AnsaldoNuclear e A Company of Ansaldo Energia DM1: WP1.5 Meeting Brussels 17-03-2006 L. Mansani [email protected] Progress on EFIT Progress on EFIT Design Design

Upload: pello

Post on 05-Jan-2016

40 views

Category:

Documents


0 download

DESCRIPTION

L. Mansani [email protected]. Progress on EFIT Design. EFIT: Reactor Block. EFIT SG & Pump Group. EFIT Purification Unit. Target Outside Diameter as a function of main Target Parameters. EFIT Windowless Target Heat Exchanger. 800 MeV 20 mA Proton Beam - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: L. Mansani mansani@nuc.ansaldo.it

AnsaldoNucleare A Company of Ansaldo Energia

DM1: WP1.5 Meeting Brussels 17-03-2006

L. Mansani

[email protected]

Progress on EFIT DesignProgress on EFIT Design

Page 2: L. Mansani mansani@nuc.ansaldo.it

AnsaldoNucleare A Company of Ansaldo Energia

DM1: WP1.5 Meeting Brussels 17-03-2006

EFIT: Reactor Block

Page 3: L. Mansani mansani@nuc.ansaldo.it

AnsaldoNucleare A Company of Ansaldo Energia

DM1: WP1.5 Meeting Brussels 17-03-2006

EFITSG & Pump Group

EFITPurification Unit

Page 4: L. Mansani mansani@nuc.ansaldo.it

AnsaldoNucleare A Company of Ansaldo Energia

DM1: WP1.5 Meeting Brussels 17-03-2006

Run Target Power[MW]

Target HX OD

[mm]

N° HX Tubes

HX Tubes radial pitch[mm]

Flow Rate[kg/s]

Primary Coolant Temp. (in/out)

[°C]

Target Coolant Temp. (in/out)

[°C]

Pump Tube Speed[m/s]

HX Tube Speed[m/s]

HX Shell Speed[m/s]

1 11.2 861 1274 19 780 400/450 422/524 1 0.54 0.55

2 11.2 861 1274 19 850 400/450 424/518 1.13 0.58 0.55

3 11.2 899 1410 19 780 400/450 419/522 1 0.48 0.49

4 11.2 899 1410 19 850 400/450 421/515 1.13 0.53 0.49

5 11.2 871 1410 18 780 400/450 418/521 1 0.48 0.56

6 11.2 871 1410 18 850 400/450 420/514 1.13 0.53 0.56

7 8.4 747 902 19 700 400/450 428/514 0.93 0.68 0.58

Target Outside Diameter as a function of main Target Parameters

Page 5: L. Mansani mansani@nuc.ansaldo.it

AnsaldoNucleare A Company of Ansaldo Energia

DM1: WP1.5 Meeting Brussels 17-03-2006

800 MeV 20 mA Proton Beam

Deposited Power in the Target 11.2 MW

EFIT Windowless Target Heat Exchanger

600 MeV 20 mA Proton Beam

Deposited Power in the Target 8.4 MW