l-03 spring loaded foundation-presentation

Upload: sam

Post on 05-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    1/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    2/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    3/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    4/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    5/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    6/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    7/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    8/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    9/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    10/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    11/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    12/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    13/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    14/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    15/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    16/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    17/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    18/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    19/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    20/34

    CHANGE OF CATENARY READINGS SIMHADRI 2X500 MW

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    21/34

    FOLLOWING HAS BEEN REPORTED FROM THE ABOVE POWER STATION:

    CHANGE IN CATENARY READING OF SIMHADRI 1 AFTER FLOATING OF

    TG DECK.

    CHANGE IN CATENARY READINGS (BEARING PEDESTAL HEIGHTS) AT

    SIMHADRI UNIT-2 WITH FOLLOWING CONDITIONS:

    - CONDENSER NECK NOT WELDED TO TURBINE.

    - COMPLETE WEIGHT OF MACHINE NOT YET ERECTED ON

    TG DECK.

    - TIE ROD BOLTS OF FEW SPRING ASSEMBLIES FOUND LOOSE, OTHERS

    COULD NOT BE CHECKED DUE TO ACCESSIBILITY

    PROBLEMS.

    SITE WAS ADVISED TO MAKE FOLLOWING MEASUREMENTS:- BETWEEN TG DECK AND COLUMN TOP.

    - BETWEEN SPRING ASSEMBLIES (REFER THE ENCLOSED SKETCH).

    DATA HAS BEEN RECEIVED FROM SITE INDICATING MAJORITY OF

    SPRING ASSEMBLIES HAVING BEING LOADED BEYOND THE EXPECTED

    DESIGN LOAD.

    CHANGE OF CATENARY READINGS SIMHADRI 2X500 MW

    CHANGE OF CATENARY READINGS SIMHADRI 2X500 MW

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    22/34

    THE ABOVE FACTS PROVE THAT ELEVATION OF THE DECK KEEPS

    CHANGING WITH ADDITION OF LOAD ON TG DECK EVEN PRIOR TO

    UNLOCKING OF SPRING ASSEMBLIES. ERECTION ENGINEERS AT

    SIMHADRI SITE ARE FINDING IT DIFFICULT TO FINALISE THE

    REFERENCE FOR CENTERING OF CYLINDER, ALIGNMENT AND

    CATENARY OF THE MACHINE.

    MOVING DECK HAS RESULTED IN FREQUENT CHECKING OF

    CENTERING AND ALIGNMENT READINGS. THIS HAS RESULTED IN

    INCREASE OF ERECTION TIME.

    CHANGE OF CATENARY READINGS SIMHADRI 2X500 MW

    CONCLUSIONS

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    23/34

    CONCLUSIONS

    FROM THE READINGS TAKEN AT SIMHADRI, ANY ONE OF THE

    FOLLOWING MAY BE TRUE:1. ERROR IN COMPUTING THE DESIGN LOAD OF TG DECK

    ALONGWITH EQUIPMENT.

    2. INADEQUATE STIFFNESS OF SPRINGS.

    ACTION PLAN FOR SIMHADRI-2

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    24/34

    REFER TO ERECTION PROTOCOLS. READINGS SET DURING

    PLACEMENTS OF SPRING ASSEMBLIES BEFORE CASTING OF TG

    DECK.

    NO NECK WELDING OF CONDENSER TO TURBINE TO BE DONE.

    IF TAG WELDED, REMOVE THESE.

    UNLOCK ALL TG DECK SPRINGS ASSEMBLIES AND FLOAT THE

    TG DECK.

    CONDUCT NECESSARY SHIMMING TO ACHIEVE THE ELEVATION

    AND CATENARY OF THE MACHINE.

    LOCK ALL TG DECK SPRING ASSEMBLIES WITH SUFFICIENT

    MARGIN FOR FURTHER LOADING OF TG DECK. WHILE DOING

    THIS ACTIVITY, REFER TO BENCH MARK AND BEARING

    PEDESTAL ELEVATION READING TAKEN BY TURBINE ERECTION

    RECORD READINGS.

    GERB TO PROVE THE HEALTHINESS OF SPRING ASSEMBLIES

    SUPPLIED FOR SIMHADRI.

    ACTION PLAN FOR SIMHADRI-2

    ISSUES

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    25/34

    SITE FEEDBACK INDICATES INCREASE IN ERECTION

    CYCLE TIME.

    NO FLEXIBILITY IN SEQUENCE OF ERECTION ACTIVITIES.

    NO APPRECIABLE GAIN IN VIBRATION LEVEL ON

    MACHINE WITH

    SPRING LOADED TG DECK.

    INCREASE IN OVERHAULING TIME OF TURBINES WITH

    SPRING

    LOADED TG DECK.

    PROTECTION FROM SEISMIC LOADS.

    PRECAUTION FROM SEISMIC LOADS NOTED.

    GE / ALSTOM MAKE TURBINES DO NOT ENCOURAGE USE

    OF SPRING LOADED TG DECK.

    ISSUES

    WHAT SHOULD BE BHELS STRATEGY FOR FUTURE SETS ?

    ACTION PLAN FOR FUTURE SETS:

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    26/34

    ACTION PLAN FOR FUTURE SETS:

    TASK

    DURING ERECTION ELEVATION OF TG DECK SHOULD NOT CHANGE

    WITH CHANGE OF LOAD IN TG DECK. TO ACHIEVE THIS WE PROPOSE:

    GERB SHOULD PROVIDE BOTH SIDE LOCKING IN SPRING

    ASSEMBLIES AS IN CONDENSER SPRING ASSEMBLIES.

    GERB TO RECONSIDER THE AMOUNT OF ADDITIONAL PRE-

    STRESSING.

    FOLLOWING ADDITIONAL PROTOCOLS NEEDS TO GENERATED

    WHILE PRE-STRESSING THE SPRINGS AT SITE FOLLOWING

    MEASUREMENTS TO BE NOTED:

    GAP BETWEEN SPRING ASSEMBLY WITH TIE BOLTS LOOSE

    (FREE LENGTH OF SPRINGS) AT FOUR LOCATIONS.

    FORCE REQUIRED TO PRE-STRESS TO THE DESIRED VALUE

    TO COMPUTE SPRING INDEX AND COMPARE WITH DESIGN

    VALUE FOR EACH SPRING ASSEMBLY.

    ACTION PLAN FOR FUTURE SETS:

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    27/34

    RANDOMLY SELECT FEW SUCH PRESTESS SPRING

    ASSEMBLIES, LOOSENING ITS TIE ROD. MEASUREMENT FREE

    LENGTH AND CAMPARE WITH FREE LENGTH REFERENCE

    COMPRESSION.

    ALL READINGS AS DEPICTED IN THE SKETCH TO BE TAKEN

    WITH INSIDE MICROMETER, LOCATION OF THE READING TO

    BE DEFINED, IDENTIFIED AND PUNCHED (USE METALMARKER, WHERE PUNCHING CANNOT BE CARRIED OUT).

    LOCATION OF MEASUREMENT A SHOULD BE CHIPPED AND

    SMOOTHENED TO AVOID ANY DISTURBANCES DUE TO

    LOOSE CONCRETE.

    BEFORE FLOATING OF TG DECK PUT FOUR DIAL GAUGE

    INDICATORS ON TOP OF TG DECK. SET IT ZERO W.R.T. TG FLOOR.

    CHECK AND RECORD THE READINGS AFTER FLOATING OF TG

    DECK.

    ACTION PLAN FOR FUTURE SETS:

    ACTION PLAN FOR FUTURE SETS:

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    28/34

    VENDOR TO GIVE INSTALLATION MANUAL TO PROVIDE A

    STEPWISE INSTRUCTIONS AND NUMBER OF PROTOCOLS TO BE

    GENERATED.

    BHEL TURBINE ERECTION ENGINEER TO INVOLVE DURING THE

    COMPLETE INSTALLATION OF DECK SPRINGS.

    ACTION PLAN FOR FUTURE SETS:

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    29/34

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    30/34

    SCHEMATIC FOR GERB SPRING

    TIE ROD

    SHIM

    TG DECK

    TG COLUMN

    NOTE:

    1. THESE READINGS ARE IN

    ADDITION TO READING

    TAKEN BY GERB ON THE

    PROTOCOL DOCUMENT.

    2 TURBINE ENGINEER

    ALONG WITH CIVIL

    ENGINEER TO ASSOCIATE.

    A. STICK MICRO METER READING AT FOUR

    LOCATIONS BETWEEN DECK AND

    COLUMN. MARK THE LOCATION OF

    READING (USE METAL MARKER).

    B. STICK MICROMETER READING AT FOUR

    LOCATION OF EACH SPRING ASSEMBLY.

    C RECORD TOTAL THICKNESS OF SHIMHEIGHT AND NUMBER OF SHIMS.

    A AB B

    C

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    31/34

    TIE

    ROD

    SCHEMATIC FOR M/S GERBS CONDENSER SPRING ASSEMBLY

    SHIM

    JACK

    BOLTS

    CONDENSER

    FOUNDATION

    CONDENSER

    BOTTOM PLATE

    BACK

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    32/34

    MOUNTING RECORD AT SIMHADRI UNIT-2 BY M/S GERB

    Sl No Gr No Type

    1 2 TVEH-750 25 5 30 229 5 16 5

    2 1 T-1030 25 5 30 226 5 22 5

    3 1 TVEH-750 25 5 30 226 5 16 5

    4 2 T-650 25 5 30 229 5 16 5

    5 2 T-650 25 5 30 229 5 16 5

    6 2 T-1200 25 5 30 229 5 16 5

    7 1 TVEH-750 25 5 30 226 5 17 5

    8 2 T-1200 25 5 30 229 5 17 5

    9 2 T-1200 25 5 30 229 5 14 5

    10 2 T-800 25 5 30 229 5 14 5

    11 2 T-1200 25 5 30 229 5 18 5

    12 2 T-1030 25 5 30 229 5 20 5

    13 2 T-650 25 5 30 229 5 13 5

    14 1 TVEH-750 25 5 30 226 5 17 5

    15 2 T-950 25 5 30 229 5 16 5

    16 1 T-1030 25 5 30 226 5 23 5

    17 2 T-650 25 5 30 229 5 16 5

    18 1 T-950 25 5 30 226 5 22 5

    19 2 T-500 25 5 30 229 5 19 5

    20 1 TVEH-750 25 5 30 226 5 18 5

    21 1 T-950 25 5 30 226 5 22 5

    22 2 T-1030 25 5 30 229 5 24 5

    23 2 T-800 25 5 30 229 5 16 5

    24 1 T-950 25 5 30 226 5 19 5

    25 2 TVEH-750 25 5 30 229 5 14 5

    26 2 T-800 25 5 30 229 5 17 5

    27 2 TVEH-750 25 5 30 229 5 14 5

    28 2 T-800 25 5 30 229 5 19 5

    Shim

    Thickness

    Actual

    (mm)

    Expected

    Settlement

    (mm)

    Prestressing and setting 31.10.2000

    Spring Unit

    Static

    Deflection

    Mounting

    Deflection

    (mm)

    Prestressi

    ng Value

    (mm)

    Spring

    Height

    Prestressing

    value

    (mm)

    Shim

    Thickness

    Theoretic

    (mm)

    18.02.2002

    1 2 3 4

    226.9 227.3 228.7 228.6

    222 224.1 225 224.5

    226 226.9 226.1 225.8

    226.4 226.1 225.2 225

    226.9 225.4 226.3 227

    226.3 225.8 227.4 228.1

    225.6 225.7 225.1 225.8

    228.1 227.9 225.6 226.2

    228.7 228.6 227.9 226.2

    226.3 227.2 226.5 225.6

    225.5 226.3 226.6 226

    227.6 226.6 227.5 225.9

    227 226.2 226.7 227.2

    224.8 225.2 225.6 224.8

    226.4 225.3 226.8 228.2

    225 225.6 224.6 224.4

    227 227 224.7 226.2

    224.4 223.5 223.2 223.7

    228.7 228 227.5 226.8

    225.6 226 226.8 226.3

    223.9 224 222.8 223.2

    223.2 227.7 227.9 228.5

    225.8 226.4 225.8 225.4

    224.7 223.4 223.3 222

    227.8 228.5 229 229

    227.5 228.1 227 227.8

    225.3 224.9 223.3 225.1

    225.1 225 225.2 226

    Releasing and adjusting

    Spring Height After Releasing

    (mm)

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    33/34

    MOUNTING RECORD AT SIMHADRI UNIT-2 BY M/S GERB

    Sl No Gr No Type31 1 TVEH-750 25 5 30 226 5 20 5

    32 1 T-1030 25 5 30 226 5 26 5

    33 1 TVEH-750 25 5 30 226 5 19 5

    34 2 T-650 25 5 30 229 5 16 5

    35 2 T-650 25 5 30 229 5 19 5

    36 2 T-1200 25 5 30 229 5 18 5

    37 2 TVEH-750 25 5 30 226 5 18 5

    38 2 T-1200 25 5 30 229 5 18 5

    39 2 T-1200 25 5 30 229 5 23 5

    40 2 T-800 25 5 30 229 5 28 541 2 T-1200 25 5 30 229 5 25 5

    42 2 T-1030 25 5 30 229 5 18 5

    43 1 T-650 25 5 30 226 5 19 5

    44 1 TVEH-750 25 5 30 226 5 16 5

    45 1 T-950 25 5 30 226 5 22 5

    46 2 T-1030 25 5 30 229 5 19 5

    47 2 T-650 25 5 30 229 5 15 5

    48 1 T-950 25 5 30 226 5 23 5

    49 2 T-500 25 5 30 229 5 16 5

    50 1 TVEH-750 25 5 30 226 5 16 551 2 T-950 25 5 30 229 5 20 5

    52 1 T-1030 25 5 30 226 5 22 5

    53 2 T-800 25 5 30 229 5 18 5

    54 1 T-950 25 5 30 226 5 20 5

    55 1 TVEH-750 25 5 30 226 5 18 5

    56 2 T-800 25 5 30 229 5 18 5

    57 2 TVEH-750 25 5 30 229 5 16 5

    58 2 T-800 25 5 30 229 5 20 5

    Expected

    Settlemen

    t

    (mm)

    31.10.2000Prestressing and setting

    Spring

    Height

    Prestressi

    ng value

    (mm)

    Shim

    Thickness

    Theoretic

    (mm)

    Shim

    Thickness

    Actual

    (mm)Spring Unit

    Static

    Deflection

    Mounting

    Deflection

    (mm)

    Prestressi

    ng Value

    (mm)

    18.02.2002

    1 2 3 4224.3 227 226.3 223.8

    225 225.3 224 224.8

    226.5 226.6 226.8 226.5

    227.5 227.1 226.3 226.8

    227 227.6 225.4 226.2

    225.7 226.2 227 226.4

    229 229.1 229 229

    227.1 227.1 226.3 227

    222 226.5 227 222

    226.6 226.4 227.1 226.5227 227.4 225.5 225

    227.5 227.8 228.8 228

    224.7 224.5 223.6 223.8

    225.9 225.2 226.3 226.2

    224 223.7 223 223.6

    226.6 225.9 228.6 227

    227.6 227 227.3 226.4

    224.3 225.1 224.1 224.8

    229 228.3 224.9 225.8

    226.7 225.9 226.7 226.9228 227.5 227.6 227.2

    224 224.5 225.3 224.8

    226.5 227.4 227.4 227

    224.1 222.3 222.2 222

    223.7 225.3 226.2 225.1

    226.7 226.8 227.3 226.9

    226 224.4 222.2 223.5

    226.1 226.3 222.9 222.9

    Releasing and adjusting

    Spring Height After Releasing

    (mm)

    BACK

  • 7/31/2019 L-03 Spring Loaded Foundation-presentation

    34/34