l-03 spring loaded foundation-presentation
TRANSCRIPT
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
1/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
2/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
3/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
4/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
5/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
6/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
7/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
8/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
9/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
10/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
11/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
12/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
13/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
14/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
15/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
16/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
17/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
18/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
19/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
20/34
CHANGE OF CATENARY READINGS SIMHADRI 2X500 MW
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
21/34
FOLLOWING HAS BEEN REPORTED FROM THE ABOVE POWER STATION:
CHANGE IN CATENARY READING OF SIMHADRI 1 AFTER FLOATING OF
TG DECK.
CHANGE IN CATENARY READINGS (BEARING PEDESTAL HEIGHTS) AT
SIMHADRI UNIT-2 WITH FOLLOWING CONDITIONS:
- CONDENSER NECK NOT WELDED TO TURBINE.
- COMPLETE WEIGHT OF MACHINE NOT YET ERECTED ON
TG DECK.
- TIE ROD BOLTS OF FEW SPRING ASSEMBLIES FOUND LOOSE, OTHERS
COULD NOT BE CHECKED DUE TO ACCESSIBILITY
PROBLEMS.
SITE WAS ADVISED TO MAKE FOLLOWING MEASUREMENTS:- BETWEEN TG DECK AND COLUMN TOP.
- BETWEEN SPRING ASSEMBLIES (REFER THE ENCLOSED SKETCH).
DATA HAS BEEN RECEIVED FROM SITE INDICATING MAJORITY OF
SPRING ASSEMBLIES HAVING BEING LOADED BEYOND THE EXPECTED
DESIGN LOAD.
CHANGE OF CATENARY READINGS SIMHADRI 2X500 MW
CHANGE OF CATENARY READINGS SIMHADRI 2X500 MW
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
22/34
THE ABOVE FACTS PROVE THAT ELEVATION OF THE DECK KEEPS
CHANGING WITH ADDITION OF LOAD ON TG DECK EVEN PRIOR TO
UNLOCKING OF SPRING ASSEMBLIES. ERECTION ENGINEERS AT
SIMHADRI SITE ARE FINDING IT DIFFICULT TO FINALISE THE
REFERENCE FOR CENTERING OF CYLINDER, ALIGNMENT AND
CATENARY OF THE MACHINE.
MOVING DECK HAS RESULTED IN FREQUENT CHECKING OF
CENTERING AND ALIGNMENT READINGS. THIS HAS RESULTED IN
INCREASE OF ERECTION TIME.
CHANGE OF CATENARY READINGS SIMHADRI 2X500 MW
CONCLUSIONS
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
23/34
CONCLUSIONS
FROM THE READINGS TAKEN AT SIMHADRI, ANY ONE OF THE
FOLLOWING MAY BE TRUE:1. ERROR IN COMPUTING THE DESIGN LOAD OF TG DECK
ALONGWITH EQUIPMENT.
2. INADEQUATE STIFFNESS OF SPRINGS.
ACTION PLAN FOR SIMHADRI-2
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
24/34
REFER TO ERECTION PROTOCOLS. READINGS SET DURING
PLACEMENTS OF SPRING ASSEMBLIES BEFORE CASTING OF TG
DECK.
NO NECK WELDING OF CONDENSER TO TURBINE TO BE DONE.
IF TAG WELDED, REMOVE THESE.
UNLOCK ALL TG DECK SPRINGS ASSEMBLIES AND FLOAT THE
TG DECK.
CONDUCT NECESSARY SHIMMING TO ACHIEVE THE ELEVATION
AND CATENARY OF THE MACHINE.
LOCK ALL TG DECK SPRING ASSEMBLIES WITH SUFFICIENT
MARGIN FOR FURTHER LOADING OF TG DECK. WHILE DOING
THIS ACTIVITY, REFER TO BENCH MARK AND BEARING
PEDESTAL ELEVATION READING TAKEN BY TURBINE ERECTION
RECORD READINGS.
GERB TO PROVE THE HEALTHINESS OF SPRING ASSEMBLIES
SUPPLIED FOR SIMHADRI.
ACTION PLAN FOR SIMHADRI-2
ISSUES
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
25/34
SITE FEEDBACK INDICATES INCREASE IN ERECTION
CYCLE TIME.
NO FLEXIBILITY IN SEQUENCE OF ERECTION ACTIVITIES.
NO APPRECIABLE GAIN IN VIBRATION LEVEL ON
MACHINE WITH
SPRING LOADED TG DECK.
INCREASE IN OVERHAULING TIME OF TURBINES WITH
SPRING
LOADED TG DECK.
PROTECTION FROM SEISMIC LOADS.
PRECAUTION FROM SEISMIC LOADS NOTED.
GE / ALSTOM MAKE TURBINES DO NOT ENCOURAGE USE
OF SPRING LOADED TG DECK.
ISSUES
WHAT SHOULD BE BHELS STRATEGY FOR FUTURE SETS ?
ACTION PLAN FOR FUTURE SETS:
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
26/34
ACTION PLAN FOR FUTURE SETS:
TASK
DURING ERECTION ELEVATION OF TG DECK SHOULD NOT CHANGE
WITH CHANGE OF LOAD IN TG DECK. TO ACHIEVE THIS WE PROPOSE:
GERB SHOULD PROVIDE BOTH SIDE LOCKING IN SPRING
ASSEMBLIES AS IN CONDENSER SPRING ASSEMBLIES.
GERB TO RECONSIDER THE AMOUNT OF ADDITIONAL PRE-
STRESSING.
FOLLOWING ADDITIONAL PROTOCOLS NEEDS TO GENERATED
WHILE PRE-STRESSING THE SPRINGS AT SITE FOLLOWING
MEASUREMENTS TO BE NOTED:
GAP BETWEEN SPRING ASSEMBLY WITH TIE BOLTS LOOSE
(FREE LENGTH OF SPRINGS) AT FOUR LOCATIONS.
FORCE REQUIRED TO PRE-STRESS TO THE DESIRED VALUE
TO COMPUTE SPRING INDEX AND COMPARE WITH DESIGN
VALUE FOR EACH SPRING ASSEMBLY.
ACTION PLAN FOR FUTURE SETS:
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
27/34
RANDOMLY SELECT FEW SUCH PRESTESS SPRING
ASSEMBLIES, LOOSENING ITS TIE ROD. MEASUREMENT FREE
LENGTH AND CAMPARE WITH FREE LENGTH REFERENCE
COMPRESSION.
ALL READINGS AS DEPICTED IN THE SKETCH TO BE TAKEN
WITH INSIDE MICROMETER, LOCATION OF THE READING TO
BE DEFINED, IDENTIFIED AND PUNCHED (USE METALMARKER, WHERE PUNCHING CANNOT BE CARRIED OUT).
LOCATION OF MEASUREMENT A SHOULD BE CHIPPED AND
SMOOTHENED TO AVOID ANY DISTURBANCES DUE TO
LOOSE CONCRETE.
BEFORE FLOATING OF TG DECK PUT FOUR DIAL GAUGE
INDICATORS ON TOP OF TG DECK. SET IT ZERO W.R.T. TG FLOOR.
CHECK AND RECORD THE READINGS AFTER FLOATING OF TG
DECK.
ACTION PLAN FOR FUTURE SETS:
ACTION PLAN FOR FUTURE SETS:
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
28/34
VENDOR TO GIVE INSTALLATION MANUAL TO PROVIDE A
STEPWISE INSTRUCTIONS AND NUMBER OF PROTOCOLS TO BE
GENERATED.
BHEL TURBINE ERECTION ENGINEER TO INVOLVE DURING THE
COMPLETE INSTALLATION OF DECK SPRINGS.
ACTION PLAN FOR FUTURE SETS:
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
29/34
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
30/34
SCHEMATIC FOR GERB SPRING
TIE ROD
SHIM
TG DECK
TG COLUMN
NOTE:
1. THESE READINGS ARE IN
ADDITION TO READING
TAKEN BY GERB ON THE
PROTOCOL DOCUMENT.
2 TURBINE ENGINEER
ALONG WITH CIVIL
ENGINEER TO ASSOCIATE.
A. STICK MICRO METER READING AT FOUR
LOCATIONS BETWEEN DECK AND
COLUMN. MARK THE LOCATION OF
READING (USE METAL MARKER).
B. STICK MICROMETER READING AT FOUR
LOCATION OF EACH SPRING ASSEMBLY.
C RECORD TOTAL THICKNESS OF SHIMHEIGHT AND NUMBER OF SHIMS.
A AB B
C
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
31/34
TIE
ROD
SCHEMATIC FOR M/S GERBS CONDENSER SPRING ASSEMBLY
SHIM
JACK
BOLTS
CONDENSER
FOUNDATION
CONDENSER
BOTTOM PLATE
BACK
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
32/34
MOUNTING RECORD AT SIMHADRI UNIT-2 BY M/S GERB
Sl No Gr No Type
1 2 TVEH-750 25 5 30 229 5 16 5
2 1 T-1030 25 5 30 226 5 22 5
3 1 TVEH-750 25 5 30 226 5 16 5
4 2 T-650 25 5 30 229 5 16 5
5 2 T-650 25 5 30 229 5 16 5
6 2 T-1200 25 5 30 229 5 16 5
7 1 TVEH-750 25 5 30 226 5 17 5
8 2 T-1200 25 5 30 229 5 17 5
9 2 T-1200 25 5 30 229 5 14 5
10 2 T-800 25 5 30 229 5 14 5
11 2 T-1200 25 5 30 229 5 18 5
12 2 T-1030 25 5 30 229 5 20 5
13 2 T-650 25 5 30 229 5 13 5
14 1 TVEH-750 25 5 30 226 5 17 5
15 2 T-950 25 5 30 229 5 16 5
16 1 T-1030 25 5 30 226 5 23 5
17 2 T-650 25 5 30 229 5 16 5
18 1 T-950 25 5 30 226 5 22 5
19 2 T-500 25 5 30 229 5 19 5
20 1 TVEH-750 25 5 30 226 5 18 5
21 1 T-950 25 5 30 226 5 22 5
22 2 T-1030 25 5 30 229 5 24 5
23 2 T-800 25 5 30 229 5 16 5
24 1 T-950 25 5 30 226 5 19 5
25 2 TVEH-750 25 5 30 229 5 14 5
26 2 T-800 25 5 30 229 5 17 5
27 2 TVEH-750 25 5 30 229 5 14 5
28 2 T-800 25 5 30 229 5 19 5
Shim
Thickness
Actual
(mm)
Expected
Settlement
(mm)
Prestressing and setting 31.10.2000
Spring Unit
Static
Deflection
Mounting
Deflection
(mm)
Prestressi
ng Value
(mm)
Spring
Height
Prestressing
value
(mm)
Shim
Thickness
Theoretic
(mm)
18.02.2002
1 2 3 4
226.9 227.3 228.7 228.6
222 224.1 225 224.5
226 226.9 226.1 225.8
226.4 226.1 225.2 225
226.9 225.4 226.3 227
226.3 225.8 227.4 228.1
225.6 225.7 225.1 225.8
228.1 227.9 225.6 226.2
228.7 228.6 227.9 226.2
226.3 227.2 226.5 225.6
225.5 226.3 226.6 226
227.6 226.6 227.5 225.9
227 226.2 226.7 227.2
224.8 225.2 225.6 224.8
226.4 225.3 226.8 228.2
225 225.6 224.6 224.4
227 227 224.7 226.2
224.4 223.5 223.2 223.7
228.7 228 227.5 226.8
225.6 226 226.8 226.3
223.9 224 222.8 223.2
223.2 227.7 227.9 228.5
225.8 226.4 225.8 225.4
224.7 223.4 223.3 222
227.8 228.5 229 229
227.5 228.1 227 227.8
225.3 224.9 223.3 225.1
225.1 225 225.2 226
Releasing and adjusting
Spring Height After Releasing
(mm)
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
33/34
MOUNTING RECORD AT SIMHADRI UNIT-2 BY M/S GERB
Sl No Gr No Type31 1 TVEH-750 25 5 30 226 5 20 5
32 1 T-1030 25 5 30 226 5 26 5
33 1 TVEH-750 25 5 30 226 5 19 5
34 2 T-650 25 5 30 229 5 16 5
35 2 T-650 25 5 30 229 5 19 5
36 2 T-1200 25 5 30 229 5 18 5
37 2 TVEH-750 25 5 30 226 5 18 5
38 2 T-1200 25 5 30 229 5 18 5
39 2 T-1200 25 5 30 229 5 23 5
40 2 T-800 25 5 30 229 5 28 541 2 T-1200 25 5 30 229 5 25 5
42 2 T-1030 25 5 30 229 5 18 5
43 1 T-650 25 5 30 226 5 19 5
44 1 TVEH-750 25 5 30 226 5 16 5
45 1 T-950 25 5 30 226 5 22 5
46 2 T-1030 25 5 30 229 5 19 5
47 2 T-650 25 5 30 229 5 15 5
48 1 T-950 25 5 30 226 5 23 5
49 2 T-500 25 5 30 229 5 16 5
50 1 TVEH-750 25 5 30 226 5 16 551 2 T-950 25 5 30 229 5 20 5
52 1 T-1030 25 5 30 226 5 22 5
53 2 T-800 25 5 30 229 5 18 5
54 1 T-950 25 5 30 226 5 20 5
55 1 TVEH-750 25 5 30 226 5 18 5
56 2 T-800 25 5 30 229 5 18 5
57 2 TVEH-750 25 5 30 229 5 16 5
58 2 T-800 25 5 30 229 5 20 5
Expected
Settlemen
t
(mm)
31.10.2000Prestressing and setting
Spring
Height
Prestressi
ng value
(mm)
Shim
Thickness
Theoretic
(mm)
Shim
Thickness
Actual
(mm)Spring Unit
Static
Deflection
Mounting
Deflection
(mm)
Prestressi
ng Value
(mm)
18.02.2002
1 2 3 4224.3 227 226.3 223.8
225 225.3 224 224.8
226.5 226.6 226.8 226.5
227.5 227.1 226.3 226.8
227 227.6 225.4 226.2
225.7 226.2 227 226.4
229 229.1 229 229
227.1 227.1 226.3 227
222 226.5 227 222
226.6 226.4 227.1 226.5227 227.4 225.5 225
227.5 227.8 228.8 228
224.7 224.5 223.6 223.8
225.9 225.2 226.3 226.2
224 223.7 223 223.6
226.6 225.9 228.6 227
227.6 227 227.3 226.4
224.3 225.1 224.1 224.8
229 228.3 224.9 225.8
226.7 225.9 226.7 226.9228 227.5 227.6 227.2
224 224.5 225.3 224.8
226.5 227.4 227.4 227
224.1 222.3 222.2 222
223.7 225.3 226.2 225.1
226.7 226.8 227.3 226.9
226 224.4 222.2 223.5
226.1 226.3 222.9 222.9
Releasing and adjusting
Spring Height After Releasing
(mm)
BACK
-
7/31/2019 L-03 Spring Loaded Foundation-presentation
34/34