joy mist drilling system presented by: dave paich joy mining machinery
TRANSCRIPT
![Page 1: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/1.jpg)
JoyMist Drilling
System
Presented By:
Dave PaichJoy Mining Machinery
![Page 2: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/2.jpg)
What is Mist Drilling?
Joy’s Mist Drilling System is patented as a “Low volume
air-water drilling systems and methods”
![Page 3: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/3.jpg)
Mist Drilling• Mist Drilling is a positive displacement
method of flushing the drill hole• It uses a mixture of low pressure air and
water to flush the drill cuttings away from the drill bit
• The air and water are combined in a simple mixing chamber
• Mine supply water is used• A compressor is onboard the bolting
machine, to provide the required air supply
![Page 4: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/4.jpg)
Waterin
Pressureand flowregulators
CheckValves
MixingChamber
CheckValves
AirIn
Pressureand flowregulators
RegulatingValve
To Drill Heads
Simplified Misting Block DiagramSimplified Misting Block Diagram
![Page 5: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/5.jpg)
Joy Mist Drilling System
![Page 6: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/6.jpg)
• Over Dry Drilling – Reduction in Noise Exposure*
Mist Drilling Advantages
Dry Drilling
Avg dBA = 101.7
As much as 10 dBa reductions seen in
some cases
Mist Drilling
Avg dBA = 91.2
Dry Drilling
Avg dBA = 101.7
As much as 10 dBa reductions seen in
some cases
Mist Drilling
Avg dBA = 91.2
*InformationCourtesyof NIOSH
*InformationCourtesyof NIOSH
![Page 7: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/7.jpg)
• Over Dry Drilling – Reduction in Noise Exposure
Mist Drilling Advantages
Avg dBA = 94.6
DOSE = 0.5% per bolt
200 bolts per shift to reach 100% dose
Avg dBA = 94.6
DOSE = 0.5% per bolt
200 bolts per shift to reach 100% dose
Avg dBA = 89.4
DOSE = 0.2% per bolt
500 bolts per shift to reach 100% dose
Avg dBA = 89.4
DOSE = 0.2% per bolt
500 bolts per shift to reach 100% dose
![Page 8: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/8.jpg)
Flow DividerFlow Divider
Joy Mist Drilling System
Mist BlockMist Block
Mist BlockMist BlockTankTank
CompressorCompressor
Heat
Exchanger
Heat
Exchanger
18 GPM Hyd Oil18 GPM Hyd Oil
3 GPM3 GPM15 GPM15 GPM
Water SupplyWater Supply
120 psi 50 cfm120 psi 50 cfm
<1 GPM<1 GPM
Mist
Out
Mist
Out
![Page 9: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/9.jpg)
Joy Mist Drilling System
Bluefield Coal Show DisplaySeptember 2003
Mine Expo - Oct 2004
![Page 10: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/10.jpg)
Hydraulic Drive29”L x 20”H x 18”W
COMPRESSOR
Joy Mist Drilling System
![Page 11: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/11.jpg)
Heat Exchanger
Fan Motor
26”L x 22”H x 13”W
Joy Mist Drilling System
![Page 12: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/12.jpg)
Water Tank: 30 gal40”L x 16”Dia.
30 gal tank for onboard water supply.
Experimentation with other options
• Accumulator
• Reservior
Joy Mist Drilling System
![Page 13: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/13.jpg)
Mist
Block
Joy Mist Drilling System
16”L x 10”H x 8.5”W16”L x 10”H x 8.5”W
![Page 14: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/14.jpg)
Rotation units• Use Wet Type• Customer Supplied• Positive Seal Required
Joy Mist Drilling System
![Page 15: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/15.jpg)
Lessons from first trial:
• Steels Need to seal• Bits 5-10x life• Varying Strata Vary Thrust
Joy Mist Drilling System
![Page 16: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/16.jpg)
Joy Mist Drilling System
OptionsOptions
• Reservoir with Pump
• Accumulator
• Pilot mist valve
• Water cooled w/ over temp shutdown
• Reservoir with Pump
• Accumulator
• Pilot mist valve
• Water cooled w/ over temp shutdown
![Page 17: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/17.jpg)
System installed above ground with reservoir
System installed above ground with reservoir
Joy Mist Drilling System
![Page 18: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/18.jpg)
2nd Trial
• No Tank - 700 psi water supply• From Wet to Mist• Floor dried up
• Operators happy• Mine management happy• Trial system purchased
Joy Mist Drilling System
![Page 19: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/19.jpg)
Joy Mist Drilling System
Mist BlockMist Block
Mist BlockMist BlockTankTank
CompressorCompressor
Heat
Exchanger
Tube
Heat
Exchanger
Tube
15 GPM Hyd Oil15 GPM Hyd Oil
Transmission Fluid ATFTransmission Fluid ATF
Water SupplyWater Supply
120 psi 50 cfm120 psi 50 cfm
<1 GPM<1 GPM
Mist
Out
Mist
Out
Piston AccumulatorPiston Accumulator
High Temp
Dump Valve
High Temp
Dump Valve
Miner-Bolter Configuration
Water Cooled
Miner-Bolter Configuration
Water Cooled
![Page 20: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/20.jpg)
Joy Mist Drilling System
Miner-Bolter Configuration Installation Miner-Bolter Configuration Installation
![Page 21: Joy Mist Drilling System Presented By: Dave Paich Joy Mining Machinery](https://reader037.vdocuments.net/reader037/viewer/2022103122/56649cfa5503460f949cbca4/html5/thumbnails/21.jpg)
Mist Drilling Advantages• Wet Drilling
• Reduction in water consumption by up to 90%.
• Improved operator environment
• Improved floor and roof conditions
• Reduced moisture content in coal
• Dry Drilling• Reduced noise levels• Improved bit life saves
time and $$• Improved penetration
rates (depends on bit and roof conditions)
• Reduction in respirable dust
• Cleaner holes• Reduces impact of
moisture in overlying strata
• Reduced maintenance• Fewer components