kulda expansion open cast...

40
CMPDI/PFR/MCL/2016-17/OCT-16/42/01 PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0 MTY) (EXPANSION FROM 10.0 MTY TO 15.0 MTY) BASUNDHARA AREA IB VALLEY COALFIELD MAHANADI COALFIELDS LIMITED January 2017 Accreditation Number: NABET/EIA/01/12/002 Dt. Jan 31, 2012. Central Mine Planning & Design Institute Limited (A Subsidiary of Coal India Ltd.) Regional Institute-VII, Samantpuri, P.O: RRL, Bhubaneswar-751013 (Odisha)

Upload: others

Post on 15-Aug-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI/PFR/MCL/2016-17/OCT-16/42/01

PRE-FEASIBILITY REPORT

FOR

KULDA EXPANSION OPEN CAST PROJECT

(CAPACITY 15.0 MTY) (EXPANSION FROM 10.0 MTY TO 15.0 MTY)

BASUNDHARA AREA IB VALLEY COALFIELD

MAHANADI COALFIELDS LIMITED

January 2017

Accreditation Number: NABET/EIA/01/12/002 Dt. Jan 31, 2012.

Central Mine Planning & Design Institute Limited (A Subsidiary of Coal India Ltd.)

Regional Institute-VII, Samantpuri, P.O: RRL, Bhubaneswar-751013 (Odisha)

Page 2: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134

LIST OF CONTENTS S.No. Particulars Page No.

1. Introduction 1 - 2

2. Status of Kulda OCP 2 - 3

3. Need/Justification for the project 3 - 4

4. Location and Communication 4 - 5

5. Topography, Drainage and Climate 5 - 5

6. Geology 5 - 8

7. Mine Boundary 8 - 10

8. Geo-Mining Characteristics 10 - 10

9. Mining Technology 11 - 12

10. Present Status Of Coal & OB 12 - 13

11. Production and dumping schedule 13 - 13

12. Land Requirement 14 - 14

13. Water Demand And Supply Arrangement 14 - 14

14. Pumping And Drainage 15 - 15

15. Coal Wining and OB removal 15 - 15

16. Manpower 15 - 15

17. Power Supply 15 - 15

18. Coal Handling And Dispatch Arrangement 15 - 16

19. Workshop And Store 16 - 16

20. Civil Construction 17 - 17

21. Diversion of Road and Drainage 17 - 17

22. Environmental Management 17 - 19

23. Safety Management And Conservation 20 - 20

24. Rehabilitation and Resettlement 20 - 20

25. Rain Water harvesting 20 - 21

Page 3: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134

LIST OF PLATES Sl.No. Particulars Plate No.

1. Location Plan I A & I B

2. Surface Master Plan II

3. Study area showing 10 Km Buffer zone III

4. Infrastructure plan showing 10 Km Buffer zone IV

5. Drainage Map showing the 10 Km Buffer zone V

6. Geological Plan VI

7. Final Stage Dump Plan VII

LIST OF ANNEXURES Sl.No. Particulars Annexure No.

1. Earlier EC letter of 10.0 Mty I

2. Copy of Mining Plan Approval Letter II

3. Standard TOR for EIA/EMP Report for Project / Activities Required Environmental Clearance III

4. Forest clearance letter IV

Page 4: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 1

PRE-FEASIBILITY REPORT FOR

KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0 MTY)

1. INTRODUCTION

Ib Valley Coalfield located in the districts of Jharsuguda, Sambalpur and

Sundergarh of Odisha is having latitudes 21031’ to 22014’N and longitudes

83032’ to 84010’E. The coalfield is named after the river Ib, a tributary of river

Mahanadi. Coal reserves of this coalfield are about 24.83 billion tonnes (as on

1.4.2015) of which about 15.10 billion tonnes lie within a depth range of 300m.

Quality of coal varies from grade C to G (largely F), suitable for power

generation.

Coal demand from Ib-valley coalfield has increased many fold due to its

strategic location with Howrah-Mumbai railway line passing through the

coalfield. Coal of this coalfield is suitable for thermal power plants.

Many pit head power plants and other coal based plants have come up due to

easy availability of coal and water. The southern, western & central India power

stations have to depend on Ib valley coalfield for their growth. The Howrah-

Mumbai line passes through the coalfield. So coal can move from this coalfield

to western India power houses via rail route. Coal to Tamil Nadu Electricity

Board is also supplied via rail-cum-sea route through Vishakhapatnam and

Haldia ports. Coal can easily move from this coalfield to Eastern India and

Northern India as well. Necessary infrastructure facilities like rail etc. are being

developed/ augmented in the region.

The proximity of Ib-valley coalfield to Hirakud reservoir has generated a lot of

opportunities for setting-up super thermal power stations in the vicinity of the

coalfield.

Gopalpur sector of Ib-valley coalfield forms the north western part of Ib River

coalfield which is a greenfield area with huge mining potential. Detailed

exploration was undertaken by CMPDI to assess the quarriable potentiality of

coal seams with primary view of opening up of new mining projects to the

Page 5: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 2

extent possible. This sector has high potential for opencast mining operations.

Kulda Opencast Project is located in this sector.

Rail link from Jharsuguda to Barpali i.e. adjacent to Kulda OCP, is in very

advance stage of completion & will soon start it’s operation.

2. STATUS OF KULDA OCP

The Advance Action Proposal (AAP) of the project was sanctioned by Govt. in

October 1995 for a capital investment of Rs.8.624 crores.

PROJECT REPORT

Project Report (PR) was approved by MCL Board in March 1995 and

subsequently by CIL Board in May 1995. The PR could not be processed

further due to lack of forestry clearance and EMP clearance. Later project

report was revised with different size of HEMM. This proposal was approved by

MCL Board on 24.11.2001 and by CIL Board on 6.3.2002. Finally the proposal

of Kulda OCP (UCE-August, 2004 cost base) was sanctioned by CCEA in

January,2005 in coal and OB outsourcing variant .

MINING PLAN

Mining Plan for Kulda OCP (10.0 Mty) was approved by MoC, Govt. of India

vide letter no: 34012/(4)/2011-CPAM dated 1st July 2011.

STATUS OF EMP

Env. Clearance for Kulda OCP (10.00 Mty) was received vide letter

No.J/11015/10/95-IA.II(M) dated 24.12.2002 (Annexure-I).Total mine lease area

was 929.60 Ha inclusive of 279.20 Ha of forest land. But environmental

clearance was accorded for 878.29 Ha inclusive of 227.89 Ha of forestland for

which diversion proposal (forestry clearance)has been obtained by the project

for first phase of mining for initial 20 years.

STATUS OF FORESTRY CLEARANCE

Stage-I forestry clearance was received for land required for a period of 20

years from MOEF in two stages for 50.72 Ha on 25.07.2001 and 177.17 Ha on

Page 6: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 3

22.01.2002 respectively. Stage-II clearance was obtained on 08.08.2007 for

227.89 Ha of land for 20 years of mine workings. (Annexure- IV)

Mining Plan/ Mine Closure Plan for Kulda Expansion OC Project

(Revision-I), Expansion from 10.0 to 15.0 Mty, has been prepared within

notified area of MCL for which stage-II forest clearance has been obtained

(634.205 Ha excluding the area under Lalma Forest). Although additional non

forest land is available to be included in the present lease area but presence of

scattered forest land does not permit these areas to be included in phase-I

mining operation. Remaining part of the block including Lalma forest will be

taken up for mining later after getting forestry clearance as phase-II. Mining

Plan/ Mine Closure Plan for Kulda Expansion OC Project (Revision-I),

Expansion from 10.0 to 15.0 Mty, has been approved by Ministry of Coal vide

Letter No. 34012/(04)/2011-CPAM dated 26-12-2016.(Annexure II).

3. NEED / JUSTIFICATION FOR THE PROJECT

To meet the increasing demand of power in the country, more and more super

thermal power stations are being planned in western, northern and eastern

India, majority of which are coal based and may be linked from Ib-valley

coalfield. Power Houses of Punjab State Electricity Board, Haryana State

Electricity Board have also been linked to MCL and will be supplied coal from

this coalfield. The New Power houses of TNEB, KPCL, WBPDCL, CESC and

DVC are also linked to the coalfield.

The consumers of MCL are linked to the company and not to any specific

coalfield. The actual supply from any coalfield of MCL will depend upon the

production and transport logistics. Under the above circumstances coalfield

wise demand has been assessed. Projected coal demand on MCL from Ib-

valley coalfield is as below:

Projected coal demand on MCL from Ib-valley coalfield (Fig. in Mt)

Sl. No

Particulars 2016-17 2021-22 2026-27

1 Total Demand on MCL 207.72 244.83 274.134 2 Projected coal demand on Ib-

valley coalfield 70.62 97.93 120.56

3 Coal Availability 46.39 69.61 70.40 Gap (-)24.23 (-)28.32 (-)50.16

Page 7: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 4

From the above table, it can be seen that all the operative mines in the coalfield

along with the new projects already formulated will not be able to meet the

future demand over the area. Demand during XII Plan period is likely to

increase with fresh linkages to various power houses. Further expansion of

these projects &/or opening of new mines may be required to meet the

projected demand.

In the light of above, expansion of Kulda OCP from 10.0 to 15.0 Mty is justified.

It is proposed that the coal produced from the proposed project will be linked to

various Thermal Power Stations for power generation, both within the state and

outside the state.

4. LOCATION AND COMMUNICATION (PLATE IA & IB)

Kulda geological block is located in the north-western part of Ib valley coalfield.

Some particulars are given below:

Coalfield Ib valley coalfield

Area Tahsil

Basundhara Himgir

District Sundergarh

Latitudes 21o42'00" to 21o44'30" N

Longitudes 83o43'00" to 83o46'30" E

Toposheet No. 64 N/12 & 64 N/16 (RF 1:50000) The area of the block under consideration is 5.84 sq.km., out of which coal

bearing area is 5.30 sq.km.

District headquarter Sundergarh, on State Highway-10 (Sambalpur to

Rourkela), is at a distance of about 40 km. from the blocks. The Sundergarh

(Odisha) – Raigarh (Chattisgarh) all weather road passes through the blocks.

The blocks are also connected by black top road with two important towns of

Odisha namely Rourkela at 145 km and Jharsuguda at 75 km.

The block is connected by road to the state capital Bhubaneswar through State

Highway-10 and National Highway-55, with a total distance of around 450 km.

The block is well connected with MCL HQ at Sambalpur situated at a distance

of about 100 km.

Page 8: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 5

Nearest railhead is Himgir on Mumbai-Howrah Broad Gauge of South Eastern

Railway at a distance of about 36 km from the blocks. Jharsuguda railway

station on Jharsuguda-Sambalpur-Bhubaneswar rail line of East Coast Railway

is at a distance of about 75 km.

The nearest port at Bay of Bengal is Paradip and situated at a distance of

about 500 km. from the block. Biju Pattanaik Airport is at a distance of about

450 km.

5. TOPOGRAPHY, DRAINAGE AND CLIMATE (PLATE-V)

The topography of the block is rugged with steep rise and fall. The central

and south eastern part lie at a comparatively higher elevation being dotted with

hillocks.

The minimum and maximum elevations of the area are 254m and 320m

respectively above the mean sea level.

The ground slopes generally towards west and north and ground water is

collected by Chattajhor nallah being fed by streamlets, which in turn feeds to

river Basundhara.

River Basundhara flows along northwest and northern boundary of the block.

The climate is sub-tropical. Temperature varies from 9.3oC (winter season) to

44.1oC (in pre-monsoon season).

The average annual rainfall is 1413 mm as measured at IMD Jharsuguda for

the last 24 years.

6. GEOLOGY

"Geological Report on Kulda Block, Ib River Coalfield" was prepared by CMPDI

in Feb.'1994. A total of 130 boreholes, have been drilled with a total meterage

of 14858.35m covering an area of 5.84 sq.km. Coal bearing area is 5.30 sq.km.

The borehole density is about 22.3 boreholes/sq.km. The geological succession of Ib Valley and Stratigraphic succession of Kulda

Block is given below.

Page 9: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 6

Geological Succession of Ib Valley

Age Formation Lithology Recent to sub-recent

- Alluvium, laterite, gravels and conglomerate.

Upper Permian Kamthi(Upper) Pebbly sandstone, ferruginous sandstone and red shales

Kamthi (Middle) = Raniganj

Fine grained sandstone, silt stone and coal seams.

Kamthi(Lower) = Barren Measures

Grey shale, carbonaceous shale, sandstone and clay ironstone nodules.

Lower Permian Barakar Grey sandstone, carbonaceous shale, siltstone with thick coal seams and fire clay.

Karharbari Black carbonaceous sandstone with pebble bed and coal seams.

Upper Carboni- ferous

Talchir Diamictite, greenish sand stone, olive and chocolate shales, rhythmites.

-------------------------------- Unconformity ------------------------------- Pre-Cambrian Metamorphics Granite, gneisses, schists etc.

Stratigraphic Succession of Kulda Block

Age Formation Lithology Thickness (m)Recent/ sub-recent

- Soil, Alluvium 0.00-17.00

Lower Permian Barakar Fine to coarse grained sandstone micaceous at places, burnt ferruginous sand-stone/shale, car-bonaceous shale grey shale, fine clay sandy-shale with thick coal seams.

0.77-236.55

Karharbari Carbonaceous medium grained sandstone with undecomposed feldspar, coarse grained to pebbly and gritty sand-stone with impersistent coal seam.

16.04-20.70

Upper Carboni- ferrous

Talchir Fine to medium grained greenish sandstone & greenish shale.

2.30-54.10

------------------------------------- Unconformity ------------------------------------ Precambrian Granite, mica schists &

gneisses 3.12-18.30

Pre-cambrians are exposed in the east of the block.

Page 10: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 7

Structure

Strike of the strata is roughly NW-SE. The dip is generally 7o towards

southwest. Dip is slightly higher in southern part and near faults compared to

rest of the area.

Existence of 3 no faults has been interpreted on the basis of borehole data with

varying throw from 0 to 15m .

Deposit Characteristics

Three coal seams namely Ib seam, Rampur seam and Lajkura seam occur in

this area. These three coal seams altogether occur in 12 split sections, leaving

mergers & sub-splits. Ib seam is the bottom most coal seam.

Ib seam occurs in three sections. Ib bottom seam, which is the lowest coal

section, is not workable in the northern part of the block. Ib middle section

which overlies Ib bottom section is also not workable in the northern part.

These two sections are combined over major part of the block. Ib top section is

not workable over major part of the block and is not considered in quarriable

reserves.

Rampur seam occurs in five sections. Rampur-I seam which overlies Ib middle

section is not workable in the northern, southern & south eastern parts. It is

combined with overlying Rampur-II seam over a long narrow strip in the

western half of the block. The workable section of Rampur-I occurs at a

minimum depth of about 34m in the region of borehole CMHG-118 while

Rampur-II seam occurs in the entire block as workable coal section. Rampur-III

bottom is not workable in the northern half of the block whereas other split

sections overlying Rampur-III bottom are workable in the area of occurrence.

Lajkura horizon occurs in four sections and all coal sections are workable in the

area of occurrence. Out of these four sections Lajkura-II seam is the thickest

with a maximum thickness (including all bands) of 34.07m.

The parting between Ib middle seam and Rampur horizon varies from 3.79 to

13.62m. The parting is thicker where Rampur I is not workable. The parting

between Rampur horizon and Lajkura horizon is thickest with thickness ranging

from 31m to 47m. Except these two partings other intervening partings between

split sections are generally thin.

Page 11: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 8

In all 438.90 Mt coal has been estimated within the block, out of which 26.06 Mt

is locked up within 60m barrier zone and 412.84Mt lies beyond barrier zone.

Succession of coal seams

The grade of coal varies between C to G.

7. MINE BOUNDARY

Kulda geological block contains about 438.90 Mt of net geological reserves

(vertical) with an overall vertical stripping ratio of 0.86 cum/t. The maximum

depth upto floor of Ib bottom seam is about 238m. The entire reserves are

quarriable.

The geological block is bounded by Basundhara river, incrop of Rampur seam

on the north/north eastern side and Chattajhor nallah on the western side.

Chattajhor nallah has a meandering course giving rise to irregular block

boundary. Therefore it is proposed to straighten nallah course at two places

Coal seams Parting (m) Thickness (m) Lajkura-IV 12.42-14.39 2.14-6.71 Lajkura-III 2.02-4.89 0.95-2.21 Lajkura-II 30.05-34.07 1.25-2.79 Lajkura-I 12.09-14.43 31.33-46.18 Rampur-V 1.94-6.40 0.39-5.10 Rampur-IV 12.33-21.58 0.89-7.27 Rampur-III(Top) 2.97-11.92 0.30-6.75 Rampur-III(Bot.) 0.16-3.73 0.17-8.21 Rampur-II 0.91-6.31 0.12-10.75 Rampur-I 0.06-5.03 1.53-11.39 IB (Top) 0.12-1.84 0.33-8.53 IB(Middle) 0.30-4.28 0.13-5.10 IB(Bottom) 0.22-3.28

Page 12: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 9

near boreholes CMHG-227 and CMHG-216. Surface boundary is arrived after

leaving a surface barrier against nallah and the river.

In this revised Mining Plan for Kulda OCP (Expansion from 10.0 to 15.0 Mty)

mining has been proposed to be done in two phases.

PHASE-I

Phase-I mining operation will be taken up initially, here surface boundary has

been restricted within notified lease area for which forest clearance has been

obtained by the project authority. In this phase certain portion of the block

towards south and south-east including area under Lalma Forest are excluded

from the mine boundary as which was present in original mining plan. This

revised mining plan has been detailed for phase-I mining operation, which is a

part of original approved mining plan.

PHASE-II

Phase-II mining operation will be taken up in later years after completion of

phase-I. remaining part of the block will be worked in phase-II after obtaining

forest clearance for the this area. Details of this phase-II will be included in a

separate mining plan at later date.

As explained earlier Ib bottom, Ib middle and Rampur-I seams are not workable

on northern side. Even after, Ib bottom seam attains workable thickness of 1m,

incremental thickness ratio is adverse due to inconsistent development of Ib

middle seam and Rampur-I seam. Hence, it is proposed to adopt Rampur-II

floor as the mine floor upto 185m/190m floor contour of Rampur-II seam and

thereafter deepen the mine floor to floor of Ib bottom seam floor.

Based on the reasons explained in previous paragraphs, mine boundaries

adopted in Phase-I are summarised below:

North : Floor boundary is arrived after leaving surface barrier of

about 60m against river. East : Roof incrop of Rampur-II seam. South : boundary of notified area by project authority for which

stage-II Forest Clearance is available (excluding Lalma RF in the south-west for which forest clearance is available).

Page 13: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 10

West : Floor boundary is marked after leaving a surface barrier of about 60m against Chattajhor nallah and its straightened part and boundary of Lalma RF.

Mine boundaries adopted as per original mining plan will remain same for both

phase of mining operations and these are summarized below.

North : Floor boundary is arrived after leaving surface barrier of about 60m against river. Quarry slope is about 370.

East : Roof incrop of Rampur-II seam. South : Geological boundary is adopted as surface boundary. West : Floor boundary is marked after leaving a surface barrier of

about 60m against Chattajhor nullah and its straightened part.

8. GEO-MINING CHARACTERISTICS :

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Sl.No. Particulars Unit Phase-I

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ 1. Floor area Ha 218.80 2. Surface area Ha 340.00 3. Mineable reserves Mt 132.29 4. Waste volume(OB) Mcum 115.49 5. Stripping ratio m3/t 0.87 6. No. of seams/sections 3/16* 7. Capacity Mty 15.00 8. Life Yrs 10 9. Average gradient R-II as floor 1 in 10.05 Ib-Bottom as floor 1 in 11.33 10. Strike length (along floor) Maximum m 2300 Minimum m 500 11. Strike length (along surface) Maximum m 2430 Minimum m 820 12. Depth Maximum m 200 Minimum m 10 13. Perimeter m 9630 ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ * This includes split and combined sections.

Page 14: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 11

9. MINING TECHNOLOGY

The prevalent mining and geological conditions comprise of the followings:

i) Presence of 3 nos. thick coal horizons namely, (a) Ib (8 m), (b) Rampur (45 m), (c) Lajkura (50 m).

ii) The above coal horizons contain multiple coal sections with intervening

partings. Thickest coal seams/sections are Rampur (IV+V) (25 m) and Lajkura II (31 m).

iii) Gradient of the seams (5o to 8o). iv) Low average stripping ratio of 0.87 cu.m per tonne. Considering the above prevalent mining and geological conditions, shovel

dumper mining system in overburden and Surface Miner with Front End loader

and Rear dumper for coal extraction has been suggested.

The external overburden and the thick parting between Rampur and Lajkura

seam horizons are proposed to be worked by horizontal slices, whereas all the

coal seam sections and the intervening partings in Ib, Rampur and Lajkura

seams are envisaged to be worked by inclined slices considering the moderate

gradient.

At present coal winning is done by surface miner and OB removal is being

done by shovel dumper combination.

Project report of Kulda OCP (10 Mty) was approved for both coal & OB

outsourcing variant. Kulda OCP (15 Mty; 5 Mty incremental) has been

approved for incremental coal & incremental OB both by outsourcing. In

sanctioned outsourcing variant equipment requirement and its phasing will

depend on the outsourcing agency. But the optimum choice of equipment as

per departmental variant has also been assessed; total requirement and its

phasing have been calculated based on the calendar plan of operations,

revised productivity of HEMM and possible physical deployment of equipment

in various horizons.

Requirement of HEMM (in case the mine is operated departmentally) is given

below.

Page 15: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 12

Requirement of HEMM

Total A. OVERBURDEN NO. 1. HYDRAULIC BACKHOE [660-760 HP] 5.9-6.1 cum. 6 2. ELECTRIC ROPE SHOVEL [6.6 kv] 10 Cum. 4 3. REAR DUMPER 100 T 30 4. REAR DUMPER 60 T 50 5. ELEC. R.B.H. DRILL TALL MAST 250 mm 6 6. R.B.H. DRILL 160 mm 6 7. DOZER 410 H.P. 10 8. RIPPER DOZER 850 HP 3

B. COAL

1. SURFACE MINER DRUM 3.8m 5 2. HYDRAULIC BACKHOE [660-760 HP] 5.9-6.1 cum. 1 2. FRONT END LOADER [~500 HP] 5.5-6.0 cum 5 3. REAR DUMPER 60 T 45 4. DOZER 410 H.P. 5

C. COMMON

1 LATTICE BOOM CRAWLER MOUNTED CRANE 75 tonne 1

2 ROUGH TERRAIN CRANE 40 tonne 2 3 HYDRAULIC MOBILE CRANE 10 tonne 2 4 SERVICE CRANE 8 tonne 3 5 HYDRAULIC BACKHOE 1.5-1.6 cum 3 6 FRONT END LOADER 3.0 cum 4 7 TYRE HANDLER FOR 60T TRUCK 3 8 MULTIPURPOSE HANDLING EQUIPMENT 1 9 GRADER 280 HP 4

10 WATER SPRINKLER 28 KL 8 11 MAINTENANCE VAN 3 12 FUEL BOWSER 20 KL 3 13 FIRE TRUCK 2 14 VIBRATORY COMPACTOR 2

10. PRESENT STATUS OF COAL & OB

The mining was started at the end of 2007-08 .The Coal and OB production

from Kulda OCP since 2007-08 is given below.

YEAR COAL (in Mt) OB ( in Mcum) 2007-08 0.15 0.29 2008-09 2.47 1.48 2009-10 3.43 0.90 2010-11 5.02 5.80 2011-12 5.54 5.33

Page 16: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 13

2012-13 5.50 2.71 2013-14 5.27 2.08 2014-15 4.80 5.71 2015-16 8.02 2.79

Total upto 31.03.2016 40.20 27.09

Balance coal reserve as on 1.4.2016 - 132.29 Mt

Balance OB as on 1.4.2016 - 115.49 M.cu.m. 11. PRODUCTION AND DUMPING SCHEDULE The year- wise coal production and OB removal programme is given below.

• Dumping schedule (Fig. in M.cu.m.)

YEAR

EXTERNAL DUMP

INTERNAL DUMP

TOTAL OB REMOVED/TO BE REMOVED

TILL 31.3.2016 22.63 4.46 27.09 Yr-1 (2016-17) 7.63 2.68 10.31 Yr-2 (2017-18) 15.46 15.46 Yr-3 (2018-19) 15.46 15.46 Yr-4 (2019-20) 15.46 15.46 Yr-5 (2020-21) 15.45 15.45 Yr-6 (2021-22) 12.40 12.40 Yr-7 (2022-23) 12.40 12.40 Yr-8 (2023-24) 12.40 12.40 Yr-9 (2024-25) 4.23 4.23 Yr-10 (2025-26) 1.92 1.92 TOTAL 30.26 112.32 142.58

YEAR

COAL (Mt)

OB (M.cu.m.)

Stripping Ratio

Yr-1 (2016-17) 10.00 10.31 1.03 Yr-2 (2017-18) 15.00 15.46 1.03 Yr-3 (2018-19) 15.00 15.46 1.03 Yr-4 (2019-20) 15.00 15.46 1.03 Yr-5 (2020-21) 15.00 15.45 1.03 Yr-6 (2021-22) 15.00 12.40 0.83 Yr-7 (2022-23) 15.00 12.40 0.83 Yr-8 (2023-24) 15.00 12.40 0.83 Yr-9 (2024-25) 15.00 4.23 0.28

Yr-10 (2025-26) 2.29 1.92 0.84

TOTAL 132.29 115.49 0.87

Page 17: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 14

12. LAND REQUIREMENT

The details of land requirement is given below.

(Area in ha) Sl. No.

Particulars Existing (10.0 Mty)

Proposed (15.0 Mty)

1. Forest 227.89 227.89

2. Non-forest 650.40 406.315

Mining lease area 878.29 634.205

Outside mining lease area

3 Residential colony 37.50 37.50

4 Rehabilitation Site 22.90 22.90

Total land 938.69 694.605

Sl. No. Particulars Forest Area

(in ha) Non Forest Area (in ha)

Total Area (in ha)

1 Excavation Area 187.155 134.755 321.91 2 OB dump Area 4.12 156.382 160.502 3 Infrastructure * 21.837 104.32 126.157 4 Embankment 10.408 7.151 17.559

5 Other area incl safety zone & Road/Nallah Diversion

4.370 3.707 8.077

TOTAL 227.89 406.315 634.205

* ( including 12.03 Ha land of Basundhara Washery) 13. WATER DEMAND AND SUPPLY ARRANGEMENT

The water supply arrangement basically includes potable and industrial water

demand of the project.

(Fig. In Kld)

Existing (10.0 Mty)

Incremental (5.0 Mty)

Total for (15.0Mty)

Potable 477 56 533

Industrial (including fire-fighting)

2665 885 3550

Total 3142 941 4083

At present manpower are residing in the residential colony of nearby mines. The potable water requirement is being met partly from Basundhara river and partly from the reservoir of Basundhara East old quarry. The same arrangement will continue for expansion project. Industrial water demand is being and will be met from mine water.

Page 18: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 15

14. PUMPING AND DRAINAGE

The pumping system has been designed to dewater the inflow of water due to

precipitation falling within the active pit limit during the monsoon season to

enable the mining activity to continue round the year.

The existing pumps as proposed in the approved project of 10 Mty are sufficient

for expansion project also.

15. COAL WINNING AND OB REMOVAL

At present coal winning is done by surface miner and OB removal is being

done by shovel dumper combination.

Because of same geomining conditions, shovel dumper mining system is

proposed for partings/top OB and surface miner is proposed for coal and in-

seam bands in proposed expansion project also.

16. MANPOWER

The existing manpower of the project is 816. The additional manpower for

expansion project has been estimated as 91.

17. POWER SUPPLY

Main power supply is from 220KV Main sub-station at Garjanbahal which was

charged in October 2012. Power is transmitted to 2.5 MVA, 33/6.6 KV

substation near existing mine.

Power at 6.6 kV for CHP is proposed to be received from the existing feeders of

2X5 MVA, 33/6.6 kV project substation at Kulda OCP through double circuit

overhead line. One of the two incoming feeders will normally be kept as stand

bye. It is proposed to establish one number of 6.6 kV substation in a suitable

location near CHP to cater to the power requirement for different equipment of

CHP.

18. COAL HANDLING, WASHING & DISPATCH ARRANGEMENT

The proposed Kulda Expansion OC Project is planned to handle the total

production of 15.0 Mty. Presently, the CHP is having 2 nos. feeder breakers of

200 to 300 tph (approx.) capacity and dispatch the crushed as well as blast free

coal through the existing truck loading hoppers to nearby siding.

Page 19: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 16

For proposed system out of 15 Mty, blast free raw coal of 10 Mty will feed to

proposed Basundhara Washery and rest coal is being dispatched to Kanika

siding to a distance of about 30 km with local sale also till the railway siding at

Sardega/Barpalli comes up.

The coal handling arrangement feeding the raw coal to 10 Mty Basundhara

washery and one silo to dispatch washed coal into wagons shall have the

following provisions:

Four numbers of reclaim feeders located at a suitable position near the

mine access trench to receive the blast free raw coal to handle 10 Mty

capacity.

The entire 10 Mty raw coal reclaimed by the reclaim feeders and

transported up to the proposed Basundhara washery (10 Mty) by sets of

belt conveyor C1&C1A, C2&C2A and C3&C3A and feed at a two points

of Washery complex at a height of 10-15 mtr.

The balance 5 Mty of conventional as well as blast free coal collected

and transported up to the existing wharfwall siding at Kanika using

existing Feeder breaker circuits.

In future, if the capacity of washery will be enhanced, modification of raw coal

feeding will be done accordingly to handle 15 Mty raw coal.

Washed Coal Transportation through Silo

The total washed coal from the Basundhara washery (10 Mty) shall be

transported upto Silo by conveyors.

The washed coal from Basundhara washery (10 Mty), shall be loaded into

wagons by Rapid loading system (i.e. SILO located on MGR loop near Barpali

yard) at the capacity of 5500 tph.

19. WORKSHOP AND STORE

As per approved Project Report of existing Kulda OCP, there is provision of a

HEMM workshop. The existing workshop and store shall cater the need for the

expansion project also.

Page 20: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 17

20. CIVIL CONSTRUCTION

Civil works for this expansion project consists of mainly construction of

residential buildings (928 nos.). There is a provision for colony road also.

There is no additional provision for service/welfare buildings. Existing

service/welfare buildings will cater the need for the expansion project.

21. DIVERSION OF ROAD & DRAINAGE

Provision for diversion of Raigarh – Sundergarh State Highway (length-2.8 km) has been made in 10.0 Mty quarry.

Chattajor nallah is crossing the mine lease hold area in the western part. Provision for straightening of Chattajor nallah (length- 617 m) has been made in 10.0 Mty quarry.

22. ENVIRONMENTAL MANAGEMENT

22.1 AIR QUALITY

The average values of Routine Environmental Monitoring data of the existing Kulda

OCP project for SPM, RPM, SO2, NOX and PM2.5 during the period October-December 2016

are given in following table. It has been observed that all the values are well within permissible

limit.

* As per National Ambient Air Quality Standards (NAAQS), 2009

Name of the Air Station (Values in µg/m3) SPM RPM SO2 NOX PM2.5

1 Balinga Market  230.6 139.8 11.40 31.33 40.2

2 Karlikachhar village  319.8 188.6 13.80 19.25 25.4

3 Farakbahal village  224.6 127 17.00 23.40 43.4

4 Near Tumulia  216.0 113.6 14.40 19.40 37.8

5. Kushra village  227.8 129.8 17.40 19.25 38.0

Permissible Limit 600 300 120 120 60*

Page 21: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 18

22.2 MINE EFFLUENT DATA

Mine effluent data of Final Discharge Point of Mine of November, 2016 is

given in following table:

Project   Kulda OCP     

NAME OF  THE STATION Final discharge Point 

of Mine  MoEF‐Sch‐VI Standards Date  24.11.16 

Colour(Hazen)  Acceptable  Acceptable Odour  Unobjectionable  Unobjectionable 

Temperature(oC)  23.5 Shall not exceed 5oC above the receiving 

temperature Nitrate Nitrogen(mg/L)  2  10.0 

Ammonical Nitrogen (as N)(mg/L) 

0.14  50.0 

Total Kjeldahl Nitrogen (as NH3)(mg/L) 

1.88  100.0 

BOD [3 days at 27oC] (mg/L)  7.3  30.0 Arsenic(mg/L)  <0.01  0.2 Lead(mg/L)  <0.05  0.1 

Hexavelent Chromium(mg/L) 

<0.01  0.1 

Total Chromium(mg/L)  <0.1  2.0 

Copper(mg/L)  <0.02  3.0 

Zinc(mg/L)  0.16  5.0 

Selenium(mg/L)  <0.01  0.05 

Cadmium(mg/L)  0.002  2.0 

Nickel(mg/L)  0.17  3.0 Fluoride(mg/L)  1.35  2.0 Sulphide(mg/L)  0.004  2.0 

Phenolic Compound(mg/L)  <0.001  1.0 Manganese(mg/L)  1.67  2.0 

Iron(mg/L)  <0.05  3.0 Disolved Phosphate(mg/L)  <0.01  5.0 

pH  6.91  5.5‐9.0 Oil and Grease (mg/L)  <4.0  10 Total Suspended Solid 

(mg/L) 42  100 

COD (mg/L)  36  250 

All the parameters are well within permissible limit.

Page 22: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 19

22.3 NOISE QUALITY

Noise is considered as a source for annoyance and health hazard. The high

noise level disturbs the ambient environmental quality. The noise level has been

monitored during day time (6:00 AM to 10:00 PM) and night time (10:00 PM to 6:00

AM) on fortnightly basis.

Monitoring Station:  Farakbahal village 

Date of Sampling (Values in dB(A)) Day Day

03-Oct-16 63.9 59.9

19-Oct-16 69.7 50.6

04-Nov-16 59.5 55.6

21-Nov-16 61.9 56.7

09-Dec-16 62.6 61.9

22-Dec-16 60.8 62.2 Standards 75.0 70.0

 

 

Monitoring Station:  Near Balinga Market 

Date of Sampling (Values in dB(A)) Day Day

03-Oct-16 66.8 60.4

19-Oct-16 63.4 59.8

04-Nov-16 56.0 65.7

21-Nov-16 69.5 59.2

09-Dec-16 58.8 89.4

22-Dec-16 68.8 76.0 Standards 75.0 70.0

The noise quality data are within the permissible limits of the Standards

prescribed by the CPCB except near Balinga Market at night time in December.

Page 23: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 20

23. SAFETY MANAGEMENT AND CONSERVATION

Adequate provisions have been made for safe working of the mine in form of

design of operational systems, provision of safety measures for safe use of

explosives, electricity and HEMM etc.

Adequate skilled & trained manpower has also been provided, for compliance

of safety provisions. Regular training/refresher courses, "on job" training shall

be conducted & mock rehearsals shall be made to make the manpower

conversant with various rules, regulations, methods of prevention & combat

with hazards.

All the regulations & schedules of Coal Mines Regulations, 1957 relating to

opencast mining have to be adhered to and implemented in order to maintain

day to day safety precautions as per statute. Special precaution should be

taken while deploying contractor’s worker in the mine. Before employing any

contractor’s labour in the mine proper vocational training should be imparted

and recommendations of the latest Safety Conference should be strictly

followed. Suitable measures should be taken to minimize coal loss during

mining operations.

24. REHABILITATION AND RESETTLEMENT

The following villages will be affected due to mining & its related activities:

Name of village Project affected families

Project affected persons

Balinga 286 1028 Bankibahal 161 566 Kulda 94 293 Siarmal (Partly) 31 85 Total 572 1972

Rehabilitation site Barapali-1 has been identified for villagers of Balinga &

Bankibahal & Chattenpali Rehabilitation site is identifies for villagers of Kulda &

Siarmal.

25. RAIN WATER HARVESTING

Rain water is naturally pure water except where it becomes acidic due to

industrial pollution. The rapid exploitation of ground water as well as surface

water due to the industrial developmental projects, increase in population

Page 24: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Pre-feasibility Report, Page - 21

resulted in acute scarcity of fresh water availability. It has become necessary to

conserve this valuable natural resource for sustainable development.

Conservation of this valuable natural resource can be done by collecting this

rain water scientifically and utilizing it either for drinking purposes or ground

water recharging purposes.

Scientifically & technically designed system which helps us to collect and utilize

the rain water effectively through various steps and collectively termed as “Rain

Water Harvesting”.

The various steps/methods are roof top catchments, check dams, percolation

pond, storage tanks, etc.

Page 25: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – I, Page - 1

Annexure-I

Page 26: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – I, Page - 2

Annexure-I (Contd.)

Page 27: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – I, Page - 3

Annexure-I (Contd.)

Page 28: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – I, Page - 4

Annexure-I (Contd.)

Page 29: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – I, Page - 5

Annexure-I (Contd.)

Page 30: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – II, Page - 1

Annexure-II

Page 31: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure –III, Page - 1

Annexure-III

Page 32: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure –III, Page - 2

Annexure-III(Contd.)

Page 33: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure –III, Page - 3

Annexure-III(Contd.)

Page 34: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure –III, Page - 4

Annexure-III(Contd.)

Page 35: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure –III, Page - 5

Annexure-III(Contd.)

Page 36: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure –III, Page - 6

Annexure-III(Contd.)

Page 37: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure –III, Page - 7

Annexure-III(Contd.)

Page 38: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – IV, Page - 1

Annexure-IV

Page 39: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – IV, Page - 2

Annexure-I (Contd.)

Page 40: KULDA EXPANSION OPEN CAST PROJECTenvironmentclearance.nic.in/writereaddata/Online/TOR/18_Jan_2017... · PRE-FEASIBILITY REPORT FOR KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0

CMPDI

Job No.706134 Annexure – IV, Page - 3

Annexure-I (Contd.)