Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Support Services (ITSS)Strategic Goal Responsibility Milestones Measurement Target Status
Enhancing Teaching, Learning and Research
Responsibility Milestones Measurement Target Status
Establish measures of the services (including costs) of providing Teaching Computer Laboratory Support
Susan McLennan Develop appropriate measures;
Ensure all laboratory support is logged through Help Desk system;
Develop systems for recording data collected;
KPI's identified
Costs of support identified.
Sem 1, 2004 pending
Work in partnership with academic staff to ensure all problems in teaching computers laboratories are reported and logged
Susan McLennan Meet with faculties to understand their needs and issues;
Develop procedures for reporting single computer outages in labs;
Develop procedures for reporting major computer lab outages in teaching computer labs;
Procedures in place for academic staff to report issues;
Sem 1, 2004 Working party formed with FOBPM.
Key areas of review identified.
Investigate Student and Curriculum laptop trial
Mark Ridge Feasibility Study; Feasibility report with recommendations completed;
Engaging with the Professions and Professional Life
Responsibility Milestones Measurement Target Status
Implement a "Best Practice" framework for IT Services
ITSS Senior staff Ensure ITSS staff have training/understanding in ITIL;
Encourage other IT areas to participate; Provide the opportunity for an additional six
(min) to undertake the Service Management Foundations course and exam.
ITIL Framework implemented throughout IT
On-going All ITSS staff attended overview or attended Foundations course;
Other managers have attended Foundations course;
Membership to appropriate Professional bodies
Mark Ridge Help Desk Institute; IT Service Management Foundation; ACS
On-going
Building Partnerships, Pathways and Precincts
Responsibility Milestones Measurement Target Status
Develop partnerships with ITSS Mangement Team
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 1 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Support Services (ITSS)Strategic Goal Responsibility Milestones Measurement Target Status
key suppliers ie. IBM, HP, Managesoft etc.)
Investigate delivery of services by students
ITSS Management Team Identify what services could be provided by students (ie Student Help Desk, student orientation, ?)
Investigate Shared Services -Joint negotiation for products and services
Utilise CAUDIT licensing agreements;
Best value purchasing of technology and services.
On-going
Improving Outcomes for Students and Staff
Responsibility Milestones Measurement Target Status
Provide Services catalog for students
Susan McLennan Service details collected; Service Catalog published
Provide Services catalog for staff
Sharon Johnston Service details collected; Service Catalog published
Establish measures of the usage and its profiles in the Megalabs
Susan McLennan Develop appropriate measures; Provide details that ECU meets benchmarks for computers provided for students.
Investigate setting up an orientation for students
Susan McLennan Work with relevant departments to coordinate orientation;
Successful studentf orientations;
Investigate setting up an orientation for students and staff
Sharon Johnston Work with relevant departments to coordinate orientation;
Successful staff orientations;
Work with LDS to develop appropriate staff computer training
David Sizer Work with LDS to define and document training required;
Upgrade Library Student PC's
David Sizer/Library Work with Library to define and document applications required;
Upgrade OS and use Managesoft;
Develop seemless IT Service (B)
IT Managers Change Help Desk name to Service Desk; Ensure all IT service requests are logged
through Service Desk; Work with other groups to resolve issues at
beginning;
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 2 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Support Services (ITSS)Strategic Goal Responsibility Milestones Measurement Target Status
Remote support for staff computers; Develop OLA's with ITI, IDS and IS; Re-initiate Senior IT staff meetings
Investigate extending support hours
Mark Ridge Investigate resource implications; Tender evaluation and selection;
Investigate IT – Media Services integrated services
Mark Ridge Work with other managers (ITI and KAS) to evaluate options;
Intel SOE MkII Mark Ridge/David Sizer Tender process; Tender evaluation and selection; Contract preferred supplier and agree on Service
Levels; Formalise rollout process; Finalise software for rollout; Rollout computers; Manage further puchases and deliveries.
Completion February 04 Tender advertised and responses recieved.
Upgrade OS of computers not renewed during Intel
David Sizer
Library Staff SOE Mark Ridge/David Sizer Upgrade to XPProvide points in Megalabs for students using personal laptops
Mark Ridge/Susan McLennan
Help Desk System Mark/Ridge/Ven Boujos Tender Tender Evaluation and Selection Scope formal works Implementation of Incident Management Implementation of Problem Management Implementation of Change Management Implementation of Configuration Management
Complete installation of all Help Desk system modules
Nov 03(not achievable) Incident Management module Installed
Enhance Service Level Agreements
Mark Ridge Work with the other IT Managers to refine SLA's relating to Service Centres and corporate applications
Develop SLA for Library Set timelines for SLA review
Comprehensive, understandable SLA's
Aug 03(in the past, this year) SLA's developed
ITSS staff/resource allocation 2004 and beyond
ITSS Managers Review CSO rotation Assess the benefits and risk of the current CSO rotation
Review staff numbers per campus for projected student/staff numbers for 2004 & 2005
Review the impact of “Managesoft” to the staff desktop, are our resouces where they need to
Move of all ITSS staff from Churchlands campus;
Greater use and understanding of Managesoft environment by CSO staff;
Transition of Coordinator
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 3 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Support Services (ITSS)Strategic Goal Responsibility Milestones Measurement Target Status
be(do we have the right skilled people) Review work-load shifts for co-ordinators
roles to align with processes;
Self Based training for students and staff
Strengthening Enterprise and Resource Base
Responsibility Milestones Measurement Target Status
Be involved in the design of the new Resources Building at JO and in particular the Megalab
Mark Ridge/Sue McLennan
IT Documentation ITSS Managers Ensure an appropriate level of documentation is available for all ITSS staff;
Strategies to keep documentation up-to-date;
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 4 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Information SecurityStrategic Goal Responsibility Milestones Measurement Target Status
Enhancing Teaching, Learning and Research
Responsibility Milestones Measurement Target Status
Increase security of staff and student information.
.
SK Increase staff and student awareness of security issues. Develop Website Provide a knowledge base of policies, procedures and FAQs on line.
Messages on Student Virus Bulletin Board. Information in newsletters. Record number of hits Complaints
Strategies to reduce downtime due to security incidents.
TH Virus management. Client firewalls. Internet filtering. Spam control.
Firewall stats Internet filtering stats Spam filtering stats
Virus management working well.
Protecting on-line teaching, learning and research materials.
TH Virus management.. Client firewalls. Report on viruses, worms, Trojans being detected and removed.
Virus management working well.
Engage with faculties and schools. Both Information Security reps Access WP
Engaging with the Professions and Professional Life
Responsibility Milestones Measurement Target Status
Attend courses, information sessions, functions. ACS, Megabite, WAISSIG, other universities, Auscert
SK TH Attend meetings to network and learn Current Regular
ACS WAISSIG Megabite Tivoli User Group
SK SK TH SK TH SK TH
Identifying professional peersSK TH Make contact Meet UWA
Curtin Murdoch WA Police AFP
Met with Marie, Alex, Bruce Talk with Peter Sinclair No contact s here At WAISSIG – Ted and Tim Regular contact – Steve Elliott
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 5 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Information SecurityStrategic Goal Responsibility Milestones Measurement Target StatusSharing information
SK Requests from government agencies and from overseas to use our policies.
Building Partnerships, Pathways and Precincts
Responsibility Milestones Measurement Target Status
Build on relationships with Symantec, AlphaWest and IBM.
SK TH These are on-going
Work with Help Desk to produce statistics of security-related issues.
SK TH Have an IS queue on the new Help Desk system so will be able to use that.
Monthly stats to enable trend analysis.
Improving Outcomes for Students and Staff
Responsibility Milestones Measurement Target Status
Raising awareness of student and staff responsibilities. Raise awareness of the existence of the Information Security team.
SK THImproved web site that provides information, downloads and useful links. Need to put a counter on the
site.
Survey staff and students.Use newsletters to advertise our services.
SK Mailing lists, firewall logs, alerts and certs, journals, virus statistics from quarantine server.
Number of emails sent out regarding viruses is now negligible.
InfoSec web site, Bulletin boards and newsletters to alert staff and students.
Better reputation for secure, stable systems and for following up incidents.
AntiVirus Server and AntiVirus Client Support; monitoring of Firewall Rules and Logs;
Review of IDS systems; investigation of security breaches
Strengthening Enterprise and Resource Base
Responsibility Milestones Measurement Target Status
Information Security Management Tools Project SK Product selection. Ranked 1 at SIMSC
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 6 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Information SecurityStrategic Goal Responsibility Milestones Measurement Target StatusInternet filtering
ITI and InfoSec Websense trial. Further trials of other products.
Spam filteringITI and InfoSec Current trial
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 7 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Library (Knowledge Access Services and Knowledge Resources & Organisation) Strategic Goal Responsibility Milestones Measurement Target Status
Enhancing Teaching Learning and Research
Priority Responsibility Milestones Measurement Target Status
Library to participate in ARLIN A Shane, Lisa Jahn
As per national project milestones ECU fulfils requirements as per national project requirements
As per national project Project proceeding as per national project timeframesAiming to have basic portal in place for 1st semester 2004
Plan Campus consolidation A Dan, Swee Kit, Greg, Julia, Ian
Critical shelving for Educ ML Shelving for JO 2004 Provide cost short term solutions ML
Completion Ongoing to 2007
Implement E-reserve A Maureen
Service available to clients of library Service intergrated into normal operations of
either KAS or KRO as determined
Service availabilityService uptake by academic staff
Project completed and process integrated into operational workflows by end of June 2004
e-Reserve service available to all academic staff at university.e-Reserve part of copyright sampling for university Jan-April 2004.
Review library/media opening hours A Dan
Costing of extending library hours Continue trial MMR hours Library survey data Benchmark with other libraries
Develop Information Literacy plan for ECU
A Agnes, Julia, Lyn Outline the ECU Library Information literacy Package/Policy. This document to include:
o General introduction - A mission statemento Information in Practice – faculty programs,
Orientation, frontline assistance/individual, Online (link to Liberty/Ask us), Self paced, General
o Faculty Research, Embedded, On demand
Take it to LCC and then Academic services for acceptance
Take it to the Faculty Outline what we have been doing and the
measurement. In the policy package, consider student centred
learning, lifelong learning and research and include a Flow Chart.
Above identification of an ECU program
Existing Liberty has been updated. It is timely now to 2004 to consider a rewrite to consider the information literacy standards and a less linear approach to learning and improve the navigation.
Julia’s team has looked at Blackboard and noted several issues – Large PDF files are not handled well, students have to be enrolled in a Blackboard unit to get access.
May need to consider Liberty as separate and link to Blackboard. Need to work together with Faculty IDs to get the program recognized when revamped.
Subject librarians have been notified to consider freely available web learning
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 8 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Library (Knowledge Access Services and Knowledge Resources & Organisation) programs to add to the subject pages.
Need to follow up the link between indoor and the web subject pages [next WAG meeting – Glynis has requested one soon]
Implement instruction program for academic staff in using multimedia equipment
B Dan + MMR Contact Faculties Book Rooms Plan content
Implement LIDDAS end-users A Ian Waiting for final install of vdx 2.3.
Develop Collection Development Policy B Glynis
Policy in draft formPolicy tabled at Collection Development Working GroupPolicy tabled and approved at Senior Librarian meetingPolicy tabled for approval at Library Consultative Committee
Policy written and agreed to by Senior Librarian Group and LCC
To be completed by end of June 2004
Develop Collection Management Policy C Glynis
Policy in draft formPolicy tabled at Collection Development Working GroupPolicy tabled and approved at Senior Librarian meeting
Policy written and agreed to by Senior Librarian Group
To be completed by end of 2004
Develop Digital Document Policy A Glynis
Policy in draft formPolicy tabled at Collection Development Working GroupPolicy tabled and approved at Senior Librarian meeting
Policy written and agreed to by Senior Librarian Group
To be completed by end of February 2004
Establish a practice for collection and presentation of statistics showing user uptake of digital services
A Maureen
Practice agreed to by Senior Librarian Group and Jeff MurrayProcedure documented and statistics collected
Practice approved and implemented
To be completed by end of February 2004
Participate in Australian Digital Thesis Project A Lisa B.
Project Plan to SIMSC in AugustMethodology for lodging of theses by end of yearSoftware issues explored and sorted by end of October
ECU ready to lodge theses in digital form to ADT database by end of year
Project completed and process integrated into operational workflows by end of June 2004
Business Case presented to, and approved by, SIMSC. ECU has officially joined ADT Program. Project team formed. Project plan in progress.
Stocktake of library collection A Deb
Annual target for multiple dewey process reached
Annual target for stocktake of collections reached
Annual scheduled targets reached
Scheduled for completion at end of 2006
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 9 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Library (Knowledge Access Services and Knowledge Resources & Organisation)
Review exam papers collection A Maureen/Glynis
Retrospective analysis of collection and address of copyright issues completed
New procedure for future collection development of exam papers completed and implemented
Exam paper collection (retrospective and future) fulfils copyright regulations
To be completed by end of 2004
Investigate server space A GlynisInvestigation of server optionsServer space made available to library for storage
of electronic information resources
Server space obtained and set up
ASAP Initial meeting with IDS took place on 12/1/04.
Redesign of Web OPAC A Lisa Billingham
Engaging with the Professions and Professional Life
Priority
Responsibility Milestones Measurement Target Status
Promote staff participation in professional organisations B Dan, Glynis
Carcit functions Alia functions Anzil Stil
Attendance On going
Review & document library/media policies B Dan, Ian Complete Documentation training
Building Partnerships, Pathways and Precincts
Priority
Responsibility Milestones Measurement Target Status
Implement TAFE Reciprocal Agreement B Ian
Investigate library services as part of MTL, JO Learning Precincts
C Swee Kit, Greg
Actively participate in WAGUL, Auslg, Caul, etc. A Dan, Glynis Attendance On going
Improving Outcomes for Students and Staff
Priority
Responsibility Milestones Measurement Target Status
Determine staff structure for 2 campus model A Dan Multimedia Resources
Ensure all A Dan, Glynis LDS to arrange for course End of 2004
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 10 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Library (Knowledge Access Services and Knowledge Resources & Organisation) supervisors/managers attend Process Improvement Course
Ensure staff attend
Establish IT competency levels for staff B Ian, Swee Kit,
Greg
Completed at MTLCompleted at JOCompleted at CHU
Survey KRO customers B Maureen
Survey writtenSurvey distributedSurvey results collated and analysedResults presented to senior librarian group and KITSC ManagementSurvey feedback responded to
Survey process completed by April 2004
Draft survey written and distributed Dec 2003.Results not yet presented.
Organise visits to KRO C MaureenVisits organizedInvites sentVisits completed
To be completed before 1dst semester 2004
Library documentation standards A Shane Documentation system
available to library staff for useMarch 2004
Integrate Library/KITSC/ECU websites A Shane
Library website and higher level KITSC website operating within university web standards
Before start of 1st semester 2004
Review acquisitions processes A Glynis
Review procedure determined.Review performed.Changes implemented as a result of review.
To be completed by end of June 2004
Visits to WAGUL Bibliographic Services departments organized for first half of Feb, 2004.
Participate in evaluation of ITIL C Dan, Glynis
Establish a staff training plan B Swee Kit, GlynisMap career paths for various Hew levels A Dan, Glynis
Improve staff safety/security A Ian C.Promote conference attendance A Dan, Glynis On-going Glynis and Lisa Billingham to attend VALA Feb
2004Investigate virtual reference service B Swee Kit
Establish student focus groups to test key service areas
B Dan
Develop Library/KITSC intranet B Shane Intranet has been developed
and is in use by staff June 2004 Prototype intranet using Microsoft Outlook in
trial modeDevelop process for making database license information available to academic staff
B Maureen Database license information available to academic staff and students
June 2004
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 11 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Library (Knowledge Access Services and Knowledge Resources & Organisation) and students
Design and implement an Innopac Champions Group
B Lisa Billingham
Perform risk management analysis of KRO functions
B Glynis/MaureenAreas of risk identified and risk
management strategies documented
Dec 2004
Strengthening Enterprise and Resource Base
Priority
Responsibility Milestones Measurement Target Status
Reviews fines & charges A Ian
Comparison of charges completed. New schedule of Library Fines prepared. Recommendation on Document Delivery
charges prepared. Discuss with student focus group
To meet with Dan to discuss all charges, September 2003
Investigate marketing strategies A Julia Implement @your library
Establish Library key performance indicators A
Glynis, Dan Select benchmark libraries Establish benchmarks Rodski survey
Develop succession plan A Dan, Glynis
Develop records managements policy A Glynis, Dan
Develop an audit trail for the library collection A
Glynis Audit trail documentedPractices related to creation of audit trail implemented
Correct management of library collection as an asset February 2004
Draft Policy written, to be tabled as Senior Librarian Meeting 30/1/04
Investigate procedure for archiving of Innopac records A Lisa B. Method for archiving of Innopac records determined
and documented September 2004
Analyse collection of KRO statistics
BGlynis, Maureen Determine what statistics should be collected and
how they should be presentedDocument procedures for collection of statistics
Procedures for statistics collection documented
End of June 2004
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 12 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Library (Knowledge Access Services and Knowledge Resources & Organisation) Investigate handling of phone calls C Ian C.
Updated Dan 131103Glynis 190104
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 13 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
Enhancing Teaching, Learning and Research
Responsibility Milestones Measurement Target Status Comments
Multimedia Projector Installations
Charlie King Existing locations at ML, JO and CH (upgrade); and
New locations (CampusWest JO, Stagehouse II ML, Building 8 JO).
Faculty satisfaction with new multimedia hardware;
Faculty sign-off. Mount Lawley complete;
Churchlands complete.
Building 8A (JO) complete;
Stagehouse II (ML) complete;
CampusWest (Building 2) complete;
CampusWest (Building 1) underway;
Joondalup underway.
The Media Services Brief needs to be completed urgently.
Priority C
SNAP Wired Network Points
Chris Blanksby New item. Wired network points within MegaLabs.
Priority B
Bunbury WAN enhancement
Steve Johnston Authority to purchase
Placement of purchase order
Installation
Commissioning
Bunbury satisfaction with new network service.
Bunbury sign-off. New item. A redundant connection to Bunbury needs to be established in 2004. There is a greater reliance on the data network within the University.
The National Communications Fund (NCF) tender can be used for selection of this network service.
Priority C
Wireless Campus Project Chris Blanksby Tender
Selection
Implementation
Commissioning
Wireless coverage. Wireless coverage for all meeting areas, teaching areas and 90% of the campus.
SIF funding has been allocated ($385k);
Due to commence in early 2004 (draft tender documentation complete).
Priority A
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 14 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
Library SunRay Installation and Upgrade
Paul Midgley / Keith Lambert
Replacement of JavaStations in the library with SunRay hardware;
Upgrade of software, etc. to cover Library requirements
Replacement of all JavaStations;
Library satisfaction with new installation.
Library sign-off. Installation complete;
Initial upgrade complete;
Second upgrade underway.
The future of SunRays within the library needs to be considered between IT (IT Infrastructure and IT Support Services in particular) and Library.
Priority C
Engaging with the Professions and Professional Life
Responsibility Milestones Measurement Target Status Comments
Collegial Groups Steve Johnston Identify appropriate collegial groups which may be of value to IT Infrastructure.
Relevance of membership against IT Infrastructure activities.
Meeting attendance, conference attendance, reports, etc.
Appropriate activities coverage.
Enhance our effectiveness by the gaining of expert knowledge from collegial groups.
New item. IT Infrastructure is currently involved in the following collegial groups:
AARNet (Australian Academic and Research Network)
ATUG (Australian Telecommunications Users Group)
TUG (Tivoli Users Group)
CAUDIT (Council of Australian Directors of Information Technology)
ACS (Australian Computer Society)
OUG (Oracle Users Group)
Other Perth UniversitiesPriority C
Implement a best practice for delivery of IT Services (ITIL)
IT Management Team New item. IT Infrastructure Library
Priority A
Building Partnerships, Pathways and Precincts
Responsibility Milestones Measurement Target Status Comments
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 15 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
WALAP authentication project
Peter Austin Tender process (including selection);
Installation and commissioning of hardware; and
Production connection between Universities.
Installation behind Alteon WSM.
Shared authentication information between Universities – and shared services;
Project completion sign-off (by all Universities);
Tender complete;
Hardware installation complete;
Provisioning complete (in production);
Documentation to be completed.
ECU and UWA are effectively in production with the WALAP system;
Other Universities are working towards production systems.
The ECU system needs to be networked behind the Alteon WSM.
Priority B
Telecommunications Restructure
Chris Blanksby / Brian Lambert
Modification of existing networks to terminate voice services in the Perth CBD;
Tender for provision of telecommunications services (as per new termination point).
Reduction in telecommunications services;
Direct telecommunications savings to Faculties (with no service degradation).
Waiting completion of prerequisite works.
Microwave decommissioning scheduled for completion in December 2003;
The tender for telecommunications services is expected to be operated in January 2004;
Priority B
Develop Partnerships with Key Suppliers
New item. Cabling – vendor to be selected
Media – vendor to be selected
Servers – IBM
Network – Nortel Networks
Telecommunications – AAPT / TelstraPriority B
Improving Outcomes for Students and Staff
Responsibility Milestones Measurement Target Status Comments
Benchmarking and Key Performance Indicators
Steve Johnston Selection of appropriate KPI’s for each functional area;
A set of KPI’s per section;
An agreed set of KPI’s defined, and in place;
Procedures established for
New item. Sub-projects may be required to implement certain KPI’s, and to ensure that appropriate measures are taken.
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 16 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
Selection of appropriate KPI’s for IT Infrastructure.
Provision of data, etc. for IT KPI’s
Provision of data, etc. for KITSC KPI”s.
provision and maintenance of data, etc.
CAUDIT benchmarks will need to be reported, and should be taken into consideration when establishing the KPI’s.
KPI’s to be considered:
Uptime (e-mail, network, directory services, etc)
Responsiveness;
Throughput;
Systems measures (CPU utilisation, disk usage, etc).Priority A
E-Trust Peter Austin Connection of Blackboard;
Connection of Innopac;
Connection of other internal web applications requiring web authentication as required;
E-trust being used as an authentication source.
Connection of appropriate systems.
New item. E-trust is to be used as the authentication source for web-based applications.
E-trust is currently being established as the source of Blackboard user authentication via LDAP;
Priority B
Student E-mail Upgrade Peter Austin Purchase, installation and commissioning of new hardware and software;
Decommissioning of ‘echidna’ – old student e-mail system.
Student e-mail satisfaction;
Improved feedback by students, as measured by survey.
Project complete1. This project is being consumed by the “Student Portal Project”;
There are concerns that e-mail may not be appropriately addressed;
The existing student e-mail hardware is not appropriate, is aging, and requires urgent replacement.Priority C
1 New works on the student e-mail system have been commissioned by the Student Services Centre – this work is underway, but is separate to the 2002/2003 e-mail upgrade.
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 17 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
Messaging and Collaboration
Peter Austin Purchase, installation and commissioning of new hardware and software;
Migration of all GroupWise users to exchange;
Migration of all POP/IMAP users to exchange; and
Decommissioning of old GroupWise hardware.
Migration of all staff to exchange server hardware for e-mail;
100% migration. Purchase, installation and commissioning of new hardware and software complete;
Migration of GroupWise is effectively complete.
Clean-up stage has commenced.
Decommissioning of the GroupWise servers will commence in December, 2003.
Completion of this project is expected by the end of 2003.
Non-GroupWise users are being targeted as part of the Intel SOE roll-out (November 2003 – March 2004).
Priority B
ADS Directory Introduction
Peter Austin / Chris Blanksby
Purchase, installation and commissioning of new hardware and software;
Migration of directory queries to make use of ADS database;
Decommissioning of NDS directory;
Decommissioning of NDS (and IPX) within the entire University network.
Nil reliance of use of NDS/IPX and full decommissioning.
Purchase, installation and commissioning of ADS domain controllers complete;
Migration of student networks to ADS complete;
Removal of staff NDS tree will be completed as part of the Intel SOE roll-out (November 2003 – March 2004).
An ADS upgrade is currently in progress (Windows 2003 ADS).
Priority B
Server Consolidation Keith Lambert
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 18 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
Purchase, installation and commissioning of new hardware and software;
Development of Server Replacement Policy;
Confirmation of staffing levels within the Enterprise Systems Group;
Improved server management within the University;
Improved server security;
Staffing levels for Enterprise Systems Support.
Approved server replacement policy;
Approved server documentation;
Confirmed staffing levels.
Purchase, installation and commissioning of SAN hardware complete;
Purchase, installation and commissioning of hardware (other than ERP systems) complete;
Purchase of Backup hardware and software complete;
Commissioning of backup hardware and software underway.
Additional tasks as raised by the Server Consolidation Steering Committee.
Priority A
Voicemail Upgrade Brian Lambert / Chris Blanksby
Purchase, installation and commissioning of new hardware and software;
Decommissioning of existing Voicemail hardware;
Service improvement. Provision of network FAX;
Provision of voicemail/e-mail integration.
Waiting completion of prerequisite works.
Microwave decommissioning scheduled for December 2003.
Priority B
Exchange Archiving Project
Peter Austin Publication of tender
Selection
Implementation
Commissioning
Accessibility of archived e-mail and the ability retain e-mail as required (without the limitation of disk space).
Time taken to backup exchange data store.
Optimum performance and availability of the exchange server;
Backup of exchange data store in 4 hours or less.
Tender process complete.
Procurement underway.
Implementation planning started.
The issue of ‘archiving’ v ‘journaling’ has been raised, and needs to be addressed by IT Infrastructure along with Information Security and Records Management.
Priority B
Modempool Services Steve Johnston / Chris Blanksby
New item. The Modempool service needs to be decommissioned (or substantially changed);
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 19 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
In conjunction with IT Support Services
Measure dissatisfaction;
Working party: Ven Boujos, Steve Johnston, Chris Blanksby, etc.Priority A
Strengthening Enterprise and Resource Base
Responsibility Milestones Measurement Target Status Comments
Internet Cost Management
Steve Johnston Introduction of hardware and software tools to control, measure and manage traffic;
Tender for provision of reporting software;
Purchase, installation and commissioning of reporting software;
Provision of Internet Accounting to Faculties and Centres;
Reduction and devolution of internet cost;
Internet cost reduced to beneath $600k;
100% of Internet cost devolved to Faculties/Centres by usage.
Introduction of hardware and software commenced;
Tender/purchase for reporting software underway.
Tender for Internet Cost Accounting Software was commenced in September 2003. There were no responses to this tender document.
Priority A
Proxy Appliance Installation
Chris Blanksby Product selection;
Purchase, installation and commissioning of proxy appliance;
Purchase, installation and commissioning of duplicate proxy appliance;
Proxy use for all purposes;
Reliable proxy service.
100% of proxiable traffic presented via proxy.
Project complete. This item may be closed.
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 20 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
AARNet PoP – Network Restructure
Chris Blanksby Relocation of AARNet PoP (Point of Presence);
Provision of redundant connections to the Internet via Perth CBD;
Relocation of services; Relocation of services. Project complete. This item may be closed.
VoIP Project Brian Lambert / Chris Blanksby
Proof of concept;
Product selection;
Purchase, installation and commissioning of VoIP hardware (for trunking only);
Decommissioning of 1993 Microwave Network.
Network usage;
Service provision (no degradation of service).
Decommissioning of 1993 Microwave Network (Metropolitan Area).
Proof of concept underway.
IP telephony for voice trunking has been put on hold.
A project for full VoIP will be conducted in 2004/2005 for installation of VoIP equipment into the Joondalup Resources Building.
Priority C
Alteon Firewall Installation
Chris Blanksby Product selection;
Purchase, installation and commissioning of Firewall;
Purchase, installation and commissioning of duplicate firewall.
Firewall protection. 100% of network protected by firewall (between University network and Internet).
Project complete. This item may be closed.
Backup & Disaster Recovery
Michael Grant / Keith Lambert
Development of IT Backup and Disaster Recovery document (in consultation with all University Stakeholders);
Development of implementation strategy;
Documentation completed, accepted and implemented.
Reference of implementation plan to SIMSC.
IT Backup and Disaster Recovery plan is complete and has been approved.
Final Backup and Disaster Recovery document as been approved.
Planning is required for implementation of the recommendations of this document.
Priority A
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 21 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
IT Infrastructure ServicesStrategic Goal Responsibility Milestones Measurement Target Status Comments
IT Infrastructure Documentation Project
Steve Johnston, Chris Blanksby, Keith Lambert, Brian Lambert, Peter Austin
Framework for documentation (ITIL compatible);
Creation of documentation repository;
Creation of documentation framework and templates;
Documentation procedures, etc.
Systems, network, hardware, etc. and procedures documented in a secure, but accessible location.
New item.
Priority A
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 22 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Information Delivery SystemsStrategic Goal Responsibility Milestones Measurement Target Status
Enhancing Teaching, Learning and Research
Responsibility Milestones Measurement Target Status
Blackboard V6 upgrade Chris Cooper Blackboard V6 QA available for CMS POC
Blackboard user acceptance testing.
QA accepted
User acceptance testing signoff by LDS
QA - December 2003
PROD – January 2004
WIP
Courses and Units Database Rick Movick Phase 3
Interfaces to other systems
Enhancements
Packaging for sale
User signoff Phase 3 - October 2004 Pending budget approval
Callista Research Lesley Reynoldson Phase 2
Development of RAI and ETHICS modules
Phase 2 – Budget Phase 2 - September 2004 Pending budget approval
Learning Content Management System
Chris Cooper Issue RFT Package selected & implemented July 2004 Planned
Unit Information Management System
Rick Movick Project started User acceptance signoff July 2004 Pending budget approval
UTEI Upgrade Rick Movick Functional requirements
Systems design & build
Application Implemented
User acceptance signoff July 2004 WIP
SONIA – Nursing placement system
Clinton Moore-Crouch Package installed User acceptance signoff January 2004 Planned
Engaging with the Professions and Professional Life
Responsibility Milestones Measurement Target Status
Join key Oracle User groups Doug Trewenack Identify membership groups Memberships completed February 2004 Planned
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 23 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Information Delivery SystemsStrategic Goal Responsibility Milestones Measurement Target Status
Join Microsoft user groups Rick Movick Meymbership subscriptions Memberships completed February 2004 Planned
HES HRIS Karen Harris Continuing participation in HES:
Concept e8.07 reconciliation and audit
Reconciliation and Audit completed September 2004 Planned
Concept User Group Karen Harris Continuing participation
Attend local user group
Network via email forum with other user organisations
Influence on Concept product direction
Implementing product incorporating ideas from other user organizations
Ongoing ongoing
Join Oracle User Group Satish K Bedekar Apply for WA Oracle User Group membership Membership Completed February 2004 Planned
Join COGNOS User Group Satish K Bedekar Apply for COGNOS User Group Membership Membership Completed February 2004 Planned
Building Partnerships, Pathways and Precincts
Responsibility Milestones Measurement Target Status
Collaboration with Joondalup City Council
R. Movick Meet to decide framework & explore opportunities
Opportunities for sharing and co development identified
March 2004 Planned – first meeting
Explore new channels for revenue R. Movick Package eShop & CUDB eShop & CUDB packaged
Agreement signed with Redbell
February 2004 Planned
Completed – Onestop & Envisage
Oracle D.Trewenack Implement BATPROD and CAT9 Databases using Oracle’s 9iRAC
Successful operation January 2004 Configuring initial cluster server
EMC D.Trewenack ECU/EMC Press release Completion February 2004 Planned
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 24 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Information Delivery SystemsStrategic Goal Responsibility Milestones Measurement Target Status
HES HRIS R&D Karen Harris Collaboration with other HES universities to develop Business requirements to fast track development in Concept
HES meeting, agree on focus initiative and BRS developed
October 2003 planned
Improving Outcomes for Students and Staff
Responsibility Milestonese Measurement Target Status
thentication Rick Movick Central Authentication System developed Authenticate staff and students for BB, Callista connect, eShop
November 2004 WIP
Digital Portal (Staff & Students) Lesley Reynoldson, Doug Trewenack
Foundations and standards
MSC portlet; GPPS and Ehics portlets developed.
User acceptance & signoff July 2004 WIP
Australia Post mail barcodes Business Analysts Incorporated into ERP systems In-house mail labels barcoded and barcode values incorporated for mailhouses
September 2004 Planned
UTEI Upgrade – Phase 2 Rick Movick Web enable unit survey forms User acceptance & signoff July 2004 WIP
Customer Relationship Management (CRM)
Rick Movick SIG (special Interest Group) formed
Business case & budget submission
Acceptance by SIMSC October 2004 Planned
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 25 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Strengthening Enterprise and Resource Base
Responsibility Milestones Measurement Target Status
Callista SMS support Rick Movick
Steve Edwards
Satish Bedekar
Development
Interim COFI interface
Gradware interface
ETS changes
EPS changes
Authentication for Connect
Active involvement – prior to Go live
Agreement reached for IDS staff roles in Version 6.1 upgrade in September 2003
DBA tasks assigned
Other tasks assigned TBA
User acceptance & signoff February 2004 WIP
HR Web Kiosk, additional functional implementation
Karen Harris ECU staff email aliases loaded into HR database and maintained
Develop procedures to automate updating of users for workflow
Support implementation of additional functionality
Leave bookings implemented in kiosk for next centre/faculty – phase 1
Leave bookings rolled out to other centres/faculties
Plan for next functionality to be implemented via kiosk
September 2004 Planned
Consolidate small & medium systems support
Rick Movick Submission for SIMSC
SIF Funding bid for additional 3 staff
SIMSC Acceptance
SIF Funding approved
August 2004 Planned
Implement ITIL framework Rick Movick IDS Staff to attend ITIL Foundations course
Enter SLA’s with MSC, SSC and FAS
Enter OLA’s with other units
Staff attendance and certification
SLAs signed with customers
October 2004
Interim SLAs signed
Half day awareness workshops being conducted.
Planned – 2 day foundations course
Increase IDS support base Rick Movick Develop proposal for SIF funding to increase IDS staff by 3.
Lodgment this year Meet SIF submission cut off date Planned
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 26 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Technology Skills Training Rick Movick Develop a skills register to support applications and SAN.
Gap analysis completed
Training schedule completed
Staff trained.
September 2004
All training to be completed by October 2004
Planned
Contingency staff support Rick Movick Develop plan & budget
Training completed
Staff able to provide backup support in other systems
June 2004 Planned
Development & Evaluation environments
Rick Movick SOE WIN2K Test and QA servers
Oracle Test and QA servers
Oracle 9i RAC Linux on Intel evaluation.
SOE Win2K servers accepted by IDS
9i RAC evaluation completed.
March 2004 WIP – to be followed up with ITI
FINPROD SAN implementation D.Trewenack Connect nadir
Migrate finqa
Test finqa backup and recovery
Connect cyclops
Migrate finprod
Test finprod backup and recovery
Operational systems February 2004 Planning physical move of nadir from Wang room to Churchlands computer room
Externally acquired system support
R.Movick Supply training
Supply manpower
Provide sufficient time and planning for successful takeover
as required under discussion
Staff Training R.Movick / D.Trewenack
Oracle 9i
SAN Administration
SAN DBTuner
to be scheduled
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 27 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
Oracle R11i Implementation Satish K Bedekar Project Scope Agreed
Finalize Tender/Quote Specification
Invite Tender/Quotes from selected vendors and Evaluate Tenders
Project Funding approved
Project PEP Finalized
Set up new software in Dev env
Set up new software in QA env
User Testing and Acceptance
Go Live
Post Implementation Review
Project Scoping Document Signed
Tender/Quote Specification Signed
Evaluate Tender/Quotes and Recommend Preferred Supplier
Contract Signed with the Vendor
PEP Document Signed
Development Environment available
QA Environment available
User Acceptance signed off
New Software in Production
Sign off on Post Imp Review document
October 2004 Planned
Cognos7 Upgrade Satish K Bedekar Get Project Funding Approval
Prepare PEP
Get Additional WEB Licenses
Upgrade Dev/QA Server
User Testing and Acceptance
Upgrade Production Server
GO Live
Update user Desktop Software
Project Funds Approved
PEP Document Signed
Contract signed with COGNOS
Cognos7 working in the new env
User Acceptance signed off
Cognos7 Prod env available
Cognos7 in Production
Desktop Users using Cognos7
January 2004 WIP
Technology Skill Training Rick Movick Callista Finance Training
Cognos Training
Oracle R11i Training
March 2004 Planned
Eshop enhancements Rick Movick Plan development , including interfaces. Plan accepted October 2004 Planned as part of the 11i implementation
File: /tt/file_convert/548f3955b47959046a8b4611/document.doc Page 28 of 29
Operating Plan 2004 (Draft)
Version 1 Updated 03/02/04 Knowledge & IT Services Centre (KITSC)
ONESTOP Upgrade Rick Movick Upgrade Clients to version 11.0
Upgrade slip printers
User acceptance October 2004 Planned as part of the 11i implementation
Securing web sites Chris Cooper & Chris Blanksby
Plan Plan developed March 2004 Planned
Establish KPIs Business Analysts Database to collect data develop
Measures and benchmarks established
Accepted by Director KITSC February 2004 Planned