judge mark barnett's feb. 9, 2012 order upholding hyperion air quality permit
TRANSCRIPT
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 1/11
CIRCUIT COURT OF SOUTH DAKOTA
SIXTH JUDICIAL CIRCUITHUGHES COUNTY COURTHOUSE
P.O. BOX 1238
PIERRE, SOUTH DAKOTA 57501-1238
MARK BARNETTCIRCUIT COURT JUDGE
Phone: (605) 773-4014
Fax: (605) 773-6492
February 9, 2012
Frederick W. Addison III
Amy L. Rickers
Munsch, Hardt, Koph & Harr, PC3800 Lincoln Plaza
500 N. Akard Street
Dallas, TX75201-6659
Sam E. Khoroosi
Khoroosi Law Office
300 N. Dakota Ave., Suite 405Sioux Falls, SD 57104
John H. Davidson
31275 Saginaw Ave.
Vermillion, SD 57069
Robert L. Graham
Allison A. TorrenceGabrielle Sigel
Jenner & Block
330 North Wabash Ave.
Chicago, IL 60611
Todd Meierhenry
Meierhenry & Sargent LLP315 S. Philips Ave.
Sioux Falls, SD 57104
Roxanne Giedd
Deputy Attorney General
Chief, Litigation Division
Attorney General's Office
1302 E. Highway 14, Suite 1Pierre, SD 57501
Re: Hughes County Civ No. 09-400;In Re In the Matter of the
Prevention of Significant Deterioration (PSD) Air Quality Permit
Application of Hyperion Energy Center - Hyper ion Refining LLC -
Permit #28.0701 - PSD
1
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 2/11
Hyperion proposes to construct a petroleum refinery and power plant
known as the Hyperion Energy Center, hereinafter HEC, in Union County,
South Dakota. Hyperion applied for and was issued a Prevention of
Significant Deterioration Air Quality Preconstruction Permit #28.0701- PSD
Permit, hereinafter PSD permit by the Board ofMinerals and Environment,
hereinafter the BME. Subsequent to the issuance of the PSD Permit,Hyperion and Citizens Opposed to Oil Pollution, Save Union County, and
Sierra Club, hereinafter collectively referred to as Sierra Club, appealed the
BME's findings and conclusions to this court. Thereafter, Hyperion
requested an extension of the commence construction deadline in the PSD
permit. Additionally, this court issued its order requiring the BME to take
additional evidence. A second hearing was held before the BME, which
consisted of the testimony of several live witnesses from all parties. The
BME subsequently issued an amended permit from which Hyperion and
Citizens now appeal.
BACKGROUND
Hyperion proposes to construct a petroleum refinery near Elk Point,
South Dakota. In addition to the petroleum refinery, the proposed facility
will include a power plant, referred to as the Integrated Gasification
Combined Cycleplant, hereinafter IGGC power plant.
Prior to constructing the petroleum refinery and power plant, Hyperion
is required to apply for a PSD permit. A PSD permit is required for any
regulated pollutant prior to construction of new major stationary sources in
areas designated as in attainment with the National Ambient Air Quality
Standards, hereinafter NAAQS. In South Dakota, the DENR's Air Quality
Program administers the air quality permitting as required by the Clean Air
Act as well as state and federal statutes and regulations.
In December of 2007, Hyperion submitted its PSD permit. Following
the submission ofHyperion's application of the PSD permit, there was a
period of time reserved for review and public comment for the proposed PSD
permit. Also, during this time, Sierra Club filed a Petition to Intervene in the
Contested Case Hearing, which was granted. Following a contested hearing
between the parties, the BME issued a PSD permit on August 20, 2009.
After the issuance of the PSD permit, Hyperion and Sierra Club appealed.
On June 23, 2010, Hyperion requested an extension from the DENR of
the "commence construction" deadline contained within the PSD permit. Also
on June 23, 2010, this court issued its order requiring the BME to take
addition evidence for issues related to the request for extension of
construction commencement date; the primary NAAQSfor Nitrogen Dioxide
2
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 3/11
Final Rule; the primary NAAQSfor Sulfur Dioxide Final Rule; the coker
quench water tank; any final greenhouse gas rules, and any additional
evidence regarding Best Available Control Technology determinations,
hereinafter BACT. Hyperion's application was supplemented several times,
and was complete in February 2011. DENR then proposed a Draft Amended
PSD permit which was subject to review and public comment for a period oftime. A second contested case hearing was held and, on September 16, 2011,
BME issued its Findings of Fact and Conclusions of Law and approved the
Proposed Amended Permit. Subsequently, Sierra Club filed a notice of
appeal regarding several issues with the Amended Permit. Hyperion also
filed a notice of appeal reasserting a single issue.
Sierra Club appeal the following issues:
I. "Whether the [BME's] decision to issue a PSD Permit to
Hyperion for construction of the REC should be reversed for
violating applicable federal or state air pollution control law
II. Whether the [BME's] decision to issue a PSD Permit to
Hyperion for construction of the REC should be reversed as
violating the mandatory public participation requirements
imposed under federal and state air pollution control law
III. Whether the failure ofDENR and the [BME]to require an
Environmental Impact Statement [hereinafter EIS] under the
South Dakota Environmental PolicyAct, SDCL Ch. 34A-9,with
respect to the construction ofthe REC ... should be reversed
as violating the South Dakota Environmental Policy Act ... "
Opening Brief by Sierra Club, January 13, 2010, 2-3.
IV. "Whether the [BME's] 2011 Decision to issue an Amendment
Permit and the [BME's] 2009 Decision to issue the Original
Permit should be reversed pursuant to S.D.C.L. § 1-26-36
V. Whether, even if the Original Permit did not expire as a matter
oflaw, the [BME's] 2011 Decision to issue an Amended Permit,
should be reversed pursuant to SDCL § 1-26-36because
Hyperion failed to establish satisfactory justification for the
extension until March 15, 2012 ofthe commence construction
deadline as provided in the Amended Permit
VI. Whether the [BME's] 2011 Decision should be reversed
pursuant to SDCL § 1-26-36because the [BME]concluded that
3
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 4/11
Hyperion and DENR met their burden of proving that their
Amended Permit applied BACT to all significant emissions units
at the REC, where: [there were several issues involving BACT]
VII. Whether the [BME's] 2011 Decision should be reversed
pursuant to SDCL § 1-26-36 because the [BME]concluded thatHyperion and DENR met their burden of proving that the REC
will not cause or contribute to a violation of the [NAAQS]or
PSD increments, when Hyperion and DENR's air quality
modeling: [failed to use representative metrological data and
failed to follow certain recommendations of the Environmental
Protection Agency, hereinafter the EPA]
VIII. Whether the [BME's] 2011 Decision should be reversed
pursuant to SDCL § 1-26-36 because the [BME] improperly
placed the burden on [Sierra Club], as intervening parties, to
prove that the REC will cause a violation of the NAAQS and
PSD increments, including by finding that the Citizens failed to
conduct independent air quality modeling."
Sierra Club Additional Opening Brief, November 9,2011,4-6.
Hyperion appeals the following issue:
I. "Whether the lack of evidence and support in the administrative
record for the DENR's proposed CO limit of 0.007 lb/mmBtu on
large process heaters renders the Board's findings of
achievability of this limit for the large process heaters at the
REC clearly erroneous?"
Hyperion's Brief on Appeal, November 10, 2011, 4.
STANDARD OF REVIEW
When reviewing a decision from an administrative agency, this court
must use the standard of review set forth in SDCL § 1-26-36, which states as
follows:
The court shall give great weight to the findings made and
inferences drawn by an agency on questions of fact. The court
may affirm the decision of the agency or remand the case for
further proceedings. The court may reverse or modify the
decision if substantial rights of the appellant have been
prejudiced because the administrative findings, inferences,
conclusions, or decisions are:
4
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 5/11
(1) In violation of constitutional or statutory provisions;
(2) In excess of the statutory authority of the agency;
(3) Made upon unlawful procedure;
(4) Affected by other error oflaw;
(5) Clearly erroneous in light of the entire evidence inthe record;
or
(6) Arbitrary or capricious or characterized by abuse of
discretion or clearly unwarranted exercise of
discretion.
A court shall enter its own findings of fact and conclusions of
law or may affirm the findings and conclusions entered by the
agency as part of its judgment. The circuit court may award
costs in the amount and manner specified in chapter 15-17.
Under this statute, the applicable standard of review "will vary depending on
whether the issue is one of fact or one oflaw." Orth v. Stoebner & Permann.
Const., Inc., 2006 SD 99, , - r 27, 724 NW2d 586, 592 (quoting Tischler v. United
Parcel Service, 1996 SD 98, , - r 23, 552 NW2d 597,602). "When the issue is a
question of fact, then the actions of the agency are judged by the clearly
erroneous standard; and when the issue is a question oflaw, then the actions
of the agency are fully reviewable [i.e., de novo]." Id. "Mixed questions of fact
and law are fully reviewable." Orth, 2006 SD 99, , - r 27, 724 NW2d at 592
(quoting Brown v. Douglas Sch. Dist., 2002 SD 92, , - r 9, 650 NW2d 264,268)."Adecision is clearly erroneous if, after reviewing the entire record, the
reviewing court is left with a definite and firm conviction that a mistake has
been made." Enger v. FMC 2000 SD 48, , - r 6,609 N.W.2d 132,134 (citing
Sopko v. C & R Transfer Co., Inc., 1998 SD 8, , - r 6, 575 N.W.2d 225, 228).
When an agency makes factual determinations on the basis of deposition
testimony or documentary evidence, the matter is reviewed de novo.
McKibben v. Horton Vehicle Components, Inc., 2009 SD 47, , - r 11, 767 NW2d
890, 894 (citing Truck Ins. Exchange v. CNA, 2001 SD 46, , - r 6, 624 NW2d 705,
708). "When findings of fact are made based on live testimony, the clearly
erroneous standard applies." Orth, 2006 SD 99, , - r 28, 724 NW2d at 592 (citing
Brown, 2002 SD 92, , - r 9,650 NW2d at 268).
ANALYSIS
In making its decision in this appeal, this court has thoroughly
reviewed, weighed, and educated itself on each assertion oferror presented
by Sierra Club and Hyperion and reflected upon the factual findings and
conclusions of law made by the BME. In educating itself on the issues
5
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 6/11
presented, this court has participated in three hours of oral argument and
carefully considered some 500 pages of briefs, which have been spread
between briefs on the initial appeal to this court; briefs on the motion to
remand for more evidence; and briefs on the return to the circuit court. In
short, this court has fully familiarized itself with virtually all of the
multitudinous issues raised by the parties, including arguments relating tovarious BACT issues for emitting equipment; arguments of statutory and
regulatory interpretation and application; arguments as to correct air
modeling data; claimed burden shifting; and the like.
I. Best Available Control Technology ("BACT")
A. Sierra Club's Claims
In assessing Sierra Club's assertions of error in the BME's factual
findings related to BACT for several emission sources, this court carefullyreviewed the following BACT findings for clear error: the method of analysis
used by the DENR in determining BACT; BACT limits for coke drum steam
vents; BACT for coker quench water handling system; BACT limits for
greenhouse gas for several emission units, including a BACT analysis for
greenhouse gases in process heaters, C02 vents, combined cycle combustion
turbines, small combustion sources, and a leak detection and repair program;
a cost analysis and BACT limit for process heaters for various regulated
pollutants including but not limited to, nitrogen oxides, volatile organic
compounds, particulate matter, and sulfur; BACT limit for cooling towers,
storage tanks, loading racks, the sulfur recovery plant, and the wastewater
treatment plant; BACT involving the IGCC for various regulated pollutants
and flaring; and BACT for flare control for the HEC.
This court has thoroughly and carefully assessed each of these alleged
factual errors under the clearly erroneous standard. It is apparent to this
court that the BME correctly analyzed the various expert opinions and
testimony relating to the BACT for several emission sources. This court also
finds, as did the BME, that the DENR followed a proper and adequate
method of analysis of weighing particular factors in order to find what
constituted BACT for several emission sources. The record clearly supports
theBME's factual findings relating to BACT, and, thus, this court is not left
with a definite and firm conviction that a mistake was made by the BME in
its factual findings relating to BACT.
B. Hyperion's Claim
Hyperion asserts one factual error in the BME's decision. Hyperion
argues that it was error for the BME to conclude that a CO limit of 0.007
6
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 7/11
Ib/mmBtu was BACTfor large process heaters. Instead, Hyperion asserts
that the stringent BACTlimit of 0.007 Ib/mmBtu is unattainable and instead
proposes that the BACTlimit for COfor the large process heaters should be
O.Ollb/mmBtu. In responding to Hyperion's argument, DENR argues that
Hyperion waived this issue by not arguing it at previous levels ofthis
administrative appeal.
Upon review, this court does not find that Hyperion waived its
argument regarding the COBACTlimit for large process heaters. In support
of such finding, the court notes that, even though there was no testimony at
the additional evidence hearing, Hyperion admitted into the administrative
record evidence regarding the COBACTlimit for large process heaters. In
finding no such waiver, this court will address the merits of the COBACT
limit for large process heaters argument.
In recommending the 0.0071b/mmBtu COlimit as BACTfor the largeprocess heaters, the BME reviewed and properly relied on several other
permits from other facilities in finding that the more stringent BACTlimit
(0.007 Ib/mmBtu) was achievable. It is not within this court's province to
overturn findings of fact by the BME that are clearly supported by the record.
Further, there is nothing in the record that would leave this court with a
definite and firm conviction that a mistake was made by the BME. A CO
limit of 0.007 Ib/mmBtu is, not only achievable, but BACT. Thus, the BME
did not err in its finding regarding the COBACTlimit for the large process
heaters.
H. Air Modeling
Sierra Club asserts that the BME erred when it concluded that the
HEC will not violate state and federal air quality standards. Sierra Club
argues that site specific data from Union County is more representative
meteorological data for air quality monitoring than data gathered at Sioux
City, Iowa or Sioux Falls, South Dakota. Sierra Club asserts that Hyperion
should be required to collect one full and complete year of site-specific Union
County meteorological data to use in a revised air quality modeling analysis.
Additionally, Sierra Club argues that Hyperion improperly modeled S02,
N02, and particulate matter emissions. Lastly, Sierra Club asserts that
there were significant errors in Hyperion's air quality modeling because it
failed to completely revise its air quality modeling as requested by the EPA.
In reviewing the record for factual error in Hyperion's air modeling,
this court is not left with a definite and firm conviction that a mistake was
made. Hyperion complied with state and federal air quality standards. This
court defers to the factual findings of the BME as its findings were supported
7
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 8/11
by the record. Further, the BMEwas in the best position to judge the
credibility ofwitnesses as to the appropriate air quality modeling; air
monitoring data; and representative data site. This court also finds that the
record supports the BME's findings as to the NAAQSand increment analysis
for S02, N02, and particulate matter and Hyperion's compliance with the
NAAQSfor nitrogen dioxide and sulfur dioxide.
III. Environmental Impact Statement
In arguing for the necessity of an Environmental Impact Statement,
hereinafter EIS, Sierra Club asserts that the BME had jurisdiction to require
an EIS. Further, Sierra Club argues that the REC is the type ofproject,
because of its size, that an EIS should be mandated for.
In reviewing the statutory authority and case law presented by Sierra
Club in support of its argument, this court finds, as did the BME, that an EISis not mandatory in the PSD permitting process in South Dakota. Further,
an EIS is outside of the jurisdiction of the BME. Lastly, this court finds, as
did the BME, that the DENR properly exercised it authority and discretion in
choosing not to perform an EIS. Thus, because it was not mandatory and
outside of the jurisdiction of the BME, an EIS was not required to be
performed by the DENR.
IV. Public Review and Comment
Sierra Club asserts that crucial permit information was not subject to
public review and comment. Sierra Club argues that such crucial information
pertaining to Hyperion's PSD permit, which was not subject to public review
and comment, includes the following:the disclosure ofcharacteristics ofcrude
fuel feedstock to be refined at REC; characteristics ofpetroleum coke;
identification and quantification ofair emissions occurring during the
construction of the REC; identification and quantification ofair emissions
occurring during the operation of support facilities to the REC; a startup,
shutdown, and malfunction plan; flare minimization plan; and a dust
suppression/dust prevention plan.
In agreeing with all of the BME's factual findings related to the public
review and comment on information contained within the permit, this court
finds the public was provided a meaningful opportunity and time to review
and comment on the PSD permit. Further, this court also finds that the
DENR conducted a due diligence review ofthe Application by spending
hundreds of hours reviewing and considering several thousand public
comments. This court also notes that many of Sierra Club's assertions of
error regarding public review and comment about particular permit
8
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 9/11
information, such as a startup, shutdown, and malfunction plan, is improper
at this time. The public will have an opportunity to comment and review
such information if Hyperion is allowed to apply for a Title V Operating
Permit. Thus, based on the public's meaningful opportunity to comment on
the permit and the due diligence review of the public comments by the
DENR, this court is not left with a definite and firm conviction that a mistakewas made by the BME in adopting the DENR's responses to the public
comments.
V. Construction Date Extension
Sierra Club argues that Hyperion allowed the initial permit to expire
by failing to commence construction of the HEC within the eighteen month
construction period. Further, Sierra Club argues that the filing of an
application for an extension of the permit is not enough to extend the period
of time in which the permit is still considered valid.
In assessing this argument, this court finds the arguments of Sierra
Club to be lacking in merit. Sierra Club's offered interpretation would render
the permit law in South Dakota completely unworkable in practical terms.
This court cannot read ARSD 74:36:09:02and S.D.C.L. § 1-26-28to render an
absurd result. Further, some of the cases cited by Sierra Club with regard to
this issue are of no assistance to the court. Notably, those decisions did not
involve an extension of a permit at all. Those cases simply held that once the
permit has expired, the permit is no longer valid. The situations presented in
Sierra Club's cited cases are not what the court and the parties are faced
with in this case. In this case, the application for extension was filed on June
23, 2010 before the initial eighteen months ran out, and therefore, the
application was timely and appropriate. The law and cases cited by DENR
are persuasive. The conclusions of the BMEwere well-reasoned and well-
supported, and thus, this court concludes that the filing of the extension
application for the commence construction date within the eighteen month
timeframe was timely and appropriate. Therefore, as the BME found, the
permit was not rendered invalid.
VI. Justification for Extension
Additionally, Sierra Club argues, in the alternative, that even if the
original permit was not invalid, Hyperion failed to justify the extension of the
commence construction deadline. The applicant must prove that the
extension to the commence construction deadline is justified. In arguing that
the commence construction deadline was not justified, Sierra Club argued
that none of the reasons proffered by Hyperion justified the requested
extension.
9
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 10/11
In reviewing de novo the BME's conclusions oflaw regarding the
justifications for the extension presented by Hyperion, this court concludes
that the evidence submitted in support ofHyperion's request for extension of
the commence construction deadline, supports the extension. The extension
was justified given the economic recession which caused delays in thedevelopment of large capital projects such as the HEC; the pending appellate
process regarding the future status of the permit; the addition of another
emissions unit for the HEC; and additional NAAQSanalyses for two more
regulated pollutants. Given the well-documented evidence of such
justifications, this court concludes that Hyperion's extension ofthe commence
construction deadline was justified.
VII. Burdens of Proof Imposed on the Parties
Sierra Club asserted that, based on several findings of fact, the BMEimproperly shifted the burden of proof regarding the PSD permit on to the
Sierra Club. During oral argument, Sierra Club directed the court's attention
to several findings of fact in which it believed the BME improperly shifted the
burden ofproof.
In addressing this argument, this court concludes that this "burden
shifting" argument is without merit. This court has scoured the record, the
factual findings by the BME, and the conclusions of law by the BME for
anything to legitimately suggest that the BME improperly shifted the burden
ofproof. Based on its own review of the record, findings, conclusions, as well
as its review of the specific factual findings as highlighted by Sierra Club in
oral arguments, the court finds that the BME did not improperly shift the
burden onto Sierra Club. The BMEwas merely discussing how much weight
to give to various contentions which Sierra Club raised but did not support
with evidence. It is readily apparent to the court that the burden was placed
on the right parties at all times, and thus this court will not overturn any of
the BME's factual findings or conclusions of law on the basis of Sierra Club's
claim that the burden of proving such findings and conclusions was borne by
the Sierra Club.
CONCLUSION
As stated above, the court has carefully reviewed some 500 pages,
which have been spread between briefs on the initial appeal to this court;
briefs on the motion to remand for more evidence; and briefs on the return to
this court. Additionally, this court spent three hours closely questioning
skilled counsel at oral argument. The court has thoroughly reviewed,
weighed, and educated itself on each assertion of error presented by the
10
5/13/2018 Judge Mark Barnett's Feb. 9, 2012 order upholding Hyperion air quality permit - slidepdf.com
http://slidepdf.com/reader/full/judge-mark-barnetts-feb-9-2012-order-upholding-hyperion-air-quality-permit 11/11
Sierra Club and Hyperion and reflected upon the findings and conclusions by
the BME.
This court regularly issues lengthy memorandum decisions. In the
present case, however, the court is of the view that drafting such a lengthy
memorandum decision would be contrary to judicial economy, when this courtis firmly convinced that the underlying decision has been reached in
accordance with all applicable statutes, administrative regulations, and case
law. This court is further convinced that the prevailing party at the
administrative hearing level, the DENR, has correctly addressed all of the
issues in its briefs to this court. The court is impressed that "great deference"
in this case is an unneeded luxury or presumption - no deference at all is
necessary to find that the BME's final decisions were well-founded. Ifgreat
deference were factored in, there would be no question that the decision
should stand. True, there are heated disputes abounding in such categories
as the appropriate BACTfor a given emitter, but these disputes are oftencentered upon factual arguments between experts; credibility; and weight of
the evidence, as perceived by the BME. Thus, it is not this court's function to
second guess fact findings of theBME, which do have more than adequate
evidentiary support.
This court is unable to find any error in the findings of fact and
conclusions of law of the BME. The issues presented by Sierra Club and
Hyperion were all correctly addressed by the DENR in its various briefs to
this court. Accordingly, the DENR shall prepare a complete set of Findings of
Fact and Conclusions of Law for this court's review, which shall serially
address all issues raised by Sierra Club and Hyperion. Sierra Club and
Hyperion will be expected to submit their own competing Findings,
Conclusions, and objections. This court fully intends to carefully "police"all
parties' Findings and Conclusions in order to see that they are correct, or
amend as need be. The court will count on the parties to point out any
proposal that is not supported in law or the record. Therefore, the decision of
the BME is AFFIRMED in its entirety.
Sincerely,
The Honorable Mark Barnett
Circuit Court Judge
11