Lab-Wide Earned Value Management System ProjectCore Team Kickoff Meeting
April 16, 2008Dean A. Hoffer.
![Page 2: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/2.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
2
Agenda• History• Definitions• Requirements• Work Scope• Project Participants• Project Collaboration Tool• Reference Material• Schedule• Team Training• Next Steps
![Page 3: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/3.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
3
Lab Earned Value History
• EV has been performed at some level since the Main Injector Project in the 1990s.
• In 1998 the Lab purchased Welcom’s (now Deltek) Cobra software tool for managing project costs, measuring earned value, and analyzing budgets, actuals and forecasts. The software was purchased to support the NuMI Project.
• The Cobra software was made the Lab’s standard software for measuring and reporting EV for projects that were required to report EV to DOE.
• Even though there was the Lab’s standard software tool for EV, there was not a Lab standard for the EVMS process. Each new project has created their own version of an EVMS.
![Page 4: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/4.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
4
Definitions
• Earned Value (EV) – The value of completed work expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure (WBS) components.
• Earned Value Management (EVM) is a management methodology for integrating scope, schedule, and recourses, and for objectively measuring project performance and progress.
• Earned Value Management System (EVMS) is a documented integrated set of processes to implement Earned Value Management.
![Page 5: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/5.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
5
Requirements
• DOE O 413.3A & DOE M 413.3-1 “Program and Project Management for the Acquisition of Capital Assets”– At CD-2, projects with a TPC <$20M are not required
to utilize an EVMS, but an alternative performance management system must be described in the respective Project Execution Plan.
– At CD-2, projects having a TPC ≥$20M and < $50M are to have a self-certified EVMS that is compliant with ANSI/EIA-748-A.
– At CD-2, projects having a TPC ≥ $50M are required to have an ANSI/EIA-748-A compliant system certified by the DOE Office of Engineering and Construction Management (OECM).
![Page 6: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/6.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
6
Requirements (continued)
• ANSI/EIA-748-A/B “Earned Value Management Systems” and Intent Guide– Standard provides basic guidelines to establish and
apply an integrated EVMS utilizing 32 Criteria that are grouped into 5 major categories
• Organization (5 criteria)
• Planning, Scheduling and Budgeting (10 criteria)
• Accounting Considerations (6 criteria)
• Analysis and Management Reports (6 criteria)
• Revisions and Data Maintenance (5 criteria)
![Page 7: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/7.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
7
Work Scope
• We are developing a Self-Certified EVMS that we are then requesting OECM to certify.
• Both a Certified and Self-Certified EVMS have to meet the same requirements, ANSI/EIA – 748.
• There are two parts that have to be accomplished to obtain a Certified system.
![Page 8: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/8.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
8
Work Scope (continued)
• Part 1 – Development and Implementation of a Lab-Wide EVMS Process– EVMS Management Policy– Lab-Wide EVMS Description Document– Implementing Procedures– Implementation Guides/Desktop Instructions– CAM Notebooks– Supporting Tools– Training– External Assessment
![Page 9: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/9.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
9
Work Scope (continued)
• Part 2 – OECM EVMS Certification Preparation Process– Readiness Assessment Site Visit– Certification Review– Corrective Action Plan (CAP)– Follow-up Review
![Page 10: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/10.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
10
Project Participants
• Project Co-Sponsors– Hugh Montgomery– Steve Holmes
![Page 11: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/11.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
11
Project Participants (continued)
• Core Team– Steve Dixon
– Ken Domann
– Harry Ferguson
– Bill Freeman
– Dean Hoffer
– Marc Kaducak
– Rob Kennedy
– Dale Knapp
– Elaine McCluskey
– Wyatt Merritt
– TJ Sarlina
– Suzanne Saxer
– Rich Stanek
![Page 12: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/12.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
12
Project Participants (continued)
• Tentative Oversight Committee– Bill Boroski
– Steve Dixon*
– Nancy Grossman
– Dave Harding
– Mike Lindgren
– Ann Nestander
– Ed Temple
– Connee Trimby
* Serves on both Core Team and Oversight Committee.
![Page 13: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/13.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
13
Project Collaboration Tool
• Will use WelcomHome for document repository, action item tracking, etc.
• Address – https://bss-pmprd.fnal.gov/wh/default.cfm
• Team members who already have WelcomHome user accounts now have access rights to the Lab-Wide EVMS Project
• Team members without a WelcomHome user account will need to complete account request form
![Page 14: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/14.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
14
Reference Material
• Material is on the memory stick and is being added to WelcomHome– EVMS documents from existing Lab Projects– EVMS documents from other Labs– DOE and ANSI requirement documents
![Page 15: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/15.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
15
Schedule
• Draft MSP Schedule based on work to be accomplished, but has not been resource loaded.
• Key Activities/Draft Dates– Documents ready for Readiness Review - 08/12/08– Readiness Review by OECM - 10/09/08– OECM On-Site Review – 01/02/09
• Need Core Team members time availability to resource load schedule
• Have to contact OECM on 6-May on updated projected Readiness Review and On-Site Review dates
![Page 16: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/16.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
16
Team Training
• Discuss potential training needs for Core Team and Oversight Committee
![Page 17: Lab-Wide Earned Value Management System Project Core Team Kickoff Meeting April 16, 2008 Dean A. Hoffer](https://reader036.vdocuments.net/reader036/viewer/2022083008/56649eff5503460f94c14c1b/html5/thumbnails/17.jpg)
16-Apr-2008 Lab-Wide EVMS Project Core Team Meeting
17
Next Steps
• Commitment of time availability of Core Team Members
• Team Members to review reference material • Team Members to review draft System
Description document • Evaluate list of Procedures needed to
implement System Description• Next meetings