kalpakkam nuclear power project, tamilnadu

2
Central Water and Power Research Station, Pune KALPAKKAM NUCLEAR POWER PROJECT, TAMILNADU Background Kalpakkam is located on the east coast about 70 km south of Chennai in Tamil Nadu State. The Madras Atomic Power Station (MAPS) having two units of 220 MW was established in 1983-85 by Nuclear Power Corporation of India Ltd (NPCIL). MAPS is operating on once-through cooling water system for which the cooling water (i.e. about 35 m 3 /s) required for the power station is drawn from the sea through an intake well which is located at 360 m from seashore and connected to the forebay of the pump house by a submarine tunnel. Department of Atomic Energy has proposed to establish a Fast Breeder Reactor Project (PFBR) of 500 MW capacity at a location 500 m south of MAPS. Studies conducted Field data collection and analysis for Condenser Cooling Water System (CCWS) of PFBR, Mathematical model studies for location of intake/outfall for 500 MWe Prototype Fast Breeder Reactor using Numerical Model MIKE 21 Wave Flume studies for the design of outfall guide bund and shore protection works Mathematical model studies for littoral drift and thermal recirculation using Numerical Model LITPACK. Location Map and Intakes

Upload: others

Post on 06-Dec-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: KALPAKKAM NUCLEAR POWER PROJECT, TAMILNADU

Central Water and Power Research Station, Pune

KALPAKKAM NUCLEAR POWER PROJECT, TAMILNADUBackgroundKalpakkam is located on the east coast about 70 km south of Chennai in Tamil Nadu State. The MadrasAtomic Power Station (MAPS) having two units of 220 MW was established in 1983-85 by Nuclear PowerCorporation of India Ltd (NPCIL). MAPS is operating on once-through cooling water system for which thecooling water (i.e. about 35 m3/s) required for the power station is drawn from the sea through an intakewell which is located at 360 m from seashore and connected to the forebay of the pump house by asubmarine tunnel. Department of Atomic Energy has proposed to establish a Fast Breeder ReactorProject (PFBR) of 500 MW capacity at a location 500 m south of MAPS.

Studies conducted Field data collection and analysis for

Condenser Cooling Water System(CCWS) of PFBR,

Mathematical model studies forlocation of intake/outfall for 500 MWePrototype Fast Breeder Reactorusing Numerical Model MIKE 21

Wave Flume studies for the designof outfall guide bund and shoreprotection works

Mathematical model studies forlittoral drift and thermal recirculationusing Numerical Model LITPACK.

Location Map and Intakes

Page 2: KALPAKKAM NUCLEAR POWER PROJECT, TAMILNADU

Central Water and Power Research Station, Pune

Recommended layout and implemented in field

Outcome and Benefits Field studies provided the data useful for

physical as well as mathematical modelstudies.

Numerical Model studies evolved thelocation of intakes to avoid recirculation ofwarm water.

Wave Flume studies accorded the criteriafor design of outfall guide wall and shoreprotection works Location map ofKalpakkam NPP.

Littoral drift studies confirmed theadvancement of coastline and its effect onnearby shoreline.

Allowable recirculation to intakes Power plant is operational to its capacity,

commercial power generation yet to start. Outfall channel is working properly

Recommended layout and implemented infield.

Shoreline advancement is limited.