k. long, 14 june, 2015 target k. long, friday, 24 th april 2009
Post on 20-Dec-2015
218 views
TRANSCRIPT
K. Long, 18 April 2023
Target
K. Long, Friday, 24th April 2009
Critical path:
• No particular issues, but:– Vacuum tubes ready to be sent to Sheffield– Stator assembly ready for vacuum tubes at Sheffield– Weld trials successful– Parts in manufacture
Manufacturing: highlights:
Installation and commissioning schedule:• Presented / discussed at Target w/s last Friday• Revised version to be presented / discussed at
CM24• Need to have Target w/s with ISIS in June:
– Make sure manufacturing remains on track;– Discuss installation and commissioning plans;– Ensure manpower assumptions for shutdown are valid