keegan werlin llp - eversource energy · keegan werlin llp attorneys at law 265 franklin street...

41
KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS : ——— (617) 951-1354 (617) 951-1400 (617) 951-0586 April 8, 2015 Mark D. Marini, Secretary Department of Public Utilities One South Station, 5 th Floor Boston, MA 02110 Re: Long-Term Contracts for Renewable Energy Projects Pursuant to Section 83A of Chapter 169 of the Acts of 2008 Dear Secretary Marini: Pursuant to the Small Emerging Renewable DG requirement of Section 83A of the Green Communities Act (Chapter 169 of the Acts of 2008, or “GCA”) (hereinafter (“Section 83A”) 1 and 220 C.M.R. § 21.05(3), Fitchburg Gas and Electric Light Company d/b/a Unitil, Massachusetts Electric Company and Nantucket Electric Company d/b/a National Grid, NSTAR Electric Company and Western Massachusetts Electric Company, each d/b/a Eversource Energy (collectively, the “Distribution Companies” or “Petitioning Parties” and individually as a “Distribution Company”), request that the Department of Public Utilities (the “Department”) approve the timetable and method for the solicitation and execution of the long-term contracts for newly developed, small emerging or diverse renewable energy distributed generation facilities (“Small Emerging Renewable DG”) as set forth in this filing. Specifically, the Distribution Companies request that the Department approve the Request for Proposals (“RFP”) submitted herewith, which encompasses the timetable and method for solicitation to be used to solicit renewable power from Small Emerging Renewable DG (electricity and/or RECs) in accordance with Section 83A and 220 C.M.R. § 21.05(3). The RFP proposed for Department approval was developed jointly by the Distribution Companies and DOER after consulting with the Office of the Attorney General (“Attorney General”). It is based on and reflects key elements of the solicitation materials that were developed jointly by the Distribution Companies and DOER and were previously reviewed and approved by the Department pursuant to Section 83A in D.P.U. 13-57. The changes from the solicitation materials previously approved in D.P.U. 13-57 have been shared and discussed at length over the past several months at multiple meetings with both DOER and the Attorney General. 1 Section 83A was added to the GCA by Section 36, An Act Relative to Competitively Prices Electricity, St. 2012, c. 209.

Upload: others

Post on 21-Sep-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

KEEGAN WERLIN LLP ATTORNEYS AT LAW

265 FRANKLIN STREET

BOSTON, MASSACHUSETTS 02110-3113 TELECOP IERS :

——— (617) 951-1354

(617) 951-1400 (617) 951-0586

April 8, 2015 Mark D. Marini, Secretary Department of Public Utilities One South Station, 5th Floor Boston, MA 02110 Re: Long-Term Contracts for Renewable Energy Projects Pursuant to Section 83A of

Chapter 169 of the Acts of 2008 Dear Secretary Marini:

Pursuant to the Small Emerging Renewable DG requirement of Section 83A of the Green Communities Act (Chapter 169 of the Acts of 2008, or “GCA”) (hereinafter (“Section 83A”)1 and 220 C.M.R. § 21.05(3), Fitchburg Gas and Electric Light Company d/b/a Unitil, Massachusetts Electric Company and Nantucket Electric Company d/b/a National Grid, NSTAR Electric Company and Western Massachusetts Electric Company, each d/b/a Eversource Energy (collectively, the “Distribution Companies” or “Petitioning Parties” and individually as a “Distribution Company”), request that the Department of Public Utilities (the “Department”) approve the timetable and method for the solicitation and execution of the long-term contracts for newly developed, small emerging or diverse renewable energy distributed generation facilities (“Small Emerging Renewable DG”) as set forth in this filing. Specifically, the Distribution Companies request that the Department approve the Request for Proposals (“RFP”) submitted herewith, which encompasses the timetable and method for solicitation to be used to solicit renewable power from Small Emerging Renewable DG (electricity and/or RECs) in accordance with Section 83A and 220 C.M.R. § 21.05(3). The RFP proposed for Department approval was developed jointly by the Distribution Companies and DOER after consulting with the Office of the Attorney General (“Attorney General”). It is based on and reflects key elements of the solicitation materials that were developed jointly by the Distribution Companies and DOER and were previously reviewed and approved by the Department pursuant to Section 83A in D.P.U. 13-57. The changes from the solicitation materials previously approved in D.P.U. 13-57 have been shared and discussed at length over the past several months at multiple meetings with both DOER and the Attorney General.

1 Section 83A was added to the GCA by Section 36, An Act Relative to Competitively Prices Electricity, St.

2012, c. 209.

Page 2: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Section 83A Small Emerging Renewable DG Request for Proposals April 8, 2014 Page 2 of 5

Section 83A and the Department’s regulations, 220 C.M.R. § 21.00 et seq., provide that all Massachusetts distribution companies shall be required to jointly solicit proposals from renewable energy developers for the purpose of entering into cost-effective long-term contracts2 to facilitate financing of renewable energy generation (“Power Purchase Agreements” or “PPA(s)”). Section 83A further provides that distribution companies shall consider multiple contracting methods, including PPAs for renewable energy certificates (“REC”), for energy, and for a combination of both RECs and energy. The distribution companies must consult with the DOER and the Attorney General regarding the choice of contracting methods and solicitation method, and consult with DOER regarding a timetable for solicitation and execution of the PPAs before selecting a proposed timetable and method for solicitation and execution of such PPAs. Section 83A specifies that the method and timetable so selected shall be subject to review and approval by the Department. Section 83A requires that the distribution companies do not contract for more than four (4) percent, in the aggregate, of energy demand from the distribution companies’ service territories. Section 83A and 220 C.M.R. § 21.05(3) further provide that ten percent (10%) of the aggregate level of PPAs must be reserved for newly developed, small, emerging or diverse renewable energy distributed generation facilities (as determined by DOER) which are located within each distribution company’s service territory. These Small Emerging Renewable DG PPAs are to be acquired through separate competitive solicitations.

The DOER has issued a Determination of Eligible Technologies for this solicitation,3 and all prospective bidders will be expected to read and understand the requirements of the Determination of Eligible Technologies. Based on the Determination of Eligible Technologies and for purposes of the RFP, Small Emerging Renewable DG projects include: biogas from anaerobic digestion; hybrid anaerobic digestion and landfill gas projects; biomass energy; marine or hydrokinetic energy; emerging run-of-river hydroelectric; fuel cells using biogas or another eligible RPS Class I Renewable Fuel; wind turbines; solar thermal electric; and geothermal.4 In addition, the Small Emerging DG project developer can only submit a proposal if such project is located in the service territory of the Distribution Company and interconnected with its electric distribution system. The precise amount of energy and RECs to be contracted for by the Distribution Companies through this solicitation will depend on the bids submitted and ensuing contract negotiations. The development of the RFP involved careful consideration of a range of logistical and substantive issues involved in creating a standardized methodology for bid solicitation and evaluation of Small Emerging Renewable DG. The DOER will coordinate with each

2 Section 83A and 220 C.M.R. § 21.02 define long-term contracts as contracts for periods of between ten

(10) and twenty (20) years. 3 Green Communities Act Section 83A – Long Term Contract Carve-out Determination of Eligible

Technologies, October 23, 2013 (Amended October 15, 2014). 4 Additional parameters necessary for Small Emerging Renewable DG to qualify for the RFP, such as that

wind turbines must have a nameplate capacity of less than or equal to 99kW or use an innovative or emerging design different from standard horizontal axis turbines, are included on pages 1-2 of the RFP.

Page 3: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Section 83A Small Emerging Renewable DG Request for Proposals April 8, 2014 Page 3 of 5

Distribution Company regarding their respective solicitation. Although the development of the RFP is a collaborative process, the Distribution Companies will separately issue this RFP and will have individual responsibility for bid evaluation and selection. Each Distribution Company will evaluate and select bids consistent with the criteria described in the RFP. Each Distribution Company will individually negotiate and file the executed PPA(s) with the Department to obtain necessary approvals. The Distribution Companies anticipate that the PPA(s) will vary to an extent based on contracting requirements that are specific to each Distribution Company and Small Emerging Renewable DG project. Prior to short list selection, final bid selection, and filing of any PPA for approval with the Department, each Distribution Company will consult with DOER. The expectation of the Petitioning Parties is that the Department’s approval of the RFP will promote the transparency, consistency, and objectivity of the solicitation process, which in turn, will greatly facilitate the Department’s review of subsequent individual PPAs with the selected bidders so that those PPAs may be approved in an efficient and timely manner in furtherance of the objectives of Section 83A. The current expectation of the Petitioning Parties is that, upon Department approval of the RFP, each Distribution Company in consultation with and as coordinated by DOER will promptly issue the RFP along with the Bidder Forms and a draft PPA that would serve as the framework for PPAs. Each Distribution Company will individually evaluate and select the winning bid(s), and enter into a PPA with the winning bidder(s). Solicitation Method The Petitioning Parties have agreed, as set forth in the proposed RFP, to a collaborative process for this solicitation of long-term renewable energy from Small Emerging DG under Section 83A. DOER will coordinate the joint solicitation. The Distribution Companies, in consultation with DOER, have agreed to jointly issue the RFP, including associated forms but individually evaluate and select bids and negotiate PPAs with the winning bidder. See RFP, Section 1.3. Section II of the proposed RFP contains additional detail on the bid evaluation and selection criteria process. At the conclusion of the process, each Distribution Company will submit to the Department, within 29 days after the execution of each PPA, a request for approval of each executed PPA, pursuant to Section 83A and the Department’s regulations. At or following the time when a Distribution Company(ies) make(s) such a filing, the DOER will submit its assessment of the process and the merits of the proposed PPA(s). Solicitation Timetable Once the Department approves the method and timetable for solicitation and execution of the PPAs, as encompassed within the RFP, the Distribution Companies will promptly issue the RFP to a wide range of potentially interested parties. As set forth in Section 3.2 of the proposed RFP, a bidders conference will be held approximately two weeks after the RFP is issued. One week later will be the deadline for notice of intent to bid and submission of written questions.

Page 4: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Section 83A Small Emerging Renewable DG Request for Proposals April 8, 2014 Page 4 of 5

Section 3.1 of the proposed RFP further lists additional timeframes as follows: Submission of Proposals 42 Days from Issuance of RFP Selection of Short-Listed Proposals 120 Days from Submission of Proposals Negotiate and Execute PPAs 30 Days from Selection of Short-List Submit PPAs for Department Approval 29 Days from Execution of PPAs The Petitioning Parties believe that this schedule sets out a fair process for bidders and sufficient opportunity for Distribution Companies to: (1) evaluate their respective bids; (2) negotiate and execute cost-effective PPAs that satisfy the criteria under Section 83A; and (3) submit the resulting PPA(s) to the Department for approval. After the Department issues an order on a PPA, the Distribution Company will have five business days after the appeal period has lapsed and after any motions or appeals are resolved to review the terms of the order to determine if there are unsatisfactory terms that require further action (see Proposed RFP at Section 2.6). Accordingly, the Distribution Companies have, pursuant to Section 83A, consulted with DOER and the Attorney General regarding the choice of contracting methods and solicitation methods and the proposed timetable. The Distribution Companies and the DOER have agreed upon timetable and method for solicitation and execution of PPAs. Approval of this solicitation process and proposed RFP will allow the Petitioning Parties to move forward with the critically important effort of fostering the Commonwealth’s renewable energy goals. Thank you for your consideration of this Petition. Please contact the counsel for the respective Distribution Companies noted below if you have any questions. Respectfully submitted, FITCHBURG GAS AND ELECTRIC LIGHT COMPANY D/B/A UNITIL By its attorney, ______________________ William D. Hewitt, Esq. Roach Hewitt Ruprecht Sanchez& Bischoff, PC 66 Pearl Street Portland, ME 04101 207-747-4870

Page 5: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Section 83A Small Emerging Renewable DG Request for Proposals April 8, 2014 Page 5 of 5

MASSACHUSETTS ELECTRIC COMPANY AND NANTUCKET ELECTRIC COMPANY d/b/a NATIONAL GRID By its attorneys, _______________________ Brooke E. Skulley, Esq. Assistant General Counsel 40 Sylvan Road Waltham, MA 02451 781-907-1846

_________________________ John K. Habib, Esq. Keegan Werlin LLP 265 Franklin Street Boston, MA 02110 617-951-1400 NSTAR ELECTRIC COMPANY WESTERN MASSACHUSETTS ELECTRIC COMPANY D/B/A EVERSOURCE ENERGY By its attorney,

Daniel Venora, Esq. Keegan Werlin LLP 265 Franklin Street Boston, MA 02110 617-951-1400

Page 6: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

REQUEST FOR PROPOSALS

FOR

LONG-TERM CONTRACTS WITH NEWLY DEVELOPED, SMALL,

EMERGING OR DIVERSE RENEWABLE ENERGY DISTRIBUTED

GENERATION FACILITIES

Issuance Date: [date], 2015

To be Used by Distribution Companies:

Fitchburg Gas & Electric Light Company d/b/a Unitil Massachusetts Electric Company d/b/a National Grid

Nantucket Electric Company d/b/a National Grid NSTAR Electric Company d/b/a Eversource Energy

Western Massachusetts Electric Company d/b/a Eversource Energy

Massachusetts Department of Energy Resources

Page 7: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

ii

Table of Contents

I. Introduction and Overview ................................................................................................................ 1 1.1 Purpose of the Request for Proposals (“RFP”) ........................................................................ 1 1.2 The Framework Established Pursuant to Section 83A of the Act ........................................... 3 1.3 Procurement by Distribution Companies in Consultation with DOER ................................... 4 1.4 Procurement Process and Bid Evaluation Approach ............................................................... 4 1.5 Communications Between the Soliciting Parties and the Bidders ........................................... 5 1.6 RFP Process ............................................................................................................................. 5

II. Bid Evaluation and Selection Criteria and Process .......................................................................... 6 2.1 Overview of Bid Evaluation and Selection Process ................................................................ 6 2.2 Eligibility, Threshold and Other Minimum Requirements—Stage One of the Evaluation

Process ........................................................................................................................................ 6 2.2.1 Introduction ...................................................................................................................... 6 2.2.2 Eligibility Requirements ................................................................................................... 7 2.2.3 Threshold Requirements ................................................................................................... 9 2.2.4 Other Minimum Requirements ....................................................................................... 12 2.3 Second Stage Evaluation – Price and Non-Price Analysis .................................................... 14 2.3.1 Initial Evaluation Using Price-Related Evaluation Criteria ........................................... 14 2.3.2 Initial Non-Price Evaluation ........................................................................................... 14 2.4 Third Stage Evaluation – Re-ranking of Proposals ............................................................... 16 2.5 Contract Finalization Process ................................................................................................ 17 2.6 Regulatory Approval .............................................................................................................. 17

III. Instructions to Bidders ................................................................................................................... 18 3.1 Schedule for the Bidding Process .......................................................................................... 18 3.2 Bidders Conference; Bidder Questions; Notice of Intent to Bid ........................................... 18 3.3 Preparation of Proposals ........................................................................................................ 19 3.4 Submission of Proposals; Confidentiality.............................................................................. 19 3.5 Official Contact for the RFP .................................................................................................. 20 3.6 Organization of the Proposal ................................................................................................. 21 3.7 Modification or Cancellation of the RFP and Solicitation Process ....................................... 21

Appendix A Notice of Intent to Bid Appendix B Bidder Response Package Appendix C Draft Power Purchase Agreement

Page 8: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

1

I. Introduction and Overview 1.1 Purpose of the Request for Proposals (“RFP”) Fitchburg Gas & Electric Light Company d/b/a Unitil (“Unitil”), Massachusetts Electric Company and Nantucket Electric Company d/b/a National Grid (“National Grid”), NSTAR Electric Company and Western Massachusetts Electric Company, each d/b/a Eversource Energy (“Eversource”), as investor-owned electric distribution companies (collectively, “Distribution Companies” and each a “Distribution Company”) serving customers in the Commonwealth of Massachusetts, in coordination with the Massachusetts Department of Energy Resources (“DOER”), have developed this model request for proposals (“RFP”) for the supply of electric energy and/or Renewable Energy Certificates (“RECs”) from newly developed, small, emerging or diverse renewable energy distributed generation facilities under long-term power purchase agreements (“PPAs” and individually a “PPA”) pursuant to Section 83A of the Green Communities Act as added by chapter 209 of the Acts of 2012, An Act relative to competitively priced electricity in the Commonwealth (the “Act”). The Distribution Companies are soliciting energy and RECs from newly developed, small, emerging or diverse renewable energy distributed generation facilities for approximately 0.4% of each Distribution Company’s annual load to be procured pursuant to PPAs with a term of 10 to 20 years. The PPAs will be finalized between each Distribution Company and successful bidders based on the bids submitted and selected by each Distribution Company in accordance with the process set forth in this RFP.1 This RFP includes a draft Power Purchase Agreement (“Draft PPA”), detailing the terms by which the Distribution Companies would purchase energy and RECs from newly developed, small, emerging or diverse renewable energy distributed generation facilities.2 The DOER has issued a Determination of Eligible Technologies for this solicitation, and all prospective bidders should read and understand the requirements of that Determination. See Section 2.2 for the eligibility determination process. The Eligible Technologies for purposes of this solicitation are:

· Biogas from anaerobic digestion (AD). · Hybrid anaerobic digestion and landfill gas projects, where AD biogas is blended with

landfill gas, provided blending increases the electricity generation of the AD facility and the

1 The actual amount of electric energy and RECs to be procured under this RFP may depend on, among

other factors, each Distribution Company’s assessment of the bids submitted and the Distribution Company’s other commitments. Under Section 83A of the Act, each Distribution Company must purchase 0.4% of its annual load from newly developed, small, emerging or diverse renewable energy distributed generation facilities and this solicitation must occur prior to December 31, 2016. For purposes of this RFP, 0.4% of load for each of the Distribution Companies, based on 2011 data, is as follows:

· National Grid: 86,660 MWh/year · NSTAR Electric Company: 85,700 MWh/year · Unitil: 1,911 MWh/year · Western Massachusetts Electric Company: 14,604 MWh/year

2 As noted in Appendix C, the Draft PPA is intended to provide a general description of the terms that the Distribution Companies are willing to agree to. Each Distribution Company may have other or different requirements, and each Distribution Company shall individually finalize the PPA terms with any successful bidder.

Page 9: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

2

landfill was previously unable to have a viable energy generation project absent the AD facility. The energy contribution (measured in Btu) of the landfill gas to the electricity generated onsite has to be less than 50% of the annual onsite electricity generation based on projected steady-state operations.

· Biomass energy using an RPS Class I eligible biomass fuel and with high Overall Efficiency to meet RPS Class I standards, in combined heat and power applications or deploying alternative technologies.

· Marine or hydrokinetic energy, including but not limited to in-line hydro, tidal, current and wave energy.

· Emerging run-of-river hydroelectric technologies with direct passage of fish and other aquatic life and which do not use conventional water turbines.

· Fuel cells using biogas or another eligible RPS Class I Renewable Fuel. · Wind turbines, having a nameplate capacity less than or equal to 99kW, or using an

innovative or emerging design different from standard horizontal axis turbines (e.g. airflow acceleration) to the extent that it has either already been tested as a prototype or is a scale-up of a previously deployed or field-tested technology, or a field verification for small offshore wind projects in state waters.

· Solar thermal electric: solar energy used to generate electricity by heating up a fluid. · Geothermal energy to produce electricity using steam from reservoirs of hot water found a

few miles or more below the Earth's surface.

The fundamental purpose of the RFP is to satisfy the policy directives encompassed within Section 83A of the Act, which require each Distribution Company in consultation to: (1) solicit proposals from developers of renewable energy projects in a reasonable fashion; and (2) execute long-term PPAs in order to facilitate the financing of these projects.3 The standards and criteria set forth in this RFP are designed so that the proposals selected for contract finalization will serve the interests of Section 83A of the Act by furthering those projects that have a strong likelihood of being financed and constructed and that will provide a low cost source of long-term renewable energy supply to the Commonwealth. In addition to the statutory requirements set forth in Section 83A of the Act, the Distribution Companies developed this model RFP in accordance with regulation 220 CMR 21.05(3), promulgated under the Act by the Massachusetts Department of Public Utilities (“MDPU”). This RFP outlines the process that the Distribution Companies plan to follow to satisfy their obligations regarding solicitations required under Section 83A of the Act and applicable regulations; sets forth timetables regarding the solicitation process; provides information and instructions to prospective bidders; and describes the bid-evaluation process that will be followed once bids are received. 3 Per Section 83A, the Distribution Companies shall consult with the DOER and the Office of the Attorney

General regarding the choice of contracting methods and solicitation methods. Also, the joint solicitations required under Section 83A shall be coordinated among the electric distribution companies by the department of energy resources.

Page 10: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

3

Each Distribution Company is soliciting bids for qualifying distributed generation projects. The distributed generation facility can only apply for a long-term contract if the project site is located in the service territory of the Distribution Company and interconnected with its electric distribution system. A bidder will be required to demonstrate ownership of or sufficient rights to and control over the proposed project site in order to develop and operate the project. The developer of a project must apply for and receive a Statement of Qualification or conditional Statement of Qualification for its project from the DOER and present such document as part of the bid package (further details on this process are found at: http://www.mass.gov/eea/energy-utilities-clean-tech/renewable-energy/rps-aps/rps-aps-sqa/rps-class-i-statement-of-qualification-application.html). In addition, the developer shall be required to demonstrate that the project has, at a minimum, submitted the pre-application report request and has received the pre-application report in accordance with the applicable Distribution Company’s Standards for Interconnection. A bidder must review and understand all requirements of this RFP prior to submitting a proposal, and any proposal submitted should demonstrate that understanding and the ability to satisfy those requirements. Bidders are strongly encouraged to engage legal counsel and any necessary subject matter experts prior to submitting a proposal, so that all RFP requirements are evaluated, and, if selected, the bidder is prepared to promptly finalize an agreement. 1.2 The Framework Established Pursuant to Section 83A of the Act Section 83A of the Act and 220 CMR 21.05(3) provide that ten percent (10%) of the aggregate level of long-term contracts required thereunder is reserved for the output of newly developed, small, emerging or diverse renewable energy distributed generation facilities, as determined by DOER, which are located within each Distribution Company’s service territory and interconnected with its electric distribution system. Each Distribution Company is soliciting proposals for such distributed generation facilities separately through a competitive bidding process for the output of newly developed small, emerging or diverse renewable energy distributed generation facilities in an amount equal to approximately 0.4% of the Distribution Company’s demand. The long-term contracting obligation established by Section 83A of the Act is separate and distinct from the Distribution Companies’ obligation to meet applicable annual renewable portfolio standards (“RPS”) requirements pursuant to Section 11F of Chapter 25A of the General Laws. However, under Section 83A of the Act, the renewable generation resource from which energy and/or RECs are procured under a long-term PPA must be eligible to participate in the RPS program and to sell RECs under the program, and a Distribution Company may use RECs purchased under such a long-term PPA to satisfy its RPS requirements. Long-term PPAs are defined within Section 83A of the Act as PPAs having a term of 10 to 20 years. A Distribution Company may decline to consider PPA proposals having terms and conditions that it determines would place an unreasonable burden on the company’s balance

Page 11: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

4

sheet. All proposed PPAs are subject to the review and approval of the MDPU before becoming effective. Consistent with the directives set forth in Section 83A of the Act, MDPU has adopted regulations at 220 CMR 21.00 et seq. As part of its approval process, the MDPU must take into consideration the Office of the Attorney General’s (“AGO”) recommendations, which must be submitted to the MDPU within 45 days following the filing of a proposed PPA with the MDPU. Section 83A of the Act provides that the MDPU “… shall consider both the potential costs and benefits of such contracts and shall approve a contract only upon a finding that it is a cost effective mechanism for procuring low cost renewable energy on a long-term basis taking into account the factors outlined in this section.” 1.3 Procurement by Distribution Companies in Consultation with DOER The Distribution Companies and the DOER have agreed to collaborate on a DOER-coordinated process with respect to this solicitation required under Section 83A. Although the development of the RFP is a collaborative process, the Distribution Companies will separately issue this RFP. The purpose of this approach is to provide prospective bidders with consistent bid submittal and evaluation requirements across all territories. Responses to the RFP will be submitted to the applicable Distribution Company for evaluation and selection consistent with the terms of the RFP. Bidders must send the submittal to the applicable Distribution Company where the qualifying distributed generation project is to be interconnected. Each Distribution Company will have the responsibility for bid evaluation and selection consistent with the criteria described in this RFP, and PPA finalization and PPA execution with any successful bidders with qualifying distributed generation projects located in that Company’s service territory and interconnected with its electric distribution system. Each Distribution Company will separately file executed PPAs with the MDPU for approval before they become effective. Prior to short listing and bid selection, entering into any PPA, and filing any PPA for approval with the MDPU, the Distribution Companies will consult with DOER. At or after such time that an executed PPA is proposed to the MDPU, DOER will submit its assessment of: (1) the process followed by the Distribution Companies resulting in the execution of the PPA; and (2) the merits of the particular PPA proposed for approval. 1.4 Procurement Process and Bid Evaluation Approach The procurement process is designed to have three stages of evaluation, as described in Section 2.1 of the RFP. Initially, bids will be evaluated on the basis of whether certain eligibility and threshold requirements are satisfied. Eligibility requirements are designed to ensure that the bids under review offer the appropriate product and PPA tenor from qualifying renewable resources. Threshold requirements are designed to ensure that proposed projects satisfy statutory criteria under Section 83A of the Act, and meet minimum standards for viability. In the second stage, bids will be evaluated in a technology-neutral manner based on specified price and non-price evaluation criteria. This portion of the bid evaluation will be quantitative in

Page 12: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

5

nature (i.e., a quantitative scoring system will be utilized). Projects that pass the eligibility and threshold review and are scored favorably in the second stage of the evaluation process will be placed on a short list and advance to the final stage of the evaluation process. At this third stage of the process, further evaluation of those remaining bids shall be conducted on matters pertaining to price, project viability and the extent to which the bids, individually and as a portfolio, achieve a variety of objectives, including cost effectiveness and diversity of resources, and the remaining bids may be re-ranked based on this analysis. All three stages of the evaluation process, including the pertinent criteria, are described in Section II of this RFP. 1.5 Communications Between the Soliciting Parties and the Bidders With the exception of the pre-bid conference (see Section 3.2 below), all pre-bid contact with prospective bidders and other interested parties will be via the website at: www.marfp.com. Links will be available on that site for submitting questions to a Distribution Company, and responses will be coordinated by DOER and posted on www.marfp.com and the applicable Distribution Company’s website. Bids will be submitted directly to each Distribution Company at the addresses set forth in Section 3.5 of this RFP, and must contain firm pricing as detailed in Section 2.2.4.1. Bids may not be withdrawn or modified once submitted without the written consent of the applicable Distribution Company. All communications regarding the bidding process and submitted bids will be conducted directly between the applicable Distribution Company and the bidder. It will be the responsibility of the bidders to keep the applicable Distribution Company informed about the details of their projects, such as status in obtaining permits and financing. 1.6 RFP Process The timeline for the bidding process following the issuance of this RFP, as well as the schedule for other steps in the process including approval by the MDPU, is set forth below at Section 3.1. 1.7 Bidder Certification An authorized officer or other authorized representative of a bidder shall certify with its submission of its bid that:

(1) The bidder has reviewed this RFP and all attachments and has investigated and informed itself with respect to all matters pertinent to this RFP and its proposal;

(2) The bidder has had an opportunity to consult with legal counsel, financial and other subject matter experts to confirm the bidder’s ability to satisfy the requirements of this RFP and as contemplated under the draft PPA;

(3) The bidder's redline of the draft PPA included with its proposal contains all of the bidder's proposed modifications to the draft PPA and the bidder is prepared to execute the draft PPA included with its proposal;

(4) The bidder’s proposal is submitted in compliance with all applicable federal, state and local laws and regulations, including antitrust and anti-corruption laws;

Page 13: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

6

(5) The bidder is bidding independently and that it has no knowledge of the substance of any proposal being submitted by another party in response to this RFP other than a response submitted by the bidder’s affiliate, which must be disclosed in writing to each applicable Distribution Company with the proposal; and

(6) The bid contains firm pricing as detailed in Section 2.2.4.1. Violation of any of the above requirements may be reported to the appropriate government authorities and will disqualify the bidder from the RFP process.

II. Bid Evaluation and Selection Criteria and Process 2.1 Overview of Bid Evaluation and Selection Process Once bids are received by the Distribution Company, the proposals will be subject to a consistent and defined review, evaluation and short-list selection process. The first stage (“Stage One”) consists of a review of whether the bids satisfy specified eligibility, threshold and other minimum requirements set forth in Section 2.2 of this RFP. The second stage (“Stage Two”) consists of a combined price and non-price evaluation of bids that pass the first stage review, as described in Section 2.3 of this RFP. Bids that are selected for further review will enter a final stage of review (“Stage Three”) which will involve additional risk assessment and consideration of the bids from a portfolio perspective consistent with the criteria set forth in Section 2.4 of this RFP. The selection of the short list will be made by each Distribution Company. Subsequent to the selection of the short list, each Distribution Company will conduct an additional evaluation and selection of bids for contract finalization. This post-short list selection stage of the process is described in Section 2.5 of this RFP. 2.2 Eligibility, Threshold and Other Minimum Requirements—Stage One of the

Evaluation Process

2.2.1 Introduction Each bid must satisfy requirements pertaining to eligibility, a variety of threshold requirements and other requirements, including bidder certifications and allowable pricing. Following receipt of the bids, the bids will be reviewed to determine whether they satisfy these minimum requirements.4 Bids that do not satisfy these Stage One requirements may be disqualified from further review and evaluation. Stage One requirements are set forth in the following section of this RFP.

4 The Distribution Company, at its discretion, may conduct additional evaluation on bids before the Stage

One evaluation is completed.

Page 14: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

7

2.2.2 Eligibility Requirements All proposals must meet the following eligibility requirements set forth below. Specifically, proposals will be considered from an Eligible Bidder with respect to Eligible Products generated from an Eligible Facility. The Eligible Products must be offered over the Allowable Contract Term in quantities that are not larger than the Maximum Contract Size. Failure to meet any of these requirements could lead to disqualification of the proposal from further review and evaluation.

2.2.2.1 Eligible Bidder An “Eligible Bidder” is the owner of an Eligible Facility or the development rights to an Eligible Facility, i.e., the developer of the Eligible Facility, in each case meeting the eligibility requirements described in this section. An Eligible Bidder is both creditworthy and in good standing with regard to all accounts and obligations it may have to the Distribution Company that serves the Eligible Facility’s proposed location. In determining “good standing,” a Distribution Company may consider compliance with obligations under an interconnection service agreement, any pending disputes or proceedings, any amounts due for electric and gas accounts, fulfilling the requirements of an approved payment plan, or amounts due to the Distribution Company for other reasons.

2.2.2.2 Eligible Facility An “Eligible Facility” is a distributed generation facility that is interconnected at the distribution system level of the electric grid and satisfies each of the following standards:

a. The distributed generation facility must be located in the service territory of the Distribution Company and interconnected with its electric distribution system.

b. The distributed generation facility shall have a nameplate capacity not larger than 6

megawatts.

c. The distributed generation facility must: (1) qualify as a RPS Class 1 Renewable Generation Unit under DOER’s Class 1 Renewable Energy Portfolio Standard regulations, 225 CMR 14.01, et seq., and qualify to sell RECs under the RPS Program; (2) utilize an eligible technology as stated in the DOER’s most recent “Determination of Eligible Technologies”, and not more than 30MW of capacity using that technology was installed in Massachusetts prior to April 1, 2012 (as determined by DOER); and, (3) have received a Statement of Qualification or conditional Statement of Qualification from DOER (further details are found at http://www.mass.gov/eea/energy-utilities-clean-tech/renewable-energy/rps-aps/rps-aps-sqa/rps-class-i-statement-of-qualification-application.html). The bidder is required to submit with its bid of the Statement of Qualification or conditional Statement of Qualification for its project issued by the DOER.

Page 15: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

8

d. The distributed generation facility must have a commercial operation date, as verified by DOER, on or after January 1, 2013 or be either a capacity expansion of an existing generation facility or a repowering of an existing generation facility that was not previously a RPS Class 1 Renewable Generation Unit, where the capacity expansion or repowering has a commercial operation date, as verified by DOER, on or after January 1, 2013. With respect to a capacity expansion or repowering of an existing generating unit, only the energy and RECs associated with the incremental capacity resulting from that expansion or repowering will be eligible to submit a proposal for this RFP. In addition, an eligible facility must be able to make the required demonstration under Section 2.2.3.12 regarding the facilitation of financing of renewable energy generation.

e. The distributed generation facility shall not receive net metering services as a Class I, II

or III net metering facility, pursuant to G.L. c. 164, § 138 and 139. An Eligible Facility can seek qualification as a net metering facility while simultaneously bidding for a long term contract under this RFP, provided that if the project is awarded a long term contract, it must demonstrate in writing it (a) has withdrawn its application for a cap allocation if the project does not currently receive net metering services, or (b) relinquished net metering services if the project is currently receiving net metering services.

f. The distributed generation facility must have, at a minimum, submitted the pre-

application report request and received the pre-application report in accordance with Distribution Company’s Standards for Interconnection.

2.2.2.3 Eligible Products An Eligible Bidder must propose separate prices to sell from an Eligible Facility under a PPA: (1) electric energy; (2) RECs; and (3) bundled electric energy and RECs. Any RECs sold under a PPA will only be purchased by the applicable Distribution Company to the extent that those RECs conform to the eligibility criteria for a RPS Class I Renewable Generation Unit under DOER’s Class I Renewable Energy Portfolio Standard regulations, 225 CMR 14.01, et seq. If a Distribution Company agrees to purchase both electric energy and RECs under a PPA and the RECs cease to conform to the RPS Class I eligibility criteria, the applicable Distribution Company will thereafter only purchase electric energy under that PPA at the price attributable to that electric energy, and the Seller will be permitted to sell those non-conforming RECs to a third party. Solar renewable energy certificates that are eligible under DOER’s Solar Carve-Out Program will not be considered Eligible Products under this solicitation. The Draft PPA (attached as Appendix C to this RFP) contains terms for the sale of both electric energy and RECs, although the purchase and sale under a particular PPA may be only for energy or only for RECs, rather than for both energy and RECs. The Distribution Companies will not purchase capacity under any PPA that result from this RFP process.

Page 16: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

9

2.2.2.4 Allowable Contract Term Consistent with Section 83A of the Act, an Eligible Bidder may submit a proposal for the sale of Eligible Products from an Eligible Facility for a term of 10 to 20 years. Each proposal must contain two offers for the sale of the Eligible Products, with price and term lengths that are five years apart (e.g., 10 years and 15 years, 11 years and 16 years, etc.). Both offers must conform to the allowable contract term of 10 to 20 years and will be evaluated as set forth in Section 2.3.1 of this RFP.

2.2.2.5 Maximum Facility Size

Distributed generation projects qualifying under this RFP shall have a nameplate capacity not larger than 6 megawatts.5 A bidder must bid the energy and/or RECs from its proposed Eligible Facility. Bidders are reminded that each Distribution Company intends to procure not more than 0.4% of their respective distribution loads in this RFP process.

2.2.3 Threshold Requirements

2.2.3.1 Introduction Bids that meet all the Eligibility Requirements will be evaluated to determine compliance with threshold requirements, which have been designed to screen out proposals that do not satisfy the requirements set forth in Section 83A of the Act; have not demonstrated project development, technical or financial viability and capability; are insufficiently mature from a project development perspective; involve ineligible technology; lack technical viability; impose unacceptable financial accounting consequences for the Distribution Company; are not in compliance with RFP requirements pertaining to credit support; or fail to satisfy minimum standards for bidder experience and ability to finance the proposed project. The threshold requirements for this RFP are set forth below.

2.2.3.2 Reasonable Project Schedule Absent other compelling circumstances, each Distribution Company is interested in projects that can demonstrate the ability to develop, permit, finance, and construct the proposed Eligible Facility within a reasonably proximate time. To that end, Eligible Bidders must provide a reasonable schedule that provides for closing of construction financing and commencement of construction on or by July 1, 2017 and a commercial operation date on or by July 1, 2018. A proposal that does not have a reasonable schedule that provides sufficient time for the application for, and receipt of, necessary permits and approvals may be determined not to have satisfied this threshold requirement. In addition, a proposal that is determined to have a “fatal 5 DOER specifies that the nameplate capacity will be (a) the rated AC capacity of the power generating

installation or (b) in the case of co-firing or blending an RPS Class I eligible with an ineligible fuel, the capacity represented by the average annual portion of the total electrical output that qualifies as RPS Class I Renewable Generation.

Page 17: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

10

flaw” such that it will be unable to obtain permits or property rights necessary to finance and construct the proposed project may be determined not to have satisfied this threshold requirement.

2.2.3.3 Site Control The bidder must demonstrate that it has control or a right to acquire control over a site for its proposed project. To meet this threshold requirement, bidders must provide documentation showing that they own or lease (or have an executed an unconditional option to own or lease) the site on which the proposed project will be located, and that they have any additional rights required to develop, operate, and interconnect the project at the site.

2.2.3.4 Technical Viability; Ability to Finance the Proposed Project The bidder must demonstrate that the technology it proposes satisfies the DOER’s eligibility requirements, is technically viable for the proposed site, the bidder has the right to employ the technology, and that the bidder has the ability to finance the proposed project. Technical viability may be demonstrated by showing that the technology is commercially available and has been used successfully. If a bidder plans to use technology that is not commercially accepted, it must provide evidence of technical viability and a credible plan to finance the project in light of the state of development of the technology. The bidder must demonstrate its own creditworthiness, and must provide a reasonable plan for financing the proposed project, including the funding of development costs and the required development period security and the ability to acquire the required equipment in the time frame proposed.

2.2.3.5 Experience The bidder must demonstrate that it has a sufficient amount of relevant experience to successfully develop, finance, construct and operate its proposed project. This demonstration can be made by showing that bidder (or a substantial member of bidder’s development team) has:

a. Successfully developed a similar type of project; OR

b. Successfully developed one or more projects of different technologies but of similar size or complexity or requiring similar skill sets; AND

c. Experience in financing power generation projects.

2.2.3.6 Contribution to Electricity Reliability within Massachusetts One criterion for approval of a long-term contract by the MDPU under Section 83A of the Act is that the proposed generation project must “provide enhanced electricity reliability within the commonwealth.” Bidders are encouraged to provide any documentation that would aid in making this determination related to their project.

Page 18: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

11

2.2.3.7 Contribution to Moderating System Peak Load Requirements

Another criterion under Section 83A of the Act is that a proposed project must “contribute to moderating system peak load requirements.” This threshold requirement can be satisfied by the bidder’s demonstration of projected energy output during the peak hours identified by the Independent System Operators of New England, Inc. (ISO-NE) summer and/or winter peak periods. For purposes of this RFP, these hours are 1 PM through 6 PM for the months of June through September (summer period), and 5 PM through 7 PM for the months of October through May (winter period).

2.2.3.8 Contribution to Employment; Economic Development Benefits

Another criterion under Section 83A of the Act is that a proposed project creates additional employment and economic development in Massachusetts, where feasible. This threshold requirement can be satisfied by a showing of both direct and indirect employment benefits as well as economic benefits associated with the project.

2.2.3.9 Security Requirements Bidders will be required to post Development Period Security and Operating Period Security. The required level of Development Period Security is the maximum hourly output in kWh multiplied by $25. Fifty percent (50%) of the Development Period Security must be provided within five business days after notification of selection and, before the finalization of a PPA commences. The remaining fifty percent (50%) of the Development Period Security must be provided within 15 business days after MDPU approval of the PPA. Development Period Security will be promptly returned if the MDPU does not approve the PPA. Once a project achieves Commercial Operation, the amount of required security (Operating Period Security) will be the same as the required amount of Development Period Security. The required security must be in the form of a cash deposit, or a letter of credit in a form and from an issuer acceptable to the applicable Distribution Company.

2.2.3.10 Unreasonable Balance Sheet Impacts Section 83A of the Act provides that a Distribution Company may decline to consider contract proposals having terms and conditions that it determines would place an unreasonable burden on the Distribution Company’s balance sheet. Each individual Distribution Company retains the right to make such a determination based upon its evaluation of particular proposals. In the Response Package, bidders are required to provide information that will assist the Distribution Companies in determining whether a contract based on the proposal submitted

Page 19: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

12

would place an unreasonable burden on its balance sheet.6 If a Distribution Company determines that a proposal would impose such a burden or at least a substantial risk of such a burden, it will notify the bidder in writing and will explore with the bidder whether the proposal and the terms of the power purchase agreement can be modified to prevent an unreasonable burden being placed on the Distribution Company’s balance sheet. If after such process, the Distribution Company determines that the bidder’s proposal, as it may have been modified, or the terms of the proposed agreement, places an unreasonable burden on the Distribution Company’s balance sheet, it may decline to give further consideration to the proposal. The Distribution Companies reserve the right to review contract proposals for balance sheet impacts at any time during the evaluation process. For example, a Distribution Company might only review highly ranked project proposals for their balance sheet impact.7

2.2.3.11 Timeliness

The bid must be timely submitted in accordance with Sections 3.1 of this RFP.

2.2.3.12 Facilitate Financing of Renewable Energy Generation

The bidder must demonstrate, as a threshold matter, that its proposal advances the goal of Section 83A of the Act for the selection of cost-effective long term contracts that facilitate the financing of renewable energy generation. The bidder should specify how a PPA resulting from this RFP process would either permit it to finance a project that would otherwise not be financeable or assist it in obtaining financing of its project.

2.2.4 Other Minimum Requirements

Other RFP requirements pertain to bid certification, allowable pricing and bid completeness, as described in this section.

2.2.4.1 Proposal Certification

Bidders are required to provide firm pricing for 180 days from the due date for submission of proposals. The bidder must also sign the certification form in Appendix B verifying that the prices, terms and conditions of the proposal are valid for at least 180 days and bids may not be modified or withdrawn without the Distribution Company’s consent during this period. An 6 Review of balance sheet impacts would include, but not be limited to, a Distribution Company’s

assessment of whether a proposal would result in the seller under the proposed PPA being a variable interest entity that would trigger consolidation of seller’s finances on to the Distribution Company’s balance sheet under Accounting Standards Codification (ASC) Topic 810 “Consolidation” and any other applicable or updated ASC topic.

7 In connection with this review, a bidder, at the request of the Distribution Company, may be required to provide pro forma income and cash flow statements for the term of the proposed PPA (including revenue and cost data by major categories, debt service, depreciation expense and other relevant information).

Page 20: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

13

officer or duly authorized representative of the bidder is required to sign the Proposal Certification Form.

2.2.4.2 Allowable Forms of Pricing

The Distribution Companies will accept proposals from renewable resources for energy and/or RECs that conform to the following requirements:

(a) Proposals must offer one or a combination of the following pricing options:

(1) a fixed flat price (in $/MWh and/or $/REC) for the term of the contract; or

(2) a fixed price (in $/MWh and/or $/REC) that increases by a fixed rate for the term of the contract (e.g. 2% increase per year).

(b) Proposals for a bundled price for energy and RECs must allocate the total

bundled price between energy and RECs, with only the energy being purchased at the stated energy price if the RECs cease to conform to the eligibility criteria for a RPS Class 1 Renewable Generation Unit under DOER’s Class 1 Renewable Energy Portfolio Standard regulations, 225 CMR 14.01, et seq. All else being equal, a preference will be given to an allocation of the price between energy and RECs that most closely aligns with the market value of those products.

(c) Proposed prices may not be conditioned upon or subject to adjustment based upon the availability or receipt of any government grant or subsidy or tax credits.

These forms of pricing are conforming under this RFP. The Distribution Companies are under no obligation to consider or accept any form of alternative pricing.

Each Bidder must identify a Delivery Point for electric energy, which must be at the revenue meter located on the Distribution Company’s distribution system. All costs associated with such delivery shall be borne by the Bidder.

2.2.4.3 Bid Completeness: Bidder Response Forms and Draft PPA Bidders must use the forms provided in Appendix B and provide complete responses. Appendix B contains the Bidder Response Forms which outline the information required from each bidder. Bidders are required to provide the information requested in each section of the Bidder Response Form. If any of the information requested is inconsistent with the type of technology or product proposed, the Bidder should include “N/A” and describe the basis for this designation. If a bidder does not have the information requested in the bid forms and cannot obtain access to that information prior to the bid submittal due date, the bidder should provide an appropriate explanation. Prior to submitting a bid, Eligible Bidders must review Appendix C, which is the draft Power Purchase Agreement (Draft PPA). Each Distribution Company may require company-specific terms on certain PPA provisions, which will be identified in the Draft PPA. If bidders do not

Page 21: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

14

propose to make any changes to the Draft PPA, they must so state. If an Eligible Bidder does wish to propose revised terms, it must provide a red-line version of the Draft PPA with all of the requested changes, specific language for each proposed change, and a detailed description of, and justification for, each proposed change. Each bidder must be willing to execute a PPA in the form attached to its bid, barring any extraordinary circumstances (e.g., changes in ISO-NE rules, etc.). Proposed changes to the material terms of the Draft PPA will be reviewed and considered in the context of a value and risk assessment. A Distribution Company has no obligation to accept any changes to the Draft PPA that are proposed by any bidder. 2.3 Second Stage Evaluation – Price and Non-Price Analysis Proposals that meet the requirements of the first stage review will then be subject to an initial price and non-price analysis. The results of the price and non-price analysis will be a relative ranking and scoring of all proposals. The Distribution Companies plan to weight price factors at 80 percent (80%) and non-price factors at 20 percent (20%) for purposes of conducting the second stage evaluation.

2.3.1 Initial Evaluation Using Price-Related Evaluation Criteria The price evaluation will be based on a comparison of: (1) the total cost (on both a unitized and net present value basis) of the products bid, which may include energy and/or RECs to (2) the estimated market value of these products, and discount factor equal to the weighted average cost of capital of the Distribution Company (for purposes of net present value calculations). The Distribution Companies plan to use a price forecast for energy derived from the NYMEX futures, and broker quotes for RECs. The metric used will be net $/MWh cost or benefit, on a net present value basis. That metric will be developed by the Distribution Companies. Each bidder will be responsible for all costs associated with interconnecting its project to the distribution system at its proposed Delivery Point.

Proposals will be ranked from highest to lowest net benefit (or lowest to highest net cost) on a dollars per MWh basis based on the result derived through the application of the methodology described above.

2.3.2 Initial Non-Price Evaluation

The non-price evaluation will be conducted separately by each applicable Distribution Company and will consist of five overall categories: (1) siting and permitting; (2) project development status and operational viability; (3) experience and capabilities of bidder and the project development team; (4) financing; and (5) exceptions to the Draft PPA. Within each category are a number of related criteria that will be considered in the evaluation. This section of the RFP will identify and describe in more detail the individual criteria within each primary category. The relative importance of each of the criteria in terms of the scoring of the bids will be developed prior to receipt of bids and will be utilized during the bid evaluation process.

Page 22: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

15

2.3.2.1 Purpose of Non-Price Evaluation Criteria

The non-price evaluation criteria other than contract exceptions are designed to assess the likelihood of a project coming to fruition based on various factors critical to successful project development. The objectives of the criteria are to provide an indication of the feasibility and viability of each project and the likelihood of meeting the proposed commercial operation date. Proposals are preferred that can demonstrate, based on the current status of project development and past experience, that the project will likely be successfully developed and operated as proposed. The purpose of contract exceptions as a non-price evaluation criterion is to assess the extent to which a bidder seeks to change the terms of the Draft PPA in a manner that is adverse to the Distribution Companies and their customers.

2.3.2.2 Factors to be Assessed in Non-Price Evaluation

Within each of the five non-price evaluation factors, a variety of project and proposal-related factors will be assessed. They are summarized as follows:

· Siting and permitting o Extent to which site control has been achieved, including acquisition of

necessary easements or rights-of-way o Identification of required permits and approvals o Status of efforts and credibility of plan to obtain permits and approvals o Community relations plan

· Project development status and operational viability o Completeness and credibility of detailed critical path schedule; ability to

meet scheduled construction start date and commercial operation date o Credibility of fuel resource plans or energy resource assessments o Reliability of proposed technology o Commercial access to proposed technology, associated equipment and

materials o Progress in interconnection process

· Experience and capabilities of bidder and project development team o Project development o Project financing o Operations and maintenance o Experience in the ISO-NE market

· Financing o Credibility of financing plan o Financial strength of project sponsors

· Exceptions to Draft PPA o The extent to which bidder accepts provisions of the Draft PPA o The extent to which bidder proposes exceptions that are adverse to the

Distribution Company buyers

The non-price evaluation will be conducted in a systematic fashion. The Distribution Companies will conduct the price evaluation before they conduct the non-price evaluation, and

Page 23: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

16

they may elect not to conduct the non-price evaluation for any proposal that could not be successful based on the difference between its price and the price of competing proposals. Following the total price and non-price rankings conducted in this second evaluation stage, a further review of the bids will be conducted and a short list selected. The Distribution Company may elect to provide all bidders on this short list with an opportunity to improve the pricing in their proposals (including the allocation of any bundled pricing between electric energy and RECs) prior to the third evaluation stage. DOER will be provided with a copy of the proposals that are selected for the short list, including any improvements to the pricing in those proposals, and an explanation of the Distribution Companies’ rationale for selecting those proposals for the short list. It is expected that not all proposals will be placed on the short list and that not all proposals on the short list will be offered the opportunity to finalize a PPA. 2.4 Third Stage Evaluation – Re-ranking of Proposals In this third stage of the evaluation, the Distribution Company will re-rank the proposals on the short-list based on the second stage evaluation criteria and, at their discretion, the following additional factors:

· Cost effectiveness of the bid;

· Project viability; o Viability of the proposed technology

o Viability of the project plan

o Interconnection challenges

· The extent to which additional employment and economic development would be created;

· Any unique risks to customers that may be associated with projects; In order to provide greater assurance that the RFP will lead to successful results, DOER and the Distribution Companies believe that a third stage evaluation process that uses the second stage evaluation as a guide and provides for a reasonable degree of considered judgment based on criteria specified in this RFP is an important part of the RFP bid evaluation and selection process. The objective of the third stage of evaluation is to select the proposal(s) which provide the greatest value consistent with the stated objectives and requirements as set forth in the RFP. Generally, DOER and the Distribution Companies prefer viable projects that provide low cost renewable energy with limited risk and some degree of resource diversity consistent with the goals of the small generator carve out. However, the Distribution Companies recognize that any particular project may not be ranked highly with respect to all of these considerations and the

Page 24: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

17

extent to which the stated RFP objectives will be satisfied will depend, in large part, on the particulars of the proposals that are submitted. 2.5 Contract Finalization Process Bidders selected by a Distribution Company for contract finalization will be required to indicate in writing to the Distribution Companies whether they intend to proceed with their proposals within five business days of being notified. As previously noted, fifty percent (50%) of the Development Period Security must be provided at that time. Any bidder that fails to honor the contract finalization schedule may be eliminated from consideration by the Distribution Company. 2.6 Regulatory Approval The obligations of both the Distribution Company and the successful bidder to perform under each PPA shall not become effective or binding until receipt of MDPU approval as described in each PPA. After the Distribution Company and successful bidder have executed a PPA as a result of this RFP process, the Distribution Company intends to submit the proposed PPA to the MDPU for review and approval within 30 days of execution, unless circumstances require a longer period to prepare the MDPU filing materials. Any bidder requiring MDPU approval of its PPA by a certain deadline must state that deadline in its proposal, and that deadline will be considered in assessing the overall viability of the bidder’s project. The PPAs filed for approval by the MDPU as a result of this RFP will be filed under Section 83A of the Act and the MDPU’s applicable regulations. Section 83A, as implemented by the MDPU, establishes several requirements relating to the MDPU’s review and approval. In addition, the MDPU has promulgated regulations at 220 CMR 21.00 et seq, setting forth the criteria for its review pursuant to the requirements of Section 83A of the Act. When evaluating a proposed PPA, the MDPU will consider the recommendations of the AGO, which must be submitted to the MDPU within 45 days of the filing of the proposed PPA. Once the MDPU issues a decision approving a Distribution Company’s request for approval of an executed PPA, the Distribution Company shall have five (5) business days after the appeal period has elapsed and after any motions or appeals are resolved to review the form and substance of the Department’s approval. The Distribution Company shall have the opportunity to terminate the PPA if the MDPU’s approval contains terms or conditions that are deemed to be unsatisfactory to the Distribution Company, in its sole discretion. Terms or conditions that may be unsatisfactory include but are not limited to denial of annual remuneration equal to 2.75 percent of the annual payments under the contract, which is required by Section 83A and is intended to compensate the Distribution Company for accepting the financial obligation of the long-term contract at issue.

Page 25: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

18

III. Instructions to Bidders 3.1 Schedule for the Bidding Process The proposed schedule for the bidding process is set forth in Chart 1.8 The Distribution Companies reserve the right to revise the schedule as necessary. Any changes to the schedule up to and including the due date for submission of bids will be posted on the website for this RFP.

Chart 1

RFP Schedule [Included for illustrative purposes, and assumes that MDPU Order permits RFP Issuance on X

date]

Event Anticipated Dates Issue RFP [Day T] [date, 20xx] Bidders Conference [T+14] [date, 20xx] Submit Notice of Intent to Bid [T+21] [date, 20xx] Deadline for Submission of Questions [T+21] [date, 20xx] Due Date for Submission of Proposals [T+42] [date, 20xx] Selection of Short-Listed Bidders [T+162] [date, 20xx] Finalize and Execute Contracts [T+192] [date, 20xx] Submit Contracts for MDPU Approval [T+221] [date, 20xx]

3.2 Bidders Conference; Bidder Questions; Notice of Intent to Bid A Joint Bidders Conference with all of the Distribution Companies in attendance will be held for interested persons approximately two weeks after the final RFP document is posted on the RFP website. The purpose of the Bidders Conference is to provide the opportunity to clarify any aspects of the RFP. Prospective bidders are encouraged to submit questions about the RFP prior to the Bidders Conference. The Distribution Companies will attempt to answer questions submitted prior to and during the Bidders Conference. Although the Distribution Companies may respond orally to questions posed at the Bidders Conference, only written answers that are provided in response to written questions will be official responses. The Distribution Companies will also accept written questions pertaining to the RFP following the Bidders Conference up to the date set forth in Chart 1. Both the questions and the written responses will be posted on the RFP website (without identifying the person who asked the question). Prospective bidders are also encouraged to submit a Notice of Intent to Bid form within 21 days of issuance of the RFP. The Notice of Intent to Bid form is attached as Appendix A to the RFP. The Distribution Companies will provide any updates by email regarding the RFP to 8 The Distribution Companies can offer no assurance that any particular schedule will be observed or that

any particular project will otherwise qualify for any tax credit or other subsidy.

Page 26: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

19

prospective bidders who submit a Notice of Intent to Bid. Persons that submit a Notice of Intent to Bid are not obligated to submit a proposal. 3.3 Preparation of Proposals Each bidder shall have sole responsibility for carefully reviewing the RFP and all attachments and for thoroughly investigating and informing itself with respect to all matters pertinent to this RFP and its proposal, including pertinent ISO-NE tariffs and documents. Bidders should rely only on information provided in the RFP and any associated written updates when preparing their proposals. Each bidder shall be solely responsible for and shall bear all of its costs incurred in the preparation of its proposal and/or its participation in this RFP. 3.4 Submission of Proposals; Confidentiality Each bidder must submit one original ring-bound copy of their entire proposal and three readable USB ‘flash’ drives that contain a copy of the entire proposal to the Official Contact for the Distribution Company that is intended to receive the proposal. Bids must be submitted by noon eastern prevailing time on the due date for proposals, as set forth in Section 3.1. Fax or email submissions will not be accepted. The Distribution Companies reserve the right to reject any proposals received after the deadline. Each proposal shall contain the full name and business address of the bidder and the bidder’s contact person and shall be signed by an authorized officer of the bidder. A bidder may sign the original proposal and include scanned copies of the signature page with the electronic copies of the proposal. A bidder must clearly identify all confidential information in a Proposal. However, a bidder should take care to designate as confidential only those portions of a Proposal that genuinely warrant confidential treatment. The practice of marking each and every page of a Proposal as “confidential” is discouraged. The Distribution Companies shall use commercially reasonable efforts to treat the confidential information that they receive from bidders in a confidential manner and to not, except: (1) as required by law; (2) pursuant to a request for information in a regulatory or judicial proceeding; or (3) pursuant to a request for information by a public utilities commission with supervisory authority over any of the Distribution Companies or their affiliates, disclose such information to any third party or use such information for any purpose other than in connection with this RFP; provided, however, that if such confidential information is sought in any regulatory or judicial inquiry or proceeding or pursuant to a request for information by a public utilities commission with supervisory authority over any of the Distribution Companies or their affiliates, the Distribution Companies shall take reasonable steps to limit disclosure and use of said confidential information through the use of non-disclosure agreements or requests for orders seeking protective treatment, and shall inform the bidders that the confidential information is being sought. Bidders are advised that the Distribution Companies will share bid information with DOER and the AGO to facilitate DOER’s and the AGO’s ability to perform their roles under Section 83A, which include their obligations to assess: (1) the process followed by the

Page 27: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

20

Distribution Companies; and (2) the merits of one or more PPAs proposed for approval to the MDPU. Pursuant to G.L. c. 25A, § 7, DOER has statutory authority to protect price, inventory and product delivery data. Notwithstanding the foregoing, in the event such confidential information is shared pursuant to a request for confidential treatment and confidential treatment is not afforded, the Distribution Companies shall not be held responsible. Similarly, bidders shall use commercially reasonable efforts to treat all confidential information received from the Distribution Companies in a confidential manner and will not, except as required by law or in a regulatory or judicial proceeding, disclose such information to any third party or use such information for any purpose other than in connection with this RFP; provided, however that if such confidential information is sought in any regulatory or judicial proceeding, the bidders shall take reasonable steps to limit disclosure and use of said confidential information through the use of non-disclosure agreements or requests for orders seeking protective treatment, and shall inform the Distribution Companies that the confidential information is being sought. Bidders are advised that, per MDPU requirements, confidential bidder information may be disclosed during the MDPU approval process to parties that are granted intervenor status in the proceeding. In past proceedings, intervenor status has been granted to competitive suppliers and industry trade groups, and therefore, confidential bidder information has been required to be disclosed to legal counsel and/or a third-party consultant retained by the intervenor for purposes of the proceeding. 3.5 Official Contact for the RFP All copies of the proposal should be sent to the attention of the Official Contact for the Distribution Company to which the proposal is being submitted using the addresses listed below: Fitchburg Gas and Electric Light Company d/b/a Unitil: Todd Bohan Senior Energy Analyst Unitil Service Corp. 6 Liberty Lane Hampton, NH 03842-1720 Massachusetts Electric Company and Nantucket Electric Company d/b/a National Grid: Corinne DiDomenico Manager, Environmental Transactions Energy Procurement National Grid 100 East Old Country Road Hicksville, NY 11801

Page 28: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

21

NSTAR Electric Company and Western Massachusetts Electric Company d/b/a Eversource Energy: Brian Rice Sr. Energy Analyst Eversource One NSTAR Way, SUMNE220 Westwood, MA 02090-9230 Any questions regarding the RFP should be sent to: Todd Bohan, [email protected] Corinne DiDomenico, [email protected] Brian Rice, [email protected] 3.6 Organization of the Proposal Bidders are required to organize their proposal consistent with the contents of the Response Package in Appendix B. The organization and content of the proposal should be as follows:

1. Certification, Project and Pricing Data 2. Executive Summary 3. Additional Operational Parameters 4. Energy Resource Plan 5. Financial/Legal 6. Siting and Interconnection 7. Environmental Assessment and Permit Acquisition Plan 8. Engineering and Technology; Commercial Access to Equipment; Contribution to

Employment and Economic Development 9. Operation and Maintenance 10. Project Schedule 11. Project Management/Experience 12. Alternatives 13. Exceptions to Draft PPA

3.7 Modification or Cancellation of the RFP and Solicitation Process Following the submission of bids, the Distribution Companies may request additional information from bidders at any time during the process. Bidders that are not responsive to such information requests may be eliminated from further consideration. Unless otherwise prohibited, the Distribution Companies may, at any time up to final award, postpone, withdraw and/or cancel this RFP; alter, extend or cancel any due date; and/or, alter, amend, withdraw and/or cancel any requirement, term or condition of this RFP (including, without limitation, in response to changes in laws, regulations or ISO-NE Rules), any and all of which shall be without any liability to DOER, the AGO and the Distribution Companies. By submitting a bid, a bidder agrees that the sole recourse that it may have with respect to the

Page 29: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

22

conduct of this RFP is by submission of a complaint or similar filing to the MDPU in a relevant docket pertaining to this RFP.

Page 30: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix A, Page 1 43136464.5

Appendix A

Notice of Intent to Bid

(Confidential)

The Notice of Intent to Bid is included as Attachment 1 to this RFP. Attachment 1 is provided on the RFP website as a Microsoft Excel spreadsheet. Attachment 1 should be filled out, saved, printed and signed. The submission of Attachment 1 should be done electronically in two formats: 1) the complete spreadsheet version; and 2) a PDF of the printed and signed version. Bidders should send the Notice of Intent to Bid Form by email to the addressees for the Distribution Company set forth in Section 3.5 of the RFP.

Page 31: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 1 43136464.5

Appendix B

Bidder Response Form

1. Attachment 2 – Certification, Project and Pricing Data Attachment 2 is provided on the RFP website as a Microsoft Excel spreadsheet. Attachment 2 has six parts listed below. If the bidder provides information in other Sections of this response that conflicts with the information in Attachment 2, Attachment 2 shall be considered to contain the governing and binding information for both the evaluation and any resulting contract offer. If a proposal for a project includes different offers on terms and/or pricing (e.g. 10 year and 15 year), a separate and complete Attachment 2 should be completed for each different offer.

Part I Guidelines and Instructions for completing the spreadsheet

Part II Proposal Certification Form

Part III Bid and Contact Information

Information includes term, pricing type and contact information.

Part IV Project Information

Information includes size, output, dates, technology, location, delivery point, capacity factor, percentage entitlement, contract maximum amount and other technical information.

Part V Pricing Information

Information includes annual peak and off-peak contract energy by contract year and corresponding prices, RECs by contract year and corresponding prices, and alternative pricing.

Part VI Operational Information

Information includes expected peak and off-peak monthly production.

2. Executive Summary of the Proposal (including the base proposal and any alternative proposals)

The Bidder is required to provide an executive summary of the project proposal in this Section of the Bid Form. The Bidder should include a description of the important elements of the proposal consistent with the sections included in the Bidder Response Forms. Bidders should provide

Page 32: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 2 43136464.5

sufficient information to clearly demonstrate how their proposal conforms to the eligibility and threshold criteria specified in Section 2.2 of the RFP.

3. Additional Operational Parameters 3.1 Maintenance Outage Requirements – Specify partial and complete planned outage

requirements in weeks or days. Also, list the number of months required for the cycle to repeat (e.g., list time interval of minor and major overhauls, and the duration of overhauls).

3.2 Operating Constraints - Specify all the expected operating constraints and operational restrictions for the project (i.e. limits on the number of hours a unit may be operated per year or unit of time).

3.3 Reliability – Describe how the proposal would provide enhanced electricity reliability within Massachusetts.

3.4 Moderation of System Peak Load – Describe how the proposal would contribute to moderating system peak load requirements. If the proposed project is an intermittent resource, please provide the following information:

i) Estimated average output for each summer period (June-September) from 1:00 pm-6:00 pm

ii) Estimated average output for each winter period (October-May) from 5:00 pm-7:00 pm

3.5 Development Stage of Facility – Describe whether the project is in operation, in construction or in the development phase. If in operation, when did the project achieve initial operation and commercial operation? If in construction, when did construction commence and what are the projected dates for initial operation and commercial operation. If the project is partly in one development stage and partly in another, please explain in detail the status of the project. If the proposed project is an expansion or repowering of an existing project, please describe the project in detail, specifying the existing project and the proposed expansion or repowering.

4. Energy Resource Plan The Bidder is required to provide an energy resource or fuel supply plan for its proposed project, including supporting documentation. The fuel supply/energy resource profile information should be consistent with the type of technology/resource option proposed and the term of the PPA proposed. The information requested is organized according to the type of project or energy resource. Bidders should respond only to relevant questions.

Wind Energy Projects

Page 33: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 3 43136464.5

i. Provide a summary of all collected wind data for the proposed site. Identify when the data was collected and by whom.

ii. Indicate where the data was collected and its proximity to the proposed site. Include an identification of the location for the anemometers that were used to arrive at an assessment of the site generation capability.

iii. Provide (a) at least one year of hourly wind resource data, or (b) a wind resource assessment report from a qualified resource assessment firm or meteorologist, or (c) both. Include an analysis of the available wind data which addresses the relationship between wind conditions and electrical output.

iv. Provide a site-adjusted power curve. Each curve should list the elevation, temperature and air density used.

v. Identify the assumptions for losses in the calculation of projected annual energy production, including each element in the calculation of losses.

Landfill Gas

i. Provide a gas production forecast for each landfill. Provide a table that shows the annual, monthly and hourly projection of gas flow and energy export to the Distribution Company from each landfill.

ii. Provide supporting data that illustrates the expected generation from each landfill based on the projected gas production.

iii. Describe any contingencies or constraints that could affect the availability of fuel or the energy resource for the project and any contingency plans for meeting projected generation levels.

Biomass

i. Describe specifically how the project will conform to DOER regulations governing resources using biomass fuel. Should these regulations result in generation of RECs that differs from the energy production, an estimate that differs from the annual contract energy should be provided in Attachment 2, Part V.

ii. Provide a resource assessment of available biomass fuel for the proposed project and its proximity to the project site.

iii. Provide a plan for obtaining the biomass fuel, including a transportation plan.

iv. Provide any contracts or letters of intent to acquire and transport the biomass fuel.

v. Demonstrate that projected energy output for the project over the term of the contract is consistent with the energy supply available.

Page 34: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 4 43136464.5

vi. Describe any contingencies or constraints that could affect the availability of fuel or the energy resource for the project and any contingency plans for meeting projected generation levels

Hybrid Anaerobic Digestion and Landfill Gas

i. Provide all required information listed above for Landfill Gas and Biomass projects

ii. Provide a table that shows the annual, monthly and hourly projection of gas flow by source to each electric generating facility.

Solar

i. Provide an assessment of the available solar incidence or resource. Describe any trends in generation capability over time (i.e. annual decline rate of expected output).

ii. Describe the methodology used to generate the projected generation and describe the in-house or consulting expertise used to arrive at the generation estimates.

Hydro, Marine or Hydrokinetic

i. Describe the project characteristics in terms of water flow (on a monthly basis) and head, and state the assumptions regarding seasonal variations, and a conversion of such flow into kilowatts and kilowatt-hours. Provide monthly flow duration curves based upon daily stream flow records.

ii. If the project is an expansion of an existing project, specify how the energy would qualify as RPS Class I Renewable Generation and the actions proposed to be taken by the Bidder to accomplish such qualification.

Other

i. Identification of availability of fuel supply (if applicable).

ii. What is the availability of the fuel supply?

iii. Does the Bidder have any firm commitments from fuel suppliers? If so, please provide a copy of any agreements with confidential information redacted if necessary.

5. Financial/Legal Bidders are required to provide responses to all questions below. Bidders are required to demonstrate the financial viability of their proposed project. Bidders should provide the following information:

5.1 Provide a description of the corporate structure of the Bidder’s organization from a financial and legal perspective, including any general and limited partners, officers, directors, managers, members and shareholders, involvement of any subsidiaries supporting the project, and the providers of equity and debt during project development.

Page 35: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 5 43136464.5

Provide an organization chart showing the relationship between the equity participants and an explanation of the relationships.

5.2 Provide a description of the financing plan for the project, including construction and term financing. The financing plan should address the following:

i) Who will finance the project and how it will be financed ii) The project’s projected financial structure iii) Expected sources of debt and equity financing iv) Estimated construction costs v) The projected capital structure vi) Describe any agreements entered into with respect to equity ownership in the

proposed project and any other financing arrangement.

In addition, the financing plan should address the financing of development costs. All bidders are required to provide this information.

5.3 Provide documentation illustrating the experience of the project sponsor in securing financing for projects of similar size and technology. For each project previously financed provide the following information:

i) Project name and location ii) Project type and size iii) Date of construction and permanent financing iv) Form of debt and equity financing

5.4 Provide evidence that the Bidder has the financial resources and financial strength to complete and operate the project as planned.

5.5 Provide copies of the most recent audited financial statement or annual report for each Bidder, including affiliates of the Bidder.

5.6 The Bidder should demonstrate its ability (and/or the ability of its credit support provider) to provide the required security, including its plan for doing so.

5.7 Provide a description of any current credit issues regarding the Bidder or affiliate entities raised by rating agencies, banks, or accounting firms.

5.8 Describe the role of the federal Production Tax Credit or Investment Tax Credit (or other incentives) on the viability of the project.

5.9 Bidders must disclose any pending or threatened litigation related to projects owned or managed by them or any of their affiliates in the United States.

5.10 What is the expected operating life of the proposed project?

5.11 Has the Bidder already obtained financing, or a commitment of financing, for the project? Is such financing or financing commitment contingent on obtaining a long-term power sales agreement, such as one that would be obtained if the Bidder’s proposal is accepted? If financing has not been obtained, explain how obtaining a long-term power sales

Page 36: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 6 43136464.5

agreement as proposed will help you in obtaining financing for the proposed project or in obtaining more favorable terms for the financing of the proposed project. Also, state whether the Bidder has obtained one or more long-term power sales agreements with respect to energy, RECs and/or capacity for the Project and provide information regarding term and quantities.

6. Siting And Interconnection This section of the response package addresses project location, siting, real property rights and interconnection issues. Bidders should ensure that the threshold criteria for siting are verified in their responses.

6.1 Provide a site plan including a map of the site that clearly identifies the location of the site, the total acreage, the anticipated interconnection point, and the relationship of the site to other local infrastructure, including transmission facilities, roadways, and water sources. In addition to providing the required map, provide a site layout plan which illustrates the location of all major equipment and facilities on the site.

6.2 Provide evidence of the right to use the site.

i) Does the project have a right to use the site (e.g., by virtue of ownership or land rights obtained from the owner)?

ii) If so, please identify the means of site control.

Include any relevant documentation, e.g., lease agreement, option to lease, purchase agreement, option to purchase, or letter of intent regarding any of the foregoing.

6.3 Provide evidence that the site is properly zoned. If the site is not currently zoned properly, identify present and required zoning and/or land use designations and provide a permitting plan and timeline to secure the necessary approvals.

6.4 Provide a description of the area surrounding the site including a description of the local zoning, flood plain information, existing land use and setting (woodlands, grasslands, agriculture, other).

6.5 Identify any real property rights (e.g., fee-owned parcels, rights-of-way or easements) that are required for access to the project or for interconnection. Describe the status of acquisition of real property rights, and describe the plan for securing the necessary real property rights, including the proposed timeline. Include these plans and the timeline in the overall project timeline.

6.6 Please describe the status of any planned interconnection to the grid. Has the Bidder made a valid interconnection request to the Electric Distribution Company (“EDC”) and/or ISO New England, Inc. (“ISO-NE”)? Describe the status of any interconnection studies already underway with ISO-NE and the transmission owner. Provide a copy of the EDC Pre-Application Report and any studies completed to date. Provide a copy of an interconnection agreement, if any, executed by the Bidder with respect to the proposed

Page 37: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 7 43136464.5

project. If an interconnection agreement has not been executed, please provide the steps that need to be completed before an interconnection agreement can be executed and the associated timeline.

6.7 Provide a copy of an electrical one-line diagram showing the interconnection facilities and the relevant facilities of the transmission owner.

6.8 Specify and describe the interconnection and transmission facilities that are required, including system control and protection.

7. Environmental Assessment And Permit Acquisition Plan This section addresses environmental and other regulatory issues associated with project siting, development and operations.

7.1 Provide a list of all the permits, licenses, and environmental assessments and/or environmental impact statements required. If a bidder has secured any permit or has applied for a permit, please identify in the response.

i) Provide a list of all Federal, state and local permits, licenses, and environmental assessments and/or environmental impact statements required to construct and operate the project.

ii) Identify the governmental agencies which will issue or approve the required permits, licenses, and environmental assessments and/or environmental impact statements.

7.2 Provide the anticipated timeline for seeking and receiving the required permits, licenses, and environmental assessments and/or environmental impact statements, using the execution date of the PPA as the starting point, if applicable. Include a project approval assessment which describes, in narrative form, each segment of the process, the required permit or approval, and the basis for projection of success by the milestone date. All requirements should be included on the project schedule in Section 11.

7.3 Provide a preliminary environmental assessment of the site and project, including both construction and operation. The Bidder should identify environmental impacts associated with the proposed project, any potential impediments to development, and its plan to mitigate such impacts or impediments. The analysis should address each of the major environmental areas presented below:

i) Site development ii) Transportation infrastructure iii) Air quality iv) Access to water resources/water quality v) Ecology vi) Land use vii) Cultural resources viii) Previous site use

Page 38: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 8 43136464.5

ix) Noise level x) Aesthetic/visual xi) Transmission infrastructure xii) Fuel supply access

7.4 Provide documentation identifying the level of public support for the project including letters from public officials, newspaper articles, etc. If the project sponsor has not yet initiated community outreach for the project, please provide a plan for community outreach activities.

8. Engineering And Technology; Commercial Access To Equipment; Contribution To Employment And Economic Development

This section includes questions pertinent to the engineering design and project technology. Bidders should provide information about the specific technology or equipment including the track record of the technology and equipment.

8.1 Provide a reasonable but preliminary engineering plan which includes the following information:

i) Type of generation technology ii) If wind turbines, provide the turbine make and model, hub height, rotor diameter,

and power curve iii) Major equipment to be used iv) Manufacturer of the equipment v) Status of acquisition of the equipment vi) Whether the Bidder has a contract for the equipment. If not, describe the Bidder’s

plan for securing equipment and the status of any pertinent commercial arrangements

vii) Equipment vendors selected/considered viii) History of equipment operations ix) If the equipment manufacturer has not yet been selected, identify in the equipment

procurement strategy the factors under consideration for selecting the preferred equipment

8.2 If the Bidder has not yet selected the major generation equipment for the project, please provide a list of the key equipment suppliers under consideration.

8.3 Please identify the same or similar equipment by the same manufacturer that are presently in commercial operations including the number installed, installed capacity and estimated generation for the past three years.

8.4 For less mature technologies provide evidence (including identifying specific applications) that the technology to be employed for energy production is ready for

Page 39: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 9 43136464.5

transfer to the design and construction phases. Also, address how the status of the technology is being considered in the financial plan for the project.

8.5 Please indicate if the Bidder has secured its equipment for the project. If not, identify the long-lead equipment options and describe the timing for securing equipment.

8.6 Please provide an estimate of the number of jobs to be created directly during project development, construction and operations and a general description of the types of jobs created, estimated annual compensation, and the employer(s) for such jobs. Please treat the development, construction, and operation periods separately in your response.

8.7 Please provide the same information as provided in response to question 10.6 but with respect to jobs that would be indirectly created as a result of the proposed project.

8.8 Please describe any other economic development benefits that could be achieved by the proposed project, such as creating property tax revenues and the provision of renewable energy at lower costs than other potential projects (to the extent known).

9. Operation And Maintenance Projects that can demonstrate that the maintenance plan, level of funding, and mechanism for funding will ensure reliable operations during the term of the contract are preferred.

9.1 Provide an operation and maintenance plan for the project that demonstrates the long term operational viability of the proposed project. The plan should include a discussion of the staffing levels proposed for the project, the expected role of the project sponsor or outside contractor, scheduling of major maintenance activity, and the plan for testing equipment.

9.2 Describe in detail the proposed O&M funding mechanism and funding levels to support planned and unplanned O&M requirements.

9.3 Describe the terms (or expected terms) of the warranties and/or guarantees on major equipment that the Bidder is seeking.

9.4 Describe the status of the project sponsor in securing any operation and maintenance agreements or contracts. Include a discussion of the sponsors plan for securing a medium-term or long-term O&M contract, including the expected provider of O&M services.

9.5 Provide examples of the Bidder’s experience with O&M services for other similar projects.

Page 40: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 10 43136464.5

10. Project Schedule Bidders are required to provide a complete critical path schedule for the project from the notice of selection of the project for contract consideration to the start of commercial operations. For each project element, list the start and end date.

10.1 Identify the elements on the critical path. The schedule should include, as a minimum, facility contracts, start of construction, construction schedule, siting, fuel supply, financing, engineering and procurement, acquisition of real property rights, Federal, state and/or local permits, licenses, environmental assessments and/or environmental impact statements (including anticipated permit submittal and approval dates) and any other requirements that could influence the project schedule and the Commercial Operation Date, including requirements pertaining to the generator interconnection process and any transmission facilities for which the bidder seeks recovery through federal transmission rates.

11. Project Management/Experience Bidders are required to demonstrate project experience and management capability to successfully develop and operate the project proposed. The Distribution Companies are particularly interested in project teams that have demonstrated success in projects of similar type, size and technology and can demonstrate an ability to work together effectively to bring the project to commercial operation in a timely fashion.

11.1 Provide an organizational chart for the project that lists the project participants and identifies the corporate structure, including general and limited partners.

11.2 For each of the project participants (including the Bidder, partners, A/E firm, EPC contractor and proposed contractors), provide statements that list the specific experience of the firm in developing, financing, owning, and operating generating facilities, other projects of similar type, size and technology, and any evidence that the project participants have worked jointly on other projects.

11.3 Provide a management chart that lists the key personnel dedicated to this project and provide biographies of the key personnel.

11.4 Provide a listing of all projects the project sponsor has successfully developed or that are currently under construction. Provide the following information as part of the response:

i) Name of the project ii) Location of the project iii) Project type, size and technology iv) Commercial operation date v) Estimated and actual capacity factor of the unit for the past three years vi) Availability factor of the unit for the past three years vii) References, including the names and current addresses and telephone numbers of

individuals to contact for each reference.

Page 41: KEEGAN WERLIN LLP - Eversource Energy · KEEGAN WERLIN LLP ATTORNEYS AT LAW 265 FRANKLIN STREET BOSTON, MASSACHUSETTS 02110-3113 TELECOPIERS: ——— (617) 951- 1354 (617) 951-

Appendix B, Page 11 43136464.5

11.5 With regard to the Bidder’s project team, identify and describe the entity responsible for the following:

i) Construction Period Lender, if any ii) Operating Period Lender and/or Tax Equity Provider, as applicable iii) Financial Advisor iv) Environmental Consultant v) Owner’s Engineer vi) EPC Contractor (if selected) vii) Transmission Consultant viii) Legal Counsel

11.6 With regard to Bidder’s experience with ISO-NE markets, please indicate the entity that will assume the duties of Lead Market Participant for your Project. Please provide a summary of the proposed Lead Market Participant’s experience with each of the ISO-NE markets.

12. Alternatives With reference to Section 2.2.4.2 of the RFP, Bidders should describe any alternative options to their proposal which could include a different pricing formula, if applicable. Price caps should be entered into the annual contract year price columns on Attachment 2, Part V. Also, the index, the base year and the base year price should be entered into the same Part V, if applicable.

13. Exceptions To Draft PPA Please attach a description of exceptions to the Draft PPA set forth in Appendix C to this RFP, including the Bidder’s counter-proposal with respect to the items to which exceptions are made and a redline to the Draft PPA showing specific proposed language changes. Please note that bidders are discouraged from proposing fundamental changes to the risk allocation set forth in the Draft PPA.