Koontz Electric Company, Inc. 1223 East Broadway Morrilton, Arkansas 72110 501-354-2526 http://www.koontzelectric.com
Koontz Electric Company, Inc., (KECI), welcomes an opportunity to make your next project a
success. We maintain a professional and technical staff to support our experienced field
craftsman. We pledge to safely deliver a quality finished product in a timely manner, and at a
competitive cost.
KECI is a diversified heavy industrial electrical contractor. We perform a wide array of
contracts specifically chosen for technical and installation complexities. KECI’s team supports
the total spectrum of power, control, and instrumentation system needs. We have proudly
served Arkansas and the nation for over 60 years. In just the last ten years we have
completed over 500 projects with contracts exceeding $350 million aggregate. We have
never failed to complete a project.
Numerous repeat customers, universal customer satisfaction, and our strong industry
reputation, is positive feedback that our approach delivers. A fervent commitment to safety,
quality, timely schedules, and cost control, are the keys to our success and longevity. Our
professional office and field staff, diverse work history and over five decades of experience,
uniquely qualify us for the most challenging projects.
Koontz Electric Company, Inc. 1223 East Broadway Morrilton, Arkansas 72110 (501) 354-2526 http://www.koontzelectric.com
I N T RODUC T I ON
Type of Ownership and Parent Company: Koontz Electric Company, Inc. is a legal U.S. CorporationYear Established: March 1, 1958Website: www.koontzelectric.com
Company Representative: Benny M. Koontz | President, CEO|[email protected] East BroadwayMorrilton, AR 72110P 501.242.6111 | F 501.251.1138
Headquarters Experience Modification Rates (EMR)1223 East Broadway 2021 – 0.63 Morrilton, AR 72110 2020 – 0.63P 501.354.2526 | F 501.251.1138 2019 – 0.71
Duns Number: 035585207Cage Code: 0FY55
NAICS Codes Small Business (Y/N)
221122 – Electric Power Distribution Y
236220 ‐ Commercial and Institutional Building Construction N
237130 ‐ Power and Communication Line and Related Structures Construction N
237990 ‐ Other Heavy and Civil Engineering Construction N
238210 ‐ Electrical Contractors and Other Wiring Installation Contractors N
238220 ‐ Plumbing, Heating, and Air‐Conditioning Contractors N
335311 ‐ Power, Distribution, and Specialty Transformer Manufacturing Y
335312 ‐ Motor and Generator Manufacturing Y
335313 ‐ Switchgear and Switchboard Apparatus Manufacturing Y
335314 ‐ Relay and Industrial Control Manufacturing Y
335999 ‐ All Other Miscellaneous Electrical Equipment and Component Manufacturing Y
423610 ‐ Electrical Apparatus and Equipment, Wiring Supplies, and Related Equipment
Merchant Wholesalers Y
541512 ‐ Computer Systems Design Services N
541990 ‐ All Other Professional, Scientific, and Technical Services N
561210 ‐ Facilities Support N
Koontz Electric Company, Inc. 1223 East Broadway Morrilton, Arkansas 72110 (501) 354-2526 http://www.koontzelectric.com
COMPANY DATA
CONTRACT NO:
Crow Sub: 1824.12
18‐6556
9/15/2018
JOB SITE LOCATION:
Pinecrest Kiln #3
Morrilton, AR
OWNER:
Green Bay Packaging
3610 US‐64
Plumerville, AR 72127
GENERAL CONTRACTOR:
Crow Construction
57 Foster Drive
Morrilton, AR 72110
Point of Contact: David Watkins
T 501.920.1297
SUB CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Jeremy Stell
T 501.242.6114
F 501.354.2580
START & COMPLETION DATE:
9/2018 – 5/2019
FINAL CONTRACT AMOUNT:
$877,386
C ROW C ON S T R U C T I O N G B P P I N E C R E S T K I L N # 3
SCOPE OF WORK:
Subcontract to Crow Construction, the scope of work included the
installation of two 1600A MCC’s, one 600A MCC, one 200Hp remote
drive , one 480vAC / 858VAR Power Factor Correction Unit, and one
1500kVA pad mount transformer 4160‐480Y/227V. This also
included 5.5kV terminations and conduit and conductors to
connect motor loads ranging in size from 1Hp to 300Hp in the newly
constructed Silo, Burner room, Fuel Prep area and existing Fuel
Prep. Conduit and conductors to connect the general lighting and
receptacle loads associated with the Silo, Burner room Cooling Shed
and Fuel Prep MCC room and fiber Optic cabling to allow the new Kiln
#3 to be monitored from the existing Kiln #1and #2 control room. This
project was completed ahead of schedule and on budget.
JOB DATES:
1976 ‐ Present
JOB SITE LOCATION:
Green Bay Packaging
Arkansas Kraft Division
Morrilton, AR 72110
OWNER:
Green Bay Packaging
Arkansas Kraft Division
Morrilton, AR 72110
Point of Contact: Mark Dellinger
T 501.354.9253
A R K A N S A S K R A F T M A I N T E N A N C E
SCOPE OF WORK:
Koontz Electric has been on‐site since 1976 performing ongoing
maintenance projects within Green Bay Packaging’s Arkansas Kraft
Division’s fully integrated 1100 TPD Pulp and Paper Facility.
CONTRACT NO / AWARD DATE:
KECI NO 16‐6454 / July 21, 2017
JOB SITE LOCATION:
Kimberly‐Clark Maumelle MNF
Spin Doctors K4 Installation
5010 Murphy Dr
Maumelle, AR 72113
OWNER:
Kimberly‐Clark Corporation
1414 West Larsen Road
Neenah, WI 54957
GENERAL CONTRACTOR:
Miron Construction Co, Inc.
1471 McMahon Dr
Neenah, WI 54956
Point of Contact: David Klein
T 920.886.7480
E david.klein@miron‐construction.com
SUB CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Jeremy Stell
T 501.242.6114
F 501.354.2580
COMPLETION DATE:
2018
CONTRACT AMOUNT:
$122,413
K IM B E R LY ‐ C L A R K K 8 AN K I E B AG G E R I N S TA L L
SCOPE OF WORK:
Project Ankie‐K8 consisted of updating the existing Wet Wipes
converting line (K8) in the Maumelle, AR plant by installing two
baggers thus adding over‐wrapping bag capability to the asset.
The scope of this project included installing two over‐bagger
machines, bag inspection and rejection systems and package
conveyors on the K8 asset. Also included with the K8 scope is a
process improvement upgrade to the exiting casepackers to enhance
successful loading of over‐wrapped bag into the cases.
CONTRACT NO / AWARD DATE:
KECI NO 16‐6441 / May 10, 2017
JOB SITE LOCATION:
Kimberly‐Clark Maumelle MNF
Spin Doctors K4 Installation
5010 Murphy Dr
Maumelle, AR 72113
OWNER:
Kimberly‐Clark Corporation
1414 West Larsen Road
Neenah, WI 54957
GENERAL CONTRACTOR:
Miron Construction Co, Inc.
1471 McMahon Dr
Neenah, WI 54956
Point of Contact: David Klein
T 920.886.7480
E david.klein@miron‐construction.com
SUB CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Jeremy Stell
T 501.242.6114
F 501.354.2580
COMPLETION DATE:
July 2017
CONTRACT AMOUNT:
$487,536
K IM B E R LY ‐ C L A R K K 4 S P I N D O C TO R S I N S TA L L
SCOPE OF WORK:
General scope for this project consisted of upgrading the existing
wet wipe converting line by replacing the refill packaging
equipment with the new RFT packaging equipment. This included
updating the Coform Hoist, Unwind Section, Folder Section and all
associated equipment, Conveying Equipment and Palletizer with
machine and safety upgrades. This project was on a strict time line
which demanded up to 20 men for a 12 week period all while
making sure all other assets were up and running without any
safety violations.
CONTRACT NO / AWARD DATE:
KECI NO: 16‐6371
2016
JOB SITE LOCATION:
Defiance Metal Products
944 Bypass Road
Heber Springs, AR 72543
OWNER:
Defiance Metal Products
POC: Keith Brown
21 Seneca Street
Defiance, OH 43512
GENERAL CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Jeremy Stell
T 501.242.6114
F 501.354.2580
COMPLETION DATE:
2016
CONTRACT AMOUNT:
$64,451.00
DE F I AN C E ME TA L S SW I TCHG EAR U PGRAD E
SCOPE OF WORK:
Koontz Electric Company, Inc. (KECI) has completed the switchgear
upgrade at Definance Metal facility in Heber Springs, Arkansas .
General scope for this project consisted of replacing existing
2000A/480V Pringle switch and switchboard. Replace existing
conductors from the transformer to the new switchboard. Install
new 480Y/277V 3PH 2000Amp switchboard with 2000A main
breaker. Install Power Metering and install phase and ground fault
protection. All work was completed in an two‐day shutdown and
did not affect production
CONTRACT NO / AWARD DATE:
14657547 / December 2014
KECI 14‐4991
JOB SITE LOCATION:
Kimberly Clark Corp
480 Exchange Ave
Conway, AR 72032
Point of Contact: Carmen Daianzo
T 501.336.6285
OWNER:
Kimberly Clark Corp
480 Exchange Ave
Conway, AR 72032
Point of Contact: Carmen Daianzo
T 501.336.6285
GENERAL CONTRACTOR:
Koontz Electric Company, Inc.
1223 East Broadway
Morrilton, AR 72110
Project Manager: Keith Foster
T 501.354.2526 ext 113
F 501.354.2580
COMPLETION DATE:
January 2015
CONTRACT AMOUNT:
$150,300
K IM B E R LY C L A R K 5 ‐ K V F E E D E R R E P L A C EM EN T
SCOPE OF WORK:
Replace (4) parallel sets of 500 MCM, 5kV feeders from the outside
substation to the interior unit substation during a minimal outage.
CONTRACT DATE:
January 2017
JOB SITE LOCATION:
Kiswire
5100 Industrial Drive South
Pine Bluff, AR 71602
OWNER:
Kiswire
5100 Industrial Drive South
Pine Bluff, AR 71602
POC: Chris Helms
T 870 489‐2882
GENERAL CONTRACTOR:
Koontz Electric Co., Inc.
1223 East Broadway
Morrilton, AR 72110
PM: Jeremy Stell
T 501 977‐6019
ACTUAL COMPLETION DATE:
December 2018
K I SWIRE – P INE B LUFF
MISCE L LANEOUS E L ECTR ICAL
SCOPE OF WORK INCLUDED:
1. Number 1 Pater: Demolition of the old Plater electrical and Plater control room. Installed
Switchgear feeder, new cable tray, new lighting in plater area, and installed the new Plater
line with all new controls.
2. New Waste Water Building: Installed general electrical for building control, installed wire
for waste water, demolition of the old waste water system after new up and running.
3. Demolition of the old and installed the new winder: Included relocating crane rails and
Buss Duct, Electrical and Air Piping, relocated old machines two and three times to
continue production.
4. General electrical for wire storage building.
5. Relocated scrapping machines and system three times to keep in operation while new
twisting machines were being installed.
6. Installed electrical and air piping for new twisting machine.
7. Movement and installation of air piping and electrical for 300 fine draw machines.
8. Changed out lighting in fine draw area—approximately 200 fixtures.
9. Removed old cabling machines and installed approximately 45 new machines; Electrical
and air.
10. Completed service work on 13,800V switchgear and main breakers for while plant.
11. Emergency installation of 3,000 kVA transformer for Twisting area.
12. Number 2 Plater: Installed new 1,000 amp rectifiers for plating line including running
Buss Bars for secondary DC pipe. Installed upgrades parts for line. Rewired control section
of furnaces. Added services, controls, and Buss Duct for 53 new take up and 53 pay off
machines for #2 Platter.
13. Predraw: Replaced old wire cleaning line for 5 Predraw machines while maintaining
production.
14. Demolition and replacement of 2 new 13 Block drawing machines.
15. Intermediate Draw: Demolition of old wiring and upgrade. Reviewed 5 machines. Pipe
in air and water plus a new 1,000A panel.
16. Beadwire: All the electrical power and control for entire plant: 5 line descaling line; 19
wire coating line; 11 Drawing machines 12 to 14 block; 20 Wire plating line then upgrade
to a 30 wire plating line.
17. General electrical for new warehouse
CONTRACT NO / AWARD DATE:
PO 91412 / November 2011
KECI 11‐7228
JOB SITE LOCATION:
Green Bay Packaging
Arkansas Kraft Division
338 Hwy 113 SMorrilton, AR 72110
OWNER:
Green Bay Packaging
Arkansas Kraft Division
338 Hwy 113 SMorrilton, AR 72110
Point of Contact: Steve Lewis
T 501.354.9532
GENERAL CONTRACTOR:
Koontz Electric Company, Inc.
1223 East Broadway
Morrilton, AR 72110
Project Manager: Jeff Ludwig
T 501.354.2526 ext 118
F 501.354.2580
INITIAL MOBILIZATION / EST COMPLETION DATE:
November 2011 / July 2013
CONTRACT AMOUNT:
$2,716,437
GREEN BAY PACKAGING UNDER GROUND FEEDER REPLACEMENT
SCOPE OF WORK:
Scope of work consisted of the installation of an all new above
ground 5kV & 15kV distribution system. Installation of a new
substation control house, distribution switchgear, BUS duct, battery
charging system and relaying. Substation upgrades included all steel,
BUS & fittings, equipment, grounding, conduit and wire.
CONTRACT NO / AWARD DATE:
PO 45432713 / July 19, 2010
KECI NO 10‐4922
JOB SITE LOCATION:
SGL Carbon
3931 Carbon Plant RD
Ozark, Arkansas 72949
Point of Contact: Craig Mathews
T 479.468.4401
F 479.468.8064
OWNER:
SGL Carbon
3931 Carbon Plant RD
Ozark, Arkansas 72949
Point of Contact: Craig Matthews
T 479.468.4401
F 479.468.8064
GENERAL CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Jeff Ludwig
T 501.354.2526 ext 118
F 501.354.2580
INITIAL MOBILIZATION / COMPLETION DATE:
July 2010/ September 2010
AWARDED / CURRENT CONTRACT AMOUNT:
$453,520 / $453,520
S G L C A R B O N R E C T I F O R M E R I N S T A L L
SCOPE OF WORK:
Koontz Electric was awarded a $453,520.00 contract for the installation of
a new 34.5kV rectiformer, controls, primary & secondary bus, and
associated steel structures for the SGL Group, located in Ozark, Arkansas.
This facility, better known as the SGL Carbon Plant implemented this
contract to expand their production of graphite/carbon electrodes.
Koontz Electric self performed 100% of this work with their own forces.
This project includes the following features of work:
•Installation of new 34.5kV rectiformer.
•Installation of new rectiformer cooling fans.
•Installation of new rectiformer heat exchangers.
•Installation of oil cooling heat exchanger and water cooling tower
assembly onto fabricated platforms.
•Steel platform fabrication and installation.
•Installation of rectiformer isolation pad.
•Installation of new rectiformer relay control cabinets.
•Electrical installation of new conduits, cable tray, control & power wiring.
•Installation of new bus and modify existing aluminum bus.
Installation of new flexible primary and secondary conductors on
recitiformer.
CONTRACT NO / AWARD DATE:
KECI JOB NO 094913 / July 19, 2010
JOB SITE LOCATION:
Unimin Dryer Building
1 Main St
Guion, AR 72540
OWNER:
Unimin Corporation
7658 HWY 226 South, Bakersville HWY
Spruce Pine, NC 28777
Point of Contact: Rick Bochme
T 828.766.7651
F 828.766.7650
GENERAL CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Paul Zimmerman
T 501.354.2526 ext 102
F 501.354.2580
INITIAL MOBILIZATION / COMPLETION DATE:
January 2010 / July 2010
FINAL CONTRACT AMOUNT:
$1,282,704
UNIMIN ELECTR ICAL & CONTROLS SYSTEMS INSTALL
SCOPE OF WORK:
Koontz Electric Company, Inc. was responsible for the following:
Provide conduit, cable tray, wire & cable, disconnect switches,
pushbutton control stations, support materials, terminations/tapes,
labor and tools necessary to install the electrical and control systems
for a new secondary screening facility for Unimin at Guion, Arkansas.
CONTRACT NO / AWARD DATE:
502000567 / August 19, 2008
KECI JOB NO 08‐4897
JOB SITE LOCATION:
Wheeling Machines
5411 Industrial Drive South
Pine Bluff, Arkansas 71602
OWNER:
US Steel Tubular Products, Inc.
PO Box 1000
Lone Star, Texas 75668‐1000
Point of Contact: Frank Kozleuchar
T 412.433.5896
GENERAL CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Keith Foster
T 501.354.2526 ext 113
F 501.354.2580
INITIAL MOBILIZATION / COMPLETION DATE:
September 2008 / July 2009
AWARDED / FINAL CONTRACT AMOUNT:
$1,572,000 / $1,587,664
Price Increase Due to Owner Requested & Approved Change Orders
US STEE L – E L ECTR I CAL D I STR IBUT ION SYSTEM INSTAL L
SCOPE OF WORK:
Koontz Electric Company, Inc. has been awarded the contract for
design / build services for the installation of a new electrical
distribution system through the Wheeling Machine Facility in
Pine Bluff, Arkansas. Wheeling Machines new safety standards
required all 13.8V to be outside of all production facilities to
allow a safe workplace for their employees. Therefore, a new
electrical distribution system from the local utility had to be
designed and installed, all while the facility remains operational
with minimal interruptions.
CONTRACT NO / AWARD DATE:
7027‐16.100.100/SU / July 26, 2007
KECI NO 07‐4884
JOB SITE LOCATION:
LM Wind Power
Port Site Facility
7901 Lindsey Rd
Little Rock, AR 72206
OWNER:
LM Wind Power Group
Jupitervej 6
6000 Kolding
Denmark
T +45.79.84.00.00
F +45.79.84.00.01
GENERAL CONTRACTOR:
RW Allen & Associates, Inc
2205 Highland Avenue
PO Box 3925
Augusta, Georgia 30914
Point of Contact: Jim Cely
T 706.733.2800
F 706.564.5252
ARCHITECT / ENGINEER:
CH2M Hill‐Lockwood Greene
Enterprise Mill
1450 Greene St Suite 200
Augusta, Georgia 30901
Point of Contact: Barry Calloway
T 706.724.8225
F 706.724.8422
LM WIND POWER / L ITTLE ROCK PORT S ITE FAC IL ITY
INITIAL MOBILIZATION / COMPLETION DATE:
March 2008 / September 2008
AWARDED / FINAL CONTRACT AMOUNT:
$1,079,980 / $4,596,483
Price Increase Due to Owner Requested & Approved Change Orders
SCOPE OF WORK:
Koontz Electric completed LM Wind Power’s manufacturing plant
under budget and before deadline. KECI’s work force peaked at 70
licensed electricians on site working 60 hours a week and finished the
project in 7 months time. KECI installed LM Wind Power’s entire
electrical system including: 2000A 15kV switchgear, 2 – 4000A unit
substations, 2 motor control centers, 7 power distribution panels, 4
power factor capacitors, 800kW generator, and over 130
disconnects. KECI installed over 1,100 lights, over 250,000 ft of cable
and over 250,000 ft of conduit. KECI also installed building’s dust
collection, building management, grounding, lightning protection, fire
alarm, heat trace, data, and telephone systems.
CONTRACT NO / AWARD DATE:
7027‐16.100.100/SU / September 2007
KECI NO 07‐4880
JOB SITE LOCATION:
LM Wind Power
Celestica Facility
7400 Scott Hamilton Rd
Little Rock, AR
OWNER:
LM Wind Power Group
Jupitervej 6
6000 Kolding
Denmark
T +45.79.84.00.00
F +45.79.84.00.01
GENERAL CONTRACTOR:
RW Allen & Associates, Inc
2205 Highland Avenue
PO Box 3925
Augusta, Georgia 30914
Point of Contact: Jim Cely
T 706.733.2800
F 706.564.5252
ARCHITECT / ENGINEER:
CH2M Hill‐Lockwood Greene
Enterprise Mill
1450 Greene St Suite 200
Augusta, Georgia 30901
Point of Contact: Barry Calloway
T 706.724.8225
F 706.724.8422
LM W I N D POWE R / C E L E S T I C A F A C I L I T Y
INITIAL MOBILIZATION / COMPLETION DATE:
September 2007 / May 2008
SUB CONTRACT AMOUNT:
$2,842,643
SCOPE OF WORK:
LM Wind Power’s remodel project for RW Allen took the old Celestica
building, 7400 Scott Hamilton Rd, and turned it into a windmill blade
production facility. KECI performed over 19,500 man hours in less than
3 months to complete the project. Crew size varied from 20 to 50
working the occasional night shift.
Scope of work included demolition of the existing electrical
equipment, installation of 480V switchgear, MCC’s, distribution panels,
generator, lights, receptacles, HVAC and all the associated electrical in
the plant. In addition, our work force assisted in the installation of the
Denmark made fiberglass molds.
KECI CONTRACT NO :
KECI NO 07‐4877
JOB SITE LOCATION:
CertainTeed Corporation RPG
2701 E. Roosevelt Rd.
Little Rock, AR 72206
OWNER:
CertainTeed Corporation RPG
2701 E. Roosevelt Rd.
Little Rock, AR 72206
Point of Contact: Ken Moll
T 610.341.6534
ken.a.moll@saint‐gobain.com
GENERAL CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Jeff Ludwig
T 501.354.2526 ext 118
F 501.354.2580
INITIAL MOBILIZATION / COMPLETION DATE:
February 2008 / August 2008
AWARDED / FINAL CONTRACT AMOUNT:
$470,545 / $577,684
Price Increase Due to Owner Requested & Approved Change Orders
C E R TA I N T E ED P I P E PRODUC T I ON L I N E
SCOPE OF WORK:
Koontz Electric performed the following work:
• Furnished and installed all conduit and wire according to the drawings.
• Furnished and installed forty‐three (43) disconnects.
• Installed one (1) electrical panel, two (2) motor control centers, and one (1) transformer.
• Installed pre‐wired PLC panels.
• Remobilized in June to connect one (1) chiller.
• Changed all disconnect requirements from NEMA 4 to NEMA 12 (except DS1111, NEMA 4X).
CONTRACT NO / AWARD DATE:
KC CONTRACT NO 623 / May 2008
PO 11507977
KECI NO 07‐4892
JOB SITE LOCATION:
Kimberly‐Clark
Maumelle Manufacturing Mill
500 Murphy Dr
Maumelle, AR 72113
Point of Contact: Michele L Tanner
T 920.721.6955
F 920.721.4183
OWNER:
Kimberly‐Clark Corporation
1414 West Larsen Road
Neenah, WI 54957
Point of Contact: Diane Pence
F 920.380.8129
GENERAL CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Jamie Zimmerman
T 501.354.2526 ext 135
F 501.354.2580
INITIAL MOBILIZATION / COMPLETION DATE:
May 2008 / July 2008
AWARDED / CURRENT CONTRACT AMOUNT:
$339,296 / $401,536
Price Increase Due to Owner Requested
& Approved Change Orders
K I M B E R L Y ‐ C L A R K N E W K 6 L I N E I N S T A L L
SCOPE OF WORK:
Koontz Electric Company, Inc. (KECI) was responsible for the
installation of the cable tray for the new K6 line. Also, KECI provided
and installed all conduit, fittings, and cables to the new equipment.
In addition, KECI provided assistance for the electrical check out.
PO NO / KECI NO:
PO #171
KECI 05‐4860
JOB SITE LOCATION:
JP Price Sawmill
218 Midway Route
Monticello, AR 71657
OWNER:
JP Price Lumber Company
218 Midway Route
PO Box 536
Monticello, AR 71655
Point of Contact: Bobby Stone
GENERAL CONTRACTOR:
Westwood Companies
887 Fairweather Road
Vernon, BC Canada VIT 8T8
Project Manager: Jason McCormick
T 250.550.3453
F 250.542.8586
INITIAL MOBILIZATION / COMPLETION DATE:
January 2006 / November 2007
SUB CONTRACT AMOUNT:
$5,688,250
JP PRICE SAWMILL ELECTR ICAL & INSTRUMENTAT ION
SCOPE OF WORK:
This project consists of the electrical and instrumentation installation
of an existing saw and planner mills disassembled from Canada, and
brought down to Monticello, Arkansas and reassembled. This
reassembling will include the installation of Motor Control Centers,
cable trays, light fixtures, receptacles, grounding, lightning
protection, fire alarm system, CCTV system, and all associated
conduit and wire. This project also includes the new construction of
an office building, storage building, and site lighting.
CONTRACT NO:
KECI NO 03‐4852
JOB SITE LOCATION:
Pace Industries, Inc.
513 Highway 62/65 Bypass N
Harrison, AR 72602
OWNER:
Pace Industries, Inc.
513 Highway 62/65 Bypass N
P.O. Box 1198
Harrison, AR 72602
Point of Contact:
David Thomason / J.W. Moore
T 870.741.8255
GENERAL CONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
Project Manager: Bryce Koontz
T 501.354.2526 ext 115
F 501.354.2580
INITIAL MOBILIZATION / COMPLETION DATE:
March 2004 / June 2004
AWARDED / FINAL CONTRACT AMOUNT:
$259,792 / $259,792
P A C E I N D U S T R I E S I N T E R R U P T I B L E POWE R D E S I G N
SCOPE OF WORK: Koontz Electric installed the following:
• (3) 1750 kW Generators
• 15 kV Paralleling Switchgear
• (3) Power Transformers
• Interrupter Switches
• High Voltage Transmission Lines
• All Conduit, Conductors and Terminations
• Concrete Foundations
PROJECT:
FLUOR / CIBA Specialty Chemicals
Project 1200
JOB SITE LOCATION:
CIBA Specialty Chemicals
West Memphis, AR
OWNER:
CIBA Specialty Chemicals
100 Bridgeport
West Memphis, AR 72301
Point of Contact: Horace Sullivan
T 870.735.8750
GENERAL CONTRACTOR / ENGINEER:
Fluor Daniel, Inc
100 Fluor Daniel Dr
Greenville, South Carolina 29607
Point of Contact : Ralph Gumpert
T 864.281.4400
SUBCONTRACTOR:
Koontz Electric Company, Inc
1223 E Broadway
Morrilton, AR 72110
T 501.354.2526
F 501.354.2580
INITIAL MOBILIZATION / COMPLETION DATE:
January 1999 / September 1999
SUB CONTRACT AMOUNT:
$3,133,509
C I BA S P EC I A LT Y CH EM I CA L S PRO J E C T 1200
SCOPE OF WORK:
Koontz Electric was a subcontractor to Fluor Daniels, who had ‘Design/Build’ responsibilities for this ‘green field’ chemical process plant. This new eight story plant produces chemicals used as an additive in water treatment processes. Koontz Electric was awarded both power / lighting and instrumentation and controls.
This new plant is fed with a primary service, 13.8kV. This is stepped down to 4,160 and 480 volts. The 4,160 serves two 800 hp chillers. The 480v, 3,200 amp service supplies the balance of plant loads, including (75) pumps. The 480v distribution system is backed up by a 450kW generator for critical loads. All power cables leave the control block in cable tray to their final load.
The instrumentation included over 1200 field devices, such as control valves, smart pressure transmitters, smart vacuum transmitters, flow transmitters, limit switches, etc. Koontz personnel bench calibrated all new instruments, field installed and assisted in loop check and system commissioning. Koontz also installed several thousand feet of ½” instrument air header, stainless steel tubing, and poly tubing. All of the instruments are connected to an APACS Moore SCADA System. Koontz Electric installed the APACS equipment and terminated all cables.
Koontz Electric Company, Inc. welcomes an opportunity to make your next project a success. We
maintain a professional and technical staff to support our expert field team of technicians and
craftsman. Please contact any one of the Koontz Management team listed below for more information.
Name Title Cell Phone Email
Benny Koontz President / CEO (501) 977-6086 [email protected]
Dean Hoover Executive Vice President / COO (501) 977-6063 [email protected]
Matt Zimmerman Executive Vice President / CFO (501) 977-6231 [email protected]
Bryce Koontz Vice President - Business Development (501 289-0965 [email protected]
Jeff Ludwig Vice President - Project Management (501) 977-6098 [email protected]
Jamie Zimmerman Project Engineer (501) 977-6538 [email protected]
Paul Zimmerman Project Engineer (501) 977-6545 [email protected]
Jeremy Stell General Manager (501) 977-6019 [email protected]
Koontz Electric Company, Inc. 1223 East Broadway Morrilton, Arkansas 72110 501-354-2526 http://www.koontzelectric.com