JULY 16, 2015 MAJOR PROJECTS Project City Project Name Date Time Online 71 Sacramento Main Electrical Substation Expansion 4209 7/16 2PM Online 18 Tracy Multi Family Plex 7/16 4PM Online 32 Delano/Wasco North Kern State Prison/Wasco State Prison Health Care Facility 7/16 2PM Online 134 Hayward Cherryland Fire Station #13024 7/17 2PM Online 55 San Mateo La Scala Condominiums 7/17 5PM 57 Redwood City La Palma Single Family Homes 7/17 2PM Online 17 So San Francisco Pad Building No. 2 7/17 2PM Online 65 Santa Cruz Courtyard By Marriott 7/17 4PM Online 66 Watsonville Fairfield Inn Suites (FFIS) 7/17 4PM 13 Castro Valley Renovation Of Castro Valley Swim Center 7/20 1:30PM 100 Santa Clara Main Bldg Replacement PH 2 Increment 2 Mission College 7/21 10AM 100 Santa Clara Main Bldg Replacement PH 2 Increment 2 Mission College 7/21 1PM Online 5 Hayward 21 st Century Library & Community Learning Center 7/21 2PM Online 57 Martinez Tenant Improvements @ Health Services Department 7/21 2PM Online 11 Watsonville Watsonville HS Relocatables Increment 2 Sitework & Utilities 7/21 2PM 7E Santa Cruz Co 1400 Emeline Reception Area Remodel Project #14C1-010 7/21 2:30PM Online 60 Davis Chemistry Rooms 1, 3 & 92 Remodel UCD 9525100 7/21 2PM 100 Santa Clara Main Bldg Replacement PH 2 Increment 2 Mission College 7/22 10AM 100 Santa Clara Main Bldg Replacement PH 2 Increment 2 Mission College 7/22 1PM 109E Santa Cruz Co Medium Security Facility Courtyard Repair Project #14C1-009 7/22 2:30PM Online 77 San Francisco E.S.E.R. Bond No. 2014, Roof, HVAC & Emergency Gen 9662A-1 7/22 2:30PM Online 52 Windsor Esposti Park Place 7/22 2PM Online 64 Martinez Renovations & Remodeling @ Contra Costa Finance Building 7/23 2PM Online 12 Soledad Correctional Training Facility Salinas Valley State Prison 7/23 2PM 8 Cupertino TD Ameritade – Main Street 7/24 11AM Online 125 Oakland Bart Earthquake Safety Program Aerial Structures Line A 7/28 2PM 22 Santa Cruz Co Mosquito Abatement & Vector Control Office Remodel 14C1-008 7/28 2:30PM Online 40 Dublin LAVTA Rapid Bus Shelter 7/28 2PM 5 Milpitas Milpitas Sports Center Pool Repair Project 3408 & 5103 7/28 2PM Online 30 Hollister West Hills Water Treatment Plant 7/29 2PM 121E San Jose Huff Gardens Apartments Rehab #1506-002 7/30 3:15PM 122E San Jose Helzer Court Apartments Rehab #1506-001 7/30 3PM 20 San Jose MDF Relocation Evergreen Valley College G2010.0014 7/30 3PM Online 8 Tehachapi California Correctional Institution CDCR-HCFIP 6000008 7/30 2PM Online 16 San Ramon San Ramon Library Expansion & Renovation 7/30 2PM Online 50 San Mateo Classic @ San Mateo Tilton Place 7/31 5PM Online 89 Berkeley Main Building South Wing Space Modifications & Renovations 8/3 5PM Online 14 Antioch Sunset Booster Pump Station Replacement PW 355-BP 8/4 2PM 27E Berkeley Fire Station #1 Renovation 15-10907-C 8/4 2PM

Upload: vanquynh

Post on 10-May-2018

220 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

 

JULY 16, 2015 MAJOR PROJECTS

Project City Project Name Date TimeOnline 71 Sacramento Main Electrical Substation Expansion 4209 7/16 2PMOnline 18 Tracy Multi Family Plex 7/16 4PMOnline 32 Delano/Wasco North Kern State Prison/Wasco State Prison Health Care Facility 7/16 2PMOnline 134 Hayward Cherryland Fire Station #13024 7/17 2PMOnline 55 San Mateo La Scala Condominiums 7/17 5PM57 Redwood City La Palma Single Family Homes 7/17 2PMOnline 17 So San Francisco Pad Building No. 2 7/17 2PMOnline 65 Santa Cruz Courtyard By Marriott 7/17 4PMOnline 66 Watsonville Fairfield Inn Suites (FFIS) 7/17 4PM13 Castro Valley Renovation Of Castro Valley Swim Center 7/20 1:30PM100 Santa Clara Main Bldg Replacement PH 2 Increment 2 Mission College 7/21 10AM100 Santa Clara Main Bldg Replacement PH 2 Increment 2 Mission College 7/21 1PMOnline 5 Hayward 21st Century Library & Community Learning Center 7/21 2PMOnline 57 Martinez Tenant Improvements @ Health Services Department 7/21 2PMOnline 11 Watsonville Watsonville HS Relocatables Increment 2 Sitework & Utilities 7/21 2PM7E Santa Cruz Co 1400 Emeline Reception Area Remodel Project #14C1-010 7/21 2:30PMOnline 60 Davis Chemistry Rooms 1, 3 & 92 Remodel UCD 9525100 7/21 2PM100 Santa Clara Main Bldg Replacement PH 2 Increment 2 Mission College 7/22 10AM100 Santa Clara Main Bldg Replacement PH 2 Increment 2 Mission College 7/22 1PM109E Santa Cruz Co Medium Security Facility Courtyard Repair Project #14C1-009 7/22 2:30PMOnline 77 San Francisco E.S.E.R. Bond No. 2014, Roof, HVAC & Emergency Gen 9662A-1 7/22 2:30PMOnline 52 Windsor Esposti Park Place 7/22 2PMOnline 64 Martinez Renovations & Remodeling @ Contra Costa Finance Building 7/23 2PMOnline 12 Soledad Correctional Training Facility Salinas Valley State Prison 7/23 2PM8 Cupertino TD Ameritade – Main Street 7/24 11AMOnline 125 Oakland Bart Earthquake Safety Program Aerial Structures Line A 7/28 2PM22 Santa Cruz Co Mosquito Abatement & Vector Control Office Remodel 14C1-008 7/28 2:30PMOnline 40 Dublin LAVTA Rapid Bus Shelter 7/28 2PM5 Milpitas Milpitas Sports Center Pool Repair Project 3408 & 5103 7/28 2PMOnline 30 Hollister West Hills Water Treatment Plant 7/29 2PM121E San Jose Huff Gardens Apartments Rehab #1506-002 7/30 3:15PM122E San Jose Helzer Court Apartments Rehab #1506-001 7/30 3PM20 San Jose MDF Relocation Evergreen Valley College G2010.0014 7/30 3PMOnline 8 Tehachapi California Correctional Institution CDCR-HCFIP 6000008 7/30 2PMOnline 16 San Ramon San Ramon Library Expansion & Renovation 7/30 2PMOnline 50 San Mateo Classic @ San Mateo Tilton Place 7/31 5PMOnline 89 Berkeley Main Building South Wing Space Modifications & Renovations 8/3 5PMOnline 14 Antioch Sunset Booster Pump Station Replacement PW 355-BP 8/4 2PM27E Berkeley Fire Station #1 Renovation 15-10907-C 8/4 2PM

Page 2: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

128E Oakland Civic Center Station Room 108 Renovation Bart 17AG-150 8/4 2PMOnline 51 Dublin Dublin Veterans & Family Housing 8/4 2PMOnline 27 So San Francisco Grand Avenue Library Renovation 8/6 2PMOnline 45 Oakland Bart Earthquake Safety Program Fruitvale Station & Coliseum 8/11 2PMOnline 28 San Francisco Pier 31 Building & Roof Repair Project 2762 8/11 10:30AM58 San Jose Building 2 Berger Drive Seismic Upgrade 8/13 2PMOnline 79 Newman Newman Skate Plaza 8/18 2PMOnline 13 Jamestown Sierra Conservation Center CDCR-HCFIP 6000001829 8/20 2PMOnline 93 Fresno Fulton Mall Reconstruction Proj Sewer & Water Mains In Merced 8/25 3PM

To receive the latest updated bid information, please visit www.onlineplanservice.com

To subscribe to our online planroom, please call the exchange or download forms from our website.

http://www.bxscco.com/online-plans/

Page 3: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

2015 Board of Directors

PRESIDENT: Ben Cooper, Commercial Door 408-727-5027 VICE PRESIDENT: Scott Hutts, Black Diamond Management Group, LLC 408-440-9582 SEC/TREASURER: Mark Idemoto, Stevens Creek Quarry 408-640-9378

PAST PRESIDENT: Dawna Cilluffo, DC Law Corporation 408-988-7946 DIRECTORS: Burt Schraga, Bell Electric 408-727-2355

Carol Wagner, Abbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions 408-982-5112 Stephanie Rocha, Miller Morton Caillat and Nevis 408-292-1765 Oskar Kabali, Kal Construction Inc. 408-988-1110 Shawna Alvarado, O’Donnell Plastering 408-988-4965

STAFF: Michael Miller, Executive Director and Safety Contact Mary Fortin, Manager Kanani Fonseca, Planroom Coordinator Noreen Finegan, Admin. Asst. Nancy Cordoba, Internet Coordinator Theresa Touchatt, Internet Coordinator

Page 4: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

PROJECTS OUT TO BID – INFORMATION UPDATED 07-16-2015 Please verify your information with the plans and specifications and addenda. Information contained in this Bulletin is obtained with the realization that you depend on its accuracy. Every reasonable effort is made to procure the most current information possible. The Builders Exchange of Santa Clara County does not make any guarantee or warranty, or assume any liability, legal or moral, or other responsibilities by reason of the compiled and published information. THE DEADLINE FOR INFORMATION TUESDAY AT 8AM

#ONLINE 71 SACRAMENTO 7/16 2PM MAIN ELECTRICAL SUBSTATION EXPANSION 4209 (ONLINE ONLY)

PROJ MGR: Co, DPW 916-874-6544 PROJ INFO: Substation expansion PRE BID: 6/15 10AM ENG EST: $1,876,000.00 ADDENDUM: 1 (6-3), 2 (6-22), 3 d/c (6-25), 4 (7-10) Auburn Constructors, Inc. Sacramento 916-924-0344 FX 934-1800Blocka Construction Inc. Fremont 510-657-3686 FX 657-3688C. Overaa & Co. Richmond 510-234-0926 FX 237-2435Clyde G. Steagall, Inc. Loomis 916-652-1700 FX 652-1702D.W. Nicholson Corporation Hayward 510-887-0900 FX 783-9948Kiewit Infrastructure West Co. Fairfield 707-439-7300 FX 439-7301Shimmick Construction Company, Inc. Oakland 510-777-5000 FX 777-5099The Ryan Company Nortan MA 508-742-2500 FX 742-2540

#ONLINE 18 TRACY 7/16 4PM MULTI FAMILY PLEX (ONLINE ONLY) PROJ MGR: See Bidding General For Questions Plans: DM Alegre Construction, Tracy 209-835-0243 FX 209-

835-4126 PROJ INFO: Construct multi plex structures; 7 buildings; 14 units including sitework DM Alegre Construction Tracy 209-835-0243 FX 835-4126

#ONLINE 32 DELANO / WASCO 7/16 2PM NORTH KERN STATE PRISON / WASCO STATE PRISON HEALTH CARE FACILITY IMPROVEMENT PROGRAM - NKSP / WSP HCFIP 6000001792 (ONLINE ONLY)

PROJ MGR: CDCR 916-255-3029 Nina Martinez PROJ INFO: New buildings PRE BID: Mandatory 6/3 9AM ENG EST: $53.5 million ADDENDUM: 1 (6-12), 2 (6-12), 3 (6-26), 4 (7-6), 5 d/c (7-9) Bernards Fresno 559-420-7505 FX 412-4744Broward Builders, Inc. Woodland 530-666-5635 FX 666-5723Colombo Construction Bakersfield 661-316-0100 FX 316-0101Lewis C. Nelson & Sons, Inc. Salma 559-896-1443 FX 896-8609Pinner Construction Anaheim 714-490-4000 FX 490-4016S.J. Amoroso Construction Co. Costa Mesa 714-433-2326 FX 433-2329Soltek Pacific Construction Co. San Diego 619-296-6247 FX 296-4314Stronghold Engineering Riverside 951-684-9303 FX 684-3813

Page 5: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#ONLINE 134 HAYWARD 7/17 2PM CHERRYLAND FIRE STATION #13024 (ONLINE ONLY)

PROJ MGR: Co, GSA 510-272-3753 PROJ INFO: Construction of a new fire station on two parcels PRE BID: Mandatory 5/15 1PM ENG EST: $5.5 million ADDENDUM: 1 (5-29), 2 d/c (6-16), 3 d/c (7-7) Alten Construction Richmond 510-234-4200 FX 234-4221Arntz Builders Novato 415-382-1188 FX 883-7529Agbayani Construction Daly City 650-994-9380 FX 415-665-9470Calstate Construction Fremont 510-657-1800 FX 657-1810Gonsalves & Stronck Construction San Carlos 650-802-2960 FX 802-2970JUV Inc. Oakland 510-836-1300 FX 836-1301Pacific-Mountain Contractors Concord 925-603-2652 FX 687-8430Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705Thompson Builders Novato 415-456-8972 FX 459-0665Zovich Construction Hayward 510-784-1273 FX 784-0173

#ONLINE 55 SAN MATEO 7/17 5PM LA SCALA CONDOMINIUMS (ONLINE ONLY) PROJ MGR: See Bidding General For Questions Plans: Michael Roberts Construction, Campbell 408-374-

3662 FX 408-374-3667 PROJ INFO: 32 walk up condos built on concrete slab on grade Michael Roberts Construction Campbell 408-374-3662 FX 374-3667

#57 REDWOOD CITY 7/17 2PM LA PALMA SINGLE FAMILY HOMES PROJ MGR: See Bidding General For Questions Plans: Nexgen Builders, E Palo Alto 650-322-5800 FX 650-

322-5806 PROJ INFO: Twelve new single family homes ADDENDUM: 1 (7-14) Nexgen Builders E Palo Alto 650-322-5800 FX 322-5806

#ONLINE 17 SO SAN FRANCISCO 7/17 2PM PAD BUILDING NO. 2 (ONLINE ONLY) PROJ MGR: See Bidding General For Questions Plans: SD Deacon, Citrus Heights 916-969-0900 FX 916-

735-0800 PROJ INFO: New 6,057 sf pad building SD Deacon Citrus Heights 916-969-0900 FX 735-0800

#ONLINE 65 SANTA CRUZ 7/17 4PM COURTYARD BY MARRIOTT (ONLINE ONLY) PROJ MGR: See Bidding General For Questions Plans: M-13 Construction, Springville UT Troy Baker

email:[email protected] PROJ INFO: New-ground up hotel, underground parking M-13 Construction Springville UT 000-000-0000 FX 000-0000

#ONLINE 66 SANTA CRUZ 7/17 4PM FAIRFIELD INN SUITES (FFIS) (ONLINE ONLY) PROJ MGR: See Bidding General For Questions Plans: M-13 Construction, Springville UT Troy Baker

email:[email protected] PROJ INFO: New ground up 4 story 90 room hotel w / parking garage M-13 Construction Springville UT 000-000-0000 FX 000-0000

Page 6: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#13 CASTRO VALLEY 7/20 1:30PM RENOVATION OF CASTRO VALLEY SWIM CENTER

PROJ MGR: City, Engng 510-881-6715 PROJ INFO: Renovation PRE BID: Mandatory 7/2 10AM ADDENDUM: 1 (7-7) Agbayani Construction Daly City 650-994-9380 FX 415-665-9470Argo Construction Inc. San Francisco 415-850-0857 FX 650-733-7127B-Side Inc. Oakland 510-451-7527 FX 451-7517Calstate Construction Fremont 510-657-1800 FX 657-1810CWS Construction Group Inc. Novato 415-599-5585 FX 209-0228ICC General Construction Inc. Sunnyvale 408-733-6656 FX 733-6657Pacific-Mountain Contractors Pittsburg 925-603-2652 FX 687-8430Romkon Inc. San Francisco 415-525-4432 FX 529-2073Sausal Corporation San Leandro 510-568-6600 FX 671-0002Strawn Construction, Inc. San Jose 408-286-1299 FX 286-1288Tricon Construction Rancho Cordova 916-638-9866 FX 638-9867W.A. Thomas Company Inc. Martinez 925-228-9600 FX 228-6932Waterworks Industries Windsor 707-837-7900 FX 837-7997

#100 SANTA CLARA 7/21 10AM MAIN BUILDING REPLACEMENT PH 2 INCREMENT 2 MISSION COLLEGE BID #13-1415

PROJ MGR: Gilbane 775-691-8454 Shaik Sihabuddin PROJ INFO: BP #03A concrete, #05A steel superstructure, #05B miscellaneous metals, #06A millwork &

interior panels, #07A roofing PRE BID: Mandatory 6/16 & 6/18 10AM & 6/25 1:30PM ENG EST: $51 million ADDENDUM: 1 (6-22), 2 (7-7), 3 (7-15) Beals Martin Redwood City 650-364-8141 FX 367-7645Best Contracting Services Hayward 510-886-7240 FX 886-7322Bobo Construction, Inc. Sacramento 916-383-7777 FX 383-1681Cal Pacific Construction Pacifica 650-557-1238 FX 557-1239Calstate Construction Fremont 510-657-1800 FX 657-1810Galeb Paving Saratoga 408-253-4747 FX 253-4753Granite Rock San Jose 408-574-1400 FX 365-9548Guerra Construction Group Santa Clara 408-279-2027 FX 279-2044Lewis & Tibbitts San Jose 408-925-0220 FX 925-0245Robert A. Bothman San Jose 408-279-2277 FX 279-2286Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705Suarez & Munoz Construction Hayward 510-782-6065 FX 782-6078Swenson & Associates Campbell 408-866-7600 FX 866-7692T.B. Penick & Sons, Inc. San Diego 858-558-1800 FX 558-1800Tarlton & Sons Inc. Fresno 805-473-8100 FX 473-8188Teichert Construction Pleasanton 925-621-5704 FX 621-5799Urate & Sons Sacramento 916-638-5364 FX 638-4375Water Rock Construction Walnut Creek 510-671-2093 FX 227-5495

Page 7: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#100 SANTA CLARA 7/21 1PM MAIN BUILDING REPLACEMENT PH 2 INCREMENT 2 MISSION COLLEGE BID #13-1415

PROJ MGR: Gilbane 775-691-8454 Shaik Sihabuddin PROJ INFO: BP #07B, metal panels, #08B glass & glazing, #09A drywall & plaster, #09B carpet & resilient

flooring, #09C ceramic tile, #09D acoustical ceiling PRE BID: Mandatory 6/16 & 6/18 10AM & 6/25 1:30PM ENG EST: $51 million ADDENDUM: 1 (6-22), 2 (7-7), 3 (7-15) Beals Martin Redwood City 650-364-8141 FX 367-7645Best Contracting Services Hayward 510-886-7240 FX 886-7322Bobo Construction, Inc. Sacramento 916-383-7777 FX 383-1681Cal Pacific Construction Pacifica 650-557-1238 FX 557-1239Calstate Construction Fremont 510-657-1800 FX 657-1810Galeb Paving Saratoga 408-253-4747 FX 253-4753Granite Rock San Jose 408-574-1400 FX 365-9548Guerra Construction Group Santa Clara 408-279-2027 FX 279-2044Lewis & Tibbitts San Jose 408-925-0220 FX 925-0245Robert A. Bothman San Jose 408-279-2277 FX 279-2286Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705Suarez & Munoz Construction Hayward 510-782-6065 FX 782-6078Swenson & Associates Campbell 408-866-7600 FX 866-7692T.B. Penick & Sons, Inc. San Diego 858-558-1800 FX 558-1800Tarlton & Sons Inc. Fresno 805-473-8100 FX 473-8188Teichert Construction Pleasanton 925-621-5704 FX 621-5799Urate & Sons Sacramento 916-638-5364 FX 638-4375Water Rock Construction Walnut Creek 510-671-2093 FX 227-5495 #ONLINE 5 HAYWARD 7/21 2PM 21ST CENTURY LIBRARY & COMMUNITY

COLLEGE LEARNING CENTER (ONLINE ONLY) PROJ MGR: City, Engng 510-583-4738 PROJ INFO: New 3 story library-building & related sitework PRE BID: 6/10 2:30PM ENG EST: $46,500,000.00 ADDENDUM: 1 (6-10), 2 (6-17), 3 d & t/c (6-18), 4 (6-25), 5 (7-15) Alten Construction, Inc. Richmond 510-234-4200 FX 234-4221Arntz Builders, Inc. Novato 415-382-1188 FX 883-7529C. Overaa Construction Richmond 510-234-0926 FX 237-2435Lathrop Construction Benicia 707-746-8000 FX 746-8080Hensel Phelps Construction Co. San Jose 408-452-1800 FX 452-1855Roebbelen Contracting, Inc. El Dorado Hills 916-939-1110 FX 939-4027S.J. Amoroso Construction Co., Inc. Redwood Shores 650-654-1900 FX 654-9002T.B. Penick & Sons, Inc. San Diego 858-558-1800 FX 558-1800USS Cal Builders Stanton 714-828-4882 FX 503-6805Thompson Builders Novato 415-456-8972 FX 459-0665Zovich Construction Hayward 510-784-1273 FX 784-0173

Page 8: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#ONLINE 57 MARTINEZ 7/21 2PM TENANT IMPROVEMENTS @ HEALTH SERVICES DEPARTMENT REBID (ONLINE ONLY)

PROJ MGR: Contra Costa Co, DPW 925-313-2000 PROJ INFO: Limited demolition, architectural and electrical improvements, and modifications such as wall

additions and alterations, painting, floor coverings, doors and hardware, lighting, low voltage, and related work

PRE BID: 7/1 1:30PM ENG EST: $294,000.00 J. Walt Construction Woodland 916-826-8665 FX 530-402-1903T. Amaral Done Right Construction Livermore 925-989-0871 FX 454-1533Vila Construction Richmond 510-236-9111 FX 236-4979 #ONLINE 11 WATSONVILLE 7/21 2PM WATSONVILLE HIGH SCHOOL RELOCATABLES

INCREMENT 2 SITEWORK & UNDERGROUND UTILITIES (ONLINE ONLY)

PROJ MGR: Pajaro Valley Unified School District, 831-786-2100 xt 2557 PROJ INFO: Two story modular classroom building, sitework & underground utilities PRE BID: Mandatory 7/1 10AM ENG EST: $935,225.00 ADDENDUM: 1 (7-15) Calstate Construction Fremont 510-657-1800 FX 657-1810CRW Industries, Inc. Scotts Valley 831-426-0743 FX 466-9597Don Chapin Co Salinas 831-449-4273 FX 449-0700Guerra Construction Group Santa Clara 408-279-2027 FX 279-2044Seward L. Schreder Construction Redding 530-229-0001 FX 229-0070Strawn Construction San Jose 408-289-1299 FX 286-1288Tombleson Inc. Salinas 831-422-9696 FX 422-0566 #107E SANTA CRUZ CO 7/21 2:30PM 1400 EMELINE RECEPTION AREA REMODEL

PROJECT #14C1-010 PROJ MGR: Co, General Services 408-454-2210 PROJ INFO: Remodel children’s mental health / adult health reception areas PRE BID: Required Pre Bid 7/8 10AM ENG EST: $74,750.00 Alaniz Construction Gilroy 408-375-0401 FX 465-5346Cal West Construction Gilroy 408-355-0951 FX 000-0000Castlewood Construction, Co., Inc. San Martin 408-887-3294 FX 683-7215CRW Industries, Inc. Scotts Valley 831-426-0743 FX 466-9597Innovation Construction San Leandro 510-777-1877 FX 777-1088Knowlton Construction Freedom 831-722-1730 FX 722-3084Phillips Construction Santa Cruz 831-818-6290 FX 000-0000

Page 9: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#ONLINE 60 DAVIS 7/21 2PM CHEMISTRY ROOMS 1, 3 & 92 REMODEL UCD 9525100 (ONLINE ONLY)

PROJ MGR: UCD 530-754-1021 PROJ INFO: Remodel PRE BID: Mandatory 7/9 2PM ENG EST: $1.1 million Abide Builders, Inc. W Sacramento 916-375-1009 FX 375-1049Airco Mechanical Sacramento 916-381-4523 FX 386-0350American River Construction, Inc. El Dorado 530-621-1785 FX 621-0360B.C.M. Construction Chico 530-342-1722 FX 342-1768Bobo Construction Inc. Sacramento 916-383-7777 FX 383-1681Cameron Builders, Inc. Moraga 925-377-7400 FX 377-7404Diede Construction Inc. Lodi 209-369-8255 FX 368-0600Divison 5-15, Inc. Gold River 916-638-1520 FX 638-1521 #100 SANTA CLARA 7/22 10AM MAIN BUILDING REPLACEMENT PH 2

INCREMENT 2 MISSION COLLEGE BID #13-1415 PROJ MGR: Gilbane 775-691-8454 Shaik Sihabuddin PROJ INFO: BP #10A general trades, #14A elevators, #21A fire protect, #22A plumbing, 23A HVAC, controls

& TAB PRE BID: Mandatory 6/16 & 6/18 10AM & 6/25 1:30PM ENG EST: $51 million ADDENDUM: 1 (6-22), 2 (7-7), 3 (7-15) Beals Martin Redwood City 650-364-8141 FX 367-7645Best Contracting Services Hayward 510-886-7240 FX 886-7322Bobo Construction, Inc. Sacramento 916-383-7777 FX 383-1681Cal Pacific Construction Pacifica 650-557-1238 FX 557-1239Calstate Construction Fremont 510-657-1800 FX 657-1810Galeb Paving Saratoga 408-253-4747 FX 253-4753Granite Rock San Jose 408-574-1400 FX 365-9548Guerra Construction Group Santa Clara 408-279-2027 FX 279-2044Lewis & Tibbitts San Jose 408-925-0220 FX 925-0245Robert A. Bothman San Jose 408-279-2277 FX 279-2286Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705Suarez & Munoz Construction Hayward 510-782-6065 FX 782-6078Swenson & Associates Campbell 408-866-7600 FX 866-7692T.B. Penick & Sons, Inc. San Diego 858-558-1800 FX 558-1800Tarlton & Sons Inc. Fresno 805-473-8100 FX 473-8188Teichert Construction Pleasanton 925-621-5704 FX 621-5799Urate & Sons Sacramento 916-638-5364 FX 638-4375Water Rock Construction Walnut Creek 510-671-2093 FX 227-5495

Page 10: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#100 SANTA CLARA 7/22 1PM MAIN BUILDING REPLACEMENT PH 2 INCREMENT 2 MISSION COLLEGE BID #13-1415

PROJ MGR: Gilbane 775-691-8454 Shaik Sihabuddin PROJ INFO: BP #26A electrical & special systems, #31A earthwork & underground utilities, #31B AC paving &

striping, #31C site concrete, #32A landscaping & irrigation PRE BID: Mandatory 6/16 & 6/18 10AM & 6/25 1:30PM ENG EST: $51 million ADDENDUM: 1 (6-22), 2 (7-7), 3 (7-15) Beals Martin Redwood City 650-364-8141 FX 367-7645Best Contracting Services Hayward 510-886-7240 FX 886-7322Bobo Construction, Inc. Sacramento 916-383-7777 FX 383-1681Cal Pacific Construction Pacifica 650-557-1238 FX 557-1239Calstate Construction Fremont 510-657-1800 FX 657-1810Galeb Paving Saratoga 408-253-4747 FX 253-4753Granite Rock San Jose 408-574-1400 FX 365-9548Guerra Construction Group Santa Clara 408-279-2027 FX 279-2044Lewis & Tibbitts San Jose 408-925-0220 FX 925-0245Robert A. Bothman San Jose 408-279-2277 FX 279-2286Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705Suarez & Munoz Construction Hayward 510-782-6065 FX 782-6078Swenson & Associates Campbell 408-866-7600 FX 866-7692T.B. Penick & Sons, Inc. San Diego 858-558-1800 FX 558-1800Tarlton & Sons Inc. Fresno 805-473-8100 FX 473-8188Teichert Construction Pleasanton 925-621-5704 FX 621-5799Urate & Sons Sacramento 916-638-5364 FX 638-4375Water Rock Construction Walnut Creek 510-671-2093 FX 227-5495 #109E SANTA CRUZ CO 7/22 2:30PM MEDIUM SECURITY FACILITY COURTYARD

REPAIR PROJECT #14C1-009 PROJ MGR: Co, General Services 831-454-2210 PROJ INFO: Repair & refinish existing steel framing around courtyard as well as install new doors PRE BID: Require Pre Bid 7/9 10AM ENG EST: $85,000.00 AL-Bana Construction Castroville 831-661-6181 FX 661-6161CA West Construction Gilroy 408-355-0951 FX 000-0000Castlewood Construction Co., Inc. San Martin 408-683-7215 FX 683-7215Innovation Construction San Leandro 510-777-1877 FX 777-1088Knowlton Construction Freedom 831-722-1730 FX 722-3084Roebbelen Construction El Dorado Hills 916-939-1110 FX 939-4027

Page 11: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#ONLINE 77 SAN FRANCISCO 7/22 2:30PM E.S.E.R. BOND NO. 2014, ROOF, HVAC & EMERGENCY GENERATOR REPLACEMENT FIRE STATION 3 9662A-1 (ONLINE ONLY)

PROJ MGR: City & Co, DPW 415-554-6229 PROJ INFO: Removing & replacing roofing, HVAC, emergency generator, skylights PRE BID: 7/9 9AM ENG EST: $760,000.00 Blocka Construction, Inc. Fremont 510-657-3686 FX 657-3688CF Contracting, Inc. San Francisco 415-721-7160 FX 296-6437EF Brett & Company, Inc. San Francisco 415-524-8351 FX 524-8349KLW Construction, Inc. San Francisco 415-720-6670 FX 593-6671KCK Builders, Inc. San Francisco 415-459-8698 FX 453-9250Ranis Construction & Electric, Inc. San Francisco 415-469-5800 FX 206-1480Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705Roebuck Construction San Francisco 415-255-1506 FX 255-1508Stronger Building Services Hayward 510-487-8363 FX 487-8246Svala Construction Inc. San Francisco 415-850-1308 FX 901-0466Swinerton Builders San Francisco 415-617-1446 FX 877-349-7167 #ONLINE 52 WINDSOR 7/22 2PM ESPOSTI PARK PLACE (ONLINE ONLY) PROJ MGR: See Bidding General For Questions Plans: Midstate Construction, Petaluma 707-762-3200 FX

707-762-0700 PROJ INFO: New; three wood framed buildings; two three story 14 unit apartment buildings & one 3 story 8

unit apartment building ADDENDUM: 1 (7-15) MEMO: #1 d/c (7-13) Midstate Construction Petaluma 707-762-3200 FX 762-0700 #ONLINE 64 MARTINEZ 7/23 2PM RENOVATIONS & REMODELING @ CONTRA

COSTA FINANCE BUILDING (ONLINE ONLY) PROJ MGR: Contra Costa Co, DPW 925-313-2000 PROJ INFO: New roofing, repairing/replacing sheet metal cornices and parapets, cleaning and repointing

masonry, entry door/area improvements, painting, new accessible toilets, drinking fountains, path of travel improvements, providing new electrical switchgear, providing new access ladder, installing fire sprinkler system, performing center-core reinforcement of exterior walls for seismic upgrades, replacing counter areas and conducting work while building is occupied.

PRE BID: 7/1 1:30PM ENG EST: $7 million ADDENDUM: 1 (7-10), 2 (7-15) Alten Construction, Inc. Richmond 510-234-4200 FX 234-4221B.B.I. Construction Oakland 510-286-8200 FX 286-8210Swinerton Builders Santa Clara 408-454-2022 FX 877-349-7167Taber Construction, Inc. Concord 925-682-6133 FX 682-6122Turner Construction Company San Jose 408-295-7598 FX 295-7698Vila Construction Richmond 510-236-9111 FX 236-4979Thompson Builders Novato 415-456-8972 FX 459-0665

Page 12: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#ONLINE 12 SOLEDAD 7/23 2PM CORRECTIONAL TRAINING FACILITY SALINAS VALLEY STATE PRISON HCFIP 6000001802 (ONLINE ONLY)

PROJ MGR: CDCR Tracey Morrison email: [email protected] PROJ INFO: New building addition, renovations, accessible path of travel, infrastructure upgrades PRE BID: Mandatory 6/17 9AM ADDENDUM: 1 (7-13), 2 (7-13), 3 (7-13) Angeles Contractor Bids Buena Park 714-443-3655 FX 443-3293Lewis C. Nelson & Sons Inc. Selma 559-896-1445 FX 896-8609Roebbelen Contracting, Inc. El Dorado Hills 916-939-1110 FX 939-4027Stronghold Engineering Inc. Riverside 951-684-9303 FX 684-3813T.B. Penick & Sons, Inc. Bids Due 7/22 San Diego 858-558-1800 FX 373-1455Zovich Construction Hayward 510-784-1273 FX 784-0173 #8 CUPERTINO 7/24 11AM TD AMERITADE – MAIN STEET PROJ MGR: See Bidding General For Questions Plans: Rycon Construction, Pittsburg PA 412-392-2525 FX

412-392-2526 PROJ INFO: Tenant improvement Rycon Construction Pittsburg PA 412-392-2525 FX 392-2526 #ONLINE 125 OAKLAND 7/28 2PM BART EARTHQUAKE SAFETY PROGRAM AERIAL

STRUCTURES A LINE LAKE MERRITT TO COLISEUM 15PB-120 (ONLINE ONLY)

PROJ MGR: Bart 510-464-6544 PROJ INFO: Preservation & restoration PRE BID: 6/24 9AM ENG EST: $12.6-13.4 million Alten Construction, Inc. Richmond 510-234-4200 FX 234-4221Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705Thompson Builders Novato 415-456-8972 FX 459-0665 #22 SANTA CRUZ CO 7/28 2:30PM MOSQUITO ABATEMENT & VECTOR CONTROL

OFFICE REMODEL #14C-008 PROJ MGR: Co, General Services 831-454-2210 PROJ INFO: Remodel PRE BID: Mandatory 7/14 10AM ENG EST: $716,000.00 #ONLINE 40 DUBLIN 7/28 2PM LAVTA RAPID BUS SHELTER (ONLINE ONLY) PROJ MGR: LAVTA 925-455-7555 PROJ INFO: Install anchors to connect bus shelter to existing foundations / sidewalk; install electrical

connections, flag sign, light pole

Page 13: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#5 MILPITAS 7/28 2PM MILPITAS SPORTS CENTER POOL REPAIR PROJECT 3408 & 5103

PROJ MGR: City, DPW 408-586-3300 PROJ INFO: The project site is located at the Milpitas Sports Center, 1325 East Calaveras Blvd., Milpitas, CA. The

work generally involves resurfacing of three pools, removal of existing ramp in yard pool and installation of new walk in stairs, new pool lighting in all pools, removal and replacement of all pool piping and a majority of the pool deck, installation of outdoor showers, shade structures, new lifeguard stands and racing platforms, and removal of wading pool.

ENG EST: $1.25-1.5 million Condor Inc. El Monte 626-455-0050 FX 455-0070California Commercial Pools Inc. Glendora 909-394-1280 FX 394-4579Tricon Construction, Inc. Rancho Cordova 916-638-9866 FX 638-9867Water Works Industries Inc. Windsor 707-837-7900 FX 000-0000 #ONLINE 30 HOLLISTER 7/29 2PM WEST HILLS WATER TREATMENT PLANT

(ONLINE ONLY) PROJ MGR: San Benito County Water District 831-637-8218 PROJ INFO: The work for the West Hills Water Treatment Plant Project (Project) generally includes the following

components and facilities. • Raw Water Pump Station: An outdoor pump station located off Union Road. The pump station generally includes three 75 horsepower horizontal split case pumps, electrical equipment, standby generator and a chemical feed unit. • Raw Water Pipeline: A 20-inch diameter pipeline approximately 3,800 feet long between the Hollister Conduit San Juan Sublateral Connection off Union Road and the new water treatment plant. The pipeline will be constructed by open trench method. • Access Roadway: A new 20-foot wide private roadway approximately 3,000 feet long, extending from Union road to the new water treatment plant. The roadway is generally 16- foot wide pavement with 2-foot wide shoulders on each side. • Water Treatment Plant: A new 4.5 million gallon per day (mgd) capacity water treatment plant. The work generally consists of constructing a new operations building, pretreatment unit (Actiflo Carb), gravity filters, chemical storage and feed system, a 0.5 million gallon capacity circular concrete storage reservoir (clearwell), washwater recovery basins, solids drying beds, site grading, yard piping, electrical and instrumentation and control. • Treated Water Pipeline: A drinking water pipeline approximately 9,550 feet long. The pipeline is 20-inch diameter except where it crosses the Nash Road Bridge, where the pipeline is reduced to 16-inch diameter

PRE BID: Mandatory 6/3 1PM ADDENDUM: 1 (7-13), 2 (7-13), 3 d/c (7-13) Q & A: 1 (7-13), 2 (7-13), 3 (7-13) Anderson Pacific Engineering & Const. Santa Clara 408-360-2873 FX 970-9900Auburn Constructors Sacramento 916-924-0344 FX 924-1800C.W. Roen Construction Danville 925-837-5501 FX 837-2674Clark Brothers Inc. Dos Palos 209-392-6144 FX 392-6147Disney Construction Burlingame 650-259-9545 FX 259-9651GSE Construction Livermore 925-447-0292 FX 447-0962J.F. Shea Construction Walnut 909-595-4397 FX 444-4268Mountain Cascade Livermore 925-373-8370 FX 373-0940Myers & Sons Sacramento 916-283-9950 FX 614-9520Slayden Construction Stayton OR 503-769-1969 FX 769-4525Specialty Construction Inc. San Luis Obispo 805-543-1706 FX 543-1712Spiess Construction Santa Maria 805-937-5859 FX 934-4432Stanek Constructors Inc. Escondido 760-871-0102 FX 871-0100Steve P. Rados Sacramento 916-475-1654 FX 475-1655Teichert Construction Davis 530-406-4200 FX 406-4299W.M. Lyles Company Bakersfield 661-387-1600 FX 387-1620Western Water Constructors Santa Rosa 707-540-9640 FX 540-9641

Page 14: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

121E SAN JOSE 7/30 3:15PM HUFF GARDENS APARTMENTS REHAB #1506-002 PROJ MGR: Housing Authority Of Santa Clara, 408-275-8770 Isaura Ayala PROJ INFO: Apartment rehabilitation EXHITBITS: H1 (7-13), H2 (7-13), H3 (7-13) Babel Construction San Jose 408-227-1702 FX 227-8934Southland Construction Pleasanton 925-469-1101 FX 469-1102 #122E SAN JOSE 7/30 3PM HELZER COURT APARTMENTS REHAB #1506-001 PROJ MGR: Housing Authority Of Santa Clara, 408-275-8770 Isaura Ayala PROJ INFO: Apartment rehabilitation Babel Construction San Jose 408-227-1702 FX 227-8934 #20 SAN JOSE 7/30 3PM MDF RELOCATION EVERGREEN VALLEY

COLLEGE G2010.0014 PROJ MGR: San Jose Evergreen College District, 408-270-6431 PROJ INFO: Renovation of storage area into new campus MDF / support space PRE BID: Mandatory 7/16 9AM ENG EST: $1 million Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705 #ONLINE 8 TEHACHAPI 7/30 2PM CALIFORNIA CORRECTIONAL INSTITUTION

CDCR-HCFIP 600000818 (ONLINE ONLY) PROJ MGR: CDCR 661-822-4402 Keri Lapham PROJ INFO: Demo, building pad prep, sitework, utility extensions, renovation of existing buildings, construct

new buildings PRE BID: 7/1 9AM Angeles Contractor Bids Due 7/29 @ 2PM Buena Park 714-443-3655 FX 443-3293Archer Western Construction, Inc. Los Angeles 310-342-3400 FX 342-3401Bowe Contractors Lancaster 661-341-1224 FX 000-0000Colombo Construction Inc. Bakersfield 661-316-0100 FX 316-0101JTS Construction Bakersfield 661-835-9270 FX 835-8424Pinner Construction Anaheim 714-490-4000 FX 490-4016TB Penick & Sons, Inc. San Diego 858-558-1800 FX 373-1455S.J. Amoroso Construction Co. Costa Mesa 714-433-2326 FX 433-2329Stronghold Engineering Inc. Riverside 951-684-9303 FX 684-3813 #ONLINE 16 SAN RAMON 7/30 2PM SAN RAMON LIBRARY EXPANSION &

RENOVATION (ONLINE ONLY) PROJ MGR: City, Engng 925-973-2681 PROJ INFO: The work consists of performing the following, including, but not limited to: selective

demolition; approximately 3,200 sq. ft. interior expansion of the second floor; approximately 18,200 sq. ft. of interior remodel and renovation; plumbing, mechanical and electrical work; site improvements including freestanding entrance portals and monument sign; new hardscape, landscaping and irrigation system and all other work necessary for a complete project in accordance with the Plans and Specifications

PRE BID: Mandatory 7/17 8AM ENG EST: $3.5 million Alten Construction, Inc. Richmond 510-234-4200 FX 234-4221Bobo Construction, Inc. Sacramento 916-383-7777 FX 383-1681Sausal Corporation San Leandro 510-568-6600 FX 671-0002Strawn Construction, Inc. San Jose 408-286-1299 FX 286-1288

Page 15: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#ONLINE 50 SAN MATEO 7/31 5PM CLASSIC @ SAN MATEO TILTON PLACE (ONLINE

ONLY) PROJ MGR: See Bidding General For Questions Plans: Nexgen Builders, E Palo Alto 650-322-5800 FX 650-

322-5806 PROJ INFO: 27 units attached & detached single family homes Nexgen Builders E Palo Alto 650-322-5800 FX 322-5806 #ONLINE 89 BERKELEY 8/3 5PM MAIN BUILDING SOUTH WING SPACE

MODIFICATIONS & RENOVATIONS (ONLINE ONLY)

PROJ MGR: See Bidding General For Questions Plans: Pre Con Industries, Santa Maria 805-928-3397 FX 805-345-3148 Pedro Diaz Owner: USDA, ARS, Western Business Service Center 510-559-6022

PROJ INFO: Modifications and renovations of the Main Building, south wing spaces, to accomodate the relocation of USDA's Food Safety and Inspection Service (FSIS). . Work is located USDA Agricultural Research Service Western Regional Research Center, Albany, CA. Div 01, 02, 05, 06, 07, 08, 09, 10, 11, 21, 22, 23, 25, 26, 27, 28 Plans and specs from Pre Con Industries, Inc.

Pre Con Industries Santa Maria 805-928-3397 FX 345-3148 #27E BERKELEY 8/4 2PM FIRE STATION #1 RENOVATION 15-10907-C PROJ MGR: City, Engng 510-981-6400 PROJ INFO: Renovation PRE BID: Mandatory 7/9 10AM A&E Emaar Albany 510-253-5337 FX 527-3614Agbayani Construction Corporation Daly City 650-994-9380 FX 415-665-9470B-Bros Construction Inc. San Leandro 510-351-3048 FX 351-9575Cumiskey Construction Corporation San Francisco 650-591-2884 FX 591-2343GECO Inc. Novato 415-299-0280 FX 884-0760John Pope Construction Fairfax 415-497-5948 FX 532-1832SLM Development, Inc. Belmont 650-288-7399 FX 376-9877Southland Construction Pleasanton 925-469-1101 FX 469-1102Strawn Construction, Inc. San Jose 408-286-1299 FX 286-1288Vila Construction Richmond 510-236-9111 FX 236-4979W.A. Thomas Co. Martinez 925-228-9600 FX 228-6932W.D. Campbell Construction, Inc. Fremont 510-456-8784 FX 000-0000W.E. Lyons Construction Walnut Creek 925-658-1600 FX 658-1604 #ONLINE 14 ANTIOCH 8/4 2PM SUNSET BOOSTER PUMP STATION

REPLACEMENT PW 355-BP (ONLINE ONLY) PROJ MGR: City, DPW 925-779-7050 PROJ INFO: Replace existing below grade booster pump station w / above grade booster pump station facility

installed pre-fabricated building ENG EST: $685,000.00 Conco West, Inc. Manteca 209-239-2110 FX 239-2384Pacific Infrastructure Corporation Pleasanton 925-249-0011 FX 249-0009

Page 16: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#128E OAKLAND 8/4 2PM CIVIC CENTER STATION ROOM 108 RENOVATION BART 17AG-150

PROJ MGR: Bart 510-464-6544 PROJ INFO: Replace existing HVAC, replace flooring, replace lighting, painting PRE BID: 7/20 10AM ENG EST: $110,000-125,000.00 Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705 #ONLINE 51 DUBLIN 8/4 2PM DUBLIN VETERANS & FAMILY HOUSING (ONLINE

ONLY) PROJ MGR: See Bidding General For Questions Plans: Midstate Construction, Petaluma 707-762-3200 FX

707-762-0700 PROJ INFO: Proposed four story 66 unit, affordable rental community for veterans & families Midstate Construction Petaluma 707-762-3200 FX 762-0700#ONLINE 27 SO SAN FRANCISCO 8/6 2PM GRAND AVENUE LIBRARY RENOVATION (ONLINE

ONLY) PROJ MGR: City, Engng 650-829-6652 PROJ INFO: Interior renovation PRE BID: Mandatory 7/21 2:30PM Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705 #ONLINE 46 OAKLAND 8/11 2PM BART EARTHQUAKE SAFETY PROGRAM

FRUITVALE STATION & COLISEUM STATION 15PJ-130 (ONLINE ONLY)

PROJ MGR: Bart 510-464-6544 PROJ INFO: Construct structural retrofit of Fruitvale & Coliseum Stations PRE BID: 7/10 10AM ENG EST: $12-14 million Alten Construction, Inc. Richmond 510-234-4200 FX 234-4221Arntz Builders, Inc. Novato 415-382-1188 FX 883-7529Rodan Builders, Inc. Burlingame 650-508-1700 FX 508-1705Sausal Corporation San Leandro 510-568-6600 FX 671-0002 #ONLINE 28 SAN FRANCISCO 8/11 10:30AM PIER 31 BUILDING & ROOF REPAIR PROJECT

2762 (ONLINE ONLY) PROJ MGR: Port Of San Francisco 415-274-0411 PROJ INFO: Selective demo, hazardous material abatement, repair of structural framing, toilet room / ADA

upgrade PRE BID: 7/14 10:30AM ENG EST: $5.7 million

Page 17: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

#58 SAN JOSE 8/13 2PM BUILDING 2 BERGER DRIVE SEISMIC UPGRADE PROJ MGR: Co, Facilities 408-993-4326 PROJ INFO: Work will consist of Adding reinforced concrete shear walls to strengthen the existing concrete columns

from the first floor to the basement; adding reinforced shotcrete to strengthen the concrete spandrel beams at the roof and on each floor; strengthening selective steel beams and their connections in the East-West and North-South direction on the 2nd and 3rd floors; removing and re-installing the existing roof mounted solar panel system to allow roof slab retrofit; reinforcing the existing low strength insulation concrete roof slab with composite carbon fiber; providing seismic bracing and anchoring to the access floor, the County network server and support equipment in the Data Center on the 2nd floor. The project also includes modifying the existing HVAC/fire protection/electrical/plumbing to clear the spot for structural retrofit work

PRE BID: Mandatory 7/22 10AM ENG EST: $9.66 million Alten Construction, Inc. Richmond 510-234-4200 FX 234-4221 #ONLINE 79 NEWMAN 8/18 2PM NEWMAN SKATE PLAZA (ONLINE ONLY) PROJ MGR: City, DPW 209-862-4448 PROJ INFO: New skate plaza PRE BID: 8/10 2PM #ONLINE 13 JAMESTOWN 8/20 2PM SIERRA CONSERVATION CENTER CDCR-HCFIP

6000001829 (ONLINE ONLY) PROJ MGR: CDCR Marie Bevilaqua email: [email protected] PROJ INFO: Demo, building pad prep, accessible paths of travel, infrastructure upgrades PRE BID: Mandatory 7/27 10AM F&H Construction Lodi 209-931-3738 FX 931-4427 #ONLINE 93 FRESNO 8/25 3PM FULTON MALL RECONSTRUCTION PROJECT

SEWER & WATER MAINS IN MERCED, TUOLUMNE & TULARE STREETS (ONLINE ONLY)

PROJ MGR: City, Engng 559-621-1332 PROJ INFO: Reconstruction of Fulton Mall corridor PRE BID: Mandatory 8/5 10AM ENG EST: $16.2 million

Page 18: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

MISCELLANEOUS PROJECTS OUT TO BID

94E Richmond Point Pinole Regional Shoreline Fishing Pier Furniture Replacement 7/16* PROJ MGR: East Bay Regional Park District 510-544-2301 2PM PRE BID: Mandatory 6/22 1PM ENG EST: $143,000.00 ADDENDUM: 1, 2 Online 61 Contra Costa Co Roof Replacement Arnold Industrial Way Rebid (Online Only) 7/16* PROJ MGR: Co, DPW 925-313-2000 2PM PRE BID: 6/24 2PM ENG EST: $300,000.00 ADDENDUM: 1, 2 Secure 2 San Francisco North Point Facility Dewatering Pump Replacement & Electrical

Upgrade SFPUC WW-579 (Secured Project) 7/16* 2PM

PROJ MGR: SFPUC 415-551-4603 This project will not be scanned in. This is a security sensitive contract. CD may be reviewed in our plan room. Confidentiality agreement must be signed to view CD

PRE BID: 6/30 9:30AM ENG EST: $800,000.00 ADDENDUM: 1 66E Richmond West County Trail Repairs 7/16* PROJ MGR: East Bay Regional Park District 510-544-2301 2PM PRE BID: Mandatory 6/25 10AM ENG EST: $450,000.00 17 Santa Clara Co Lawrence Expressway Pavement Rehabilitation Project Between

Homestead & Hwy 237 7/16* 2PM

PROJ MGR: Co, Roads & Airports 408-573-2485 Paul Pascoal PRE BID: 7/7 10:30AM ADDENDUM: 1, 2 123E Santa Clara Job Order Contract Rad 2015-01 7/16* PROJ MGR: Co, Roads & Airports 408-573-2442 Albert Eydam 2PM PRE BID: Mandatory 6/10 10AM Online 44 Sacramento El Camino Avenue-Median Improvements 40824 (Online Only) 7/16 PROJ MGR: Co, DPW 916-874-6544 2PM ENG EST: $140,000.00 Online 4 San Rafael Merrydale Road Pipeline Project MMWD 1764 (Online Only) 7/16* PROJ MGR: Marin Municipal Water District 415-945-1530 10AM ADDENDUM: 1 Online 6 Fresno Co California Avenue Shoulder Improvements 0.64 MI West Of Washoe

To Derrick Ave 15-03-C (Online Only) 7/16* 2PM

PROJ MGR: Co, DPW 559-600-4530 ADDENDUM: 1, 2 d/c, 3

Page 19: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

3E Sonoma Co Service Center Parking Lot Phase II, 800 Aviation Boulevard 7/17* PROJ MGR: Sonoma Co Water Agency 707-547-1900 2PM PRE BID: Mandatory 6/30 & 7/2 2PM ENG EST: $225,000.00-$300,000.00 7E Los Gatos Annual Street Repair & Resurfacing & Pavement Rehabilitation 7/17* PROJ MGR: Town, DPW 408-399-5770 10AM ADDENDUM: 1 22E Oakland Various Streets Rehabilitation C476510 7/17* PROJ MGR: City, DPW 510-238-3621 2PM PRE BID: Mandatory 7/2 2PM ENG EST: $3,774,082.00 ADDENDUM: 1, 2, 3 d/c

Online 26 So San Francisco Grand Avenue & Magnolia Avenue Traffic Signal & Intersection Improvement (Online Only)

7/20* 2PM

PROJ MGR: City, Engng 650-829-6652 PRE BID: Mandatory 7/7 2PM & 7/15 2PM ADDENDUM: 1 Online 23 So San Francisco Mission Road-Evergreen Drive Traffic Signal & Intersection (Online

Only) 7/20* 2PM

PROJ MGR: City, Engng 650-829-6652 PRE BID: Mandatory 7/7 2PM Online 70 So San Francisco Mission Road-Evergreen Drive Traffic Signal & Intersection (Online

Only) 7/20

PROJ MGR: City, Engng 650-829-6652 2PM PRE BID: Mandatory 7/15 2PM

12 Livermore Water Reclamation Plant Electrical Improvements 2008-48 7/21* PROJ MGR: City, Engng 925-960-4500 2:30PM PRE BID: 7/7 2:30PM ADDENDUM: 1 Online 29 Santa Cruz Co Soquel Creek Habitat Enhancement Project (Online Only) 7/21 PROJ MGR: Resource Conservation District Of Santa Cruz County 831-

464-2950 3PM

PRE BID: Mandatory 6/30 10AM ADDENDUM: 1, 2 Online 20 Walnut Creek Lar Rieu House Demolition 15-06 (Online Only) 7/21 PROJ MGR: City, DPW 925-943-5899 2:30PM PRE BID: 7/8 10AM ENG EST: $90,000.00 Online 10 Bakersfield Municipal Airport Northeast Hangar Taxilane Pavement Rehab

(Online Only) 7/21* 11AM

PROJ MGR: City, DPW 661-326-3700 PRE BID: Site Visit 7/7 10AM

Page 20: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

Online 7 Monterey RFP To Provide On-Call Mechanical Engineering Service (Online Only)

7/21 2PM

PROJ MGR: City, DPW 831-646-3997 36E Cupertino Stevens Creek Boulevard @ Perimeter Road Turn Pocket Extension

Project Rebid 2015-20 7/21* 2PM

PROJ MGR: City, DPW 408-777-3354 ENG EST: $87,094.00 26 Milpitas 2014 Soundwall Renovation Jacklin Road @ Hillview Drive 4267 7/21* PROJ MGR: City, DPW 408-586-3301 2PM ENG EST: $300,00.00-$500,000.00 Online 84 Dublin Recycled Water Expansion Phase 1 Distribution To West Dublin

Onsite Conversions CIP 15-R009 (Online Only) 7/21* 2PM

PROJ MGR: Dublin San Ramon Services District 925-875-2258 PRE BID: 7/1 10AM ENG EST: $750,000.00 ADDENDUM: 1 d/c Online 48 Morgan Hill New Multi-Use Building @ Morgan Hill Charter School Wastewater

System Project MHUSD (Online Only) 7/21* 3PM

PROJ MGR: Morgan Hill Unified School District 408-201-6087 PRE BID: Mandatory 6/17 1:30PM ADDENDUM: 1 d/c, 2 d & t/c, 3 d & t/c

Online 87 San Francisco San Marcos & Santa Rita Avenue Roadway Improvements 2438J (Online Only)

7/22* 2:30PM

PROJ MGR: City & Co, DPW 415-554-6229 PRE BID: 6/23 2PM ENG EST: $1.3 million 23E San Rafael Street Resurfacing 2014-2015 7/22 PROJ MGR: City, DPW 415-485-3355 10:30AM Online 59 Santa Clara Valley Montague Expressway & South Milpitas Boulevard Improvements

C640 (15014) (Online Only) 7/22 2PM

PROJ MGR: SCVTA Fax 408-955-9729 Edward Lao PRE BID: 7/8 10AM 83E Capitola Rispin / Peery Park ADA Pathway Improvements Phase 1 7/22 PROJ MGR: City, DPW 831-475-7300 11AM ENG EST: $101,200.00 85E Santa Clara Removal Of Barriers To Physically Challenged FY 2015-16 7/22 PROJ MGR: City, DPW 650-615-3000 3PM ADDENDUM: 1 Online 78 Stanislaus Co Central Avenue @ East Taylor Road Intersection (Online Only) 7/22 PROJ MGR: Co, Norma Williams email: [email protected] 2PM ENG EST: $548,000.00

Page 21: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

37E Belmont 2015 Sewer Rehabilitation Project 2015-534 7/22 PROJ MGR: City, DPW 650-595-7443 2PM PRE BID: 6/22 10AM ENG EST: $1,570,000.00 ADDENDUM: 1 d/c, 2 d/c

Online121 San Francisco Holloway Green Street Stormwater Improvements WW-609 (Online Only)

7/23* 2PM

PROJ MGR: SFPUC 415-551-4603 PRE BID: 6/15 & 6/30 10AM ADDENDUM: 1 111E San Jose Paving Improvements @ Coyote Creek Parkway Trail 7/23 PROJ MGR: Co Of Santa Clara, Parks 408-355-2231 Ubaldo Perez 2PM PRE BID: 7/14 10AM ADDENDUM: 1 5E San Joaquin Co Cathodic Protection Rehabilitation-Install Insulated Sleeve

Couplings Devil’s Den 15-05 7/23 11AM

PROJ MGR: Department Of Water Resources 916-653-4867 PRE BID: 7/8 10AM 19 Gilroy Library, Student Center & Theater Fire Alarm Replacement Gavilan

College 7/23 2PM

PROJ MGR: Gilbane 408-660-4400 PRE BID: Mandatory 7/7 11AM 24 San Jose 7575 Evergreen Park Play Lot Retrofit & Community Center Lot 7/23 PROJ MGR: City, DPW 408-535-8300 Stacy Palomar 3PM 25 San Jose 7235 Mise Park Element Renovation 7/23 PROJ MGR: City, DPW 408-535-3539 Jane Wu 3PM 51E San Jose 6028 Penitencia Creek Park Play Area Renovation 7/23 PROJ MGR: City, DPW 408-535-8439 Mike Pruitt 3PM ADDENDUM: 1 Online 38 Sacramento El Camino Avenue-Monument Wall Improvements 40825 (Online

Only) 7/23 2PM

PROJ MGR: Co, DPW 916-874-6544 ENG EST: $40,000.00 ADDENDUM: 1 d/c 70E San Mateo Co Resurfacing Of Portions Of Pescadero Creek Road & Cloverdale

Road 7/23 2:30PM

PROJ MGR: Co, DPW 650-363-4100 ENG EST: $1 million 124E San Mateo Co Road Oil Application In Conjunction With County’s 2015 Chip Seal

Road Maintenance 7/23 2:30PM

PROJ MGR: Co, DPW 650-363-4100 ENG EST: $127,000.00

Page 22: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

77E Marin Co 2015 Road Rehabilitation Project Western Region 2015-07 7/23 PROJ MGR: Co, DPW 415-473-7877 2:30PM ENG EST: $2.4 million 34E San Jose 7545 Doerr Park Play Area Renovation 7/23 PROJ MGR: City, DPW 408-535-8416 Chris Mastrodicasa 3PM ADDENDUM: 1 d/c 82E San Mateo Labor To Install Lights @ 4 Schools SMFCSD 7/23 PROJ MGR: San Mateo Foster City School District 650-312-7889 Mark

Sherrill 2PM

PRE BID: Mandatory 7/14 1:30PM 80E La Honda Portola Redwoods State Park Shade Ramada & Picnic Area

#C15680047/23 7/23 2PM

PROJ MGR: Department Of Parks & Recreation Santa Cruz District 831-335-6388

PRE BID: Mandatory 7/16 1PM ENG EST: $200,000.00 91E San Mateo Co Reconstruction Of North Street From Stage Road To Pescadero

Creek Road 7/23 2:30PM

PROJ MGR: Co, DPW 650-599-1411 ENG EST: $1 million Online 47 Kentfield PS 15, Kentfield Pump Station, Electrical Service Replacement

(Online Only) 7/23* 2PM

PROJ MGR: Ross Valley Sanitary District 415-259-2949 PRE BID: Mandatory 7/7 10AM ADDENDUM: 1, 2 d/c

79E San Carlos San Carlos Dog Park Fence C9343 7/27 PROJ MGR: City, DPW 650-802-4198 3PM ENG EST: $70,000.00-$80,000.00

46E Richmond Point Pinole Regional Shoreline Breuner Marsh Restoration & Public Access Improvement

7/28 10AM

PROJ MGR: East Bay Regional Park District 510-544-2300 PRE BID: 7/14 10AM ENG EST: $1,265,000.00 Online 62 Orinda 2015 Annual & Measure J & L Pavement Rehabilitation (Online Only) 7/28 PROJ MGR: City, DPW 925-253-4200 2PM PRE BID: 7/20 10AM ENG EST: $4,998,000.00 Online 31 Marin Sequoia Valley Rd / Tourist Club FFIP Pipeline Replacement MMWD

1789 (Online Only) 7/28 10AM

PROJ MGR: Marin Municipal Water District 415-945-1530 ENG EST: $555,000.00 127E Palo Alto 2015 Pole Replacement 158031 7/28 PROJ MGR: City, DPW 650-329-2271 3PM

Page 23: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

28E Healdsburg Healdsburg Intermodal Facility Phase 1 7/29 PROJ MGR: County Of Sonoma, Department Of Transportation 707-565-

2231 2:30PM

ADDENDUM: 1 d/c, 2, 3 Online 2 Pittsburg W. Leland Reservoir Demolition 2014-09 (Online Only) 7/29 PROJ MGR: City, Engng 925-252-4930 2PM PRE BID: 7/22 10AM ENG EST: $35,000.00 24E Yolo Co North Levee Setback-Cache Creek 15-02 7/29 PROJ MGR: Department Of Water Resources 916-653-4867 2PM PRE BID: Site inspection 7/14 10AM Online 67 San Francisco Webster Street Pavement Renovation, Sewer Replacement &

Waterman Installation 2386J (Online Only) 7/29 2:30PM

PROJ MGR: City & Co, DPW 415-554-6229 PRE BID: 7/7 1:30PM ENG EST: $4 million 92E Napa Drainage Improvements Project Stonecrest Drive, Casswall Street &

Linda Mesa Way 7/29 3PM

PROJ MGR: City, DPW 707-257-9520 PRE BID: 7/21 3PM ENG EST: $138,000.00

52E Santa Clara Valley CCTV @ Various Locations Phase 7 C15120 7/30 PROJ MGR: SCVTA Fax 408-955-9729 Florante Tanada 2PM PRE BID: 6/12 10AM RFI: #1 60 San Lorenzo Phase I Renovation @ San Lorenzo Community Park 7/30* PROJ MGR: Hayward Area Recreation Park District 510-881-6715 1:30PM PRE BID: Mandatory 7/7 9AM ENG EST: $8.5 million 47E Cupertino 2015 Contractual Crossing Guard Services Rebid 7/30 PROJ MGR: City, DPW 408-777-3350 2PM 71E Santa Clara Valley Downtown San Jose & City Hall Bart Stations C837 15156 7/30 PROJ MGR: SCVTA Fax 408-955-9729 Florante Tanada 1PM PRE BID: 7/15 11AM 98E Union City South Decoto Green Streets Project 11-29 7/30* PROJ MGR: City, DPW 510-675-5308 2PM ENG EST: $2.9 million ADDENDUM: 1 d/c 8E Santa Clara Valley SR 237 Phase 1 Restripe C15129 7/30 PROJ MGR: SCVTA Fax 408-952-4181 Surinder Singh 2PM ADDENDUM: 1 d/c, 2 d/c

Page 24: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

130E Sacramento PCA Bridge Railing Replacement 40826 7/30 PROJ MGR: Co, DPW 1-874-6544 2PM ENG EST: $175,000.00 84E Napa Earthquake Damage Repair-Senior Center 7/30 PROJ MGR: City, DPW 707-257-9520 3PM PRE BID: 7/21 10AM ENG EST: $122,000.00

Online 91 San Francisco RFP For Construction Manager / General Contractor For New Fire Station 5 7440A (Online Only)

7/31 3PM

PROJ MGR: City & Co, DPW 415-554-6229 PRE BID: 7/14 10:30AM ADDENDUM: 1 Online 85 Tulare Prequalification Package For South County Detention Facility AB900

(Online Only) 7/31 12PM

PROJ MGR: Co, General Services Department 559-636-5300 ADDENDUM: 1 113E San Carlos San Carlos Traffic Sign Installation 7/31 PROJ MGR: City, DPW 650-802-4198 3PM ENG EST: $40,000.00-$50,000.00

3 San Leandro Siempre Verde Park Rehabilitation Project 8/3* PROJ MGR: City, Engng 510-577-3428 3PM PRE BID: 6/9 10AM ENG EST: $1-5 million ADDENDUM: 1, 2, 3, 4 d/c, 5 93E Santa Clara Valley Canoas Creek Rodent Damage Repair 30114002 8/3 PROJ MGR: SCVWD 408-630-3005 2PM PRE BID: Mandatory 7/22 10AM ENG EST: $3.5-4.5 million

Online 35 Sacramento Electric Vehicle Supply Equipment Installation DGS 138353 (Online Only)

8/4 2PM

PROJ MGR: DGS 916-376-5314 Abdi Farhang PRE BID: Mandatory 7/16 9AM Online 76 Solano Co Vacaville-Dixon Bicycle Route Phase 5B (Online Only) 8/4 PROJ MGR: Solano Co, Department Of Resource Management 707-784-

6074 2PM

112E San Carlos On Call Sidewalk Repair Project C9465-15 8/5 PROJ MGR: City, DPW 650-802-4212 9AM Online 72 San Francisco Mansell Streetscape Improvements 2235J (Online Only) 8/5 PROJ MGR: City & Co, DPW 415-554-6229 2:30PM PRE BID: 7/8 11AM ENG EST: $3.8 million

Page 25: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

129E Los Gatos Guadalupe Creek Overlook Construction Sierra Azul Open Space 8/5 PROJ MGR: Midpeninsula Regional Open Space District 650-691-1200 3PM PRE BID: Mandatory 7/15 11AM 9 Los Altos Hills 2015 Pavement Rehabilitation Project 8/5 PROJ MGR: Town, DPW 650-941-7222 2PM

Online 39 Sacramento Sacramento Power Authority Recycled Water Pipeline Phase 1A 4289 (Online Only)

8/6 2PM

PROJ MGR: Co, DPW 916-874-6544 PRE BID: 7/8 2PM ENG EST: $3.3 million 101E Santa Clara Co Canyon Drive, Miguelita Road, & Anderson Road Sewer

Replacement CU-14109 8/6 2PM

PROJ MGR: County Sanitation District 2-3 408-453-5373 Online 83 Martinez Fuel System Upgrades Contra Costa Area Office #320 136336

(Online Only) 8/6 2PM

PROJ MGR: DGS 916-375-4230 Aubree French PRE BID: Mandatory 7/16 10AM 86E Redwood City Primary Sedimentation Tank Rehabilitation CIP #9080, 9128 SCVW 8/6 PROJ MGR: Silicon Valley Clean Water 650-591-7121 2PM PRE BID: Mandatory 7/23 10AM

Online 75 San Francisco Sloat Boulevard Pedestrian Safety Improvements II 2238J(R) (Online Only)

8/12 2:30PM

PROJ MGR: City & Co, DPW 415-554-6229 ENG EST: $450,000.00 114E San Rafael 2015 Road Sealant Project 2015-16 8/13 PROJ MGR: Marin Co, DPW 415-473-7877 2:30PM ENG EST: $850,000.00

Online 3 Sausalito Beach Force Main & Gravity Sewer Inspection Project (Online Only) 8/18 PROJ MGR: Sausalito-Marin City Sanitary District Fax 415-322-0453

Kevin Rahman 2PM

PRE BID: Mandatory 8/4 9AM ENG EST: $350,000.00

Online 43 San Francisco Twin Peaks Tunnel Trackway Improvement Project 1282 (Online Only)

8/20* 3PM

PROJ MGR: SFMTA 415-701-4300 Fax Allan Andaya PRE BID: 7/7 10AM ADDENDUM: 1 d/c, 2

Page 26: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

4 Ceres Monterey Park Tract Community Services District Water Supply 8/26 PROJ MGR: Quad Knopf, 209-723-2066 2PM PRE BID: 8/5 10AM *Bid list on file at the Exchange The bidders listed may not represent all of the potential bidders on each project. The Builders Exchange does not assume responsibility in determining if all bidders have been identified. Any general contractor wishing to add or delete their name from the list is requested to inform the Exchange. We receive plans that are out of our area. We do not verify list on these projects. We do confirm our regular sources to insure lists are as complete as possible.

Page 27: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

CALTRANS PROJECTS OUT TO BID (* = Addendums on Project)

# Bid Date Bid Time Zone & Project Location C-41 7/16 2PM 06-0S7504 06-Ker-5,58,99,178-Var Remove & Replace Sign Panels C-43 7/16 2PM 10-0Y6804 10-SJ-88 Construct Rumble Strips C-27 7/21 2PM 01-0B5704 01-Men-253 Construct Soldier Pile Wall C-39 7/21 2PM 06-0S2804 06-Ker-58 Cold Plane AC Pavement C-34 7/21 2PM* 05-0R5104 05-Mon,SC4-1,9,68,218-Vrs Construct Curb Ramps C-36 7/21 2PM* 06-0M0504 06-Fre-168 Realign 2 Lane Roadway C-07 7/21 2PM 04-3G7104 04-Ala-238,580,680,880-Var Construct Roadside Paving C-12 7/21 2PM 01-4939U4 01-Men-20,162 Construct Turnouts C-06 7/22 2PM* 10-0Y90U4 10-SJ-99 Place JPCP C-30 7/22 2PM* 02-2E8004 02-Sis-5 Reconstruction Of Dunsmuir Commercial Vehicle Facility C-15 7/22 2PM 06-0S9304 06-Fre,Ker,Mad,Tul-58,63,65,137 Modify Signals C-11 7/22 2PM 01-0E2604 01-DN-101 Cold Plane AC C-01 7/23 2PM* 04-4A4804 04-Ala-260 Replace Guardrail C-35 7/23 2PM* 05-1A7604 05-Mon-1 Grind PCC Traveled Lanes C-38 7/23 2PM 06-0S2704 06-Ker-395 Resurface Existing Pavement C-25 7/28 2PM* 010A3204 01-Hum-299 Widen Roadway C-37 7/28 2PM 06-0N9604 06-Ker-204 Clean & Paint Existing Bridge C-26 7/29 2PM 01-0B3404 01-Hum-36 Reconstruct Roadways & Drainage C-42 7/29 2PM* 06-424714 06-Ker-119 Construct Truck Climbing Lanes C-02 7/29 2PM 04-0G2214 04-Ala,CC-13,24,61,160,580-Var Construct Curb Ramps C-28 7/30 2PM 01-463924 01-Hum-Var Reconstruct Guard Railing C-32 7/30 2PM 02-4E8904 02-Sha-299 Earthwork, HMA, Concrete Box Culvert C-33 7/30 2PM 03-2F6004 03-ED-49 Roadway Excavation, Curbs, HMA Paving C-17 8/4 2PM 04-0J2904 04-Ala-61 Spot Blast Clean C-21 8/4 2PM 10-0Y6504 10-Cal,SJ-12,26-Var Construct Rumble Strips C-18 8/5 2PM 04-2G8604 04-Ala-580 Construct Retaining Wall C-03 8/11 2PM 04-2G5214 04-Ala-580 & 680 Upgrade Transition Railing C-20 8/11 2PM 10-0S7204 10-Ama-49 Cold Plane Asphalt Concrete Pavement C-09 8/12 2PM 01-0B03U4 01-Hum-96 Soldier Pile Wall With Ground Anchors

Page 28: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

C-19 8/12 2PM 04-3G6804 04-SM-101,280,380-Var Construct Roadside Pavement C-14 8/13 2PM 03-4E8604 03-Pla-193 Curve Improvement C-16 8/13 2PM 05-1A8704 05-SC4-1,17 Widen Shoulder C-04 8/18 2PM 04-3G4864 04-SM-92 Clean & Paint Structural Steel On Bridge C-05 10/20 2PM* 04-264094 04-Mrn,Son-101 Realign Highway

Page 29: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

BID RESULTS & APPARENT LOW BIDDER

Location Project Bid Date & Amt Martinez Ferrous Chloride Tank Replacement, Contact No. 3-15 5-28-15 Pacific Infrastructure Corporation $304,000.00 San Jose 7398 Yolo Drive & Lanfair Drive Cast Iron Pipe Replacement 6-18-15 Pacific Underground Const., Inc. $339,385.00 Livermore 2015 Slurry Seal City Project No. 2015-04 7-1-15 American Asphalt $973,972.37 San Mateo Ryder Park Bayfront Levee Erosion Repair Project 7-1-15 CV Larsen Co. $141,645.00 Redwood City 2014-2015 Slurry Seal Project 7-2-15 Pavement Coatings Co. $463,565.00 Dublin Secondary Clarifier No. 3 Rehabilitation CIP 14-S013 7-2-15 NMI Industrial Holdings, Inc. $379,000.00 Concord Contra Costa Canal Trail Citrus To Treat & Tioga To Cowell Avenue 7-6-15 R&M Paving $145,297.00 San Carlos 2015 Storm Drain Improvements Project C9531-14 7-8-15 Stoloski & Gonzales, Inc. $179,245.00 Hercules Ohlone Elementary School Parking & Landscape Completion Phase 4 7-8-15 Michael G. McKim Co. $239,950.00 San Mateo Co Sanitary Sewer Rehabilitation Project Along Eleanor Drive 7-8-15 D’Arcy & Harty Const., Inc. $1,782,998.00 El Sobrante Crespi Middle School Hot Water Boiler Replacement 7-9-15 Arthulia, Inc. $254,000.00 Vallejo Clearwell Pump Building WT7056 7-9-15 B Side Inc. $299,000.00 Davis Well 34 Cleaning, CIP 8174 & Well 24 Pump Removal, Program 7522 7-9-15 Zim Industries $62,200.00 San Rafael Glenwood Pump Station Improvements Project 7-9-15 JMB Const., Inc. $1,795,085.00 Santa Cruz Methacrylate Bridge Deck Seal Project 7-9-15 Truesdell Corp. $124,124.00 Santa Cruz Soquel Drive @ Rodeo Gulch Bridge Repair Project 7-9-15 Bay Line Cutting & Coating $401,643.00 San Jose 7981 Mineta San Jose Airport Airfield Fence Improvements 2015 7-9-15 Granite Rock Const., Inc. $4,003,249.00 Gilroy Gully Repair & Drainageway Restoration Diablo Foothills Open Space Preserve 7-13-15 Granite Const., Co. $254,237.80 Fresno Co Remove & Replace Sign Panels 06-0S7404 7-14-15 Peterson-Chase General Engineering Const., Inc. $1,525,426.00 Menlo Park 2014-2015 Street Rehabilitation Project 20-010 7-14-15 O’Grady Paving, Inc. $4,390,860.00 Walnut Creek Ygnacio Valley Road / San Carlos Drive Improvements 7-14-15 Bay Cities Paving & Grading $757,106.12 Danville Bocce Court Expansion Sycamore Valley Park B-591 7-14-05 Suarez & Munoz Const. $1,192,194.50 Santa Clara Co Leland Avenue Traffic Calming Circle @ Basile Ave R15-01 7-14-15 Wattis Const.

Page 30: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

For more information and how to apply online:

www. sjcc.edu Phone: 408.288.3782

FALL SEMESTER 2015

CNSTR 101A Tools, Materials, & Processes 4.00 Units

CNSTR 101B Residential Construction Framing 4.00 Units

CNSTR 102A Residential Plumbing Systems 3.00 Units

CNSTR 102B Residential/Commercial Wiring 4.00 Units

CNSTR 103 Roof Framing Systems 4.00 Units

CNSTR 104 Interior/Exterior Finish 4.00 Units

CNSTR 106 Blueprint Reading, Estimating, Codes 3.00 Units

CNSTR 107 Principles of Contracting 3.00 Units

CNSTR 115 Blueprint Reading 1.00 Unit

CNSTR 116 Estimating 1.00 Unit

CNSTR 117 OSHA Safety Standards 1.50 Units

CNSTR 120 Construction Building Code 1.00 Unit

CNSTR 125 Green Construction 3.00 Units

CNSTR 128 NEC & Calculations 4.00 Units

CNSTR 130 House Building Practicum 4.50 Units

CNSTR 133 Leadership in Energy & Environmental Design Exam Prep 3.00 Units

■■■ DON’T DELAY and APPLY TODAY ■■■

FALL SEMESTER

AUGUST 31 through December 17

Day and evening classes are available.

Page 31: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

Capitol Connection Q&A for Contractors Week of 7/20/15

By Shauna Krause of Capitol Services, Inc.

We often hear from aspiring contractors who have grown up in the business and want to follow in their

parent’s footsteps. If you want to keep the same license number timing is everything as we learn here. A

landscaper’s ambition gets ‘cut short’ and we review what it takes to be a Responsible Managing Em-

ployee…

Q: My Dad retired a couple of years ago and inactivated his license. I have been doing construction

work for over 10 years for a General Building company and I want to get my own license. Would it be

possible for me to take over my Dad’s license number since it’s a low number? I did work for him for

several years when I first started in the industry. Also, would I be able to waive the exams? A: To answer your first question, B&P Code 7075.1(c) allows for a Sole Owner license to be transferred

to an immediate family under certain circumstances, however one of the conditions is that the license in

question must be current and Active. Since your father’s license has been Inactive for several years, you

cannot request that number be reassigned to you. Unfortunately you would not qualify for a Waiver of

the exams. In order for that to occur you would be required to have worked for your father and actively

engaged in his business for five out of the last seven years. It sounds like you have the requisite experience to obtain your own license by taking the exams, so con-

tact us if you’d like our assistance. Q: I am a “C-27” Landscaping contractor and I have had a few customers ask me to repair or maintain

their pool. Am I allowed to contract and perform this work for them? A: If the swimming pool is part of your landscaping project, you can sub-contract the pool part of it out

to a licensed swimming pool contractor, however it is my understanding that you cannot self-perform

the work. Note that you cannot just take a pool contract by itself and self-perform or sub-contract the

work out to a licensed pool contractor. Q: I have my own license and I was recently talking with a company that wants me to be their Responsi-

ble Managing Employee (RME) and transfer my license to them. What kind of salary do RME’s typically

get for letting a company use their license? Are there other requirements of RME’s that I should know

about? A: While we don’t offer advice on what is appropriate compensation, we frequently get asked that ques-

tion, and as far as we know, there is no “going rate.” Your compensation is something that you work out

with the company. Talking with others who hold RME positions might be a good place to learn more. With regards to RME requirements, B&P Code Section 7068.1 states that the qualifying individual is re-

sponsible for exercising direct supervision and control of the employer’s construction operations. RME’s

are also required to be actively involved in the operation of the business for at least 32 hours or 80% of

the total operating hours, whichever is less.

While knowledge is power, knowing where to go for the answers is half the battle. Get expert assistance

immediately when you call 866-443-0657, email [email protected], or write us at Capitol Services,

Inc., 1225 8th St. Ste. 500, Sacramento, CA 95814. Research past columns at www.cutredtape.com.

Page 32: JULY 16, 2015 MAJOR PROJECTS - Builders' … Wagner,A bbott, Stringham & Lynch 408-377-8700 Anita Woodson, Woodson Administrative Services 408-859-9029 John Pluff, Facilities Solutions

Tailgate TopicsSlips & Falls - Avoid Slip-Ups

Slips and falls are a leading cause of workplace injuries. What do experts recommend as the single most important step to take in preventing slips and falls? Simple...keep fl oors clean, dry, and free of obstruction. When it comes to safeguards against slips and falls, nothing is more important than good housekeeping.

When you walk through a work area, look for spills, grease spots or dust (fl our and machine byproducts can be highly slippery). Water spilled by drinking fountains or tracked in on wet or snowy days can create a major hazard. Look around and be aware of wet areas or objects on the fl oor. Then take the time to do something about it. Clean up the hazard or place cones or hazard signs nearby, warning of the danger. People can walk on extremely slippery surfaces by modifying their speed and stride, provided they know about the dangerous condition. It’s the lack of warning that can cause problems. An unexpected shift from a smooth to a slick surface heightens the likelihood of a slip or fall.

Look for signs of fl ooring change. Changes in lighting and fl oor color can conceal a change in friction or angle between adjacent surfaces. Wherever possible, waxes and polishes should cover an entire area, extending to natural breaks in fl ooring. Choose footwear according to fl oor surface.

Consider slips and falls when you’re doing a job. Some tasks, such as pushing loads, may require special attention to slip-resistant fl oor surfaces or carefully selected sole material and treads. For some jobs, better lighting or a stable brace is helpful. Carefully placed and mounted hand rails, poles or hip bars may help operators brace themselves. This reduces reliance on foot/fl oor friction, which thereby reduces the potential for slipping.

Slips can occur because of how you walk on a surface. Some simple things you can do to minimize your chance of slipping and falling would be to wear appropriate footwear; watch where you’re going; take slow, short steps where slip potential is high; and use hand holds where possible.

XXXXX

Supervisor’s SignatureMeeting Attended By:XXXXX

Tailgate topic provided courtesty of State Compensation Insurance Fund. For more tailgate topics, check out the State Fund website at:

http://www.statefundca.com/safety/safetymeeting/SafetyMeetingTopics.aspx

The above evaluations and/or recommendations are for general guidance only and should not be relied upon for legal compliance purposes. They are based solely on the information provided to us and relate only to those conditions specifi cally discussed. We do not make any warranty, expressed or implied, that your workplace is safe or healthful or that it complies with all laws, regulations or standards.