kota thermal power plant ppt
TRANSCRIPT
KOTA SUPER THERMAL POWER STATION KOTA (RAJ.)
SUBMITTED BY:
Prakash Chandra Jarotia
2011UEE!374
INTRODUCTION OF THE THERMAL POWER PLANT
It was established in 1983.It is located at the left bank of the CHAMBAL River at theupstream of KOTA BAIRAJ.Favorable conditionAbundant quantity of clean cooling water.Good transport facilityConcentration of load in Kota region due to large number ofindustries.
INSTALLED CAPACITY
Kota Thermal Power Station is Rajasthan's First major coal power station. Presently
it is in operation with installed capacity of 1240MW.
DEFINITION OF THERMAL POWER STATION
A thermal power station is a power
plant in which the prime mover is steam
driven. Water is heated, turns into
steam and spins a steam turbine which
either drives an electrical generator .
After it passes through the turbine, the
steam is condensed in a condenser
and recycled to where it was heated;
this is known as a Rankine cycle . The
greatest variation in the design of
thermal power stations is due to the
different fuel sources. Some prefer to
use the term energy center because
such facilities convert forms of heat
energy into electrical energy.
OPERATIONS IN THERMAL POWER STATION
Step wise operations in a
thermal power plant are as
follows:-
Coal is used as a fuel to boil
the water.
Water is boiled to form
pressurized steam.
Pressurized steam is the
force that cause the turbine to
rotate at a very high speed.
Low pressure steam after
pushing through the turbine
,it’s going into the condenser.
Condenser – the place where
the steam is condensed back
it it’s liquid form .Then the
process is repeated
MAIN PARTS OF THERMAL POWER STATION
1. Coal supply
2. Coal pulverizer
3. Boiler
4. Precipitators
and stack
5. Turbine and
generator
6. Condensers
and cooling
water system
7. Water
purification
8. Ash systems
9. transformer
and
transmission
lines
Coal Handling Plant
• Wagon unloading system
• Crushing system
• Conveying system
Coal handling plant section
WAGON UNLOADING SYSTEM
Rated Output : 71 KW.
Rated
Voltage. : 415 V.
Rated
Current. : 14.22 Amp.
Rated Speed. : 975rpm.
No. of phases. : 3
Frequency. : 50 HZ.
Unload the coal from wagon
to hopper with the help of
wagon Tripler.
Hopper allows to pass coal
pieces ≤ 200mm
From hopper coal fall on
vibrator which is supported
by roller.
CRUSHING SYSTEM
CRUSHER HOUSE:- It consists of crushers which are used to crush the coal to 20 mm size.
Two types
Primary crusher Rail crusher
Rotary breaker
Secondary crusher
Capacity : 1350 TPH (Rates/ 1500 TPH Design.)
Feed material : Rom Coal.
Feed size : (-) 1200 mm
(approx.)
End Product size : (-) 500
mm Motor rating : 125
KW,100 rpm
Crushers : 225.
CONVEYOR BELT
Conveyor Belt Specification :- Belt width : 1400 mm.
Speed : 2.2 m/second.
Schedule of motor : All 3-phas
induction motor
Travel Motor : 7.5 KW.
Vibrating Feeder : 2x6 KW.
Total installed power. : 360 KW.
Capacity : 1) 1350
tonne per hour
2) 750
tonne per hour.
No. of conveyor : 38
Horizontal length : 28 meters
Belt are used to convey coal from coal handling plant to furnace.
BOILER
It is a closed vessel in which water under pressure is converted into steam.
Hot water or steam used to transfer heat to a process.
A boiler is always designed to absorb maximum amount of heat released in process of combustion.
This is transferred to the boiler by all the three modes of heat transfer i.e. conduction. Convection and radiation.
Furnace:- It is primary part of boiler where the fuel is burnt to liberate the heat energy.
Chemical
Energy of
fuel
Thermal
Energy by
combustion
FIGURE BOILER
Boilers are classified as:-
Fire tube boiler:- In this type the products of
combustion pass through the tubes which
are surrounded by water. These are
economical for low pressure only.
Water tube boiler:- In this type of boiler
water flows inside the tubes and hot gases
flow outside the tubes. These tubes are
interconnected to common water channels
and to steam outlet.
SUPER HEATER :- Superheated steam is that steam, which contains
more heat than the saturated steam at the same pressure i.e. it, has been
heated above the temperature corresponding to its pressure. A
superheater is a device which removes the last traces of moisture from the
saturated steam leaving the boiler tubes and also increases its
temperature above the saturation temperature.
REHEATER :- Reheaters are provided to raise the temperature of the
steam from which part of energy has already been extracted by HP turbine
PRECIPTATOR AND STACK :-
ELECTRO-STATIC PRECIPTATOR For general mankind, today an Eco friendly industry is must. As far as air pollution is concerned now a day various flue gases filter are there in service. The choice depends on the size of suspended particle matter. These filters are E.S.P. Fabric filter high efficiency cyclone separations and stalling room. Fop fly ash, where the particle size vary from 0.75 microns to 100 micron use gradually use E.S.P. to purify the flue gases due to its higher efficiency & low running cost etc.
In an ESP the dust lidder gas is passed through an intense electric field, which causes ionization of the gases& they changed into ion while travelling towards opposite charged electrode get deposited as particles and thus dust is electric deposited an electrode creating the field. It is continuous process.
The gas exiting the boiler is laden with fly ash.The fly ash is removed by electrostatic precipitators and passes through stack in environment.
STEAM TURBINE
It is a machine in which a shaft is rotated steadily by reaction of steam, air upon blades of a wheel.
When Steam is used then it is called steam turbine.
It works on Modified Rankine cycle.
Heat of
steam
Mechanical
Energy
THE MAIN TECHNICAL DATA OF 110 MW TURBINES IS
GIVEN BELOW :-
Rated output : 110 MW.
Economic output : 95 MW.
Rated speed : 3000 rpm
Direction of rotation viewing from the front bearing pedestal : clock wise
Rated steam pressure before stop valve : 130 ata
Maximum steam pressure before stop valve : 146 ata
Rated temperature of steam before the stop valve. 535°C Maximum temperature of steam before the stop valve. 545°C Rated pressure of steam 31.6 ata
•An electrical generator is a machine which converts mechanical energy into electrical energy through electro mechanical energy conversion .
•The generator is driven by directly coupled steam turbine at a speed of 3000 r.p.m.
Electrical
Energy
Mechanical
Energy
GENERATOR
CONDENSERS AND COOLING WATER SYSTEM
A condenser is a commonly used term
for a water-cooled shell and tube heat
exchanger installed on the exhaust
steam from a steam turbine in thermal
power stations.
These condensers are heat exchangers
which convert steam from its gaseous to
its liquid state at a pressure below
atmospheric pressure
In thermal power plants, the primary
purpose of a condenser is to condense
the exhaust steam from a steam turbine
to obtain maximum efficiency, and also
to convert the turbine exhaust steam
into pure water so that it may be reused
in the steam generator or boiler as
boiler feed water.
COOLING TOWERS
o A condenser needs huge quantity of water to condense the steam .
o Most plants use a closed cooling system where warm water coming from condenser is cooled and reused
o Small plants use spray ponds and medium and large plants use cooling towers.
o Cooling tower is a steel or concrete hyperbolic structure having a reservoir at the base for storage of cooled water
o Diameter at the base is 150 m
WATER TREATTENT PLANT
The principle problem in high pressure
boiler is to control corrosion and steam
quality.
The impurities present in water are
as follows:-
1) Un-dissolved and suspended
solid materials.
2) Dissolved slats and minerals.
3) Dissolved gases.
4) Other minerals (oil, acid etc.).
5). a) Turbidity & Sediment.
b) Silica.
c) Micro Biological.
d) Sodium& Potassium Salt.
e) Dissolved Sales Minerals.
6). a) O2gas. b) CO2 gas.
Pressure filter removes undisclosed impurities from
raw water.
Carbon filter removes excess chlorine from clarified
water.
D.M. plant removes dissolved impurities from clarified
water.
Conductivity ,pH & silica content of this water must be
checked time to time.
ASH HANDLING PLANT
The percentage of ash in coal varies from 5% in good quality
coal to about 40% in poor quality coal
Power plants generally use poor quality of coal , thus amount
of ash produced by it is pretty large.
Electrostatic Precipitator is used in ash handling plant to
remove fly ash
The stations use some conveyor arrangement to carry ash to
dump sites directly or for carrying and loading it to trucks and
wagons which transport it to the site of disposal
UTILIZATION OF ASH
1. Manufacturing of building materials.
2. Making of concrete.
3. Manufacturing of cement.
4. Road construction etc.
SWITCHYARD
Two 220 KV bus bars have been
provided in switch yard and are
inter-connected through a bus
coupler.
Each station transformer has two
windings one secondary side and
is rated for 50/25/25mva,
270/7/7.2 kva four feeder take off
from 220 switch yard two to
SKATPURA GSS and other to
HEERAPURA , Jaipur GSS.
Each of four feeder are provided
with bypass isolators which is
connected across line breaker
and breaker isolator
SALIENT FEATURE OF K.S.T.P.S. LOCATION
LOCATION -:Sakatpura, Kota.
CAPACITY-:
A) 1st Stage-: 2x110 MW .
B) 2nd Stage-: 2x210 MW.
C) 3rd Stage-: 1x210 MW.
D) 4th Stage-: 1x195 MW.
E) 5th Stage-: 1x195 MW
SOURCE OF WATER- : Chambal River.
BOILER-: a) Types. Fire tube boiler and Water tube boiler.
b) No. of units . 7
c) Max. Efficiency. BHEL 87.6 %
d) Capacity. 375 tonnes 1 Hr.
e) Steam Pressure -:139 Kg./cm²
f) Steam Temp. -:540
CONCLUSION
The first phase of practical training has proved to be quiet fruitful. It provided an opportunity for encounter with such huge machines like wagon tippler .110 MW, 210 MW & 195 MW turbines and generators.
The architecture of the power plant the way various units are linked and the way working of whole plant is controlled make the student realize that engineering is not just learning the structured description and working of various machines, but the greater part is of planning proper management.
However training has proved to be quite fruitful. It has allowed an opportunity to get an exposure of the practical implementation to theoretical fundamentals.