Jonathan WheelerTeam Manager

Strategic Economic Infrastructure

East Sussex Strategic PartnershipStrategic Transport Update

30 October 2014

Summary

• Transport and Economic Growth• Progress during 2014

– Bexhill Hastings Link Road– A27 and A21– Rail & Aviation– Local Transport and LSTF

• 2015 onwards: delivering the Strategic Economic Plan and Local Growth Deal

Transport and Economic Growth

• Delivering transport infrastructure to support economic growth underpinned by:– Local Transport Plan – District & Borough Local Plans & Infrastructure

Delivery Plans– SELEP Strategic Economic Plan– Sustainable Community Strategy and Local

Community Strategies– The Council Plan– Emerging East Sussex Growth Strategy

Bexhill Hastings Link Road• Construction started

early 2013• Completed Spring 2015• Unlocks up to 2,000

new homes and 50,000sqm of employment space

• Creates 3,000 jobs• Complimentary

Measures

A27 Feasibility Improvement Study• Study scope: Pevensey to

Portsmouth• Lewes - Polegate identified

as priority for intervention• Identified range of options to

address issues• Assessing deliverability,

affordability & value for money

Study

A21 and Highways Agency• A21 Tonbridge

to Pembury• Highways

Agency reorganisation

Rail

• New super franchise: Govia Thameslink– Commenced September

2014– Southern services integrated

July 2015

• South East area: Sussex Route Study

• High Speed Rail to Bexhill and Hastings

High Speed Rail

• Good business case for running High Speed Rail to Bexhill and Hastings

• Network Rail undertaking technical work

• ESCC, HBC & RDC commissioned economic assessment to support business case

• Delivery 2019 – 2024?

Aviation

• Airports Commission– Interim report end 2013– Second runway at

Gatwick shortlisted – National consultation this

autumn– Final report summer

2015

• Developing proposals for Hailsham –Eastbourne sustainable transport corridor

• Consulted on proposals for Hailsham town centre package

• Uckfield town centre package: Phase 1 on site; Phases 2 & 3 – starts next year

• Eastbourne Terminus Road improvements• Linking Communities Fund: Ringmer – Lewes

Phase 2

Local Transport Infrastructure

Local Sustainable Transport Fund

• Station Street improvements, Lewes• Station Forecourt, Lewes• A259 Newhaven – Peacehaven cycle route• Eastbourne cycle routes• Real Time Passenger Information

 

Strategic Economic Plan & Local Growth Deal

• Multi-year growth strategy for the LEP area• Specifically sets out growth plans for East Sussex • Infrastructure required to unlock growth – link to LTP &

Local Plan infrastructure priorities• Over £67m for East Sussex• Significant proportion on transport infrastructure• Augmented by funding from other sources• Freedoms and flexibilities – Highways Agency and

Network Rail

Strategic Economic Plan & Local Growth Deal

A21/A259 Bexhill/Hastings Growth CorridorScheme Amount Available

Hastings & Bexhill junction improvement package

£6m £1.5m per year from 17/18 onwards

Hastings & Bexhill walking and cycling package

£6m £2m per year from 18/19 onwards

Queensway Gateway Road £15m 15/16 & 16/17

North Bexhill Access Road £5m 17/18

TOTAL £33m

Local Sustainable Transport Fund

• Wheels to Work• Bike It programme• £684,000 Local

Sustainable Transport Fund revenue funding in 2015/16

• Fund extension of existing LSTF schemes

Strategic Economic Plan & Local Growth Deal

A7/A22 Eastbourne/South Wealden Growth Corridor

Scheme Amount Available

A22/A27 junction improvements £4m 17/18

Eastbourne/South Wealden walking & cycling package

£8.6m 15/16 & 17/18 onwards

Eastbourne town centre movement and access package

£6m £2m per year from 18/19 onwards

Hailsham – Polegate – Eastbourne Sustainable Transport Corridor

£2.1m 15/16 & 17/18

TOTAL £20.7m

Strategic Economic Plan & Local Growth Deal

NewhavenScheme Amount Available

Newhaven Port Access Road £10m 2016/17

Newhaven Flood Defences £3m £1.5m – SELEP£1.5m – C2C

2016/17

Strategic Economic Plan & Local Growth Deal

Round 2 – bidsScheme Amount Year sought for

Bexhill Enterprise Park: site infrastructure, servicing & business space

£2.6m 2014/15

Swallow Business Park: site infrastructure

£1.4m 2014/15

Sovereign Harbour Innovation Park: site infrastructure

£4.6m 2014/15

Newhaven Ring Road & Town Centre Access Package

£1m 2016/17

North Queensway Innovation Park: site infrastructure & servicing

£1m 2015/16