KONZA TECHNO CITYINFRASTRUCTURE
-
Konza’s Value Proposition
Catalyst program
Office: ITO/BPO/Telecom
Vision
Implementation
Retail Residential
City elements
Vision
A self-sustaining city anchored by a cluster of knowledge industries
Lab/Hospital
University
Ancillary program
Hotel
Retail Residential
Public services
Vibrant public realm
Creative Industries Clusters
Services
Activating elements
ICT / ITES Life Sciences
Engineering
-
CONTRIBUTION TO KENYA’S ECONOMIC OUTPUT
$1.3 B
Konza gross regional product (GRP)
2%
of Kenya GDP in 2020
7%
AAAAtttt fulfulfulfull l l l PhasPhasPhasPhaseeee 1111 bbbbuiluiluiluildddd----out, out, out, out, assumeassumeassumeassumed d d d totototo bebebebe 2020202022220000
of Kenya GDP growth 2015-2023
8%
of Kenya wage growth 2015-2023
+19%
Real IRR:
land lease revenue + taxes
3
-
Total development: 5,000 AcresTotal residents 200,000
Konza Masterplan
4
-
Phase 1 Master plan
5
Total development: 1.5M m2Total workers: ~17,000Total residents: 30,000
-
BAND
University
BAND
Residential
BAND
Life ScienceBAND
Office
HOW WE WANT IT DONE
•Create Demand– City Elements
• Retail• Services• Residential BAR
Mixed Use• Residential• Active Public
– Enabling Elements
• Students• Jobs
6
-
Phase 1A
7
Total development: 60 acresNumber of Parcels: 245,000 - 10,000 residentsReady by 2018
-
Key Milestones
• Provision of Initial backbone infrastructure (Power, Water, Phase 1 access roads)
• Phase 1 Master plan and Local Physical Development Plan (LPDP) Approved.
• 60 acres (Phase 1 A)constituting 24 parcels ready to be taken by investors. Request for EOI closing on 30th January 2016
• Request for EOI for private Secondary and Primary schools closed on December 2015
8
Approved.• Approval of Strategic
Environmental Assessment (SEAs) Report by NEMA.
• Phase 1 Cadastral Survey completed by UNES
• Completion of priority development guidelines and standards
closed on December 2015• The groundbreaking of the
KoTDA Office, designed to be a mixed use building is scheduled for March 2016 . The completion date is set for April 2017 , KoTDA staff and the city’s early residents will be leaving and working in the city by April 2017.
-
Phase 1A access roads to 24 parcels
Phase 1 access road (100% Complete)
Phase 1A access roads to 24 parcels
-
EPC+ Financing opportunity
No DescriptionCost Estimate
(KShs) for Phase 1
Cost Estimate (KShs)
Phase 1A
1Streetscape and Sub-Surface Utilities
20,193,000,000 3,908,000,00
0
2Waste Water Treatment and Recycling Facility
3,598,000,000 1,666,000,00
0 Recycling Facility
3Bulk Water Treatment, Booster Station and Storage
3,986,000,000 1,661,000,00
0
4Fibre Optic Reticulation
3,350,000,000 607,000,000
5Power/ Electrical Distribution and Substation
9,072,000,000 2,094,000,00
0
6 Solid Waste 410,000,000 83,000,000
Total 40,609,000,000 10,019,000,0
00
10
-
KoTDA Complex
11
Budget: Kshs 2.5 B
DesignProcurementConstruction
Start: 01 October 2015
Finish: 28 April 2017
Designs being finalized; construction to begin in April 2016
-