kulda expansion open cast...
TRANSCRIPT
CMPDI/PFR/MCL/2016-17/OCT-16/42/01
PRE-FEASIBILITY REPORT
FOR
KULDA EXPANSION OPEN CAST PROJECT
(CAPACITY 15.0 MTY) (EXPANSION FROM 10.0 MTY TO 15.0 MTY)
BASUNDHARA AREA IB VALLEY COALFIELD
MAHANADI COALFIELDS LIMITED
January 2017
Accreditation Number: NABET/EIA/01/12/002 Dt. Jan 31, 2012.
Central Mine Planning & Design Institute Limited (A Subsidiary of Coal India Ltd.)
Regional Institute-VII, Samantpuri, P.O: RRL, Bhubaneswar-751013 (Odisha)
CMPDI
Job No.706134
LIST OF CONTENTS S.No. Particulars Page No.
1. Introduction 1 - 2
2. Status of Kulda OCP 2 - 3
3. Need/Justification for the project 3 - 4
4. Location and Communication 4 - 5
5. Topography, Drainage and Climate 5 - 5
6. Geology 5 - 8
7. Mine Boundary 8 - 10
8. Geo-Mining Characteristics 10 - 10
9. Mining Technology 11 - 12
10. Present Status Of Coal & OB 12 - 13
11. Production and dumping schedule 13 - 13
12. Land Requirement 14 - 14
13. Water Demand And Supply Arrangement 14 - 14
14. Pumping And Drainage 15 - 15
15. Coal Wining and OB removal 15 - 15
16. Manpower 15 - 15
17. Power Supply 15 - 15
18. Coal Handling And Dispatch Arrangement 15 - 16
19. Workshop And Store 16 - 16
20. Civil Construction 17 - 17
21. Diversion of Road and Drainage 17 - 17
22. Environmental Management 17 - 19
23. Safety Management And Conservation 20 - 20
24. Rehabilitation and Resettlement 20 - 20
25. Rain Water harvesting 20 - 21
CMPDI
Job No.706134
LIST OF PLATES Sl.No. Particulars Plate No.
1. Location Plan I A & I B
2. Surface Master Plan II
3. Study area showing 10 Km Buffer zone III
4. Infrastructure plan showing 10 Km Buffer zone IV
5. Drainage Map showing the 10 Km Buffer zone V
6. Geological Plan VI
7. Final Stage Dump Plan VII
LIST OF ANNEXURES Sl.No. Particulars Annexure No.
1. Earlier EC letter of 10.0 Mty I
2. Copy of Mining Plan Approval Letter II
3. Standard TOR for EIA/EMP Report for Project / Activities Required Environmental Clearance III
4. Forest clearance letter IV
CMPDI
Job No.706134 Pre-feasibility Report, Page - 1
PRE-FEASIBILITY REPORT FOR
KULDA EXPANSION OPEN CAST PROJECT (CAPACITY 15.0 MTY)
1. INTRODUCTION
Ib Valley Coalfield located in the districts of Jharsuguda, Sambalpur and
Sundergarh of Odisha is having latitudes 21031’ to 22014’N and longitudes
83032’ to 84010’E. The coalfield is named after the river Ib, a tributary of river
Mahanadi. Coal reserves of this coalfield are about 24.83 billion tonnes (as on
1.4.2015) of which about 15.10 billion tonnes lie within a depth range of 300m.
Quality of coal varies from grade C to G (largely F), suitable for power
generation.
Coal demand from Ib-valley coalfield has increased many fold due to its
strategic location with Howrah-Mumbai railway line passing through the
coalfield. Coal of this coalfield is suitable for thermal power plants.
Many pit head power plants and other coal based plants have come up due to
easy availability of coal and water. The southern, western & central India power
stations have to depend on Ib valley coalfield for their growth. The Howrah-
Mumbai line passes through the coalfield. So coal can move from this coalfield
to western India power houses via rail route. Coal to Tamil Nadu Electricity
Board is also supplied via rail-cum-sea route through Vishakhapatnam and
Haldia ports. Coal can easily move from this coalfield to Eastern India and
Northern India as well. Necessary infrastructure facilities like rail etc. are being
developed/ augmented in the region.
The proximity of Ib-valley coalfield to Hirakud reservoir has generated a lot of
opportunities for setting-up super thermal power stations in the vicinity of the
coalfield.
Gopalpur sector of Ib-valley coalfield forms the north western part of Ib River
coalfield which is a greenfield area with huge mining potential. Detailed
exploration was undertaken by CMPDI to assess the quarriable potentiality of
coal seams with primary view of opening up of new mining projects to the
CMPDI
Job No.706134 Pre-feasibility Report, Page - 2
extent possible. This sector has high potential for opencast mining operations.
Kulda Opencast Project is located in this sector.
Rail link from Jharsuguda to Barpali i.e. adjacent to Kulda OCP, is in very
advance stage of completion & will soon start it’s operation.
2. STATUS OF KULDA OCP
The Advance Action Proposal (AAP) of the project was sanctioned by Govt. in
October 1995 for a capital investment of Rs.8.624 crores.
PROJECT REPORT
Project Report (PR) was approved by MCL Board in March 1995 and
subsequently by CIL Board in May 1995. The PR could not be processed
further due to lack of forestry clearance and EMP clearance. Later project
report was revised with different size of HEMM. This proposal was approved by
MCL Board on 24.11.2001 and by CIL Board on 6.3.2002. Finally the proposal
of Kulda OCP (UCE-August, 2004 cost base) was sanctioned by CCEA in
January,2005 in coal and OB outsourcing variant .
MINING PLAN
Mining Plan for Kulda OCP (10.0 Mty) was approved by MoC, Govt. of India
vide letter no: 34012/(4)/2011-CPAM dated 1st July 2011.
STATUS OF EMP
Env. Clearance for Kulda OCP (10.00 Mty) was received vide letter
No.J/11015/10/95-IA.II(M) dated 24.12.2002 (Annexure-I).Total mine lease area
was 929.60 Ha inclusive of 279.20 Ha of forest land. But environmental
clearance was accorded for 878.29 Ha inclusive of 227.89 Ha of forestland for
which diversion proposal (forestry clearance)has been obtained by the project
for first phase of mining for initial 20 years.
STATUS OF FORESTRY CLEARANCE
Stage-I forestry clearance was received for land required for a period of 20
years from MOEF in two stages for 50.72 Ha on 25.07.2001 and 177.17 Ha on
CMPDI
Job No.706134 Pre-feasibility Report, Page - 3
22.01.2002 respectively. Stage-II clearance was obtained on 08.08.2007 for
227.89 Ha of land for 20 years of mine workings. (Annexure- IV)
Mining Plan/ Mine Closure Plan for Kulda Expansion OC Project
(Revision-I), Expansion from 10.0 to 15.0 Mty, has been prepared within
notified area of MCL for which stage-II forest clearance has been obtained
(634.205 Ha excluding the area under Lalma Forest). Although additional non
forest land is available to be included in the present lease area but presence of
scattered forest land does not permit these areas to be included in phase-I
mining operation. Remaining part of the block including Lalma forest will be
taken up for mining later after getting forestry clearance as phase-II. Mining
Plan/ Mine Closure Plan for Kulda Expansion OC Project (Revision-I),
Expansion from 10.0 to 15.0 Mty, has been approved by Ministry of Coal vide
Letter No. 34012/(04)/2011-CPAM dated 26-12-2016.(Annexure II).
3. NEED / JUSTIFICATION FOR THE PROJECT
To meet the increasing demand of power in the country, more and more super
thermal power stations are being planned in western, northern and eastern
India, majority of which are coal based and may be linked from Ib-valley
coalfield. Power Houses of Punjab State Electricity Board, Haryana State
Electricity Board have also been linked to MCL and will be supplied coal from
this coalfield. The New Power houses of TNEB, KPCL, WBPDCL, CESC and
DVC are also linked to the coalfield.
The consumers of MCL are linked to the company and not to any specific
coalfield. The actual supply from any coalfield of MCL will depend upon the
production and transport logistics. Under the above circumstances coalfield
wise demand has been assessed. Projected coal demand on MCL from Ib-
valley coalfield is as below:
Projected coal demand on MCL from Ib-valley coalfield (Fig. in Mt)
Sl. No
Particulars 2016-17 2021-22 2026-27
1 Total Demand on MCL 207.72 244.83 274.134 2 Projected coal demand on Ib-
valley coalfield 70.62 97.93 120.56
3 Coal Availability 46.39 69.61 70.40 Gap (-)24.23 (-)28.32 (-)50.16
CMPDI
Job No.706134 Pre-feasibility Report, Page - 4
From the above table, it can be seen that all the operative mines in the coalfield
along with the new projects already formulated will not be able to meet the
future demand over the area. Demand during XII Plan period is likely to
increase with fresh linkages to various power houses. Further expansion of
these projects &/or opening of new mines may be required to meet the
projected demand.
In the light of above, expansion of Kulda OCP from 10.0 to 15.0 Mty is justified.
It is proposed that the coal produced from the proposed project will be linked to
various Thermal Power Stations for power generation, both within the state and
outside the state.
4. LOCATION AND COMMUNICATION (PLATE IA & IB)
Kulda geological block is located in the north-western part of Ib valley coalfield.
Some particulars are given below:
Coalfield Ib valley coalfield
Area Tahsil
Basundhara Himgir
District Sundergarh
Latitudes 21o42'00" to 21o44'30" N
Longitudes 83o43'00" to 83o46'30" E
Toposheet No. 64 N/12 & 64 N/16 (RF 1:50000) The area of the block under consideration is 5.84 sq.km., out of which coal
bearing area is 5.30 sq.km.
District headquarter Sundergarh, on State Highway-10 (Sambalpur to
Rourkela), is at a distance of about 40 km. from the blocks. The Sundergarh
(Odisha) – Raigarh (Chattisgarh) all weather road passes through the blocks.
The blocks are also connected by black top road with two important towns of
Odisha namely Rourkela at 145 km and Jharsuguda at 75 km.
The block is connected by road to the state capital Bhubaneswar through State
Highway-10 and National Highway-55, with a total distance of around 450 km.
The block is well connected with MCL HQ at Sambalpur situated at a distance
of about 100 km.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 5
Nearest railhead is Himgir on Mumbai-Howrah Broad Gauge of South Eastern
Railway at a distance of about 36 km from the blocks. Jharsuguda railway
station on Jharsuguda-Sambalpur-Bhubaneswar rail line of East Coast Railway
is at a distance of about 75 km.
The nearest port at Bay of Bengal is Paradip and situated at a distance of
about 500 km. from the block. Biju Pattanaik Airport is at a distance of about
450 km.
5. TOPOGRAPHY, DRAINAGE AND CLIMATE (PLATE-V)
The topography of the block is rugged with steep rise and fall. The central
and south eastern part lie at a comparatively higher elevation being dotted with
hillocks.
The minimum and maximum elevations of the area are 254m and 320m
respectively above the mean sea level.
The ground slopes generally towards west and north and ground water is
collected by Chattajhor nallah being fed by streamlets, which in turn feeds to
river Basundhara.
River Basundhara flows along northwest and northern boundary of the block.
The climate is sub-tropical. Temperature varies from 9.3oC (winter season) to
44.1oC (in pre-monsoon season).
The average annual rainfall is 1413 mm as measured at IMD Jharsuguda for
the last 24 years.
6. GEOLOGY
"Geological Report on Kulda Block, Ib River Coalfield" was prepared by CMPDI
in Feb.'1994. A total of 130 boreholes, have been drilled with a total meterage
of 14858.35m covering an area of 5.84 sq.km. Coal bearing area is 5.30 sq.km.
The borehole density is about 22.3 boreholes/sq.km. The geological succession of Ib Valley and Stratigraphic succession of Kulda
Block is given below.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 6
Geological Succession of Ib Valley
Age Formation Lithology Recent to sub-recent
- Alluvium, laterite, gravels and conglomerate.
Upper Permian Kamthi(Upper) Pebbly sandstone, ferruginous sandstone and red shales
Kamthi (Middle) = Raniganj
Fine grained sandstone, silt stone and coal seams.
Kamthi(Lower) = Barren Measures
Grey shale, carbonaceous shale, sandstone and clay ironstone nodules.
Lower Permian Barakar Grey sandstone, carbonaceous shale, siltstone with thick coal seams and fire clay.
Karharbari Black carbonaceous sandstone with pebble bed and coal seams.
Upper Carboni- ferous
Talchir Diamictite, greenish sand stone, olive and chocolate shales, rhythmites.
-------------------------------- Unconformity ------------------------------- Pre-Cambrian Metamorphics Granite, gneisses, schists etc.
Stratigraphic Succession of Kulda Block
Age Formation Lithology Thickness (m)Recent/ sub-recent
- Soil, Alluvium 0.00-17.00
Lower Permian Barakar Fine to coarse grained sandstone micaceous at places, burnt ferruginous sand-stone/shale, car-bonaceous shale grey shale, fine clay sandy-shale with thick coal seams.
0.77-236.55
Karharbari Carbonaceous medium grained sandstone with undecomposed feldspar, coarse grained to pebbly and gritty sand-stone with impersistent coal seam.
16.04-20.70
Upper Carboni- ferrous
Talchir Fine to medium grained greenish sandstone & greenish shale.
2.30-54.10
------------------------------------- Unconformity ------------------------------------ Precambrian Granite, mica schists &
gneisses 3.12-18.30
Pre-cambrians are exposed in the east of the block.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 7
Structure
Strike of the strata is roughly NW-SE. The dip is generally 7o towards
southwest. Dip is slightly higher in southern part and near faults compared to
rest of the area.
Existence of 3 no faults has been interpreted on the basis of borehole data with
varying throw from 0 to 15m .
Deposit Characteristics
Three coal seams namely Ib seam, Rampur seam and Lajkura seam occur in
this area. These three coal seams altogether occur in 12 split sections, leaving
mergers & sub-splits. Ib seam is the bottom most coal seam.
Ib seam occurs in three sections. Ib bottom seam, which is the lowest coal
section, is not workable in the northern part of the block. Ib middle section
which overlies Ib bottom section is also not workable in the northern part.
These two sections are combined over major part of the block. Ib top section is
not workable over major part of the block and is not considered in quarriable
reserves.
Rampur seam occurs in five sections. Rampur-I seam which overlies Ib middle
section is not workable in the northern, southern & south eastern parts. It is
combined with overlying Rampur-II seam over a long narrow strip in the
western half of the block. The workable section of Rampur-I occurs at a
minimum depth of about 34m in the region of borehole CMHG-118 while
Rampur-II seam occurs in the entire block as workable coal section. Rampur-III
bottom is not workable in the northern half of the block whereas other split
sections overlying Rampur-III bottom are workable in the area of occurrence.
Lajkura horizon occurs in four sections and all coal sections are workable in the
area of occurrence. Out of these four sections Lajkura-II seam is the thickest
with a maximum thickness (including all bands) of 34.07m.
The parting between Ib middle seam and Rampur horizon varies from 3.79 to
13.62m. The parting is thicker where Rampur I is not workable. The parting
between Rampur horizon and Lajkura horizon is thickest with thickness ranging
from 31m to 47m. Except these two partings other intervening partings between
split sections are generally thin.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 8
In all 438.90 Mt coal has been estimated within the block, out of which 26.06 Mt
is locked up within 60m barrier zone and 412.84Mt lies beyond barrier zone.
Succession of coal seams
The grade of coal varies between C to G.
7. MINE BOUNDARY
Kulda geological block contains about 438.90 Mt of net geological reserves
(vertical) with an overall vertical stripping ratio of 0.86 cum/t. The maximum
depth upto floor of Ib bottom seam is about 238m. The entire reserves are
quarriable.
The geological block is bounded by Basundhara river, incrop of Rampur seam
on the north/north eastern side and Chattajhor nallah on the western side.
Chattajhor nallah has a meandering course giving rise to irregular block
boundary. Therefore it is proposed to straighten nallah course at two places
Coal seams Parting (m) Thickness (m) Lajkura-IV 12.42-14.39 2.14-6.71 Lajkura-III 2.02-4.89 0.95-2.21 Lajkura-II 30.05-34.07 1.25-2.79 Lajkura-I 12.09-14.43 31.33-46.18 Rampur-V 1.94-6.40 0.39-5.10 Rampur-IV 12.33-21.58 0.89-7.27 Rampur-III(Top) 2.97-11.92 0.30-6.75 Rampur-III(Bot.) 0.16-3.73 0.17-8.21 Rampur-II 0.91-6.31 0.12-10.75 Rampur-I 0.06-5.03 1.53-11.39 IB (Top) 0.12-1.84 0.33-8.53 IB(Middle) 0.30-4.28 0.13-5.10 IB(Bottom) 0.22-3.28
CMPDI
Job No.706134 Pre-feasibility Report, Page - 9
near boreholes CMHG-227 and CMHG-216. Surface boundary is arrived after
leaving a surface barrier against nallah and the river.
In this revised Mining Plan for Kulda OCP (Expansion from 10.0 to 15.0 Mty)
mining has been proposed to be done in two phases.
PHASE-I
Phase-I mining operation will be taken up initially, here surface boundary has
been restricted within notified lease area for which forest clearance has been
obtained by the project authority. In this phase certain portion of the block
towards south and south-east including area under Lalma Forest are excluded
from the mine boundary as which was present in original mining plan. This
revised mining plan has been detailed for phase-I mining operation, which is a
part of original approved mining plan.
PHASE-II
Phase-II mining operation will be taken up in later years after completion of
phase-I. remaining part of the block will be worked in phase-II after obtaining
forest clearance for the this area. Details of this phase-II will be included in a
separate mining plan at later date.
As explained earlier Ib bottom, Ib middle and Rampur-I seams are not workable
on northern side. Even after, Ib bottom seam attains workable thickness of 1m,
incremental thickness ratio is adverse due to inconsistent development of Ib
middle seam and Rampur-I seam. Hence, it is proposed to adopt Rampur-II
floor as the mine floor upto 185m/190m floor contour of Rampur-II seam and
thereafter deepen the mine floor to floor of Ib bottom seam floor.
Based on the reasons explained in previous paragraphs, mine boundaries
adopted in Phase-I are summarised below:
North : Floor boundary is arrived after leaving surface barrier of
about 60m against river. East : Roof incrop of Rampur-II seam. South : boundary of notified area by project authority for which
stage-II Forest Clearance is available (excluding Lalma RF in the south-west for which forest clearance is available).
CMPDI
Job No.706134 Pre-feasibility Report, Page - 10
West : Floor boundary is marked after leaving a surface barrier of about 60m against Chattajhor nallah and its straightened part and boundary of Lalma RF.
Mine boundaries adopted as per original mining plan will remain same for both
phase of mining operations and these are summarized below.
North : Floor boundary is arrived after leaving surface barrier of about 60m against river. Quarry slope is about 370.
East : Roof incrop of Rampur-II seam. South : Geological boundary is adopted as surface boundary. West : Floor boundary is marked after leaving a surface barrier of
about 60m against Chattajhor nullah and its straightened part.
8. GEO-MINING CHARACTERISTICS :
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Sl.No. Particulars Unit Phase-I
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ 1. Floor area Ha 218.80 2. Surface area Ha 340.00 3. Mineable reserves Mt 132.29 4. Waste volume(OB) Mcum 115.49 5. Stripping ratio m3/t 0.87 6. No. of seams/sections 3/16* 7. Capacity Mty 15.00 8. Life Yrs 10 9. Average gradient R-II as floor 1 in 10.05 Ib-Bottom as floor 1 in 11.33 10. Strike length (along floor) Maximum m 2300 Minimum m 500 11. Strike length (along surface) Maximum m 2430 Minimum m 820 12. Depth Maximum m 200 Minimum m 10 13. Perimeter m 9630 ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ * This includes split and combined sections.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 11
9. MINING TECHNOLOGY
The prevalent mining and geological conditions comprise of the followings:
i) Presence of 3 nos. thick coal horizons namely, (a) Ib (8 m), (b) Rampur (45 m), (c) Lajkura (50 m).
ii) The above coal horizons contain multiple coal sections with intervening
partings. Thickest coal seams/sections are Rampur (IV+V) (25 m) and Lajkura II (31 m).
iii) Gradient of the seams (5o to 8o). iv) Low average stripping ratio of 0.87 cu.m per tonne. Considering the above prevalent mining and geological conditions, shovel
dumper mining system in overburden and Surface Miner with Front End loader
and Rear dumper for coal extraction has been suggested.
The external overburden and the thick parting between Rampur and Lajkura
seam horizons are proposed to be worked by horizontal slices, whereas all the
coal seam sections and the intervening partings in Ib, Rampur and Lajkura
seams are envisaged to be worked by inclined slices considering the moderate
gradient.
At present coal winning is done by surface miner and OB removal is being
done by shovel dumper combination.
Project report of Kulda OCP (10 Mty) was approved for both coal & OB
outsourcing variant. Kulda OCP (15 Mty; 5 Mty incremental) has been
approved for incremental coal & incremental OB both by outsourcing. In
sanctioned outsourcing variant equipment requirement and its phasing will
depend on the outsourcing agency. But the optimum choice of equipment as
per departmental variant has also been assessed; total requirement and its
phasing have been calculated based on the calendar plan of operations,
revised productivity of HEMM and possible physical deployment of equipment
in various horizons.
Requirement of HEMM (in case the mine is operated departmentally) is given
below.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 12
Requirement of HEMM
Total A. OVERBURDEN NO. 1. HYDRAULIC BACKHOE [660-760 HP] 5.9-6.1 cum. 6 2. ELECTRIC ROPE SHOVEL [6.6 kv] 10 Cum. 4 3. REAR DUMPER 100 T 30 4. REAR DUMPER 60 T 50 5. ELEC. R.B.H. DRILL TALL MAST 250 mm 6 6. R.B.H. DRILL 160 mm 6 7. DOZER 410 H.P. 10 8. RIPPER DOZER 850 HP 3
B. COAL
1. SURFACE MINER DRUM 3.8m 5 2. HYDRAULIC BACKHOE [660-760 HP] 5.9-6.1 cum. 1 2. FRONT END LOADER [~500 HP] 5.5-6.0 cum 5 3. REAR DUMPER 60 T 45 4. DOZER 410 H.P. 5
C. COMMON
1 LATTICE BOOM CRAWLER MOUNTED CRANE 75 tonne 1
2 ROUGH TERRAIN CRANE 40 tonne 2 3 HYDRAULIC MOBILE CRANE 10 tonne 2 4 SERVICE CRANE 8 tonne 3 5 HYDRAULIC BACKHOE 1.5-1.6 cum 3 6 FRONT END LOADER 3.0 cum 4 7 TYRE HANDLER FOR 60T TRUCK 3 8 MULTIPURPOSE HANDLING EQUIPMENT 1 9 GRADER 280 HP 4
10 WATER SPRINKLER 28 KL 8 11 MAINTENANCE VAN 3 12 FUEL BOWSER 20 KL 3 13 FIRE TRUCK 2 14 VIBRATORY COMPACTOR 2
10. PRESENT STATUS OF COAL & OB
The mining was started at the end of 2007-08 .The Coal and OB production
from Kulda OCP since 2007-08 is given below.
YEAR COAL (in Mt) OB ( in Mcum) 2007-08 0.15 0.29 2008-09 2.47 1.48 2009-10 3.43 0.90 2010-11 5.02 5.80 2011-12 5.54 5.33
CMPDI
Job No.706134 Pre-feasibility Report, Page - 13
2012-13 5.50 2.71 2013-14 5.27 2.08 2014-15 4.80 5.71 2015-16 8.02 2.79
Total upto 31.03.2016 40.20 27.09
Balance coal reserve as on 1.4.2016 - 132.29 Mt
Balance OB as on 1.4.2016 - 115.49 M.cu.m. 11. PRODUCTION AND DUMPING SCHEDULE The year- wise coal production and OB removal programme is given below.
• Dumping schedule (Fig. in M.cu.m.)
YEAR
EXTERNAL DUMP
INTERNAL DUMP
TOTAL OB REMOVED/TO BE REMOVED
TILL 31.3.2016 22.63 4.46 27.09 Yr-1 (2016-17) 7.63 2.68 10.31 Yr-2 (2017-18) 15.46 15.46 Yr-3 (2018-19) 15.46 15.46 Yr-4 (2019-20) 15.46 15.46 Yr-5 (2020-21) 15.45 15.45 Yr-6 (2021-22) 12.40 12.40 Yr-7 (2022-23) 12.40 12.40 Yr-8 (2023-24) 12.40 12.40 Yr-9 (2024-25) 4.23 4.23 Yr-10 (2025-26) 1.92 1.92 TOTAL 30.26 112.32 142.58
YEAR
COAL (Mt)
OB (M.cu.m.)
Stripping Ratio
Yr-1 (2016-17) 10.00 10.31 1.03 Yr-2 (2017-18) 15.00 15.46 1.03 Yr-3 (2018-19) 15.00 15.46 1.03 Yr-4 (2019-20) 15.00 15.46 1.03 Yr-5 (2020-21) 15.00 15.45 1.03 Yr-6 (2021-22) 15.00 12.40 0.83 Yr-7 (2022-23) 15.00 12.40 0.83 Yr-8 (2023-24) 15.00 12.40 0.83 Yr-9 (2024-25) 15.00 4.23 0.28
Yr-10 (2025-26) 2.29 1.92 0.84
TOTAL 132.29 115.49 0.87
CMPDI
Job No.706134 Pre-feasibility Report, Page - 14
12. LAND REQUIREMENT
The details of land requirement is given below.
(Area in ha) Sl. No.
Particulars Existing (10.0 Mty)
Proposed (15.0 Mty)
1. Forest 227.89 227.89
2. Non-forest 650.40 406.315
Mining lease area 878.29 634.205
Outside mining lease area
3 Residential colony 37.50 37.50
4 Rehabilitation Site 22.90 22.90
Total land 938.69 694.605
Sl. No. Particulars Forest Area
(in ha) Non Forest Area (in ha)
Total Area (in ha)
1 Excavation Area 187.155 134.755 321.91 2 OB dump Area 4.12 156.382 160.502 3 Infrastructure * 21.837 104.32 126.157 4 Embankment 10.408 7.151 17.559
5 Other area incl safety zone & Road/Nallah Diversion
4.370 3.707 8.077
TOTAL 227.89 406.315 634.205
* ( including 12.03 Ha land of Basundhara Washery) 13. WATER DEMAND AND SUPPLY ARRANGEMENT
The water supply arrangement basically includes potable and industrial water
demand of the project.
(Fig. In Kld)
Existing (10.0 Mty)
Incremental (5.0 Mty)
Total for (15.0Mty)
Potable 477 56 533
Industrial (including fire-fighting)
2665 885 3550
Total 3142 941 4083
At present manpower are residing in the residential colony of nearby mines. The potable water requirement is being met partly from Basundhara river and partly from the reservoir of Basundhara East old quarry. The same arrangement will continue for expansion project. Industrial water demand is being and will be met from mine water.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 15
14. PUMPING AND DRAINAGE
The pumping system has been designed to dewater the inflow of water due to
precipitation falling within the active pit limit during the monsoon season to
enable the mining activity to continue round the year.
The existing pumps as proposed in the approved project of 10 Mty are sufficient
for expansion project also.
15. COAL WINNING AND OB REMOVAL
At present coal winning is done by surface miner and OB removal is being
done by shovel dumper combination.
Because of same geomining conditions, shovel dumper mining system is
proposed for partings/top OB and surface miner is proposed for coal and in-
seam bands in proposed expansion project also.
16. MANPOWER
The existing manpower of the project is 816. The additional manpower for
expansion project has been estimated as 91.
17. POWER SUPPLY
Main power supply is from 220KV Main sub-station at Garjanbahal which was
charged in October 2012. Power is transmitted to 2.5 MVA, 33/6.6 KV
substation near existing mine.
Power at 6.6 kV for CHP is proposed to be received from the existing feeders of
2X5 MVA, 33/6.6 kV project substation at Kulda OCP through double circuit
overhead line. One of the two incoming feeders will normally be kept as stand
bye. It is proposed to establish one number of 6.6 kV substation in a suitable
location near CHP to cater to the power requirement for different equipment of
CHP.
18. COAL HANDLING, WASHING & DISPATCH ARRANGEMENT
The proposed Kulda Expansion OC Project is planned to handle the total
production of 15.0 Mty. Presently, the CHP is having 2 nos. feeder breakers of
200 to 300 tph (approx.) capacity and dispatch the crushed as well as blast free
coal through the existing truck loading hoppers to nearby siding.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 16
For proposed system out of 15 Mty, blast free raw coal of 10 Mty will feed to
proposed Basundhara Washery and rest coal is being dispatched to Kanika
siding to a distance of about 30 km with local sale also till the railway siding at
Sardega/Barpalli comes up.
The coal handling arrangement feeding the raw coal to 10 Mty Basundhara
washery and one silo to dispatch washed coal into wagons shall have the
following provisions:
Four numbers of reclaim feeders located at a suitable position near the
mine access trench to receive the blast free raw coal to handle 10 Mty
capacity.
The entire 10 Mty raw coal reclaimed by the reclaim feeders and
transported up to the proposed Basundhara washery (10 Mty) by sets of
belt conveyor C1&C1A, C2&C2A and C3&C3A and feed at a two points
of Washery complex at a height of 10-15 mtr.
The balance 5 Mty of conventional as well as blast free coal collected
and transported up to the existing wharfwall siding at Kanika using
existing Feeder breaker circuits.
In future, if the capacity of washery will be enhanced, modification of raw coal
feeding will be done accordingly to handle 15 Mty raw coal.
Washed Coal Transportation through Silo
The total washed coal from the Basundhara washery (10 Mty) shall be
transported upto Silo by conveyors.
The washed coal from Basundhara washery (10 Mty), shall be loaded into
wagons by Rapid loading system (i.e. SILO located on MGR loop near Barpali
yard) at the capacity of 5500 tph.
19. WORKSHOP AND STORE
As per approved Project Report of existing Kulda OCP, there is provision of a
HEMM workshop. The existing workshop and store shall cater the need for the
expansion project also.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 17
20. CIVIL CONSTRUCTION
Civil works for this expansion project consists of mainly construction of
residential buildings (928 nos.). There is a provision for colony road also.
There is no additional provision for service/welfare buildings. Existing
service/welfare buildings will cater the need for the expansion project.
21. DIVERSION OF ROAD & DRAINAGE
Provision for diversion of Raigarh – Sundergarh State Highway (length-2.8 km) has been made in 10.0 Mty quarry.
Chattajor nallah is crossing the mine lease hold area in the western part. Provision for straightening of Chattajor nallah (length- 617 m) has been made in 10.0 Mty quarry.
22. ENVIRONMENTAL MANAGEMENT
22.1 AIR QUALITY
The average values of Routine Environmental Monitoring data of the existing Kulda
OCP project for SPM, RPM, SO2, NOX and PM2.5 during the period October-December 2016
are given in following table. It has been observed that all the values are well within permissible
limit.
* As per National Ambient Air Quality Standards (NAAQS), 2009
Name of the Air Station (Values in µg/m3) SPM RPM SO2 NOX PM2.5
1 Balinga Market 230.6 139.8 11.40 31.33 40.2
2 Karlikachhar village 319.8 188.6 13.80 19.25 25.4
3 Farakbahal village 224.6 127 17.00 23.40 43.4
4 Near Tumulia 216.0 113.6 14.40 19.40 37.8
5. Kushra village 227.8 129.8 17.40 19.25 38.0
Permissible Limit 600 300 120 120 60*
CMPDI
Job No.706134 Pre-feasibility Report, Page - 18
22.2 MINE EFFLUENT DATA
Mine effluent data of Final Discharge Point of Mine of November, 2016 is
given in following table:
Project Kulda OCP
NAME OF THE STATION Final discharge Point
of Mine MoEF‐Sch‐VI Standards Date 24.11.16
Colour(Hazen) Acceptable Acceptable Odour Unobjectionable Unobjectionable
Temperature(oC) 23.5 Shall not exceed 5oC above the receiving
temperature Nitrate Nitrogen(mg/L) 2 10.0
Ammonical Nitrogen (as N)(mg/L)
0.14 50.0
Total Kjeldahl Nitrogen (as NH3)(mg/L)
1.88 100.0
BOD [3 days at 27oC] (mg/L) 7.3 30.0 Arsenic(mg/L) <0.01 0.2 Lead(mg/L) <0.05 0.1
Hexavelent Chromium(mg/L)
<0.01 0.1
Total Chromium(mg/L) <0.1 2.0
Copper(mg/L) <0.02 3.0
Zinc(mg/L) 0.16 5.0
Selenium(mg/L) <0.01 0.05
Cadmium(mg/L) 0.002 2.0
Nickel(mg/L) 0.17 3.0 Fluoride(mg/L) 1.35 2.0 Sulphide(mg/L) 0.004 2.0
Phenolic Compound(mg/L) <0.001 1.0 Manganese(mg/L) 1.67 2.0
Iron(mg/L) <0.05 3.0 Disolved Phosphate(mg/L) <0.01 5.0
pH 6.91 5.5‐9.0 Oil and Grease (mg/L) <4.0 10 Total Suspended Solid
(mg/L) 42 100
COD (mg/L) 36 250
All the parameters are well within permissible limit.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 19
22.3 NOISE QUALITY
Noise is considered as a source for annoyance and health hazard. The high
noise level disturbs the ambient environmental quality. The noise level has been
monitored during day time (6:00 AM to 10:00 PM) and night time (10:00 PM to 6:00
AM) on fortnightly basis.
Monitoring Station: Farakbahal village
Date of Sampling (Values in dB(A)) Day Day
03-Oct-16 63.9 59.9
19-Oct-16 69.7 50.6
04-Nov-16 59.5 55.6
21-Nov-16 61.9 56.7
09-Dec-16 62.6 61.9
22-Dec-16 60.8 62.2 Standards 75.0 70.0
Monitoring Station: Near Balinga Market
Date of Sampling (Values in dB(A)) Day Day
03-Oct-16 66.8 60.4
19-Oct-16 63.4 59.8
04-Nov-16 56.0 65.7
21-Nov-16 69.5 59.2
09-Dec-16 58.8 89.4
22-Dec-16 68.8 76.0 Standards 75.0 70.0
The noise quality data are within the permissible limits of the Standards
prescribed by the CPCB except near Balinga Market at night time in December.
CMPDI
Job No.706134 Pre-feasibility Report, Page - 20
23. SAFETY MANAGEMENT AND CONSERVATION
Adequate provisions have been made for safe working of the mine in form of
design of operational systems, provision of safety measures for safe use of
explosives, electricity and HEMM etc.
Adequate skilled & trained manpower has also been provided, for compliance
of safety provisions. Regular training/refresher courses, "on job" training shall
be conducted & mock rehearsals shall be made to make the manpower
conversant with various rules, regulations, methods of prevention & combat
with hazards.
All the regulations & schedules of Coal Mines Regulations, 1957 relating to
opencast mining have to be adhered to and implemented in order to maintain
day to day safety precautions as per statute. Special precaution should be
taken while deploying contractor’s worker in the mine. Before employing any
contractor’s labour in the mine proper vocational training should be imparted
and recommendations of the latest Safety Conference should be strictly
followed. Suitable measures should be taken to minimize coal loss during
mining operations.
24. REHABILITATION AND RESETTLEMENT
The following villages will be affected due to mining & its related activities:
Name of village Project affected families
Project affected persons
Balinga 286 1028 Bankibahal 161 566 Kulda 94 293 Siarmal (Partly) 31 85 Total 572 1972
Rehabilitation site Barapali-1 has been identified for villagers of Balinga &
Bankibahal & Chattenpali Rehabilitation site is identifies for villagers of Kulda &
Siarmal.
25. RAIN WATER HARVESTING
Rain water is naturally pure water except where it becomes acidic due to
industrial pollution. The rapid exploitation of ground water as well as surface
water due to the industrial developmental projects, increase in population
CMPDI
Job No.706134 Pre-feasibility Report, Page - 21
resulted in acute scarcity of fresh water availability. It has become necessary to
conserve this valuable natural resource for sustainable development.
Conservation of this valuable natural resource can be done by collecting this
rain water scientifically and utilizing it either for drinking purposes or ground
water recharging purposes.
Scientifically & technically designed system which helps us to collect and utilize
the rain water effectively through various steps and collectively termed as “Rain
Water Harvesting”.
The various steps/methods are roof top catchments, check dams, percolation
pond, storage tanks, etc.
CMPDI
Job No.706134 Annexure – I, Page - 1
Annexure-I
CMPDI
Job No.706134 Annexure – I, Page - 2
Annexure-I (Contd.)
CMPDI
Job No.706134 Annexure – I, Page - 3
Annexure-I (Contd.)
CMPDI
Job No.706134 Annexure – I, Page - 4
Annexure-I (Contd.)
CMPDI
Job No.706134 Annexure – I, Page - 5
Annexure-I (Contd.)
CMPDI
Job No.706134 Annexure – II, Page - 1
Annexure-II
CMPDI
Job No.706134 Annexure –III, Page - 1
Annexure-III
CMPDI
Job No.706134 Annexure –III, Page - 2
Annexure-III(Contd.)
CMPDI
Job No.706134 Annexure –III, Page - 3
Annexure-III(Contd.)
CMPDI
Job No.706134 Annexure –III, Page - 4
Annexure-III(Contd.)
CMPDI
Job No.706134 Annexure –III, Page - 5
Annexure-III(Contd.)
CMPDI
Job No.706134 Annexure –III, Page - 6
Annexure-III(Contd.)
CMPDI
Job No.706134 Annexure –III, Page - 7
Annexure-III(Contd.)
CMPDI
Job No.706134 Annexure – IV, Page - 1
Annexure-IV
CMPDI
Job No.706134 Annexure – IV, Page - 2
Annexure-I (Contd.)
CMPDI
Job No.706134 Annexure – IV, Page - 3
Annexure-I (Contd.)