs 113
41Direct cost 6338.3of which subcontracting 2039.0indirect cost 636.9Total eligible costs 6975.2
2610.0
Requested EC contribution
Requested EC contribution
Requested EC contribution
Eligible costs
Eligible costs
TOTAL
NOVA
GTC
Requested EC contribution
Eligible costs
Eligible costs
Eligible costs
Requested EC contribution
MPIA
ONERA
Durham
INSU
Eligible costs
Eligible costs
Requested EC contribution
Requested EC contribution
FINANCIAL INFORMATION- FIRST 18-months(K€)
ESO
INAF-OAA
Eligible costs
Requested EC contribution
Eligible costs
Requested EC contribution
Estimated eligible costs and requested EC contribution
![Page 56: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/56.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 56Page 56
JRA1 cashJRA1 cash--flowflow
00M49 - M60Reporting Periods 5
200300M36 - M48Reporting Periods 4
5001000M25 - M36Reporting Periods 3
8501700M12 - M24Reporting Periods 2
1800M1 - M12Reporting Periods 1
in which first 6 monthsTOTAL
Estimated Grant to the Budget
Month x - Month yReporting Periods
ESTIMATED BREAKDOWN OF THE EC CONTRIBUTION PER REPORTING PERIOD
![Page 57: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/57.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 57Page 57
Change of EC financial rules (1)Change of EC financial rules (1)
1) Organizations with AC financial model MUST charge 20% 1) Organizations with AC financial model MUST charge 20% indirect costs. Request exactly 100% of Eligible costs indirect costs. Request exactly 100% of Eligible costs
(a) direct costs:(a) direct costs: A of which subA of which sub--contractingcontracting(b) indirect costs:(b) indirect costs: 0.2 x (A 0.2 x (A -- subcontracting)subcontracting)(c) Total eligible costs:(c) Total eligible costs: C= A+ BC= A+ B(d) EC contribution:(d) EC contribution: CC
2) Organizations with FCF model MUST charge indirect costs 2) Organizations with FCF model MUST charge indirect costs at 20% of direct costs. (FC contractors can use any indirect at 20% of direct costs. (FC contractors can use any indirect value they wish, for later audit)value they wish, for later audit)
3) Organizations with either FC or FCF model must claim from 3) Organizations with either FC or FCF model must claim from the EC exactly 50% of their listed total eligible cost. the EC exactly 50% of their listed total eligible cost.
![Page 58: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/58.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 58Page 58
Partner contract changes requiredPartner contract changes required
ESO ESO FCF FCF Eligible costs reduced 5223K Eligible costs reduced 5223K 4606K, 4606K, INSU INSU FCF FCF Eligible costs reduced 2969K Eligible costs reduced 2969K 2104K,2104K,INAFINAF FCFFCF Eligible costs reduced 750K Eligible costs reduced 750K 678K,678K,MPIA MPIA AC AC Eligible costs reduced 1653K Eligible costs reduced 1653K 246K, 246K, NOVANOVA AC AC Eligible costs reduced 922K Eligible costs reduced 922K 170K170KIACIAC FCFFCF Eligible costs reduced 223K Eligible costs reduced 223K 122K122KONERAONERA FC FC no change needed no change needed DurhamDurham ACAC Eligible costs reduced 599K t Eligible costs reduced 599K t 312K312KNO IMPACT ON MONEY ACTUALLY RECEIVED FROM ECNO IMPACT ON MONEY ACTUALLY RECEIVED FROM EC
EC AUDIT WILL BE BASED ON THESE NEW NUMBERSEC AUDIT WILL BE BASED ON THESE NEW NUMBERSBUT NO CHANGE ON DELIVERABLESBUT NO CHANGE ON DELIVERABLES
THEREFORE INTERNAL MONITORING WILL BE BASED ON THEREFORE INTERNAL MONITORING WILL BE BASED ON THE AGREED RESSOURCES DURING NEGOTIATIONTHE AGREED RESSOURCES DURING NEGOTIATION
![Page 59: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/59.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 59Page 59
Financial contractual Financial contractual situation after the situation after the
change of financial change of financial rulerule
CAREFULL:Absolutely no change in term of deliverablesPartner should keep internal resources as
promised during negotiation
Organisation short name
RTD activities
Direct cost 4259of which subcontracting 2524indirect cost 347Total eligible costs 4606
2303Direct cost 565of which subcontracting 0indirect cost 113Total eligible costs 678
339Direct cost 260of which subcontracting 0indirect cost 52Total eligible costs 312
312Direct cost 1890of which subcontracting 820indirect cost 214Total eligible costs 2104
1052Direct cost 205of which subcontracting 0indirect cost 41Total eligible costs 246
246Direct cost 384of which subcontracting 0indirect cost 237Total eligible costs 621
317Direct cost 142of which subcontracting 0indirect cost 28Total eligible costs 170
170Direct cost 102of which subcontracting 0indirect cost 20Total eligible costs 122
61Direct cost 7806.1of which subcontracting 3344.0indirect cost 1052.8Total eligible costs 8858.8
4800
GTC Eligible costs
Requested EC contribution
TOTAL Eligible costs
Requested EC contribution
ONERA Eligible costs
Requested EC contribution
NOVA Eligible costs
Requested EC contribution
INSU Eligible costs
Requested EC contribution
MPIA Eligible costs
Requested EC contribution
INAF-OAA Eligible costs
Requested EC contribution
Durham Eligible costs
Requested EC contribution
FINANCIAL INFORMATION- WHOLE DURATION OF THE Estimated eligible costs and requested
EC contribution
ESO Eligible costs
Requested EC contribution
![Page 60: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/60.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 60Page 60
JRA1 detailed schedule toolJRA1 detailed schedule tool
![Page 61: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/61.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 61Page 61
JRA1 schedule (2)JRA1 schedule (2)
![Page 62: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/62.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 62Page 62
JRA1 schedule (3)JRA1 schedule (3)
![Page 63: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/63.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 63Page 63
JRA1 schedule (4)JRA1 schedule (4)
![Page 64: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/64.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 64Page 64
JRA1 MONITORINGJRA1 MONITORING
JRA1 general meeting every 9 monthsJRA1 general meeting every 9 monthsJRA1 progress report / each partner every 9 months JRA1 progress report / each partner every 9 months (.doc template will be provided) including technical (.doc template will be provided) including technical annexannexFTE & HW sheets (.FTE & HW sheets (.xlsxls template will be provided)template will be provided)General meeting viewgraphs to be provided in .General meeting viewgraphs to be provided in .pptpptWEB page with password will be createdWEB page with password will be created
![Page 65: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/65.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 65Page 65
JRA 1 Monitoring: Progress reportsJRA 1 Monitoring: Progress reports
Scope: Scope: WPsWPs concerned by the reportconcerned by the reportWP XXWP XX
Status of WP xx (max 2 pages) as far as possible refer to the teStatus of WP xx (max 2 pages) as far as possible refer to the technical chnical annex avoid annex avoid blablablabla….….Milestones achieved, actions completed (Milestones achieved, actions completed (w.r.tw.r.t JRA1 schedule)JRA1 schedule)Area of concerns: change of specs, schedule, deliverables, cost,Area of concerns: change of specs, schedule, deliverables, cost, FTEs….FTEs….Plan for next period: activities, deliverablesPlan for next period: activities, deliverables
WP YY etc…..WP YY etc…..Technical annex shall include (in electronic form):Technical annex shall include (in electronic form):
Specifications/ Statement of workSpecifications/ Statement of workConceptualConceptual--PreliminaryPreliminary--Final design reportsFinal design reportsTest reportsTest reportsPapers mentioning OPTICON & present EC contract (info to be provPapers mentioning OPTICON & present EC contract (info to be provided)ided)
FTE time sheets & list of expenditures (.FTE time sheets & list of expenditures (.xlsxls))
![Page 66: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/66.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 66Page 66
RECOMMENDED EXAMPLE OF FTE TIME SHEETS / RECOMMENDED EXAMPLE OF FTE TIME SHEETS / MONTHMONTH
![Page 67: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/67.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 67Page 67
Reporting: Time sheet reportReporting: Time sheet reportTIME SHEET
WORK PACKAGES WP #
Mgmt Coordination WP 1 11 0.01
XAO System Feasibility and Design WP 2.1
(L/NGS) MCAO Design f. VLT WP 2.2
Multi-object WFS f. GTC WP 2.3
Multiple FOV WFS f. LBT WP 2.4
2nd Gen RTC Platform WP 3.1
Optimal Control Methods f. MCAO Systems WP 3.2
Hifg Density Piezo-Stack Deform. Mirror (DM) WP 3.3
Piezo DM Control Electronics WP 3.4
VLT Adaptive Secondary Design Study WP 3.5
Demonstration of a Large Convex Glass Shell WP 3.6
2K Actuator & Low Order Micro-DM (MDM) R&D WP 3.7
High Order WFS Experimental Study WP 3.8
EC funded manpower (Y/N) Y 11 0.01
Hours/Year 1760 313
Date: Signature by Partner Scientific in Charge:
Please indicate the Cost (EUR) of 1 FTE / Year (including overhead): 50,000
EC FUNDED GRAND TOTAL MANPOWER COST(EUR)
PARTNER FUNDED GRAND TOTAL MANPOWER COST (EUR)
GRAND TOTAL HOURS/FTE
Total in FTE (EUR)Total Hours
Jul Aug SepFeb Mar JunApr May
Name of staff:
Partner: REPORTING PERIOD 1
JANUARY - SEPTEMBER 2004
11
Jan
EUROPEAN COMMISSION AO - JRA 1 / OPTICON
![Page 68: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/68.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 68Page 68
Reporting: HW / travel ExpendituresReporting: HW / travel Expenditures
Additional tables might be necessary to detail & justify all expenditures per WP.
WORK PACKAGES WP # Subcontract Hardware Subcontract Hardware
Mgmt Coordination WP 1 10 10 5 5
XAO System Feasibility and Design WP 2.1
(L/NGS) MCAO Design f. VLT WP 2.2
Multi-object WFS f. GTC WP 2.3
Multiple FOV WFS f. LBT WP 2.4
2nd Gen RTC Platform WP 3.1
Optimal Control Methods f. MCAO Systems WP 3.2
Hifg Density Piezo-Stack Deform. Mirror (DM) WP 3.3
Piezo DM Control Electronics WP 3.4
VLT Adaptive Secondary Design Study WP 3.5
Demonstration of a Large Convex Glass Shell WP 3.6
2K Actuator & Low Order Micro-DM (MDM) R&D WP 3.7
High Order WFS Experimental Study WP 3.8
10 10 5 5
GRAND TOTAL FUNDED BY THE PARTNER (including 20% overhead) 11
GRAND TOTAL
GRAND TOTAL (including 20% overhead)
13
Total Amount (k€ ) (w/o Overhead)
Total Amount (k€ ) charged to EC (w/o Overhead)
HARDWARE & TRAVEL EXPENDITURES REPORT
AO - JRA 1 OPTICON
Partner:
24
TRAVEL COSTS (k€ ) 2
GRAND TOTAL TO BE INVOICED TO EC (including 20% overhead)
DESCRIPTION
REPORTING PERIOD 1
January 2004 - September 2004
Date: Signature by Partner Scientific in Charge:
![Page 69: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/69.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 69Page 69
AURAAURA--ESO agreementESO agreement
Agreement has been signed between ESO and AURA to Agreement has been signed between ESO and AURA to collaborate on critical collaborate on critical ELT technologyELT technology developmentsdevelopmentsThis agreement includes AO R&D & in particular:This agreement includes AO R&D & in particular:
Large Deformable mirrorLarge Deformable mirrorLarge thin shell Large thin shell CCD for AOCCD for AOPiezoPiezo stack Deformable mirrorstack Deformable mirrorMCAO reconstructionMCAO reconstruction
Objectives is to share development cost or explore Objectives is to share development cost or explore alternative technologies for a given specificationalternative technologies for a given specificationOPTICON board position on if / how coordinate with related OPTICON board position on if / how coordinate with related JRA 1JRA 1--2 activities is required2 activities is required
![Page 70: Joint Research Activity 1 2nd generation Adaptive Optics ... · Final Design Review May, 2007 Phase A Conceptual design study November, 2004 Preliminary design Review May , 2006 Start](https://reader034.vdocuments.net/reader034/viewer/2022050300/5f69cff3eea45853d772f5d5/html5/thumbnails/70.jpg)
1st-2nd April ’04 GENT OPTICON-JRA1 KO N. Hubin Page 70Page 70
CONCLUSIONSCONCLUSIONS
WPsWPs defined: Tasks, milestones, resourcesdefined: Tasks, milestones, resourcesManagement tools are definedManagement tools are definedMonitoring/reporting tools have been defined: Monitoring/reporting tools have been defined:
Time sheet, Time sheet, HW expenditures, HW expenditures, Matching fundsMatching fundsRegular progress report from each partnerRegular progress report from each partner
National agencies should maintain the original level National agencies should maintain the original level of funding independently of EC contract of funding independently of EC contract