Page 1: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works
Page 2: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Materials Coefficient (Civil Works) - 2013

Foreword

The Department of Engineering Services of Ministry of Works and Human Settlement ispleased to publish "Labour and Material Coefficient (LMC) - 2013".

This document forms the basis for the analysis of rate and the Bhutan Schedule of Rates-2013. The purpose for publishing this document is to provide the users an understandingof how the rates are calculated.

This document shall be read in conjunction with the BSR-2013 and the specifications forBuilding and Road Works (SBRW)-20l2.

I hope this document will prove useful to all the users within Bhutan.

>

Dr. Sonam TenzinSecretaryMinistry of Works and Human SettlementThimphu

Date:- 2- 2, !os I u> I~

Department of Engineering Services, MoWHS

Page 3: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Materials Coefficients (Civil Works) - 2013

Contents

CONTENTS

1. Labour and Materials Coefficients

Sl. No Description Page

01 Dismantling and Demolition 1

02 Clearing and Grubbing 7

03 Earthwork 9

04 Drainage 17

05 Mortars 29

06 Concrete Works 31

07 Damp Proofing 39

08 Reinforced Concrete 40

09 Brick Work 55

10 Stone/Mud 64

11 Wood Work 73

12 Steel 102

13 Flooring 108

14 Tiling – Wall and Floor 117

15 Roofing 118

16 Plumbing – Indoor Work 126

17 Plumbing – Outdoor Work 141

18 Plastering 175

19 Painting and Wall Paper 181

20 Additions, Alterations and Repairs 188

21 Road Works 190-211

2. Transportation Worksheets (Mechanical and Manual)

Page 4: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 1

CHAPTER 1

DD0001

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.89000 day DD0002 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.79000 day DD0003

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 4.21300 day DD0004 Coefficient for per cu.m Code Description Quant Units LB0077 Labour 0.76000 day

DD0005

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.10000 day

DD0006

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.25000 day

DD0007

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.40000 day

DD0008

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.70000 day

DD0009

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.05000 day

LB0051 Mason Gd.2 0.08000 day

DD0010

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.15000 day

LB0051 Mason Gd.2 0.10000 day

DD0011

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 4.08500 day

Demolishing hollow block masonry including stacking useful Materials & disposal of rubbish within 50m lead

Demolishing stone rubble masonry including stacking useful materials & disposal of rubbish within 50m lead - in lime mortar

Demolishing stone rubble masonry including stacking useful materials & disposal of rubbish within 50m lead - in cement mortar

Dismantling dressed ashlar face stone work includin g stacking useful materials & disposal of rubbish w ithin 50m lead - in lime mortar

Demolishing dressed ashlar face stone work includin g stacking useful materials & disposal of rubbish w ithin 50m lead - in cement mortar

Removing Mortar from stones and cleaning stones an d concrete articles and arranging in stacks - In li me mortar

Removing Mortar from stones and cleaning stones and concrete articles and arranging in stacks - In ce ment mortar

DISMANTLING & DEMOLITION WORK

Demolishing cement concrete 1:3:6 & richer, includi ng disposal of Materials within 50m lead

Demolishing cement concrete 1:4:8 & leaner, includi ng disposal of Materials within 50m lead

Demolishing lime concrete and disposal of rubbish w ithin 50m lead

Demolishing reinforced concrete, including stacking steel bars and disposal of rubbish within 50m lead

Department of Engineering Services, MoWHS

Page 5: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 2

DD0012

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 3.77500 day

DD0013 Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.00330 day LB0077 Labour 0.00660 day DD0014

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 1.20000 day

DD0015

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.65000 day

DD0016

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.77000 day

DD0017

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.90000 day

DD0018

Coefficient for per 1000#

Code Description Quant Units LB0077 Labour 3.90000 day

LB0051 Mason Gd.2 0.35000 day

DD0019

Coefficient for per 1000#

Code Description Quant Units LB0077 Labour 4.10000 day

LB0051 Mason Gd.2 0.70000 day

DD0020

Coefficient for per 1000#

Code Description Quant Units LB0077 Labour 4.85000 day

LB0051 Mason Gd.2 1.10000 day

DD0021

Coefficient for per kg

Code Description Quant Units LB0077 Labour 0.00340 day

Removing Mortar from bricks and cleaning bricks inc luding stacking useful materials within 50m lead - from BW in lime mortar

Removing Mortar from bricks and cleaning bricks inc luding stacking useful materials within 50m lead - from BW in cement mortar

Removing Mortar from bricks and cleaning bricks inc luding stacking useful materials within 50m lead - from BW in mud mortar

Demolishing reinforced brickwork, including stackin g steel bars and disposal of rubbish within 50m lea d

Extra, for scraping, cleaning, straightening reinfo rcement from R.C & reinforced brick work

Extra for cutting reinforcement bars in reinforced cement concrete and reinforced brickwork (payment t o be made the cross sectional area of RCC or RB work)

Demolishing brick work including stacking useful ma terials & disposal of rubbish within 50m lead - in mud mortar

Demolishing brick work including stacking useful ma terials & disposal of rubbish within 50m lead - in lime mortar

Demolishing brick work including stacking useful ma terials & disposal of rubbish within 50m lead - in cement mortar

Dismantling steelwork in single sections including dismembering and stacking within 50m lead in RS joi sts

Department of Engineering Services, MoWHS

Page 6: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 3

DD0022

Coefficient for per kg

Code Description Quant Units LB0077 Labour 0.00300 day

DD0023

Coefficient for per kg

Code Description Quant Units LB0077 Labour 0.00700 day

DD0024

Coefficient for per kg

Code Description Quant Units LB0077 Labour 0.00600 day

DD0025

Coefficient for per cu.m

Code Description Quant Units LB0033 Carpenter Gd.2 1.00000 day LB0077 Labour 1.60000 day DD0026

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.05000 day LB0077 Labour 0.20000 day DD0027

Coefficient for per cu.m/m span

Code Description Quant Units LB0033 Carpenter Gd. 2 0.10000 day LB0077 Labour 0.45000 dayDD0028

Coefficient for per cu.m/m span

Code Description Quant Units LB0033 Carpenter Gd. 2 0.00050 day LB0077 Labour 0.00200 day DD0029

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd. 2 0.06250 day LB0051 Mason Gd.2 0.12500 day LB0077 Labour 0.22500 day DD0030

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd. 2 0.08800 day LB0051 Mason Gd.2 0.16300 day LB0077 Labour 0.31250 day DD0031

Coefficient for per each

Code Description Quant Units LB0051 Mason Gd.2 0.06250 day LB0077 Labour 0.10000 day

Dismantling steelwork in built up sections in chann els, angles, tees and flats in all gusset plates, b olts, nuts, cutting rivets, welding etc. including dismembering and stacking wi thin 50 m lead

Dismantling steelwork in built up sections without dismembering and stacking within 50 m lead

Dismantling wood work of sectional area 40 sq.cm an d above in frames,trusses (<10m span) including sta cking within 50m lead

Dismantling wood work of sectional area <40 sq.cm i n frames, trusses including stacking within 50m lea d

Extra for dismantling trusses, rafters, purlins etc . of every additional span of 1 metre or part there of for span >10m (sectional area > 40sq.cm)

Extra for dismantling trusses, rafters, purlins etc . every additional span of 1 metre or part thereof >10m (sectional area < 40sq.cm)

Dismantling doors, windows, and clerestory windows <3sq.m (steel, wood) including architrave, hold fas ts, stacking within 50m lead

Dismantling doors, windows and clerestory windows > 3sq.m (steel/wood) including architrave, hold fasts , and stacking within 50m lead

Taking out doors, windows and clerestory windows sh utters <3sq.m (steel, wood) including stacking with in 50m lead

Dismantling steelwork in single sections including dismembering and stacking within 50m lead in channe ls, angles, tees and flats

Department of Engineering Services, MoWHS

Page 7: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 4

DD0032

Coefficient for per each

Code Description Quant Units LB0051 Mason Gd.2 0.08800 day LB0077 Labour 0.31300 day DD0040

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.05600 day LB0077 Labour 0.11200 day

DD0041

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.25000 day

DD0042

Coefficient for per sq.m of stone flooring

Code Description Quant UnitsLB0051 Mason Gd.2 0.02500 day

LB0077 Labour 0.22500 day

DD0043

Coefficient for per sq.m of jack arch roof and floo r

Code Description Quant Units LB0077 Labour 0.25000 day DD0045

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.06250 day LB0077 Labour 0.12500 day

DD0046

Coefficient for per sq.m of tile roofing

Code Description Quant Units LB0077 Labour 0.19500 day

LB0033 Carpenter Gd.2 0.02000 day DD0050

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.01250 day LB0077 Labour 0.07500 day DD0055

Coefficient for per kg

Code Description Quant Units LB0077 Labour 0.04400 day DD0056

Coefficient for per each

Code Description Quant Units LB0077 Labour 0.41748 day

Dismantling dry brick patching in floors, drains et c including stacking useful materials & disposal of rubbish within 50m lead

Dismantling stone slab flooring laid in cement mort ar including stacking useful materials & disposal o f rubbish within 50m lead

Dismantling jack arch roofing and floors including stacking useful materials & disposal of rubbish wit hin 50m lead

Dismantling tiled roofing with batten boarding etc . complete including stacking useful materials & di sposal of rubbish within 50m lead

Taking out doors, windows and clerestory window shu tters >3sq.m (steel or wood) including stacking wit hin 50m lead

Dismantling expanded metal, fabrics & battens, bead ing including stacking useful materials within 50m lead

Dismantling barbed wire, flexible wire including ma king rolls, & stacking within 50m lead

Dismantling fence posts, struts/T & L iron/pipes & earth work/demolishing of concrete and stacking wit hin 50m lead

Dismantling wooden flooring including stacking usef ul materials & disposal rubbish within 50m lead

Dismantling G.I sheets including ridges, hips, vall eys, gutters, & stacking Materials within 50m lead

Department of Engineering Services, MoWHS

Page 8: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 5

DD0057

Coefficient for per each

Code Description Quant Units LB0077 Labour 0.49690 day DD0058

Coefficient for per each

Code Description Quant Units LB0077 Labour 0.12500 day DD0065

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.02500 day LB0077 Labour 0.03800 day DD0066

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.02500 day LB0077 Labour 0.09300 day DD0067

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.05000 day

DD0075

Coefficient for per m

Code Description Quant Units LB0077 Labour 0.10700 day DD0076

Coefficient for per m

Code Description Quant Units LB0077 Labour 0.11800 day DD0077

Coefficient for per m

Code Description Quant Units LB0077 Labour 0.12600 day

DD0078

Coefficient for per m length of pipe

Code Description Quant Units LB0077 Labour 0.04720 day

LB0054 plumber Gd. 2 0.01860 dayMT0035 Kerosene 0.00940 litreMT0040 Firewood 0.00086 cu.mMT0042 Mud dry 0.01100 cu.mEW0135 Excavation and refilling in all kinds of soil 0.40200 cu.m

Dismantling CI pipes including excavation and refil ling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, stacking of pies at site and disposal of rubbish within 50m le ad - upto 150 mm dia

Demolishing of old S.W pipes including breaking joi nts, bed concrete, stacking of useful materials & d isposal of rubbish within 50m lead - 150mm dia

Demolishing of old S.W pipes including breaking joi nts, bed concrete, stacking of useful materials & d isposal of rubbish within 50m lead - 200mm dia

Dismantling of ekra wall in cement mortar 1:6 or ri cher including stacking useful materials & disposal of rubbish within 50m lead

Dismantling fence posts, struts R.C including earth work/demolishing concrete footings, stacking, 50m lead

Cutting ballies/wooden posts at ground or projectio n above concrete & stacking within 50m lead

Dismantling cement A.C., celotex, hardboard ceiling , partition, including stacking useful materials, d isposal rubbish within 50m

Demolishing of old S.W pipes including breaking joi nts, bed concrete, stacking of useful materials, & disposal of rubbish within 50m lead - 100mm dia

Dismantling old plaster or skirting, raking out joi nts and cleaning the surface for plaster including disposal of rubbish within 50m lead

Department of Engineering Services, MoWHS

Page 9: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 6

DD0079

Coefficient for per m length of pipe

Code Description Quant Units LB0077 Labour 0.14280 day

LB0054 plumber Gd. 2 0.04350 dayMT0035 Kerosene 0.02830 litreMT0040 Firewood 0.00200 cu.mMT0042 Mud dry 0.05880 cu.mEW0135 Excavation and refilling in all kinds of soil 0.42870 cu.m

DD0080

Coefficient for per m length of pipe

Code Description Quant Units LB0077 Labour 0.29810 day

LB0054 plumber Gd. 2 0.08690 dayMT0035 Kerosene 0.56380 litreMT0040 Firewood 0.00273 cu.mMT0042 Mud dry 0.18080 cu.mEW0316 Excavation and refilling in all kinds of soil 0.45650 cu.m

DD0085

Coefficient for per m

Code Description Quant Units LB0077 Labour 0.09700 day DD0086

Coefficient for per m

Code Description Quant Units LB0077 Labour 0.12800 day

DD0090

Coefficient for per sq.m area of wall

Code Description Quant Units LB0077 Labour 0.23000 day

LB0051 Mason Gd.2 0.05000 day

DD0091

Coefficient for per sq.m area of wall

Code Description Quant Units LB0077 Labour 0.32500 day

LB0051 Mason Gd.2 0.08500 day

DD0095

Coefficient for per sq.m area of road

Code Description Quant Units LB0077 Labour 0.22400 day

DD0096

Coefficient for per sq.m area of road

Code Description Quant Units LB0077 Labour 0.03450 day

DD0100

Coefficient for per no of flushing cistern

Code Description Quant Units LB0077 Labour 0.45000 day

LB0054 Plumber Gd.2 0.35000 day

Dismantling CI pipes including excavation and refil ling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, stacking of pies at site and disposal of rubbish within 50m le ad - above 300 mm dia

Dismantling of G.I or HDPE pipes of diameter 100mm to 250mm including breaking bed concrete, clamps, e tc. and stacking of useful materials, & disposal of rubbish within 5 0 m lead. - H.D.P.E Pipes

Dismantling of precast concrete or stone slabs in w alls, partition walls etc. including of useful mate rials & disposal of rubbish within 50 m lead - upto 40 mm thickness

Dismantling of precast concrete or stone slabs in w alls, partition walls etc. including of useful mate rials & disposal of rubbish within 50 m lead - above 40 mm thickness an d upto 74mm thickness

Dismantling of G.I or HDPE pipes of diameter 100mm to 250mm including breaking bed concrete, clamps, e tc. and stacking of useful materials & disposal of rubbish within 50 m lead. - G.I Pipes

Dismantling of flushing cistern of any size includi ng stacking of useful materials & disposal of rubbi sh within 50 m lead

Dismantling CI pipes including excavation and refil ling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, stacking of pies at site and disposal of rubbish within 50m le ad - from 150 mm upto 300 mm

Dismantling water bound macadam road including stac king of useful materials & disposal of rubbish with in 50 m lead

Dismantling bituminous road including cutting, stac king of useful materials & disposal of rubbish with in 50 m lead

Department of Engineering Services, MoWHS

Page 10: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 7

CHAPTER 2

CG0001 Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01060 day CG0002

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03350 day CG0010

Coefficient for per each

Code Description Quant Units LB0077 Labour 0.31260 day CG0011

Coefficient for per each

Code Description Quant Units LB0077 Labour 1.41000 day CG0012

Coefficient for per each

Code Description Quant Units LB0077 Labour 6.56250 day CG0013

Coefficient for per each

Code Description Quant Units LB0077 Labour 13.12500 day CG0020

Coefficient for per Each

Code Description Quant Units MP0208 Bull Dozer ( IH TD20E) 0.00360 day CG0021

Coefficient for per Each

Code Description Quant Units LB0047 Blaster 0.01000 day MP0208 Bull Dozer ( IH TD20E) 0.01000 day MT0020 Superdyne / Gelatine 0.50000 kg MT0021 Fuse Coil 0.25000 each MT0022 Detonator 1.00000 each

CLEARING AND GRUBBING

Clearing jungle including uprooting of vegetation & trees of girth < 300mm, disposal within 50m of the site

Felling of trees including removal of roots and dis posal of rubbish using bull dozer (excluding cuttin g of trunks, branches & stacking) - Girth 300 to 600mm

Felling of trees including removal of roots and dis posal of rubbish using bull dozer (excluding cuttin g of trunks, branches & stacking) - Girth 600 to 1200m

Felling trees including cutting of trunks and branc hes, removal of roots, stacking of serviceable mate rials and disposal of rubbish within 50m lead - Girth 300 to 600mm

Felling trees including cutting of trunks and branc hes, removal of roots, stacking of serviceable mate rials and disposal of rubbish within 50m lead - Girth 600 to 1200mm

Felling trees including cutting of trunks and branc hes, removal of roots, stacking of serviceable mate rials and disposal of rubbish within 50m lead - Girth 1200 to 2400 mm

Felling trees including cutting of trunks and branc hes, removal of roots, stacking of serviceable mate rials and disposal of rubbish within 50m lead - Girth > 2400mm

Clearing grass including removal of rubbish within 50m of site

Department of Engineering Services, MoWHS

Page 11: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 8

CG0022

Coefficient for per Each

Code Description Quant Units LB0047 Blaster 0.02000 day MP0208 Bull Dozer ( IH TD20E) 0.02000 day MT0020 Superdyne / Gelatine 1.00000 kg MT0021 Fuse Coil 0.50000 each MT0022 Detonator 2.00000 each CG0023

Coefficient for per Each

Code Description Quant Units LB0047 Blaster 0.04000 day MP0208 Bull Dozer ( IH TD20E) 0.03500 day MT0020 Superdyne / Gelatine 2.00000 kg MT0021 Fuse Coil 1.00000 each MT0022 Detonator 4.00000 each CG0030

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.22600 day

Felling of trees including removal of roots and dis posal of rubbish using bull dozer (excluding cuttin g of trunks, branches & stacking) - Girth 1200 to 2400 mm

Felling of trees including removal of roots and dis posal of rubbish using bull dozer (excluding cuttin g of trunks, branches & stacking) - Girth > 2400m

Clearing grass removal of landslide debris & surfac e material including excav.& disposal within 50m le ad

Department of Engineering Services, MoWHS

Page 12: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 9

CHAPTER 3

EW0001

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03390 day EW0002

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.04760 day

EW0010

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01252 day

EW0011

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03000 day

EW0020

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.06260 day

EW0021

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.08750 day EW0030

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.43010 day

EW0031

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.55630 day EW0032

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.59600 day MT0020 Superdyne / Gelatine 0.19700 kg MT0021 Fuse Coil 0.20000 each MT0022 Detonator 0.20000 each

Earth work in surface excavation, depth <300mm, wid th >1.5m, area >10 Sq.m in plan, including disposal of excavated earth within 50m lead & 1.5m lift and disposed soil to be neatly dressed - Ordinary soil

Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including dispo sal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Ordinary Soil

Ploughing the existing ground to a depth 150mm to 2 50mm, and watering the same - Hard Soil

EARTH WORK

Surface dressing of ground, including removal of ve getations and inequalities < 150mm deep, disposal o f rubbish within 50m lead and 1.5m lifts - Ordinary Soil

Ploughing the existing ground to a depth 150mm to 2 50mm, and watering the same - Ordinary Soil

Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including dispo sal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard Soil

Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including dispo sal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Ordinary rock with or witho ut blasting

Surface dressing of ground, including removal of ve getations and inequalities < 150mm deep, disposal o f rubbish within 50m lead and 1.5m lifts - Hard Soil

Earth work in surface excavation, depth <300mm, wid th >1.5m, area >10 Sq.m in plan, including disposal of excavated earth within 50m lead & 1.5m lift and disposed soil to be neatly dressed - Hard soil

Department of Engineering Services, MoWHS

Page 13: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 10

EW0033

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.11800 day MT0020 Superdyne / Gelatine 0.39300 kg MT0021 Fuse Coil 0.40000 each MT0022 Detonator 0.40000 each EW0034

Coefficient for per cu.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.05060 day LB0051 Mason Gd.2 0.30500 day LB0077 Labour 3.20720 day EW0035

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.13000 day EW0040

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.02420 day MP0203 Pay Loader ( Cat -910) 0.00200 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00610 day EW0046

Coefficient for per cu.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00330 day MP0208 Bull Dozer ( IH TD20E) 0.00370 day EW0047

Coefficient for per cu.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00330 day MP0208 Bull Dozer ( IH TD20E) 0.00500 day EW0055

Coefficient for per cu.m

Code Description Quant Units LB0047 Blaster 0.00250 day LB0077 Labour 0.00400 day MP0212 Compressor (CPS - 300) 0.00400 day MT0020 Superdyne / Gelatine 0.16600 kg MT0021 Fuse Coil 0.20000 each MT0022 Detonator 0.20000 each MT0023 Drill rod- 8' 0.00250 each EW0056

Coefficient for per cu.m

Code Description Quant Units LB0047 Blaster 0.00500 day LB0077 Labour 0.00800 day MP0212 Compressor (CPS - 300) 0.00800 day MT0020 Superdyne / Gelatine 0.33200 kg MT0021 Fuse Coil 0.40000 each MT0022 Detonator 0.40000 each MT0023 Drill rod 0.00500 each

Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including dispo sal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard rock requiring blastin g

Earth work in excavation over areas, depth >300mm, width >1.5m, area >10 Sq.m on plan, including dispo sal of excavated earth within 50m lead and 1.5m lift & disposed soil to be neatly dressed - Hard rock requiring chisell ing (where blasting is prohibited)

Extra, for every additional lead of 25m beyond 50m upto 250m and deposit to a level upto 1.5m - All ki nds of soil

Extra, for every additional lead of 25m beyond 250m upto 1000m and deposit to a level upto 1.5m - All kinds of soil

Earth work in excavation over areas by Dozer includ ing levelling and dressing - All kinds of soils

Earth work in excavation over areas by Dozer includ ing levelling and dressing - All kinds of rocks ( b lasted)

Blasting of rocks complete excluding the cost of co llection and stacking of blasted rock - Ordinary ro ck

Blasting of rocks complete excluding the cost of co llection and stacking of blasted rock - Hard rock

Department of Engineering Services, MoWHS

Page 14: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 11

EW0065

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.01600 day MP0212 Compressor (CPS - 300) 0.00800 day MT0023 Drill rod 0.00125 each MT0024 Silent Blaster 10.00000 kg EW0066

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.50000 day MP0212 Compressor (CPS - 300) 0.00800 day MT0023 Drill rod 0.00600 each MT0024 Silent Blaster 10.00000 kg EW0075

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.20000 day MP0212 Compressor (CPS - 300) 0.00800 day MT0023 Drill rod 0.00125 each MT0024 Silent Blaster 10.00000 kg EW0076

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.80000 day MP0212 Compressor (CPS - 300) 0.00800 day MT0023 Drill rod 0.00600 each MT0024 Silent Blaster 10.00000 kg EW0085

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.56538 day MP0200 Roller, CAT -CS551 0.00200 day EW0096

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.34706 day MP0200 Roller, CAT -CS551 0.00200 day EW0097

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.00100 day MP0200 Roller, CAT -CS551 0.00200 day EW0098

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.02130 day

Breaking of rocks using non-explosive blaster (sile nt blaster) in foundation trenches width <1.5m, are a <10sq.m on plan including stacking of boulders or useful materials and disposal of rubbish etc complete - Ordinary roc k

Breaking of rocks using non-explosive blaster (sile nt blaster) in foundation trenches width <1.5m, are a <10sq.m on plan including stacking of boulders or useful materials and disposal of rubbish etc complete - Hard rock

Banking excavated earth for road, flood banks, guid e banks & depressions, in layers <200mm depth, incl uding watering, rolling & dressing up within 50m lead & 1.5m lift - Deduction - for not watering in layered, banking w orks

Breaking of rocks using non-explosive blaster (sile nt blaster) in over areas, depth >300mm, width >1.5 m, area >10sq.m on plan including stacking of boulders or useful mater ials and disposal of rubbish etc complete - Ordinar y rock

Breaking of rocks using non-explosive blaster (sile nt blaster) in over areas, depth >300mm, width >1.5 m, area >10sq.m on plan including stacking of boulders or useful mater ials and disposal of rubbish etc complete - Hard ro ck

Earth work in rough excavation & banking of excavat ed earth in layers < 200 mm in depth for road, floo d/guide banks & depressions, including watering, power rolling, dre ssing, lead upto 50m & 1.5m lift - All kinds of Soi l

Banking excavated earth for road, flood banks, guid e banks & depressions, in layers <200mm depth, incl uding watering, rolling & dressing up within 50m lead & 1.5m lift - All kinds of Soil

Banking excavated earth for road, flood banks, guid e banks & depressions, in layers <200mm depth, incl uding watering, rolling & dressing up within 50m lead & 1.5m lift - Deduction - for not rolling with power roller in layered banking works

Department of Engineering Services, MoWHS

Page 15: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 12

EW0105

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.45880 day

EW0106

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.58800 day EW0107

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.68380 day MT0020 Superdyne / Gelatine 0.22500 kg MT0021 Fuse Coil 0.30000 each MT0022 Detonator 0.30000 each EW0108

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.25880 day MT0020 Superdyne / Gelatine 0.64200 kg MT0021 Fuse Coil 0.70000 each MT0022 Detonator 0.70000 each EW0109

Coefficient for per cu.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.04400 day LB0051 Mason Gd.2 0.26500 day LB0077 Labour 3.31630 day EW0115 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.05000 day EW0116

Coefficient for per cu.m

Code Description Quant Units LB0076 Labour 0.08900 day EW0125

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.11760 day MP0201 Water pump AVI type 0.01000 day EW0126 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.14700 day

Extra, for trench, pit works per cu.m per m depth - Under water

Excavation in foundation trenches or drains, not ex ceeding 1.5m in width or area 10 sq.m on plan, and depth > 300 mm including dressing & ramming, disposal of surplus s oil within 50m lead & 1.5m lift - Ordinary Soil

Excavation in foundation trenches or drains, not ex ceeding 1.5m in width or area 10 sq.m on plan, and depth > 300 mm including dressing & ramming, disposal of surplus s oil within 50m lead & 1.5m lift - Ordinary rock wit h or without blasting

Excavation in foundation trenches or drains, not ex ceeding 1.5m in width or area 10 sq.m on plan, and depth > 300 mm including dressing & ramming, disposal of surplus s oil within 50m lead & 1.5m lift - Hard rock requiri ng blasting

Excavation in foundation trenches or drains not exc eeding 1.5m in width or area 10 sq.m on plan, and depth > 300 mm including dressing & ramming, disposal of surplus soil within 50m lead & 1.5m lift

Extra for every additional lift of 1.5m or part the reof - All kinds of Soils

Extra, for trench, pit works per cu.m per m depth - In foul conditions

Excavation in foundation trenches or drains, not ex ceeding 1.5m in width or area 10 sq.m on plan, and depth > 300 mm including dressing & ramming, disposal of surplus s oil within 50m lead & 1.5m lift - Hard Soil

Extra for every additional lift of 1.5m or part the reof - All kinds of rocks

- Hard rock requiring chiselling (where blasting i s prohibited)

Department of Engineering Services, MoWHS

Page 16: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 13

EW0135

Coefficient for per m

Code Description Quant Units LB0077 Labour 0.64217 day EW0136

Coefficient for per m

Code Description Quant Units LB0077 Labour 1.00234 day EW0155

Coefficient for per m

Code Description Quant Units LB0077 Labour 2.35878 day MT0020 Superdyne / Gelatine 0.26325 kg MT0021 Fuse Coil 0.35100 each MT0022 Detonator 0.35100 each EW0156

Coefficient for per m

Code Description Quant Units LB0077 Labour 2.71413 day MT0020 Superdyne / Gelatine 0.30299 kg MT0021 Fuse Coil 0.40398 each MT0022 Detonator 0.40398 each EW0165

Coefficient for per m

Code Description Quant Units LB0077 Labour 3.03154 day MT0020 Superdyne / Gelatine 0.75114 kg MT0021 Fuse Coil 0.81900 each MT0022 Detonator 0.81900 each EW0166

Coefficient for per m

Code Description Quant Units LB0077 Labour 3.48842 day MT0020 Superdyne / Gelatine 0.86452 kg MT0021 Fuse Coil 0.94262 each MT0022 Detonator 0.94262 each EW0175

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.05148 day LB0051 Mason Gd.2 0.31005 day LB0077 Labour 4.26881 day

- Pipes, cables etc. 80mm < dia < 300mm

Hand excavation and refilling in layers < 200mm, of trenches for pipes & sockets, cables, including dr essing of sides, ramming of bottom, depth < 1.5m, disposal of surplu s material within lead of 50m: Hard rock requiring blasting

Hand excavation and refilling in layers < 200mm, of trenches for pipes & sockets, cables, including dr essing of sides/ ramming of bottom, depth < 1.5m, disposal of surplu s material within lead of 50m: Ordinary rock with o r without blasting

- Pipes, cables etc. 80mm < dia < 300mm

- Pipes, cables etc. dia.> 300mm

- Pipes, cables etc. dia.> 300mm

Hand excavation and refilling in layers < 200mm, of trenches for pipes & sockets, cables, including dr essing of sides/ ramming of bottom, depth < 1.5m, disposal of surplu s material within lead of 50m: Ordinary rock with o r without blasting

Hand excavation and refilling in layers < 200mm, of trenches for pipes & sockets, cables, including dr essing of sides, ramming of bottom, depth < 1.5m, disposal of surplu s material within lead of 50m: Hard rock requiring blasting

- Pipes, cables etc. 80mm < dia < 300mm

- Pipes, cables etc. dia.>300 mm

Hand excavation and refilling in layers < 200mm, of trenches for pipes & sockets, cables, including dr essing of sides/ ramming of bottom, depth upto 1.5m, disposal of sur plus material within lead of 50m: All kinds of soi l

Hand excavation and refilling in layers < 200mm, of trenches for pipes & sockets, cables, including dr essing of sides/ ramming of bottom, depth upto 1.5m, disposal of sur plus material within lead of 50m: All kinds of Soil

Hand excavation and refilling in layers < 200mm, of trenches for pipes & sockets, cables, including dr essing of sides \ramming of bottom, depth < 1.5m, disposal of surpl us material within lead of 50m:

Hard rock requiring chiselling (where blasting is p rohibited) - Pipes, cables etc. 80mm < dia < 300mm

Department of Engineering Services, MoWHS

Page 17: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 14

EW0176

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.05925 day LB0051 Mason Gd.2 0.35685 day LB0077 Labour 4.91245 day EW0185

Coefficient for per m

Code Description Quant Units LB0077 Labour 1.33077 day EW0186 Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.07406 day LB0051 Mason Gd.2 0.44606 day LB0077 Labour 6.14056 day EW0195

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.29550 day EW0196

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.28880 day MT0043 Sand 1.00000 cu.m EW0197

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.30300 day MT0042 Mud dry 1.00000 cu.m EW0205

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.00330 day LB0077 Labour 0.00690 day MT0325 Ballies 75 to 125mm dia 0.28330 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00870 cu.m EW0206

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.00690 day LB0077 Labour 0.01360 day MT0325 Ballies 75 to 125mm dia 0.28330 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00870 cu.m EW0207

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.01390 day LB0077 Labour 0.02440 day MT0325 Ballies 75 to 125mm dia 0.28330 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00870 cu.m

Providing & laying dry earth bedding, including con solidating each deposited layer by watering, rammin g and dressing

Open timbering over areas including lagging & strut ting of trenches, cuts (per sq.m face area timbered ) - Depth not exceeding 1.5m

Extra for excavating trenches for pipes, cables etc ., 1.5 < depth < 3m - All kinds of soil

Extra for excavating trenches for pipes, cables etc ., 1.5 < depth < 3m - Ordinary, hard rock

Filling of trenches, sides of foundations etc. in l ayers <200mm using selected excavated earth, rammin g etc. within lead 50 m & lift 1.5m

Providing & laying sand bedding, including watering , ramming, dressing

Hand excavation and refilling in layers < 200mm, of trenches for pipes & sockets, cables, including dr essing of sides \ramming of bottom, depth < 1.5m, disposal of surpl us material within lead of 50m:

Open timbering over areas including lagging & strut ting of trenches, cuts (per sq.m face area timbered ) - 1.5m < depth < 3 m

Open timbering over areas including lagging & strut ting of trenches, cuts (per sq.m face area timbered ) - Depth > 3 m

Hard rock requiring chiselling (where blasting is p rohibited) - Pipes, cables etc. dia.> 300mm

Department of Engineering Services, MoWHS

Page 18: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 15

EW0215

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.00690 day LB0077 Labour 0.01390 day MT0325 Ballies 75 to 125mm dia 0.28330 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.02570 cu.m EW0216

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.01385 day LB0077 Labour 0.03500 day MT0325 Ballies 75 to 125mm dia 0.28330 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.02570 cu.m EW0217

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.02080 day LB0077 Labour 0.05600 day MT0325 Ballies 75 to 125mm dia 0.28330 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.02570 cu.m EW0225

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.01140 day LB0077 Labour 0.02270 day MT0325 Ballies 75 to 125mm dia 0.49940 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.02240 cu.m EW0226

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.02270 day LB0077 Labour 0.04730 day MT0325 Ballies 75 to 125mm dia 0.49940 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.02240 cu.m EW0227

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.03600 day LB0077 Labour 0.07200 day MT0325 Ballies 75 to 125mm dia 0.49940 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.02240 cu.m EW0235

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.22910 day MP0201 Water pump AVI type 0.03440 day EW0240

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.02300 day LB0077 Labour 0.23000 day MT0030 Aldrin Emulsifiable Concentrate 30% (for anti-termite treatment) 0.15000 litre

Close timbering including lagging & strutting of sh afts, wells, cess pits, manholes (per sq.m face are a timbered) - Depth not exceeding 1.5m

Close timbering over areas including lagging & stru tting of trenches, cuts ( per sq.m face area timber ed) - Depth not exceeding 1.5m

Close timbering over areas including lagging & stru tting of trenches, cuts ( per sq.m face area timber ed) - 1.5m < depth < 3m

Close timbering over areas including lagging & stru tting of trenches, cuts ( per sq.m face area timber ed) - 3m < depth < 4.5m

Close timbering including lagging & strutting of sh afts, wells, cess pits, manholes (per sq.m face are a timbered) - 1.5m < Depth < 3m

Close timbering including lagging & strutting of sh afts, wells, cess pits, manholes (per sq.m face are a timbered) - 3m < Depth < 4.5m

Pumping out water caused by springs, river, seepage , broken water mains, drains, and alike

Providing and injecting chemical emulsion for Pre-c onstruction anti-termite treatment using aldrin emu lsifiable 0.5% concentration

Department of Engineering Services, MoWHS

Page 19: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 16

EW0245

Coefficient for per m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.08100 day LB0077 Labour 0.74800 day MT0030 Aldrin Emulsifiable Concentrate 30% (for anti-termite treatment) 0.15000 litre EW0246

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.05750 day LB0039 Work Supervisor (Lajab) 0.05750 day LB0077 Labour 0.57500 day MT0030 Aldrin Emulsifiable Concentrate 30% (for anti-termite treatment) 0.02500 litre EW0247

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.05750 day LB0039 Work Supervisor (Lajab) 0.05750 day LB0077 Labour 1.15000 day MT0030 Aldrin Emulsifiable Concentrate 30% (for anti-termite treatment) 0.03300 litre EW0248

Coefficient for per m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.05750 day LB0077 Labour 0.74800 day MT0030 Aldrin Emulsifiable Concentrate 30% (for anti-termite treatment) 0.01600 litre EW0249

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.11500 day LB0039 Work Supervisor (Lajab) 0.05750 day LB0077 Labour 0.57500 day MT0030 Aldrin Emulsifiable Concentrate 30% (for anti-termite treatment) 0.00500 litre

Providing and injecting chemical emulsion for Post- construction, using aldrin emulsifiable 0.5% concen tration - Woodwork (using chemical in oil or kerosene based solution) including drilling & plugging 6mm holes

Providing and injecting chemical emulsion for Post- construction, using aldrin emulsifiable 0.5% concen tration - Along external walls below concrete/ masonry apron

Providing and injecting chemical emulsion for Post- construction, using aldrin emulsifiable 0.5% concen tration - Under existing floors including drilling & plugging 12mm holes with mortar 1:2

Providing and injecting chemical emulsion for Post- construction, using aldrin emulsifiable 0.5% concen tration - Voids in masonry including drilling holes at 45 degree & plu gging with cement mortar 1:2)

Providing and injecting chemical emulsion for Post- construction, using aldrin emulsifiable 0.5% concen tration - Along outside of foundation

Department of Engineering Services, MoWHS

Page 20: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 17

CHAPTER 4

DR0001

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.00313 day LB0039 Work Supervisor (Lajab) 0.00250 day LB0051 Mason Gd.2 0.03692 day LB0053 Plant Operator Gd.3 0.00350 day LB0077 Labour 0.41453 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00350 day MP0206 Concrete Vibrator(M/C5) 0.00350 day MT0043 Sand 0.02950 cu.m MT0070 Crushed Rock - 20mm 0.04700 cu.m MT0080 Gravel\Shingles (River stone) - 40mm to 20mm 0.07500 cu.m MT0145 Cement (OPC / PSC) 0.01100 tonne DR0002

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.00313 day LB0039 Work Supervisor (Lajab) 0.00250 day LB0051 Mason Gd.2 0.03692 day LB0053 Plant Operator Gd.3 0.00350 day LB0077 Labour 0.41452 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00350 day MP0206 Concrete Vibrator(M/C5) 0.00350 day MT0043 Sand 0.08350 cu.m MT0080 Gravel\Shingles (River stone) - 40mm to 20mm 0.00600 cu.m MT0081 Gravel\Shingles (River stone) - 20mm to 10mm 0.04700 cu.m MT0145 Cement (OPC / PSC) 0.01100 tonne DR0003

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.00319 day LB0039 Work Supervisor (Lajab) 0.00255 day LB0051 Mason Gd.2 0.03719 day LB0053 Plant Operator Gd.3 0.00357 day LB0077 Labour 0.41674 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00357 day MP0206 Concrete Vibrator(M/C5) 0.00357 day MT0043 Sand 0.02997 cu.m MT0070 Crushed Rock - 20mm 0.04794 cu.m MT0126 Brick aggregate 0.07500 cu.m MT0145 Cement (OPC / PSC) 0.01122 tonne DR0004

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.00319 day LB0039 Work Supervisor (Lajab) 0.00255 day LB0051 Mason Gd.2 0.03719 day LB0053 Plant Operator Gd.3 0.00357 day LB0077 Labour 0.41674 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00357 day MP0206 Concrete Vibrator(M/C5) 0.00357 day MT0043 Sand 0.02997 cu.m MT0081 Gravel\Shingles (River stone) - 20mm to 10mm 0.04794 cu.m MT0126 Brick aggregate 0.07500 cu.m MT0145 Cement (OPC / PSC) 0.01122 tonne

Providing and laying 50mm thick Plinth Protection and grouted with fine sand mix including well ramme d, finishing the top smooth - With cement concrete 1:3:6, 20mm aggregate s, laid over 75mm thick layer of compacted gravel ( 40mm)

DRAINAGE

Providing and laying 50mm thick Plinth Protection and grouted with fine sand mix including well ramme d, finishing the top smooth - With cement concrete 1:3:6, 20mm gravel or shingles laid over 75mm thick layer of compacted g ravel (40mm)

Providing and laying 50mm thick Plinth Protection and grouted with fine sand mix including well ramme d, finishing the top smooth - With cement concrete 1:3:6, 20mm aggregate , laid over 75mm thick layer of compacted dry brick aggregate (40mm)

Providing and laying 50mm thick Plinth Protection and grouted with fine sand mix including well ramme d, finishing the top smooth - With cement concrete 1:3:6, 20mm gravel or shingles laid on 75mm thick layer of compacted dry brick aggregate (40mm)

Department of Engineering Services, MoWHS

Page 21: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 18

DR0010

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.10608 day LB0039 Work Supervisor (Lajab) 0.00238 day LB0051 Mason Gd.2 0.01653 day LB0053 Plant Operator Gd.3 0.00333 day LB0077 Labour 0.37223 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00333 day MP0206 Concrete Vibrator(M/C5) 0.00333 day MT0043 Sand 0.04298 cu.m MT0068 Crushed Rock - 40mm 0.04005 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.00222 cu.m MT0125 Bricks 2nd class 0.01628 1000# MT0145 Cement (OPC / PSC) 0.01571 tonne DR0011

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.10803 day LB0039 Work Supervisor (Lajab) 0.00270 day LB0051 Mason Gd.2 0.01694 day LB0053 Plant Operator Gd.3 0.00378 day LB0077 Labour 0.39505 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00378 day MP0206 Concrete Vibrator(M/C5) 0.00378 day MT0043 Sand 0.04600 cu.m MT0068 Crushed Rock - 40mm 0.04450 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.00356 cu.m MT0125 Bricks 2nd class 0.01628 1000# MT0145 Cement (OPC / PSC) 0.01695 tonne DR0012

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.14527 day LB0039 Work Supervisor (Lajab) 0.00330 day LB0051 Mason Gd.2 0.02447 day LB0053 Plant Operator Gd.3 0.00462 day LB0077 Labour 0.54427 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00462 day MP0206 Concrete Vibrator(M/C5) 0.00462 day MT0043 Sand 0.06002 cu.m MT0068 Crushed Rock - 40mm 0.05340 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.00534 cu.m MT0125 Bricks 2nd class 0.02442 1000# MT0145 Cement (OPC / PSC) 0.02256 tonne DR0013

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.18437 day LB0039 Work Supervisor (Lajab) 0.00350 day LB0051 Mason Gd.2 0.09257 day LB0053 Plant Operator Gd.3 0.00490 day LB0077 Labour 0.71695 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00490 day MP0206 Concrete Vibrator(M/C5) 0.00490 day MT0043 Sand 0.07022 cu.m MT0068 Crushed Rock - 40mm 0.04005 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02225 cu.m MT0125 Bricks 2nd class 0.04680 1000# MT0145 Cement (OPC / PSC) 0.02740 tonne

Constructing second class brick masonry open surfac e drain in cement mortar 1:4 including earth work i n excavation 100 mm thick concrete bed 1:5:10, 40mm aggregate and 2 5mm thick cement concrete 1:2:4, 12 mm aggregate for filling haunches including 12mm cement plastering 1:4 with a floating coat of neat cement and disposal of surp lus earth etc. complete - 150mm x 200mm depth

Constructing second class brick masonry open surfac e drain in cement mortar 1:4 including earth work i n excavation 100 mm thick concrete bed 1:5:10, 40mm aggregate and 25mm thick cement concrete 1:2:4, 12 mm aggregate for filling haunches including 12mm cement plastering 1:4 with a floating coat of neat cement and disposal of surp lus earth etc. complete - 250mm x 300mm depth

Constructing second class brick masonry open surfac e drain in cement mortar 1:4 including earth work i n excavation 100 mm thick concrete bed 1:5:10, 40mm aggregate and 2 5mm thick cement concrete 1:2:4, 12 mm aggregate for filling haunches including 12mm cement plastering 1:4 with a floating coat of neat cement and disposal of surp lus earth etc. complete - 300mm x 450mm depth

Constructing second class brick masonry open surfac e drain in cement mortar 1:4 including earth work i n excavation 100 mm thick concrete bed 1:5:10, 40mm aggregate and 25mm thick cement concrete 1:2:4, 12 mm aggregate f or filling haunches including 12mm cement plastering 1:4 with a floating coat of neat cement and disposal of surp lus earth etc. complete - 100mm x 200mm depth

Department of Engineering Services, MoWHS

Page 22: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 19

DR0020

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.33380 day LB0051 Mason Gd.2 0.06780 day LB0077 Labour 0.98924 day MT0043 Sand 0.08432 cu.m MT0125 Bricks 2nd class 0.08140 1000# MT0145 Cement (OPC / PSC) 0.03434 tonne DR0021

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.33380 day LB0051 Mason Gd.2 0.06780 day LB0077 Labour 1.01280 day MT0043 Sand 0.08432 cu.m MT0125 Bricks 2nd class 0.08140 1000# MT0145 Cement (OPC / PSC) 0.03434 tonne DR0022

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.33380 day LB0051 Mason Gd.2 0.06780 day LB0077 Labour 1.05806 day MT0043 Sand 0.08432 cu.m MT0125 Bricks 2nd class 0.08140 1000# MT0145 Cement (OPC / PSC) 0.03434 tonne DR0030

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.17370 day LB0039 Work Supervisor (Lajab) 0.00363 day LB0051 Mason Gd.2 0.16510 day LB0053 Plant Operator Gd.3 0.00508 day LB0077 Labour 0.83233 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00508 day MP0206 Concrete Vibrator(M/C5) 0.00508 day MT0043 Sand 0.10040 cu.m MT0060 Boulder 0.12000 cu.m MT0068 Crushed Rock - 40mm 0.06230 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.00231 cu.m MT0145 Cement (OPC / PSC) 0.03084 tonne DR0031

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.17558 day LB0039 Work Supervisor (Lajab) 0.00395 day LB0051 Mason Gd.2 0.16549 day LB0053 Plant Operator Gd.3 0.00552 day LB0077 Labour 0.85464 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00552 day MP0206 Concrete Vibrator(M/C5) 0.00552 day MT0043 Sand 0.10333 cu.m MT0060 Boulder 0.12000 cu.m MT0068 Crushed Rock - 40mm 0.06675 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.00347 cu.m MT0145 Cement (OPC / PSC) 0.03202 tonne

Constructing random rubble masonry open surface dra in in cement mortar 1:6 including earth work in exc avation, 100mm thick concrete base 1:5:10, 40 mm aggregate 25mm th ick cement concrete 1:2:4, 12mm aggregate for fil ling haunches, including 20mm cement plaster with a floating coat of neat cement , disposal of surplus earth - 100 x 200mm depth

Extra, for additional depth of brick masonry drain - 250mm wide ........per metre additional depth

Extra, for additional depth of brick masonry drain - 100mm wide ........per metre additional depth

Extra, for additional depth of brick masonry drain - 150mm wide ........per metre additional depth

Constructing random rubble masonry open surface dra in in cement mortar 1:6 including earth work in exc avation, 100mm thick concrete base 1:5:10, 40 mm aggregate 25mm th ick cement concrete 1:2:4, 12mm aggregate for fil ling haunches, including 20mm cement plaster with a floating coat of neat cement , disposal of surplus earth - 150 x 200mm depth

Department of Engineering Services, MoWHS

Page 23: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 20

DR0032

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.21266 day LB0039 Work Supervisor (Lajab) 0.00457 day LB0051 Mason Gd.2 0.24655 day LB0053 Plant Operator Gd.3 0.00640 day LB0077 Labour 1.15009 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00640 day MP0206 Concrete Vibrator(M/C5) 0.00640 day MT0043 Sand 0.13512 cu.m MT0060 Boulder 0.18000 cu.m MT0068 Crushed Rock - 40mm 0.07565 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.00570 cu.m MT0145 Cement (OPC / PSC) 0.04145 tonne DR0033

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.09618 day LB0039 Work Supervisor (Lajab) 0.00350 day LB0051 Mason Gd.2 0.80718 day LB0053 Plant Operator Gd.3 0.00490 day LB0077 Labour 2.14301 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00490 day MP0206 Concrete Vibrator(M/C5) 0.00490 day MT0043 Sand 0.25800 cu.m MT0060 Boulder 0.60000 cu.m MT0068 Crushed Rock - 40mm 0.04005 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02225 cu.m MT0145 Cement (OPC / PSC) 0.06835 tonne DR0040

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.43160 day LB0051 Mason Gd.2 0.80280 day LB0077 Labour 2.58883 day MT0043 Sand 0.27418 cu.m MT0060 Boulder 0.60000 cu.m MT0145 Cement (OPC / PSC) 0.07735 tonne DR0041

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.43160 day LB0051 Mason Gd.2 0.80280 day LB0077 Labour 2.61177 day MT0043 Sand 0.27418 cu.m MT0060 Boulder 0.60000 cu.m MT0145 Cement (OPC / PSC) 0.07735 tonne DR0042 Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.43160 day LB0051 Mason Gd.2 0.80280 day LB0077 Labour 2.65765 day MT0043 Sand 0.27418 cu.m MT0060 Boulder 0.60000 cu.m MT0145 Cement (OPC / PSC) 0.07735 tonne

12mm aggregate for filling haunches, including 20mm cement plaster with a floating coat of neat cement , disposal of surplus earth - 250 x 300mm depth

Constructing random rubble masonry open surface dra in in cement mortar 1:6 including earth work in exc avation, 100mm thick concrete base 1:5:10, 40 mm aggregate 25mm th ick cement concrete 1:2:4,

Constructing random rubble masonry open surface dra in in cement mortar 1:6 including earth work in exc avation, 100mm thick concrete base 1:5:10, 40 mm aggregate 25mm th ick cement concrete 1:2:4,

Extra, for additional depth of random rubble masonr y drain - 100mm wide ........per metre additional d epth

12mm aggregate for filling haunches, including 20mm cement plaster with a floating coat of neat cement , disposal of surplus earth - 300mm x 450mm depth

Extra, for additional depth of random rubble masonr y drain - 150mm wide ........per metre additional d epth

Extra, for additional depth of random rubble masonr y drain - 250mm wide ........per metre additional d epth

Department of Engineering Services, MoWHS

Page 24: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 21

DR0047

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.04200 day LB0051 Mason Gd.2 0.04200 day LB0077 Labour 0.16670 day MT0043 Sand 0.00117 cu.m MT0145 Cement (OPC / PSC) 0.00057 tonne MT0795 Stoneware pipes 60 cm long - 100mm dia 1.83000 each DR0048

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.06300 day LB0051 Mason Gd.2 0.06300 day LB0077 Labour 0.20830 day MT0043 Sand 0.00175 cu.m MT0145 Cement (OPC / PSC) 0.00083 tonne MT0796 Stoneware pipes 60 cm long - 150mm dia 1.83000 each DR0049

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.07300 day LB0051 Mason Gd.2 0.07300 day LB0077 Labour 0.24000 day MT0043 Sand 0.00233 cu.m MT0145 Cement (OPC / PSC) 0.00110 tonne MT0797 Stoneware pipes 60 cm long - 200mm dia 1.83000 each DR0050

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.04200 day LB0051 Mason Gd.2 0.04200 day LB0077 Labour 0.16670 day MT0043 Sand 0.00127 cu.m MT0145 Cement (OPC / PSC) 0.00167 tonne MT0795 Stoneware pipes 60 cm long - 100mm dia 1.83000 each

DR0051

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.06300 day LB0051 Mason Gd.2 0.06300 day LB0077 Labour 0.20830 day MT0043 Sand 0.00175 cu.m MT0145 Cement (OPC / PSC) 0.00250 tonne MT0796 Stoneware pipes 60 cm long - 150mm dia 1.83000 each DR0052

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.07300 day LB0051 Mason Gd.2 0.07300 day LB0077 Labour 0.24000 day MT0043 Sand 0.00233 cu.m MT0145 Cement (OPC / PSC) 0.00330 tonne MT0797 Stoneware pipes 60 cm long - 200mm dia 1.83000 each

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 sand) including testing of joints complete - 200mm dia.

Providing, laying and jointing glazed Stoneware pi pes with stiff mixture of cement mortar 1:3 (1 ceme nt : 3 Sand) including testing of joints complete - 100mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1: 3 (1 ce ment : 3 Sand) including testing of joints complete - 150mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:3 (1 cem ent : 3 sand) including testing of joints complete - 200mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 Sand) including testing of joints complete - 100 mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 Sand) including testing of joints complete - 150mm dia.

Department of Engineering Services, MoWHS

Page 25: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 22

DR0053

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.08000 day LB0051 Mason Gd.2 0.08000 day LB0077 Labour 0.28000 day MT0043 Sand 0.00267 cu.m MT0145 Cement (OPC / PSC) 0.03750 tonne MT0778 Stoneware pipes 60 cm long - 230mm dia 1.83000 each

DR0054

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.08500 day LB0051 Mason Gd.2 0.08500 day LB0077 Labour 0.30000 day MT0043 Sand 0.00292 cu.m MT0145 Cement (OPC / PSC) 0.00417 tonne MT0779 Stoneware pipes 60 cm long - 250mm dia 1.83000 each

DR0055

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.09200 day LB0051 Mason Gd.2 0.09200 day LB0077 Labour 0.35000 day MT0043 Sand 0.00380 cu.m MT0145 Cement (OPC / PSC) 0.00542 tonne MT0780 Stoneware pipes 60 cm long - 300mm dia 1.83000 each

DR0056

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.10000 day LB0051 Mason Gd.2 0.10000 day LB0077 Labour 0.40000 day MT0043 Sand 0.00533 cu.m MT0145 Cement (OPC / PSC) 0.00750 tonne MT0781 Stoneware pipes 60 cm long - 350mm dia 1.83000 each

DR0057

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.11000 day LB0051 Mason Gd.2 0.11000 day LB0077 Labour 0.44000 day MT0043 Sand 0.00633 cu.m MT0145 Cement (OPC / PSC) 0.00917 tonne MT0782 Stoneware pipes 60 cm long - 400mm dia 1.83000 each

DR0058

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.12000 day LB0051 Mason Gd.2 0.12000 day LB0077 Labour 0.50000 day MT0043 Sand 0.00700 cu.m MT0145 Cement (OPC / PSC) 0.01000 tonne MT0793 Stoneware pipes 60 cm long - 500mm dia 1.83000 each

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 sand) including testing of joints complete - 230mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 sand) including testing of joints complete - 400 mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 sand) including testing of joints complete - 300mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 sand) including testing of joints complete - 250mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 sand) including testing of joints complete - 500 mm dia.

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 sand) including testing of joints complete - 350 mm dia.

Department of Engineering Services, MoWHS

Page 26: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 23

DR0059

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.13000 day LB0051 Mason Gd.2 0.13000 day LB0077 Labour 0.55000 day MT0043 Sand 0.00800 cu.m MT0145 Cement (OPC / PSC) 0.01133 tonne MT0794 Stoneware pipes 60 cm long - 600mm dia 1.83000 each

DR0060

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.01137 day LB0039 Work Supervisor (Lajab) 0.00910 day LB0051 Mason Gd.2 0.01137 day LB0053 Plant Operator Gd.3 0.01274 day LB0077 Labour 0.40268 day MP0205 Concrete Mixer(7/5 cu.ft) 0.01274 day MP0206 Concrete Vibrator(M/C5) 0.01274 day MT0043 Sand 0.08554 cu.m MT0068 Crushed Rock - 40mm 0.16198 cu.m MT0145 Cement (OPC / PSC) 0.02384 tonne DR0061

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.01219 day LB0039 Work Supervisor (Lajab) 0.00975 day LB0051 Mason Gd.2 0.01219 day LB0053 Plant Operator Gd.3 0.01365 day LB0077 Labour 0.43144 day MP0205 Concrete Mixer(7/5 cu.ft) 0.01365 day MP0206 Concrete Vibrator(M/C5) 0.01365 day MT0043 Sand 0.09165 cu.m MT0068 Crushed Rock - 40mm 0.17355 cu.m MT0145 Cement (OPC / PSC) 0.02554 tonne DR0062

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.01400 day LB0039 Work Supervisor (Lajab) 0.01120 day LB0051 Mason Gd.2 0.01400 day LB0053 Plant Operator Gd.3 0.01568 day LB0077 Labour 0.49560 day MP0205 Concrete Mixer(7/5 cu.ft) 0.01568 day MP0206 Concrete Vibrator(M/C5) 0.01568 day MT0043 Sand 0.10528 cu.m MT0068 Crushed Rock - 40mm 0.19936 cu.m MT0145 Cement (OPC / PSC) 0.02934 tonne DR0070

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.00763 day LB0039 Work Supervisor (Lajab) 0.00610 day LB0051 Mason Gd.2 0.00763 day LB0053 Plant Operator Gd.3 0.00854 day LB0077 Labour 0.26992 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00854 day MP0206 Concrete Vibrator(M/C5) 0.00854 day MT0043 Sand 0.05734 cu.m MT0068 Crushed Rock - 40mm 0.10858 cu.m MT0145 Cement (OPC / PSC) 0.01598 tonne

P&L cement concrete 1:5:10, 40mm aggregates upto ha unches of S.W pipes including 150mm concrete bed - 100mm dia. S.W pipe

Providing, laying and jointing glazed Stone Ware p ipes with stiff mixture of cement mortar 1:1 (1 cem ent : 1 sand) including testing of joints complete - 600 mm dia.

Providing and laying cement concrete 1:5:10, 40mm a ggregates encasing Stone Ware pipes including 150mm concrete bed - 100mm dia. S.W pipe

Providing and laying cement concrete 1:5:10, 40mm a ggregates encasing Stone Ware pipes including 150mm concrete bed - 150mm dia. S.W pipe

Providing and laying cement concrete 1:5:10, 40mm a ggregates encasing Stone Ware pipes including 150mm concrete bed - 200mm dia. S.W pipe

Department of Engineering Services, MoWHS

Page 27: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 24

DR0071

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.00838 day LB0039 Work Supervisor (Lajab) 0.00670 day LB0051 Mason Gd.2 0.00838 day LB0053 Plant Operator Gd.3 0.00938 day LB0077 Labour 0.29648 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00938 day MP0206 Concrete Vibrator(M/C5) 0.00938 day MT0043 Sand 0.06298 cu.m MT0068 Crushed Rock - 40mm 0.11926 cu.m MT0145 Cement (OPC / PSC) 0.01755 tonne DR0072

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.00975 day LB0039 Work Supervisor (Lajab) 0.00780 day LB0051 Mason Gd.2 0.00975 day LB0053 Plant Operator Gd.3 0.01092 day LB0077 Labour 0.34515 day MP0205 Concrete Mixer(7/5 cu.ft) 0.01092 day MP0206 Concrete Vibrator(M/C5) 0.01092 day MT0043 Sand 0.07332 cu.m MT0068 Crushed Rock - 40mm 0.13884 cu.m MT0145 Cement (OPC / PSC) 0.02044 tonne DR0080

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.08123 day LB0039 Work Supervisor (Lajab) 0.00430 day LB0051 Mason Gd.2 0.04266 day LB0053 Plant Operator Gd.3 0.00602 day LB0077 Labour 0.44884 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00602 day MP0206 Concrete Vibrator(M/C5) 0.00602 day MT0043 Sand 0.07416 cu.m MT0068 Crushed Rock - 40mm 0.07120 cu.m MT0070 Crushed Rock - 20mm 0.00534 cu.m MT0125 Bricks 2nd class 0.04477 1000# MT0145 Cement (OPC / PSC) 0.02370 tonne

MT0750Watertight C.I. Manhole Cover with frame, 300 x 300mm inside size Wt. of cover not less than 4.53 kg, wt. of frame not less than 2.72 kg 1.00000 each

MT0766 Cast Iron - Grating 1.00000 each MT0800 S/W trap - P Type - 100 x 100mm 1.00000 each DR0081

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.11485 day LB0039 Work Supervisor (Lajab) 0.00030 day LB0051 Mason Gd.2 0.07496 day LB0053 Plant Operator Gd.3 0.00042 day LB0077 Labour 0.47939 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00042 day MP0206 Concrete Vibrator(M/C5) 0.00042 day MT0043 Sand 0.06614 cu.m MT0070 Crushed Rock - 20mm 0.00534 cu.m MT0125 Bricks 2nd class 0.08954 1000# MT0145 Cement (OPC / PSC) 0.02184 tonne

MT0750 Watertight C.I. Manhole Cover with frame, 300 x 300mm inside size Wt. of cover

not less than 4.53 kg wt. of frame not less than 2.72 kg1.00000 each

MT0766 Cast Iron - Grating 1.00000 each MT0801 S\W trap - P Type - 150 x 100mm 1.00000 each

Providing & fixing square mouth S.W gully-trap A-gr ade including C.I grating, C.I. cover with frame of 300 x 300 mm, brick masonry chamber - 100 x 100mm P Type

P&L cement concrete 1:5:10, 40mm aggregates upto ha unches of S.W pipes including 150mm concrete bed - 200mm dia. S.W pipe

P&L cement concrete 1:5:10, 40mm aggregates upto ha unches of S.W pipes including 150mm concrete bed - 150mm dia. S.W pipe

Providing & fixing square mouth S.W gully-trap A-gr ade including C.I grating, C.I. cover with frame of 300 x 300 mm, brick masonry chamber - 150 x 100mm P or S Type

Department of Engineering Services, MoWHS

Page 28: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 25

DR0082

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.06732 day LB0039 Work Supervisor (Lajab) 0.00700 day LB0051 Mason Gd.2 0.04604 day LB0053 Plant Operator Gd.3 0.00980 day LB0077 Labour 0.54463 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00980 day MP0206 Concrete Vibrator(M/C5) 0.00980 day MT0043 Sand 0.09619 cu.m MT0068 Crushed Rock - 40mm 0.07120 cu.m MT0070 Crushed Rock - 20mm 0.05340 cu.m MT0125 Bricks 2nd class 0.04477 1000# MT0145 Cement (OPC / PSC) 0.03981 tonne

MT0750 Watertight C.I. Manhole Cover with frame, 300 x 300mm inside size Wt. of cover

not less than 4.53 kg wt. of frame not less than 2.72 kg1.00000 each

MT0766 Cast Iron - Grating 1.00000 each MT0802 SW trap - P Type - 180 x 150mm 1.00000 each

DR0088

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.02250 day LB0051 Mason Gd.2 0.02250 day LB0077 Labour 0.09000 day MT0043 Sand 0.00065 cu.m MT0145 Cement (OPC / PSC) 0.00470 tonne MT0768 NP2 class - 100mm dia 1.00000 m MT0783 NP2 Class Collar - 100mm dia 0.40000 each

DR0089

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.02750 day LB0051 Mason Gd.2 0.02750 day LB0077 Labour 0.10000 day MT0043 Sand 0.00080 cu.m MT0145 Cement (OPC / PSC) 0.00580 tonne MT0769 NP2 class - 150mm dia 1.00000 m MT0784 NP2 Class Collar - 150mm dia 0.40000 each DR0090

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.06750 day LB0051 Mason Gd.2 0.06750 day LB0077 Labour 0.21630 day MT0043 Sand 0.00120 cu.m MT0145 Cement (OPC / PSC) 0.00090 tonne MT0770 NP2 class - 225mm dia 1.00000 m MT0785 NP2 Class Collar - 225mm dia 0.50000 each DR0091

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.07400 day LB0051 Mason Gd.2 0.07400 day LB0077 Labour 0.17000 day MT0043 Sand 0.00150 cu.m MT0145 Cement (OPC / PSC) 0.00110 tonne MT0771 NP2 class - 300mm dia 1.00000 m MT0786 NP2 Class Collar - 300mm dia 0.40000 each

Providing & fixing square mouth S.W gully-trap A-gr ade including C.I grating, C.I. cover with frame of 300 x 300 mm, brick masonry chamber - 180 x 150mm P or S Type

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 100mm dia.

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 150mm dia.

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 225mm dia.

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 300mm dia.

Department of Engineering Services, MoWHS

Page 29: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 26

DR0092

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.09400 day LB0051 Mason Gd.2 0.09400 day LB0077 Labour 0.22880 day MT0043 Sand 0.00330 cu.m MT0145 Cement (OPC / PSC) 0.00240 tonne MT0772 NP2 class - 450mm dia 1.00000 m MT0787 NP2 Class Collar - 450mm dia 0.40000 each DR0093

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.11500 day LB0051 Mason Gd.2 0.11500 day LB0077 Labour 0.27000 day MT0043 Sand 0.00430 cu.m MT0145 Cement (OPC / PSC) 0.00320 tonne MT0773 NP2 class - 600mm dia 1.00000 m MT0788 NP2 Class Collar - 600mm dia 0.40000 each DR0094

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.10200 day LB0051 Mason Gd.2 0.10200 day LB0077 Labour 0.35000 day MT0043 Sand 0.00360 cu.m MT0145 Cement (OPC / PSC) 0.00260 tonne MT0774 NP2 class - 750mm dia 1.00000 m MT0789 NP2 Class Collar - 750mm dia 0.40000 each DR0095

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.15600 day LB0051 Mason Gd.2 0.15600 day LB0077 Labour 0.43750 day MT0043 Sand 0.00660 cu.m MT0145 Cement (OPC / PSC) 0.00500 tonne MT0775 NP2 class - 900mm dia 1.00000 m MT0790 NP2 Class Collar - 900mm dia 0.40000 each DR0096

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.04000 day LB0051 Mason Gd.2 0.04000 day LB0077 Labour 0.09800 day MT0043 Sand 0.00060 cu.m MT0145 Cement (OPC / PSC) 0.00050 tonne MT0776 NP2 class - 1050mm dia 1.00000 m MT0791 NP2 Class Collar - 1050mm dia 0.50000 each DR0097

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.04900 day LB0051 Mason Gd.2 0.04900 day LB0077 Labour 0.50000 day MT0043 Sand 0.00080 cu.m MT0145 Cement (OPC / PSC) 0.00060 tonne MT0777 NP2 class - 1200mm dia 1.00000 m MT0792 NP2 Class Collar - 1200mm dia 0.50000 each

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 900mm dia

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 1050mm dia.

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 1200mm dia.

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 450mm dia.

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 600mm dia.

P&L NP2 class R.C pipes, including collars, jointin g in cement mortar 1:2 including testing of joints etc. complete - 750mm dia.

Department of Engineering Services, MoWHS

Page 30: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 27

DR0105

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.11413 day LB0033 Carpenter Gd.2 0.24640 day LB0036 Mason Gd.1 0.26231 day LB0039 Work Supervisor (Lajab) 0.04650 day LB0051 Mason Gd.2 0.22906 day LB0053 Plant Operator Gd.3 0.05180 day LB0077 Labour 2.84746 day MP0205 Concrete Mixer(7/5 cu.ft) 0.05180 day MP0206 Concrete Vibrator(M/C5) 0.05180 day MT0043 Sand 0.42048 cu.m MT0068 Crushed Rock - 40mm 0.34710 cu.m MT0070 Crushed Rock - 20mm 0.31150 cu.m MT0125 Bricks 2nd class 0.11803 1000# MT0145 Cement (OPC / PSC) 0.20362 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 9.58650 kg MT0325 Ballies 75 to 125mm dia 0.91300 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00739 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

1.00000 each

DR0106

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.11413 day LB0033 Carpenter Gd.2 0.06864 day LB0036 Mason Gd.1 0.37082 day LB0039 Work Supervisor (Lajab) 0.04650 day LB0051 Mason Gd.2 0.26974 day LB0053 Plant Operator Gd.3 0.05180 day LB0077 Labour 3.05056 day MP0205 Concrete Mixer(7/5 cu.ft) 0.05180 day MP0206 Concrete Vibrator(M/C5) 0.05180 day MT0043 Sand 0.46044 cu.m MT0068 Crushed Rock - 40mm 0.34710 cu.m MT0070 Crushed Rock - 20mm 0.31150 cu.m MT0125 Bricks 2nd class 0.16687 1000# MT0145 Cement (OPC / PSC) 0.21778 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 9.58650 kg MT0325 Ballies 75 to 125mm dia 0.18480 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00594 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

1.00000 each

Constructing Brick masonry manhole in cement mortar 1:5, R.C.C top slab with 1:2:4 20mm aggregates, fo undation concrete 1:4:8 40mm aggregates, 12mm plaster in CM 1:3 finished with floating coat of neat cement and making channels in cement concrete 1:2:4 20mm aggregates, neatly fi nished complete - Inside dimension 900 x 800mm & 60 0mm deep including C.I. cover & frame (weight >38kg.)

Constructing Brick masonry manhole in cement mortar 1:5, R.C.C top slab with 1:2:4 20mm aggregates, fo undation concrete 1:4:8 40mm aggregates, 12mm plaster in CM 1:3 finished with floating coat of neat cement and making channels in cement concrete 1:2:4 20mm aggregates, neatly fi nished complete - Inside dimension 900 x 800mm & 45 0mm deep including C.I. cover & frame (weight >38kg.)

Department of Engineering Services, MoWHS

Page 31: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 28

DR0107

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.28325 day LB0033 Carpenter Gd.2 0.13728 day LB0036 Mason Gd.1 0.73808 day LB0039 Work Supervisor (Lajab) 0.06600 day LB0051 Mason Gd.2 0.44681 day LB0053 Plant Operator Gd.3 0.07280 day LB0077 Labour 5.27458 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07280 day MP0206 Concrete Vibrator(M/C5) 0.07280 day MT0043 Sand 0.72062 cu.m MT0068 Crushed Rock - 40mm 0.45390 cu.m MT0070 Crushed Rock - 20mm 0.47170 cu.m MT0125 Bricks 2nd class 0.32153 1000# MT0145 Cement (OPC / PSC) 0.33912 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 23.79300 kg MT0325 Ballies 75 to 125mm dia 0.36960 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01188 cu.m

MT0752 C.I. manhole cover and frame (medium duty) 500mm internal dia. Total weight of cover and frame not less than 116 kg. (cover 58 kg. and frame 58 kg)

1.00000 each

DR0115

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.73696 day LB0051 Mason Gd.2 0.28476 day LB0077 Labour 2.19049 day MT0043 Sand 0.27709 cu.m MT0125 Bricks 2nd class 0.34188 1000# MT0145 Cement (OPC / PSC) 0.09755 tonne DR0116

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.89760 day LB0051 Mason Gd.2 0.33900 day LB0077 Labour 2.63549 day MT0043 Sand 0.33221 cu.m MT0125 Bricks 2nd class 0.40700 1000# MT0145 Cement (OPC / PSC) 0.11758 tonne

Constructing Brick masonry manhole in cement mortar 1:5, R.C.C top slab with 1:2:4 20mm aggregates, fo undation concrete 1:4:8 40mm aggregates, 12mm plaster in CM 1:3 finished with floating coat of neat cement and making channels in cement concrete 1:2:4 20mm aggregates, neatly fi nished complete - Inside dimension 1200 x 900mm & 9 00mm deep including C.I. cover & frame (weight >116kg.)

Extra, for additional depth of manholes - 900 x 800 mm

Extra, for additional depth of manholes - 1200 x 90 0mm

Department of Engineering Services, MoWHS

Page 32: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 29

CHAPTER 5

MR0001 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.12500 day MT0043 Sand 0.71250 cu.m MT0145 Cement (OPC / PSC) 1.02000 tonne MR0002 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.12500 day MT0043 Sand 0.95000 cu.m MT0145 Cement (OPC / PSC) 0.68000 tonne MR0003 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.12500 day MT0043 Sand 1.07000 cu.m MT0145 Cement (OPC / PSC) 0.51000 tonne MR0004 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.12500 day MT0043 Sand 1.07000 cu.m MT0145 Cement (OPC / PSC) 0.38000 tonne MR0005 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.12500 day MT0043 Sand 1.07000 cu.m MT0145 Cement (OPC / PSC) 0.31000 tonne MR0006 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.12500 day MT0043 Sand 1.07000 cu.m MT0145 Cement (OPC / PSC) 0.25000 tonne MR0010 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.68750 day MT0120 Slaked lime 270.00000 kg MT0127 Graded brick aggregate 0.95000 cu.m

MR0011Coefficient for per cu.m

Code Description Quant UnitsLB0077 Labour 1.45000 dayMT0121 Unslaked lime 301.00000 kgMT0127 Graded brick aggregate 0.47500 cu.mMT0043 Sand 0.47500 cu.m

MR0015 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.13750 day MT0042 Mud dry 1.20000 cu.m

Cement mortar 1:1 (1 cement : 1 sand)

MORTARS

Cement mortar 1:2 (1 cement : 2 sand)

Cement mortar 1:3 (1 cement : 3 sand)

Cement mortar 1:4 (1 cement : 4 sand)

Cement mortar 1:5 (1 cement : 5 sand)

Cement mortar 1:6 (1 cement : 6 sand)

Lime mortar 1:2 (1 lime putty : 2 Brick Powder)

Lime Mortar 1:1 :1 (1 Lime putty : 1 Brick Powder : 1 Sand)

Mud mortar

Department of Engineering Services, MoWHS

Page 33: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 30

MR0020 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.95000 day MT0146 White Cement 0.68400 tonne

MT0043 sand 0.95000 cu.m

MR0021 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.95000 day MT0146 White Cement 0.51000 tonne

MT0043 sand 1.07000 cu.m

MR0022 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.95000 day MT0146 White Cement 0.31000 tonne

MT0043 sand 1.07000 cu.m

MR0025 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.40000 day MT0145 Cement 0.41000 tonne

MT0043 sand 0.86000 cu.mMT0121 unslaked lime 181.00000 kg

MR0026 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.40000 day MT0145 Cement 0.25000 tonne

MT0043 sand 1.07000 cu.mMT0121 unslaked lime 113.00000 kg

White Cement mortar 1:3 (1 white cement : 3 sand)

White Cement mortar 1:5 (1 white cement : 5 sand)

Cement lime mortar 1:1:3 (1 cement : 1 lime putty : 3 sand)

Cement lime mortar 1:1:6 (1 cement : 1 lime putty : 3 sand)

White Cement mortar 1:2 (1 white cement : 2 sand)

Department of Engineering Services, MoWHS

Page 34: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 31

CHAPTER 6

CW0001

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.57500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20 mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5 mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne CW0002

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.57500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20 mm 0.66150 cu.m

MT0071 Crushed Rock - 12.5 mm - 6 mm 0.22050 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

CW0003

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.57500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20 mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5 mm - 6 mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

CW0004

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.80500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m

MT0068 Crushed Rock - 40 mm 0.54400 cu.m MT0070 Crushed Rock - 20 mm 0.24100 cu.m

MT0071 Crushed Rock - 12.5 mm- 6 mm 0.12600 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

Providing and laying in position plain cement concr ete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

Providing and laying in position plain cement concr ete 1:2:4 (1 cement : 2 sand : 4 crushed rock 20 mm nominal size) excluding the cost of centering and shuttering - A ll work upto plinth level.

Providing and laying in position plain cement concr ete 1:1:2 (1 cement : 1 sand : 2 graded crushed roc k 20 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

CONCRETE WORK

Providing and laying in position plain cement concr ete 1:2:4 (1 cement : 2 sand : 4 graded crushed roc k 40 mm nominal size) excluding the cost of centering and shutteri ng - All work upto plinth level.

Department of Engineering Services, MoWHS

Page 35: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 32

CW0005

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.80500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.48500 cu.m MT0070 Crushed Rock - 20 mm 0.72700 cu.m

MT0071 Crushed Rock - 12.5 mm - 6 mm 0.24200 cu.m MT0145 Cement (OPC / PSC) 0.22000 tonne

CW0006

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.80500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.48500 cu.m

MT0068 Crushed Rock - 40 mm 0.67200 cu.m MT0070 Crushed Rock - 20 mm 0.26200 cu.m MT0145 Cement (OPC / PSC) 0.22000 tonne

CW0007

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.80500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.48500 cu.m MT0080 Gravel/Shingles ( river stone) 40 mm to 20 mm 0.67200 cu.m

MT0081 Gravel/Shingles ( river stone) 20 mm to 10 mm 0.26200 cu.m MT0145 Cement (OPC / PSC) 0.22000 tonne

CW0008

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.42500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.50000 cu.m MT0068 Crushed rock 40 mm 0.68830 cu.m

MT0070 Crushed rock 20 mm 0.27500 cu.m MT0145 Cement (OPC / PSC) 0.17000 tonne

Providing and laying in position plain cement concr ete 1:3:6 (1 cement : 3 sand : 6 graded crushed roc k 20 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

Providing and laying in position plain cement concr ete 1:3:6 (1 cement : 3 sand : 6 graded crushed roc k 40 mm nominal size) excluding the cost of centering and shutteri ng - All work upto plinth level.

Providing and laying in position plain cement concr ete 1:3:6 (1 cement : 3 sand : 6 graded gravel/shin gles 40 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

Providing and laying in position plain cement concr ete 1:4:8 (1 cement : 4 sand : 8 graded crushed sto ne 40 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

Department of Engineering Services, MoWHS

Page 36: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 33

CW0009

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.42500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.50000 cu.m MT0067 Crushed rock 50 mm 0.68830 cu.m

MT0070 Crushed rock 20 mm 0.27500 cu.m MT0145 Cement (OPC / PSC) 0.17000 tonne

CW0010

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.42500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.50000 cu.m MT0080 Gravel/Shingles ( river stone) 40 mm to 20 mm 0.68830 cu.m

MT0081 Gravel/Shingles ( river stone) 20 mm to 10 mm 0.27500 cu.m MT0145 Cement (OPC / PSC) 0.17000 tonne

CW0011

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.42500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47500 cu.m MT0068 Crushed rock 40 mm 0.66230 cu.m

MT0070 Crushed rock 20 mm 0.25830 cu.m MT0145 Cement (OPC / PSC) 0.13100 tonne

CW0012

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.37500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47500 cu.m MT0067 Crushed rock 50 mm 0.66230 cu.m

MT0070 Crushed rock 20 mm 0.25830 cu.m MT0145 Cement (OPC / PSC) 0.13100 tonne

Providing and laying in position plain cement concr ete 1:4:8 (1 cement : 4 sand : 8 graded gravel/shin gles 40 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

Providing and laying in position plain cement concr ete 1:5:10 (1 cement : 5 sand : 10 graded crushed s tone 40 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

Providing and laying in position plain cement concr ete 1:5:10 (1 cement : 5 sand : 10 graded crushed s tone 50 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

Providing and laying in position plain cement concr ete 1:4:8 (1 cement : 4 sand : 8 graded crushed sto ne 50 mm nominal size) excluding the cost of centering and shutterin g - All work upto plinth level.

Department of Engineering Services, MoWHS

Page 37: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 34

CW0013

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.06250 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.06250 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.37500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47500 cu.m MT0080 Gravel/Shingles ( river stone) 40 mm to 20 mm 0.66230 cu.m

MT0081 Gravel/Shingles ( river stone) 20 mm to 10 mm 0.25830 cu.m MT0145 Cement (OPC / PSC) 0.13100 tonne

CW0020

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.09000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.09000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.70500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20 mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5 mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne CW0021

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.09000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.09000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.70500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20 mm 0.66200 cu.m

MT0071 Crushed Rock - 12.5 mm - 6mm 0.22100 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

CW0022

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.09000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.09000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.70500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20 mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5 mm - 6mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

Providing and laying in position plain cement concr ete 1:5:10 (1 cement : 5 sand : 10 graded gravel/sh ingles 40 mm nominal size) excluding the cost of centering and s huttering - All work upto plinth level.

Providing and laying in position plain cement concr ete 1:1:2 (1 cement : 1 sand : 2 graded crushed roc k 20 mm nominal size) in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses , parapets, coping, bed blocks, anchor blocks, plai n window sills, fillets etc. upto floor five level, excluding the cost of c entering and shuttering

Providing and laying in position plain cement concr ete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses , parapets, coping, bed blocks, anchor blocks, plai n window sills, fillets etc. upto floor five level, excluding the cost of c entering and shuttering

Providing and laying in position plain cement concr ete 1:2:4 (1 cement : 2 sand : 4 graded crushed roc k 20 mm nominal size) in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses , parapets, coping, bed blocks, anchor blocks, plai n window sills, fillets etc. upto floor five level, excluding the cost of c entering and shuttering

Department of Engineering Services, MoWHS

Page 38: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 35

CW0023

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.09000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.09000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.70500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0068 Crushed Rock - 40 mm 0.54400 cu.m

MT0070 Crushed Rock - 20 mm 0.24100 cu.mMT0071 Crushed Rock - 12.5 mm - 6mm 0.12500 cu.m

MT0145 Cement (OPC / PSC) 0.32130 tonne CW0024

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.09000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.09000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.70500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.48500 cu.m

MT0070 Crushed Rock - 20 mm 0.72700 cu.mMT0071 Crushed Rock - 12.5 mm - 6mm 0.24200 cu.m

MT0145 Cement (OPC / PSC) 0.22000 tonne

CW0025

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.09000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.09000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.70500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.48500 cu.m

MT0068 Crushed Rock - 40 mm 0.67200 cu.mMT0070 Crushed Rock - 20 mm 0.26200 cu.m

MT0145 Cement (OPC / PSC) 0.22000 tonne

Providing and laying in position plain cement concr ete 1:3:6 (1 cement : 3 sand : 6 graded crushed roc k 20 mm nominal size) in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses , parapets, coping, bed blocks, anchor blocks, plai n window sills, fillets etc. upto floor five level, excluding the cost of c entering and shuttering

Providing and laying in position plain cement concr ete 1:3:6 (1 cement : 3 sand : 6 graded crushed roc k 40 mm nominal size) in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses , parapets, coping, bed blocks, anchor blocks, plai n window sills, fillets etc. upto floor five level, excluding the cost of c entering and shuttering

Providing and laying in position plain cement concr ete 1:2:4 (1 cement : 2 sand : 4 graded crushed roc k 40 mm nominal size) in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses , parapets, coping, bed blocks, anchor blocks, plai n window sills, fillets etc. upto floor five level, excluding the cost of c entering and shuttering

Department of Engineering Services, MoWHS

Page 39: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 36

CW0026

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.09000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.09000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.70500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.48500 cu.m

MT0080 Gravel/Shingles ( river stone) 40 mm to 20 mm 0.67200 cu.mMT0081 Gravel/Shingles ( river stone) 20 mm to 10 mm 0.26200 cu.m

MT0145 Cement (OPC / PSC) 0.22000 tonne

CW0050

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.05000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 5.49000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.50670 cu.m

MT0070 Crushed Rock - 20 mm 0.70500 cu.mMT0071 Crushed Rock - 12.5 mm - 6mm 0.23500 cu.m

MT0145 Cement (OPC / PSC) 0.38000 tonne

CW0051

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.05000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 5.49000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.61170 cu.m

MT0070 Crushed Rock - 20 mm 0.72700 cu.mMT0071 Crushed Rock - 12.5 mm - 6mm 0.24200 cu.m

MT0145 Cement (OPC / PSC) 0.28000 tonne

Providing and laying in position plain cement concr ete 1:3:6 (1 cement : 3 sand : 6 graded gravel/shin gles 40 mm nominal size) in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers,

abutments, pillars, posts, struts, buttresses, stri ng or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets etc. upto floor five level, e xcluding the cost of centering and shuttering

Providing and fixing upto floor five level pre-cast cement concrete lacing courses, copings, bed plate s, anchor blocks, plain window sills, shelves, louvers, steps, staircases e tc. including hoisting and setting in position with

cement mortar 1:3 (1 cement : 3 sand) cost of requi red formwork and finishing smooth with 6 mm thick c ement plaster on exposed surface complete - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size)

Providing and fixing upto floor five level pre-cast cement concrete lacing courses, copings, bed plate s, anchor blocks, plain window sills, shelves, louvers, steps, staircases e tc. including hoisting and setting in position with

cement mortar 1:3 (1 cement : 3 sand) cost of requi red formwork and finishing smooth with 6 mm thick c ement plaster on exposed surface complete - 1:3:6 (1 cement : 3 sand : 6 graded crushed rock 20 mm nominal size)

Department of Engineering Services, MoWHS

Page 40: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 37

CW0060

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.35000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.35000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.17500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.55820 cu.m

MT0070 Crushed Rock - 20 mm 0.70500 cu.mMT0071 Crushed Rock - 12.5 mm - 6 mm 0.23500 cu.m

MT0145 Cement (OPC / PSC) 0.36200 tonne

CW0070

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.37500 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.37500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.67500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.66530 cu.m

MT0070 Crushed Rock - 20 mm 0.70500 cu.mMT0071 Crushed Rock - 12.5 mm - 6mm 0.23500 cu.m

MT0145 Cement (OPC / PSC) 0.41300 tonne

CW0071

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.37500 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.37500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.67500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.68030 cu.m

MT0070 Crushed Rock - 20 mm 0.72700 cu.mMT0071 Crushed Rock - 12.5 mm - 6mm 0.24200 cu.m

MT0145 Cement (OPC / PSC) 0.31300 tonne

CW0080

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.37500 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.37500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 3.70000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.37570 cu.m

MT0070 Crushed Rock - 20 mm 0.42300 cu.mMT0071 Crushed Rock - 12.5 mm - 6mm 0.14100 cu.m

MT0145 Cement (OPC / PSC) 0.23660 tonne

Providing and fixing at or near ground level pre-ca st cement concrete in kerbs, edgings etc. as per ap proval pattern and setting in position with cement mortar 1:3 (1 cemen t : 3 sand) cost of required formwork and finishing smooth with 6 mm thick cement plaster on exposed surface complete - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nominal size)

smooth with 6 mm thick cement plaster on exposed su rface complete - 1:2:4 (1 cement : 2 sand : 4 grad ed crushed rock 20 mm nominal size)

Providing and fixing upto floor five level pre-cast cement concrete solid block including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 sand) includin g the cost of required formwork and finishing

Providing and fixing upto floor five level pre-cast cement concrete solid block including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 sand) includin g the cost of required formwork and finishing smoot h with 6 mm thick cement plaster on exposed surface complete - 1:3:6 (1 cement : 3 sand : 6 graded crushed rock 20 mm no minal size)

Providing and fixing upto floor five level pre-cast cement concrete hollow block including hoisting an d setting in position with cement mortar 1:3 (1 cement : 3 sand) includin g the cost of required formwork and finishing smoot h with 6 mm thick cement plaster on exposed surface complete - 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm no minal size)

Department of Engineering Services, MoWHS

Page 41: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 38

CW0081

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.37500 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.37500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 3.70000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.37570 cu.m

MT0070 Crushed Rock - 20 mm 0.43620 cu.mMT0071 Crushed Rock - 12.5 mm - 6 mm 0.14520 cu.m

MT0145 Cement (OPC / PSC) 0.17660 tonne

CW0090

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.04000 day LB0051 Mason Gd.2 0.04000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.40000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day

MT0068 Crushed Rock - 40 mm 0.94000 cu.mMR0011 Lime mortar 0.40000 cu.m

CW0091

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.04000 day LB0051 Mason Gd.2 0.04000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.40000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day

MT0127 Graded brick aggregates 0.94000 cu.mMR0011 Lime mortar 0.40000 cu.m

CW0135

8% of the rates worked out for upto five floors per cu.

CW0136

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.19050 day MP0201 Water pump AVI type 0.08930 day MT0145 Cement (OPC / PSC) 0.02200 tonne CW0137

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 1.70000 day LB0036 Mason Gd 1 0.30000 day

CW0140

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.04170 day MT0151 Water proofing compound 6.00000 kg

Providing and laying lime concrete, with graded bri ck aggregate of 40 mm and 40 % mortar comprising of 1:1:1 lime mortar, in footings and bases for columns excluding cost of formwork

Providing and laying lime concrete, with graded sto ne aggregate of 40 mm and 40 % mortar comprising of 1:1:1 lime mortar, in footings and bases for columns excluding cost of formwork

Extra for cement concrete work under foul condition s

Extra for cement concrete work in super-structure a bove floor five level for each four floors or part thereof

Extra for laying cement concrete work in or under w ater, mud, including the cost of pumping or bailing out water and removing slush etc. complete - per metre depth (con crete not leaner than 1:2:4)

Extra for laying cement concrete work - Providing a nd mixing water-proofing materials in in the propor tion 12 kg/cu.m or as prescribed by the manufacturer

Providing and fixing upto floor five level pre-cast cement concrete hollow block including hoisting an d setting in position with cement mortar 1:3 (1 cement : 3 sand) includin g the cost of required formwork and finishing smoot h with 6 mm thick cement plaster on exposed surface complete - 1:3:6 (1 cement : 3 sand : 6 graded crushed rock 20 mm no minal size)

Department of Engineering Services, MoWHS

Page 42: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 39

CHAPTER 7

DP0001

Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 0.05156 day LB0039 Work Supervisor (Lajab) 0.00125 day LB0051 Mason Gd.2 0.05156 day LB0053 Plant Operator Gd.3 0.00175 day LB0077 Labour 0.05531 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00175 day MP0206 Concrete Vibrator(M/C5) 0.00175 day MT0043 Sand 0.01113 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02225 cu.m MT0145 Cement (OPC / PSC) 0.00803 tonne DP0002

Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 0.05250 day LB0039 Work Supervisor (Lajab) 0.00200 day LB0051 Mason Gd.2 0.05250 day LB0053 Plant Operator Gd.3 0.00280 day LB0077 Labour 0.08850 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00280 day MP0206 Concrete Vibrator(M/C5) 0.00280 day MT0043 Sand 0.01780 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.03560 cu.m MT0145 Cement (OPC / PSC) 0.01285 tonne DP0010

Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 0.05313 day LB0039 Work Supervisor (Lajab) 0.00250 day LB0051 Mason Gd.2 0.05313 day LB0053 Plant Operator Gd.3 0.00350 day LB0077 Labour 0.11062 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00350 day MP0206 Concrete Vibrator(M/C5) 0.00350 day MT0043 Sand 0.02225 cu.m MT0070 Crushed Rock - 20mm 0.04450 cu.m MT0145 Cement (OPC / PSC) 0.01606 tonne DP0015

Coefficient for per sq.m Code Description Quant Units LB0077 Labour 0.15000 day MT0001 Bitumen 80\100 0.00170 tonne MT0035 Kerosene 0.12300 litre DP0020

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03380 day MT0155 Plastic Sheet - 50 micro-metre 1.05000 sq.m DP0021

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03380 day MT0156 Plastic Sheet - 100 micro-metre 1.05000 sq.m DP0022

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03380 day MT0157 Plastic Sheet - 200 micro-metre 1.05000 sq.m DP0030

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.04000 day MT0006 Bitumen felt Type 3 - Grade 2 1.05000 sq.m

Providing and laying Bitumen felt Type 3 in wall ba ses etc - Grade 2

Providing and laying moisture barrier using plastic sheeting underlay - 100 micro-metre

Providing and laying moisture barrier using plastic sheeting underlay - 200 micro-metre

Providing and laying moisture barrier using plastic sheeting underlay - 50 micro-metre

DAMP-PROOFING

Providing and laying damp-proof course with cement concrete 1:2:4, 12.5mm aggregate - 25mm thick

Providing and laying damp-proof course with cement concrete 1:2:4, 20mm aggregate - 50mm thick

Applying a coat of hot bitumen (maxphalt) 80/100 or equivalent using 1.7 kg per sq.m including the sur face cleaning

Providing and laying damp-proof course with cement concrete 1:2:4, 12.5mm aggregate - 40mm thick

Department of Engineering Services, MoWHS

Page 43: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 40

CHAPTER 8

RC0001

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07500 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.57500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne RC0002

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07500 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.57500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20mm 0.66150 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22050 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

RC0003

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07500 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.57500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

RC0005

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.05000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.67500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne

P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nomi nal size) excluding the cost of centering, shuttering and rei nforcement - all work upto plinth level

P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nomi nal size) work in walls (any thickness) including attached pilasters buttresses, piers, abutments etc.

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) excluding the cost of centering, shuttering and rei nforcement - all work upto plinth level

P&L in position reinforced cement concrete 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nomi nal size) excluding the cost of centering, shuttering and rei nforcement - all work upto plinth level

REINFORCED CONCRETE

Department of Engineering Services, MoWHS

Page 44: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 41

RC0006

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.05000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.67500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20mm 0.66150 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22050 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

RC0007

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.05000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.57500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

RC0009

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.05000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.89500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne RC0010

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.05000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.89500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20mm 0.66150 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22050 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

P&L in position reinforced cement concrete 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nomi nal size ) work in walls (any thickness) including attached pilasters buttresses, piers, abutments, etc.

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) work in walls (any thickness) including attached pilaste rs buttresses, piers, abutments, etc.

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nomi nal size) work in plinth and skirting courses, fillets, columns , pil lars, posts and struts

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) work in plinth and skirting courses, fillets, columns , pillars, posts and struts

Department of Engineering Services, MoWHS

Page 45: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 42

RC0011

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.05000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.89500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

RC0013

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.12500 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.12500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.95000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne RC0014

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.12500 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.12500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.95000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20mm 0.66150 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22050 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

RC0015

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.12500 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.12500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.95000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) work in suspended floor, roofs having slope upto 15o, la ndings, balconies, shelves and chajjas

P&L in position reinforced cement concrete 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nomi nal size) work in suspended floor, roofs having slope upto 15o, landi ngs, balconies, shelves and chajjas

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nomi nal size) work in plinth and skirting courses, fillets, columns , pil lars, posts and struts

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nomi nal size) work in suspended floor, roofs having slope upto 15o, landi ngs, balconies, shelves and chajjas

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

Department of Engineering Services, MoWHS

Page 46: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 43

RC0017

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.77500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne RC0018

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.77500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20mm 0.66150 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22050 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

RC0019

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.77500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

RC0020

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.77500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nomi nal size) work in beams, lintels, bands, plain window sills, staircas es, spiral staircases

P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nomi nal size) work in kerbs, steps and the like upto floor five level exc luding the cost of centering, shuttering and reinfo rcement.

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) work in beams, lintels, bands, plain window sills, stair cases, spiral staircases

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nomi nal size) work in beams, lintels, bands, plain window sills, staircas es, spiral staircases

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

Department of Engineering Services, MoWHS

Page 47: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 44

RC0021

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.77500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20mm 0.66150 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22050 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

RC0022

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0051 Mason Gd.2 0.07000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.77500 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

RC0023

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.50000 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.50000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.80000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20mm 0.67500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.61000 tonne RC0024

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.50000 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.50000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.80000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.44100 cu.m MT0070 Crushed Rock - 20mm 0.66150 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22050 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) work in kerbs, steps and the like upto floor five level excluding the cost of centering, shuttering and rei nforcement.

P&L in position reinforced cement concrete 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nomi nal size) work in kerbs, steps and the like upto floor five level exc luding the cost of centering, shuttering and reinfo rcement.

P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nomi nal size) work in arches and arch ribs upto floor five level excludin g the cost of centering, shuttering and reinforceme nt.

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) work in arches and arch ribs upto floor five level exclu ding the cost of centering, shuttering and reinforc ement.

Department of Engineering Services, MoWHS

Page 48: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 45

RC0025

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.50000 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.50000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.80000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.70500 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23500 cu.m MT0145 Cement (OPC / PSC) 0.32130 tonne

RC0026

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.37500 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.37500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.75000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45900 cu.m MT0070 Crushed Rock - 20mm 0.68850 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.25950 cu.m MT0145 Cement (OPC / PSC) 0.62220 tonne RC0027

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.37500 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.37500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.75000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.45000 cu.m MT0070 Crushed Rock - 20mm 0.67300 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.22500 cu.m MT0145 Cement (OPC / PSC) 0.41111 tonne

RC0028

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.37500 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.37500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 4.75000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47940 cu.m MT0070 Crushed Rock - 20mm 0.71910 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23970 cu.m MT0145 Cement (OPC / PSC) 0.32770 tonne

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

upto floor five level excluding the cost of center ing, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nomi nal size) work in arches and arch ribs upto floor five level excludin g the cost of centering, shuttering and reinforceme nt.

P&L in position reinforced cement concrete 1:1:2 (1 cement : 1 sand : 2 graded crushed rock 20 mm nomi nal size) work in domes, vaults, shells folded plates and roofs havin g more than 15o

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) work in domes, vaults, shells folded plates and roofs ha ving more than 15deg

upto floor five level excluding the cost of centeri ng, shuttering and reinforcement.

P&L in position reinforced cement concrete 1:2:4 (1 cement : 2 sand : 4 graded crushed rock 20 mm nomi nal size) work in domes, vaults, shells folded plates and roofs havin g more than 15o

Department of Engineering Services, MoWHS

Page 49: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 46

RC0029

Coefficient for per cu.m Code Description Quant Units LB0036 Mason Gd.1 0.02400 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.02400 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 3.28000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47600 cu.m MT0070 Crushed Rock - 20mm 0.95200 cu.m MT0145 Cement (OPC / PSC) 0.40300 tonne RC0030

Coefficient for per m Code Description Quant Units LB0021 Carpenter Gd.1 0.75000 day LB0033 Carpenter Gd.2 0.41652 day LB0036 Mason Gd.1 0.52953 day LB0039 Work Supervisor (Lajab) 0.20362 day LB0051 Mason Gd.2 0.27953 day LB0053 Plant Operator Gd.3 0.00253 day LB0077 Labour 2.06768 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00253 day MP0206 Concrete Vibrator(M/C5) 0.00253 day MT0043 Sand 0.02008 cu.m MT0070 Crushed Rock - 20mm 0.03077 cu.m MT0145 Cement (OPC / PSC) 0.01683 tonne MT0325 Ballies 75 to 125mm dia 0.46410 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00734 cu.m RC0031

Coefficient for per m Code Description Quant Units LB0021 Carpenter Gd.1 0.75000 day LB0033 Carpenter Gd.2 0.40018 day LB0036 Mason Gd.1 0.52867 day LB0039 Work Supervisor (Lajab) 0.25358 day LB0051 Mason Gd.2 0.27867 day LB0053 Plant Operator Gd.3 0.00251 day LB0077 Labour 2.10654 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00251 day MP0206 Concrete Vibrator(M/C5) 0.00251 day MT0043 Sand 0.01976 cu.m MT0070 Crushed Rock - 20mm 0.03043 cu.m MT0145 Cement (OPC / PSC) 0.01659 tonne MT0325 Ballies 75 to 125mm dia 0.44590 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00706 cu.m RC0032

Coefficient for per m Code Description Quant Units LB0021 Carpenter Gd.1 0.75000 day LB0033 Carpenter Gd.2 0.68766 day LB0036 Mason Gd.1 0.55303 day LB0039 Work Supervisor (Lajab) 0.25825 day LB0051 Mason Gd.2 0.30303 day LB0053 Plant Operator Gd.3 0.00578 day LB0077 Labour 2.42256 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00578 day MP0206 Concrete Vibrator(M/C5) 0.00578 day MT0043 Sand 0.04309 cu.m MT0070 Crushed Rock - 20mm 0.07013 cu.m MT0145 Cement (OPC / PSC) 0.03707 tonne MT0325 Ballies 75 to 125mm dia 0.76622 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01212 cu.m

P&L in position reinforced cement concrete 1:1.5:3 (1 cement : 1.5 sand : 3 graded crushed rock 20 mm nominal size) work in vertical and horizontal fins individually or for ming box louvers, fascias and eaves boards - upto floor five level excluding the cost of centering, shuttering and reinforcement

Bhutan type Traditional Cornices in R.C.C 1:1.5:3, 20 mm aggregate including cost of formwork includin g finishing with 6mm thick plaster on the exposed surface with cemen t mortar 1:3 (1 cement : 3 sand), excluding reinfor cement & decorative painting cost as per standard design (Me asurement to be taken along the cornice and wall ju nction) - Single Storeyed building, including Phana

Bhutan type Traditional Cornices in R.C.C 1:1.5:3, 20 mm aggregate including cost of formwork includin g finishing with 6mm thick plaster on the exposed surface with cement m ortar 1:3 (1 cement : 3 sand), excluding reinforcem ent & decorative painting cost as per standard design (Measurement to be take n along the cornice and wall junction) - Multi-Stor eyed building..at floor 2 level including the cost of lhanglag and at other f loors where Lhanglag is provided

Bhutan type Traditional Cornices in R.C.C 1:1.5:3, 20 mm aggregate including cost of formwork includin g finishing with 6mm thick plaster on the exposed surface with cement mortar 1 :3 (1 cement : 3 sand), excluding reinforcement & d ecorative painting cost as per standard design (Measurement to be taken along the cornice and wall junction) - Multi-Storeyed buildin g.. at all middle floor levels (excluding the cost of phana)

Department of Engineering Services, MoWHS

Page 50: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 47

RC0033

Coefficient for per m of E0827

Code Description Quant Units LB0021 Carpenter Gd.1 0.50000 day LB0033 Carpenter Gd.2 0.09523 day LB0036 Mason Gd.1 0.51691 day LB0039 Work Supervisor (Lajab) 0.25067 day LB0051 Mason Gd.2 0.01691 day LB0053 Plant Operator Gd.3 0.00047 day LB0077 Labour 1.36601 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00047 day MP0206 Concrete Vibrator(M/C5) 0.00047 day MT0043 Sand 0.00587 cu.m MT0070 Crushed Rock - 20mm 0.00569 cu.m MT0145 Cement (OPC / PSC) 0.00414 tonne MT0325 Ballies 75 to 125mm dia 0.10611 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00168 cu.m RC0034

Coefficient for per m of E0830

Code Description Quant Units LB0021 Carpenter Gd.1 0.50000 day LB0033 Carpenter Gd.2 0.20417 day LB0036 Mason Gd.1 0.26000 day LB0039 Work Supervisor (Lajab) 0.15144 day LB0051 Mason Gd.2 0.51000 day LB0053 Plant Operator Gd.3 0.00101 day LB0077 Labour 0.90716 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00101 day MP0206 Concrete Vibrator(M/C5) 0.00101 day MT0043 Sand 0.00766 cu.m MT0070 Crushed Rock - 20mm 0.01224 cu.m MT0145 Cement (OPC / PSC) 0.00654 tonne MT0325 Ballies 75 to 125mm dia 0.22750 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00360 cu.m RC0040

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.75000 day LB0033 Carpenter Gd.2 0.41652 day LB0036 Mason Gd.1 0.52953 day LB0039 Work Supervisor (Lajab) 0.20362 day LB0051 Mason Gd.2 0.27953 day LB0053 Plant Operator Gd.3 0.00253 day LB0077 Labour 2.06768 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00253 day MP0206 Concrete Vibrator(M/C5) 0.00253 day MT0043 Sand 0.02081 cu.m MT0070 Crushed Rock - 20mm 0.03222 cu.m MT0145 Cement (OPC / PSC) 0.01387 tonne MT0325 Ballies 75 to 125mm dia 0.46410 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00734 cu.m

Bhutan type Traditional Cornices in R.C.C 1:1.5:3, 20 mm aggregate including cost of formwork includin g finishing with 6mm thick plaster on the exposed surface with cemen t mortar 1:3 (1 cement : 3 sand), excluding reinf orcement & decorative painting cost as per standard design (Me asurement to be taken along the cornice and wall ju nction) - Phana

Bhutan type Traditional Cornices in R.C.C 1:1.5:3, 20 mm aggregate including cost of formwork includin g finishing with 6mm thick plaster on the exposed surface with cemen t mortar 1:3 (1 cement : 3 sand), excluding reinfor cement & decorative painting cost as per standard design (Me asurement to be taken along the cornice and wall ju nction) - Lintel Cornice (only cornice portion at external face)

Bhutan type Traditional Cornices in R.C.C 1:2:4, 20 mm aggregate including cost of formwork including finishing with 6mm thick plaster on the exposed surface with cement mo rtar 1:3 (1 cement : 3 sand ), excluding reinforcem ent & decorative painting cost as per standard design (Measurement t o be taken along the cornice and wall junction) - S ingle Storeyed building, including Phana

Department of Engineering Services, MoWHS

Page 51: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 48

RC0041

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.75000 day LB0033 Carpenter Gd.2 0.40018 day LB0036 Mason Gd.1 0.52867 day LB0039 Work Supervisor (Lajab) 0.25358 day LB0051 Mason Gd.2 0.27867 day LB0053 Plant Operator Gd.3 0.00251 day LB0077 Labour 2.10654 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00251 day MP0206 Concrete Vibrator(M/C5) 0.00251 day MT0043 Sand 0.02048 cu.m MT0070 Crushed Rock - 20mm 0.03186 cu.m MT0145 Cement (OPC / PSC) 0.01367 tonne MT0325 Ballies 75 to 125mm dia 0.44590 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00706 cu.m RC0042

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.75000 day LB0033 Carpenter Gd.2 0.68766 day LB0036 Mason Gd.1 1.05303 day LB0039 Work Supervisor (Lajab) 0.25825 day LB0051 Mason Gd.2 0.30303 day LB0053 Plant Operator Gd.3 0.00578 day LB0077 Labour 2.42256 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00578 day MP0206 Concrete Vibrator(M/C5) 0.00578 day MT0043 Sand 0.04474 cu.m MT0070 Crushed Rock - 20mm 0.07343 cu.m MT0145 Cement (OPC / PSC) 0.03033 tonne MT0325 Ballies 75 to 125mm dia 0.76622 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01212 cu.m RC0043

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.50000 day LB0033 Carpenter Gd.2 0.09523 day LB0036 Mason Gd.1 0.51691 day LB0039 Work Supervisor (Lajab) 0.25067 day LB0051 Mason Gd.2 0.01691 day LB0053 Plant Operator Gd.3 0.00047 day LB0077 Labour 1.36601 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00047 day MP0206 Concrete Vibrator(M/C5) 0.00047 day MT0043 Sand 0.00600 cu.m MT0070 Crushed Rock - 20mm 0.00596 cu.m MT0145 Cement (OPC / PSC) 0.00359 tonne MT0325 Ballies 75 to 125mm dia 0.10611 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00168 cu.m

Bhutan type Traditional Cornices in R.C.C 1:2:4, 20 mm aggregate including cost of formwork including finishing with 6mm thick plaster on the exposed surface with cement mo rtar 1:3 (1 cement : 3 sand) , excluding reinforcem ent & decorative painting cost as per standard design (Measurement t o be taken along the cornice and wall junction) - M ulti-Storeyed building..at floor 2 level and at other floors wher e lhanglag is provided including the cost of lhangl ag

reinforcement & decorative painting cost as per sta ndard design (Measurement to be taken along the cor nice and wall junction) - Phana

Bhutan type Traditional Cornices in R.C.C 1:2:4, 20 mm aggregate including cost of formwork including finishing with 6mm thick plaster on the exposed surface with cement mo rtar 1:3 (1 cement : 3 sand) , excluding

reinforcement & decorative painting cost as per sta ndard design (Measurement to be taken along the cor nice and wall junction) - Multi-Storeyed building.. at all middle floor levels (excluding the cost of phana)

Bhutan type Traditional Cornices in R.C.C 1:2:4, 20 mm aggregate including cost of formwork including finishing with 6mm thick plaster on the exposed surface with cement mo rtar 1:3 ( 1 cement : 3 sand) , excluding

Department of Engineering Services, MoWHS

Page 52: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 49

RC0044

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.50000 day LB0033 Carpenter Gd.2 0.20417 day LB0036 Mason Gd.1 0.26000 day LB0039 Work Supervisor (Lajab) 0.15144 day LB0051 Mason Gd.2 0.51000 day LB0053 Plant Operator Gd.3 0.00101 day LB0077 Labour 0.90716 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00101 day MP0206 Concrete Vibrator(M/C5) 0.00101 day MT0043 Sand 0.00795 cu.m MT0070 Crushed Rock - 20mm 0.01282 cu.m MT0145 Cement (OPC / PSC) 0.00536 tonne MT0325 Ballies 75 to 125mm dia 0.22750 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00360 cu.m RC0050

Coefficient for per sq.m Code Description Quant Units LB0077 Labour 0.03100 day MT0145 Cement (OPC / PSC) 0.00275 tonne RC0051

8% of respective rates per cu.m RC0052

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.02500 day LB0051 Mason Gd.2 0.02500 day LB0077 Labour 0.03468 day MT0043 Sand 0.00285 cu.m MT0145 Cement (OPC / PSC) 0.00204 tonne RC0053

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.04100 day LB0051 Mason Gd.2 0.04100 day LB0077 Labour 0.14310 day MT0043 Sand 0.00770 cu.m MT0145 Cement (OPC / PSC) 0.00367 tonne RC0054

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.02100 day LB0051 Mason Gd.2 0.02100 day LB0077 Labour 0.04200 day RC0060

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.25313 day LB0039 Work Supervisor (Lajab) 0.00250 day LB0051 Mason Gd.2 0.25313 day LB0053 Plant Operator Gd.3 0.00350 day LB0077 Labour 1.01062 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00350 day MP0206 Concrete Vibrator(M/C5) 0.00350 day MT0043 Sand 0.02225 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.04450 cu.m MT0145 Cement (OPC / PSC) 0.01606 tonne MT0215 Welded Mesh - 75mmx25mm 1.00000 sq.m

Providing throating, plastering drip and moulding t o R.C.C chajjas

Providing & fixing, below & including floor 2 level , Precast R.C.C jali 1:2:4, 12.5mm aggregate, reinf orced with mild steel wire 1.6mm dia., including roughening, cleaning, fi xing, finishing in cement mortar 1:3 excluding pla stering of the jambs, sills, soffits - 50 mm thick

Extra for R.C.C work above floor 5 level for every four floors or part thereof, excluding cost of rein forcement

Extra, for rendering in cement mortar 1:2, the top of suspended floors\landings\staircase treads and r isers

Applying cement slurry on R.C.C slabs using 2.75 kg per sq.m for receiving C.C. floor including roughe ning, cleaning & dampen the surface

Bhutan type Traditional Cornices in R.C.C 1:2:4, 20 mm aggregate including cost of formwork including finishing with 6mm thick plaster on the exposed surface with cement mortar 1 :3 (1 cement : 3 sand), excluding reinforcement & d ecorative painting cost as per standard design (Measurement to be taken along the cornice and wall junction) - Lintel cornice (only c ornice portion at external face)

Rendering smooth finishing of the exposed surface w ith 6mm thick C.M 1:3

Department of Engineering Services, MoWHS

Page 53: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 50

RC0061

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.20250 day LB0039 Work Supervisor (Lajab) 0.00200 day LB0051 Mason Gd.2 0.20250 day LB0053 Plant Operator Gd.3 0.00280 day LB0077 Labour 0.92180 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00280 day MP0206 Concrete Vibrator(M/C5) 0.00280 day MT0043 Sand 0.01780 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.03560 cu.m MT0145 Cement (OPC / PSC) 0.01285 tonne MT0215 Welded Mesh - 75mmx25mm 1.00000 sq.m RC0062

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.20156 day LB0039 Work Supervisor (Lajab) 0.00125 day LB0051 Mason Gd.2 0.20156 day LB0053 Plant Operator Gd.3 0.00175 day LB0077 Labour 0.88831 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00175 day MP0206 Concrete Vibrator(M/C5) 0.00175 day MT0043 Sand 0.01113 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02225 cu.m MT0145 Cement (OPC / PSC) 0.00803 tonne MT0215 Welded Mesh - 75mmx25mm 1.00000 sq.m RC0070

Coefficient for per cu.m

Code Description Quant Units LB0033 Carpenter Gd.2 1.87200 day LB0036 Mason Gd.1 0.74740 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.74740 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 6.50634 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.57135 cu.m MT0070 Crushed Rock - 20mm 0.89000 cu.m MT0145 Cement (OPC / PSC) 0.38152 tonne MT0325 Ballies 75 to 125mm dia 5.04000 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.16200 cu.m RC0071

Coefficient for per cu.m

Code Description Quant Units LB0033 Carpenter Gd.2 1.72224 day LB0036 Mason Gd.1 0.54691 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.54691 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 5.65682 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.53367 cu.m MT0070 Crushed Rock - 20mm 0.89000 cu.m MT0145 Cement (OPC / PSC) 0.36356 tonne MT0325 Ballies 75 to 125mm dia 4.63680 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.14904 cu.m

excluding plastering of the jambs, sills, soffits - 25 mm thick

- String courses, copings, bed plates, anchor block s, plain window sills

Providing & fixing, below & including floor 2 level , Precast R.C.C 1:2:4, 20mm aggregate including fin ishing, plastering with 6mm cement plaster 1:3 and formwork, but excluding reinforcement cost - Small lintels & joists < 1.5 m clear span, shelves

Providing & fixing, below & including floor 2 level , Precast R.C.C 1:2:4, 20mm aggregate including fin ishing, plastering with 6mm cement plaster 1:3 and formwork, but excluding reinforcement cost

excluding plastering of the jambs, sills, soffits - 40 mm thick

Providing & fixing, below & including floor 2 level , Precast R.C.C jali 1:2:4, 12.5mm aggregate, reinf orced with mild steel wire 1.6mm dia., including roughening, cleaning, fi xing, finishing in cement mortar 1:3

Providing & fixing, below & including floor 2 level , Precast R.C.C jali 1:2:4, 12.5mm aggregate, reinf orced with mild steel wire 1.6mm dia., including roughening, cleaning, fi xing, finishing in cement mortar 1:3

Department of Engineering Services, MoWHS

Page 54: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 51

RC0072

Coefficient for per cu.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.31793 day LB0036 Mason Gd.1 0.91077 day LB0039 Work Supervisor (Lajab) 0.05000 day LB0051 Mason Gd.2 0.91077 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 5.52246 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.60204 cu.m MT0070 Crushed Rock - 20mm 0.89000 cu.m MT0145 Cement (OPC / PSC) 0.39615 tonne MT0325 Ballies 75 to 125mm dia 0.85596 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.02751 cu.m RC0083

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01376 day LB0077 Labour 0.01376 day MT0208 Reinforcing Bars & Mesh - Thermo Mechanically Treated Bars (TMT bars) 1.05000 kg RC0090

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.15600 day LB0077 Labour 0.15600 day MT0325 Ballies 75 to 125mm dia 0.42000 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01350 cu.m RC0091

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.81670 day LB0077 Labour 0.36080 day MT0325 Ballies 75 to 125mm dia 0.91000 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01440 cu.m RC0092

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.20000 day LB0077 Labour 0.20000 day MT0325 Ballies 75 to 125mm dia 1.41000 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01650 cu.m RC0093

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.37100 day LB0077 Labour 0.37100 day MT0325 Ballies 75 to 125mm dia 1.20640 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01730 cu.m RC0094

Coefficient for per sq.m Code Description Quant Units LB0033 Carpenter Gd.2 0.37800 day LB0077 Labour 0.21600 day MT0325 Ballies 75 to 125mm dia 0.36800 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01550 cu.m

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Staircase (except spiral staircase) excluding landi ng

Providing & fixing, below & including floor 2 level , Precast R.C.C 1:2:4, 20mm aggregate including fin ishing, plastering with 6mm cement plaster 1:3 and formwork, but excluding reinforcement cost - Joists, span > 1.5m, shelves

Providing & fixing, Thermo Mechanically Treated (TM T) bars for R.C.C work including cutting, bending, binding and placing in position complete

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Foundation and plinth etc.

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Walls, pilasters, buttresses, string course etc.

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Columns, pillars, post, struts, etc.

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Lintels, beams, girders, bresummers, cantilevers et c.

Department of Engineering Services, MoWHS

Page 55: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 52

RC0095

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.56000 day LB0077 Labour 0.56000 day MT0325 Ballies 75 to 125mm dia 2.07500 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01680 cu.m RC0096

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.56336 day LB0077 Labour 0.28671 day MT0325 Ballies 75 to 125mm dia 0.87841 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.01516 cu.m RC0097

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.98180 day LB0077 Labour 0.79770 day MT0250 Plain G.I Sheet, 24-gauge (0.63mm) 0.00600 tonne MT0325 Ballies 75 to 125mm dia 2.48000 m MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.05500 cu.m RC0098

Coefficient for per sq.m

Code Description Quant UnitsLB0033 Carpenter Gd.2 1.00000 dayLB0077 Labour 0.85000 day

MT0250 Plain G.I Sheet, 24-gauge (0.63mm) 0.00600 tonne MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.11800 cu.m RC0105

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 2.66600 day LB0051 Mason Gd.2 2.66600 day LB0077 Labour 8.52900 day MT0001 Bitumen 80/100 1.05000 tonne MT0040 Firewood (stacked volume) 2.60000 cu.m RC0106

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 2.66600 day LB0051 Mason Gd.2 2.66600 day LB0077 Labour 8.52900 day MT0001 Bitumen 80/100 0.25630 tonne MT0040 Firewood (stacked volume) 0.69550 cu.m MT0043 Sand 0.80000 cu.m MT0145 Cement (OPC / PSC) 0.00320 tonne RC0107

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.01500 day LB0051 Mason Gd.2 0.01500 day LB0077 Labour 0.03200 day MT0010 Hot sealing compound Grade A 4.00000 kg MT0011 Bitumen Solution primer 0.16670 litre MT0015 Pre-moulded bitumen impregnated fibre board, 12mm thick (IS: 1838 or equivalent) 1.05000 sq.m

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Suspended floor, roof, landing, shelves and their s upports, balconies, chajjas, etc.

Providing & filling or fixing in position in expans ion joints - Bitumen mix filler of proportion 80 kg of hot bitumen, 1 kg of cement and 0.25 cum of sand for expansion joints

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Spiral stair case excluding landing

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Arches, curved surfaces

Providing & fixing centering and shuttering (formwo rk), including strutting, propping etc. and removal of formwork - Domes, vaults, shell roof

Providing & filling or fixing in position in expans ion joints - 12 mm bitumen impregnated fibre board

Providing & filling or fixing in position in expans ion joints - Blown bitumen

Department of Engineering Services, MoWHS

Page 56: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 53

RC0116

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.08300 day LB0077 Labour 0.08300 day MT0160 Aluminium Fluted Strips 3.15mm thick 150mm wide 1.05000 m RC0130

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.07500 day LB0039 Work Supervisor (Lajab) 0.50000 day LB0051 Mason Gd.2 0.07500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 1.30000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.71910 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23970 cu.m MT0145 Cement (OPC / PSC) 0.32770 tonne

RC0131

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.15000 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.15000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.30000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.71910 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23970 cu.m MT0145 Cement (OPC / PSC) 0.32770 tonne

RC0132

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.15000 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.15000 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.55000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.71910 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23970 cu.m MT0145 Cement (OPC / PSC) 0.32770 tonne

- All work from plinth level to floor five level

Including admixtures in recommended proportions (as per IS 9103) to accelerate, retard setting of conc rete, improve workability without impairing strength and durabili ty as per the direction of the engineer

P&L in position machine batched, machine mixed and machine vibrated M-20 design mix cement concrete fo r reinforced cement concrete structural elements, excluding the cost of centering, shuttering and reinforcement.

- Walls, Columns, Pillars, posts and struts

- All work upto plinth level

P&L in position machine batched, machine mixed and machine vibrated M-20 design mix cement concrete fo r reinforced cement concrete structural elements, excluding the cost of centering, shuttering and reinforcement.

Including admixtures in recommended proportions (as per IS 9103) to accelerate, retard setting of conc rete, improve workability without impairing strength and durabili ty as per the direction of the engineer

Including admixtures in recommended proportions (as per IS 9103) to accelerate, retard setting of conc rete, improve workability without impairing strength and durabili ty as per the direction of the engineer

P&L in position machine batched, machine mixed and machine vibrated M-20 design mix cement concrete fo r reinforced cement concrete structural elements, excluding the cost of centering, shuttering and reinforcement.

Providing and fixing sheet-covering over expansion joints with iron screws as per design to Match the colour shade of the distemper or wall treatment - Aluminium fluted stri p 3.15x150mm

Department of Engineering Services, MoWHS

Page 57: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 54

RC0133

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.17500 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0051 Mason Gd.2 0.17500 day LB0053 Plant Operator Gd.3 0.07000 day LB0077 Labour 2.85000 day MP0205 Concrete Mixer(7/5 cu.ft) 0.07000 day MP0206 Concrete Vibrator(M/C5) 0.07000 day MT0043 Sand 0.47000 cu.m MT0070 Crushed Rock - 20mm 0.71910 cu.m

MT0071 Crushed Rock - 12.5mm - 6 mm 0.23970 cu.m MT0145 Cement (OPC / PSC) 0.32770 tonne

RC0135

Increase rate by 3% per cu.m

RC0136

Coefficient for per cu.m

Code Description Quant Units MT0145 Cement ( OPC/PSC) 0.02000 MT RC0137

Coefficient for per cu.m

Code Description Quant Units MT0145 Cement ( OPC/PSC) 0.04000 MT

Including admixtures in recommended proportions (as per IS 9103) to accelerate, retard setting of conc rete, improve workability without impairing strength and durabili ty as per the direction of the engineer

- Beams, Plinth beams, girders, bresummers, cantile vers, suspended floors, lintels, roofs and staircas es including spiral staircases, shelves etc.

Add or deduct for providing richer or leaner mixes respectively at all floors: providing M-25 grade RC C instead of M-20 grade RCC

Add or deduct for providing richer or leaner mixes respectively at all floors: providing M-30 grade RC C instead of M-20 grade RCC

Add or deduct for providing richer or leaner mixes respectively at all floors: providing M-35 grade RC C instead of M-20 grade RCC

P&L in position machine batched, machine mixed and machine vibrated M-20 design mix cement concrete fo r reinforced cement concrete structural elements, excluding the cost of centering, shuttering and reinforcement.

Department of Engineering Services, MoWHS

Page 58: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 55

CHAPTER 9

BW0001

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.33900 day LB0051 Mason Gd.2 0.33900 day LB0077 Labour 1.87025 day MT0043 Sand 0.26750 cu.m MT0125 Bricks 2nd class 0.40700 1000# MT0145 Cement (OPC / PSC) 0.12750 tonne BW0002

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.33900 day LB0051 Mason Gd.2 0.33900 day LB0077 Labour 1.87025 day MT0043 Sand 0.26750 cu.m MT0125 Bricks 2nd class 0.40700 1000# MT0145 Cement (OPC / PSC) 0.09500 tonne BW0003

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.33900 day LB0051 Mason Gd.2 0.33900 day LB0077 Labour 1.87025 day MT0043 Sand 0.26750 cu.m MT0125 Bricks 2nd class 0.40700 1000# MT0145 Cement (OPC / PSC) 0.07750 tonne BW0004

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.33900 day LB0051 Mason Gd.2 0.33900 day LB0077 Labour 1.87025 day MT0043 Sand 0.26750 cu.m MT0125 Bricks 2nd class 0.40700 1000# MT0145 Cement (OPC / PSC) 0.06250 tonne BW0005

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.33900 day LB0051 Mason Gd.2 0.33900 day LB0077 Labour 1.62238 day MT0042 Mud dry 0.30000 cu.m MT0125 Bricks 2nd class 0.40700 1000# BW0010

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.33900 day LB0051 Mason Gd.2 0.33900 day LB0076 Labour 0.33900 day

BW0011 Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.88600 day

LB0051 Mason Gd.2 0.88600 day LB0076 Labour 0.43800 day

MT0125 Bricks 2nd class 0.14200 1000#

Extra, for brick in circular pillars

P&L Second-Class Brick work in Foundation & Plinth - In cement mortar 1:6

P&L Second-Class Brick work in Foundation & Plinth - In cement mortar 1:5

P&L Second-Class Brick work in Foundation & Plinth - In cement mortar 1:4

BRICK WORK

P&L Second-Class Brick work in Foundation & Plinth - In mud mortar

Extra, for brick work in square or rectangular pill ars

P&L Second-Class Brick work in Foundation & Plinth - In cement mortar 1:3

Department of Engineering Services, MoWHS

Page 59: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 56

BW0012 Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.09900 day LB0051 Mason Gd.2 0.09900 day LB0076 Labour 0.41300 day BW0013

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.29000 day BW0014

Coefficient for per sq.m

Code Description Quant Units MT0182 Rolled sections (250 MPa) - Flats 1.03000 kg BW0015

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.01470 day MT0151 Water proofing compound 2.00000 kg BW0020

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.09800 day LB0051 Mason Gd.2 0.09800 day LB0077 Labour 0.31913 day MT0043 Sand 0.02675 cu.m MT0125 Bricks 2nd class 0.05200 1000# MT0145 Cement (OPC / PSC) 0.01275 tonne BW0021

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.09800 day LB0051 Mason Gd.2 0.09800 day LB0077 Labour 0.31913 day MT0043 Sand 0.02675 cu.m MT0125 Bricks 2nd class 0.05200 1000# MT0145 Cement (OPC / PSC) 0.00950 tonne BW0030

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03400 day BW0031 Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01470 day

MT0151 Water proofing compound 0.20000 kg BW0032

Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 0.02800 day LB0051 Mason Gd.2 0.02800 day LB0077 Labour 0.08236 day

MT0043 Sand 0.01937 cu.m MT0125 Bricks 2nd class 0.03100 1000# MT0145 Cement (OPC / PSC) 0.00923 tonne

Extra, for half-brick masonry in superstructure abo ve floor 2 level...per floor

P&L Second-Class Half-brick Masonry (125 mm) in sup erstructure below floor 2 level - In cement mortar 1:4

75mm thick brick masonry (second class bricks) in c ement mortar 1:3 in partitions etc in superstructur e below floor 2 level

Extra, for mixing water-proofing compound in cement mortar

Extra, for providing hoop iron 25x1.6mm or equivale nt reinforcement in masonry at every third course, embedded in cement mortar

P&L Second-Class Half-brick Masonry (125 mm) in sup erstructure below floor 2 level - In cement mortar 1:3

Extra, for mixing water-proofing compound in cement mortar

Extra, for brick work in superstructure above plint h level, up to floor two level

Extra, for brick work in superstructure above floor two level...per floor

Department of Engineering Services, MoWHS

Page 60: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 57

BW0033

Coefficient for per sq.m

Code Description Quant Units

LB0077 Labour 0.03400 day BW0040

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.63085 day LB0051 Mason Gd.2 0.56568 day LB0077 Labour 1.27102 day MT0043 Sand 0.01713 cu.m MT0125 Bricks 2nd class 0.01457 1000#

MT0145 Cement (OPC / PSC) 0.00783 tonne BW0041

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.95074 day LB0051 Mason Gd.2 0.86486 day LB0077 Labour 1.43508 day MT0043 Sand 0.03732 cu.m MT0125 Bricks 2nd class 0.03704 1000# MT0145 Cement (OPC / PSC) 0.01536 tonne BW0050 Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.04700 day LB0051 Mason Gd.2 0.04700 day LB0077 Labour 0.12038 day MT0043 Sand 0.00321 cu.m MT0145 Cement (OPC / PSC) 0.00153 tonne BW0051 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.05000 day

LB0051 Mason Gd.2 0.05100 day LB0077 Labour 0.13838 day MT0043 Sand 0.00321 cu.m MT0145 Cement (OPC / PSC) 0.00153 tonne BW0052 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.07550 day LB0051 Mason Gd.2 0.07550 day LB0077 Labour 0.18838 day MT0043 Sand 0.00321 cu.m

MT0145 Cement (OPC / PSC) 0.00153 tonne BW0053 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.10100 day LB0051 Mason Gd.2 0.10100 day LB0077 Labour 0.23618 day MT0043 Sand 0.00492 cu.m MT0145 Cement (OPC / PSC) 0.00235 tonne

- Floor one level including lhanglag

Pointing on brickwork with cement mortar 1:3 - Rule d pointing

Pointing on brickwork with cement mortar 1:3 - Cut, weather struck pointing

Pointing on brickwork with cement mortar 1:3 - Rais ed & cut pointing

P&L second class brick work in Bhutan type Traditio nal Cornices in cement mortar 1:3, including 12mm p laster in cement mortar 1:5, but excluding decorative painting. (Mea surement to be taken along the cornice and wall jun ction)

- Middle Floor levels excluding phana

Pointing on brickwork with cement mortar 1:3 - Flus h pointing

P&L second class brick work in Bhutan type Traditio nal Cornices in cement mortar 1:3, including 12mm p laster in cement mortar 1:5, but excluding decorative painting. (Mea surement to be taken along the cornice and wall jun ction)

Extra, for 75mm brick masonry in cement mortar 1:3 in partitions etc in superstructure above floor 2 l evel...Per floor

Department of Engineering Services, MoWHS

Page 61: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 58

BW0060

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.17790 day

LB0051 Mason Gd.2 0.17790 day

LB0077 Labour 0.98180 day

MT0043 Sand 0.18620 cu.m

MT0128 ICEB(300mmX150mmX100mm) 0.22200 1000#

MT0145 Cement (OPC / PSC) 0.07949 tonne

BW0061

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.17790 day

LB0051 Mason Gd.2 0.17790 day

LB0077 Labour 0.98180 day

MT0043 Sand 0.17290 cu.m

MT0128 ICEB(300mmX150mmX100mm) 0.22200 1000#

MT0145 Cement (OPC / PSC) 0.05031 tonne

BW0062

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.17790 day

LB0051 Mason Gd.2 0.17790 day

LB0077 Labour 0.98180 day

MT0043 Sand 0.18620 cu.m

MT0128 ICEB(300mmX150mmX100mm) 0.22200 1000#

MT0145 Cement (OPC / PSC) 0.041254 tonne

BW0063

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.17790 day

LB0051 Mason Gd.2 0.17790 day

LB0077 Labour 0.98180 day

MT0043 Sand 0.18620 cu.m

MT0128 ICEB(300mmX150mmX100mm) 0.22200 1000#

MT0145 Cement (OPC / PSC) 0.03270 tonne

BW0064

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.17790 day

LB0051 Mason Gd.2 0.17790 day

LB0077 Labour 0.98180 day

MT0042 Mud dry 0.13500 cu.m

MT0128 ICEB(300mmX150mmX100mm) 0.22200 1000#

BW0070

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.17790 day

LB0051 Mason Gd.2 0.17790 day

LB0076 Labour 0.17672 day

P&L ICEB(300mmX150mmX100mm) in Foundation & Plinth - In cement mortar 1:3

P&L ICEB(300mmX150mmX100mm) in Foundation & Plinth - In cement mortar 1:4

P&L ICEB (300mmX150mmX100mm) in Foundation & Plinth - In cement mortar 1:5

P&L ICEB(300mmX150mmX100mm) in Foundation & Plinth - In cement mortar 1:6

P&L ICEB (300mmX150mmX100mm) in Foundation & Plinth - In mud mortar

Extra, for ICEB work in square or rectangular pilla rs

Department of Engineering Services, MoWHS

Page 62: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 59

BW0071

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.05337 day

LB0051 Mason Gd.2 0.05337 day

LB0076 Labour 0.21599 day

BW0072

Coefficient for per cu.m

Code Description Quant Units

LB0077 Labour 0.151193 day

BW0080

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.06064 day

LB0051 Mason Gd.2 0.06064 day

LB0077 Labour 0.19742 day

MT0043 Sand 0.01097 cu.m

MT0128 ICEB(300mmX150mmX100mm) 0.03333 1000#

MT0145 Cement (OPC / PSC) 0.00490 tonne

BW0081

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.06064 day

LB0051 Mason Gd.2 0.06064 day

LB0077 Labour 0.19742 day

MT0043 Sand 0.01097 cu.m

MT0128 ICEB(300mmX150mmX100mm) 0.03333 1000#

MT0145 Cement (OPC / PSC) 0.00392 tonne

BW0090

Coefficient for per sq.m

Code Description Quant Units

LB0077 Labour 0.03555 day

BW0100

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.25420 day

LB0051 Mason Gd.2 0.25420 day

LB0077 Labour 1.40260 day

MT0043 Sand 0.13300 cu.m

MT0129 ICEB(250mmX125mmX100mm) 0.32000 1000#

MT0145 Cement (OPC / PSC) 0.05186 tonne

BW0101

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.25420 day

LB0051 Mason Gd.2 0.25420 day

LB0077 Labour 1.40260 day

MT0043 Sand 0.13300 cu.m

MT0129 ICEB(250mmX125mmX100mm) 0.32000 1000#

MT0145 Cement (OPC / PSC) 0.03870 tonne

Extra, for ICEB work in superstructure above floor 2 level...per floor

Extra, for ICEB work in superstructure above plinth level, up to floor two level

Extra, for ICEB work in superstructure above floor two level...per floor

P&L ICEB (250mmX125mmX100mm) in Foundation & Plinth - In cement mortar 1:3

P&L ICEB (250mmX125mmX100mm) in Foundation & Plinth - In cement mortar 1:4

P&L ICEB(300mmX150mmX100mm) in superstructure below floor 2 level - In cement mortar 1:3

P&L ICEB (300mmX150mmX100mm) in superstructure belo w floor 2 level - In cement mortar 1:4

Department of Engineering Services, MoWHS

Page 63: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 60

BW0102

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.25420 day

LB0051 Mason Gd.2 0.25420 day

LB0077 Labour 1.40260 day

MT0043 Sand 0.13300 cu.m

MT0129 ICEB(250mmX125mmX100mm) 0.32000 1000#

MT0145 Cement (OPC / PSC) 0.02602 tonne

BW0103

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.25420 day

LB0051 Mason Gd.2 0.25420 day

LB0077 Labour 1.40260 day

MT0043 Sand 0.13300 cu.m

MT0129 ICEB(250mmX125mmX100mm) 0.32000 1000#

MT0145 Cement (OPC / PSC) 0.02516 tonne

BW0104

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.25420 day

LB0051 Mason Gd.2 0.25420 day

LB0077 Labour 1.40260 day

MT0042 Mud dry 0.18000 cu.m

MT0129 ICEB(250mmX125mmX100mm) 0.32000 1000#

BW0110

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.25420 day

LB0051 Mason Gd.2 0.25420 day

LB0076 Labour 0.25248 day

BW0111

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.07626 day

LB0051 Mason Gd.2 0.07626 day

LB0076 Labour 0.30857 day

BW0112

Coefficient for per cu.m

Code Description Quant Units

LB0077 Labour 0.215999 day

BW0120

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.07350 day

LB0051 Mason Gd.2 0.07350 day

LB0077 Labour 0.23930 day

MT0043 Sand 0.01330 cu.m

MT0129 ICEB(250mmX125mmX100mm) 0.04000 1000#

MT0145 Cement (OPC / PSC) 0.00594 tonne

P&L ICEB (250mmX125mmX100mm) in Foundation & Plinth - In mud mortar

Extra, for ICEB work in square or rectangular pilla rs

P&L ICEB(250mmX125mmX100mm)in superstructure below floor 2 level - In cement mortar 1:3

P&L ICEB (250mmX125mmX100mm) in Foundation & Plinth - In cement mortar 1:5

P&L ICEB (250mmX125mmX100mm) in Foundation & Plinth - In cement mortar 1:6

Extra, for ICEB work in superstructure above plinth level, up to floor two level

Extra, for ICEB work in superstructure above floor two level...per floor

Department of Engineering Services, MoWHS

Page 64: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 61

BW0121

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.07350 day

LB0051 Mason Gd.2 0.07350 day

LB0077 Labour 0.23930 day

MT0043 Sand 0.01330 cu.m

MT0129 ICEB(250mmX125mmX100mm) 0.04000 1000#

MT0145 Cement (OPC / PSC) 0.00475 tonne

BW0130

Coefficient for per sq.m

Code Description Quant Units

LB0077 Labour 0.043074 day

BW0140 P&L concrete block brick work in Foundation & Plint h - In cement mortar 1:3

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.33900 day

LB0051 Mason Gd.2 0.33900 day

LB0077 labourer 1.87025 day

MT0043 Sand 0.26750 cu.m

MT0130 Concrete block bricks 0.40700 1000#

MT0145 Cement (OPC / PSC) 0.12750 tonne

BW0141 P&L concrete block brick work in Foundation & Plint h - In cement mortar 1:4

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.33900 day

LB0051 Mason Gd.2 0.33900 day

LB0077 labourer 1.87025 day

MT0043 Sand 0.26750 cu.m

MT0130 Concrete block bricks 0.40700 1000#

MT0145 Cement (OPC / PSC) 0.09500 tonne

BW0142 P&L concrete block brick work in Foundation & Plint h - In cement mortar 1:5

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.33900 day

LB0051 Mason Gd.2 0.33900 day

LB0077 labourer 1.87025 day

MT0043 Sand 0.26750 cu.m

MT0130 Concrete block bricks 0.40700 1000#

MT0145 Cement (OPC / PSC) 0.07750 tonne

BW0143 P&L concrete block brick work in Foundation & Plint h - In cement mortar 1:6

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.33900 day

LB0051 Mason Gd.2 0.33900 day

LB0077 labourer 1.87025 day

MT0043 Sand 0.26750 cu.m

MT0130 Concrete block bricks 0.40700 1000#

MT0145 Cement (OPC / PSC) 0.06250 tonne

P&L ICEB(250mmX125mmX100mm)in superstructure below floor 2 level - In cement mortar 1:4

Extra, for ICEB work in superstructure above floor 2 level...per floor

Department of Engineering Services, MoWHS

Page 65: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 62

BW0150 Extra, for concrete block brick work in square or r ectangular pillars

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.33900 day

LB0051 Mason Gd.2 0.33900 day

LB0076 labourer 0.33900 day

BW0151 Extra, for concrete block brick in circular pillars

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.88600 day

LB0051 Mason Gd.2 0.88600 day

LB0076 labourer 0.43800 day

MT0130 Concrete block bricks 0.14200 1000#

BW0152 Extra, for concrete block brick work in superstruct ure above plinth level, up to floor two level

Coefficient for per cu.m

Code Description Quant Units

LB0036 Mason Gd.1 0.09900 day

LB0051 Mason Gd.2 0.09900 day

LB0076 labourer 0.41300 day

BW0153 Extra, for concrete block brick work in superstruct ure above floor two level...per floor

Coefficient for per cu.m

Code Description Quant Units

LB0077 labourer 0.29000 day

BW0154

Coefficient for per sq.m

Code Description Quant Units

MT0182 Rolled sections (250 MPa) - Flats 1.03000 kg

BW0155 Extra, for mixing water-proofing compound in cement mortar

Coefficient for per cu.m

Code Description Quant Units

LB0077 labourer 0.01470 day

MT0151 Water proofing compound 2.00000 kg

BW0160

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.09800 day

LB0051 Mason Gd.2 0.09800 day

LB0077 labourer 0.31913 day

MT0043 Sand 0.02675 cu.m

MT0130 Concrete block bricks 0.05200 1000#

MT0145 Cement (OPC / PSC) 0.01275 tonne

Extra, for providing hoop iron 25x1.6mm or equivale nt reinforcement in masonry at every third course, embedded in cement mortar

P& L concrete block half-brick Masonry (125 mm) in superstructure below floor 2 level - In cement mort ar 1:3

Department of Engineering Services, MoWHS

Page 66: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 63

BW0161

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.09800 day

LB0051 Mason Gd.2 0.09800 day

LB0077 labourer 0.31913 day

MT0043 Sand 0.02675 cu.m

MT0130 Concrete block bricks 0.05200 1000#

MT0145 Cement (OPC / PSC) 0.00950 tonne

BW0170 Extra, for concrete block half-brick masonry in sup erstructure above floor 2 level...per floor

Coefficient for per sq.m

Code Description Quant Units

LB0077 labourer 0.03400 day

BW0171 Extra, for mixing water-proofing compound in cement mortar

Coefficient for per sq.m

Code Description Quant Units

LB0077 labourer 0.01470 day

MT0151 Water proofing compound 0.20000 kg

BW0180 Pointing on concrete block brick work with cement m ortar 1:3 - Flush pointing

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.04700 day

LB0051 Mason Gd.2 0.04700 day

LB0077 labourer 0.12038 day

MT0043 Sand 0.00321 cu.m

MT0145 Cement (OPC / PSC) 0.00153 tonne

BW0181 Pointing on concrete block brick work with cement m ortar 1:3 - Ruled pointing

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.05000 day

LB0051 Mason Gd.2 0.05100 day

LB0077 labourer 0.13838 day

MT0043 Sand 0.00321 cu.m

MT0145 Cement (OPC / PSC) 0.00153 tonne

BW0182 Pointing on concrete block brick work with cement m ortar 1:3 - Cut, weather struck pointing

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.07550 day

LB0051 Mason Gd.2 0.07550 day

LB0077 labourer 0.18838 day

MT0043 Sand 0.00321 cu.m

MT0145 Cement (OPC / PSC) 0.00153 tonne

BW0183 Pointing on concrete block brick work with cement m ortar 1:3 - Raised & cut pointing

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.10100 day

LB0051 Mason Gd.2 0.10100 day

LB0077 labourer 0.23618 day

MT0043 Sand 0.00492 cu.m

MT0145 Cement (OPC / PSC) 0.00235 tonne

P&L concrete block half-brick Masonry (125 mm) in s uperstructure below floor 2 level - In cement morta r 1:4

Department of Engineering Services, MoWHS

Page 67: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 64

CHAPTER 10

SM0001

Coefficient for per cu.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.26951 day LB0077 Labour 1.11906 day MT0042 Mud dry 1.00000 cu.m MT0325 Ballies 75 to 125mm dia 0.30030 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00475 cu.m SM0005

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 1.33800 day

LB0077 Labour 2.70825 day MT0043 Sand 0.35310 cu.m MT0060 Boulder 1.00000 cu.m MT0145 Cement (OPC / PSC) 0.12540 tonne SM0006

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 1.33800 day LB0077 Labour 2.70825 day MT0043 Sand 0.35310 cu.m MT0060 Boulder 1.00000 cu.m MT0145 Cement (OPC / PSC) 0.10230 tonne SM0007

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 1.33800 day LB0077 Labour 2.70825 day MT0043 Sand 0.35310 cu.m MT0060 Boulder 1.00000 cu.m MT0145 Cement (OPC / PSC) 0.08250 tonne SM0008

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 1.42000 day LB0077 Labour 2.85537 day MT0042 Mud dry 0.39600 cu.m

MT0060 Boulder 1.00000 cu.m SM0015

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.33900 day LB0077 Labour 0.48000 day SM0016

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.29000 day SM0017

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.33900 day

LB0077 Labour 0.88000 day

P&L Random Rubble Masonry with hard stone in founda tion & plinth - Hammer dressed, in mud mortar

Extra for random rubble masonry with hard stone in superstructure above plinth, below & including floo r 2 level

Extra for random rubble masonry with hard stone in superstructure above floor 2 level

Extra for random rubble masonry work with hard ston e in square or rectangular pillars

P&L Random Rubble Masonry with hard stone in founda tion & plinth - In cement mortar 1:5

P&L Random Rubble Masonry with hard stone in founda tion & plinth - In cement mortar 1:6

Constructing rammed mud walls in superstructure inc luding the cost of form work

STONE/MUD

P&L Random Rubble Masonry with hard stone in founda tion & plinth - In cement mortar 1:4

Department of Engineering Services, MoWHS

Page 68: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 65

SM0018

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 1.77600 day LB0076 Labour 0.43800 day SM0019

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.01470 day MT0151 Water proofing compound 1.90000 kg SM0025

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 2.20000 day LB0077 Labour 2.88650 day

MT0043 Sand 0.32100 cu.m MT0060 Boulder 1.10000 cu.m MT0145 Cement (OPC / PSC) 0.15300 tonne SM0026

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 2.20000 day LB0077 Labour 2.88650 day

MT0043 Sand 0.32100 cu.m MT0060 Boulder 1.10000 cu.m MT0145 Cement (OPC / PSC) 0.11400 tonne SM0027

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 2.20000 day LB0077 Labour 2.88650 day MT0043 Sand 0.32100 cu.m MT0060 Boulder 1.10000 cu.m MT0145 Cement (OPC / PSC) 0.09300 tonne SM0028

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 2.20000 day

LB0077 Labour 2.88650 day MT0043 Sand 0.32100 cu.m MT0060 Boulder 1.10000 cu.m MT0145 Cement (OPC / PSC) 0.07500 tonne SM0035

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.33000 day LB0077 Labour 0.44000 day SM0036

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.29000 day

Providing &laying Coursed Rubble Masonry with hard stone hammer-dressed in foundation & plinth - In ce ment mortar 1:5

Providing &laying Coursed Rubble Masonry with hard stone hammer-dressed in foundation & plinth - In ce ment mortar 1:6

Extra, for C.R. masonry with hard stone in superstr ucture above plinth, below & including floor 2 leve l

Extra, for C.R. masonry with hard stone in superstr ucture above floor 2 level

Extra for random rubble masonry work with hard ston e in circular pillars

Extra for random rubble masonry work with hard ston e for mixing water-proofing Materials in cement mor tar

Providing &laying Coursed Rubble Masonry with hard stone hammer-dressed in foundation & plinth - In ce ment mortar 1:3

Providing &laying Coursed Rubble Masonry with hard stone hammer-dressed in foundation & plinth - In ce ment mortar 1:4

Department of Engineering Services, MoWHS

Page 69: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 66

SM0037

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.84000 day LB0076 Labour 0.34000 day SM0038 Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 2.09000 day LB0076 Labour 0.44000 day MT0060 Boulder 0.32000 cu.m SM0039

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.18000 day LB0077 Labour 0.07000 day SM0040

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.37000 day LB0077 Labour 0.48000 day SM0041

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.01470 day MT0151 Water proofing compound 2.30000 kg SM0050

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 1.06000 day LB0077 Labour 1.77000 day MT0060 Boulder 1.00000 cu.m SM0051

Coefficient for per cu.m Code Description Quant Units LB0051 Mason Gd.2 1.35000 day LB0077 Labour 1.77000 day MT0060 Boulder 1.10000 cu.m SM0052

Coefficient for per cu.m

Code Description Quant Units

LB0051 Mason Gd.2 1.60000 day LB0077 Labour 2.00100 day MT0060 Boulder 1.10000 cu.m SM0060

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.02063 day LB0039 Work Supervisor (Lajab) 0.01650 day LB0051 Mason Gd.2 1.08062 day LB0053 Plant Operator Gd.3 0.02310 day LB0077 Labour 2.59012 day

MP0205 Concrete Mixer(7/5 cu.ft) 0.02310 day MP0206 Concrete Vibrator(M/C5) 0.02310 day MT0043 Sand 0.14685 cu.m MT0060 Boulder 1.00000 cu.m MT0070 Crushed Rock - 20mm 0.29370 cu.m MT0145 Cement (OPC / PSC) 0.10603 tonne

Extra, for C.R masonry with hard stone in circular pillars

Extra, for C.R masonry with hard stone chisel dress ed in foundations and plinth

Extra, for C.R masonry with hard stone chisel dress ed in superstructure above plinth, below & includin g floor 2 level

Dry hand packed rubble masonry hammer dressed (faci ng), with stone-boulder > 0.04 Cu.m

Dry hand packed rubble masonry chisel dressed (faci ng) with stone-boulder > 0.04 Cu.m

Providing and laying with hard stone (average volum e 0.008 Cu.m) hand packed stone masonry in cement c oncrete mortar 1:2:4, 20mm aggregates

Extra, for C.R masonry with hard stone in square or rectangular pillars

Extra, for C.R masonry with hard stone for mixing w ater-proofing Materials

Dry hand packed rubble masonry with stone boulders >0.04 Cu.m

Department of Engineering Services, MoWHS

Page 70: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 67

SM0061

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.02063 day LB0039 Work Supervisor (Lajab) 0.01650 day LB0051 Mason Gd.2 1.08062 day LB0053 Plant Operator Gd.3 0.02310 day

LB0077 Labour 2.50012 day MP0205 Concrete Mixer(7/5 cu.ft) 0.02310 day MP0206 Concrete Vibrator(M/C5) 0.02310 day MT0043 Sand 0.15510 cu.m MT0060 Boulder 1.00000 cu.m MT0070 Crushed Rock - 20mm 0.31020 cu.m MT0145 Cement (OPC / PSC) 0.07260 tonne

SM0062

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.02063 day LB0039 Work Supervisor (Lajab) 0.01650 day

LB0051 Mason Gd.2 1.43362 day LB0053 Plant Operator Gd.3 0.02310 day LB0077 Labour 2.50012 day MP0205 Concrete Mixer(7/5 cu.ft) 0.02310 day MP0206 Concrete Vibrator(M/C5) 0.02310 day MT0043 Sand 0.14685 cu.m MT0060 Boulder 1.10000 cu.m

MT0070 Crushed Rock - 20mm 0.29370 cu.m MT0145 Cement (OPC / PSC) 0.10603 tonne SM0063

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.02063 day

LB0039 Work Supervisor (Lajab) 0.01650 day LB0051 Mason Gd.2 1.43362 day LB0053 Plant Operator Gd.3 0.02310 day LB0077 Labour 2.50012 day MP0205 Concrete Mixer(7/5 cu.ft) 0.02310 day MP0206 Concrete Vibrator(M/C5) 0.02310 day MT0043 Sand 0.15510 cu.m MT0060 Boulder 1.10000 cu.m

MT0070 Crushed Rock - 20mm 0.31020 cu.m MT0145 Cement (OPC / PSC) 0.07260 tonne SM0064

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 2.31563 day LB0039 Work Supervisor (Lajab) 0.01650 day LB0051 Mason Gd.2 0.02063 day LB0053 Plant Operator Gd.3 0.02310 day LB0077 Labour 3.22212 day MP0205 Concrete Mixer(7/5 cu.ft) 0.02310 day MP0206 Concrete Vibrator(M/C5) 0.02310 day MT0043 Sand 0.14685 cu.m MT0060 Boulder 1.10000 cu.m MT0070 Crushed Rock - 20mm 0.29370 cu.m MT0145 Cement (OPC / PSC) 0.10603 tonne

Providing and laying rubble masonry chisel dressed (facing) with hard stone (average volume 0.008 cu.m ) in concrete mortar 1:2:4 20mm aggregates

Providing and laying hammer dressed stone masonry w ith hard stone (average volume 0.008 Cu.m) in concr ete mortar 1:3:6 20mm aggregates

Providing and laying hammer dressed stone masonry w ith hard stone (average volume 0.008 Cu.m) in cemen t concrete mortar 1:2:4 20mm aggregates

P&L with hard stone (average volume 0.008 Cu.m) han d packed stone masonry in cement concrete mortar 1: 3:6, 20mm aggregates

Department of Engineering Services, MoWHS

Page 71: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 68

SM0065

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 2.31563 day LB0039 Work Supervisor (Lajab) 0.01650 day LB0051 Mason Gd.2 0.02063 day LB0053 Plant Operator Gd.3 0.02310 day LB0077 Labour 3.22212 day MP0205 Concrete Mixer(7/5 cu.ft) 0.02310 day MP0206 Concrete Vibrator(M/C5) 0.02310 day MT0043 Sand 0.15510 cu.m MT0060 Boulder 1.10000 cu.m MT0070 Crushed Rock - 20mm 0.31020 cu.m MT0145 Cement (OPC / PSC) 0.07260 tonne SM0070

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.83000 day

LB0077 Labour 0.83000 day MT0060 Boulder 1.10000 cu.m SM0071

Coefficient for per cu.m

Code Description Quant Units LB0036 Mason Gd.1 0.18000 day LB0051 Mason Gd.2 0.83000 day LB0077 Labour 0.86300 day MT0060 Boulder 1.10000 cu.m SM0072

Coefficient for per cu.m

Code Description Quant Units

LB0051 Mason Gd.2 0.53000 day LB0077 Labour 0.53000 day MT0060 Boulder 1.00000 cu.m SM0073

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.03300 day LB0051 Mason Gd.2 0.01700 day LB0077 Labour 0.09900 day MT0060 Boulder 0.04600 cu.m SM0080

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.06549 day LB0039 Work Supervisor (Lajab) 0.00175 day LB0051 Mason Gd.2 0.12879 day LB0053 Plant Operator Gd.3 0.00245 day LB0077 Labour 0.32124 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00245 day MP0206 Concrete Vibrator(M/C5) 0.00245 day MT0043 Sand 0.01645 cu.m MT0060 Boulder 0.19360 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.03290 cu.m MT0145 Cement (OPC / PSC) 0.00779 tonne

Providing and laying Hammer dressed stone edging 15 0 x 250 mm with stones including excavation, refill ing and disposal of surplus earth within 30 m lead

Providing and laying Chisel dressed dry stone solin g

Providing and laying Hand packed stone filling or s oling with stones

Providing and laying rubble masonry chisel dressed (facing) with hard stone (average volume 0.008 cu.m ) in concrete mortar 1:3:6 20mm aggregates

Providing and laying Hammer dressed dry stone solin g

Providing and laying hammer dressed 150mm thick fla t stone pavement with hammer dressed stone edging 1 50mm wide & 250mm deep on both sides, including grouting joints - With cement concrete mortar 1:3:6, 12mm aggregat e

Department of Engineering Services, MoWHS

Page 72: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 69

SM0081

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.13030 day LB0051 Mason Gd.2 0.12660 day LB0077 Labour 0.34469 day MT0043 Sand 0.00246 cu.m MT0060 Boulder 0.19360 cu.m MT0145 Cement (OPC / PSC) 0.00117 tonne SM0082

Coefficient for per sq.m

Code Description Quant Units

LB0036 Mason Gd.1 0.07260 day LB0051 Mason Gd.2 0.14530 day LB0077 Labour 0.42570 day MT0043 Sand 0.00200 cu.m MT0060 Boulder 0.24420 cu.m SM0090

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.90000 day LB0077 Labour 0.20112 day MT0043 Sand 0.00107 cu.m MT0060 Boulder 0.02300 cu.m MT0145 Cement (OPC / PSC) 0.00025 tonne SM0091

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.20000 day LB0077 Labour 0.20112 day MT0043 Sand 0.00107 cu.m MT0060 Boulder 0.03450 cu.m MT0145 Cement (OPC / PSC) 0.00025 tonne SM0092

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.50000 day LB0077 Labour 0.20112 day MT0043 Sand 0.00107 cu.m MT0060 Boulder 0.04600 cu.m MT0145 Cement (OPC / PSC) 0.00025 tonne

SM0093

Coefficient for per sq.mCode Description Quant UnitsLB0036 Mason Gd. 1 1.20000 dayLB0077 Labour 0.20000 dayMT0060 Boulder 0.03450 cu.m

SM0094

Coefficient for per sq.mCode Description Quant UnitsLB0036 Mason Gd. 1 1.50000 dayLB0077 Labour 0.20000 dayMT0060 Boulder 0.04600 cu.m

Providing and laying hammer dressed dry dolep pavin g with minimum stone thickness 30mm including prepa ration of bed

Providing and laying hammer dressed 150mm thick fla t stone pavement with hammer dressed stone edging 1 50mm wide & 250mm deep on both sides, including grouting joints - With cement mortar 1:3

Providing and laying hammer dressed 150mm thick fla t stone pavement with hammer dressed stone edging 1 50mm wide & 250mm deep on both sides, including grouting joints - With sand or earth etc.

P&L hammer dressed flat stone paving in cement mort ar 1:6 on prepared bedding (excluding the cost of b edding) - 20mm

P&L hammer dressed flat stone paving in cement mort ar 1:6 on prepared bedding (excluding the cost of b edding) - 30mm

P&L hammer dressed flat stone paving in cement mort ar 1:6 on prepared bedding (excluding the cost of b edding) - 40mm

Providing and laying hammer dressed dry dolep pavin g with minimum stone thickness 40mm including prepa ration of bed

Department of Engineering Services, MoWHS

Page 73: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 70

SM0100

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.20000 day LB0077 Labour 0.20112 day MT0043 Sand 0.00107 cu.m MT0060 Boulder 0.02300 cu.m MT0145 Cement (OPC / PSC) 0.00025 tonne SM0101

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.50000 day LB0077 Labour 0.20112 day MT0043 Sand 0.00107 cu.m MT0060 Boulder 0.03450 cu.m MT0145 Cement (OPC / PSC) 0.00025 tonne SM0102

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.90000 day LB0077 Labour 0.20112 day MT0043 Sand 0.00107 cu.m MT0060 Boulder 0.04600 cu.m MT0145 Cement (OPC / PSC) 0.00025 tonne

SM0103

Coefficient for per sq.mCode Description Quant UnitsLB0036 Mason Gd. 1 1.50000 dayLB0077 Labour 0.20000 dayMT0060 Boulder 0.03450 cu.m

SM0104

Coefficient for per sq.mCode Description Quant UnitsLB0036 Mason Gd. 1 1.90000 dayLB0077 Labour 0.20000 dayMT0060 Boulder 0.04600 cu.m

SM0110

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.09400 day LB0077 Labour 0.12789 day MT0043 Sand 0.00246 cu.m MT0145 Cement (OPC / PSC) 0.00117 tonne SM0111

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.10100 day LB0077 Labour 0.13759 day MT0043 Sand 0.00246 cu.m MT0145 Cement (OPC / PSC) 0.00117 tonne SM0112

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.20250 day LB0077 Labour 0.24078 day MT0043 Sand 0.00407 cu.m MT0145 Cement (OPC / PSC) 0.00194 tonne

P&L pointing on stone work with cement mortar 1:3 - Flush pointing

P&L pointing on stone work with cement mortar 1:3 - Raised and cut pointing

P&L all sides chisel dressed flat stone paving in c ement mortar 1:6 on prepared bedding (excluding the cost of bedding) - 40mm

P&L all sides chisel dressed flat stone paving in c ement mortar 1:6 on prepared bedding (excluding the cost of bedding) - 20mm

P&L all sides chisel dressed flat stone paving in c ement mortar 1:6 on prepared bedding (excluding the cost of bedding) - 30mm

Providing and laying chisel dressed dry dolep pavin g with minimum stone thickness 30mm including prepa ration of bed

Providing and laying chisel dressed dry dolep pavin g with minimum stone thickness 40mm including prepa ration of bed

P&L pointing on stone work with cement mortar 1:3 - Ruled pointing

Department of Engineering Services, MoWHS

Page 74: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 71

SM0120

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.53000 day LB0077 Labour 1.59000 day MT0060 Boulder 1.00000 cu.m MT0230 G.I double knotted mesh - 100 x 100 x 8-gauge 4.00000 sq.m

SM0121

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.53000 day LB0077 Labour 1.59000 day MT0060 Boulder 1.00000 cu.m MT0232 G.I double knotted mesh - 150 x 150 x 8-gauge 4.00000 sq.m SM0122

Coefficient for per cu.m

Code Description Quant Units LB0051 Mason Gd.2 0.53000 day LB0077 Labour 1.59000 day MT0060 Boulder 1.00000 cu.m

MT0240 G.I chain-link mesh - 100 x 100 x 8-gauge 4.00000 sq.m SM0130

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.65900 day LB0039 Work Supervisor (Lajab) 0.01030 day LB0051 Mason Gd.2 0.01290 day LB0077 Labour 1.24395 day MT0043 Sand 0.12339 cu.m MT0060 Boulder 0.00500 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.18400 cu.m MT0145 Cement (OPC / PSC) 0.03310 tonne SM0131

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.44000 day

LB0039 Work Supervisor (Lajab) 0.00803 day LB0051 Mason Gd.2 0.00900 day LB0077 Labour 0.82184 day MT0043 Sand 0.08116 cu.m MT0060 Boulder 0.00370 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.12900 cu.m MT0145 Cement (OPC / PSC) 0.02207 tonne SM0140

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.44000 day LB0039 Work Supervisor (Lajab) 0.00700 day LB0051 Mason Gd.2 0.00900 day LB0077 Labour 0.83568 day MT0043 Sand 0.08116 cu.m

MT0060 Boulder 0.00370 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.12900 cu.m MT0145 Cement (OPC / PSC) 0.02207 tonne

Providing & filling hand-packed stone in G.I mesh 4 mm (8swg)including supplying and weaving of mesh co mplete - Double-knotted mesh....150mm

Providing & filling hand-packed stone in G.I mesh 4 mm (8swg)including supplying and weaving of mesh co mplete - Chain-link mesh....100mm

Providing & filling hand-packed stone in G.I mesh 4 mm (8swg)including supplying and weaving of mesh co mplete - Double-knotted mesh....100mm

P&L Precast Stone Masonry blocks (1:5:8) in cement mortar 1:6 in superstructure up to floor two level - 20 cms thick

P&L Precast Stone Masonry blocks (1:5:8) in cement mortar 1:6 in foundation and plinth - 30 cms thick

P&L Precast Stone Masonry blocks (1:5:8) in cement mortar 1:6 in foundation and plinth - 20 cms thick

Department of Engineering Services, MoWHS

Page 75: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 72

SM0141

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.33000 day

LB0039 Work Supervisor (Lajab) 0.00525 day LB0051 Mason Gd.2 0.00680 day LB0077 Labour 0.62670 day MT0043 Sand 0.06084 cu.m MT0060 Boulder 0.00270 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.09700 cu.m MT0145 Cement (OPC / PSC) 0.01660 tonne SM0142

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.22000 day LB0039 Work Supervisor (Lajab) 0.00350 day LB0051 Mason Gd.2 0.00450 day LB0077 Labour 0.43794 day MT0043 Sand 0.04063 cu.m MT0060 Boulder 0.00150 cu.m

MT0071 Crushed Rock - 12.5 - 6mm 0.06500 cu.m MT0145 Cement (OPC / PSC) 0.01105 tonne SM0150

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.29000 day

P&L Precast Stone Masonry blocks (1:5:8) in cement mortar 1:6 in superstructure up to floor two level - 15 cms thick

P&L Precast Stone Masonry blocks (1:5:8) in cement mortar 1:6 in superstructure up to floor two level - 10 cms thick

Extra, for Precast Stone Masonry blocks in superstr ucture above floor two level...per floor

Department of Engineering Services, MoWHS

Page 76: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 73

CHAPTER 11

WW0001

Coefficient for per cu.m6

Code Description Quant Units LB0021 Carpenter Gd.1 6.62100 day LB0033 Carpenter Gd.2 6.62100 day LB0077 Labour 6.62100 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 1.05000 cu.m WW0002

Coefficient for per cu.m

Code Description Quant Units LB0021 Carpenter Gd.1 6.62100 day LB0033 Carpenter Gd.2 6.62100 day LB0077 Labour 6.62100 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 1.05000 cu.m WW0003

Coefficient for per cu.m

Code Description Quant Units LB0021 Carpenter Gd.1 6.62100 day LB0033 Carpenter Gd.2 6.62100 day LB0077 Labour 6.62100 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 1.05000 cu.m WW0010

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.13250 day LB0052 Painter Gd.1 0.00248 day LB0076 Labour 0.00248 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.00066 cu.m MT0714 Pink primer, for wood 0.00600 litre WW0011

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.13250 day LB0052 Painter Gd.1 0.00279 day LB0076 Labour 0.00279 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.00110 cu.m MT0714 Pink primer, for wood 0.00675 litre WW0020

Coefficient for per cu.m

Code Description Quant Units LB0033 Carpenter Gd.2 3.50000 day LB0039 Work Supervisor (Lajab) 3.50000 day LB0052 Painter Gd.1 0.03990 day LB0077 Labour 7.03990 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 1.05000 cu.m MT0735 Wood preservative -Brown 0.21000 litre WW0021

Coefficient for per cu.m

Code Description Quant Units LB0033 Carpenter Gd.2 3.50000 day LB0039 Work Supervisor (Lajab) 3.50000 day LB0052 Painter Gd.1 0.03990 day LB0077 Labour 7.03990 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 1.05000 cu.m MT0735 Wood preservative -Brown 0.21000 litre

Providing & fixing blue pine moulded beading to doo r, window frames with iron screws including plugs, priming coat on unexposed surfaces - 50 x 12 mm

Providing & fixing blue pine moulded beading to doo r, window frames with iron screws including plugs, priming coat on unexposed surfaces - 50 x 20 mm

Providing & fixing joists, including hoisting, appl ying wood preservative on unexposed surfaces - Blue pine

Providing & fixing joists, including hoisting, appl ying wood preservative on unexposed surfaces - Mixe d Conifer

Providing & fixing in position dressed wood work in frames of doors, windows, clerestory windows and o ther frames, wrought and framed - Blue pine

WOOD WORK

Providing & fixing in position dressed wood work in frames of doors, windows, clerestory windows and o ther frames, wrought and framed - Champ wood

Providing & fixing in position dressed wood work in frames of doors, windows, clerestory windows and o ther frames, wrought and framed - Mixed Conifer

Department of Engineering Services, MoWHS

Page 77: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 74

WW0030

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.10200 day LB0077 Labour 0.07000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00610 cu.m WW0035

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 1.00000 day LB0033 Carpenter Gd.2 1.00000 day LB0052 Painter Gd.1 0.01900 day LB0077 Labour 1.01900 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.06740 cu.m MT0735 Wood preservative -Brown 0.20000 litre WW0036

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 1.25000 day LB0033 Carpenter Gd.2 1.25000 day LB0052 Painter Gd.1 0.03990 day LB0077 Labour 1.53990 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.09860 cu.m MT0735 Wood preservative -Brown 0.30000 litre WW0037

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 1.00000 day LB0033 Carpenter Gd.2 1.00000 day LB0052 Painter Gd.1 0.05700 day LB0077 Labour 1.01900 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.09790 cu.m MT0735 Wood preservative -Brown 0.33000 litre WW0038

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.50000 day LB0033 Carpenter Gd.2 0.50000 day LB0052 Painter Gd.1 0.03800 day LB0077 Labour 1.04370 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.03338 cu.m MT0735 Wood preservative -Brown 0.20000 litre WW0039

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.86000 day LB0033 Carpenter Gd.2 0.86000 day LB0077 Labour 0.14300 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.07600 cu.m

Providing & fixing Eaves board (225x25mm) with moul ding fitted and fixed with necessary screws - Mixed Conifer

Providing, making & fixing woodwork dressed in trad itional cornices complete as per standard design in Mixed Conifer, including applying wood preservative on unexposed surfaces, excluding decorative painting

(Measurement to be taken along the cornice and wall junction line) - At floor one level including lhan glag

Providing, making & fixing woodwork dressed in trad itional cornices complete as per standard design in Mixed Conifer, including applying wood preservative on unexposed surfaces, excluding decorative painting

(Measurement to be taken along the cornice and wall junction line) - At all other floor levels (exclud ing phana)

Providing, making & fixing woodwork dressed in trad itional cornices complete as per standard design in Mixed Conifer, including applying wood preservative on unexposed surfaces, excluding decorative painting

(Measurement to be taken along the cornice and wall junction line) - For single-storeyed structure inc luding phana

Providing, making & fixing woodwork dressed in trad itional cornices complete as per standard design in Mixed Conifer, including applying wood preservative on unexposed surfaces, excluding decorative painting

(Measurement to be taken along the cornice and wall junction line) - Phana

Providing, making & fixing woodwork dressed in trad itional cornices complete as per standard design in Mixed Conifer, including applying wood preservative on unexposed surfaces, excluding decorative painting

(Measurement to be taken along the cornice and wall junction line) - Lintel level

Department of Engineering Services, MoWHS

Page 78: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 75

WW0045

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 5.05000 day LB0077 Labour 1.05300 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.03200 cu.m WW0046

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 5.05000 day LB0077 Labour 1.05300 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.03200 cu.m WW0055

Coefficient for per cu.m

Code Description Quant Units LB0033 Carpenter Gd.2 7.53300 day LB0077 Labour 7.53300 day MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 1.05000 cu.m WW0060

Coefficient for per cu.m

Code Description Quant Units LB0021 Carpenter Gd.1 8.30000 day LB0033 Carpenter Gd.2 8.30000 day LB0077 Labour 8.30000 day MT0330 Rough-sawn timber (urban rate) - Class 'B'/ (Mixed Conifer) 1.05000 cu.m WW0061

Coefficient for per cu.m

Code Description Quant Units LB0021 Carpenter Gd.1 8.30000 day LB0033 Carpenter Gd.2 8.30000 day LB0077 Labour 8.30000 day MT0331 Rough-sawn timber (urban rate) - Class 'A'/ (Blue pine, Champ) 1.05000 cu.m WW0070

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.27870 day LB0077 Labour 0.16630 day MT0342 12mm, commercial ply 1.05000 sq.m WW0075

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.24000 day LB0033 Carpenter Gd.2 0.27000 day LB0077 Labour 0.24000 day MT0330 Rough-sawn timber (urban rate) - Class 'B' (Mixed Conifer) 0.00420 cu.m MT0335 Asbestos Cement Plain Sheet 4mm thick - 1.2 m x 1.2 m 0.70600 each WW0080

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.27000 day LB0077 Labour 0.24000 day MT0345 Gypsum Wallboard - 10mm 1.05000 sq.m

Providing & fixing to frames (wall or ceiling), pla in 4mm A.C sheet including 50 x 12.5 mm Mixed Conif er beading (excluding cost of frame)

Providing and fixing to frames (wall or ceiling) Gy psum plaster board including finishing of joints sm ooth complete (excluding cost of frame) - 10mm thick

Providing & fixing traditional wooden Tshegay for w indows/railing etc. as per standard design - In mix ed conifer

Providing & fixing traditional wooden Tshegay for w indows/railing etc. as per standard design - In blu e pine

Providing & fixing Mixed Conifer (undressed) in wal l-frames etc

Providing & fixing roof framing, in trusses, purlin s, rafters, posts, post plates including hoisting, etc (excluding steel items) - Mixed Conifer

Providing & fixing roof framing, in trusses, purlin s, rafters, posts, post plates including hoisting, etc (excluding steel items) - Blue Pine

Providing & fixing gussets for timber trusses inclu ding wood preservative (coal tar) - 12mm phenolic p lywood

Department of Engineering Services, MoWHS

Page 79: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 76

WW0081

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.27000 day LB0077 Labour 0.24000 day MT0346 Gypsum Wallboard - 12mm 1.05000 sq.m WW0082

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.27000 day LB0077 Labour 0.24000 day MT0347 Gypsum Wallboard - 15mm 1.05000 sq.m WW0090

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.20250 day LB0052 Painter Gd.1 0.03100 day LB0077 Labour 0.13100 day MT0331 Rough-sawn timber (urban rate) - Class 'A' (Blue pine, Champ) 0.01320 cu.m MT0714 Pink primer, for wood 0.07500 litre WW0091

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.20250 day LB0077 Labour 0.10000 day MT0331 Rough-sawn timber (urban rate) - Class 'A' (Blue pine, Champ) 0.02200 cu.m WW0100

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0365 Plain Particle Board - 6mm 1.00000 sq.m WW0101

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0366 Plain Particle Board - 10mm 1.00000 sq.m WW0102

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0367 Plain Particle Board - 12mm 1.00000 sq.m WW0103

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0368 Plain Particle Board - 18mm 1.00000 sq.m

Providing & fixing to frames (wall or ceiling) Plai n Particle Board Lining with necessary nails etc. c omplete (excluding cost of frames) - 12mm

Providing & fixing to frames (wall or ceiling) Plai n Particle Board Lining with necessary nails etc. c omplete (excluding cost of frames) - 18mm

Providing & fixing to frames (wall or ceiling) Plai n Particle Board Lining with necessary nails etc. c omplete (excluding cost of frame) - 6mm

Providing & fixing to frames (wall or ceiling) Plai n Particle Board Lining with necessary nails etc. c omplete (excluding cost of frames) - 10mm

Providing and fixing to frames (wall or ceiling) Gy psum plaster board including finishing of joints sm ooth complete (excluding cost of frame) - 12mm thick

Providing and fixing to frames (wall or ceiling) Gy psum plaster board including finishing of joints sm ooth complete (excluding cost of frame) - 15mm thick

Providing & fixing to frames (wall or ceiling) blue pine plain lining, tongued and grooved, including necessary fixtures, wooden plugs and priming coat on unexposed surfaces (excluding cost of frames) - 12 mm thick

Providing & fixing to frames (wall or ceiling) blue pine plain lining, tongued and grooved, including necessary fixtures, wooden plugs and priming coat on unexposed surfaces (excluding cost of frames) - 20 mm thick

Department of Engineering Services, MoWHS

Page 80: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 77

WW0110

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0375 Pre-laminated Particle Board (one side) - 8mm 1.00000 sq.m WW0111

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0376 Pre-laminated Particle Board (one side) - 10mm 1.00000 sq.m WW0112

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0377 Pre-laminated Particle Board (one side) - 12mm 1.00000 sq.m WW0113

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0378 Pre-laminated Particle Board (one side) - 18mm 1.00000 sq.m WW0120

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0350 Pre-laminated (both sides) Bison panel - 6mm 1.00000 sq.m WW0121

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0351 Pre-laminated (both sides) Bison panel - 8mm 1.00000 sq.m WW0122

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0352 Pre-laminated (both sides) Bison panel - 10mm 1.00000 sq.m WW0123

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0353 Pre-laminated (both sides) Bison panel - 12mm 1.00000 sq.m WW0124

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0354 Pre-laminated (both sides) Bison panel - 16mm 1.00000 sq.m

Providing & fixing Pre-laminated Particle Board Lin ing with necessary nails etc. complete (excluding c ost of frame) - 12 mm

Providing & fixing Pre-laminated Particle Board Lin ing with necessary nails etc. complete (excluding c ost of frame) - 18 mm

Providing & fixing bison panel (pre-laminated both sides for wall/ceiling) lining with necessary nails /screws etc. complete, excluding the cost of frame) - 6 mm

Providing & fixing bison panel (pre-laminated both sides for wall/ceiling) lining with necessary nails /screws etc. complete, excluding the cost of frame) - 8 mm

Providing & fixing bison panel (pre-laminated both sides for wall/ceiling) lining with necessary nails /screws etc. complete, excluding the cost of frame) - 10 mm

Providing & fixing bison panel (pre-laminated both sides for wall/ceiling) lining with necessary nails /screws etc. complete, excluding the cost of frame) - 12 mm

Providing & fixing bison panel (pre-laminated both sides for wall/ceiling) lining with necessary nails /screws etc. complete, excluding the cost of frame) - 16 mm

Providing & fixing Pre-laminated Particle Board Lin ing with necessary nails etc. complete (excluding c ost of frame) - 10 mm

Providing & fixing Pre-laminated Particle Board Lin ing with necessary nails etc. complete (excluding c ost of frame) - 8 mm

Department of Engineering Services, MoWHS

Page 81: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 78

WW0125

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0355 Pre-laminated (both sides) Bison panel - 20mm 1.00000 sq.m WW0130

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.24000 day LB0033 Carpenter Gd.2 0.27000 day LB0077 Labour 0.24000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00420 cu.m MT0340 4mm, commercial ply 1.05000 sq.m WW0131

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.24000 day LB0033 Carpenter Gd.2 0.27000 day LB0077 Labour 0.24000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00420 cu.m MT0341 4mm, teak ply 1.05000 sq.m WW0132

Coefficient for per sq.m

Code Description Quant UnitsLB0021 Carpenter Gd.1 0.24000 dayLB0033 Carpenter Gd.2 0.27000 dayLB0077 Labour 0.24000 dayMT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00420 cu.mMT0342 6mm, commercial ply 1.05000 sq.m

WW0140

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0400 Wall panelling - 19mm, blue pine 1.00000 sq.m WW0141

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0403 Wall panelling - 19mm, mixed conifer 1.00000 sq.m WW0142

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0401 Wall panelling - 15mm, blue pine 1.00000 sq.m WW0150

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 2.10420 day LB0036 Mason Gd.1 0.10420 day LB0052 Painter Gd.1 0.03100 day LB0077 Labour 0.60390 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02100 cu.m MT0714 Pink primer, for wood 0.07500 litre

Providing & fixing Plywood lining with necessary na ils etc. including beading complete (excluding cost of frame) - 4 mm, commercial

Providing & fixing Plywood lining with necessary na ils etc. including beading complete (excluding cost of frame) - 4 mm, teak

Providing & fixing bison panel (pre-laminated both sides for wall/ceiling) lining with necessary nails /screws etc. complete, excluding the cost of frame) - 20 mm

Providing & fixing Pre-fabricated wall panelling pr ofiles with necessary nails etc. complete but exclu ding the cost of frame) - 19 mm, mixed conifer

Providing & fixing Pre-fabricated wall panelling pr ofiles with necessary nails etc. complete but exclu ding the cost of frame) - 15 mm, blue pine

Providing & fixing wooden skirting in mixed conifer with necessary nails or screws complete - 20 mm

Providing & fixing Plywood lining with necessary na ils etc. including beading complete (excluding cost of frame) - 6 mm, commercial

Providing & fixing Pre-fabricated wall panelling pr ofiles with necessary nails etc. complete but exclu ding the cost of frame) - 19 mm, blue pine

Department of Engineering Services, MoWHS

Page 82: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 79

WW0151

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 2.10420 day LB0036 Mason Gd.1 0.10420 day LB0052 Painter Gd.1 0.03100 day LB0077 Labour 0.60390 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02630 cu.m MT0714 Pink primer, for wood 0.07500 litre WW0160

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.10760 day LB0036 Mason Gd.1 0.27000 day LB0077 Labour 0.51310 day MT0043 Sand 0.04794 cu.m MT0145 Cement (OPC / PSC) 0.01702 tonne MT0391 Bamboo - 75mm dia 13.30000 m WW0161

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.10760 day LB0036 Mason Gd.1 0.27000 day LB0077 Labour 0.51310 day MT0043 Sand 0.04794 cu.m MT0145 Cement (OPC / PSC) 0.01389 tonne MT0391 Bamboo - 75mm dia 13.30000 m WW0162

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.10760 day LB0036 Mason Gd.1 0.27000 day LB0077 Labour 0.51310 day MT0043 Sand 0.04794 cu.m MT0145 Cement (OPC / PSC) 0.01120 tonne MT0391 Bamboo - 75mm dia 13.30000 m WW0163

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.10760 day LB0077 Labour 0.19166 day MT0042 Mud dry 0.05376 cu.m MT0391 Bamboo - 75mm dia 13.30000 m WW0164

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.10760 day LB0077 Labour 0.38750 day MT0042 Mud dry 0.14400 cu.m MT0391 Bamboo - 75mm dia 13.30000 m WW0165

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.04230 day MT0392 Bamboo mat 1.05000 sq.m

Providing & fixing 75mm thick split bamboo wall inc luding grooving frames, 20mm plaster cement mortar 1:4 both sides (excluding cost of frame)

Providing & fixing 75mm thick split bamboo wall inc luding grooving frames, 20mm plaster cement mortar 1:5 both sides (excluding cost of frame)

Providing & fixing 75mm thick split bamboo wall inc luding grooving frames, 20mm plaster cement mortar 1:6 both sides ( excluding cost of frame)

Providing & fixing 75mm thick split bamboo wall inc luding grooving frames, 20mm mud plaster both sides ( excluding cost of frame)

Providing & fixing wooden skirting in mixed conifer with necessary nails or screws complete - 25 mm

Providing & fixing 150mm thick split bamboo wall in cluding grooving frames, 60mm mud plaster both side s (excluding cost of frame)

Providing & fixing split Bamboo Matting (excluding the cost of framing and beading)

Department of Engineering Services, MoWHS

Page 83: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 80

WW0170

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 1.56567 day LB0033 Carpenter Gd.2 0.85727 day LB0036 Mason Gd.1 0.05000 day LB0077 Labour 0.77397 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.05252 cu.m MT0655 Plain Glass - 3mm thick 0.23670 sq.m WW0171

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 1.52793 day LB0033 Carpenter Gd.2 0.81953 day LB0036 Mason Gd.1 0.05000 day LB0077 Labour 0.73623 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04654 cu.m MT0655 Plain Glass - 3mm thick 0.23670 sq.m WW0172

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 1.56567 day LB0033 Carpenter Gd.2 0.85727 day LB0036 Mason Gd.1 0.05000 day LB0077 Labour 0.77397 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.05252 cu.m MT0655 Plain Glass - 3mm thick 0.23670 sq.m WW0173

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 1.52793 day LB0033 Carpenter Gd.2 0.81953 day LB0036 Mason Gd.1 0.05000 day LB0077 Labour 0.73623 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.04654 cu.m MT0655 Plain Glass - 3mm thick 0.23670 sq.m WW0180

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0033 Carpenter Gd.2 0.16949 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.10385 day LB0077 Labour 0.56334 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02362 cu.m MT0340 4mm, commercial ply 2.20000 sq.m MT0714 Pink primer, for wood 0.25125 litre WW0181

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0033 Carpenter Gd.2 0.12655 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.10385 day LB0077 Labour 0.52040 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01764 cu.m MT0340 4mm, commercial ply 2.20000 sq.m MT0714 Pink primer, for wood 0.25125 litre

Providing & fixing Panelled or Panelled-&-Glazed pa rtition, single-central-panelling including frame e tc complete - 100mm framing, 38mm thick Mixed Conifer panelling

Providing & fixing Panelled or Panelled-&-Glazed pa rtition, single-central-panelling including frame e tc complete - 75mm framing, 38mm thick Mixed Conifer panelling

Providing & fixing Panelled or Panelled-&-Glazed pa rtition, single-central-panelling including frame e tc complete - 100mm framing, 38mm thick Champ or Blue Pine panelling

Providing & fixing Panelled or Panelled-&-Glazed pa rtition, single-central-panelling including frame e tc complete - 75mm framing, 38mm thick Champ or Blue Pine panelling

Providing & fixing Panelled or Panelled-&-Glazed, P lywood panelling from both sides including frame - 100mm framing, 4mm Commercial Ply

Providing & fixing Panelled or Panelled-&-Glazed, P lywood panelling from both sides including frame - 75mm framing, 4mm Commercial Ply

Department of Engineering Services, MoWHS

Page 84: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 81

WW0182

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0033 Carpenter Gd.2 0.16949 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.10385 day LB0077 Labour 0.56334 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02362 cu.m MT0341 4mm, teak ply 2.20000 sq.m MT0714 Pink primer, for wood 0.25125 litre WW0183

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0033 Carpenter Gd.2 0.12655 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.09672 day LB0077 Labour 0.51327 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01764 cu.m MT0341 4mm, teak ply 2.20000 sq.m MT0714 Pink primer, for wood 0.23400 litre WW0190

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.30000 day LB0033 Carpenter Gd.2 0.16949 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.10385 day LB0077 Labour 0.57334 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02362 cu.m MT0402 Wall panelling - 12mm, blue pine 2.00000 sq.m MT0714 Pink primer, for wood 0.25125 litre WW0191

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.30000 day LB0033 Carpenter Gd.2 0.12655 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.09672 day LB0077 Labour 0.52327 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01764 cu.m MT0402 Wall panelling - 12mm, blue pine 2.00000 sq.m MT0714 Pink primer, for wood 0.23400 litre WW0192

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.30000 day LB0033 Carpenter Gd.2 0.16949 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.10385 day LB0077 Labour 0.57334 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02362 cu.m MT0404 Wall panelling - 12mm, mixed conifer 2.00000 sq.m MT0714 Pink primer, for wood 0.25125 litre WW0193

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.30000 day LB0033 Carpenter Gd.2 0.12655 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.09672 day LB0077 Labour 0.52327 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01764 cu.m MT0404 Wall panelling - 12mm, mixed conifer 2.00000 sq.m MT0714 Pink primer, for wood 0.23400 litre

Providing & fixing Panelled with Pre-fabricated pro files from both sides including the frame and prime coat on concealed face - 100mm, 12mm mixed conifer

Providing & fixing Panelled with Pre-fabricated pro files from both sides including the frame and prime coat on concealed face - 75mm, 12mm mixed conifer

Providing & fixing Panelled or Panelled-&-Glazed, P lywood panelling from both sides including frame - 100mm framing, 4mm Teak Ply

Providing & fixing Panelled or Panelled-&-Glazed, P lywood panelling from both sides including frame - 75mm framing, 4mm Teak Ply

Providing & fixing Panelled with Pre-fabricated pro files from both sides including the frame and prime coat on concealed face - 100mm, 12mm blue pine

Providing & fixing Panelled with Pre-fabricated pro files from both sides including the frame and prime coat on concealed face - 75mm, 12mm blue pine

Department of Engineering Services, MoWHS

Page 85: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 82

WW0194

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.30000 day LB0033 Carpenter Gd.2 0.16949 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.10385 day LB0077 Labour 0.57334 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02362 cu.m MT0405 Wall panelling - 12mm, Champ wood 2.00000 sq.m MT0714 Pink primer, for wood 0.25125 litre WW0195

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.30000 day LB0033 Carpenter Gd.2 0.12655 day LB0036 Mason Gd.1 0.05000 day LB0052 Painter Gd.1 0.09672 day LB0077 Labour 0.52327 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01764 cu.m MT0405 Wall panelling - 12mm, Champ wood 2.00000 sq.m MT0714 Pink primer, for wood 0.23400 litre WW0200

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.64000 day LB0033 Carpenter Gd.2 1.16000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0077 Labour 0.53000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.02400 cu.m MT0531 Anodised Aluminium Fittings: Butt Hinges - 75mm 3.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m WW0201

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.44000 day LB0033 Carpenter Gd.2 0.73000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0077 Labour 0.47000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02400 cu.m MT0531 Anodised Aluminium Fittings: Butt Hinges - 75mm 3.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m WW0210

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.66200 day LB0033 Carpenter Gd.2 1.22700 day LB0077 Labour 0.58000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.03200 cu.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each MT0532 Anodised Aluminium Fittings: Butt Hinges - 50mm 1.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m WW0211

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.44000 day LB0033 Carpenter Gd.2 0.89400 day LB0077 Labour 0.44000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.03200 cu.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each MT0532 Anodised Aluminium Fittings: Butt Hinges - 50mm 1.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m

Providing & fixing 25mm thick Panelled or glazed Sh utters for cup-boards etc. complete including hinge s - Champ wood

Providing & fixing 25mm thick Panelled or glazed Sh utters for cup-boards etc. complete including hinge s - Mixed Conifer

Providing & fixing 35mm thick Panelled or glazed do ors and windows Shutters etc. complete including hi nges - Champ wood

Providing & fixing 35mm thick Panelled or glazed do ors and windows Shutters etc. complete including hi nges - Mixed Conifer

Providing & fixing Panelled with Pre-fabricated pro files from both sides including the frame and prime coat on concealed face - 100mm, 12mm champ wood

Providing & fixing Panelled with Pre-fabricated pro files from both sides including the frame and prime coat on concealed face - 75mm, 12mm champ wood

Department of Engineering Services, MoWHS

Page 86: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 83

WW0220

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.66200 day LB0033 Carpenter Gd.2 1.22700 day LB0077 Labour 0.58000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.03400 cu.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each MT0532 Anodised Aluminium Fittings: Butt Hinges - 50mm 1.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m WW0221

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.44000 day LB0033 Carpenter Gd.2 0.89400 day LB0077 Labour 0.44000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.03400 cu.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each MT0532 Anodised Aluminium Fittings: Butt Hinges - 50mm 1.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m WW0230

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.66200 day LB0033 Carpenter Gd.2 1.16000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0077 Labour 0.58000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.03710 cu.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each MT0532 Anodised Aluminium Fittings: Butt Hinges - 50mm 1.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m WW0231

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.44000 day LB0033 Carpenter Gd.2 0.81000 day LB0039 Work Supervisor (Lajab) 0.08300 day LB0077 Labour 0.44000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.03710 cu.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each MT0532 Anodised Aluminium Fittings: Butt Hinges - 50mm 1.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m WW0240

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.66200 day LB0033 Carpenter Gd.2 1.16000 day LB0039 Work Supervisor (Lajab) 0.07000 day LB0077 Labour 0.58000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.04200 cu.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each MT0532 Anodised Aluminium Fittings: Butt Hinges - 50mm 1.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m WW0241

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.44000 day LB0033 Carpenter Gd.2 0.81000 day LB0039 Work Supervisor (Lajab) 0.08000 day LB0077 Labour 0.44000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04200 cu.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 4.00000 each MT0655 Plain Glass - 3mm thick 0.46000 sq.m

Providing & fixing 44mm thick Panelled or glazed do ors and windows Shutters etc. complete including hi nges - Champ wood

Providing & fixing 44mm thick Panelled or glazed do ors and windows Shutters etc. complete including hi nges - Mixed Conifer

Providing & fixing 50mm thick Panelled or glazed do ors and windows Shutters etc. complete including hi nges - Champ wood

Providing & fixing 50mm thick Panelled or glazed do ors and windows Shutters etc. complete including hi nges - Mixed Conifer

Providing & fixing 38mm thick Panelled or glazed do ors and windows Shutters etc. complete including hi nges - Champ wood

Providing & fixing 38mm thick Panelled or glazed do ors and windows Shutters etc. complete including hi nges - Mixed Conifer

Department of Engineering Services, MoWHS

Page 87: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 84

WW0250

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.81000 day LB0033 Carpenter Gd.2 0.58000 day LB0039 Work Supervisor (Lajab) 0.06500 day LB0077 Labour 0.65000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.01800 cu.m

MT0410Galv. mild steel wire gauze, 85G (0.85mm average width of aperture), 0.56mm dia. 0.66000 sq.m

MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each WW0251

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.44000 day LB0033 Carpenter Gd.2 0.35000 day LB0039 Work Supervisor (Lajab) 0.06500 day LB0077 Labour 0.33000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01800 cu.m

MT0410Galv. mild steel wire gauze, 85G (0.85mm average width of aperture), 0.56mm dia. 0.66000 sq.m

MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each WW0260

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.81000 day LB0033 Carpenter Gd.2 0.58000 day LB0039 Work Supervisor (Lajab) 0.06500 day LB0077 Labour 0.65000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.02410 cu.m

MT0410Galv. mild steel wire gauze, 85G (0.85mm average width of aperture), 0.56mm dia. 0.66000 sq.m

MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each WW0261

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.44000 day LB0033 Carpenter Gd.2 0.35000 day LB0039 Work Supervisor (Lajab) 0.06500 day LB0077 Labour 0.33000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02410 cu.m MT0410 Galv. mild steel wire gauze, 85G (0.85mm average width of aperture), 0.56mm dia. 0.66000 sq.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each WW0270

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.81000 day LB0033 Carpenter Gd.2 0.58000 day LB0039 Work Supervisor (Lajab) 0.06500 day LB0077 Labour 0.65000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.02600 cu.m MT0410 Galv. mild steel wire gauze, 85G (0.85mm average width of aperture), 0.56mm dia. 0.66000 sq.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each WW0271

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.44000 day LB0033 Carpenter Gd.2 0.35000 day LB0039 Work Supervisor (Lajab) 0.06500 day LB0077 Labour 0.33000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02600 cu.m MT0410 Galv. mild steel wire gauze, 85G (0.85mm average width of aperture), 0.56mm dia. 0.66000 sq.m MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 3.00000 each

Providing & fixing Wire-gauze Shutters 25mm for doo rs & windows using galvanised M.S. wire-gauze 0.56m m dia wire including the cost of hinges - Champ wood

Providing & fixing Wire-gauze Shutters 25mm for doo rs & windows using galvanised M.S. wire-gauze 0.56m m dia wire including the cost of hinges - Mixed Conifer

Providing & fixing Wire-gauze Shutters 38mm for doo rs & windows using galvanised M.S. wire-gauze 0.56m m dia wire including the cost of hinges - Champ wood

Providing & fixing Wire-gauze Shutters 38mm for doo rs & windows using galvanised M.S. wire-gauze 0.56m m dia wire including the cost of hinges - Mixed Conifer

Providing & fixing Wire-gauze Shutters 35mm for doo rs & windows using galvanised M.S. wire-gauze 0.56m m dia wire including the cost of hinges - Champ wood

Providing & fixing Wire-gauze Shutters 35mm for doo rs & windows using galvanised M.S. wire-gauze 0.56m m dia wire including the cost of hinges - Mixed Conifer

Department of Engineering Services, MoWHS

Page 88: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 85

WW0280

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 1.32000 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0077 Labour 0.33000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.03600 cu.m MT0615 Mild Steel: Butt Hinges - 100mm 2.00000 each WW0281

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 1.32000 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0077 Labour 0.33000 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.03600 cu.m MT0615 Mild Steel: Butt Hinges - 100mm 2.00000 each WW0282

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 1.32000 day LB0039 Work Supervisor (Lajab) 0.10000 day LB0077 Labour 0.33000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.03600 cu.m MT0615 Mild Steel: Butt Hinges - 100mm 2.00000 each WW0290

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 1.00000 day LB0039 Work Supervisor (Lajab) 0.05200 day LB0077 Labour 0.21000 day MT0182 Rolled sections (250 MPa) - Flats 1.83000 kg MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04700 cu.m WW0295

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 1.10000 day LB0039 Work Supervisor (Lajab) 0.09000 day LB0077 Labour 0.55000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02960 cu.m MT0615 Mild Steel: Butt Hinges - 100mm 1.88000 each MT0617 Mild Steel: Butt Hinges - 50mm 0.62500 each WW0300

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.48000 day LB0033 Carpenter Gd.2 0.68000 day LB0039 Work Supervisor (Lajab) 0.11000 day LB0077 Labour 0.48000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.03000 cu.m MT0616 Mild Steel: Butt Hinges - 75mm 4.30000 each MT0617 Mild Steel: Butt Hinges - 50mm 2.15000 each WW0301

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.72000 day LB0077 Labour 0.36000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00510 cu.m

Providing & fixing battened and framed door shutter s, Mixed Conifer excluding the cost of hinges - 38m m

Providing & fixing 38mm thick louvered shutters for windows, doors with fixed 12mm Venetians, in Mixed Conifer excluding the cost of hinges

Providing & fixing battened garage door with ledges and braces (38mm) in Mixed Conifer, including moun tings etc complete - 22 mm

Providing & fixing Battened door & window shutters 20mm, with ledges and braces (25 mm), including the cost of hinges - Champ wood

Providing & fixing Battened door & window shutters 20mm, with ledges and braces (25 mm), including the cost of hinges - Blue pine

Providing & fixing Mixed Conifer Venetians 50mm wid e, 10mm thick at 45mm apart in ventilators above do ors (excluding frame)

Providing & fixing Battened door & window shutters 20mm, with ledges and braces (25 mm), including the cost of hinges - Mixed Conifer

Department of Engineering Services, MoWHS

Page 89: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 86

WW0310

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.43000 day LB0033 Carpenter Gd.2 0.57000 day LB0039 Work Supervisor (Lajab) 0.06000 day LB0077 Labour 0.29000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01700 cu.m WW0311

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.68100 day LB0033 Carpenter Gd.2 0.57000 day LB0039 Work Supervisor (Lajab) 0.06000 day LB0077 Labour 0.79000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.03000 cu.m MT0615 Mild Steel: Butt Hinges - 100mm 3.31000 each MT0617 Mild Steel: Butt Hinges - 50mm 1.32500 each WW0320

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.70000 day LB0039 Work Supervisor (Lajab) 0.02500 day LB0077 Labour 0.28000 day MT0182 Rolled sections (250 MPa) - Flats 8.23000 kg MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04000 cu.m WW0325

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.04000 day LB0033 Carpenter Gd.2 0.00800 day LB0077 Labour 0.01200 day MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 1.10000 kg WW0326

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01300 day LB0033 Carpenter Gd.2 0.00700 day LB0077 Labour 0.01700 day MT0182 Rolled sections (250 MPa) - Flats 0.20000 kg MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 0.91000 kg WW0327

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.08300 day LB0077 Labour 0.16800 day MT0182 Rolled sections (250 MPa) - Flats 1.10000 kg WW0328

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.27000 day LB0077 Labour 0.20000 day MT0216 Welded Mesh - Expanded Metal (19mm x 3mm x 16 gauge) 1.10000 sq.m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00450 cu.m WW0335

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0356 Pre-laminated (both sides) Bison panel - 25mm 1.00000 sq.m

Providing & fixing expanded metal 20x60mm strands 3 .25x1.6mm including 60x20mm beading of Mixed Conife r

Providing & fixing Flush Door shutters with pre-la minated bison panel - 25mm

Providing & fixing Compound Gate including hinge-su pports complete as per standard design- Mixed Conif er

Providing & fixing M.S. round or square bars in win dow frames

Providing & fixing M.S. round or square bars with M .S. flats in window frames

Providing & fixing ornamental steel grills in frame s with M.S. flats & bars including round headed bol ts and nuts etc.

Providing & fixing plain trellis of 38x12mm laths w ith 38mm gap (excluding frames) including fixing be ading 50x12mm with Mixed Conifer

Providing & fixing Door & window shutters of plain trellis of 38x12mm laths with 38mm gap (excluding f rame) including fixing beading 50x12mm with Mixed conifer

Department of Engineering Services, MoWHS

Page 90: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 87

WW0336

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0357 Pre-laminated (both sides) Bison panel - 30mm 1.00000 sq.m WW0345

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0415 Flush Door, block board core, commercial ply veneer, U\F bonded - 25mm 1.00000 sq.m WW0346

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0416 Flush Door, block board core, commercial ply veneer, U\F bonded - 30mm 1.00000 sq.m WW0347

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0417 Flush Door, block board core, commercial ply veneer, U\F bonded - 35mm 1.00000 sq.m WW0348

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0418 Flush Door, block board core, commercial ply veneer, U\F bonded - 40mm 1.00000 sq.m WW0355

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0425 Flush Door, block board core, teak ply veneer, U\F bonded - 25mm 1.00000 sq.m WW0356

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0426 Flush Door, block board core, teak ply veneer, U\F bonded - 30mm 1.00000 sq.m WW0357

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0427 Flush Door, block board core, teak ply veneer, U\F bonded - 35mm 1.00000 sq.m WW0358

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0428 Flush Door, block board core, teak ply veneer, U\F bonded - 40mm 1.00000 sq.m

Providing & fixing flush door shutters (pre-fabrica ted), block-board core with teak ply veneer - 40mm

Providing & fixing Flush Door shutters (pre-fabrica ted), block-board core with commercial ply veneer - 40mm

Providing & fixing flush door shutters (pre-fabrica ted), block-board core with teak ply veneer - 25mm

Providing & fixing flush door shutters (pre-fabrica ted), block-board core with teak ply veneer - 30mm

Providing & fixing Flush Door shutters (pre-fabrica ted), block-board core with commercial ply veneer - 30mm

Providing & fixing Flush Door shutters (pre-fabrica ted), block-board core with commercial ply veneer - 35mm

Providing & fixing Flush Door shutters with pre-la minated bison panel - 30mm

Providing & fixing Flush Door shutters (pre-fabrica ted), block-board core with commercial ply veneer - 25mm

Providing & fixing flush door shutters (pre-fabrica ted), block-board core with teak ply veneer - 35mm

Department of Engineering Services, MoWHS

Page 91: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 88

WW0365

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0435 Flush Door, block board core, ply veneer, chemically treated - 25mm 1.00000 sq.m WW0366

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0436 Flush Door, block board core, ply veneer, chemically treated - 30mm 1.00000 sq.m WW0367

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0437 Flush Door, block board core, ply veneer, chemically treated - 35mm 1.00000 sq.m WW0368

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0438 Flush Door, block board core, ply veneer, chemically treated - 40mm 1.00000 sq.m WW0375

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0445 Panelled Door, with single lock rail - 30mm, 12mm veneered particle board panel 1.00000 sq.m WW0376

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0446 Panelled Door, with single lock rail - 35mm, 12mm veneered particle board panel 1.00000 sq.m WW0377

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0447 Panelled Door, with single lock rail - 40mm, 12mm veneered particle board panel 1.00000 sq.m WW0385

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0448 Panelled Door, with single lock rail - 30mm, 12mm plywood panel 1.00000 sq.m

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal middle rail includi ng prime coat - 40mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal middle rail including prim e coat - 30mm

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal middle rail includi ng prime coat - 30mm

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal middle rail includi ng prime coat - 35mm

Providing & fixing flush door shutters (pre-fabrica ted), block-board core with ply veneer, chemically treated - 35mm

Providing & fixing flush door shutters (pre-fabrica ted), block-board core with ply veneer, chemically treated - 40mm

Providing & fixing flush door shutters (pre-fabrica ted), block-board core with ply veneer, chemically treated - 25mm

Providing & fixing flush door shutters (pre-fabrica ted), block-board core with ply veneer, chemically treated - 30mm

Department of Engineering Services, MoWHS

Page 92: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 89

WW0386

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0449 Panelled Door, with single lock rail - 35mm, 12mm plywood panel 1.00000 sq.m WW0387

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0450 Panelled Door, with single lock rail - 40mm, 12mm plywood panel 1.00000 sq.m WW0395

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0451 Panelled Door, with single lock rail - 30mm, 9mm plywood panel 1.00000 sq.m WW0396

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0452 Panelled Door, with single lock rail - 35mm, 9mm plywood panel 1.00000 sq.m WW0397

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0453 Panelled Door, with single lock rail - 40mm, 9mm plywood panel 1.00000 sq.m WW0400

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0465Panelled Door, with single lock rail & stile - 30mm, 12mm veneered particle board panel 1.00000 sq.m

WW0401

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0466Panelled Door, with single lock rail & stile - 35mm, 12mm veneered particle board panel 1.00000 sq.m

WW0402

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0467Panelled Door, with single lock rail & stile - 40mm, 12mm veneered particle board panel 1.00000 sq.m

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal single lock rail & stile including prime coat - 35mm

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal single lock rail & stile including prime coat - 40mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal middle rail including prime coat - 40mm

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal single lock rail & stile including prime coat - 30mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal middle rail including prim e coat - 35mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal middle rail including prim e coat - 40mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal middle rail including prime coat - 30mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal middle rail including prime coat - 35mm

Department of Engineering Services, MoWHS

Page 93: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 90

WW0410

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0468 Panelled Door, with single lock rail & stile - 30mm, 12mm plywood panel 1.00000 sq.m WW0411

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0469 Panelled Door, with single lock rail & stile - 35mm, 12mm plywood panel 1.00000 sq.m WW0412

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0470 Panelled Door, with single lock rail & stile - 40mm, 12mm plywood panel 1.00000 sq.m WW0420

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0471 Panelled Door, with single lock rail & stile - 30mm, 9mm plywood panel 1.00000 sq.m WW0421

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0472 Panelled Door, with single lock rail & stile - 35mm, 9mm plywood panel 1.00000 sq.m WW0422

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0473 Panelled Door, with single lock rail & stile - 40mm, 9mm plywood panel 1.00000 sq.m WW0430

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0485Panelled Door, with double lock rail & stile - 30mm, 12mm veneered particle board panel 1.00000 sq.m

WW0431

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0486Panelled Door, with double lock rail & stile - 35mm, 12mm veneered particle board panel 1.00000 sq.m

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal double lock rail & stile including prime coat - 30mm

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal double lock rail & stile including prime coat - 35mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal single lock rail & stile i ncluding prime coat - 30mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal single lock rail & stile i ncluding prime coat - 35mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal single lock rail & stile i ncluding prime coat - 40mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal single lock rail & stile in cluding prime coat - 30mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal single lock rail & stile in cluding prime coat - 35mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal single lock rail & stile in cluding prime coat - 40mm

Department of Engineering Services, MoWHS

Page 94: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 91

WW0432

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0487Panelled Door, with double lock rail & stile - 40mm, 12mm veneered particle board panel 1.00000 sq.m

WW0440

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0488 Panelled Door, with double lock rail & stile - 30mm, 12mm plywood panel 1.00000 sq.m WW0441

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0489 Panelled Door, with double lock rail & stile - 35mm, 12mm plywood panel 1.00000 sq.m WW0442

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0490 Panelled Door, with double lock rail & stile - 40mm, 12mm plywood panel 1.00000 sq.m WW0450

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0491 Panelled Door, with double lock rail & stile - 30mm, 9mm plywood panel 1.00000 sq.m WW0451

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0492 Panelled Door, with double lock rail & stile - 35mm, 9mm plywood panel 1.00000 sq.m WW0452

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day MT0493 Panelled Door, with double lock rail & stile - 40mm, 9mm plywood panel 1.00000 sq.m WW0460

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0505Prefab. fully glazed window shutters, incl. 75mm rail with preservative & one primer coat, excl. glass - 30 mm 1.00000 sq.m

Providing & fixing panelled doors, with 12mm partic le board panels with horizontal double lock rail & stile including prime coat - 40mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal double lock rail & stile in cluding prime coat - 30mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal double lock rail & stile i ncluding prime coat - 30mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal double lock rail & stile i ncluding prime coat - 35mm

Providing & fixing panelled doors, with 12mm plywoo d panels with horizontal double lock rail & stile i ncluding prime coat - 40mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal double lock rail & stile in cluding prime coat - 30mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal double lock rail & stile in cluding prime coat - 35mm

Providing & fixing panelled doors, with 9mm plywood panels with horizontal double lock rail & stile in cluding prime coat - 40mm

Department of Engineering Services, MoWHS

Page 95: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 92

WW0461

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0506Prefab. fully glazed window shutters, incl. 75mm rail with preservative & one primer coat, excl. glass - 35 mm 1.00000 sq.m

WW0462

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.02270 day LB0077 Labour 0.02270 day

MT0507Prefab. fully glazed window shutters, incl. 75mm rail with preservative & one primer coat, excl. glass - 40mm 1.00000 sq.m

WW0470

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.35000 day LB0033 Carpenter Gd.2 0.25000 day LB0036 Mason Gd.1 0.00029 day LB0039 Work Supervisor (Lajab) 0.00023 day LB0051 Mason Gd.2 0.35029 day LB0053 Plant Operator Gd.3 0.00033 day LB0077 Labour 0.16040 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00033 day MP0206 Concrete Vibrator(M/C5) 0.00033 day MT0043 Sand 0.00221 cu.m MT0070 Crushed Rock - 20mm 0.00442 cu.m MT0145 Cement (OPC / PSC) 0.00103 tonne MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04100 cu.m WW0475

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 1.25089 day LB0033 Carpenter Gd.2 2.96489 day LB0039 Work Supervisor (Lajab) 0.11200 day LB0052 Painter Gd.1 2.20580 day LB0077 Labour 2.53649 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.12513 cu.m MT0531 Anodised Aluminium Fittings: Butt Hinges - 75mm 4.80000 each MT0655 Plain Glass - 3mm thick 0.73600 sq.m MT0731 Clear synthetic varnish 1.33660 litre WW0476

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 1.57089 day LB0033 Carpenter Gd.2 3.65289 day LB0039 Work Supervisor (Lajab) 0.11200 day LB0052 Painter Gd.1 2.20580 day LB0077 Labour 2.63249 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.08673 cu.m MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.03840 cu.m MT0531 Anodised Aluminium Fittings: Butt Hinges - 75mm 4.80000 each MT0655 Plain Glass - 3mm thick 0.73600 sq.m MT0731 Clear synthetic varnish 1.33660 litre

Providing & fixing panelled doors, with 9mm plywood panels with horizontal double lock rail & stile in cluding prime coat - 40mm

Providing & fixing 38mm thick wooden shelves suppor ted on 40x40x6mm `T' or `L' iron brackets fixed at suitable distance but not exceeding 75 cm apart in 7.5x7.5x15cm block s of cement concrete 1:3:6, 20 mm aggregates - Mixe d Conifer

Providing & fixing 25mm thick Cupboard (900x2000x45 0 mm...LxHxD) with glazed or panelled shutters, 25m m thick partitions and shelves supported on 25x25mm wooden runners, 50x20mm architraves and 25mm dia

curtain rod mounted on wooden brackets, including w ith Anodised Aluminium Hinges and frame in mixed co nifer - Mixed Conifer

Providing & fixing panelled doors, with 9mm plywood panels with horizontal double lock rail & stile in cluding prime coat - 35mm

Providing & fixing 25mm thick Cupboard (900x2000x45 0 mm...LxHxD) with glazed or panelled shutters, 25m m thick partitions and shelves supported on 25x25mm wooden runners, 50x20mm architraves and 25mm dia

curtain rod mounted on wooden brackets, including w ith Anodised Aluminium Hinges and frame in mixed co nifer - Champ wood

Department of Engineering Services, MoWHS

Page 96: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 93

WW0485

Coefficient for per 50mm

Code Description Quant Units LB0021 Carpenter Gd.1 0.18237 day LB0033 Carpenter Gd.2 0.04237 day LB0052 Painter Gd.1 0.13181 day LB0077 Labour 0.16569 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00672 cu.m MT0731 Clear synthetic varnish 0.07987 litre WW0486

Coefficient for per 100mm

Code Description Quant Units LB0021 Carpenter Gd.1 0.12477 day LB0033 Carpenter Gd.2 0.03046 day LB0052 Painter Gd.1 0.19099 day LB0077 Labour 0.13305 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00483 cu.m MT0492 Panelled Door, with double lock rail & stile - 35mm, 9mm plywood panel 0.19000 sq.m MT0731 Clear synthetic varnish 0.11573 litre WW0487

Coefficient for per 100mm

Code Description Quant Units LB0021 Carpenter Gd.1 0.12477 day LB0033 Carpenter Gd.2 0.03046 day LB0052 Painter Gd.1 0.19099 day LB0077 Labour 0.13305 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00483 cu.m MT0491 Panelled Door, with double lock rail & stile - 30mm, 9mm plywood panel 0.19000 sq.m MT0731 Clear synthetic varnish 0.11573 litre WW0488

Coefficient for per 100mm

Code Description Quant Units LB0021 Carpenter Gd.1 0.11772 day LB0033 Carpenter Gd.2 0.03509 day LB0052 Painter Gd.1 0.14795 day LB0077 Labour 0.12712 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00556 cu.m MT0492 Panelled Door, with double lock rail & stile - 35mm, 9mm plywood panel 0.11600 sq.m MT0731 Clear synthetic varnish 0.08965 litre WW0489

Coefficient for per 100mm

Code Description Quant Units LB0021 Carpenter Gd.1 0.11772 day LB0033 Carpenter Gd.2 0.03509 day LB0052 Painter Gd.1 0.14795 day LB0077 Labour 0.12712 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00556 cu.m MT0491 Panelled Door, with double lock rail & stile - 30mm, 9mm plywood panel 0.11600 sq.m MT0731 Clear synthetic varnish 0.08965 litre WW0495

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.22000 day LB0052 Painter Gd.1 0.12139 day LB0077 Labour 0.34139 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.01900 cu.m MT0714 Pink primer, for wood 0.09150 litre MT0722 Synthetic enamel paint 0.15250 litre

Extras, for Cupboards including frame of mixed coni fer - For additional depth of 50mm or part thereof

Providing & fixing railing with 90x60mm top & botto m rails, trellis 60x45mm including 2 coats of paint etc. all complete - 900 mm high- Champ wood

Extras, for Cupboards including frame of mixed coni fer - For additional width of 100mm or part thereof , including shutters of Champ wood

Extras, for Cupboards including frame of mixed coni fer - For additional height of 100mm or part thereo f, including shutters of Mixed Conifer

Extras, for Cupboards including frame of mixed coni fer - For additional height of 100mm or part thereo f, including shutters of Champ wood

Extras, for Cupboards including frame of mixed coni fer - For additional width of 100mm or part thereof including shutters of Mixed Conifer

Department of Engineering Services, MoWHS

Page 97: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 94

WW0496

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.22000 day LB0052 Painter Gd.1 0.12139 day LB0077 Labour 0.34139 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01900 cu.m MT0714 Pink primer, for wood 0.09150 litre MT0722 Synthetic enamel paint 0.15250 litre WW0497

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.25310 day LB0052 Painter Gd.1 0.14255 day LB0077 Labour 0.39555 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.02170 cu.m MT0714 Pink primer, for wood 0.10745 litre MT0722 Synthetic enamel paint 0.17909 litre WW0498

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.25310 day LB0052 Painter Gd.1 0.14255 day LB0077 Labour 0.39555 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02170 cu.m MT0714 Pink primer, for wood 0.10745 litre MT0722 Synthetic enamel paint 0.17909 litre WW0499

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29980 day LB0052 Painter Gd.1 0.16881 day LB0077 Labour 0.46861 day MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.02560 cu.m MT0714 Pink primer, for wood 0.12725 litre MT0722 Synthetic enamel paint 0.21207 litre WW0500

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29980 day LB0052 Painter Gd.1 0.16881 day LB0077 Labour 0.46861 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02560 cu.m MT0714 Pink primer, for wood 0.12725 litre MT0722 Synthetic enamel paint 0.21207 litre WW0505

Coefficient for per m Code Description Quant Units LB0021 Carpenter Gd.1 0.12500 day LB0039 Work Supervisor (Lajab) 0.08000 day LB0077 Labour 0.12500 day MT0182 Rolled sections (250 MPa) - Flats 0.06000 kg MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.00363 cu.m WW0506

Coefficient for per m Code Description Quant Units LB0033 Carpenter Gd.2 0.12500 day LB0039 Work Supervisor (Lajab) 0.08000 day LB0077 Labour 0.12500 day MT0182 Rolled sections (250 MPa) - Flats 0.06000 kg MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00363 cu.m

Providing & fixing 100x12mm, with 25mm dia. wooden curtain rod and brackets including M.S flats 25x3x1 00mm and plugs etc. complete - Mixed Conifer

Providing & fixing railing with 90x60mm top & botto m rails, trellis 60x45mm including 2 coats of paint etc. all complete - 1200 mm high, Mixed Conifer

Providing & fixing railing with 90x60mm top & botto m rails, trellis 60x45mm including 2 coats of paint etc. all complete - 1200 mm high, Champ wood

Providing & fixing 100x12mm, with 25mm dia. wooden curtain rod and brackets including M.S flats 25x3x1 00mm and plugs etc. complete - Champ wood

Providing & fixing railing with 90x60mm top & botto m rails, trellis 60x45mm including 2 coats of paint etc. all complete - 900 mm high, Mixed Conifer

Providing & fixing railing with 90x60mm top & botto m rails, trellis 60x45mm including 2 coats of paint etc. all complete - 1000 mm high, Champ wood

Providing & fixing railing with 90x60mm top & botto m rails, trellis 60x45mm including 2 coats of paint etc. all complete - 1000 mm high, Mixed Conifer

Department of Engineering Services, MoWHS

Page 98: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 95

WW0515

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.12500 day LB0039 Work Supervisor (Lajab) 0.08000 day LB0077 Labour 0.12500 day MT0182 Rolled sections (250 MPa) - Flats 0.06000 kg MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.00420 cu.m WW0516

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.12500 day LB0039 Work Supervisor (Lajab) 0.08000 day LB0077 Labour 0.12500 day MT0182 Rolled sections (250 MPa) - Flats 0.03000 kg MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00420 cu.m WW0525

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.01800 day LB0077 Labour 0.01100 day MT0615 Mild Steel: Butt Hinges - 100mm 1.00000 each WW0526

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.01800 day LB0077 Labour 0.01100 day MT0616 Mild Steel: Butt Hinges - 75mm 1.00000 each WW0527

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.01800 day LB0077 Labour 0.01100 day MT0617 Mild Steel: Butt Hinges - 50mm 1.00000 each WW0535

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.01300 day MT0645 Mild Steel: Tower Bolts (Barrel Type) - 250mm 1.00000 each WW0536

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.01000 day LB0077 Labour 0.00800 day MT0646 Mild Steel: Tower Bolts (Barrel Type) - 150mm 1.00000 each WW0537

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.01000 day

LB0077 Labour 0.00800 day MT0647 Mild Steel: Tower Bolts (Barrel Type) - 100mm 1.00000 each WW0545

Coefficient for per each Code Description Quant Units LB0033 Carpenter Gd.2 0.03100 day MT0221 Fasteners - M.S. Bolts & Nuts, Screws etc 0.10000 kg MT0640 Mild Steel: Sliding Door Bolts - 300mm 1.00000 each

Providing & fixing M.S. pressed butt hinges with ne cessary screws etc. complete - 50mm

Providing & fixing M.S. tower bolt (barrel type) wi th necessary screws etc. complete - 250mm

Providing & fixing M.S. tower bolt (barrel type) wi th necessary screws etc. complete - 150mm

Providing & fixing M.S. tower bolt (barrel type) wi th necessary screws etc. complete - 100mm

Providing & fixing 150x12mm, with 25mm dia. wooden curtain rod and brackets including M.S flats 25x3x1 00mm and plugs etc. complete - Champ wood

Providing & fixing 150x12mm, with 25mm dia. wooden curtain rod and brackets including M.S flats 25x3x1 00mm and plugs etc. complete - Mixed Conifer

Providing & fixing M.S. pressed butt hinges with ne cessary screws etc. complete - 100mm

Providing & fixing M.S. pressed butt hinges with ne cessary screws etc. complete - 75mm

Providing & fixing M.S. sliding door bolt, bright f inished, enamelled with necessary screws etc. compl ete - 300mm

Department of Engineering Services, MoWHS

Page 99: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 96

WW0546

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.03100 day MT0221 Fasteners - M.S. Bolts & Nuts, Screws etc 0.10000 kg MT0641 Mild Steel: Sliding Door Bolts - 250mm 1.00000 each WW0547

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.03100 day MT0221 Fasteners - M.S. Bolts & Nuts, Screws etc 0.10000 kg MT0642 Mild Steel: Sliding Door Bolts - 200mm 1.00000 each WW0555

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.00800 day MT0620 Mild Steel: Handles - 150mm 1.00000 each WW0556

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.00800 day MT0621 Mild Steel: Handles - 125mm 1.00000 each WW0557

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.00800 day MT0622 Mild Steel: Handles - 100mm 1.00000 each WW0558

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.00800 day MT0623 Mild Steel: Handles - 75mm 1.00000 each WW0565

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.00800 day MT0630 Mild Steel: Hooks and Eyes - 300mm 1.00000 each WW0566

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.00800 day MT0631 Mild Steel: Hooks and Eyes - 200mm 1.00000 each WW0567

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.00800 day MT0632 Mild Steel: Hooks and Eyes - 150mm 1.00000 each WW0568

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.00800 day MT0633 Mild Steel: Hooks and Eyes - 100mm 1.00000 each

Providing & fixing M.S. sliding door bolt, bright f inished, enamelled with necessary screws etc. compl ete - 200mm

Providing & fixing M.S. handle with necessary screw s etc. complete - 150mm

Providing & fixing M.S. handle with necessary screw s etc. complete - 125mm

Providing & fixing M.S. hook-and-eye with necessary screws etc. complete - 150mm

Providing & fixing M.S. hook-and-eye with necessary screws etc. complete - 100mm

Providing & fixing M.S. sliding door bolt, bright f inished, enamelled with necessary screws etc. compl ete - 250mm

Providing & fixing M.S. handle with necessary screw s etc. complete - 100mm

Providing & fixing M.S. handle with necessary screw s etc. complete - 75mm

Providing & fixing M.S. hook-and-eye with necessary screws etc. complete - 300mm

Providing & fixing M.S. hook-and-eye with necessary screws etc. complete - 200mm

Department of Engineering Services, MoWHS

Page 100: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 97

WW0575

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.07000 day MT0650 Mild Steel: Tower Bolts (Barrel Type) - Mild Steel: Door Stopper 1.00000 each WW0580

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01800 day MT0530 Anodised Aluminium Fittings: Butt Hinges - 100mm 1.00000 each WW0581

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01800 day MT0531 Anodised Aluminium Fittings: Butt Hinges - 75mm 1.00000 each WW0590

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01300 day MT0570 Anodised Aluminium Fittings: Tower Bolts (Barrel Type) - 200mm 1.00000 each WW0591

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01000 day MT0571 Anodised Aluminium Fittings: Tower Bolts (Barrel Type) - 150mm 1.00000 each WW0592

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01000 day MT0572 Anodised Aluminium Fittings: Tower Bolts (Barrel Type) - 100mm 1.00000 each WW0600

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.06300 day MT0565 Anodised Aluminium Fittings: Sliding Door Bolts - 300mm 1.00000 each WW0601

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.06300 day MT0566 Anodised Aluminium Fittings: Sliding Door Bolts - 250mm 1.00000 each WW0602

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.06300 day MT0567 Anodised Aluminium Fittings: Sliding Door Bolts - 200mm 1.00000 each WW0610

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0540 Anodised Aluminium Fittings: Handles - 150mm 1.00000 each

Providing & fixing anodised aluminium tower bolt (b arrel type) with aluminium screws etc. complete - 1 50mm

Providing & fixing anodised aluminium tower bolt (b arrel type) with aluminium screws etc. complete - 1 00mm

Providing & fixing anodised aluminium sliding door bolts with nuts and aluminium screws etc. complete - 300mm

Providing & fixing anodised aluminium sliding door bolts with nuts and aluminium screws etc. complete - 250mm

Providing & fixing anodised aluminium sliding door bolts with nuts and aluminium screws etc. complete - 200mm

Providing & fixing anodised aluminium handle with n ecessary aluminium screws etc. complete - 150mm

Providing & fixing M.S. door stopper with nuts and necessary screws complete

Providing & fixing anodised aluminium butt hinges w ith necessary aluminium screws etc. complete - 100m m

Providing & fixing anodised aluminium butt hinges w ith necessary aluminium screws etc. complete - 75mm

Providing & fixing anodised aluminium tower bolt (b arrel type) with aluminium screws etc. complete - 2 00mm

Department of Engineering Services, MoWHS

Page 101: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 98

WW0611

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0541 Anodised Aluminium Fittings: Handles - 125mm 1.00000 each WW0612

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0542 Anodised Aluminium Fittings: Handles - 100mm 1.00000 each WW0613

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0543 Anodised Aluminium Fittings: Handles - 75mm 1.00000 each WW0620

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0550 Anodised Aluminium Fittings: Hooks and Eyes - 300mm 1.00000 each WW0621

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0551 Anodised Aluminium Fittings: Hooks and Eyes - 200mm 1.00000 each WW0622

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0552 Anodised Aluminium Fittings: Hooks and Eyes - 150mm 1.00000 each WW0623

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0553 Anodised Aluminium Fittings: Hooks and Eyes - 100mm 1.00000 each WW0630

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.17600 day LB0077 Labour 0.12500 day MT0560 Anodised Aluminium Fittings: Kicking Plate - 4mm thick 1.00000 sq.m WW0635

Coefficient for per each Code Description Quant Units LB0021 Carpenter Gd.1 0.01800 day LB0077 Labour 0.01100 day MT0575 Bright finished brass: Butt Hinges - 100mm 1.00000 each WW0636

Coefficient for per each Code Description Quant Units LB0021 Carpenter Gd.1 0.01800 day LB0077 Labour 0.01100 day MT0576 Bright finished brass: Butt Hinges - 75mm 1.00000 each

Providing & fixing anodised aluminium hook-and-eye with necessary screws etc complete - 100mm

Providing & fixing anodised aluminium kicking plate , 4mm thick with necessary aluminium screws etc. co mplete

Providing & fixing brass pressed butt hinges with n ecessary screws etc. complete - 100mm

Providing & fixing brass pressed butt hinges with n ecessary screws etc. complete - 75mm

Providing & fixing anodised aluminium handle with n ecessary aluminium screws etc. complete - 125mm

Providing & fixing anodised aluminium handle with n ecessary aluminium screws etc. complete - 100mm

Providing & fixing anodised aluminium handle with n ecessary aluminium screws etc. complete - 75mm

Providing & fixing anodised aluminium hook-and-eye with necessary screws etc complete - 300mm

Providing & fixing anodised aluminium hook-and-eye with necessary screws etc complete - 200mm

Providing & fixing anodised aluminium hook-and-eye with necessary screws etc complete - 150mm

Department of Engineering Services, MoWHS

Page 102: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 99

WW0637

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01800 day LB0077 Labour 0.01100 day MT0577 Bright finished brass: Butt Hinges - 50mm 1.00000 each WW0645

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01300 day MT0600 Bright finished brass: Tower Bolts (Barrel Type) - 250mm 1.00000 each WW0646

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01000 day MT0601 Bright finished brass: Tower Bolts (Barrel Type) - 150mm 1.00000 each WW0647

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.01000 day MT0602 Bright finished brass: Tower Bolts (Barrel Type) - 100mm 1.00000 each WW0655

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.05000 day MT0595 Bright finished brass: Sliding Door Bolts - 300mm 1.00000 each WW0656

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.05000 day MT0596 Bright finished brass: Sliding Door Bolts - 250mm 1.00000 each WW0657

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.05000 day MT0597 Bright finished brass: Sliding Door Bolts - 200mm 1.00000 each WW0665

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0580 Bright finished brass: Handles - 150mm 1.00000 each WW0666

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0581 Bright finished brass: Handles - 125mm 1.00000 each WW0667

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0582 Bright finished brass: Handles - 100mm 1.00000 each WW0668

Coefficient for per each Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0583 Bright finished brass: Handles - 75mm 1.00000 each

Providing & fixing brass tower bolt (barrel type) w ith necessary screws etc. complete - 150mm

Providing & fixing brass tower bolt (barrel type) w ith necessary screws etc. complete - 100mm

Providing & fixing brass sliding door bolt with nut s necessary screws etc. complete - 300mm

Providing & fixing brass sliding door bolt with nut s necessary screws etc. complete - 250mm

Providing & fixing brass sliding door bolt with nut s necessary screws etc. complete - 200mm

Providing & fixing brass handle with necessary scre ws etc. complete - 150mm

Providing & fixing brass handle with necessary scre ws etc. complete - 75mm

Providing & fixing brass handle with necessary scre ws etc. complete - 125mm

Providing & fixing brass handle with necessary scre ws etc. complete - 100mm

Providing & fixing brass pressed butt hinges with n ecessary screws etc. complete - 50mm

Providing & fixing brass tower bolt (barrel type) w ith necessary screws etc. complete - 250mm

Department of Engineering Services, MoWHS

Page 103: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 100

WW0675

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.02100 day

MT0606Bright finished brass: Tower Bolts (Barrel Type) - Bright finished brass: Mortise Latch 100mm 1.00000 each

WW0676

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.05000 day MT0607 Door Closers - brass, hinged, spring-loaded type 1.00000 each WW0677

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.05000 day LB0077 Labour 0.02500 day MT0608 Door Closers - brass, over-head, hydraulic type 1.00000 each WW0678

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00880 day

MT0605Bright finished brass: Tower Bolts (Barrel Type) - Bright finished brass: Door Stopper 1.00000 each

WW0685

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0590 Bright finished brass: Hooks and Eyes - 150mm 1.00000 each WW0686

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day MT0591 Bright finished brass: Hooks and Eyes - 100mm 1.00000 each WW0695

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03800 day LB0036 Mason Gd.1 0.03831 day LB0039 Work Supervisor (Lajab) 0.00025 day LB0051 Mason Gd.2 0.00031 day LB0053 Plant Operator Gd.3 0.00034 day LB0077 Labour 0.04885 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00034 day MP0206 Concrete Vibrator(M/C5) 0.00034 day MT0043 Sand 0.00230 cu.m MT0070 Crushed Rock - 20mm 0.00461 cu.m MT0145 Cement (OPC / PSC) 0.00108 tonne MT0182 Rolled sections (250 MPa) - Flats 0.40300 kg WW0700

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.28880 day MT0042 Mud dry 1.20000 cu.m MT0155 Plastic Sheet - 50 micro-metre 10.00000 sq.m

Providing & fixing bright finished brass hook-and-e ye with necessary screws etc. complete - 100mm

P&f 40x3mm M.S. hold fast 400mm long, fixing to fra me with 10mm bolts & nuts, plugs, concrete blocks 3 00x100x150mm with 1:3:6, 20mm aggregate

Providing & fixing bright finish brass hydraulic do or-closer

Providing & fixing bright finished brass door stopp er with nuts and necessary screws etc. complete

Providing & fixing bright finished brass hook-and-e ye with necessary screws etc. complete - 150mm

Providing & fixing bright finish brass spring-loade d, hinged door-closer with necessary screws etc. co mplete

Providing & fixing bright finish brass 100 mm morti se latch & pair of levers, handles with necessary s crews etc. complete

P&L dry earth in ceilings in proportion 1:5 (1 stra w: 5 dry earth) including plastic underlay

Department of Engineering Services, MoWHS

Page 104: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 101

WW0705

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.24000 day LB0033 Carpenter Gd.2 0.27000 day LB0077 Labour 0.24000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00420 cu.m

MT0385Pre-laminated Particle Board (one side) - Translucent diffuser panel, for skylights etc 1.05000 sq.m

WW0710

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 3.00000 day

Providing & fixing skylight translucent diffuser pa nel including 50x12 beading etc. complete

Providing & fixing Decorative Traditional Timber Ca rving

Department of Engineering Services, MoWHS

Page 105: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 102

CHAPTER 12

SW0001

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.00110 day LB0052 Painter Gd.1 0.00079 day LB0077 Labour 0.02679 day MT0183 Rolled sections (250 MPa) - Joists 1.05000 kg MT0711 Synthetic red lead primer 0.00143 litre SW0002

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01250 day LB0052 Painter Gd.1 0.00090 day LB0077 Labour 0.01340 day MT0182 Rolled sections (250 MPa) - Flats 1.05000 kg MT0711 Synthetic red lead primer 0.00162 litre SW0003

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01400 day LB0052 Painter Gd.1 0.00090 day LB0077 Labour 0.01340 day MT0181 Rolled sections (250 MPa) - Channels 1.05000 kg MT0711 Synthetic red lead primer 0.00162 litre SW0010

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.00860 day LB0052 Painter Gd.1 0.00056 day LB0077 Labour 0.01556 day MT0183 Rolled sections (250 MPa) - Joists 0.57100 kg MT0184 Rolled sections (250 MPa) - Plates 0.45600 kg MT0220 Fasteners - M.S. Rivets 0.02300 kg MT0711 Synthetic red lead primer 0.00101 litre SW0011

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.20000 day LB0052 Painter Gd.1 0.00054 day LB0077 Labour 0.03054 day MT0180 Rolled sections (250 MPa) - Angles 0.40500 kg MT0182 Rolled sections (250 MPa) - Flats 0.13800 kg MT0184 Rolled sections (250 MPa) - Plates 0.48000 kg MT0220 Fasteners - M.S. Rivets 0.01800 kg MT0221 Fasteners - M.S. Bolts & Nuts, Screws etc 0.01400 kg MT0711 Synthetic red lead primer 0.00097 litre SW0020

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.00460 day LB0052 Painter Gd.1 0.00056 day LB0077 Labour 0.00976 day MP0202 Welder - electric arc 0.01740 day MT0183 Rolled sections (250 MPa) - Joists 0.58300 kg MT0184 Rolled sections (250 MPa) - Plates 0.46700 kg MT0711 Synthetic red lead primer 0.00100 litre

STEEL

Steel work in single section including cutting, hoi sting, fixing and applying priming coat of red lead paint - In Flats

Steel work in single section including cutting, hoi sting, fixing and applying priming coat of red lead paint - In Tees, angles and channels

Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and applying. priming coat of red lead paint - In R.S. joists

Steel work riveted or bolted, in built up sections, trusses, frame-works, including cutting, hoisting, fixing and applying. priming coat of red lead paint - In Tees, angles, f lats and channels

Steel work welded, in built up sections, trusses, f rame-works including cutting, hoisting, fixing and applying priming coat of red lead paint - In R.S. joists

Steel work in single section including cutting, hoi sting, fixing and applying priming coat of red lead paint - In R.S. joists

Department of Engineering Services, MoWHS

Page 106: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 103

SW0021

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.00480 day LB0052 Painter Gd.1 0.00055 day LB0077 Labour 0.02065 day MP0202 Welder - electric arc 0.01740 day MT0180 Rolled sections (250 MPa) - Angles 0.41300 kg MT0182 Rolled sections (250 MPa) - Flats 0.13600 kg MT0184 Rolled sections (250 MPa) - Plates 0.48900 kg MT0221 Fasteners - M.S. Bolts & Nuts, Screws etc 0.01360 kg MT0711 Synthetic red lead primer 0.00099 litre SW0022

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01580 day LB0052 Painter Gd.1 0.00072 day LB0077 Labour 0.01372 day MT0200 Welded Tube (250 MPa) - 50mm dia 0.14600 m MT0201 Welded Tube (250 MPa) - 40mm dia 0.08400 m MT0711 Synthetic red lead primer 0.00130 litre SW0030

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 5.20800 day LB0036 Mason Gd.1 0.17400 day LB0051 Mason Gd.2 0.17400 day LB0052 Painter Gd.1 0.08760 day LB0077 Labour 0.26160 day MT0180 Rolled sections (250 MPa) - Angles 3.61000 kg MT0181 Rolled sections (250 MPa) - Channels 14.78100 kg MT0182 Rolled sections (250 MPa) - Flats 16.67000 kg MT0711 Synthetic red lead primer 0.15768 litre SW0035

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.43000 day LB0036 Mason Gd.1 0.02000 day LB0051 Mason Gd.2 0.02000 day LB0077 Labour 0.38000 day MT0515 Rolling shutters with all accessories, excluding top cover 1.00000 sq.m SW0036

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.05000 day LB0077 Labour 0.50000 day MT0516 Top cover for Rolling shutter 1.00000 m SW0045

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.02500 day LB0033 Carpenter Gd.2 0.02200 day LB0077 Labour 0.06500 day

MT0165Anodised Aluminium Section for doors, windows - Sliding, openable and pivoted windows 1.00000 kg

Providing & fixing in position with vertical channe ls 20x10x2mm and braced with flat iron, diagonals 2 0x5mm with top and bottom rails of T-iron 40x40x6mm with 38mm dia stee l pulleys complete with bolts, nuts, locking arrang ement, stoppers handles including applying a priming coat of red le ad paint - Collapsible steel shutters

Providing & fixing anodised Aluminium section for d oors, windows, ventilators, partitions framing, fal se ceiling framing of specified sections including all accessories such a s U-rubber gasket for fixing glass panes, weather

strips or weather seals, roller, springs, etc compl ete (excluding the cost of glass panes or boards in case of partitions/doors/windows and ceiling boards in case of ceiling) - Sliding, openable and pivoted window s

Providing & fixing in position including applying a priming coat of red lead paint - Top cover for rol ling shutters

Steel work welded, in built up sections, trusses, f rame-works including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tees, angles, flats and chan nels

Steel work welded, in built up sections, trusses, f rame-works including cutting, hoisting, fixing and applying priming coat of red lead paint - In Tubular sections

Providing & fixing in position including applying a priming coat of red lead paint - Rolling shutters, including all accessories complete but excluding top cover

Department of Engineering Services, MoWHS

Page 107: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 104

SW0046

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03000 day LB0033 Carpenter Gd.2 0.02200 day LB0077 Labour 0.06500 day MT0166 Anodised Aluminium Section for doors, windows - Sliding and openable doors 1.00000 kg SW0047

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01500 day LB0033 Carpenter Gd.2 0.02200 day LB0077 Labour 0.06500 day MT0167 Anodised Aluminium Section for doors, windows - Partitions framing 1.00000 kg SW0048

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01100 day LB0033 Carpenter Gd.2 0.02200 day LB0077 Labour 0.06500 day MT0168 Anodised Aluminium Section for doors, windows - False ceiling framing 1.00000 kg SW0055

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.25000 day LB0077 Labour 0.01000 day MT0656 Plain Glass - 4mm thick 1.00000 sq.m SW0056

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.25000 day LB0077 Labour 0.01000 day MT0657 Plain Glass - 5.5mm thick 1.00000 sq.m SW0057

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.25000 day LB0077 Labour 0.01000 day MT0661 Frosted Glass - 5.5mm thick 1.00000 sq.m SW0065

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.14000 day LB0033 Carpenter Gd.2 0.14000 day LB0036 Mason Gd.1 0.06600 day LB0051 Mason Gd.2 0.06600 day LB0052 Painter Gd.1 0.03750 day LB0077 Labour 0.44850 day MT0510 Steel door with necessary hinges, lugs, glazing clips 1.00000 sq.m MT0655 Plain Glass - 3mm thick 0.80000 sq.m MT0711 Synthetic red lead primer 0.06750 litre

Extra, for providing and fixing plain glass panes o n aluminium section complete (excluding the cost of aluminium frame & accessories) - 4mm thick plain glass

Providing & fixing steel glazed doors, windows, ven tilators of standard rolled steel sections joints m itred and welded with 15x3mm lugs embedded as required including p&f glas s panes and a coat of primer - Doors

Extra, for providing and fixing plain glass panes o n aluminium section complete (excluding the cost of aluminium frame & accessories) - 5.5mm thick, plain glass

Providing & fixing anodised Aluminium section for d oors, windows, ventilators, partitions framing, fal se ceiling framing of specified sections including all accessories such a s U-rubber gasket for fixing glass panes, weather s trips or weather seals, roller, springs, etc complete (excluding the cost of glass panes or boards in case of partition s/doors/windows and ceiling boards in case of ceiling) - Partition fram ing

Extra, for providing and fixing plain glass panes o n aluminium section complete (excluding the cost of aluminium frame & accessories) - 5.5mm thick frosted glass

Providing & fixing anodised Aluminium section for d oors, windows, ventilators, partitions framing, fal se ceiling framing of specified sections including all accessories such a s U-rubber gasket for fixing glass panes, weather s trips or weather seals, roller, springs, etc complete (excluding th e cost of glass panes or boards in case of partitio ns/doors/windows and ceiling boards in case of ceiling) - Sliding and op enable doors

Providing & fixing anodised Aluminium section for d oors, windows, ventilators, partitions framing, fal se ceiling framing of specified sections including all accessories such a s U-rubber gasket for fixing glass panes, weather strips or weather seals, roller, springs, etc complete (excluding the cost of glass panes or boards in case of partition s/doors/windows and ceiling boards in case of ceiling) - False ceiling framing

Department of Engineering Services, MoWHS

Page 108: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 105

SW0066

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.14000 day LB0033 Carpenter Gd.2 0.14000 day LB0036 Mason Gd.1 0.06600 day LB0051 Mason Gd.2 0.06600 day LB0052 Painter Gd.1 0.03726 day LB0077 Labour 0.44826 day MT0511 Steel windows (fixed) with lugs and glazing clips 1.00000 sq.m MT0655 Plain Glass - 3mm thick 0.79000 sq.m MT0711 Synthetic red lead primer 0.06707 litre SW0067

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.14000 day LB0033 Carpenter Gd.2 0.14000 day LB0036 Mason Gd.1 0.06600 day LB0051 Mason Gd.2 0.06600 day LB0052 Painter Gd.1 0.03726 day LB0077 Labour 0.44826 day MT0512 Steel windows (side hung) with hinges, lugs and glazing clips 1.00000 sq.m MT0655 Plain Glass - 3mm thick 0.80270 sq.m MT0711 Synthetic red lead primer 0.06707 litre SW0068

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.14000 day LB0033 Carpenter Gd.2 0.14000 day LB0036 Mason Gd.1 0.06600 day LB0051 Mason Gd.2 0.06600 day LB0052 Painter Gd.1 0.03726 day LB0077 Labour 0.44826 day MT0513 Steel ventilators (top hung) with hinges, lugs and glazing clips. 1.00000 sq.m MT0655 Plain Glass - 3mm thick 0.79000 sq.m MT0711 Synthetic red lead primer 0.06707 litre SW0069

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.14000 day LB0033 Carpenter Gd.2 0.14000 day LB0036 Mason Gd.1 0.06600 day LB0051 Mason Gd.2 0.06600 day LB0052 Painter Gd.1 0.03726 day LB0077 Labour 0.44826 day MT0514 Steel ventilators (centre hung) with pivots, lugs and glazing clips 1.00000 sq.m MT0655 Plain Glass - 3mm thick 0.79000 sq.m MT0711 Synthetic red lead primer 0.06707 litre SW0075

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.16670 day LB0052 Painter Gd.1 0.00675 day LB0077 Labour 0.17345 day MP0202 Welder - electric arc 0.05000 day MT0190 Sheet (250 MPa) - 1mm 1.85460 kg MT0711 Synthetic red lead primer 0.01215 litre

Providing & fixing steel glazed doors, windows, ven tilators of standard rolled steel sections joints m itred and welded with 15x3mm lugs embedded as required including p&f glas s panes and a coat of primer - Windows side hung

Providing & fixing steel glazed doors, windows, ven tilators of standard rolled steel sections joints m itred and welded with 15x3mm lugs embedded as required including p&f glas s panes and a coat of primer - Ventilators top hung

Providing & fixing steel glazed doors, windows, ven tilators of standard rolled steel sections joints m itred and welded with 15x3mm lugs embedded as required including p&f glas s panes and a coat of primer - Windows fixed

Extra, for Providing & fixing. Bhutan type architra ves with 24G steel sheet....per sq.m. of window are a

Providing & fixing steel glazed doors, windows, ven tilators of standard rolled steel sections joints m itred and welded with 15x3mm lugs embedded as required including p&f glas s panes and a coat of primer - Ventilators centre h ung

Department of Engineering Services, MoWHS

Page 109: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 106

SW0080

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01570 day MT0184 Rolled sections (250 MPa) - Plates 0.20830 kg MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 0.79160 kg SW0081

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.04800 day LB0077 Labour 0.04800 day MT0221 Fasteners - M.S. Bolts & Nuts, Screws etc 1.00000 kg SW0082

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.10400 day LB0077 Labour 0.10400 day MT0220 Fasteners - M.S. Rivets 1.00000 kg SW0090

Coefficient for per kg

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.00430 day LB0077 Labour 0.00300 day MP0202 Welder - electric arc 0.01740 day MT0182 Rolled sections (250 MPa) - Flats 0.44690 kg MT0184 Rolled sections (250 MPa) - Plates 0.54360 kg MT0220 Fasteners - M.S. Rivets 0.01050 kg SW0095

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.05000 day LB0077 Labour 0.05000 day MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 1.70000 kg

SW0100

Coefficient for per sq.m

Code Description Quant Units

LB0032 Blacksmith (metal worker) 0.0700 day

LB0049 General Mechanic Gd.3 0.1400 day

MT0201 M.S tube 40 mm dia 0.0213 each

MT0221 Nuts and bolts 2.0000 eachMT1670 Plates, angles and channels 0.5330 kgMT1671 Single clip 0.0160 eachMT1672 Double clip 0.0314 each

SW0101

Coefficient for per sq.m

Code Description Quant Units

LB0032 Blacksmith (metal worker) 0.2600 dayLB0049 General Mechanic Gd.3 0.4500 day

MT0221 Nuts and bolts 2.0000 each

MT1670 Plates, angles and channels 1.2500 kgMT1673 Adjustable span ESO+SI 0.0080 eachMT1674 Adjustable telescopic prop (3m) 0.0094 each

Providing and fixing steel form work in foundations , footings, bases of columns etc for mass concrete

Providing and fixing steel form work in suspended f loors, roofs, landings, shelves and their support, balconies, chajjas etc

Providing, making and fixing M.S. straps, flats, so le plates etc.

Providing & fixing M.S. fan clamps of 16 mm dia. in R.C. slabs, including painting with red lead paint

Providing & fixing M.S. round hold-down bolts with nuts and washer plates

Providing & fixing bolts of various sizes including nuts & washers

Providing & fixing M.S. rivets of various sizes

Department of Engineering Services, MoWHS

Page 110: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 107

SW0102

Coefficient for per sq.m

Code Description Quant Units

LB0032 Blacksmith (metal worker) 0.1600 day

LB0049 General Mechanic Gd.3 0.3210 day

MT0221 Nuts and bolts 2.8300 each

MT1670 Plates, angles and channels 0.7860 kg

MT1674 Adjustable telescopic prop (3m) 0.0163 each

MT1675 Beam Clamp 0.0136 each

SW0103

Coefficient for per sq.m

Code Description Quant Units

LB0032 Blacksmith (metal worker) 0.2220 dayLB0049 General Mechanic Gd.3 0.4440 day

MT0221 Nuts and bolts 6.1400 each

MT1670 Plates, angles and channels 0.2630 kg

MT1676 Column clamp 0.0236 each

MT1677 Prop 2 m 0.0190 each

Providing and fixing steel form work in columns, pi llars, posts, struts etc.

Providing and fixing steel form work in lintels, be ams, girders, bresummers, cantilevers, etc.

Department of Engineering Services, MoWHS

Page 111: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 108

CHAPTER 13

FL0001

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.13450 day LB0077 Labour 0.26793 day MT0043 Sand 0.03103 cu.m MT0125 Bricks 2nd class 0.05160 1000# MT0145 Cement (OPC / PSC) 0.01102 tonne FL0002

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.13450 day LB0077 Labour 0.26832 day MT0043 Sand 0.03103 cu.m MT0125 Bricks 2nd class 0.05165 1000# MT0145 Cement (OPC / PSC) 0.00725 tonne FL0003

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.11300 day LB0077 Labour 0.27206 day MT0042 Mud dry 0.01800 cu.m MT0043 Sand 0.01500 cu.m MT0125 Bricks 2nd class 0.05165 1000# FL0010

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.13450 day LB0077 Labour 0.26284 day MT0043 Sand 0.02600 cu.m MT0125 Bricks 2nd class 0.03210 1000# MT0145 Cement (OPC / PSC) 0.00923 tonne FL0011

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.13450 day LB0077 Labour 0.26284 day MT0043 Sand 0.02600 cu.m MT0125 Bricks 2nd class 0.03200 1000# MT0145 Cement (OPC / PSC) 0.00607 tonne FL0012

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.11290 day LB0077 Labour 0.14391 day MT0042 Mud dry 0.01452 cu.m MT0043 Sand 0.01210 cu.m MT0125 Bricks 2nd class 0.03200 1000# FL0020

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.06750 day LB0077 Labour 0.10375 day MT0043 Sand 0.00214 cu.m MT0145 Cement (OPC / PSC) 0.00076 tonne

P&L 2nd class Brick-on-edge flooring - In cement mo rtar 1:6

P&L 2nd class Brick-on-edge flooring - In cement mo rtar 1:4

FLOORING

P&L 2nd class Flat brick flooring - In dry brick, f illing joints with sand, on a base of 12.5mm mud mo rtar

P&L pointing on brick flooring with cement mortar 1 :2 - Flush pointing

P&L 2nd class Brick-on-edge flooring - In dry brick , including filling joints with sand on bedding of 12.5mm mud mortar

P&L 2nd class Flat brick flooring - In cement morta r 1:4

P&L 2nd class Flat brick flooring - In cement morta r 1:6

Department of Engineering Services, MoWHS

Page 112: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 109

FL0021

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.07400 day LB0077 Labour 0.11325 day MT0043 Sand 0.00214 cu.m MT0145 Cement (OPC / PSC) 0.00076 tonne FL0030

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.06750 day LB0077 Labour 0.10375 day MT0043 Sand 0.00214 cu.m MT0145 Cement (OPC / PSC) 0.00076 tonne FL0031

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.07400 day LB0077 Labour 0.11325 day MT0043 Sand 0.00214 cu.m MT0145 Cement (OPC / PSC) 0.00076 tonne FL0040

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.06750 day LB0077 Labour 0.10375 day MT0043 Sand 0.00214 cu.m MT0145 Cement (OPC / PSC) 0.00050 tonne FL0041

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.07400 day LB0077 Labour 0.11325 day MT0043 Sand 0.00214 cu.m MT0145 Cement (OPC / PSC) 0.00050 tonne FL0050

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.13450 day LB0077 Labour 0.23570 day MT0043 Sand 0.01100 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02200 cu.m MT0145 Cement (OPC / PSC) 0.01020 tonne FL0051

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.16890 day LB0077 Labour 0.26910 day MT0043 Sand 0.01780 cu.m MT0070 Crushed Rock - 20mm 0.03560 cu.m MT0145 Cement (OPC / PSC) 0.01506 tonne FL0052

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.16890 day LB0077 Labour 0.30310 day MT0043 Sand 0.02224 cu.m MT0070 Crushed Rock - 20mm 0.04449 cu.m MT0145 Cement (OPC / PSC) 0.01829 tonne

P&L cement concrete flooring 1:2:4, finished with f loating coat of neat cement - 20mm aggregates, 50mm thick

P&L pointing on brick flooring with cement mortar 1 :2 - Ruled pointing

P&L cement concrete flooring 1:2:4, finished with f loating coat of neat cement - 20mm aggregates, 40mm thick

P&L Pointing on brick flooring with cement mortar 1 :6 - Flush pointing

P&L Pointing on brick flooring with cement mortar 1 :6 - Ruled pointing

P&L cement concrete flooring 1:2:4, finished with f loating coat of neat cement - 12mm aggregates, 25mm thick

P&L pointing on brick flooring with cement mortar 1 :4 - Flush pointing

P&L pointing on brick flooring with cement mortar 1 :4 - Ruled pointing

Department of Engineering Services, MoWHS

Page 113: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 110

FL0053

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.18720 day LB0077 Labour 0.36180 day MT0043 Sand 0.03339 cu.m MT0070 Crushed Rock - 20mm 0.06679 cu.m MT0145 Cement (OPC / PSC) 0.02580 tonne FL0054

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.16890 day LB0077 Labour 0.26910 day MT0043 Sand 0.17800 cu.m MT0081 Gravel\Shingles (River stone) - 20mm to 10mm 0.35600 cu.m MT0145 Cement (OPC / PSC) 0.01500 tonne FL0055

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.16890 day LB0077 Labour 0.30310 day MT0043 Sand 0.22200 cu.m MT0081 Gravel\Shingles (River stone) - 20mm to 10mm 0.44500 cu.m MT0145 Cement (OPC / PSC) 0.01820 tonne FL0060

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.15700 day LB0077 Labour 0.29700 day MT0043 Sand 0.02430 cu.m MT0070 Crushed Rock - 20mm 0.04870 cu.m MT0145 Cement (OPC / PSC) 0.01380 tonne FL0061

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.15700 day LB0077 Labour 0.29700 day MT0043 Sand 0.02430 cu.m MT0081 Gravel\Shingles (River stone) - 20mm to 10mm 0.04870 cu.m MT0145 Cement (OPC / PSC) 0.01380 tonne FL0070

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.33750 day LB0077 Labour 1.16100 day MT0043 Sand 0.02624 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02670 cu.m MT0145 Cement (OPC / PSC) 0.01792 tonne MT0150 Red Oxide Pigment\other pigments 0.58100 kg FL0075

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.27000 day LB0077 Labour 0.47000 day MT0043 Sand 0.02220 cu.m MT0070 Crushed Rock - 20mm 0.03340 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02260 cu.m MT0145 Cement (OPC / PSC) 0.02630 tonne MT0152 Floor Hardener (metallic) 2.07000 kg

P&L cement concrete flooring 1:3:6, finished with a floating coat of neat cement - 20mm river gravel, 50mm

P&L cement concrete flooring 1:2:4, finished with f loating coat of neat cement - 20mm river gravel, 50 mm thick

P&L cement concrete flooring 1:3:6, finished with a floating coat of neat cement - 20mm aggregates, 50 mm

P&L 62mm thick flooring with sub-layer cement concr ete 1:2:4 20mm aggregates, top layer with metallic cement hardener consisting of mix 1:2 (1 cement hardener: 2 6mm sto ne aggregate), the metallic hardening compound is m ixed by volume in the ratio 4 parts of cement & 1 part of metallic ha rdening compound including cement slurry - 50mm thi ck sub-layer and 12mm topping

P&L cement concrete flooring 1:2:4, finished with f loating coat of neat cement - 20mm aggregates, 75mm thick

P&L 40mm red oxide flooring, finished with a floati ng coat of neat cement (red oxide mixed) including cement slurry etc. complete - Under layer of 30mm thick cement concret e 1:2:4, 12.5mm aggregates and top layer of 10mm th ick plaster of cement red oxide mixed

P&L cement concrete flooring 1:2:4, finished with f loating coat of neat cement - 20mm river gravel, 40 mm thick

Department of Engineering Services, MoWHS

Page 114: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 111

FL0080

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.04400 day LB0077 Labour 0.04400 day FL0085

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.27000 day LB0077 Labour 1.75600 day MT0043 Sand 0.01510 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.03029 cu.m MT0085 Marble Chips 6mm - Black or White 0.00870 tonne MT0145 Cement (OPC / PSC) 0.01500 tonne FL0086

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.27000 day LB0077 Labour 1.75600 day MT0043 Sand 0.01510 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.03029 cu.m MT0085 Marble Chips 6mm - Black or White 0.00870 tonne MT0145 Cement (OPC / PSC) 0.01180 tonne MT0146 White Cement 0.00430 tonne FL0095

Coefficient for per sq.m

Code Description Quant Units MT0086 Marble Chips 6mm - Coloured 0.00870 tonne FL0096

Coefficient for per sq.m

Code Description Quant Units MT0086 Marble Chips 6mm - Coloured 0.01400 tonne FL0105

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.27000 day LB0077 Labour 1.75600 day MT0043 Sand 0.01398 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02800 cu.m MT0085 Marble Chips 6mm - Black or White 0.01398 tonne MT0145 Cement (OPC / PSC) 0.01600 tonne FL0106

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.27000 day LB0077 Labour 1.75600 day MT0043 Sand 0.01400 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02800 cu.m MT0085 Marble Chips 6mm - Black or White 0.01400 tonne MT0145 Cement (OPC / PSC) 0.01000 tonne MT0146 White Cement 0.00600 tonne

Extra, for coloured chips instead of black, white o r black and white chips in top 10mm layer marble ch ips flooring

P&L 40mm thick marble chips flooring top layer 10mm thick with white, black or black and white marble chips of size 6mm in proportion 1:2 (cement : chips), on 30mm cement concrete 1:2:4 base, 12.5mm aggregate - In grey cem ent

P&L 40mm thick marble chips flooring top layer 10mm thick with white, black or black and white marble chips of size 6mm in proportion 1:2 (cement : chips), on 30mm cement concrete 1:2:4 base, 12.5mm aggregate - In white ce ment

Extra, for coloured chips instead of black, white o r black and white chips in top 6mm layer of marble chips flooring

Extra for making chequers on concrete floors, steps , landings, pavements etc.

P&L 40mm thick marble chips flooring top layer 6mm thick with white, black or black and white marble c hips of nominal size 1.5-3mm in proportion 1:2 (cement: chips), on 34mm thick concrete base in cement concrete 1:2:4, 12.5mm aggregate ( cement and marble powder mix shall be of the ratio 3 part of cement to 1 part of marble powder) - In w hite cement

P&L 40mm thick marble chips flooring top layer 6mm thick with white, black or black and white marble c hips of nominal size 1.5-3mm in proportion 1:2 (cement: chips), on 34mm thick concrete base in cement concrete 1:2:4, 12.5mm aggregate ( cement and marble powder mix shall be of the ratio 3 part of cement to 1 part of marble powder) - In g rey cement

Department of Engineering Services, MoWHS

Page 115: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 112

FL0115

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.03313 day LB0077 Labour 0.03313 day MT0655 Plain Glass - 3mm thick 0.04800 sq.m FL0116

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.02500 day LB0077 Labour 0.05000 day FL0117

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.03750 day LB0077 Labour 0.07500 day FL0118

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.00315 day LB0077 Labour 0.00470 day FL0119

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.12500 day LB0077 Labour 0.15600 day FL0120

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.03130 day LB0077 Labour 0.03130 day MT0161 Aluminium Strip 40x1.6mm 1.00000 m FL0130

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.23400 day LB0077 Labour 0.32744 day MT0043 Sand 0.02514 cu.m MT0145 Cement (OPC / PSC) 0.01308 tonne FL0131

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.23400 day LB0077 Labour 0.33081 day MT0043 Sand 0.02836 cu.m MT0145 Cement (OPC / PSC) 0.01461 tonne FL0140

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.33700 day LB0077 Labour 1.80758 day MT0043 Sand 0.01862 cu.m MT0085 Marble Chips 6mm - Black or White 0.00870 tonne MT0145 Cement (OPC / PSC) 0.01317 tonne

Extra, for laying terrazzo in narrow bands width <7 5mm

Extra, for making moulded nosing in terrazzo, inclu ding moulded returns, ends, angles

Providing & fixing aluminium strip 40x1.6mm in join ts of terrazzo floor

P&L Cement plaster skirting < 300mm height with cem ent mortar 1:3 with a floating coat of neat cement including rounding off junctions with floor - 20mm

P&L Cement plaster skirting < 300mm height with cem ent mortar 1:3 with a floating coat of neat cement including rounding off junctions with floor - 22mm

Providing & fixing Terrazzo or Marble chips skirtin g < 300mm height top layer 6mm thick with white or black, black and white marble chips size 4mm in proportion 1:2 ,laid on 12.5mm thick cement plaster 1:3 base - In grey cement

Extra, for Providing & fixing glass strips in joint s of terrazzo floors

Extra, for terrazzo flooring laid as floor borders, margins, bands, 75 < width > 300mm

Extra, for laying terrazzo flooring on stair case t reads, width < 300mm, including forming nosing

Department of Engineering Services, MoWHS

Page 116: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 113

FL0141

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.33700 day LB0077 Labour 1.80758 day MT0043 Sand 0.01862 cu.m MT0085 Marble Chips 6mm - Black or White 0.00870 tonne MT0145 Cement (OPC / PSC) 0.00887 tonne MT0146 White Cement 0.00430 tonne FL0150

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 2.87720 day MT0043 Sand 0.02397 cu.m MT0090 Marble Slab 20mm - Black 1.15000 sq.m MT0145 Cement (OPC / PSC) 0.01351 tonne FL0151

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 2.87720 day MT0043 Sand 0.02397 cu.m MT0091 Marble Slab 20mm - White 1.15000 sq.m MT0145 Cement (OPC / PSC) 0.01351 tonne FL0152

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 2.87720 day MT0043 Sand 0.02397 cu.m MT0092 Marble Slab 20mm - Black and White 1.15000 sq.m MT0145 Cement (OPC / PSC) 0.01351 tonne FL0153

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 2.87720 day MT0043 Sand 0.02397 cu.m MT0103 Marble Slab 40mm - Coloured 1.15000 sq.m MT0145 Cement (OPC / PSC) 0.01351 tonne FL0154

Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 2.87720 day MT0043 Sand 0.02397 cu.m MT0100 Marble Slab 40mm - Black 1.15000 sq.m MT0145 Cement (OPC / PSC) 0.01391 tonne FL0155

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 1.66520 day MT0043 Sand 0.02397 cu.m MT0101 Marble Slab 40mm - White 1.15000 sq.m MT0145 Cement (OPC / PSC) 0.01391 tonne

P&L marble stone flooring over 20mm thick base of c ement mortar 1:4, jointed with grey cement slurry m ixed with pigment where necessary, rubbing & polishing complete - 40m m thick white marble

Providing & fixing Terrazzo or Marble chips skirtin g < 300mm height top layer 6mm thick with white or black, black and white marble chips size 4mm in proportion 1:2 ,laid on 12.5mm thick cement plaster 1:3 base - In white cement

P&L marble stone flooring over 20mm thick base of c ement mortar 1:4, jointed with grey cement slurry m ixed with pigment where necessary, rubbing & polishing complete - 20m m thick black marble

P&L marble stone flooring over 20mm thick base of c ement mortar 1:4, jointed with grey cement slurry m ixed with pigment where necessary, rubbing & polishing complete - 20m m thick white marble

P&L marble stone flooring over 20mm thick base of c ement mortar 1:4, jointed with grey cement slurry m ixed with pigment where necessary, rubbing & polishing complete - 20m m thick black and white marble

P&L marble stone flooring over 20mm thick base of c ement mortar 1:4, jointed with grey cement slurry m ixed with pigment where necessary, rubbing & polishing complete - 20m m thick coloured marble

P&L marble stone flooring over 20mm thick base of c ement mortar 1:4, jointed with grey cement slurry m ixed with pigment where necessary, rubbing & polishing complete - 40m m thick black marble

Department of Engineering Services, MoWHS

Page 117: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 114

FL0156

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 2.87720 day MT0043 Sand 0.02397 cu.m MT0102 Marble Slab 40mm - Black and White 1.15000 sq.m MT0145 Cement (OPC / PSC) 0.01391 tonne FL0157

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 2.87720 day MT0043 Sand 0.02397 cu.m MT0093 Marble Slab 20mm - Coloured 1.15000 sq.m MT0145 Cement (OPC / PSC) 0.01351 tonne FL0160

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 1.87720 day MT0043 Sand 0.02397 cu.m MT0110 Kota Stone Slab - 20mm 1.10000 sq.m MT0145 Cement (OPC / PSC) 0.01351 tonne FL0161

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 1.75000 day LB0077 Labour 1.87720 day MT0043 Sand 0.02397 cu.m MT0111 Kota Stone Slab - 40mm 1.10000 sq.m MT0145 Cement (OPC / PSC) 0.01351 tonne FL0170

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.24380 day LB0077 Labour 0.66630 day FL0171

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.25000 day LB0077 Labour 0.50000 day FL0180

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0356 Pre-laminated (both sides) Bison panel - 25mm 1.05000 sq.m FL0181

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0357 Pre-laminated (both sides) Bison panel - 30mm 1.05000 sq.m

Extra, for marble stone flooring for nosing in step -treads

Providing & fixing bison panel flooring including n ails/screws etc. complete excluding the cost of fra me - 25mm

Providing & fixing bison panel flooring including n ails/screws etc. complete excluding the cost of fra me - 30mm

P&L marble stone flooring over 20mm thick base of c ement mortar 1:4, jointed with grey cement slurry m ixed with pigment where necessary, rubbing & polishing complete - 40m m thick black and white marble

P&L marble stone flooring over 20mm thick base of c ement mortar 1:4, jointed with grey cement slurry m ixed with pigment where necessary, rubbing & polishing complete - 40m m thick coloured marble

P&L Kota stone flooring over 20mm thick base of cem ent mortar 1:4, jointed with grey cement slurry mix ed with pigment where necessary, rubbing & polishing complete - 20m m

P&L Kota stone flooring over 20mm thick base of cem ent mortar 1:4, jointed with grey cement slurry mix ed with pigment where necessary, rubbing & polishing complete - 40m m

Extra, for marble stone flooring for laying in step -treads, width < 300 mm

Department of Engineering Services, MoWHS

Page 118: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 115

FL0190

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0369 Plain Particle Board - 25mm 1.00000 sq.m FL0191

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0370 Plain Particle Board - 35mm 1.00000 sq.m FL0200

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.27000 day LB0077 Labour 0.13500 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02981 cu.m FL0201

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.21000 day LB0077 Labour 0.11000 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02981 cu.m FL0202

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0077 Labour 0.14300 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04600 cu.m FL0203

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.26000 day LB0077 Labour 0.15600 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04600 cu.m FL0204

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.31200 day LB0077 Labour 0.15700 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04950 cu.m FL0205

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.27200 day LB0077 Labour 0.16700 day MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04950 cu.m

Providing & fixing Mixed Conifer Flooring including fixing with iron screws etc. complete, excluding t he cost of frame - 25mm thick, half-lapped

Providing & fixing Mixed Conifer Flooring including fixing with iron screws etc. complete, excluding t he cost of frame - 40mm thick, T&G

Providing & fixing Mixed Conifer Flooring including fixing with iron screws etc. complete, excluding t he cost of frame - 40mm thick, half-lapped

Providing & fixing Mixed Conifer Flooring including fixing with iron screws etc. complete, excluding t he cost of frame - 45mm thick, T&G

Providing & fixing Mixed Conifer Flooring including fixing with iron screws etc. complete, excluding t he cost of frame - 45mm thick, half-lapped

Providing & fixing Plain Particle-Board Flooring fi xing with necessary screws etc. complete, excluding cost of frame - 25mm

Providing & fixing Plain Particle-Board Flooring fi xing with necessary screws etc. complete, excluding cost of frame - 35mm

Providing & fixing Mixed Conifer Flooring including fixing with iron screws etc. complete, excluding t he cost of frame - 25mm thick, T&G

Department of Engineering Services, MoWHS

Page 119: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 116

FL0210

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 2.18700 day LB0039 Work Supervisor (Lajab) 0.12500 day LB0077 Labour 4.68500 day MT0001 Bitumen 80\100 0.00450 tonne MT0331 Rough-sawn timber (urban rate) - Class 'A', (Blue pine, Champ) 0.04180 cu.m FL0215

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0395 Flooring - 25mm, Mixed conifer 1.00000 sq.m FL0216

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.23800 day LB0077 Labour 0.23800 day MT0396 Flooring - 38mm, Blue pine 1.00000 sq.m FL0225

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.07000 day LB0051 Mason Gd.2 0.13450 day LB0077 Labour 0.41070 day MT0001 Bitumen 80\100 0.00357 tonne MT0035 Kerosene 0.25830 litre MT0043 Sand 0.01100 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02200 cu.m MT0145 Cement (OPC / PSC) 0.01020 tonne MT0672 Linoleum sheet, 1.3mm 1.00000 sq.m FL0230

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.01000 day LB0077 Labour 0.03000 day MT0042 Mud dry 0.10000 cu.m MT0044 Hay/husk 0.80000 kg

Providing & fixing Pre-Fabricated Flooring Profiles in mixed conifer including necessary screws etc. c omplete - 25mm thick

Providing & fixing Pre-Fabricated Flooring Profiles in mixed conifer including necessary screws etc. c omplete - 38mm thick

Providing & fixing 2mm thick Vinyl or Linoleum shee t 1.3mm laid with special adhesive, including 2 coa t of bitumen applied over subfloor on prepared surface @ 1.5 kg/sq.m eac h coat including the cost of base concrete

- Over base of 25mm thick cement concrete 1:2:4 , 1 2.5mm aggregate

P&L rammed mud flooring complete

Providing & fixing Parquet (wood block) flooring in cluding blown bitumen underlay and iron screws etc. complete, excluding cost of frame - 38mm thick, champ wood

Department of Engineering Services, MoWHS

Page 120: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 117

CHAPTER 14

GL0001

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.96000 day LB0077 Labour 0.97575 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.01044 tonne MT0665 Glazed tiles - white, 150 x 150mm 45.00000 each GL0005

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.58300 day LB0077 Labour 0.59875 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.01044 tonne MT0665 Glazed tiles - white, 150 x 150mm 45.00000 each GL0006

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.87500 day LB0077 Labour 0.89075 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.01044 tonne MT0671 Glazed tiles - White,100 x 100 mm 100.00000 each GL0007

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.87500 day LB0077 Labour 0.81575 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.01044 tonne MT0670 Glazed tiles - White,200 x 100 mm 50.00000 each GL0008

Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 0.73000 day LB0077 Labour 0.74575 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.01044 tonne MT0669 Glazed tiles - White,200 x 200 mm 25.00000 each GL0009

Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 0.66000 day LB0077 Labour 0.67575 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.01044 tonne MT0668 Glazed tiles - White, 300 x 300 mm 12.00000 each GL0015 Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 0.19000 day LB0077 Labour 0.19000 day GL0016

Coefficient for per sq.m Code Description Quant Units LB0036 Mason Gd.1 1.09500 day LB0077 Labour 1.09500 day

Extra for laying glazed tiles - In treads of steps, width <300mm

Extra for laying glazed tiles - In skirting, risers of steps, dado where tiles are required to be cut (only area of portion of cut tiles to be measured)

Providing & fixing white/ coloured Glazed tiles, 15 0 x 150 mm in skirting, step risers, dado, finished with flush-pointing in white cement

Providing & fixing white/ coloured glazed tiles in flooring, treads of steps and landings laid on bed of 12mm thick cement mortar 1:3 finished with flush pointing in white ce ment: - for 150 x 150 mm

Providing & fixing white/ coloured glazed tiles in flooring, treads of steps and landings laid on bed of 12mm thick cement mortar 1:3 finished with flush pointing in white ce ment: - for 100 x 100 mm

Providing & fixing white/ coloured glazed tiles in flooring, treads of steps and landings laid on bed of 12mm thick cement mortar 1:3 finished with flush pointing in white ce ment: - for 200 x 100 mm

Providing & fixing white/ coloured glazed tiles in flooring, treads of steps and landings laid on bed of 12mm thick cement mortar 1:3 finished with flush pointing in white ce ment: - for 200 x 200 mm

Providing & fixing white/ coloured glazed tiles in flooring, treads of steps and landings laid on bed of 12mm thick cement mortar 1:3 finished with flush pointing in white ce ment: - for 300 x 300 mm

TILING - WALL & FLOOR

Department of Engineering Services, MoWHS

Page 121: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 118

CHAPTER 15

RF0001

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.10500 day LB0039 Work Supervisor (Lajab) 0.00900 day LB0077 Labour 0.10500 day MT0275 Corrugated G.I Sheets - 24G (0.63mm) 0.00710 tonne RF0003

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.10500 day LB0039 Work Supervisor (Lajab) 0.00900 day LB0077 Labour 0.10500 day MT0278 Pre Painted Galvanised Steel Corrugated Roofing sheets 24g 0.00710 tonne

RF0005

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.24100 day LB0039 Work Supervisor (Lajab) 0.04800 day LB0077 Labour 0.29000 day MT0250 Plain G.I Sheet, 24-gauge (0.63mm) 0.00454 tonne RF0006

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.24100 day LB0039 Work Supervisor (Lajab) 0.04800 day LB0077 Labour 0.29000 day MT0252 Pre Painted Galvanised Steel sheets 24g 0.00454 tonne

RF0010

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.11600 day LB0033 Carpenter Gd.2 0.08630 day LB0039 Work Supervisor (Lajab) 0.03160 day LB0077 Labour 0.23200 day MT0182 Rolled sections (250 MPa) - Flats 0.83000 kg MT0250 Plain G.I Sheet, 24-gauge (0.63mm) 0.00283 tonne RF0015

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.01400 day LB0039 Work Supervisor (Lajab) 0.00086 day LB0077 Labour 0.01400 day RF0016

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03400 day

Extra, for Providing & fixing curved C.G.I sheet in roofing

Extra, for Providing & fixing C.G.I sheets vertical ly or to a pitch >60 degrees

Providing & fixing Corrugated Galvanised Iron (CGI) sheeting, including bolts, hooks and nuts 8mm dia. with bitumen and G.I limpet washers filled with white lead for conne ction, excluding the cost of purlins, rafter and tr usses - 24g

ROOFING

Providing & fixing 600mm ridges or hips in plain G. I including bolts, hooks and nuts 8mm dia G.I limpe t and bitumen washers for connection - 24g

Providing & fixing 450mm over all semi-circular pla in G.I gutter, including brackets, bolts, nuts, was hers & rain water pipes connections, excluding the cost of pipes - 24g shee t

Providing & fixing Pre Painted Galvanised Steel Cor rugated Roofing sheets, including bolts, hooks and nuts 8mm dia. with bitumen and G.I limpet washers filled with white le ad for connection, excluding the cost of purlins, r after and trusses - 24g

Providing & fixing 600mm ridges or hips in Pre Pain ted Galvanised Steel sheets, including bolts, hooks and nuts 8mm dia G.I limpet and bitumen washers for connection - 24g

Department of Engineering Services, MoWHS

Page 122: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 119

RF0017

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.05000 day LB0033 Carpenter Gd.2 0.01753 day LB0039 Work Supervisor (Lajab) 0.00150 day LB0077 Labour 0.06753 day MT0275 Corrugated G.I Sheets - 24G (0.63mm) 0.00119 tonne RF0025

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.06250 day LB0077 Labour 0.01550 day RF0026

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.10400 day LB0077 Labour 0.10400 day RF0027

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.15600 day LB0077 Labour 0.15600 day RF0060

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.02100 day LB0077 Labour 0.02100 day MT0182 Rolled sections (250 MPa) - Flats 2.00000 kg RF0065

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.20600 day LB0077 Labour 0.37100 day MT0045 Straw, girth <100mm 15.00000 bundle MT0390 Bamboo - 25mm dia 23.40000 m RF0066

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.16000 day LB0077 Labour 0.10500 day MT0390 Bamboo - 25mm dia 18.64000 m RF0067

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.43800 day LB0077 Labour 0.40700 day MT0044 Hay/husk 10.00000 kg MT0390 Bamboo - 25mm dia 25.20000 m RF0075

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.18600 day LB0051 Mason Gd.2 0.18600 day LB0077 Labour 0.37300 day MT0005 Bitumen felt Type 3 - Grade 1 1.05000 sq.m MT0285 R o o f i n g S l a t e - 600mm x 300mm 10.00000 each

Providing & fixing wind tie of 40 x 6 mm flats

Providing & fixing 150mm thatched roofing, includin g straws/grass bundles, half split bamboo fillet, t ying strings complete

Providing & fixing 25mm dia. bamboos at 225mm apart including moonj ban(rope) or string

Providing & fixing thatched coping to ridges and hi ps, girth < 1 metre including tying and split bambo o wind tie complete

Providing & fixing single slate roofing including b itumen felt water-proofing etc complete, excluding the cost of wooden reapers, trusses

Extra, for making straight-cut openings (in 24g) fo r chimney, sky lights

Extra, for making opening or recess in CGI roofing of girth < 1 metre - Area upto 0.01sq.m

Extra, for making opening or recess in CGI roofing of girth < 1 metre - 0.01 < Area < 0.04sq.m

Extra, for making opening or recess in CGI roofing of girth < 1 metre - Area > 0.04sq.m

Department of Engineering Services, MoWHS

Page 123: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 120

RF0080

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.01300 day LB0033 Carpenter Gd.2 0.01300 day LB0077 Labour 0.07000 day MT0290 Plain Pantile / Roman II 500mm x 250mm concrete tiles - 6mm 12.50000 each RF0081

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.01300 day LB0033 Carpenter Gd.2 0.01300 day LB0077 Labour 0.07000 day MT0291 Plain Pantile / Roman II 500mm x 250mm concrete tiles - 8mm 12.50000 each RF0082

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.01300 day LB0033 Carpenter Gd.2 0.01300 day LB0077 Labour 0.07000 day MT0292 Plain Pantile / Roman II 500mm x 250mm concrete tiles - 10mm 12.50000 each RF0090

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.01300 day LB0033 Carpenter Gd.2 0.01300 day LB0077 Labour 0.07000 day MT0295 Coloured Pantile / Roman II 500mm x 250mm concrete tiles - 6mm 12.50000 each RF0091

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.01300 day LB0033 Carpenter Gd.2 0.01300 day LB0077 Labour 0.07000 day MT0296 Coloured Pantile / Roman II 500mm x 250mm concrete tiles - 8mm 12.50000 each RF0092

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.01300 day LB0033 Carpenter Gd.2 0.01300 day LB0077 Labour 0.07000 day MT0297 Coloured Pantile / Roman II 500mm x 250mm concrete tiles - 10mm 12.50000 each RF0100

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.01000 day LB0033 Carpenter Gd.2 0.01000 day LB0077 Labour 0.05000 day MT0300 Super Roman 600mm x 330mm x 10mm concrete tiles - Plain 8.00000 each RF0105

Coefficient for per sq.m Code Description Quant Units LB0021 Carpenter Gd.1 0.01000 day LB0033 Carpenter Gd.2 0.01000 day LB0077 Labour 0.05000 day MT0301 Super Roman 600mm x 330mm x 10mm concrete tiles - Coloured 8.00000 each

Providing & fixing COLOURED Super Roman concrete ti les-600mm x 330mm including tying wires but excludi ng the cost of frame work - 10mm

Providing & fixing PLAIN Pantile or Roman II conc rete tiles-500mm x 250mm including tying wires but excluding the cost of frame work - 8mm

Providing & fixing PLAIN Pantile or Roman II conc rete tiles-500mm x 250mm including tying wires but excluding the cost of frame work - 10mm

Providing & fixing COLOURED Pantile or Roman concr ete tiles-500mm x 250mm including tying wires but e xcluding the cost of frame work - 6mm

Providing & fixing COLOURED Pantile or Roman concr ete tiles-500mm x 250mm including tying wires but e xcluding the cost of frame work - 8mm

Providing & fixing COLOURED Pantile or Roman concr ete tiles-500mm x 250mm including tying wires but e xcluding the cost of frame work - 10mm

Providing & fixing PLAIN Super Roman concrete tiles -600mm x 330mm including tying wires but excluding the cost of frame work - 10mm

Providing & fixing PLAIN Pantile or Roman II conc rete tiles-500mm x 250mm including tying wires but excluding the cost of frame work - 6mm

Department of Engineering Services, MoWHS

Page 124: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 121

RF0110

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day LB0033 Carpenter Gd.2 0.00800 day LB0077 Labour 0.05000 day MT0305 Semi-sheet 600mm x 600mm x 8mm concrete tiles - Plain 4.00000 each RF0115

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.00800 day LB0033 Carpenter Gd.2 0.00800 day LB0077 Labour 0.05000 day MT0306 Semi-sheet 600mm x 600mm x 8mm concrete tiles - Coloured 4.00000 each RF0120

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.00200 day LB0033 Carpenter Gd.2 0.00200 day LB0077 Labour 0.02500 day MT0310 Hip/Ridge, 600mm - Plain 2.00000 each RF0121

Coefficient for per m

Code Description Quant Units LB0021 Carpenter Gd.1 0.00200 day LB0033 Carpenter Gd.2 0.00200 day LB0077 Labour 0.02500 day MT0311 Hip/Ridge, 600mm - Coloured 2.00000 each RF0130

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.15000 day LB0077 Labour 0.15000 day MT0060 Boulder 0.06000 cu.m MT0315 S h i n g l e p r o o f i n g - 1500mm (approx.) 10.00000 pair RF0135

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.10500 day LB0039 Work Supervisor (Lajab) 0.00900 day LB0077 Labour 0.10500 day MT0320 Red mud plastic corrugated sheet, 1.5mm 1.28000 sq.m RF0136

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.24100 day LB0039 Work Supervisor (Lajab) 0.04800 day LB0077 Labour 0.29000 day MT0321 Red mud plastic plain sheet, 1.3mm 1.18520 m RF0150

Coefficient for per sq.m

Code Description Quant Units LB0033 Carpenter Gd.2 0.15000 day LB0039 Work Supervisor (Lajab) 0.08800 day LB0077 Labour 0.15000 day MT0280 Reinforced polyester transparent sheets - 1.2mm, corrugated 1.05000 sq.m

Providing & fixing red mud corrugated plastic sheet ing, 1.5 mm thick

Providing & fixing red mud plastic sheet 600 mm rid ging, 1.3mm thick

P&f 1.2mm transparent sheet including 8mm G.I J or L hooks, bitumen & G.I limpet washers etc complete, excluding cost of frame

Providing & fixing PLAIN Semi-Sheet concrete tiles- 600mm x 600mm including tying wires but excluding t he cost of frame work - 8mm

Providing & fixing COLOURED Semi-Sheet concrete til es-600mm x 600mm including tying wires but excludin g the cost of frame work - 8mm

Providing and fixing concrete tiles ridges or hips including tying wire etc. complete - Plain

Providing and fixing concrete tiles ridges or hips including tying wire etc. complete - Coloured

Providing & fixing shinglep roofing with shinglep o f size 1350x125x12mm in 3 layers including tying, u plift protection complete

Department of Engineering Services, MoWHS

Page 125: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 122

RF0155

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.00600 day LB0039 Work Supervisor (Lajab) 0.00500 day LB0051 Mason Gd.2 0.13100 day LB0077 Labour 1.14438 day MT0120 Slaked lime 13.50000 kg MT0126 Brick aggregate 0.10000 cu.m MT0127 Graded brick aggregate 0.04750 cu.m RF0156

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.00600 day LB0039 Work Supervisor (Lajab) 0.00500 day LB0051 Mason Gd.2 0.13100 day LB0077 Labour 1.19438 day MT0001 Bitumen 80\100 0.00170 tonne MT0035 Kerosene 0.12300 litre MT0120 Slaked lime 13.50000 kg MT0126 Brick aggregate 0.10000 cu.m MT0127 Graded brick aggregate 0.04750 cu.m RF0165

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.00863 day LB0039 Work Supervisor (Lajab) 0.00575 day LB0051 Mason Gd.2 0.00863 day LB0052 Painter Gd.1 0.01870 day LB0053 Plant Operator Gd.3 0.00805 day LB0077 Labour 0.31969 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00805 day MP0206 Concrete Vibrator(M/C5) 0.00805 day MT0001 Bitumen 80\100 0.00170 tonne MT0035 Kerosene 0.12200 litre MT0040 Firewood (stacked volume) 0.00410 cu.m MT0043 Sand 0.06005 cu.m MT0070 Crushed Rock - 20mm 0.10810 cu.m MT0145 Cement (OPC / PSC) 0.02530 tonne RF0166

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.01870 day LB0077 Labour 0.04800 day MT0001 Bitumen 80\100 0.00170 tonne MT0035 Kerosene 0.12200 litre MT0040 Firewood (stacked volume) 0.00041 cu.m MT0043 Sand 0.00600 cu.m RF0175

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.04700 day LB0077 Labour 0.11600 day MT0760 Cast Iron - Pipe, 100mm dia. 1.05000 m RF0176

Coefficient for per each

Code Description Quant UnitsLB0077 Labour 0.00773 day

MT0762 Cast Iron - Head 100mm 1.00000 each

P&L cement concrete terracing on roof with cement c oncrete 1:3:6, 20mm aggregates over a base coat of bitumen 80/100 mixed with coarse sand - Painting roof with bitumen including spreading sand, cleaning slab etc. compl ete

Providing & fixing C.I. rain water pipes & fittings with necessary screws on the wall face including f illing joints etc. complete - 100mm dia C.I pipes

Providing & fixing C.I. rain water pipes & fittings with necessary screws on the wall face including f illing joints etc. complete - 100mm dia C.I. head for pipe

P&L lime concrete terracing on roofing , average de pth 100mm - including drainage fall, ramming, round ing at parapets

P&L lime concrete terracing on roofing , average de pth 100mm - including drainage fall, ramming, round ing at parapets and under-coat of hot bitumen 80/100

P&L cement concrete terracing on roof with cement c oncrete 1:3:6, 20mm aggregates over a base coat of bitumen 80/100 mixed with coarse sand - 115mm average thickness

Department of Engineering Services, MoWHS

Page 126: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 123

RF0177

Coefficient for per each

Code Description Quant UnitsLB0077 Labour 0.00773 day

MT0761 Cast Iron - Bend 100mm 1.00000 each RF0178

Coefficient for per each

Code Description Quant UnitsLB0077 Labour 0.00773 day

MT0765 Cast Iron - Shoe, 100mm 1.00000 each RF0185

Coefficient for per each

Code Description Quant UnitsLB0077 Labour 0.00773 day

MT0763 Cast Iron - Offset 100mm, 75mm projection 1.00000 each RF0186

Coefficient for per each

Code Description Quant UnitsLB0077 Labour 0.00773 day

MT0764 Cast Iron - Offset 100mm, 150mm projection 1.00000 each

RF0190

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber gd.1 0.35000 dayLB0077 Labour 0.40000 dayMT1160 Pipe, single socketed 3m long, 75 mm dia 0.33333 mMT1320 seal ring - 75 mm 0.33333 each

RF0191

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber gd.1 0.35000 dayLB0077 Labour 0.40000 dayMT1161 Pipe, single socketed 3m long, 90 mm dia 0.33333 mMT1321 seal ring - 90 mm 0.33333 each

RF0192

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber gd.1 0.35000 dayLB0077 Labour 0.40000 dayMT1162 Pipe, single socketed 3m long, 110 mm dia 0.33333 mMT1322 seal ring -110 mm 0.33333 each

RF0195

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1205 Coupler - 75 mm 1.00000 eachMT1320 seal ring -75 mm 2.00000 each

Providing & fixing 100mm dia C.I. offset for rain w ater pipe on wall face including filling joints - 1 50mm projection

Providing and fixing on wall face single socketed r igid PVC ( Working Pressure 4kgf per sq.cm) rain wa ter pipes including jointing with seal ring leaving 10 mm gap for therm al expansion complete - 75 mm dia

Providing and fixing on wall face single socketed r igid PVC (Working Pressure 4kgf per sq.cm) rain wat er pipes including jointing with seal ring leaving 10 mm gap for therm al expansion complete - 90 mm dia

Providing and fixing on wall face single socketed r igid PVC (Working Pressure 4kgf per sq.cm) rain wat er pipes including jointing with seal ring leaving 10 mm gap for therm al expansion complete - 110 mm dia

Providing and fixing on wall face PVC coupler for r igid rain water pipes including jointing with seal ring leaving 10 mm gap for thermal expansion complete - 75 mm dia

Providing & fixing C.I. rain water pipes & fittings with necessary screws on the wall face including f illing joints etc. complete - 100mm dia C.I bend for pipe

Providing & fixing C.I. rain water pipes & fittings with necessary screws on the wall face including f illing joints etc. complete - 100mm dia C.I. shoes for pipe

Providing & fixing 100mm dia C.I. offset for rain w ater pipe on wall face including filling joints - 7 5mm projection

Department of Engineering Services, MoWHS

Page 127: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 124

RF0196

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1206 Coupler - 90 mm 1.00000 eachMT1321 seal ring -90 mm 2.00000 each

RF0197

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1207 Coupler - 110 mm 1.00000 eachMT1322 seal ring -110 mm 2.00000 each

RF0200

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1255 Single Tee with door- 75 mm 1.00000 eachMT1320 seal ring -75 mm 2.00000 each

RF0201

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1256 Single Tee with door- 90 mm 1.00000 eachMT1321 seal ring -90 mm 2.00000 each

RF0202

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1257 Single Tee with door- 110 mm 1.00000 eachMT1322 seal ring -110 mm 2.00000 each

RF0205

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1245 Single Tee , plain - 75 mm 1.00000 eachMT1320 seal ring -75 mm 2.00000 each

RF0206

Coefficient for eachCode Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1246 Single Tee , plain - 90 mm 1.00000 eachMT1321 seal ring -90 mm 2.00000 each

RF0207

Coefficient for eachCode Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1247 Single Tee , plain - 110 mm 1.00000 eachMT1322 seal ring -110 mm 2.00000 each

Providing and fixing on wall face PVC plain single tee for rigid rain water pipes including jointing with seal ring leaving 10 mm gap for thermal expansion complete - 110mm dia

Providing and fixing on wall face PVC coupler for r igid rain water pipes including jointing with seal ring leaving 10 mm gap for thermal expansion complete - 110 mm dia

Providing and fixing on wall face PVC single tee wi th door for rigid rain water pipes including jointi ng with seal ring leaving 10 mm gap for thermal expansion complete - 75 mm di a

Providing and fixing on wall face PVC single tee wi th door for rigid rain water pipes including jointi ng with seal ring leaving 10 mm gap for thermal expansion complete -90 mm dia

Providing and fixing on wall face PVC single tee wi th door for rigid rain water pipes including jointi ng with seal ring leaving 10 mm gap for thermal expansion complete -110 mm di a

Providing and fixing on wall face PVC plain single tee for rigid rain water pipes including jointing with seal ring leaving 10 mm gap for thermal expansion complete - 75 mm dia

Providing and fixing on wall face PVC plain single tee for rigid rain water pipes including jointing with seal ring leaving 10 mm gap for thermal expansion complete - 90 mm dia

Providing and fixing on wall face PVC coupler for r igid rain water pipes including jointing with seal ring leaving 10 mm gap for thermal expansion complete - 90 mm dia

Department of Engineering Services, MoWHS

Page 128: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 125

RF0210

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1215 Plain Bend - 75 mm 1.00000 eachMT1320 seal ring -75 mm 2.00000 each

RF0211

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1216 Plain Bend -90 mm 1.00000 eachMT1321 seal ring -90 mm 2.00000 each

RF0212

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1217 Plain Bend -110 mm 1.00000 eachMT1322 seal ring -110 mm 2.00000 each

RF0215

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1239 Plain Shoe - 75 mm 1.00000 eachMT1320 seal ring -75 mm 2.00000 each

RF0216

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1240 Plain Shoe - 90 mm 1.00000 eachMT1321 seal ring -90 mm 2.00000 each

RF0217

Coefficient for each

Code Description Quant UnitsLB0038 Plumber gd.1 0.05000 dayLB0077 Labour 0.05000 dayMT1241 Plain Shoe -110 mm 1.00000 eachMT1322 seal ring -110 mm 2.00000 each

Providing and fixing on wall face PVC bend for rig id rain water pipes including jointing with seal ri ng leaving 10 mm gap for thermal expansion complete -110 mm dia

Providing and fixing on wall face PVC bend for rig id rain water pipes including jointing with seal ri ng leaving 10 mm gap for thermal expansion complete - 75 mm dia

Providing and fixing on wall face PVC bend for rig id rain water pipes including jointing with seal ri ng leaving 10 mm gap for thermal expansion complete - 90 mm dia

Providing and fixing on wall face PVC bend for rig id rain water pipes including jointing with seal ri ng leaving 10 mm gap for thermal expansion complete - 110 mm dia

Providing and fixing on wall face PVC bend for rig id rain water pipes including jointing with seal ri ng leaving 10 mm gap for thermal expansion complete - 75 mm dia

Providing and fixing on wall face PVC bend for rig id rain water pipes including jointing with seal ri ng leaving 10 mm gap for thermal expansion complete - 90 mm dia

Department of Engineering Services, MoWHS

Page 129: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 126

CHAPTER 16

PI0001

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.08400 day LB0077 Labour 0.08400 day MT0805 G.I pipe - 15mm 1.00000 m PI0002

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.10250 day LB0077 Labour 0.08400 day MT0806 G.I pipe - 20mm 1.00000 m PI0003

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.12300 day LB0077 Labour 0.08400 day MT0807 G.I pipe - 25mm 1.00000 m PI0004

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.12300 day LB0077 Labour 0.12300 day MT0808 G.I pipe - 32mm 1.00000 m PI0005

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.16400 day LB0077 Labour 0.16400 day MT0809 G.I pipe - 40mm 1.00000 m PI0006

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.20500 day LB0077 Labour 0.20500 day MT0810 G.I pipe - 50mm 1.00000 m PI0010

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.10250 day LB0077 Labour 0.08400 day MT0817 H.D.P.E pressure class 10kg/sq.cm - 20mm 1.00000 m PI0011

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.12300 day LB0077 Labour 0.08400 day MT0818 H.D.P.E pressure class 10kg/sq.cm - 25mm 1.00000 m

Providing & fixing G.I pipes including G.I fittings & clamps & repair walls - 40mm

Providing & fixing G.I pipes including G.I fittings & clamps & repair walls - 50mm

Providing & fixing H.D.P.E pipes including clamps & repair walls etc. complete - 20mm

Providing & fixing H.D.P.E pipes including clamps & repair walls etc. complete - 25mm

Providing & fixing G.I pipes including G.I fittings & clamps & repair walls - 15mm

PLUMBING - INDOOR WORK

Providing & fixing G.I pipes including G.I fittings & clamps & repair walls - 20mm

Providing & fixing G.I pipes including G.I fittings & clamps & repair walls - 25mm

Providing & fixing G.I pipes including G.I fittings & clamps & repair walls - 32mm

Department of Engineering Services, MoWHS

Page 130: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 127

PI0012

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.21300 day LB0077 Labour 0.21300 day MT0819 H.D.P.E pressure class 10kg/sq.cm - 32mm 1.00000 m PI0013

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.16400 day LB0077 Labour 0.16400 day MT0820 H.D.P.E pressure class 10kg/sq.cm - 40mm 1.00000 m PI0014

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04200 day LB0054 Plumber Gd.2 0.20500 day LB0077 Labour 0.20500 day MT0821 H.D.P.E pressure class 10kg/sq.cm - 50mm 1.00000 m PI0020

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.94000 day LB0052 Painter Gd.1 0.28224 day LB0077 Labour 2.15724 day MP0202 Welder - electric arc 4.70400 day MT0191 Sheet (250 MPa) - 2mm 46.00000 kg MT0711 Synthetic red lead primer 0.15552 litre MT0726 Black\White bitumen enamel 0.27360 litre

MT0753C.I manhole cover 400mm dia. inside, mosquito proof with locking arrangement (Wt of cover not less than 7kg). 1.00000 each

MT0807 G.I pipe - 25mm 1.50000 m MT0809 G.I pipe - 40mm 0.30000 m MT1440 15mm ball valve with plastic float 1.00000 each PI0021

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 1.25000 day LB0052 Painter Gd.1 0.58212 day LB0077 Labour 3.08212 day MP0202 Welder - electric arc 6.72000 day MT0192 Sheet (250 MPa) - 2.8mm 134.00000 kg MT0711 Synthetic red lead primer 0.32076 litre MT0726 Black\White bitumen enamel 0.56430 litre

MT0753C.I manhole cover 400mm dia. inside, mosquito proof with locking arrangement (Wt of cover not less than 7 kg 1.00000 each

MT0807 G.I pipe - 25mm 1.50000 m MT0809 G.I pipe - 40mm 0.30000 m MT1440 15mm ball valve with plastic float 1.00000 each

Providing & fixing H.D.P.E pipes including clamps & repair walls etc. complete - 50mm

Providing & fixing storage tank of M.S. sheet welde d all round, including 40mm G.I scour pipe, 25mm G. I overflow , 15mm ball valve , pads for inlet and outlet pipes , red lead primer & two coats of bitumastic paint - 270 l itre capacity of 2mm steel sheet

Providing & fixing storage tank of M.S. sheet welde d all round, including 40mm G.I scour pipe, 25mm G. I overflow , 15mm ball valve , pads for inlet and outlet pipes , red lead primer & two coats of bitumastic paint

- 810 litre capacity of 2.8mm steel sheet

Providing & fixing H.D.P.E pipes including clamps & repair walls etc. complete - 32mm

Providing & fixing H.D.P.E pipes including clamps & repair walls etc. complete - 40mm

Department of Engineering Services, MoWHS

Page 131: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 128

PI0022

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 2.18750 day LB0052 Painter Gd.1 0.84672 day LB0077 Labour 5.22172 day MP0202 Welder - electric arc 8.06400 day MT0193 Sheet (250 MPa) - 3.5mm 219.00000 kg MT0711 Synthetic red lead primer 0.46656 litre MT0726 Black\White bitumen enamel 0.82080 litre

MT0753 C.I manhole cover 400mm dia. inside, mosquito proof with locking arrangement (Wt of cover not less than 7kg)

1.00000 each MT0807 G.I pipe - 25mm 1.50000 m MT0809 G.I pipe - 40mm 0.30000 m MT1440 15mm ball valve with plastic float 1.00000 each PI0030

Coefficient for per each

Code Description Quant Units LB0054 Plumber Gd.2 0.16670 day LB0077 Labour 0.33330 day MT1440 15mm ball valve with plastic float 1.00000 each MT1665 H.D.P.E water storage tank - 270 litres 1.00000 each PI0031

Coefficient for per each

Code Description Quant Units LB0054 Plumber Gd.2 0.20000 day LB0077 Labour 0.40000 day MT1440 15mm ball valve with plastic float 1.00000 each MT1666 H.D.P.E water storage tank - 500 litres 1.00000 each PI0032

Coefficient for per each

Code Description Quant Units LB0054 Plumber Gd.2 0.25000 day LB0077 Labour 0.50000 day MT1440 15mm ball valve with plastic float 1.00000 each MT1667 H.D.P.E water storage tank - 1000 litres 1.00000 each PI0033

Coefficient for per each

Code Description Quant Units LB0054 Plumber Gd.2 0.20000 day LB0077 Labour 0.60000 day MT1440 15mm ball valve with plastic float 1.00000 each MT1668 H.D.P.E water storage tank - 2000 litres 1.00000 each PI0034

Coefficient for per each

Code Description Quant Units LB0054 Plumber Gd.2 0.20000 day LB0077 Labour 0.80000 day MT1440 15mm ball valve with plastic float 1.00000 each MT1669 H.D.P.E water storage tank - 3000 litres 1.00000 each PI0040

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.63000 day LB0038 Plumber Gd.1 1.56000 day LB0077 Labour 1.25000 day MT1142 P-type Nahani Trap - C.I. P-trap 100mm 1.00000 each MT1402 W.C. P a n s - Vitreous China Indian type - 500mm, white 1.00000 each MT1430 Vitreous China cistern - low level, incl. fittings & flush-bend - 10 litres, white 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair

Providing & fixing plastic tank including all acces sories complete - 270 litre capacity

Providing & fixing plastic tank including all acces sories complete - 500 litre capacity

Providing & fixing plastic tank including all acces sories complete - 1000 litre capacity

Providing & fixing plastic tank including all acces sories complete - 2000 litre capacity

Providing & fixing plastic tank including all acces sories complete - 3000 litre capacity

Providing & fixing Indian-type vitreous china w.c s quatting pan, including 100 mm H.C.I. P or S trap, 10l low level vitreous china cistern & fittings, repair walls - 500mm, whi te

Providing & fixing storage tank of M.S. sheet welde d all round, including 40mm G.I scour pipe, 25mm G. I overflow , 15mm ball valve , pads for inlet and outlet pipes , red lead primer & two coats of bitumastic paint

- 1620 litre capacity of 3.15mm steel sheet

Department of Engineering Services, MoWHS

Page 132: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 129

PI0041

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.63000 day LB0038 Plumber Gd.1 1.56000 day LB0077 Labour 1.25000 day MT1142 P-type Nahani Trap - C.I. P-trap 100mm 1.00000 each MT1403 W.C. P a n s - Vitreous China Indian type - 580mm Orissa, white 1.00000 each MT1430 Vitreous China cistern - low level, incl. fittings & flush-bend - 10 litres, white 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair PI0042

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.63000 day LB0038 Plumber Gd.1 1.56000 day LB0077 Labour 1.25000 day MT1142 P-type Nahani Trap - C.I. P-trap 100mm 1.00000 each MT1404 W.C. P a n s - Vitreous China Indian type - 580mm Orissa, colour 1.00000 each MT1430 Vitreous China cistern - low level, incl. fittings & flush-bend - 10 litres, white 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair PI0050

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 1.25000 day LB0051 Mason Gd.2 1.25000 day LB0077 Labour 1.25000 day MT1400 W.C. P a n s - Vitreous China European - white 1.00000 each MT1405 W.C. P a n s - Plastic seat & lid for European pan 1.00000 each MT1430 Vitreous China cistern - low level, incl. fittings & flush-bend - 10 litres, white 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair PI0051

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 1.25000 day LB0051 Mason Gd.2 1.25000 day LB0077 Labour 1.25000 day MT1401 W.C. P a n s - Vitreous China European - colour 1.00000 each MT1405 W.C. P a n s - Plastic seat & lid for European pan 1.00000 each MT1431 Vitreous China cistern - low level, incl. fittings & flush-bend - 10 litres, colour 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair PI0060

Coefficient for per pair

Code Description Quant Units LB0036 Mason Gd.1 0.07500 day MT1406 W.C. P a n s - Vitreous China Footrests (250 x 130 x 30), for Indian pan 1.00000 pair PI0065

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 1.10000 day LB0038 Plumber Gd.1 1.10000 day LB0077 Labour 1.88000 day MT1420 C.I. Automatic flushing Cistern with fittings - 5 litres 1.00000 each MT1445 White vitreous China flat-back lipped-front type urinals, 430 x 260 x 350mm 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair

Providing & fixing Indian-type vitreous china w.c s quatting pan, including 100 mm H.C.I. P or S trap, 10l low level vitreous china cistern & fittings, repair walls - 580mm, whi te Orissa-model

Providing & fixing Indian-type vitreous china w.c s quatting pan, including 100 mm H.C.I. P or S trap, 10l low level vitreous china cistern & fittings, repair walls - 580mm, col our Orissa-model

Providing & fixing European-type vitreous china w.c pedestal including seat and lid with c.p. brass hi nges, 15l white vitreous china low level cistern, fittings, bracket s, repair walls - white, with plastic seat & lid

Providing & fixing European-type vitreous china w.c pedestal including seat and lid with c.p. brass hi nges, 15l white vitreous china low level cistern, fittings, bracket s, repair walls - coloured, with plastic seat & lid

Providing & fixing white vitreous china foot rests (250x130x30mm) for Indian W.C

Providing & fixing white vitreous china flat back, lipped front urinal basin 430x260x350mm including C .I cistern & fittings, brackets, G.I flush pipe & spreaders, brass unions, G.I clamps, painting, repair walls - One bowl-5 li tres. C.I. cistern

Department of Engineering Services, MoWHS

Page 133: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 130

PI0066

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 1.88000 day LB0038 Plumber Gd.1 1.88000 day LB0077 Labour 2.50000 day MT1421 C.I. Automatic flushing Cistern with fittings - 10 litres 1.00000 each MT1445 White vitreous China flat-back lipped-front type urinals, 430 x 260 x 350mm 2.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair PI0067

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 2.50000 day LB0038 Plumber Gd.1 2.50000 day LB0077 Labour 3.75000 day MT1421 C.I. Automatic flushing Cistern with fittings - 10 litres 1.00000 each MT1445 White vitreous China flat-back lipped-front type urinals, 430 x 260 x 350mm 3.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair PI0075

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.63000 day LB0077 Labour 1.25000 day MT0922 M.I. Fittings Union - 40mm 1.00000 each MT1355 Porcelain bath tub, white enamelled, 1700x740x440mm 1.00000 each MT1541 C.p Mixers - basin, elbow action, surgical, 15mm 1.00000 each MT1591 C.p. brass waste - 40mm 1.00000 each MT1601 C.p. brass chain with plug - 40mm 1.00000 each PI0076

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.41250 day LB0038 Plumber Gd.1 0.28000 day LB0077 Labour 0.70000 day MT0922 M.I. Fittings Union - 40mm 1.00000 each MT1356 Fibreglass bath tub 1.00000 each MT1541 C.p Mixers - basin, elbow action, surgical, 15mm 1.00000 each MT1591 C.p. brass waste - 40mm 1.00000 each MT1601 C.p. brass chain with plug - 40mm 1.00000 each PI0077

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1581 Traps, c.p - for bath 1.00000 each PI0085

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.41000 day LB0038 Plumber Gd.1 0.41000 day LB0077 Labour 0.84000 day MT0921 M.I. Fittings Union - 32mm 1.00000 each MT1360 Flat-back wash basin, white vitreous - 630 x 450mm 1.00000 each MT1460 15mm pillar cock 2.00000 each MT1580 Traps, c.p - 32mm 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair MT1590 C.p. brass waste - 32mm 1.00000 each MT1600 C.p. brass chain with plug - 32mm 1.00000 each

- Flat back wash basin 630x450mm with a pair of 15m m c.p. brass pillar taps

Providing & fixing white vitreous china flat back, lipped front urinal basin 430x260x350mm including C .I cistern & fittings, brackets, G.I flush pipe & spreaders, brass unions, G.I clamps, painting, repair walls - Two bowls-10 litres. C.I. cistern

Providing & fixing white vitreous china flat back, lipped front urinal basin 430x260x350mm including C .I cistern & fittings, brackets, G.I flush pipe & spreaders, brass unions, G.I clamps, painting, repair walls - Three bowls-1 0 litres. C.I. cistern

Providing and fixing bath tubs with fittings and ac cessories complete - Porcelain, white enamelled, wi th a pair of 20mm C.P pillar tap, 40mm C.P brass waste, 32mm C.P brass ov er flow, rubber plug, 40mm C.P trap etc.

Providing and fixing bath tubs with fittings and ac cessories complete - Fibreglass tub, white

Providing and fixing bath tubs with fittings and ac cessories complete - P-Trap, heavy duty, for bath-t ub

Providing & fixing white vitreous china wash basin, including C.I brackets, 15mm C.P. brass pillar tap s, c.p. chain & rubber plug, 32mm pvc. waste, 32mm dia. trap & union, repa ir walls

Department of Engineering Services, MoWHS

Page 134: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 131

PI0086

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.41000 day LB0038 Plumber Gd.1 0.38000 day LB0077 Labour 0.80000 day MT0921 M.I. Fittings Union - 32mm 1.00000 each MT1360 Flat-back wash basin, white vitreous - 630 x 450mm 1.00000 each MT1460 15mm pillar cock 1.00000 each MT1580 Traps, c.p - 32mm 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair MT1590 C.p. brass waste - 32mm 1.00000 each MT1600 C.p. brass chain with plug - 32mm 1.00000 each PI0087

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.41000 day LB0038 Plumber Gd.1 0.41000 day LB0077 Labour 0.84000 day MT0921 M.I. Fittings Union - 32mm 1.00000 each MT1361 Flat-back wash basin, white vitreous - 550 x 400mm 1.00000 each MT1460 15mm pillar cock 2.00000 each MT1580 Traps, c.p - 32mm 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair MT1590 C.p. brass waste - 32mm 1.00000 each MT1600 C.p. brass chain with plug - 32mm 1.00000 each PI0088

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.41000 day LB0038 Plumber Gd.1 0.38000 day LB0077 Labour 0.80000 day MT0921 M.I. Fittings Union - 32mm 1.00000 each MT1361 Flat-back wash basin, white vitreous - 550 x 400mm 1.00000 each MT1460 15mm pillar cock 1.00000 each MT1580 Traps, c.p - 32mm 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair MT1590 C.p. brass waste - 32mm 1.00000 each MT1600 C.p. brass chain with plug - 32mm 1.00000 each PI0095

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.41000 day LB0038 Plumber Gd.1 0.38000 day LB0077 Labour 0.80000 day MT0921 M.I. Fittings Union - 32mm 1.00000 each MT1365 Angle back wash basin - 400mm x 400mm, white vitreous china 1.00000 each MT1460 15mm pillar cock 1.00000 each MT1580 Traps, c.p - 32mm 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair MT1590 C.p. brass waste - 32mm 1.00000 each MT1600 C.p. brass chain with plug - 32mm 1.00000 each

- Flat back wash basin 550x400mm with single 15mm c .p. brass pillar tap

Providing & fixing white vitreous china angle back wash basin 400x400mm including brackets, 15mm c.p. brass pillar taps, c.p. brass chain & rubber plug, 32mm c.p. brass was te, 32mm dia c.p. brass trap and M.I. union and rep air

walls - With single 15mm c.p. brass pillar tap

Providing & fixing white vitreous china wash basin, including C.I brackets, 15mm C.P. brass pillar tap s, c.p. chain & rubber plug, 32mm pvc. waste, 32mm dia. trap & union, repa ir walls

- Flat back wash basin 630x450mm with single 15mm c.p. brass pillar tap.

Providing & fixing white vitreous china wash basin, including C.I brackets, 15mm C.P. brass pillar tap s, c.p. chain & rubber plug, 32mm pvc. waste, 32mm dia. trap & union, repa ir walls

- Flat back wash basin 550x400mm with a pair of 15m m c.p. brass pillar taps

Providing & fixing white vitreous china wash basin, including C.I brackets, 15mm C.P. brass pillar tap s, c.p. chain & rubber plug, 32mm pvc. waste, 32mm dia. trap & union, repa ir walls

Department of Engineering Services, MoWHS

Page 135: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 132

PI0096

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.41000 day LB0038 Plumber Gd.1 0.41000 day LB0077 Labour 0.84000 day MT0921 M.I. Fittings Union - 32mm 1.00000 each MT1365 Angle back wash basin - 400mm x 400mm, white vitreous china 1.00000 each MT1460 15mm pillar cock 2.00000 each MT1580 Traps, c.p - 32mm 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair MT1590 C.p. brass waste - 32mm 1.00000 each MT1600 C.p. brass chain with plug - 32mm 1.00000 each PI0105

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1450 Flush fittings - c.p flush valve, 32mm 1.00000 each PI0106

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1451 Flush fittings - c.p flush valve, 32mm, concealed 1.00000 each PI0107

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1452 Flush fittings - c.p flush bend, long 1.00000 each PI0108

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1453 Flush fittings - c.p flush valve elbow 1.00000 each PI0115

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.05000 day MT1370 Pedestal for wash basin - white vitreous china 1.00000 each PI0120

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.41000 day LB0038 Plumber Gd.1 0.28000 day LB0077 Labour 0.70000 day MT0922 M.I. Fittings Union - 40mm 1.00000 each MT1375 Sinks White glazed vitreous China - 600 x 450 x 250 1.00000 each MT1585 Brackets - R.S. or C.I Brackets 1.00000 pair MT1600 C.p. brass chain with plug - 32mm 1.00000 each PI0121

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.20500 day LB0038 Plumber Gd.1 0.14000 day LB0077 Labour 0.35000 day MT1380 Stainless Steel Kitchen Sinks - single bowl, 450 x 400 x 150mm 1.00000 each

Providing & fixing c.p. concealed flush valve, 32mm with 40mm outlet

Providing & fixing c.p. flush bend, long

Providing & fixing c.p. flush valve elbow

Providing & fixing pedestals for basins, white vitr eous china, recessed back for pipes and necessary f ittings

Providing & fixing Kitchen Sinks including all conn ections and fittings - White glazed vitreous china 600 x 450 x 250 mm including accessories and repairs to walls etc.

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 450 x 400 x 150 mm, single bowl

Providing & fixing white vitreous china angle back wash basin 400x400mm including brackets, 15mm c.p. brass pillar taps, c.p. brass chain & rubber plug, 32mm c.p. brass was te, 32mm dia c.p. brass trap and M.I. union and rep air

walls - With pair of 15mm c.p. brass pillar taps

Providing & fixing c.p. flush valve, 32mm with 40mm outlet

Department of Engineering Services, MoWHS

Page 136: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 133

PI0122

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.20500 day LB0038 Plumber Gd.1 0.14000 day LB0077 Labour 0.35000 day MT1381 Stainless Steel Kitchen Sinks - single bowl, 580 x 480 x 175mm 1.00000 each PI0123

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.30750 day LB0038 Plumber Gd.1 0.21000 day LB0077 Labour 0.52500 day MT1382 Stainless Steel Kitchen Sinks - single bowl & drain-board, 940 x 460 x 160mm 1.00000 each PI0124

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.30750 day LB0038 Plumber Gd.1 0.21000 day LB0077 Labour 0.52500 day MT1383 Stainless Steel Kitchen Sinks - single bowl & drain-board, 1080 x 520 x 175mm 1.00000 each PI0125

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.30750 day LB0038 Plumber Gd.1 0.21000 day LB0077 Labour 0.52500 day MT1384 Stainless Steel Kitchen Sinks - single bowl & drain-board, 1150 x 515 x 175mm 1.00000 each PI0126

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.41000 day LB0038 Plumber Gd.1 0.28000 day LB0077 Labour 0.70000 day

MT1385 Stainless Steel Kitchen Sinks - single bowl & double drain-board, 1740 x 520 x 200mm 1.00000 each PI0127

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.30750 day LB0038 Plumber Gd.1 0.21000 day LB0077 Labour 0.52500 day MT1386 Stainless Steel Kitchen Sinks - double bowl, 940 x 460 x 160mm 1.00000 each PI0128

Coefficient for per each Code Description Quant Units LB0021 Carpenter Gd.1 0.30750 day LB0038 Plumber Gd.1 0.21000 day LB0077 Labour 0.52500 day MT1387 Stainless Steel Kitchen Sinks - double bowl, 1150 x 520 x 150mm 1.00000 each PI0129

Coefficient for per each Code Description Quant Units LB0021 Carpenter Gd.1 0.41000 day LB0038 Plumber Gd.1 0.28000 day LB0077 Labour 0.70000 day

MT1388 Stainless Steel Kitchen Sinks - double bowl & single drain-board, 1740 x 520 x 200mm 1.00000 each

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 1150 x 520 x 160 mm, single bowl

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 1740 x 520 x 200 mm, double bowl & single drain-board

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 580 x 480 x 175 mm, single bowl

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 940 x 460 x 160 mm, single bowl & drain-board

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 1080 x 520 x 175 mm, single bowl & drain-board

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 1150 x 515 x 175 mm, single bowl & drain-board

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 1740 x 520 x 200 mm, single bowl & double drain-board

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 940 x 460 x 160 mm, double bowl

Department of Engineering Services, MoWHS

Page 137: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 134

PI0130

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.41000 day LB0038 Plumber Gd.1 0.28000 day LB0077 Labour 0.70000 day

MT1389Stainless Steel Kitchen Sinks - double bowl & double drain-board, 1740 x 520 x 165mm 1.00000 each

PI0140

Coefficient for per each

Code Description Quant Units LB0021 Carpenter Gd.1 0.22000 day LB0038 Plumber Gd.1 0.07500 day LB0077 Labour 0.28000 day MT1390 Stainless Steel Kitchen Sinks - single drain-board, 610 x 460mm 1.00000 each PI0141

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.05000 day MT1600 C.p. brass chain with plug - 32mm 1.00000 each PI0150

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.05000 day MT1595 PVC waste - 32mm 1.00000 each PI0151

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.05000 day MT1590 C.p. brass waste - 32mm 1.00000 each PI0152

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.05000 day MT1591 C.p. brass waste - 40mm 1.00000 each PI0160

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day LB0077 Labour 0.01271 day MT0043 Sand 0.01209 cu.m MT0145 Cement (OPC / PSC) 0.00576 tonne MT1645 Electric Water Heaters - 10 litres, vertical 1.00000 each PI0161

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day LB0077 Labour 0.01541 day MT0043 Sand 0.01466 cu.m MT0145 Cement (OPC / PSC) 0.00699 tonne MT1646 Electric Water Heaters - 15 litres, vertical 1.00000 each PI0162

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day LB0077 Labour 0.01620 day MT0043 Sand 0.01541 cu.m MT0145 Cement (OPC / PSC) 0.00734 tonne MT1647 Electric Water Heaters - 25 litres, vertical 1.00000 each

Providing & fixing 32mm c.p. brass waste

Providing & fixing 40mm c.p. brass waste

Providing & fixing Electric water heater including necessary fittings - 10 litres

Providing & fixing Electric water heater including necessary fittings - 15 litres

Providing & fixing Electric water heater including necessary fittings - 25 litres

Providing & fixing Kitchen Sinks including all conn ections and fittings - Stainless steel, 1740 x 520 x 200 mm, double bowl & double drain-board

Providing & fixing stainless steel drain-board, 610 x 460 mm with all necessary fittings

Providing & fixing c.p. brass chain & rubber plug f or basin and sink

Providing & fixing 32mm dia pvc. waste

Department of Engineering Services, MoWHS

Page 138: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 135

PI0163

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day LB0077 Labour 0.01620 day MT0043 Sand 0.01541 cu.m MT0145 Cement (OPC / PSC) 0.00734 tonne MT1648 Electric Water Heaters - 35 litres, vertical 1.00000 each PI0164

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day LB0077 Labour 0.02025 day MT0043 Sand 0.01926 cu.m MT0145 Cement (OPC / PSC) 0.00918 tonne MT1649 Electric Water Heaters - 50 litres, vertical 1.00000 each PI0165

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day LB0077 Labour 0.02025 day MT0043 Sand 0.01926 cu.m MT0145 Cement (OPC / PSC) 0.00918 tonne MT1650 Electric Water Heaters - 75 litres, vertical 1.00000 each PI0166

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day LB0077 Labour 0.02149 day MT0043 Sand 0.02044 cu.m MT0145 Cement (OPC / PSC) 0.00974 tonne MT1651 Electric Water Heaters - 100 litres, vertical 1.00000 each PI0175

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1513 C.p Brass Shower fittings for 15 to 20mm inlet - shower, revolving joint 1.00000 each PI0176

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day

MT1514C.p Brass Shower fittings for 15 to 20mm inlet - shower, adjustable with locking key 1.00000 each

PI0177

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1515 C.p Brass Shower fittings for 15 to 20mm inlet - shower arm, 15mm 1.00000 each PI0178

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day

MT1516 C.p Brass Shower fittings for 15 to 20mm inlet - shower arm, 15mm, heavy duty 1.00000 each PI0179

Coefficient for per each Code Description Quant Units LB0038 Plumber Gd.1 0.25000 day LB0077 Labour 0.25000 day MT1512 C.p Brass Shower fittings for 15 to 20mm inlet - shower, with flex tube 1.00000 each

Providing & fixing C.P. Brass shower fittings - Sho wer arm, heavy duty 15mm

Providing & fixing C.P. Brass shower fittings - Fle xible shower tube & shower

Providing & fixing Electric water heater including necessary fittings - 50 litres

Providing & fixing Electric water heater including necessary fittings - 75 litres

Providing & fixing Electric water heater including necessary fittings - 100 litres

Providing & fixing C.P. Brass shower fittings - Sho wer with revolving joint, 15mm

Providing & fixing C.P. Brass shower fittings - Adj ustable shower, with locking key, 15mm

Providing & fixing C.P. Brass shower fittings - Sho wer arm, standard 15mm

Providing & fixing Electric water heater including necessary fittings - 35 litres

Department of Engineering Services, MoWHS

Page 139: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 136

PI0185

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1468 15mm stop cock, c.p knob 1.00000 each PI0186

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1469 20mm stop cock, c.p knob 1.00000 each PI0187

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1472 20mm stop cock, H\D concealed, c.p knob 1.00000 each PI0188

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1470 15mm stop cock, concealed, c.p knob 1.00000 each PI0189

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1473 15mm angle stop cock, c.p knob 1.00000 each PI0195

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1460 15mm pillar cock 1.00000 each PI0196

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1461 15mm pillar cock, swan neck, c.p knob 1.00000 each PI0205

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1464 15mm bib cock, vertical, c.p knob 1.00000 each PI0206

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1465 15mm bib cock, inclined, c.p knob 1.00000 each PI0207

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1466 15mm bib cock, long nose, c.p knob 1.00000 each PI0208

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1467 15mm bib cock, long body, c.p knob 1.00000 each

Providing & fixing c.p. brass bibcock - 15mm, long body, c.p. knob

Providing & fixing c.p. brass stop cock - 15mm, ang le, c.p knob

Providing & fixing c.p. brass pillar-cock - 15mm, s tandard, c.p knob

Providing & fixing c.p. brass pillar-cock - 15mm, s wan neck, c.p knob

Providing & fixing c.p. brass bibcock - 15mm, stand ard vertical, c.p knob

Providing & fixing c.p. brass bibcock - 15mm, incli ned, c.p. knob

Providing & fixing c.p. brass bibcock - 15mm, long nose, c.p. knob

Providing & fixing c.p. brass stop cock - 15mm, sta ndard, c.p knob

Providing & fixing c.p. brass stop cock - 20mm, sta ndard, c.p knob

Providing & fixing c.p. brass stop cock - 20mm, hea vy-duty, c.p knob

Providing & fixing c.p. brass stop cock - 15mm, con cealed, c.p knob

Department of Engineering Services, MoWHS

Page 140: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 137

PI0215

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1530 C.p Mixers - basin, single-hole, casted spout, 15mm 1.00000 each PI0216

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1531 C.p Mixers - basin, close-hole, 15mm 1.00000 each PI0217

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1541 C.p Mixers - basin, elbow action, surgical, 15mm 1.00000 each PI0218

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1542 C.p Mixers - basin, elbow action, surgical with shower, 15mm 1.00000 each PI0219

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1532 C.p Mixers - sink, with spout J pipe, 15mm 1.00000 each PI0220

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1533 C.p Mixers - sink, with casted spout swinging, 15mm 1.00000 each PI0221

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1546 C.p Mixers - sink, with swivel spout, 15mm 1.00000 each PI0222

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1534 C.p Mixers - wall, non-telephonic type, 15mm 1.00000 each PI0223

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1535 C.p Mixers - wall, telephonic type with crutch and tel. shower, 15mm 1.00000 each PI0224

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1536 C.p Mixers - wall, telephonic type without crutch and tel. shower, 15mm 1.00000 each

Providing & fixing c.p. brass mixers, 15mm - For si nk, with casted spout swinging

Providing & fixing c.p. brass mixers, 15mm - For si nk, with swivel spout

Providing & fixing c.p. brass mixers, 15mm - For wa ll, non-telephonic type

Providing & fixing c.p. brass mixers, 15mm - For wa ll, telephonic type with crutch and tel. shower

Providing & fixing c.p. brass mixers, 15mm - For wa ll, telephonic type without crutch and tel. shower

Providing & fixing c.p. brass mixers, 15mm - For ba sin, single-hole, casted spout

Providing & fixing c.p. brass mixers, 15mm - For ba sin, close-hole

Providing & fixing c.p. brass mixers, 15mm - For ba sin, elbow action, surgical

Providing & fixing c.p. brass mixers, 15mm - For ba sin, elbow action, surgical with shower

Providing & fixing c.p. brass mixers, 15mm - For si nk, with spout J pipe

Department of Engineering Services, MoWHS

Page 141: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 138

PI0225

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1537 C.p Mixers - wall, telephonic type with crutch and without tel. shower, 15mm 1.00000 each PI0226

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1538 C.p Mixers - wall, telephonic type with C.P bend & flanges, 15mm 1.00000 each PI0227

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day

MT1544C.p Mixers - wall, with telephonic shower arrangement with 115mm long bend pipe for over head shower connection, 15 mm 1.00000 each

PI0228

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1539 C.p Mixers - Three hole mixer without pop-up, 15mm 1.00000 each PI0229

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1540 C.p Mixers - Three hole mixer with pop-up, 15mm 1.00000 each PI0230

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day

MT1543C.p Mixers - bath, with exposed adjustable legs with telephone shower arrangement with crutch, 15mm 1.00000 each

PI0231

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day

MT1545C.p Mixers - shower, three in one, with bend flexible tube, and shower & hook, 15mm 1.00000 each

PI0240

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.05000 day MT1474 Wall spout, std, 15mm 1.00000 each PI0241

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.05000 day MT1476 Wall spout, with diverter, used with single-lever mixers 1.00000 each PI0250

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.42000 day LB0077 Labour 0.42000 day MT1631 Mirror (Bevelled edge) 600mm x 450mm 1.00000 each

Providing & fixing Wall Spouts - C.p., standard, 15 mm

Providing & fixing Wall Spouts - With diverter, for use with single lever mixers

Providing & fixing 600x450mm bevelled edge mirror ( superior glass) fixed to wooden cleats

Providing & fixing c.p. brass mixers, 15mm - For wa ll, telephonic type with C.P bend & flanges

Providing & fixing c.p. brass mixers, 15mm - For wa ll, with telephonic shower arrangement with 115mm l ong bend pipe for over head shower connection

Providing & fixing c.p. brass mixers, 15mm - Three hole mixer without pop-up

Providing & fixing c.p. brass mixers, 15mm - Three hole mixer with pop-up

Providing & fixing c.p. brass mixers, 15mm - For ba th, with exposed adjustable legs with telephone sho wer arrangement with crutch

Providing & fixing c.p. brass mixers, 15mm - For sh ower, three in one, with bend flexible tube, and sh ower & hook

Providing & fixing c.p. brass mixers, 15mm - For wa ll, telephonic type with crutch and without tel. sh ower

Department of Engineering Services, MoWHS

Page 142: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 139

PI0251

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.32000 day LB0077 Labour 0.32000 day MT1630 Glass Shelf 1.00000 each PI0252

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.22000 day LB0077 Labour 0.22000 day MT1617 C.p Towel Rails - 20mm x 750mm 1.00000 each PI0253

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.22000 day LB0077 Labour 0.22000 day MT1616 C.p Towel Rails - 20mm x 600mm 1.00000 each PI0254

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.22000 day LB0077 Labour 0.22000 day MT1615 C.p Towel Rails - 20mm x 450mm 1.00000 each PI0255

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.11000 day LB0077 Labour 0.11000 day MT1618 C.p Towel Rails - C.p Towel Ring 1.00000 each PI0260

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.15000 day LB0077 Labour 0.15000 day MT1635 Toilet paper holders - C.P. brass 1.00000 each PI0261

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.15000 day LB0077 Labour 0.15000 day MT1637 Toilet paper holders - recessed ceramic (coloured), 200 x 100mm 1.00000 each PI0262

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1636 Toilet paper holders - recessed ceramic (white), 200 x 100mm 1.00000 each PI0263

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1638 Toilet paper holders - recessed ceramic (roll-type), 150 x 150mm 1.00000 each

Providing & fixing c.p. towel rail 450 x 20mm with c.p brass brackets fixed to wooden cleats

Providing & fixing c.p. towel ring

Providing & fixing toilet paper holder - C.P. brass

Providing & fixing toilet paper holder - Recessed c eramic, 200 x 100 mm, coloured

Providing & fixing toilet paper holder - Recessed c eramic, 200 x 100 mm, white

Providing & fixing toilet paper holder - Recessed c eramic, roll-type, 150 x 150 mm

Providing & fixing 450x120mm glass shelf, including c.p brass brackets fixed to wooden cleats

Providing & fixing c.p. towel rail 750 x 20mm with c.p brass brackets fixed to wooden cleats

Providing & fixing c.p. towel rail 600 x 20mm with c.p brass brackets fixed to wooden cleats

Department of Engineering Services, MoWHS

Page 143: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 140

PI0270

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.15000 day LB0077 Labour 0.15000 day MT1606 Soap Containers - c.p Liquid Soap Container 1.00000 each PI0275

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.15000 day LB0077 Labour 0.15000 day MT1605 Soap Containers - c.p brass with bracket 1.00000 each PI0276

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1608 Soap Containers - Recessed ceramic, 150 x 150mm 1.00000 each PI0277

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.10000 day MT1607 Soap Containers - Recessed ceramic, 200 x 100mm 1.00000 each PI0285

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.11000 day LB0077 Labour 0.11000 day MT1625 C.p Coat Hooks - single 1.00000 each PI0286

Coefficient for per each

Code Description Quant Units LB0033 Carpenter Gd.2 0.11000 day LB0077 Labour 0.11000 day MT1626 C.p Coat Hooks - double 1.00000 each

Providing & fixing Liquid soap container, c.p, incl uding c.p brass lid & brackets, wooden cleats, c.p brass screws

Providing & fixing soap dish - including brackets, wooden cleats, c.p. brass screws

Providing & fixing soap dish - Recessed, ceramic, 1 50x150 mm

Providing & fixing soap dish - Recessed, ceramic, 2 00x100 mm

Providing & fixing c.p. coat hook - Single

Providing & fixing c.p. coat hook - Double

Department of Engineering Services, MoWHS

Page 144: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 141

CHAPTER 17

PO0001

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.01000 day LB0077 Labour 0.02000 day MT0805 G.I pipe - 15mm 1.00000 m PO0002

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.01000 day LB0077 Labour 0.02000 day MT0806 G.I pipe - 20mm 1.00000 m PO0003

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.01500 day LB0077 Labour 0.03100 day MT0807 G.I pipe - 25mm 1.00000 m PO0004

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.01500 day LB0077 Labour 0.03600 day MT0808 G.I pipe - 32mm 1.00000 m PO0005

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day LB0077 Labour 0.04100 day MT0809 G.I pipe - 40mm 1.00000 m PO0006

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day LB0077 Labour 0.04100 day MT0810 G.I pipe - 50mm 1.00000 m PO0007

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03200 day LB0077 Labour 0.08300 day MT0811 G.I pipe - 65mm 1.00000 m PO0008

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03200 day LB0077 Labour 0.08300 day MT0812 G.I pipe - 80mm 1.00000 m PO0009

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04160 day LB0077 Labour 0.10800 day MT0813 G.I pipe - 100mm 1.00000 m

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 50mm

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 65mm

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 80mm

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 100mm

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 15mm

PLUMBING - OUTDOOR WORK

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 20mm

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 25mm

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 32mm

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 40mm

Department of Engineering Services, MoWHS

Page 145: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 142

PO0010

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0814 G.I pipe - 150mm 1.00000 m PO0015

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.01500 day LB0077 Labour 0.03100 day MT0818 H.D.P.E pressure class 10kg/sq.cm - 25mm 1.00000 m PO0016

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.01500 day LB0077 Labour 0.03600 day MT0819 H.D.P.E pressure class 10kg/sq.cm - 32mm 1.00000 m PO0017

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day LB0077 Labour 0.04100 day MT0820 H.D.P.E pressure class 10kg/sq.cm - 40mm 1.00000 m PO0018

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day LB0077 Labour 0.04100 day MT0821 H.D.P.E pressure class 10kg/sq.cm - 50mm 1.00000 m PO0019

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03200 day LB0077 Labour 0.08300 day MT0822 H.D.P.E pressure class 10kg/sq.cm - 63mm 1.00000 m PO0020

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03200 day LB0077 Labour 0.08300 day MT0823 H.D.P.E pressure class 10kg/sq.cm - 75mm 1.00000 m PO0021

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03680 day LB0077 Labour 0.10800 day MT0824 H.D.P.E pressure class 10kg/sq.cm - 90mm 1.00000 m PO0022

Coefficient for per m Code Description Quant Units LB0038 Plumber Gd.1 0.04780 day LB0077 Labour 0.10800 day MT0825 H.D.P.E pressure class 10kg/sq.cm - 110mm 1.00000 m

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 110mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 32mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 40mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 50mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 63mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 75mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 90mm

P&L G.I pipes including G.I fittings (excluding tre nching, refilling & thrust block) - 150mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) -25mm

Department of Engineering Services, MoWHS

Page 146: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 143

PO0023

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0826 H.D.P.E pressure class 10kg/sq.cm - 140mm 1.00000 m PO0024

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0827 H.D.P.E pressure class 10kg/sq.cm - 160mm 1.00000 m PO0025

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0828 H.D.P.E pressure class 10kg/sq.cm - 225mm 1.00000 m PO0030

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.01500 day LB0077 Labour 0.03600 day MT0830 H.D.P.E Pipes of pressure class 6kg/sq.cm - 32mm 1.00000 m PO0031

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day LB0077 Labour 0.04100 day MT0831 H.D.P.E Pipes of pressure class 6kg/sq.cm - 40mm 1.00000 m PO00032

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day LB0077 Labour 0.04100 day MT0832 H.D.P.E Pipes of pressure class 6kg/sq.cm - 50mm 1.00000 m PO0033

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03200 day LB0077 Labour 0.08300 day MT0833 H.D.P.E Pipes of pressure class 6kg/sq.cm - 63mm 1.00000 m PO0034

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03200 day LB0077 Labour 0.08300 day MT0834 H.D.P.E Pipes of pressure class 6kg/sq.cm - 75mm 1.00000 m

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 50mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 63mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 75mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 140mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 160mm

P&L H.D.P.E pipes, pressure class 10kg/sq.m, includ ing H.D.P.E fittings (excluding trenching, refillin g & thrust block) - 225mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 32 mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 40mm

Department of Engineering Services, MoWHS

Page 147: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 144

PO0035

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03680 day LB0077 Labour 0.10800 day MT0835 H.D.P.E Pipes of pressure class 6kg/sq.cm - 90mm 1.00000 m PO0036

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04780 day LB0077 Labour 0.10800 day MT0836 H.D.P.E Pipes of pressure class 6kg/sq.cm - 110mm 1.00000 m PO0037

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0837 H.D.P.E Pipes of pressure class 6kg/sq.cm - 140mm 1.00000 m PO0038

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0838 H.D.P.E Pipes of pressure class 6kg/sq.cm - 160mm 1.00000 m PO0039

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0839 H.D.P.E Pipes of pressure class 6kg/sq.cm - 225mm 1.00000 m PO0045

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day LB0077 Labour 0.04100 day MT0841 H.D.P.E Pipes of pressure class 4kg/sq.cm - 40mm 1.00000 m PO0046

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day LB0077 Labour 0.04100 day MT0842 H.D.P.E Pipes of pressure class 4kg/sq.cm - 50mm 1.00000 m PO0047

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03200 day LB0077 Labour 0.08300 day MT0843 H.D.P.E Pipes of pressure class 4kg/sq.cm - 63mm 1.00000 m

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 160mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 225mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 40mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 50mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 63mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 90mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 110mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 6 kg/sq.cm (excluding trenching, refilling & thrust block) - 140mm

Department of Engineering Services, MoWHS

Page 148: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 145

PO0048

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03200 day LB0077 Labour 0.08300 day MT0844 H.D.P.E Pipes of pressure class 4kg/sq.cm - 75mm 1.00000 m PO0049

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03680 day LB0077 Labour 0.10800 day MT0845 H.D.P.E Pipes of pressure class 4kg/sq.cm - 90mm 1.00000 m PO0050

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04780 day LB0077 Labour 0.10800 day MT0846 H.D.P.E Pipes of pressure class 4kg/sq.cm - 110mm 1.00000 m PO0051

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0847 H.D.P.E Pipes of pressure class 4kg/sq.cm - 140mm 1.00000 m PO0052

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0848 H.D.P.E Pipes of pressure class 4kg/sq.cm - 160mm 1.00000 m PO0053

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0849 H.D.P.E Pipes of pressure class 4kg/sq.cm - 225mm 1.00000 m PO0060

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04780 day LB0077 Labour 0.10800 day MT0852 H.D.P.E Pipes of pressure class 2.5kg/sq.cm - 110mm 1.00000 m PO0061

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0853 H.D.P.E Pipes of pressure class 2.5kg/sq.cm - 140mm 1.00000 m

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 2.5 kg/sq.cm (excluding trenching, refilli ng & thrust block) - 140mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 90mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 110mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 140mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 160mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 225mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 2.5 kg/sq.cm (excluding trenching, refilli ng & thrust block) - 110mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 4 kg/sq.cm (excluding trenching, refilling & thrust block) - 75mm

Department of Engineering Services, MoWHS

Page 149: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 146

PO0062

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0854 H.D.P.E Pipes of pressure class 2.5kg/sq.cm - 160mm 1.00000 m PO0063

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.06560 day LB0077 Labour 0.17000 day MT0855 H.D.P.E Pipes of pressure class 2.5kg/sq.cm - 225mm 1.00000 m

PO0065

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.01818 dayLB0077 Labour 0.04545 dayMT0856 DI pipe - 80 mm 1.00000 m

PO0066

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.01818 dayLB0077 Labour 0.04545 dayMT0857 DI pipe - 100 mm 1.00000 m

PO0067

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.03182 dayLB0077 Labour 0.06818 dayMT0858 DI pipe - 150 mm 1.00000 m

PO0068

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.04318 dayLB0077 Labour 0.07955 dayMT0859 DI pipe - 200 mm 1.00000 m

PO0069

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.05682 dayLB0077 Labour 0.10227 dayMT0860 DI pipe - 250 mm 1.00000 m

PO0070

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.06820 dayLB0077 Labour 0.13636 dayMT0861 DI pipe - 300 mm 1.00000 m

PO0071

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.08400 dayLB0077 Labour 0.15900 dayMT0862 DI pipe - 350 mm 1.00000 m

Providing and Laying Ductile Iron K - 9 pipes - 20 0 mm

Providing and Laying Ductile Iron K - 9 pipes - 25 0 mm

Providing and Laying Ductile Iron K - 9 pipes - 30 0 mm

Providing and Laying Ductile Iron K - 9 pipes - 35 0 mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 2.5 kg/sq.cm (excluding trenching, refilli ng & thrust block) - 160mm

P&L H.D.P.E Pipes including H.D.P.E fittings pressu re class 2.5 kg/sq.cm (excluding trenching, refilli ng & thrust block) - 225mm

Providing and Laying Ductile Iron K - 9 pipes - 80 mm

Providing and Laying Ductile Iron K - 9 pipes - 10 0 mm

Providing and Laying Ductile Iron K - 9 pipes - 15 0 mm

Department of Engineering Services, MoWHS

Page 150: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 147

PO0072

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.11360 dayLB0077 Labour 0.20450 dayMT0863 DI pipe - 350 mm 1.00000 m

PO0073

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.13636 dayLB0077 Labour 0.23860 dayMT0864 DI pipe - 450 mm 1.00000 m

PO0074

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.16346 dayLB0077 Labour 0.27272 dayMT0865 DI pipe - 500 mm 1.00000 m

PO0075

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.19318 dayLB0077 Labour 0.38600 dayMT0866 DI pipe - 600 mm 1.00000 m

PO0078Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.01818 dayLB0077 Labour 0.04545 dayMT0871 DI pipe - 100 mm 1.00000 m

PO0079Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.03182 dayLB0077 Labour 0.06818 dayMT0872 DI pipe - 150 mm 1.00000 m

PO0080Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.04318 dayLB0077 Labour 0.07955 dayMT0873 DI pipe - 200 mm 1.00000 m

PO0081Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.05682 dayLB0077 Labour 0.10227 dayMT0874 DI pipe - 250 mm 1.00000 m

PO0082Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.06820 dayLB0077 Labour 0.13636 dayMT0875 DI pipe - 300 mm 1.00000 m

PO0083Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.08400 dayLB0077 Labour 0.15900 dayMT0876 DI pipe - 350 mm 1.00000 m

Providing and Laying Ductile Iron K - 7 pipes -250 mm

Providing and Laying Ductile Iron K - 7 pipes -300 mm

Providing and Laying Ductile Iron K - 7 pipes -350 mm

Providing and Laying Ductile Iron K - 9 pipes - 50 0 mm

Providing and Laying Ductile Iron K - 9 pipes - 60 0 mm

Providing and Laying Ductile Iron K - 7 pipes -100 mm

Providing and Laying Ductile Iron K - 7 pipes -150 mm

Providing and Laying Ductile Iron K - 7 pipes -200 mm

Providing and Laying Ductile Iron K - 9 pipes - 40 0 mm

Providing and Laying Ductile Iron K - 9 pipes - 45 0 mm

Department of Engineering Services, MoWHS

Page 151: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 148

PO0084Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.11360 dayLB0077 Labour 0.20450 dayMT0877 DI pipe - 400 mm 1.00000 m

PO0085Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.13636 dayLB0077 Labour 0.23860 dayMT0878 DI pipe - 450 mm 1.00000 m

PO0086Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.16346 dayLB0077 Labour 0.27272 dayMT0879 DI pipe - 500 mm 1.00000 m

PO0087Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.19318 dayLB0077 Labour 0.38600 dayMT0880 DI pipe - 600 mm 1.00000 m

PO0090

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.03410 dayLB0077 Labour 0.07286 dayMT0882 DI pipe - 100 mm 1.00000 m

PO0091

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.05237 dayLB0077 Labour 0.09563 dayMT0883 DI pipe - 150 mm 1.00000 m

PO0092

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.06489 dayLB0077 Labour 0.12980 dayMT0884 DI pipe - 200 mm 1.00000 m

PO0093

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.08424 dayLB0077 Labour 0.17076 dayMT0885 DI pipe - 250 mm 1.00000 m

PO0094

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.11156 dayLB0077 Labour 0.21860 dayMT0886 DI pipe - 300 mm 1.00000 m

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes -300mm

Providing and Laying Ductile Iron K - 7 pipes -500 mm

Providing and Laying Ductile Iron K - 7 pipes -600 mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes -100mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes -150mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes -200mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes -250mm

Providing and Laying Ductile Iron K - 7 pipes -400 mm

Providing and Laying Ductile Iron K - 7 pipes -450 mm

Department of Engineering Services, MoWHS

Page 152: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 149

PO0095

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.15030 dayLB0077 Labour 0.26640 dayMT0887 DI pipe - 350 mm 1.00000 m

PO0096

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.17530 dayLB0077 Labour 0.33700 dayMT0888 DI pipe - 400 mm 1.00000 m

PO0097

Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.23910 dayLB0077 Labour 0.47810 dayMT0889 DI pipe - 450 mm 1.00000 m

PO0098Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.32560 dayLB0077 Labour 0.64210 dayMT0890 DI pipe - 500 mm 1.00000 m

PO0099Coefficient for per m

Code Description Quant UnitsLB0038 Plumber Gd.1 0.42120 dayLB0077 Labour 1.00870 dayMT0891 DI pipe - 600 mm 1.00000 m

PO0100

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0930 Stopcock - 15mm nom-bore 1.00000 each PO0101

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0931 Stopcock - 20mm nom-bore 1.00000 each PO0102

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0932 Stopcock - 25mm nom-bore 1.00000 each PO0105

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0940 Wheel valve - 32mm nom-bore 1.00000 each PO0106

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0941 Wheel valve - 40mm nom-bore 1.00000 each

Providing & fixing brass stop cock - 15mm

Providing & fixing brass stop cock - 20mm

Providing & fixing brass stop cock - 25mm

Providing & fixing brass full way valve with wheel - 32mm

Providing & fixing brass full way valve with wheel - 40mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes -350mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes - 400mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes - 450mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes -500mm

Providing and Laying Double Flanged(Screwed or Weld ed) Ductile Iron K-9 Pipes -600mm

Department of Engineering Services, MoWHS

Page 153: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 150

PO0107

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0942 Wheel valve - 50mm nom-bore 1.00000 each PO0108

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0943 Wheel valve - 65mm nom-bore 1.00000 each PO0109

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0944 Wheel valve - 80mm nom-bore 1.00000 each PO0110

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0950 Non return valve - 50mm nom-bore 1.00000 each PO0111

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0951 Non return valve - 65mm nom-bore 1.00000 each PO0112

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0952 Non return valve - 80mm nom-bore 1.00000 each PO0114

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0925 Brass Fittings Bibcock - 15mm 1.00000 each PO0115

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0895 H.D.P.E welded-type fittings - TEE, 20mm 1.00000 each PO0116

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0896 H.D.P.E welded-type fittings - TEE, 25mm 1.00000 each PO0117

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0897 H.D.P.E welded-type fittings - TEE, 32mm 1.00000 each PO0118

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0898 H.D.P.E welded-type fittings - TEE, 50mm 1.00000 each

Providing & fixing H.D.P.E, Equal Tee butt-welded-t ype fittings - 20mm

Providing & fixing H.D.P.E, Equal Tee butt-welded-t ype fittings - 25mm

Providing & fixing H.D.P.E, Equal Tee butt-welded-t ype fittings - 32mm

Providing & fixing H.D.P.E, Equal Tee butt-welded-t ype fittings - 50mm

Providing & fixing brass full way valve with wheel - 65mm

Providing & fixing brass full way valve with wheel - 80mm

Providing & fixing non-return valve - 50mm

Providing & fixing non-return valve - 65mm

Providing & fixing non-return valve - 80mm

Providing & fixing brass bibcock - 15mm, brass

Providing & fixing brass full way valve with wheel - 50mm

Department of Engineering Services, MoWHS

Page 154: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 151

PO0119

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0899 H.D.P.E welded-type fittings - TEE, 63mm 1.00000 each PO0120

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0900 H.D.P.E welded-type fittings - TEE, 90mm 1.00000 each PO0121

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0901 H.D.P.E welded-type fittings - TEE, 110mm 1.00000 each PO0122

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0902 H.D.P.E welded-type fittings - TEE, 160mm 1.00000 each PO0125

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0903 H.D.P.E welded-type fittings - Elbow, 32mm 1.00000 each PO0126

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0904 H.D.P.E welded-type fittings - Elbow, 50mm 1.00000 each PO0127

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0905 H.D.P.E welded-type fittings - Elbow, 63mm 1.00000 each PO0128

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0906 H.D.P.E welded-type fittings - Elbow, 90mm 1.00000 each PO0129

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0907 H.D.P.E welded-type fittings - Elbow, 110mm 1.00000 each PO0130

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0908 H.D.P.E welded-type fittings - Reducer, 90 x 50mm 1.00000 each PO0131

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0909 H.D.P.E welded-type fittings - Reducer, 90 x 63mm 1.00000 each

Providing & fixing H.D.P.E Elbow - 110mm

Providing & fixing H.D.P.E Reducer - 90 x 50mm

Providing & fixing H.D.P.E Reducer - 90 x 63mm

Providing & fixing H.D.P.E, Equal Tee butt-welded-t ype fittings - 110mm

Providing & fixing H.D.P.E, Equal Tee butt-welded-t ype fittings - 160mm

Providing & fixing H.D.P.E Elbow - 32mm

Providing & fixing H.D.P.E Elbow - 50mm

Providing & fixing H.D.P.E Elbow - 63mm

Providing & fixing H.D.P.E Elbow - 90mm

Providing & fixing H.D.P.E, Equal Tee butt-welded-t ype fittings - 63mm

Providing & fixing H.D.P.E, Equal Tee butt-welded-t ype fittings - 90mm

Department of Engineering Services, MoWHS

Page 155: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 152

PO0132

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0910 H.D.P.E welded-type fittings - Reducer, 110 x 63mm 1.00000 each PO0133

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0911 H.D.P.E welded-type fittings - Reducer, 160 x 90mm 1.00000 each PO0140

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0912 H.D.P.E welded-type fittings - Blank end, 50mm 1.00000 each PO0141

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0913 H.D.P.E welded-type fittings - Blank end, 63mm 1.00000 each PO0142

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0914 H.D.P.E welded-type fittings - Blank end, 90mm 1.00000 each PO0143

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0915 H.D.P.E welded-type fittings - Blank end, 110mm 1.00000 each PO0144

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0916 H.D.P.E welded-type fittings - Blank end, 160mm 1.00000 each

PO0150

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.01600 dayLB0077 Labour 0.03000 dayMT0960 Rubber Gasket - 80 mm 1.00000 each

PO0151

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.02200 dayLB0077 Labour 0.04000 dayMT0961 Rubber Gasket - 100 mm 1.00000 each

PO0152

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.04300 dayLB0077 Labour 0.08000 dayMT0962 Rubber Gasket - 150 mm 1.00000 each

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 150 mm

Providing & fixing H.D.P.E Blank End (Cap) - 63mm

Providing & fixing H.D.P.E Blank End (Cap) - 90mm

Providing & fixing H.D.P.E Blank End (Cap) - 110mm

Providing & fixing H.D.P.E Blank End (Cap) - 160mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 80 mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 100 mm

Providing & fixing H.D.P.E Reducer - 110 x 63mm

Providing & fixing H.D.P.E Reducer - 110 x 90mm

Providing & fixing H.D.P.E Blank End (Cap) - 50mm

Department of Engineering Services, MoWHS

Page 156: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 153

PO0153

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.05900 dayLB0077 Labour 0.11000 dayMT0963 Rubber Gasket - 200 mm 1.00000 each

PO0154

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.07500 dayLB0077 Labour 0.14000 dayMT0964 Rubber Gasket - 250 mm 1.00000 each

PO0155

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.08600 dayLB0077 Labour 0.16000 dayMT0965 Rubber Gasket - 300 mm 1.00000 each

PO0156

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.09000 dayLB0077 Labour 0.16000 dayMT0966 Rubber Gasket - 350 mm 1.00000 each

PO0157

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.13000 dayLB0077 Labour 0.23000 dayMT0967 Rubber Gasket - 400 mm 1.00000 each

PO0158

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.15000 dayLB0077 Labour 0.25000 dayMT0968 Rubber Gasket - 450 mm 1.00000 each

PO0159

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.16500 dayLB0077 Labour 0.26000 dayMT0969 Rubber Gasket - 500 mm 1.00000 each

PO0160

Coefficient for per each

Code Description Quant UnitsLB0038 Plumber Gd.1 0.23000 dayLB0077 Labour 0.36000 dayMT0970 Rubber Gasket - 600 mm 1.00000 each

PO0162

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.05000 day LB0054 Plumber Gd.2 0.06250 day LB0077 Labour 0.06250 day MT1145 Pig lead 0.77000 kg

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 350 mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 400 mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 450 mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 500 mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 200 mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 250 mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 300 mm

Providing push-on joints to Centrifugally Spun D.I pipes including the cost of rubber gaskets - 600 mm

Providing lead-caulked joints to C.I pipes and fitt ings - 50mm dia pipe

Department of Engineering Services, MoWHS

Page 157: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 154

PO0163

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.06250 day LB0054 Plumber Gd.2 0.06250 day LB0077 Labour 0.11200 day MT1145 Pig lead 0.88000 kg PO0164

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.07500 day LB0054 Plumber Gd.2 0.07500 day LB0077 Labour 0.15000 day MT1145 Pig lead 0.98000 kg PO0165 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.09000 day LB0054 Plumber Gd.2 0.09000 day LB0077 Labour 0.18000 day MT1145 Pig lead 1.76000 kg PO0166 Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02100 day LB0054 Plumber Gd.2 0.01000 day LB0077 Labour 0.04200 day MT0975 Cast Iron Pipes, Single Socketted, 1.83m long - 50mm 0.58000 each PO0167 Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02600 day LB0054 Plumber Gd.2 0.13000 day LB0077 Labour 0.05200 day MT0976 Cast Iron Pipes, Single Socketted, 1.83m long - 75mm 0.58000 each PO0168

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03100 day LB0054 Plumber Gd.2 0.01600 day LB0077 Labour 0.06200 day MT0977 Cast Iron Pipes, Single Socketted, 1.83m long - 100mm 0.58000 each PO0169

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.04100 day LB0054 Plumber Gd.2 0.02200 day LB0077 Labour 0.08200 day MT0978 Cast Iron Pipes, Single Socketted, 1.83m long - 150mm 0.58000 each PO0170

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0990 Door bend - 50mm 1.00000 each PO0171

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0991 Door bend - 75mm 1.00000 each

Providing & fixing C.I Soil Waste and Vent pipes - 150mm dia

Providing & fixing C.I door bend including fittings - 50mm dia

Providing & fixing C.I door bend including fittings - 75mm dia

Providing & fixing C.I Soil Waste and Vent pipes - 50mm dia

Providing & fixing C.I Soil Waste and Vent pipes - 75mm dia

Providing & fixing C.I Soil Waste and Vent pipes - 100mm dia

Providing lead-caulked joints to C.I pipes and fitt ings - 75mm dia pipe

Providing lead-caulked joints to C.I pipes and fitt ings - 100mm dia pipe

Providing lead-caulked joints to C.I pipes and fitt ings - 150mm dia pipe

Department of Engineering Services, MoWHS

Page 158: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 155

PO0172

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0992 Door bend - 100mm 1.00000 each PO0180 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0985 Plain bend - 50mm 1.00000 each PO0181 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0986 Plain bend - 75mm 1.00000 each PO0182 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT0987 Plain bend - 100mm 1.00000 each PO0190 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1010 Heel rest bend - 50mm 1.00000 each PO0191 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1011 Heel rest bend - 75mm 1.00000 each PO0192 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1012 Heel rest bend - 100mm 1.00000 each PO0200

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1052 Double equal junction, door - 100mm 1.00000 each PO0201

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1051 Double equal junction, door - 75mm 1.00000 each PO0202

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1050 Double equal junction, door - 50mm 1.00000 each PO0210

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1042 Double equal junction, plain - 100mm 1.00000 each

Providing & fixing C.I double equal door junction i ncluding fittings - 75mm

Providing & fixing C.I double equal door junction i ncluding fittings - 50mm

Providing & fixing C.I double equal plain junction including fittings - 100mm

Providing & fixing C.I double equal door junction i ncluding fittings - 100mm

Providing & fixing C.I door bend including fittings - 100mm dia

Providing & fixing C.I plain bend including fitting s - 50mm dia

Providing & fixing C.I plain bend including fitting s - 75mm dia

Providing & fixing C.I plain bend including fitting s - 100mm dia

Providing & fixing C.I heel rest bend - 50mm

Providing & fixing C.I heel rest bend - 75mm

Providing & fixing C.I heel rest bend - 100mm

Department of Engineering Services, MoWHS

Page 159: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 156

PO0211

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1041 Double equal junction, plain - 75mm 1.00000 each PO0212

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1040 Double equal junction, plain - 50mm 1.00000 each PO0220

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1033 Single equal junction, door - 150mm 1.00000 each PO0221

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1032 Single equal junction, door - 100mm 1.00000 each PO0222

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1031 Single equal junction, door - 75mm 1.00000 each PO0223 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1030 Single equal junction, door - 50mm 1.00000 each PO0230

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1022 Single equal junction - plain - 100mm 1.00000 each PO0231

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1021 Single equal junction - plain - 75mm 1.00000 each PO0232

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1020 Single equal junction - plain - 50mm 1.00000 each PO0240

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1086 Double unequal junction, door - 100 x 75 1.00000 each PO0241

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1085 Double unequal junction, door - 100 x 50 1.00000 each

Providing & fixing C.I double unequal door junction including fittings - 100x75mm

Providing & fixing C.I double unequal door junction including fittings - 100x50mm

Providing & fixing C.I single equal plain junction including fittings - 75mm

Providing & fixing C.I single equal plain junction including fittings - 50mm

Providing & fixing C.I double equal plain junction including fittings - 75mm

Providing & fixing C.I double equal plain junction including fittings - 50mm

Providing & fixing C.I single equal door junction i ncluding fittings - 150mm

Providing & fixing C.I single equal door junction i ncluding fittings - 100mm

Providing & fixing C.I single equal door junction i ncluding fittings - 75mm

Providing & fixing C.I single equal door junction i ncluding fittings - 50mm

Providing & fixing C.I single equal plain junction including fittings - 100mm

Department of Engineering Services, MoWHS

Page 160: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 157

PO0250

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1081 Double unequal junction, plain - 100 x 75 1.00000 each PO0251

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1080 Double unequal junction, plain - 100 x 50 1.00000 each PO0260

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1072 Single unequal junction, door - 100 x 75mm 1.00000 each PO0261

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1071 Single unequal junction, door - 100 x 50mm 1.00000 each PO0262

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1070 Single unequal junction, door - 75 x 50mm 1.00000 each PO0270

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1062 Single unequal junction, plain - 100 x 75mm 1.00000 each PO0271

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1061 Single unequal junction, plain - 100 x 50mm 1.00000 each PO0272

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1060 Single unequal junction, plain - 75 x 50mm 1.00000 each PO0280

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1102 Double equal Y-Junction - 100mm 1.00000 each PO0281

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1101 Double equal Y-Junction - 75mm 1.00000 each PO0282

Coefficient for per each Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1100 Double equal Y-Junction - 50mm 1.00000 each

Providing & fixing C.I double equal Y-Junction - 10 0mm

Providing & fixing C.I double equal Y-Junction - 75 mm

Providing & fixing C.I double equal Y-Junction - 50 mm

Providing & fixing C.I double unequal plain junctio n - 100x75mm

Providing & fixing C.I double unequal plain junctio n - 100x50mm

Providing & fixing C.I single unequal door junction - 100x75mm

Providing & fixing C.I single unequal door junction - 100x50mm

Providing & fixing C.I single unequal door junction - 75x50mm

Providing & fixing C.I single unequal plain junctio n - 100x75mm

Providing & fixing C.I single unequal plain junctio n - 100x50mm

Providing & fixing C.I single unequal plain junctio n - 75x50mm

Department of Engineering Services, MoWHS

Page 161: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 158

PO0290

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1092 Single equal Y-Junction - 100mm 1.00000 each PO0291

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1091 Single equal Y-Junction - 75mm 1.00000 each PO0292

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1090 Single equal Y-Junction - 50mm 1.00000 each PO0300

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1111 Single unequal invert branch - 100 x 50mm 1.00000 each PO0301

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1110 Single unequal invert branch - 75 x 50mm 1.00000 each PO0310

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1120 100mm dia offset - with 75mm projection 1.00000 each PO0311

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1126 100mm dia offset - with 150mm projection 1.00000 each PO0320

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1120 75mm dia offset - with 75mm projection 1.00000 each PO0321

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1121 75mm dia offset - with 150mm projection 1.00000 each PO0330

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1115 Offsets 50mm dia offset - with 75mm projection 1.00000 each PO0331

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1116 Offsets 50mm dia offset - with 150mm projection 1.00000 each

Providing & fixing C.I single equal Y-Junction - 10 0mm

Providing & fixing C.I single equal Y-Junction - 75 mm

Providing & fixing C.I single equal Y-Junction - 50 mm

Providing & fixing S.C.I offsets - 50 mm offset - 7 5mm projection

Providing & fixing S.C.I offsets - 50 mm offset - 1 50mm projection

Providing & fixing S.C.I offsets - 100mm Offsets - 75mm projection

Providing & fixing S.C.I offsets - 100mm Offsets - 150mm projection

Providing & fixing S.C.I offsets - 75mm offset - 7 5mm projection

Providing & fixing S.C.I offsets - 75mm offset - 1 50mm projection

Providing & fixing single unequal plain in vertical branch - 100x50mm

Providing & fixing single unequal plain in vertical branch - 75x50mm

Department of Engineering Services, MoWHS

Page 162: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 159

PO0340

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1133 Terminal Guard - 150mm 1.00000 each PO0341

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1132 Terminal Guard - 100mm 1.00000 each PO0342

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1131 Terminal Guard - 75mm 1.00000 each PO0343

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1130 Terminal Guard - 50mm 1.00000 each PO0350

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1002 Collar - 100mm 1.00000 each PO0351

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1001 Collar - 75mm 1.00000 each PO0352

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1000 Collar - 50mm 1.00000 each PO0360

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.30000 day LB0038 Plumber Gd.1 0.30000 day MT1141 P-type Nahani Trap - 100mm inlet & 75mm outlet 1.00000 each PO0361 Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.30000 day LB0038 Plumber Gd.1 0.30000 day MT1140 P-type Nahani Trap - 100mm inlet & 50mm outlet 1.00000 each PO0370

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02100 day LB0054 Plumber Gd.2 0.01000 day LB0077 Labour 0.04200 day MT1150 Pipes, Single Socketed 1.83 m long - 75mm 0.56000 each

Providing & fixing C.I terminal guard - 150mm

Providing & fixing C.I terminal guard - 100mm

Providing & fixing C.I terminal guard - 75mm

Providing & fixing C.I terminal guard - 50mm

Providing & fixing C.I collar - 75mm

Providing & fixing C.I collar - 50mm

Providing & fixing C.I P-Type Nahani trap - 100mm i nlet & 75mm outlet

Providing & fixing C.I P-Type Nahani trap - 100mm i nlet & 50mm outlet

Providing & fixing P.V.C soil waste and vent pipes, single or double socketed, including pipe clip com plete (excluding the cost of PVC fittings) - 75mm dia

Providing & fixing C.I collar - 100mm

Department of Engineering Services, MoWHS

Page 163: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 160

PO0371

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.02600 day LB0054 Plumber Gd.2 0.01300 day LB0077 Labour 0.05200 day MT1151 Pipes, Single Socketed 1.83 m long - 90mm 0.56000 each PO0372

Coefficient for per m

Code Description Quant Units LB0038 Plumber Gd.1 0.03100 day LB0054 Plumber Gd.2 0.01600 day LB0077 Labour 0.06200 day MT1152 Pipes, Single Socketed 1.83 m long - 110mm 0.56000 each PO0380 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1190 Pipe Connector - 110mm 1.00000 each PO0385 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1205 Coupler - 75mm 1.00000 each PO0386 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1206 Coupler - 90mm 1.00000 each PO0387 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1207 Coupler - 110mm 1.00000 each PO0395 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1195 Reducer - 90x75mm 1.00000 each PO0396 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1196 Reducer - 110x75mm 1.00000 each PO0397 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1197 Reducer - 110x90mm 1.00000 each PO0405 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1215 Plain bend - 75mm 1.00000 each

Providing & fixing P.V.C Reducer - 110x75mm

Providing & fixing P.V.C Reducer - 110x90mm

Providing & fixing P.V.C plain bend - 75mm dia

Providing & fixing P.V.C soil waste and vent pipes, single or double socketed, including pipe clip com plete (excluding the cost of PVC fittings) - 110mm dia

Providing & fixing P.V.C Pipe connector - 110mm dia

Providing & fixing P.V.C Coupler - 75mm dia

Providing & fixing P.V.C Coupler - 90mm dia

Providing & fixing P.V.C Coupler - 110mm dia

Providing & fixing P.V.C Reducer - 90x75mm

Providing & fixing P.V.C soil waste and vent pipes, single or double socketed, including pipe clip com plete (excluding the cost of PVC fittings) - 90mm dia

Department of Engineering Services, MoWHS

Page 164: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 161

PO0406 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1216 Plain bend - 90mm 1.00000 each PO0407 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1217 Plain bend - 110mm 1.00000 each PO0415 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1225 Door bend - 75mm 1.00000 each PO0416 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1226 Door bend - 90mm 1.00000 each PO0417 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1227 Door bend - 110mm 1.00000 each PO0425 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1235 Long Arm Bend - 75mm 1.00000 each PO0426 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1236 Long Arm Bend - 90mm 1.00000 each PO0427 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1237 Long Arm Bend - 110mm 1.00000 each PO0435 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1245 Single Tee, Plain - 75mm 1.00000 each PO0436 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1246 Single Tee, Plain - 90mm 1.00000 each PO0437 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1247 Single Tee, Plain - 110mm 1.00000 each

Providing & fixing P.V.C Single Tee plain - 90mm di a

Providing & fixing P.V.C Single Tee plain - 110mm d ia

Providing & fixing P.V.C door bend - 90mm dia

Providing & fixing P.V.C door bend - 110mm dia

Providing & fixing P.V.C Long arm bend with door - 75mm dia

Providing & fixing P.V.C Long arm bend with door - 90mm dia

Providing & fixing P.V.C Long arm bend with door - 110mm dia

Providing & fixing P.V.C Single Tee plain - 75mm di a

Providing & fixing P.V.C plain bend - 90mm dia

Providing & fixing P.V.C plain bend - 110mm dia

Providing & fixing P.V.C door bend - 75mm dia

Department of Engineering Services, MoWHS

Page 165: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 162

PO0445 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1255 Single Tee, With Door - 75mm 1.00000 each PO0446 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1256 Single Tee, With Door - 90mm 1.00000 each PO0447 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1257 Single Tee, With Door - 110mm 1.00000 each PO0455 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1265 Double Tee, Plain - 75mm 1.00000 each PO0456 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1266 Double Tee, Plain - 90mm 1.00000 each PO0457 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1267 Double Tee, Plain - 110mm 1.00000 each PO0465 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1275 Double Tee, With Door - 75mm 1.00000 each PO0466 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1276 Double Tee, With Door - 90mm 1.00000 each PO0467 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1277 Double Tee, With Door - 110mm 1.00000 each PO0475 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1285 Single Y, Plain - 75mm 1.00000 each PO0476 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1286 Single Y, Plain - 90mm 1.00000 each

Providing & fixing P.V.C Single Y, plain - 90mm dia

Providing & fixing P.V.C Double Tee plain - 90mm di a

Providing & fixing P.V.C Double Tee plain - 110mm d ia

Providing & fixing P.V.C Double Tee with door - 75m m dia

Providing & fixing P.V.C Double Tee with door - 90m m dia

Providing & fixing P.V.C Double Tee with door - 110 mm dia

Providing & fixing P.V.C Single Y, plain - 75mm dia

Providing & fixing P.V.C Single Tee with door - 75m m dia

Providing & fixing P.V.C Single Tee with door - 90m m dia

Providing & fixing P.V.C Single Tee with door - 110 mm dia

Providing & fixing P.V.C Double Tee plain - 75mm di a

Department of Engineering Services, MoWHS

Page 166: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 163

PO0477 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1287 Single Y, Plain - 110mm 1.00000 each PO0485 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1295 Single Y, With Door - 75mm 1.00000 each PO0486 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1296 Single Y, With Door - 90mm 1.00000 each PO0487 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1297 Single Y, With Door - 110mm 1.00000 each PO0495 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1305 Double Y, Plain - 75mm 1.00000 each PO0496 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1306 Double Y, Plain - 90mm 1.00000 each PO0497

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1307 Double Y, Plain - 110mm 1.00000 each PO0505 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1315 Double Y, With Door - 75mm 1.00000 each PO0506 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1316 Double Y, With Door - 90mm 1.00000 each PO0507 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1317 Double Y, With Door - 110mm 1.00000 each PO0515 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1325 75mm dia. offset - With 75mm projection 1.00000 each

Providing & fixing P.V.C Double Y, plain - 90mm dia

Providing & fixing P.V.C Double Y, plain - 110mm di a

Providing & fixing P.V.C Double Y, with door - 75mm dia

Providing & fixing P.V.C Double Y, with door - 90mm dia

Providing & fixing P.V.C Double Y, with door - 110m m dia

Providing & fixing P.V.C Offset, 75mm dia - With 75 mm projection

Providing & fixing P.V.C Single Y, plain - 110mm di a

Providing & fixing P.V.C Single Y, with door - 75mm dia

Providing & fixing P.V.C Single Y, with door - 90mm dia

Providing & fixing P.V.C Single Y, with door - 110m m dia

Providing & fixing P.V.C Double Y, plain - 75mm dia

Department of Engineering Services, MoWHS

Page 167: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 164

PO0516 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1326 75mm dia. offset - With 150mm projection 1.00000 each PO0525 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1330 90mm dia. offset - With 75mm projection 1.00000 each PO0526 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1331 90mm dia. offset - With 150mm projection 1.00000 each PO0535 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1335 110mm dia. offset - With 75mm projection 1.00000 each PO0536 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1336 110mm dia. offset - With 150mm projection 1.00000 each PO0545 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1340 Terminal Guard - 75mm 1.00000 each PO0546 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1341 Terminal Guard - 90mm 1.00000 each PO0547 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1342 Terminal Guard - 110mm 1.00000 each PO0555

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1350 P-Trap without air vent - Big 1.00000 each PO0556 Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1351 P-Trap without air vent - Small 1.00000 each PO0565

Coefficient for per each

Code Description Quant Units LB0038 Plumber Gd.1 0.02000 day MT1345 Nahani Trap - 100mm inlet & 75mm outlet 1.00000 each

Providing & fixing P.V.C Terminal guard - 90mm dia

Providing & fixing P.V.C Terminal guard - 110mm dia

Providing & fixing P.V.C P-Trap, without air vent - Big

Providing & fixing P.V.C P-Trap, without air vent - Small

Providing & fixing P.V.C Nahani Trap - 110mm inlet & 75mm outlet

Providing & fixing P.V.C Offset, 75mm dia - With 15 0mm projection

Providing & fixing P.V.C Offset, 90mm dia - With 75 mm projection

Providing & fixing P.V.C Offset, 90mm dia - With 15 0mm projection

Providing & fixing P.V.C Offset, 110mm dia - With 7 5mm projection

Providing & fixing P.V.C Offset, 110mm dia - With 1 50mm projection

Providing & fixing P.V.C Terminal guard - 75mm dia

Department of Engineering Services, MoWHS

Page 168: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 165

PO0570

Coefficient for per m

Code Description Quant Units LB0052 Painter Gd.1 0.00141 day LB0067 Painter Gd.2 0.00317 day LB0077 Labour 0.00458 day MT0712 Red oxide primer, for metals 0.00254 litre MT0723 High gloss synthetic enamel 0.00564 litre PO0571

Coefficient for per m

Code Description Quant Units LB0052 Painter Gd.1 0.00189 day LB0067 Painter Gd.2 0.00425 day LB0077 Labour 0.00614 day MT0712 Red oxide primer, for metals 0.00340 litre MT0723 High gloss synthetic enamel 0.00756 litre PO0572 Coefficient for per m

Code Description Quant Units LB0052 Painter Gd.1 0.00234 day LB0067 Painter Gd.2 0.00527 day LB0077 Labour 0.00761 day MT0712 Red oxide primer, for metals 0.00421 litre MT0723 High gloss synthetic enamel 0.00936 litre PO0573 Coefficient for per m

Code Description Quant Units LB0052 Painter Gd.1 0.00300 day LB0067 Painter Gd.2 0.00675 day LB0077 Labour 0.00975 day MT0712 Red oxide primer, for metals 0.00540 litre MT0723 High gloss synthetic enamel 0.01200 litre PO0580

Coefficient for per m

Code Description Quant Units LB0052 Painter Gd.1 0.00480 day LB0067 Painter Gd.2 0.01080 day LB0077 Labour 0.01560 day MT0711 Synthetic red lead primer 0.00864 litre MT0723 High gloss synthetic enamel 0.01920 litre PO0581

Coefficient for per m

Code Description Quant Units LB0052 Painter Gd.1 0.02352 day LB0077 Labour 0.02352 day MT0711 Synthetic red lead primer 0.01296 litre MT0726 Black\White bitumen enamel 0.02280 litre PO0582

Coefficient for per m

Code Description Quant Units LB0052 Painter Gd.1 0.00960 day LB0067 Painter Gd.2 0.02160 day LB0077 Labour 0.03120 day MT0711 Synthetic red lead primer 0.01728 litre MT0723 High gloss synthetic enamel 0.03840 litre PO0590

Coefficient for per m Code Description Quant Units LB0067 Painter Gd.2 0.00720 day LB0077 Labour 0.00720 day MT0723 High gloss synthetic enamel 0.01280 litre

Repainting C.I spun soil waste vent pipes & fitting s including paints of any colour - 50mm

Painting G.I pipes and fittings including primer & white coat, for new work - 20mm dia pipe

Painting G.I pipes and fittings including primer & white coat, for new work - 25mm dia pipe

Painting G.I pipes and fittings including primer & white coat, for new work - 32mm dia pipe

Painting C.I spun soil waste vent pipes & fittings including primer, top coat (any colour), for new wo rk - 50mm

Painting C.I spun soil waste vent pipes & fittings including primer, top coat (any colour), for new wo rk - 75mm

Painting C.I spun soil waste vent pipes & fittings including primer, top coat (any colour), for new wo rk - 100mm

Painting G.I pipes and fittings including primer & white coat, for new work - 15mm dia pipe

Department of Engineering Services, MoWHS

Page 169: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 166

PO0591 Coefficient for per m

Code Description Quant Units LB0067 Painter Gd.2 0.01080 day LB0077 Labour 0.01080 day MT0723 High gloss synthetic enamel 0.01920 litre PO0592 Coefficient for per m

Code Description Quant Units LB0067 Painter Gd.2 0.01440 day LB0077 Labour 0.01440 day MT0723 High gloss synthetic enamel 0.02560 litre PO0600

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.07800 day LB0051 Mason Gd.2 0.07800 day LB0077 Labour 1.58622 day MT0125 Bricks 2nd class 0.06000 1000# MT0126 Brick aggregate 1.73000 cu.m MT0795 Stoneware pipes 60 cm long - 100mm dia 2.00000 each PO0601

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.02000 day LB0033 Carpenter Gd.2 0.03744 day LB0036 Mason Gd.1 0.63995 day LB0039 Work Supervisor (Lajab) 0.00100 day LB0051 Mason Gd.2 0.63995 day LB0053 Plant Operator Gd.3 0.00140 day LB0077 Labour 15.65825 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00140 day MP0206 Concrete Vibrator(M/C5) 0.00140 day MT0043 Sand 0.01143 cu.m MT0070 Crushed Rock - 20mm 0.01780 cu.m MT0125 Bricks 2nd class 0.23600 1000# MT0126 Brick aggregate 13.78000 cu.m MT0145 Cement (OPC / PSC) 0.00763 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 1.68000 kg MT0325 Ballies 75 to 125mm dia 0.10080 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00324 cu.m MT0795 Stoneware pipes 60 cm long - 100mm dia 3.00000 each

Repainting C.I spun soil waste vent pipes & fitting s including paints of any colour - 75mm

Repainting C.I spun soil waste vent pipes & fitting s including paints of any colour - 100mm

Constructing Soak Pit - Size 1200x1200x1200mm, fill ed with brick bats including 100mm S. W drain-pipe x 1200mm long

Constructing Soak Pit - Size 2500 dia. x 3000mm dep th including 450x450mm dry brick honeycomb shaft an d 100mm S.W drain x 1800mm long

Department of Engineering Services, MoWHS

Page 170: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 167

PO0610

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.16250 day LB0033 Carpenter Gd.2 0.69264 day LB0036 Mason Gd.1 1.89631 day LB0038 Plumber Gd.1 0.10473 day LB0039 Work Supervisor (Lajab) 0.08600 day LB0051 Mason Gd.2 5.26711 day LB0053 Plant Operator Gd.3 0.12040 day LB0054 Plumber Gd.2 0.02130 day LB0077 Labour 24.18409 day MP0205 Concrete Mixer(7/5 cu.ft) 0.12040 day MP0206 Concrete Vibrator(M/C5) 0.12040 day MT0043 Sand 2.28400 cu.m MT0060 Boulder 3.43000 cu.m MT0068 Crushed Rock - 40mm 1.20150 cu.m MT0070 Crushed Rock - 20mm 0.36953 cu.m MT0145 Cement (OPC / PSC) 0.76793 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 13.65000 kg MT0325 Ballies 75 to 125mm dia 1.86480 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.05994 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each MT0795 Stoneware pipes 60 cm long - 100mm dia 5.01000 each MT0975 Cast Iron Pipes, Single Socketted, 1.83m long - 50mm 1.23540 each MT1031 Single equal junction, door - 100mm 2.00000 each MT1130 Terminal Guard - 50mm 1.00000 each PO0611

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.20000 day LB0033 Carpenter Gd.2 0.82368 day LB0036 Mason Gd.1 2.47511 day LB0038 Plumber Gd.1 0.11538 day LB0039 Work Supervisor (Lajab) 0.09900 day LB0051 Mason Gd.2 7.01278 day LB0053 Plant Operator Gd.3 0.13860 day LB0054 Plumber Gd.2 0.27690 day LB0077 Labour 31.05563 day MP0205 Concrete Mixer(7/5 cu.ft) 0.13860 day MP0206 Concrete Vibrator(M/C5) 0.13860 day MT0043 Sand 2.92144 cu.m MT0060 Boulder 4.64000 cu.m MT0068 Crushed Rock - 40mm 1.37060 cu.m MT0070 Crushed Rock - 20mm 0.44500 cu.m MT0145 Cement (OPC / PSC) 0.96554 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 16.80000 kg MT0325 Ballies 75 to 125mm dia 2.21760 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.07128 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0795 Stoneware pipes 60 cm long - 100mm dia 5.01000 each MT0976 Cast Iron Pipes, Single Socketted, 1.83m long - 75mm 1.23540 each MT1031 Single equal junction, door - 100mm 2.00000 each MT1131 Terminal Guard - 75mm 1.00000 each

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:6, including fittings, C.I cover with fra me, 40mm thick concrete flooring (40mm aggregates) cement plaster concrete base in C.M 1:4:8 etc. complete as per sta ndard design - 25 users

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:6, including fittings, C.I cover with fra me, 40mm thick concrete flooring (40mm aggregates) cement plaster concrete base in C.M 1:4:8 etc. complete as per sta ndard design - 15 users

Department of Engineering Services, MoWHS

Page 171: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 168

PO0612

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.27500 day LB0033 Carpenter Gd.2 1.14192 day LB0036 Mason Gd.1 3.66114 day LB0038 Plumber Gd.1 0.12603 day LB0039 Work Supervisor (Lajab) 0.15900 day LB0051 Mason Gd.2 10.39309 day LB0053 Plant Operator Gd.3 0.22260 day LB0054 Plumber Gd.2 0.03408 day LB0077 Labour 46.44651 day MP0205 Concrete Mixer(7/5 cu.ft) 0.22260 day MP0206 Concrete Vibrator(M/C5) 0.22260 day MT0043 Sand 4.43757 cu.m MT0060 Boulder 6.85000 cu.m MT0068 Crushed Rock - 40mm 2.28730 cu.m MT0070 Crushed Rock - 20mm 0.63190 cu.m MT0145 Cement (OPC / PSC) 1.46627 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 23.10000 kg MT0325 Ballies 75 to 125mm dia 3.07440 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.09882 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each MT0796 Stoneware pipes 60 cm long - 150mm dia 5.01000 each MT0977 Cast Iron Pipes, Single Socketted, 1.83m long - 100mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1132 Terminal Guard - 100mm 1.00000 each PO0613

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.31250 day LB0033 Carpenter Gd.2 1.32912 day LB0036 Mason Gd.1 4.65440 day LB0038 Plumber Gd.1 0.12603 day LB0039 Work Supervisor (Lajab) 0.14850 day LB0051 Mason Gd.2 13.19085 day LB0053 Plant Operator Gd.3 0.20790 day LB0054 Plumber Gd.2 0.03408 day LB0077 Labour 57.10320 day MP0205 Concrete Mixer(7/5 cu.ft) 0.20790 day MP0206 Concrete Vibrator(M/C5) 0.20790 day MT0043 Sand 5.18914 cu.m MT0060 Boulder 8.81000 cu.m MT0068 Crushed Rock - 40mm 2.01140 cu.m MT0070 Crushed Rock - 20mm 0.74618 cu.m MT0145 Cement (OPC / PSC) 1.68463 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 26.25000 kg MT0325 Ballies 75 to 125mm dia 3.57840 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.11502 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each MT0796 Stoneware pipes 60 cm long - 150mm dia 5.01000 each MT0977 Cast Iron Pipes, Single Socketted, 1.83m long - 100mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1132 Terminal Guard - 100mm 1.00000 each

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:6, including fittings, C.I cover with fra me, 40mm thick concrete flooring(40mm aggregates) cement plaster c oncrete base in C.M 1:4:8 etc. complete as per stan dard design - 50 users

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:6, including fittings, C.I cover with fra me, 40mm thick concrete flooring(40mm aggregates) cement plaster c oncrete base in C.M 1:4:8 etc. complete as per stan dard design - 75 users

Department of Engineering Services, MoWHS

Page 172: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 169

PO0614

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.35000 day LB0033 Carpenter Gd.2 1.46016 day LB0036 Mason Gd.1 5.50235 day LB0038 Plumber Gd.1 0.14733 day LB0039 Work Supervisor (Lajab) 0.19850 day LB0051 Mason Gd.2 15.52316 day LB0053 Plant Operator Gd.3 0.27790 day LB0054 Plumber Gd.2 0.04686 day LB0077 Labour 68.27673 day MP0205 Concrete Mixer(7/5 cu.ft) 0.27790 day MP0206 Concrete Vibrator(M/C5) 0.27790 day MT0043 Sand 6.33432 cu.m MT0060 Boulder 10.38000 cu.m MT0068 Crushed Rock - 40mm 2.83910 cu.m MT0070 Crushed Rock - 20mm 0.82770 cu.m MT0145 Cement (OPC / PSC) 2.05572 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 29.40000 kg MT0325 Ballies 75 to 125mm dia 3.93120 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.12636 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each MT0797 Stoneware pipes 60 cm long - 200mm dia 5.01000 each MT0978 Cast Iron Pipes, Single Socketted, 1.83m long - 150mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1133 Terminal Guard - 150mm 1.00000 each PO0620

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.12500 day LB0033 Carpenter Gd.2 0.48672 day LB0036 Mason Gd.1 2.57199 day LB0038 Plumber Gd.1 0.10473 day LB0039 Work Supervisor (Lajab) 0.08450 day LB0051 Mason Gd.2 1.35079 day LB0053 Plant Operator Gd.3 0.11830 day LB0054 Plumber Gd.2 0.02130 day LB0077 Labour 17.02730 day MP0205 Concrete Mixer(7/5 cu.ft) 0.11830 day MP0206 Concrete Vibrator(M/C5) 0.11830 day MT0043 Sand 1.54889 cu.m MT0068 Crushed Rock - 40mm 1.27270 cu.m MT0070 Crushed Rock - 20mm 0.27163 cu.m MT0125 Bricks 2nd class 0.78629 1000# MT0145 Cement (OPC / PSC) 0.63399 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 10.50000 kg MT0325 Ballies 75 to 125mm dia 1.31040 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.04212 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0795 Stoneware pipes 60 cm long - 100mm dia 4.34200 each MT0975 Cast Iron Pipes, Single Socketted, 1.83m long - 50mm 1.23540 each MT1031 Single equal junction, door - 100mm 2.00000 each MT1130 Terminal Guard - 50mm 1.00000 each

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:6, including fittings, C.I cover with fra me, 40mm thick concrete flooring(40mm aggregates) cement plaster c oncrete base in C.M 1:4:8 etc. complete as per stan dard design - 100 users

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:4, including fittings, C.I cover with fra me, 40mm thick concrete flooring(40mm aggregates) cement plaster c oncrete base in C.M 1:4:8 etc. complete as per stan dard design - 15 users

Department of Engineering Services, MoWHS

Page 173: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 170

PO0621

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.15000 day LB0033 Carpenter Gd.2 0.59904 day LB0036 Mason Gd.1 3.41801 day LB0038 Plumber Gd.1 0.11538 day LB0039 Work Supervisor (Lajab) 0.09550 day LB0051 Mason Gd.2 1.74470 day LB0053 Plant Operator Gd.3 0.13370 day LB0054 Plumber Gd.2 0.27690 day LB0077 Labour 21.68204 day MP0205 Concrete Mixer(7/5 cu.ft) 0.13370 day MP0206 Concrete Vibrator(M/C5) 0.13370 day MT0043 Sand 1.93373 cu.m MT0068 Crushed Rock - 40mm 1.41510 cu.m MT0070 Crushed Rock - 20mm 0.33820 cu.m MT0125 Bricks 2nd class 1.08749 1000# MT0145 Cement (OPC / PSC) 0.79192 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 12.60000 kg MT0325 Ballies 75 to 125mm dia 1.61280 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.05184 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0795 Stoneware pipes 60 cm long - 100mm dia 4.34200 each MT0976 Cast Iron Pipes, Single Socketted, 1.83m long - 75mm 1.23540 each MT1031 Single equal junction, door - 100mm 2.00000 each MT1131 Terminal Guard - 75mm 1.00000 each PO0622

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.21250 day LB0033 Carpenter Gd.2 0.87984 day LB0036 Mason Gd.1 5.01521 day LB0038 Plumber Gd.1 0.12603 day LB0039 Work Supervisor (Lajab) 0.11300 day LB0051 Mason Gd.2 2.57920 day LB0053 Plant Operator Gd.3 0.15820 day LB0054 Plumber Gd.2 0.03408 day LB0077 Labour 31.20809 day MP0205 Concrete Mixer(7/5 cu.ft) 0.15820 day MP0206 Concrete Vibrator(M/C5) 0.15820 day MT0043 Sand 2.62265 cu.m MT0068 Crushed Rock - 40mm 1.59310 cu.m MT0070 Crushed Rock - 20mm 0.50730 cu.m MT0125 Bricks 2nd class 1.63402 1000# MT0145 Cement (OPC / PSC) 1.08722 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 17.85000 kg MT0325 Ballies 75 to 125mm dia 2.36880 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.07614 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0796 Stoneware pipes 60 cm long - 150mm dia 4.34200 each MT0977 Cast Iron Pipes, Single Socketted, 1.83m long - 100mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1132 Terminal Guard - 100mm 1.00000 each

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:4, including fittings, C.I cover with fra me, 40mm thick concrete flooring(40mm aggregates) cement plaster c oncrete base in C.M 1:4:8 etc. complete as per stan dard design - 25 users

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:4, including fittings, C.I cover with fra me, 40mm thick concrete flooring(40mm aggregates) cement plaster c oncrete base in C.M 1:4:8 etc. complete as per stan dard design - 50 users

Department of Engineering Services, MoWHS

Page 174: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 171

PO0623

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.25000 day LB0033 Carpenter Gd.2 1.04832 day LB0036 Mason Gd.1 6.51974 day LB0038 Plumber Gd.1 0.12603 day LB0039 Work Supervisor (Lajab) 0.14900 day LB0051 Mason Gd.2 3.26575 day LB0053 Plant Operator Gd.3 0.20860 day LB0054 Plumber Gd.2 0.03408 day LB0077 Labour 34.55444 day MP0205 Concrete Mixer(7/5 cu.ft) 0.20860 day MP0206 Concrete Vibrator(M/C5) 0.20860 day MT0043 Sand 3.42050 cu.m MT0068 Crushed Rock - 40mm 2.15380 cu.m MT0070 Crushed Rock - 20mm 0.61268 cu.m MT0125 Bricks 2nd class 2.10749 1000# MT0145 Cement (OPC / PSC) 1.40722 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 21.00000 kg MT0325 Ballies 75 to 125mm dia 2.82240 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.09072 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0796 Stoneware pipes 60 cm long - 150mm dia 4.34200 each MT0977 Cast Iron Pipes, Single Socketted, 1.83m long - 100mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1132 Terminal Guard - 100mm 1.00000 each PO0624

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.27500 day LB0033 Carpenter Gd.2 1.16064 day LB0036 Mason Gd.1 7.67268 day LB0038 Plumber Gd.1 0.14733 day LB0039 Work Supervisor (Lajab) 0.16750 day LB0051 Mason Gd.2 3.80107 day LB0053 Plant Operator Gd.3 0.23450 day LB0054 Plumber Gd.2 0.04686 day LB0077 Labour 47.38435 day MP0205 Concrete Mixer(7/5 cu.ft) 0.23450 day MP0206 Concrete Vibrator(M/C5) 0.23450 day MT0043 Sand 3.95589 cu.m MT0068 Crushed Rock - 40mm 2.42970 cu.m MT0070 Crushed Rock - 20mm 0.68530 cu.m MT0125 Bricks 2nd class 2.48378 1000# MT0145 Cement (OPC / PSC) 1.62512 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 23.10000 kg MT0325 Ballies 75 to 125mm dia 3.12480 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.10044 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0797 Stoneware pipes 60 cm long - 200mm dia 4.34200 each MT0978 Cast Iron Pipes, Single Socketted, 1.83m long - 150mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1133 Terminal Guard - 150mm 1.00000 each

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:4, including fittings, C.I cover with fra me, 40mm thick concrete flooring(40mm aggregates) cement plaster c oncrete base in C.M 1:4:8 etc. complete as per stan dard design - 75 users

Constructing Septic Tanks, in R.R Masonry in cement mortar 1:4, including fittings, C.I cover with fra me, 40mm thick concrete flooring(40mm aggregates) cement plaster c oncrete base in C.M 1:4:8 etc. complete as per stan dard design - 100 users

Department of Engineering Services, MoWHS

Page 175: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 172

PO0630

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.81250 day LB0033 Carpenter Gd.2 13.80673 day LB0036 Mason Gd.1 2.07570 day LB0038 Plumber Gd.1 0.10473 day LB0039 Work Supervisor (Lajab) 0.17750 day LB0051 Mason Gd.2 0.44618 day LB0053 Plant Operator Gd.3 0.13230 day LB0054 Plumber Gd.2 0.02130 day LB0077 Labour 19.88881 day MP0205 Concrete Mixer(7/5 cu.ft) 0.13230 day MP0206 Concrete Vibrator(M/C5) 0.13230 day MT0043 Sand 1.10372 cu.m MT0068 Crushed Rock - 40mm 0.03560 cu.m MT0070 Crushed Rock - 20mm 1.64650 cu.m MT0145 Cement (OPC / PSC) 0.72279 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 68.25000 kg MT0325 Ballies 75 to 125mm dia 15.94530 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.26795 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0795 Stoneware pipes 60 cm long - 100mm dia 4.00800 each MT0975 Cast Iron Pipes, Single Socketted, 1.83m long - 50mm 1.23540 each MT1031 Single equal junction, door - 100mm 2.00000 each MT1130 Terminal Guard - 50mm 1.00000 each PO0631

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 1.07500 day LB0033 Carpenter Gd.2 18.81686 day LB0036 Mason Gd.1 2.72521 day LB0038 Plumber Gd.1 0.11538 day LB0039 Work Supervisor (Lajab) 0.23400 day LB0051 Mason Gd.2 0.54955 day LB0053 Plant Operator Gd.3 0.17360 day LB0054 Plumber Gd.2 0.27690 day LB0077 Labour 27.44991 day MP0205 Concrete Mixer(7/5 cu.ft) 0.17360 day MP0206 Concrete Vibrator(M/C5) 0.17360 day MT0043 Sand 1.45144 cu.m MT0068 Crushed Rock - 40mm 0.03560 cu.m MT0070 Crushed Rock - 20mm 2.17160 cu.m MT0145 Cement (OPC / PSC) 0.95061 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 90.30000 kg MT0325 Ballies 75 to 125mm dia 21.67550 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.36274 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0795 Stoneware pipes 60 cm long - 100mm dia 4.00800 each MT0976 Cast Iron Pipes, Single Socketted, 1.83m long - 75mm 1.23540 each MT1031 Single equal junction, door - 100mm 2.00000 each MT1131 Terminal Guard - 75mm 1.00000 each

Constructing Septic Tanks, in reinforced concrete 1 :2:4 (20mm aggregates) including fittings, C.I cove r with frame, 40mm thick concrete flooring (40mm aggregates) cement pl aster concrete base in C.M 1:4:8 etc. complete as p er standard design - 15 users

Constructing Septic Tanks, in reinforced concrete 1 :2:4 (20mm aggregates) including fittings, C.I cove r with frame, 40mm thick concrete flooring (40mm aggregates) cement pl aster concrete base in C.M 1:4:8 etc. complete as p er standard design - 25 users

Department of Engineering Services, MoWHS

Page 176: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 173

PO0632

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 1.58750 day LB0033 Carpenter Gd.2 28.05209 day LB0036 Mason Gd.1 4.09987 day LB0038 Plumber Gd.1 0.12603 day LB0039 Work Supervisor (Lajab) 0.34650 day LB0051 Mason Gd.2 0.82661 day LB0053 Plant Operator Gd.3 0.25760 day LB0054 Plumber Gd.2 0.03408 day LB0077 Labour 41.39547 day MP0205 Concrete Mixer(7/5 cu.ft) 0.25760 day MP0206 Concrete Vibrator(M/C5) 0.25760 day MT0043 Sand 2.16261 cu.m MT0068 Crushed Rock - 40mm 0.05340 cu.m MT0070 Crushed Rock - 20mm 3.22180 cu.m MT0145 Cement (OPC / PSC) 1.41440 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 133.34999 kg MT0325 Ballies 75 to 125mm dia 32.34980 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.54234 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0796 Stoneware pipes 60 cm long - 150mm dia 4.00800 each MT0977 Cast Iron Pipes, Single Socketted, 1.83m long - 100mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1132 Terminal Guard - 100mm 1.00000 each PO0633

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 1.98750 day LB0033 Carpenter Gd.2 36.49952 day LB0036 Mason Gd.1 5.31868 day LB0038 Plumber Gd.1 0.12603 day LB0039 Work Supervisor (Lajab) 0.43450 day LB0051 Mason Gd.2 0.98966 day LB0053 Plant Operator Gd.3 0.32200 day LB0054 Plumber Gd.2 0.03408 day LB0077 Labour 53.45296 day MP0205 Concrete Mixer(7/5 cu.ft) 0.32200 day MP0206 Concrete Vibrator(M/C5) 0.32200 day MT0043 Sand 2.73456 cu.m MT0068 Crushed Rock - 40mm 0.05340 cu.m MT0070 Crushed Rock - 20mm 4.04060 cu.m MT0145 Cement (OPC / PSC) 1.78295 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 166.95000 kg MT0325 Ballies 75 to 125mm dia 41.99860 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.70160 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0796 Stoneware pipes 60 cm long - 150mm dia 4.00800 each MT0977 Cast Iron Pipes, Single Socketted, 1.83m long - 100mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1132 Terminal Guard - 100mm 1.00000 each

Constructing Septic Tanks, in reinforced concrete 1 :2:4 (20mm aggregates) including fittings, C.I cove r with frame, 40mm thick concrete flooring (40mm aggregates) cement pl aster concrete base in C.M 1:4:8 etc. complete as p er standard design - 50 users

Constructing Septic Tanks, in reinforced concrete 1 :2:4 (20mm aggregates) including fittings, C.I cove r with frame, 40mm thick concrete flooring (40mm aggregates) cement pl aster concrete base in C.M 1:4:8 etc. complete as p er standard design - 75 users

Department of Engineering Services, MoWHS

Page 177: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 174

PO0634

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 2.30000 day LB0033 Carpenter Gd.2 48.85418 day LB0036 Mason Gd.1 6.26724 day LB0038 Plumber Gd.1 0.14733 day LB0039 Work Supervisor (Lajab) 0.50350 day LB0051 Mason Gd.2 1.13975 day LB0053 Plant Operator Gd.3 0.37310 day LB0054 Plumber Gd.2 0.04686 day LB0077 Labour 65.72349 day MP0205 Concrete Mixer(7/5 cu.ft) 0.37310 day MP0206 Concrete Vibrator(M/C5) 0.37310 day MT0043 Sand 3.18427 cu.m MT0068 Crushed Rock - 40mm 0.07120 cu.m MT0070 Crushed Rock - 20mm 4.67250 cu.m MT0145 Cement (OPC / PSC) 2.07196 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 193.20000 kg MT0325 Ballies 75 to 125mm dia 55.94190 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.92718 cu.m

MT0751 C.I. manhole cover with frame (light duty) internal dimension 455 x 610mm Total weight of Cover and frame not less than 38 kg. (Cover 23 kg. and frame 15 kg.)

2.00000 each

MT0797 Stoneware pipes 60 cm long - 200mm dia 4.00800 each MT0978 Cast Iron Pipes, Single Socketted, 1.83m long - 150mm 1.23540 each MT1033 Single equal junction, door - 150mm 2.00000 each MT1133 Terminal Guard - 150mm 1.00000 each

Constructing Septic Tanks, in reinforced concrete 1 :2:4 (20mm aggregates) including fittings, C.I cove r with frame, 40mm thick concrete flooring (40mm aggregates) cement pl aster concrete base in C.M 1:4:8 etc. complete as p er standard design - 100 users

Department of Engineering Services, MoWHS

Page 178: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 175

CHAPTER 18

PL0001 Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.11700 day LB0077 Labour 0.17956 day MT0042 Mud dry 0.02064 cu.m PL0002 Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.13500 day LB0077 Labour 0.17548 day MT0042 Mud dry 0.02688 cu.m PL0010 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.08125 day LB0077 Labour 0.14330 day MT0043 Sand 0.00770 cu.m MT0145 Cement (OPC / PSC) 0.00367 tonne PL0011 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.08125 day LB0077 Labour 0.14335 day MT0043 Sand 0.00770 cu.m MT0145 Cement (OPC / PSC) 0.00274 tonne PL0012

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00800 day PL0020 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.10200 day LB0077 Labour 0.15120 day MT0043 Sand 0.01541 cu.m MT0145 Cement (OPC / PSC) 0.00734 tonne PL0021 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.10200 day LB0077 Labour 0.15120 day MT0043 Sand 0.01541 cu.m MT0145 Cement (OPC / PSC) 0.00547 tonne PL0022 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.10200 day LB0077 Labour 0.15120 day MT0043 Sand 0.01541 cu.m MT0145 Cement (OPC / PSC) 0.00446 tonne PL0023 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.10200 day LB0077 Labour 0.15120 day MT0043 Sand 0.01541 cu.m MT0145 Cement (OPC / PSC) 0.00360 tonne

P&L 6mm cement plaster (in ceilings) - Extra, for p laster to ceiling height > 5m ......per additional metre. ht

P&L 12mm cement plaster - C.M 1:3

P&L mud plaster including neat finish - 20mm

P&L 6mm cement plaster (in ceilings) - C.M 1:3

P&L 6mm cement plaster (in ceilings) - C.M 1:4

P&L 12mm cement plaster - C.M 1:6

P&L 12mm cement plaster - C.M 1:4

P&L 12mm cement plaster - C.M 1:5

P&L mud plaster including neat finish - 15mm

PLASTERING

Department of Engineering Services, MoWHS

Page 179: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 176

PL0030 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.11700 day LB0077 Labour 0.17835 day MT0043 Sand 0.01840 cu.m MT0145 Cement (OPC / PSC) 0.00877 tonne PL0031 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.11700 day LB0077 Labour 0.17835 day MT0043 Sand 0.01840 cu.m MT0145 Cement (OPC / PSC) 0.00654 tonne PL0032 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.11700 day LB0077 Labour 0.17835 day MT0043 Sand 0.01840 cu.m MT0145 Cement (OPC / PSC) 0.00533 tonne PL0033 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.11700 day LB0077 Labour 0.17835 day MT0043 Sand 0.01840 cu.m MT0145 Cement (OPC / PSC) 0.00430 tonne PL0040 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.13500 day LB0077 Labour 0.21620 day MT0043 Sand 0.02397 cu.m MT0145 Cement (OPC / PSC) 0.01142 tonne PL0041 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.13500 day LB0077 Labour 0.21620 day MT0043 Sand 0.02397 cu.m MT0145 Cement (OPC / PSC) 0.00851 tonne PL0042 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.13500 day LB0077 Labour 0.21620 day MT0043 Sand 0.02397 cu.m MT0145 Cement (OPC / PSC) 0.00694 tonne PL0043 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.13500 day LB0077 Labour 0.21620 day MT0043 Sand 0.02397 cu.m MT0145 Cement (OPC / PSC) 0.00560 tonne

P&L 15mm cement plaster on rough side of single or half-brick wall - C.M 1:3

P&L 15mm cement plaster on rough side of single or half-brick wall - C.M 1:4

P&L 15mm cement plaster on rough side of single or half-brick wall - C.M 1:5

P&L 20mm cement plaster - C.M 1:6

P&L 15mm cement plaster on rough side of single or half-brick wall - C.M 1:6

P&L 20mm cement plaster - C.M 1:3

P&L 20mm cement plaster - C.M 1:4

P&L 20mm cement plaster - C.M 1:5

Department of Engineering Services, MoWHS

Page 180: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 177

PL0050 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.16900 day LB0051 Mason Gd.2 0.16900 day LB0077 Labour 0.41625 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.00532 tonne PL0051 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.18800 day LB0051 Mason Gd.2 0.18800 day LB0077 Labour 0.45375 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.00532 tonne PL0052 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.21900 day LB0051 Mason Gd.2 0.21900 day LB0077 Labour 0.51675 day MT0043 Sand 0.01498 cu.m MT0145 Cement (OPC / PSC) 0.00532 tonne PL0060 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.20300 day LB0051 Mason Gd.2 0.20300 day LB0077 Labour 0.50250 day MT0043 Sand 0.02140 cu.m MT0145 Cement (OPC / PSC) 0.00760 tonne PL0061 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.22500 day LB0051 Mason Gd.2 0.22500 day LB0077 Labour 0.54750 day MT0043 Sand 0.02140 cu.m MT0145 Cement (OPC / PSC) 0.00760 tonne PL0062 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.26300 day LB0051 Mason Gd.2 0.26300 day LB0077 Labour 0.62250 day MT0043 Sand 0.02140 cu.m MT0145 Cement (OPC / PSC) 0.00760 tonne PL0070

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.13300 day LB0077 Labour 0.18220 day MT0043 Sand 0.01541 cu.m MT0145 Cement (OPC / PSC) 0.00954 tonne PL0071 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.14800 day LB0077 Labour 0.20935 day MT0043 Sand 0.01840 cu.m MT0145 Cement (OPC / PSC) 0.01097 tonne

P&L 12mm plain cement mortar band in C.M 1:4 - Flus h band

P&L cement plaster, finished with floating coat of neat cement - 15mm plaster in C.M 1:3

P&L 20mm plain cement mortar band in C.M 1:4 - Flus h band

P&L 20mm plain cement mortar band in C.M 1:4 - Sunk band

P&L 20mm plain cement mortar band in C.M 1:4 - Rais ed band

P&L cement plaster, finished with floating coat of neat cement - 12mm plaster in C.M 1:3

P&L 12mm plain cement mortar band in C.M 1:4 - Sunk band

P&L 12mm plain cement mortar band in C.M 1:4 - Rais ed band

Department of Engineering Services, MoWHS

Page 181: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 178

PL0072 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.16600 day LB0077 Labour 0.24720 day MT0043 Sand 0.02397 cu.m MT0145 Cement (OPC / PSC) 0.01362 tonne PL0073 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.13300 day LB0077 Labour 0.18220 day MT0043 Sand 0.01541 cu.m MT0145 Cement (OPC / PSC) 0.00767 tonne PL0074 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.14800 day LB0077 Labour 0.20935 day MT0043 Sand 0.01840 cu.m MT0145 Cement (OPC / PSC) 0.00874 tonne PL0075 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.16600 day LB0077 Labour 0.24720 day MT0043 Sand 0.02397 cu.m MT0145 Cement (OPC / PSC) 0.01071 tonne PL0076

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.11225 day LB0067 Painter Gd.2 0.00800 day LB0077 Labour 0.18230 day MT0043 Sand 0.00770 cu.m MT0121 Unslaked lime 0.10000 kg MT0145 Cement (OPC / PSC) 0.00587 tonne PL0080

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.28800 day LB0077 Labour 0.31770 day MT0043 Sand 0.02825 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.01000 cu.m MT0120 Slaked lime 0.92900 kg MT0145 Cement (OPC / PSC) 0.01159 tonne PL0081

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.28800 day LB0077 Labour 0.31770 day MT0043 Sand 0.02825 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.01000 cu.m MT0120 Slaked lime 0.92900 kg MT0145 Cement (OPC / PSC) 0.01159 tonne MT0146 White Cement 0.00510 tonne

Rough cast plaster with a mixture of sand and grave l or crushed stone 2-12mm including plaster in 2 la yers-12mm 1:4, & 10mm 1:3 hydrated lime cement - White cement

P&L cement plaster, finished with floating coat of neat cement - 6mm cement plaster in C.M 1:3, includ ing lime wash on top of wall when dry for bearing R.C slabs and beams

Rough cast plaster with a mixture of sand and grave l or crushed stone 2-12mm including plaster in 2 la yers-12mm 1:4, & 10mm 1:3 hydrated lime cement - Grey cement

P&L cement plaster, finished with floating coat of neat cement - 12mm plaster in C.M 1:4

P&L cement plaster, finished with floating coat of neat cement - 15mm plaster in C.M 1:4

P&L cement plaster, finished with floating coat of neat cement - 20mm plaster in C.M 1:4

P&L cement plaster, finished with floating coat of neat cement - 20mm plaster in C.M 1:3

Department of Engineering Services, MoWHS

Page 182: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 179

PL0090

Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.25750 day LB0077 Labour 0.35120 day MT0043 Sand 0.02825 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.01000 cu.m MT0120 Slaked lime 0.92900 kg MT0145 Cement (OPC / PSC) 0.01159 tonne PL0091

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.11500 day LB0077 Labour 0.25000 day PL0022 12 mm C.P in C.M 1:5 0.01440 cu.m PL0011 6 mm C.P in C.M 1:4 0.00720 cu.m PL0092

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.11500 day LB0077 Labour 0.25000 day PL0022 12 mm C.P in C.M 1:5 0.01440 cu.m PL0010 6 mm C.P in C.M 1:3 0.00720 cu.m

PL0095

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.17500 day LB0077 Labour 0.16500 day MR0026 Cement Lime mortar 1:1:6 0.01440 cu.m PL0096

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.08500 day LB0077 Labour 0.18000 day MR0026 Cement Lime mortar 1:1:6 0.01720 cu.m

PL0100

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01000 day MT0151 Water proofing compound 0.14800 kg PL0101

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01000 day MT0151 Water proofing compound 0.11500 kg PL0102

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01000 day MT0151 Water proofing compound 0.16450 kg

Extra, for providing and mixing water-proofing Mate rials in proportion recommended by the manufacturer s - 12mm plaster in C.M 1:3

Extra, for providing and mixing water-proofing Mate rials in proportion recommended by the manufacturer s - 12mm plaster in C.M 1:4

Extra, for providing and mixing water-proofing Mate rials in proportion recommended by the manufacturer s - 15mm plaster in C.M 1:3

12 mm cement lime plaster of mix on fair side of br ick work - 1:1:6 ( 1 cement :1 lime : 6 sand) finis hed even and smooth and curing etc. complete

12 mm cement lime plaster of mix on rough side of b rick work - 1:1:6 ( 1 cement :1 lime : 6 sand) fini shed even and smooth and curing etc. complete

Pebble dash plaster with a mixture of washed pebble or crushed stone 6mm to 12mm nominal size dashed o ver fresh plaster in the layers, under layer 12mm cement plas ter 1:4 and top layer 10mm cement plaster mixed wit h

finely ground hydrated lime by volume of cement - G rey cement

18 mm cement plaster in two coats; under layer 12 m m C.P 1:5 ( 1 cement : 5 sand) and top layer 6 mm t hick C.P 1:4 ( 1 cement : 6 sand) finished even and smooth and curin g etc. complete

18 mm cement plaster in two coats; under layer 12 m m C.P 1:5 ( 1 cement : 5 sand) and top layer 6 mm t hick C.P 1:3 ( 1 cement : 6 sand) finished even and smooth and curin g etc. complete

Department of Engineering Services, MoWHS

Page 183: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 180

PL0103

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01000 day MT0151 Water proofing compound 0.13200 kg PL0104

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01000 day MT0151 Water proofing compound 0.20430 kg PL0105

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.01000 day MT0151 Water proofing compound 0.16100 kg PL0110 Coefficient for per sq.m

Code Description Quant Units LB0036 Mason Gd.1 0.03100 day LB0076 Labour 0.03100 day MT0145 Cement (OPC / PSC) 0.00220 tonne PL0120

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.20100 day LB0036 Mason Gd.1 0.34000 day LB0077 Labour 0.34000 day MT0685 Plaster of Paris 16.10000 kg PL0121

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.06250 day LB0077 Labour 0.06250 day

Neat cement punning

Providing & fixing 12mm Plaster of Paris (gypsum an hydrous) tiles, rendered smooth with Plaster of Par is - Height above floor < 5m

Providing & fixing 12mm Plaster of Paris (gypsum an hydrous) tiles, rendered smooth with Plaster of Par is - Extra, for heights-above-floor > 5m.....per metre height

Extra, for providing and mixing water-proofing Mate rials in proportion recommended by the manufacturer s - 20mm plaster in C.M 1:3

Extra, for providing and mixing water-proofing Mate rials in proportion recommended by the manufacturer s - 20mm plaster in C.M 1:4

Extra, for providing and mixing water-proofing Mate rials in proportion recommended by the manufacturer s - 15mm plaster in C.M 1:4

Department of Engineering Services, MoWHS

Page 184: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 181

CHAPTER 19

PT0001

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.02130 day PT0002

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.02630 day PT0010 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.03400 day LB0076 Labour 0.03400 day MT0710 Cement primer 0.07000 litre PT0011

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.03000 day LB0076 Labour 0.03000 day MT0712 Red oxide primer, for metals 0.05400 litre PT0012

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.03100 day LB0076 Labour 0.03100 day MT0714 Pink primer, for wood 0.07500 litre PT0013

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.03000 day LB0076 Labour 0.03000 day MT0713 White primer, for wood 0.05400 litre PT0014

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.03000 day LB0076 Labour 0.03000 day MT0711 Synthetic red lead primer 0.05400 litre PT0020

Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.02300 day LB0076 Labour 0.02300 day MT0120 Unslaked lime 0.30000 kg PT0021

Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.01300 day LB0076 Labour 0.01300 day MT0120 Unslaked lime 0.20000 kg PT0022

Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.00800 day LB0076 Labour 0.00800 day MT0120 Unslaked lime 0.10000 kg

Surface preparation removing by scraping, sand pape ring, including scratch repairs - White colour-wash

PAINTING & WALL PAPER

Surface preparation removing by scraping, sand pape ring, including scratch repairs - Dry oil bound dis temper

Providing & applying one coat of primers - Cement p rimer

Providing & applying one coat of primers - Metal wo rk - synthetic red oxide primer

Providing & applying one coat of primers - Wood wor k - pink primer

Providing & applying one coat of primers - Wood wor k - white primer

Providing & applying one coat of primers - Red lead primer

Providing & applying white or colour washing - Whit e washing with lime-new work-three coats

Providing & applying white or colour washing - Whit e washing with lime, old work, two coats

Providing & applying white or colour washing - Whit e washing with lime, old work, one coat

Department of Engineering Services, MoWHS

Page 185: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 182

PT0023

Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.02300 day LB0076 Labour 0.02300 day MT0120 Unslaked lime 0.30000 kg PT0024

Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.01300 day LB0076 Labour 0.01300 day MT0120 Unslaked lime 0.20000 kg PT0025

Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.00800 day LB0076 Labour 0.00800 day MT0120 Unslaked lime 0.10000 kg PT0030

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.05000 day LB0076 Labour 0.05000 day MT0692 Water proofing Cement paint 0.54700 kg PT0031

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.02800 day LB0076 Labour 0.02800 day MT0692 Water proofing Cement paint 0.22000 kg PT0040

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.06600 day LB0076 Labour 0.06600 day MT0120 Unslaked lime 0.10000 kg MT0690 Dry Distemper 0.15000 kg PT0041

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.02800 day LB0076 Labour 0.02800 day MT0690 Dry Distemper 0.10000 kg PT0042

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.08400 day LB0076 Labour 0.08400 day MT0691 Acrylic washable distemper 0.15000 kg MT0710 Cement primer 0.07000 litre PT0043

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.02800 day LB0076 Labour 0.02800 day MT0691 Acrylic washable distemper 0.10000 kg

Providing & applying white or colour washing - Colo ur washing\new work, two coats, including base coat of white-wash with lime

Providing & applying white or colour washing - Colo ur washing with lime, old work, two coats

Providing & applying white or colour washing - Colo ur washing with lime, old work, one coat

Finishing wall with Water-Proof Cement Paint - New work, three coats

Finishing wall with Water-Proof Cement Paint - Old work, one coats

Providing and applying finishing coats - Dry distem per, two coats on new work, including white priming coat

Providing and applying finishing coats - Dry distem per, one coat on old work

Providing and applying finishing coats - Acrylic wa shable distemper, two coats on new work, including cement primer coat

Providing and applying finishing coats - Acrylic wa shable distemper, one coat on old work

Department of Engineering Services, MoWHS

Page 186: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 183

PT0044

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.06800 day LB0076 Labour 0.06800 day MT0726 Black\White bitumen enamel 0.09500 litre PT0045

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.04500 day LB0076 Labour 0.04500 day MT0726 Black\White bitumen enamel 0.05700 litre PT0046

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.04500 day LB0076 Labour 0.04500 day MT0722 Synthetic enamel paint 0.07500 litre PT0047

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.06850 day LB0076 Labour 0.06850 day MT0722 Synthetic enamel paint 0.12500 litre PT0048

Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.06750 day LB0076 Labour 0.06750 day MT0723 High gloss synthetic enamel 0.12000 litre PT0049

Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.04500 day LB0076 Labour 0.04500 day MT0723 High gloss synthetic enamel 0.08000 litre PT0050

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.06800 day LB0076 Labour 0.06800 day MT0721 Red Corrugal paint 0.08000 litre PT0051

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.04500 day LB0076 Labour 0.04500 day MT0721 Red Corrugal paint 0.04600 litre PT0052

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.06750 day LB0076 Labour 0.06750 day MT0725 Vinyl plastic emulsion paint (for cement plaster) 0.12100 litre

Providing and applying finishing coats - Bituminast ic enamel, for steel work, two coats on new work

Providing and applying finishing coats - Bituminast ic enamel, for steel work, one coat on old work

Providing and applying finishing coats - Synthetic enamel, for steel & wood work\one coat on old work

Providing and applying finishing coats - Synthetic enamel, for steel & wood work, two coats on new wor k

Providing and applying finishing coats - High gloss synthetic enamel/for steel & wood work, two coats on new work

Providing and applying finishing coats - High gloss synthetic enamel, for steel & wood work/one coat o n old work

Providing and applying finishing coats - Red corrug al, ready mixed/on G.I sheets, two coats on new wor k

Providing and applying finishing coats - Red corrug al, ready mixed, on G.I sheets/one coat on old work

Providing and applying finishing coats - Vinyl plas tic emulsion paint, for cement, masonry, plaster, t wo coats on new work

Department of Engineering Services, MoWHS

Page 187: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 184

PT0053 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.03400 day LB0076 Labour 0.03400 day MT0724 Acrylic emulsion 0.08100 litre PT0054

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.04400 day LB0076 Labour 0.04400 day MT0720 Aluminium paint 0.04700 litre PT0055

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.06800 day LB0076 Labour 0.06800 day MT0720 Aluminium paint 0.08000 litre PT0060

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.06800 day LB0076 Labour 0.06800 day MT0730 Wood Stain (various colours) 0.07000 litre PT0061

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.13500 day LB0076 Labour 0.04500 day MT0731 Clear synthetic varnish 0.10000 litre PT0062

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.26900 day LB0077 Labour 0.06800 day MT0731 Clear synthetic varnish 0.16300 litre PT0063

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.13500 day LB0077 Labour 0.04500 day MT0732 French Polish 0.10000 litre PT0064

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.26900 day LB0077 Labour 0.06800 day MT0732 French Polish 0.16300 litre PT0070

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.01900 day LB0076 Labour 0.01900 day MT0735 Wood preservative -Brown 0.10000 litre

Providing and applying finishing coats - Acrylic em ulsion, one coat

Providing and applying finishing coats - Aluminium paint, one coat on old work

Providing and applying finishing coats - Aluminium paint, two coats on new work

Providing and applying wood stains, varnishes & po lishes - Wood stain (various colours), one coat

Providing and applying wood stains, varnishes & po lishes - Synthetic varnish (clear) - one coat, on o ld work

Providing and applying wood stains, varnishes & po lishes - Synthetic varnish (clear) - two coats, inc luding coat of wood filler on new work

Providing and applying wood stains, varnishes & po lishes - French polish - one coat, on old work

Providing and applying wood stains, varnishes & po lishes - French polish - two coats, on new work

Providing and applying wood preservatives - Brown, two coats on new work

Department of Engineering Services, MoWHS

Page 188: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 185

PT0071

Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.01400 day LB0076 Labour 0.01400 day MT0735 Wood preservative -Brown 0.08100 litre PT0072

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.05400 day MT0035 Kerosene 0.05000 litre MT0736 Crude Coal Tar 0.28000 litre PT0073 Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.04500 day MT0736 Crude Coal Tar 0.12000 litre PT0080 Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.04500 day LB0077 Labour 0.04500 day MT0745 Wall paper: - Standard 1.05000 sq.m PT0081 Coefficient for per sq.m

Code Description Quant Units LB0067 Painter Gd.2 0.04500 day LB0077 Labour 0.04500 day MT0746 Wall paper: - High Quality 1.05000 sq.m PT0090 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.84000 day LB0067 Painter Gd.2 0.84000 day MT0691 Acrylic washable distemper 0.04020 kg MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0696 Animal glue 0.04020 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0699 Colour powder(excluding gold powder) 0.07002 kg MT0700 Gold powder 0.00498 kg MT0720 Aluminium paint 0.04020 litre PT0091 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.60000 day LB0067 Painter Gd.2 0.60000 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0696 Animal glue 0.04020 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0699 Colour powder(excluding gold powder) 0.07002 kg PT0092 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.42000 day LB0067 Painter Gd.2 0.42000 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0696 Animal glue 0.04020 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0699 Colour powder(excluding gold powder) 0.07002 kg

Providing and applying wood preservatives - Brown, one coat on old work

Providing and applying wood preservatives - Coal ta r, two coats on new work

Providing and applying wood preservatives - Coal ta r, one coat on old work

Providing & fixing wall paper - Standard Quality

Providing & fixing wall paper - High Quality

Providing, preparing and applying Sumdang painting (Not washable) - Rab

Providing, preparing and applying Sumdang painting (Not washable) - Ding

Providing, preparing and applying Sumdang painting (Not washable) - Thamar

Department of Engineering Services, MoWHS

Page 189: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 186

PT0100 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 1.20000 day LB0067 Painter Gd.2 1.20000 day MT0691 Acrylic washable distemper 0.04020 kg MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0696 Animal glue 0.04020 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0699 Colour powder(excluding gold powder) 0.07002 kg MT0700 Gold powder 0.00498 kg MT0720 Aluminium paint 0.04020 litre PT0101 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.90000 day LB0067 Painter Gd.2 0.90000 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0696 Animal glue 0.04020 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0699 Colour powder(excluding gold powder) 0.07002 kg PT0102 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.60000 day LB0067 Painter Gd.2 0.60000 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0696 Animal glue 0.04020 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0699 Colour powder(excluding gold powder) 0.07002 kg PT0110 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.97800 day LB0067 Painter Gd.2 0.97800 day MT0691 Acrylic washable distemper 0.04020 kg MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0700 Gold powder 0.00498 kg MT0720 Aluminium paint 0.04020 litre MT0722 Synthetic enamel paint 0.04020 litre PT0111 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.75600 day LB0067 Painter Gd.2 0.75600 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0722 Synthetic enamel paint 0.04020 litre PT0112 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.55800 day LB0067 Painter Gd.2 0.55800 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0722 Synthetic enamel paint 0.04020 litre

Providing, preparing and applying Dangtshon paintin g (Not washable) - Rab

Providing, preparing and applying Dangtshon paintin g (Not washable) - Ding

Providing, preparing and applying Dangtshon paintin g (Not washable) - Thamar

Providing, preparing and applying Sumdang washable painting - Rab

Providing, preparing and applying Sumdang washable painting - Ding

Providing, preparing and applying Sumdang washable painting - Thamar

Department of Engineering Services, MoWHS

Page 190: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 187

PT0120 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 1.26000 day LB0067 Painter Gd.2 1.26000 day MT0691 Acrylic washable distemper 0.04020 kg MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0700 Gold powder 0.00498 kg MT0720 Aluminium paint 0.04020 litre MT0722 Synthetic enamel paint 0.04020 litre PT0121 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.97800 day LB0067 Painter Gd.2 0.97800 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0722 Synthetic enamel paint 0.04020 litre PT0122 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.70200 day LB0067 Painter Gd.2 0.70200 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0697 Cloth for Bhutanese painting 0.00120 sq.m MT0698 Paper for Bhutanese painting 0.00480 sq.m MT0722 Synthetic enamel paint 0.04020 litre PT0130 Coefficient for per sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.24000 day LB0067 Painter Gd.2 0.24000 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0722 Synthetic enamel paint 0.04020 litre PT0131 Coefficient for per sq.m Code Description Quant Units LB0052 Painter Gd.1 0.21000 day LB0067 Painter Gd.2 0.21000 day MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg PT0140

Coefficient for per Sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.08700 day LB0067 Painter Gd.2 0.08700 day MT0691 Acrylic washable distemper 0.04020 kg MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0697 Cloth for Bhutanese painting 0.40020 sq.m MT0698 Paper for Bhutanese painting 0.30000 sq.m MT0700 Gold powder 0.00498 kg MT0720 Aluminium paint 0.04020 litre PT0142

Coefficient for per Sq.m

Code Description Quant Units LB0052 Painter Gd.1 0.07800 day LB0067 Painter Gd.2 0.07800 day MT0691 Acrylic washable distemper 0.04020 kg MT0695 Mud Paint for Bhutanese traditional painting 0.16200 kg MT0697 Cloth for Bhutanese painting 0.40020 sq.m MT0698 Paper for Bhutanese painting 0.30000 sq.m MT0700 Gold powder 0.00498 kg MT0720 Aluminium paint 0.04020 litre

Providing, preparing and applying Dangtshon washabl e painting - Rab

Providing, preparing and applying Dangtshon washabl e painting - Ding

Providing, preparing and applying Dangtshon washabl e painting - Thamar

Providing, preparing and applying Yutshon painting (plain) - Washable

Providing, preparing and applying Yutshon painting (plain) - Not Washable

Providing, preparing and applying flower natural pa inting for wall decoration design such as Tashitage y symbols, Tashi Zeegay, Za-Tshering, etc.. - Dangtshon - Rab

Providing, preparing and applying flower natural pa inting for wall decoration design such as Tashitage y symbols, Tashi Zeegay, Za-Tshering, etc.. - Sumdang - Rab

Department of Engineering Services, MoWHS

Page 191: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 188

CHAPTER 20

AA0001

Coefficient for per sq.m

Code Description Quant Units LB0051 Mason Gd.2 0.16800 day LB0077 Labour 0.29025 day MT0043 Sand 0.01926 cu.m MT0145 Cement (OPC / PSC) 0.00684 tonne AA0005

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0077 Labour 0.29000 day MT0655 Plain Glass - 3mm thick 1.10000 sq.m MT0740 Putty 0.68000 kg AA0006

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0077 Labour 0.29000 day MT0656 Plain Glass - 4mm thick 1.10000 sq.m MT0740 Putty 0.68000 kg AA0007

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0077 Labour 0.29000 day MT0657 Plain Glass - 5.5mm thick 1.10000 sq.m MT0740 Putty 0.68000 kg AA0008

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0077 Labour 0.29000 day MT0660 Frosted Glass - 3mm thick 1.10000 sq.m MT0740 Putty 0.68000 kg AA0009

Coefficient for per sq.m

Code Description Quant Units LB0021 Carpenter Gd.1 0.29000 day LB0077 Labour 0.29000 day MT0661 Frosted Glass - 5.5mm thick 1.10000 sq.m MT0740 Putty 0.68000 kg AA0015

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.10206 day LB0051 Mason Gd.2 0.08610 day LB0077 Labour 0.25552 day MT0043 Sand 0.00666 cu.m MT0125 Bricks 2nd class 0.00733 1000# MT0145 Cement (OPC / PSC) 0.00263 tonne

Repair to plaster including cutting to shape, surfa ce preparation, proving and applying cement plaster to the surface, disposal rubbish within 50m lead - Patch area <2.5s q.m

ADDITIONS, ALTERATIONS & REPAIRS

Providing & fixing glass panes with putty, nails in cluding remaining. broken glass panes - 3mm thick p lain

Providing & fixing glass panes with putty, nails in cluding remaining. broken glass panes - 4mm thick p lain

Providing & fixing glass panes with putty, nails in cluding remaining. broken glass panes - 5.5mm thick plain

Providing & fixing glass panes with putty, nails in cluding remaining. broken glass panes - 3mm thick f rosted

Providing & fixing glass panes with putty, nails in cluding remaining. broken glass panes - 5.5mm thick frosted

Cutting holes < 300x300mm in brick walls including repair wall

Department of Engineering Services, MoWHS

Page 192: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 189

AA0016

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.10414 day LB0039 Work Supervisor (Lajab) 0.00011 day LB0051 Mason Gd.2 0.10414 day LB0053 Plant Operator Gd.3 0.00015 day LB0077 Labour 0.21387 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00015 day MP0206 Concrete Vibrator(M/C5) 0.00015 day MT0043 Sand 0.00098 cu.m MT0070 Crushed Rock - 20mm 0.00196 cu.m MT0145 Cement (OPC / PSC) 0.00071 tonne AA0017

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.03128 day LB0039 Work Supervisor (Lajab) 0.00019 day LB0051 Mason Gd.2 0.03128 day LB0053 Plant Operator Gd.3 0.00027 day LB0077 Labour 0.13369 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00027 day MP0206 Concrete Vibrator(M/C5) 0.00027 day MT0043 Sand 0.00179 cu.m MT0070 Crushed Rock - 20mm 0.00357 cu.m MT0145 Cement (OPC / PSC) 0.00084 tonne AA0025

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.03750 day LB0036 Mason Gd.1 0.10400 day LB0077 Labour 0.10400 day MT0160 Aluminium Strip Edging - 57mmx12mmx1.6mm 1.05000 m AA0026

Coefficient for per m

Code Description Quant Units LB0033 Carpenter Gd.2 0.03750 day LB0036 Mason Gd.1 0.10400 day LB0077 Labour 0.10400 day MT0176 Aluminium Strip Edging - 38mmx12mmx1.6mm 1.05000 m

Cutting holes < 150x150mm in R.C. floors or roof in cluding making leak proofing with concrete 1:2:4, 2 0mm aggregates

Making chases < 75x75mm in walls including repair a fter fixing G.I pipe etc.

Providing & fixing Aluminium strip edging to stai rcases including rawl plugs and screws, a thin laye r of cement mortar 1:3 - 57mm x 12mm x 3mm

Providing & fixing Aluminium strip edging to stai rcases including rawl plugs and screws, a thin laye r of cement mortar 1:3 - 38mm x 12mm x 3mm

Department of Engineering Services, MoWHS

Page 193: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 190

CHAPTER 21

RW0001

RW0002

RW0006

RW0007

RW0008

RW0009

RW0010

RW0011

RW0012

RW0013

Coefficient for per cu.m

Code Description Quant UnitsMP0124 Excavator ( cat 320) 0.00350 day

RW0014

Coefficient for per cu.m

Code Description Quant UnitsLB0047 Blaster 0.00500 dayLB0077 Labour 0.00500 dayMP0124 Excavator ( cat 320) 0.00350 dayMP0212 Compressor ( cps - 300) 0.00800 dayMP0158 Jack Hammer 0.00800 dayMT0020 Gelatine/Superdyne 0.33200 kgMT0021 Fuse coil 0.40000 eachMT0022 Detonator 0.40000 eachMT0023 Drill rod - 8' 0.00500 each

RW0015

RW0016

RW0017

RW0018

RW0019

ROAD WORKS

Installation of Labour camps: Installation of Labou r camps including water supply, pit latrines, soli d waste disposal etc. according to Environment Code of Practice

Restoration of Labour camps: Restoration of camp si tes including disposal of wreckage, rubbish, restor ation of site using Bioengineering, enclosure of temporary access accor ding to Environment Code of Practice

Earth work in excavation over areas, exceeding 300 mm in depth 1.5 m in width as well as 10 sq.m. On p lan, including disposal of excavated earth, (disposed earth to be levelled and neatly dressed) - ordinary soil

Earth work in excavation over areas, exceeding 300 mm in depth 1.5 m in width as well as 10 sq.m. On p lan, including disposal of excavated earth, (disposed earth to be levelled and neatly dressed) - hard soil

Earth work in excavation over areas, exceeding 300 mm in depth 1.5 m in width as well as 10 sq.m. On p lan, including disposal of excavated earth, (disposed earth to be levelled and neatly dressed) - ordinary rock with o r without blasting

Earth work in excavation over areas, exceeding 300 mm in depth 1.5 m in width as well as 10 sq.m. On p lan, including disposal of excavated earth, (disposed earth to be levelled and neatly dressed) - hard rock requiring blasting

Earth work in excavation over areas, exceeding 300 mm in depth 1.5 m in width as well as 10 sq.m. On p lan, including disposal of excavated earth, (disposed earth to be levelled and neatly dressed) - hard rock requiring chiselling ( blasting prohibited)

Excavation of road formation/trace/box cutting, wit h bulldozer including separate deposition of soil, rocks and stones within 50m for reuse - all kinds of soil

Excavation of road formation/trace/box cutting, wit h bull dozer including separate deposition of soil, rocks and stones within 50m for reuse - all kinds of rock

Excavation of road formation/trace/box cutting, wit h excavator including separate deposition of soil, rocks and stones within 50m for reuse - all kinds of soil

Excavation of road formation/trace/box cutting, wit h excavator including separate deposition of soil, rocks and stones within 50m for reuse - all kinds of rocks

Earthwork in excavation in foundation trenches or d rains including dressing of sides and ramming of bo ttom, disposal of surplus excavated soil within 50m lead - hard soil

Earthwork in excavation in foundation trenches or d rains including dressing of sides and ramming of bo ttom, disposal of surplus excavated soil within 50m lead - Ordinary r ock with or without blasting

Earthwork in excavation in foundation trenches or d rains including dressing of sides and ramming of bo ttom, disposal of surplus excavated soil within 50m lead - ordinary s oil

Earthwork in excavation in foundation trenches or d rains including dressing of sides and ramming of bo ttom, disposal of surplus excavated soil within 50m lead - Hard rock requiring blasting

Transport of loose spoil materials in designated lo cations including loading/unloading. Dressing of du mp sites and plantation of vegetation after completion of dumpin g - beyond 50 up to 200 m

Department of Engineering Services, MoWHS

Page 194: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 191

RW0020

RW0021

RW0035

RW0040

RW0041

RW0044

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.55000 day MT0064 Crushed Rock - 100mm 1.00000 cu.m

RW0045 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.35000 day MT0065 Crushed Rock - 75mm 1.00000 cu.m RW0046 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.40000 day MT0067 Crushed Rock - 50mm 1.00000 cu.m RW0047 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.40000 day MT0066 Crushed Rock - 63mm 0.35000 cu.m MT0067 Crushed Rock - 50mm 0.32500 cu.m MT0068 Crushed Rock - 40mm 0.32500 cu.m RW0048 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.45000 day MT0070 Crushed Rock - 20mm 1.00000 cu.m RW0049 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.50000 day MT0071 Crushed Rock - 12.5 - 6mm 1.00000 cu.m RW0050 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.42500 day MT0067 Crushed Rock - 50mm 0.30000 cu.m MT0068 Crushed Rock - 40mm 0.30000 cu.m MT0069 Crushed Rock - 25mm 0.20000 cu.m MT0070 Crushed Rock - 20mm 0.20000 cu.m

Transport of loose spoil materials in designated lo cations including loading/unloading. Dressing of du mp sites and plantation of vegetation after completion of dumpin g - beyond 200 up to 500 m

Transport of loose spoil materials in designated lo cations including loading/unloading. Dressing of du mp sites and plantation of vegetation after completion of dumpin g - beyond 500 up to 1000 m

Filling of trenches, sides of foundations, walls, e tc including filter material ( 600 mm wide) with 10 0 to 200 mm stones wherever applicable including filling with selected suitable excavated material in layer not exceedin g

200 mm in depth (compacted), consolidating each lay er with power roller or portable compactor, waterin g etc. within 50 m lead

Opening, running and restoration of quarries accor ding to Environmental Code of Practice (ECP) and as per technical specification

Opening, running and restoration of sand quarries according to Environmental Code of Practice (ECP) f or Highways & Roads and as per technical specification

Supplying/collection and stacking stone aggregate - 100 mm

Supplying/collection and stacking stone aggregate - 75 mm

Supplying/collection and stacking stone aggregate - 50 mm

Supplying/collection and stacking stone aggregate - 63 - 40 mm

Supplying/collection and stacking stone aggregate - 20 mm

Supplying/collection and stacking stone aggregate - 12 - 6 mm

Supplying/collection and stacking stone aggregate - 50 - 20 mm

Department of Engineering Services, MoWHS

Page 195: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 192

RW0055

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.20900 day MP0203 Pay Loader ( Cat -910) 0.00410 day MP0211 Truck/Tipper (Tata,1210SK32) 0.01200 day MT0042 Mud dry 1.00000 cu.m RW0056 Coefficient for per cu.m

Code Description Quant Units LB0047 Blaster 0.00500 day LB0077 Labour 0.10420 day MP0203 Pay Loader ( Cat -910) 0.00700 day MP0211 Truck/Tipper (Tata,1210SK32) 0.03240 day MP0212 Compressor (CPS - 300) 0.03240 day MT0020 Superdyne / Gelatine 0.16200 kg MT0021 Fuse Coil 0.22700 each MT0022 Detonator 0.32400 each MT0023 Drill rod - 8' 0.00500 each MT0041 Royalty for earth, mud, boulder, sand & gravel 0.18200 truck RW0057 Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.33670 day MP0203 Pay Loader ( Cat -910) 0.00410 day MP0211 Truck/Tipper (Tata,1210SK32) 0.03240 day MT0041 Royalty for earth, mud, boulder, sand & gravel 0.18200 truck RW0065

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 1.00000 cu.m

LB0077 Labour 0.84900 dayLB0051 Mason Gd. II 0.42500 dayLB0039 Supervisor 0.10000 dayMT0256 G.I wire ( assorted diameters) 11.00000 kgs

RW0066

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 2.00000 cu.m

LB0077 Labour 1.72900 day

LB0051Mason Gd. II for weaving & assembling, placing in position/fixing binding wires, closing and finishing 0.86500 day

LB0039 Supervisor 0.10000 dayMT0256 G.I wire ( assorted diameters) 22.40000 kgs

RW0067

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 3.50000 cu.m

LB0077 Labour 3.11900 day

LB0051Mason Gd. II for weaving & assembling, placing in position/fixing binding wires, closing and finishing 1.55900 day

LB0039 Supervisor 0.12500 dayMT0256 G.I wire ( assorted diameters) 40.40000 kgs

Supplying/collection and stacking at site - Blindin g Materials

Supplying/collection and stacking at site - Boulder

Supplying/collection and stacking at site - Gravel/ coarse sand

Construction of gabion wall, height up to 1.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Construction of gabion wall, height up to 2.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Construction of gabion wall, height up to 3.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Department of Engineering Services, MoWHS

Page 196: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 193

RW0068

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 5.50000 cu.m

LB0077 Labour 4.81700 day

LB0051Mason Gd. II for weaving & assembling, placing in position/fixing binding wires, closing and finishing 2.40900 day

LB0039 Supervisor 0.15000 dayMT0256 G.I wire ( assorted diameters) 62.40000 kgs

RW0069

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 8.00000 cu.m

LB0077 Labour 7.05600 day

LB0051Mason Gd. II for weaving & assembling, placing in position/fixing binding wires, closing and finishing 3.52800 day

LB0039 Supervisor 0.15000 dayMT0256 G.I wire ( assorted diameters) 91.40000 kgs

RW0070

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 11.00000 cu.m

LB0077 Labour 9.65000 day

LB0051Mason Gd. II for weaving & assembling, placing in position/fixing binding wires, closing and finishing 4.82500 day

LB0039 Supervisor 0.15000 dayMT0256 G.I wire ( assorted diameters) 125.00000 kgs

RW0071

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 14.50000 cu.m

LB0077 Labour 12.73800 day

LB0051Mason Gd. II for weaving & assembling, placing in position/fixing binding wires, closing and finishing 6.36900 day

LB0039 Supervisor 0.16000 dayMT0256 G.I wire ( assorted diameters) 165.00000 kgs

RW0072

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 18.50000 cu.m

LB0077 Labour 15.98000 day

LB0051Mason Gd. II for weaving & assembling, placing in position/fixing binding wires, closing and finishing 7.99000 day

LB0039 Supervisor 0.17000 dayMT0256 G.I wire ( assorted diameters) 207.00000 kgs

Construction of gabion wall, height up to 4.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Construction of gabion wall, height up to 5.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Construction of gabion wall, height up to 6.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Construction of gabion wall, height up to 7.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Construction of gabion wall, height up to 8.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Department of Engineering Services, MoWHS

Page 197: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 194

RW0073

Coefficient for per metre

Code Description Quant Units

SM0051Dry hand packed rubble masonry hammer dressed (facing), with stone boulder > 0.04 cu.m 23.00000 cu.m

LB0077 Labour 19.96400 day

LB0051Mason Gd. II for weaving & assembling, placing in position/fixing binding wires, closing and finishing 9.98200 day

LB0039 Supervisor 0.18000 dayMT0256 G.I wire ( assorted diameters) 258.60000 kgs

RW0075

Coefficient for per sq.m

Code Description Quant Units

EW0195Filling of trenches, sides of foundations etc. in layers < 200mm using selected excavated earth, ramming etc within lead 50 m & lift 200 mm 1.50000 cu.m

LB0077 Labour 0.41670 dayLB0033 Carpenter Gd. II 0.08300 dayLB0039 Work Supervisor - Lajab 0.03300 dayMT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 1.44000 KgMT0325 Timber ballies 100 to 150 mm dia 21.24100 m

RW0076

Coefficient for per sq.m

Code Description Quant Units

EW0195Filling of trenches, sides of foundations etc. in layers < 200mm using selected excavated earth, ramming etc within lead 50 m & lift 200 mm 3.00000 cu.m

LB0077 Labour 0.66250 dayLB0033 Carpenter Gd. I 0.12500 dayLB0039 Supervisor 0.05000 dayMT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 2.98625 KgMT0326 Timber ballies 250 to 300 mm dia 6.62300 m

RW0081

Coefficient for per metre

Code Description Quant UnitsLB0077 Labour 0.30000 dayLB0039 Work Supervisor ( Lajab) 0.05000 dayLB0036 Mason - Gd 1 0.05000 day

RW0095

Coefficient for per metre

Code Description Quant Units

CG0002 Jungle clearance 1.00000 sq.mEW0106 Earthwork in Foundation Trenches - All kinds of soil 0.70000 cu.mRW0045 Supplying/Collection and Stacking stone aggregates - 75 mm 0.64750 cu.mLB0077 Labour 0.69300 day

RW0096

Coefficient for per metre

Code Description Quant UnitsCG0002 Jungle clearance 1.50000 sq.mEW0106 Earthwork in Foundation Trenches - All kinds of soil 1.65000 cu.mRW0045 Supplying/Collection and Stacking stone aggregates - 75 mm 1.52630 cu.mLB0077 Labour 0.69300 day

Construction of gabion wall, height up to 9.00 mm w ith dry stone masonry (hammer dressed facing) inclu ding delivery of materials, weaving of gabion mesh with GI wire 2.70 mm dia, fixing of selvedged wire 3.4 mm dia,

binding/lacing wire 2.40 mm dia complete

Providing and Construction of light timber crib wal ls with timber section of 100 to 150 mm diameter in cluding backfilling with suitable materials, ramming/compacting complet e

Providing and Construction of heavy timber crib wal ls with timber section of 250 to 300 mm diameter in cluding backfilling with suitable materials, ramming/compacting complet e

Providing and constructing boulder barriers, width not less than 900 mm, height not exceeding 1.5 m, 2 0 deg. Maximum inclination to the road alignment within 50 m lead

Construction of French Drain ( Size = 600 mm & 1000 mm deep), including clearing jungle, earthwork in excavation in trenches (all types of soil), levelling the excavat ed earth, filling the trench with stone 50 to 100 m m size complete as per drawing

Construction of French Drain ( Size = 1000 mm & 150 0 mm deep), including clearing jungle, earthwork in excavation in trenches (all types of soil), levelling the excavat ed earth, filling the trench with stone 50 to 100 m m size complete as per drawing

Department of Engineering Services, MoWHS

Page 198: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 195

RW0100

Coefficient for per metre

Code Description Quant UnitsEW0106 Earthwork in Foundation Trenches - All kinds of soil 0.05000 cu.mRW0045 Supplying/Collection and Stacking stone aggregates - 75 mm 0.04630 cu.mLB0077 Labour 0.69300 day

RW0105

Coefficient for per metre

Code Description Quant UnitsEW0106 Earthwork in foundation trenches - All kinds of soil 0.20000 cu.mSM0072 Providing and Laying hand packed stone filling or soling with stones 0.12000 sq.mSM0050 Dry hand packed rubble masonry with stone boulders > 0.04 cu.m 0.10000 cu.m

RW0106

Coefficient for per m

Code Description Quant Units LB0036 Mason Gd.1 0.04200 day LB0051 Mason Gd.2 0.04200 day LB0077 Labour 0.25032 day MT0060 Boulder 0.10000 cu.m

RW0107

Coefficient for per metre

Code Description Quant UnitsEW0106 Earthwork in foundation trenches - All kinds of soil 0.15000 cu.m

RW0108

Coefficient for per metre

Code Description Quant UnitsEW0106 Earthwork in foundation trenches 0.20000 cu.mSM0072 Providing and Laying hand packed stone filling or soling with stones 0.12000 cu.mSM0006 Providing and Laying Random Rubble Masonry with hard stone in CM 1:5 0.10000 cu.mCW0045 Providing and Laying Plain Cement Concrete 1:2:4 with stone aggregate 20 mm

down gauge 0.04000 cu.mPL0041 Providing and Laying Cement Plaster 20 mm thick in cement mortar 1:4 0.30000 sq.m

RW0120

Coefficient for per m

Code Description Quant UnitsLB0036 Mason Gd.1 0.03300 dayLB0051 Mason Gd.2 0.01700 dayLB0077 labourer 0.09900 dayMT0060 Boulder 0.04600 cu.m

RW0121

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.11772 day MP0200 Roller, CAT -CS551 0.00054 day

Construction of lined V-shaped drain ( finished siz e = 600 mm wide & 300 mm deep) with 50mm thick PCC 1:2:4, 150 mm thick stone soling, RRM in CM 1:5 on sides, finishe d with 20 mm thick, 1:4 cement plaster including

excavation, levelling and disposal of surplus earth within 50m

Construction of Foundation Drain (minimum size = 2 00 mm wide & 250 mm deep), including clearing jungl e, earthwork in excavation in trenches (all types of soil), levelli ng the excavated earth, filling the trench with sto ne

Preparation of sub grade with proper camber by exca vating earth to depth equal to pavement thickness, consolidation with roller, disposal of surplus earth up to 50m - All k inds of soil

Providing and laying Hammer dressed stone edging 15 0 x 250 mm with stones including excavation, refill ing and disposal of surplus earth within 30 m lead

50 to 100 mm size complete as per drawing

Construction of V-shaped dry stone pitched drain ( finished size = 600 mm wide X 300 mm deep) includin g excavation, levelling and disposal of surplus excavated earth w ithin 50 m

Providing and laying V-shaped drain with stone dry pitch, bedding of stone to the profile as per stand ard design - 450mm wide x 300mm deep, including disposal of rubbish wi thin 50m lead

Construction of V-shaped dry earthen drain ( finish ed size = 600 mm wide X 500 mm deep) including exca vation, levelling and disposal of surplus excavated earth within 50 m

Department of Engineering Services, MoWHS

Page 199: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 196

RW0122

Coefficient for per cu.m Code Description Quant UnitsLB0077 Labour 0.48131 dayMP0200 Roller, CAT -CS551 0.00054 day

RW0123

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00054 day MP0200 Roller, CAT -CS551 0.00054 day RW0124

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 0.02180 day MP0200 Roller, CAT -CS551 0.00080 day RW0130

Coefficient for per cu.m

Code Description Quant UnitsLB0077 Labour 0.10372 dayMP0133 Pay loader ( cat 928F) 0.00741 dayMP0146 Tanker ( TATA) 0.00741 dayMP0168 TATA tipper 1612SE 0.04444 dayMP0200 Roller, CAT - CS551 0.00741 dayMP0212 Compressor ( CPS 300) 0.00741 dayMP0210 Motor Grader ( CAT - 130G) 0.00741 dayMT0080 Gravel/Shingles 40mm - 20 mm 0.18 cu.mMT0081 Gravel / Shingles 20mm to 10mm 0.66 cu.mMT0043 sand 0.36 cu.m

RW0131

Coefficient for per cu.m

Code Description Quant UnitsLB0077 Labour 0.75 dayMP0205 Concrete Mixer ( 7/5 cu.ft) 0.05 dayMP0200 Roller, CAT - CS551 0.05 dayMT0080 Gravels/Shingles, 40mm - 20 mm 0.4 cu.mMT0071 Crushed rock , 12.5 - 6 mm 0.5 cu.mMT0043 sand 0.1 cu.m

RW0132

Coefficient for sq.m

Code Description Quant UnitsLB0077 Labour 0.05120 dayMP0213 Road Broom ( TD -96) 0.00007 DayMP0153 Tractor with trailer, Toyota 0.00007 DayMP0157 Asphalt/Bitumen Heating kettle, India make 0.00062 dayMP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 dayMP0118 Spot Mix Plant, 10/16 TPH 0.00165 dayMP0111 Asphalt Paver 0.00014 dayMP0140 Road Roller ( SV91, Sakai) 0.00045 dayMP0139 Road Roller ( Pneumatic tyre), TS - 300 0.00045 dayMP0133 Pay loader ( cat 928F) 0.00091 dayMP0168 TATA tipper 1612SE 0.00180 dayMP0114 Compactor, plate type 0.00330 dayMT0001 Bitumen 80/100 0.00735 MTMT0070 Crushed rock, 20 mm 0.01602 cu.mMT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.01602 cu.mMT0043 sand 0.02136 cu.m

Preparation of sub grade with proper camber by exca vating earth to depth equal to pavement thickness, consolidation with roller, disposal of surplus earth up to 50m - Blast ed Rock

Consolidation of sub-grade with roller, and making good the undulation with earth and re-rolling the s ub grade

Extra for compaction of earth in embankments under suitable moisture conditions to give at least 95% o f the proctor density

Providing and laying Granular sub-base course ( GSB ) to required degree of compaction with proper form ation of cross fall using motor grader for laying and compacted to requ ired density as per material gradation and aggregat e quality specified

Providing and laying wet mix macadam graded aggrega te base course to required degree of compaction wit h proper formation of cross fall by using well graded crushe d aggregates premixed with OMC using suitable mixe r, motor grader as per material gradation and aggregate quality spe cified

Providing and Laying Dense Bituminous Macadam ( DBM ) to required degree of compaction based on mixture design (job mix formula) approved by the supervising engineer i ncluding preparation of surface with

road broom, application of prime coat @ 0.75 kg/sq. m by mechanized method using asphalt plant, paver, steel roller, tyre roller etc complete - 50mm

Department of Engineering Services, MoWHS

Page 200: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 197

RW0133

Coefficient for sq.m

Code Description Quant UnitsLB0077 Labour 0.05120 dayMP0213 Road Broom ( TD -96) 0.00007 DayMP0153 Tractor with trailer, Toyota 0.00007 DayMP0157 Asphalt/Bitumen Heating kettle, India make 0.00062 dayMP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 dayMP0118 Spot Mix Plant, 10/16 TPH 0.00200 dayMP0111 Asphalt Paver 0.00014 dayMP0140 Road Roller ( SV91, Sakai) 0.00045 dayMP0139 Road Roller ( Pneumatic tyre), TS - 300 0.00045 dayMP0133 Pay loader ( cat 928F) 0.00091 dayMP0168 TATA tipper 1612SE 0.00180 dayMP0114 Compactor, plate type 0.00330 dayMT0001 Bitumen 80/100 0.00867 MTMT0070 Crushed rock, 20 mm 0.01922 cu.mMT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.01922 cu.mMT0043 sand 0.02563 cu.m

RW0134

Coefficient for sq.m

Code Description Quant UnitsLB0077 Labour 0.05120 dayMP0213 Road Broom ( TD -96) 0.00007 DayMP0153 Tractor with trailer, Toyota 0.00007 DayMP0157 Asphalt/Bitumen Heating kettle, India make 0.00062 dayMP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 dayMP0118 Spot Mix Plant, 10/16 TPH 0.00231 dayMP0111 Asphalt Paver 0.00014 dayMP0140 Road Roller ( SV91, Sakai) 0.00045 dayMP0139 Road Roller ( Pneumatic tyre), TS - 300 0.00045 dayMP0133 Pay loader ( cat 928F) 0.00091 dayMP0168 TATA tipper 1612SE 0.00180 dayMP0114 Compactor, plate type 0.00330 dayMT0001 Bitumen 80/100 0.00999 MTMT0070 Crushed rock, 20 mm 0.02243 cu.mMT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.02243 cu.mMT0043 sand 0.02990 cu.m

RW0135

Coefficient for sq.m

Code Description Quant UnitsLB0077 Labour 0.05120 dayMP0213 Road Broom ( TD -96) 0.00007 DayMP0153 Tractor with trailer, Toyota 0.00007 DayMP0157 Asphalt/Bitumen Heating kettle, India make 0.00062 dayMP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 dayMP0118 Spot Mix Plant, 10/16 TPH 0.00264 dayMP0111 Asphalt Paver 0.00014 dayMP0140 Road Roller ( SV91, Sakai) 0.00045 dayMP0139 Road Roller ( Pneumatic tyre), TS - 300 0.00045 dayMP0133 Pay loader ( cat 928F) 0.00091 dayMP0168 TATA tipper 1612SE 0.00180 dayMP0114 Compactor, plate type 0.00330 dayMT0001 Bitumen 80/100 0.01131 MTMT0070 Crushed rock, 20 mm 0.02563 cu.mMT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.02563 cu.mMT0043 sand 0.03418 cu.m

Providing and Laying Dense Bituminous Macadam ( DBM ) to required degree of compaction based on mixture design (job mix formula) approved by the supervising engineer i ncluding preparation of surface with

road broom, application of prime coat @ 0.75 kg/sq. m by mechanized method using asphalt plant, paver, steel roller, tyre roller etc complete - 60mm

Providing and Laying Dense Bituminous Macadam ( DBM ) to required degree of compaction based on mixture design (job mix formula) approved by the supervising engineer i ncluding preparation of surface with

road broom, application of prime coat @ 0.75 kg/sq. m by mechanized method using asphalt plant, paver, steel roller, tyre roller etc complete - 70mm

Providing and Laying Dense Bituminous Macadam ( DBM ) to required degree of compaction based on mixture design (job mix formula) approved by the supervising engineer i ncluding preparation of surface with

road broom, application of prime coat @ 0.75 kg/sq. m by mechanized method using asphalt plant, paver, steel roller, tyre roller etc complete - 80mm

Department of Engineering Services, MoWHS

Page 201: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 198

RW0136

Coefficient for sq.m

Code Description Quant UnitsLB0077 Labour 0.01081 dayMP0213 Road Broom ( TD -96) 0.00007 DayMP0153 Tractor with trailer, Toyota 0.00007 DayMP0157 Asphalt/Bitumen Heating kettle, India make 0.00044 dayMP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 dayMP0118 Spot Mix Plant, 10/16 TPH 0.00083 dayMP0111 Asphalt Paver 0.00014 dayMP0140 Road Roller ( SV91, Sakai) 0.00045 dayMP0139 Road Roller ( Pneumatic tyre), TS - 300 0.00045 dayMP0133 Pay loader ( cat 928F) 0.00091 dayMP0168 TATA tipper 1612SE 0.00180 dayMP0114 Compactor, plate type 0.00330 dayMT0001 Bitumen 80/100 0.00426 MTMT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.01302 cu.mMT0043 sand 0.01302 cu.m

RW0137

Coefficient for sq.m

Code Description Quant UnitsLB0077 Labour 0.01190 dayMP0213 Road Broom ( TD -96) 0.00007 DayMP0153 Tractor with trailer, Toyota 0.00007 DayMP0157 Asphalt/Bitumen Heating kettle, India make 0.00044 dayMP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 dayMP0118 Spot Mix Plant, 10/16 TPH 0.00099 dayMP0111 Asphalt Paver 0.00014 dayMP0140 Road Roller ( SV91, Sakai) 0.00045 dayMP0139 Road Roller ( Pneumatic tyre), TS - 300 0.00045 dayMP0133 Pay loader ( cat 928F) 0.00091 dayMP0168 TATA tipper 1612SE 0.00180 dayMP0114 Compactor, plate type 0.00330 dayMT0001 Bitumen 80/100 0.00505 MTMT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.01562 cu.mMT0043 sand 0.01562 cu.m

RW0138

Coefficient for sq.m

Code Description Quant UnitsLB0077 Labour 0.01311 dayMP0213 Road Broom ( TD -96) 0.00007 DayMP0153 Tractor with trailer, Toyota 0.00007 DayMP0157 Asphalt/Bitumen Heating kettle, India make 0.00044 dayMP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 dayMP0118 Spot Mix Plant, 10/16 TPH 0.00116 dayMP0111 Asphalt Paver 0.00014 dayMP0140 Road Roller ( SV91, Sakai) 0.00045 dayMP0139 Road Roller ( Pneumatic tyre), TS - 300 0.00045 dayMP0133 Pay loader ( cat 928F) 0.00091 dayMP0168 TATA tipper 1612SE 0.00180 dayMP0114 Compactor, plate type 0.00330 dayMT0001 Bitumen 80/100 0.00584 MTMT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.01823 cu.mMT0043 sand 0.01823 cu.m

Providing and Laying Asphalt/Bituminous Concrete to required degree of compaction based on the job mix ture design approved by the supervising engineer using asphalt plant, paver, steel roller, tyre roller etc. as per

material gradation and aggregate quality specified : 25mm

Providing and Laying Asphalt/Bituminous Concrete to required degree of compaction based on the job mix ture design approved by the supervising engineer using asphalt plant, paver, steel roller, tyre roller etc. as per

material gradation and aggregate quality specified : 30mm

Providing and Laying Asphalt/Bituminous Concrete to required degree of compaction based on the job mix ture design approved by the supervising engineer using asphalt plant, paver, steel roller, tyre roller etc. as per

material gradation and aggregate quality specified : 35mm

Department of Engineering Services, MoWHS

Page 202: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 199

RW0139

Coefficient for sq.m

Code Description Quant UnitsLB0077 Labour 0.01431 dayMP0213 Road Broom ( TD-96) 0.00007 DayMP0153 Tractor with trailer, Toyota 0.00007 DayMP0157 Asphalt/Bitumen Heating kettle, India make 0.00044 dayMP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 dayMP0118 Spot Mix Plant, 10/16 TPH 0.00130 dayMP0111 Asphalt Paver 0.00014 dayMP0140 Road Roller ( SV91, Sakai) 0.00045 dayMP0139 Road Roller ( Pneumatic tyre), TS - 300 0.00045 dayMP0133 Pay loader ( cat 928F) 0.00091 dayMP0168 TATA tipper 1612SE 0.00180 dayMP0114 Compactor, plate type 0.00330 dayMT0001 Bitumen 80/100 0.00663 MTMT0071 Crushed rock , 12.5 mm to 6mm ( preferably 10 mm) 0.02083 cu.mMT0043 sand 0.02083 cu.m

RW0145

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.03223 day MP0200 Roller, CAT -CS551 0.00183 day RW0146

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.63541 day MP0203 Pay Loader ( Cat -910) 0.00005 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00015 day MT0042 Mud dry 0.01250 cu.m MT0067 Crushed Rock - 50mm 0.02500 cu.m

RW0147

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour (Male) 1.02300 day MP0200 Roller, CAT -CS551 0.03300 day RW0150

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 1.35000 day MP0200 Roller, CAT -CS551 0.00300 day MT0002 Bitumen Emulsion 0.00270 tonne MT0043 Sand 0.00500 cu.m MT0068 Crushed Rock - 40mm 0.03000 cu.m RW0151

Coefficient for per cu.m

Code Description Quant Units LB0077 Labour 2.69800 day MP0200 Roller, CAT -CS551 0.00300 day MT0002 Bitumen Emulsion 0.00315 tonne MT0068 Crushed Rock - 40mm 0.12500 cu.m

Providing and Laying Asphalt/Bituminous Concrete to required degree of compaction based on the job mix ture design approved by the supervising engineer using asphalt plant, paver, steel roller, tyre roller etc. as per

material gradation and aggregate quality specified : 40mm

Scarifying metalled (water bound) road surface disp osal of rubbish up to 50m and consolidation of the aggregate received from scarifying

Cutting and repairing of roads, including supply of required quantities of aggregates complete - Water bound macadam road

Laying wearing course including screening, sorting, spreading to template and consolidation (measureme nt of wearing course to be taken equal to the quantity of aggrega te used, excluding blinding materials) - With stone aggregates and blinding materials

Cutting & repairing bituminous road including suppl y of required quantity of aggregate & bitumen emuls ion - Manually

Cutting bituminous road along with W.B.M layer & so ling and making good the same including supply of e xtra quantities of aggregate, grit & bitumen emulsion required complet e - Manually

Department of Engineering Services, MoWHS

Page 203: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 200

RW0152

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00068 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00136 day MP0213 Road Broom ( TD - 96 ) 0.00023 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0002 Bitumen Emulsion 0.00280 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.01600 cu.m RW0153

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00182 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00027 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00125 day MP0213 Road Broom ( TD - 96 ) 0.00022 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0002 Bitumen Emulsion 0.00230 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.00200 cu.m RW0154

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00240 day LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00091 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00180 day MP0213 Road Broom ( TD - 96 ) 0.00022 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0002 Bitumen Emulsion 0.00591 tonne MT0068 Crushed Rock - 40mm 0.05400 cu.m RW0155

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00045 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00091 day MP0213 Road Broom ( TD - 96 ) 0.00023 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0002 Bitumen Emulsion 0.00477 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.03000 cu.m RW0156

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00045 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00091 day MP0213 Road Broom ( TD - 96 ) 0.00023 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0002 Bitumen Emulsion 0.00383 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.02400 cu.m

Painting two coats with bitumen emulsion (coat 1 - 12 kg emulsion and 0.1 cu.m, 12 mm aggregates per 1 0 sq.m, coat 2 - 16 kg emulsion 0.06 cu.m, 10 mm aggregates per 10 sq.m ) complete - Mechanized

Repainting one coat with bitumen emulsion @ 2.3 kg of emulsion and 0.002 cu.m of 10 mm nominal size st one chips per sq.m of surface area complete - Mechanized

Premix consolidated carpet surfacing including a ta ck coat @ 0.75 kg bitumen emulsion per sq.m of road surface - 50mm thick with 6.0 cu.m of aggregate 10mm nominal size per 100 sq.m using 96 kg of emulsion of approved

quality per cu.m of stone aggregate (Mechanized)

Premix consolidated carpet surfacing including a ta ck coat @ 0.75 kg bitumen emulsion per sq.m of road surface - 25 mm thick with 2.7 cu.m of stone aggregate, 10 mm nomin al size per 100 sq.m using 149 kg of bitumen

emulsion per cu.m of stone aggregate (Mechanized)

Premix consolidated carpet surfacing including a ta ck coat @ 0.75 kg bitumen emulsion per sq.m of road surface - 20 mm thick with 2.10 cu.m of stone aggregate, 10 mm nomi nal size per 100 sq.m using 147 kg of bitumen

emulsion per cu.m of stone aggregate (Mechanized)

Department of Engineering Services, MoWHS

Page 204: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 201

RW0157

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00034 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00068 day MP0213 Road Broom ( TD - 96 ) 0.00015 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00034 day MT0002 Bitumen Emulsion 0.00130 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.00800 cu.m RW0158

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00080 day LB0077 Labour 0.04360 day MP0200 Roller, CAT -CS551 0.00060 day MT0002 Bitumen Emulsion 0.00053 tonne MT0043 Sand 0.00450 cu.m

RW0160

Coefficient for per sq.m

Code Description Quant Units LB0077 labourer 1.36371 day

MP0200 Roller, CAT -CS551 0.00300 day MP0203 Pay Loader ( Cat -910) 0.00005 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00015 day

MT0001 Bitumen 80\100 0.00306 tonne MT0040 Firewood (stacked volume) 0.00780 cu.m MT0042 Mud dry 0.01250 cu.m MT0066 Crushed Rock - 63mm 0.00875 cu.m MT0067 Crushed Rock - 50mm 0.00812 cu.m MT0068 Crushed Rock - 40mm 0.00812 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02560 cu.m RW0161

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 2.69800 day MP0200 Roller, CAT -CS551 0.00300 day MT0001 Bitumen 80\100 0.00315 tonne MT0040 Firewood (stacked volume) 0.00780 cu.m MT0068 Crushed Rock - 40mm 0.12500 cu.m

RW0165

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00045 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00091 day MP0213 Road Broom ( TD - 96 ) 0.00045 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0001 Bitumen 80\100 0.00300 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.02400 cu.m

RW0166

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00160 day LB0077 Labour 0.12800 day MP0200 Roller, CAT -CS551 0.00170 day MT0001 Bitumen 80\100 0.00300 tonne MT0040 Firewood (stacked volume) 0.00780 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02400 cu.m

Providing seal coat with bitumen emulsion - Using 1 .3 kg of emulsion and 0.80 cu.m stone aggregate of 10mm per 10 sq.m of road surface complete

Providing seal coat of premixed sand with bitumen e mulsion - Using 5.3 kg of emulsion and 0.045 cu.m c oarse sand per 10 sq.m of road surface complete

Painting two coats with bitumen 80/100 (coat 1 - 2 kg bitumen per sq.m, 1.5 cu.m, 12.5 mm aggregates p er 100 sq.m; coat 2 - 1 kg bitumen per sq.m, 0.9 cu.m, 10 mm aggregates p er 100 sq.m) complete - Mechanised

Painting two coats of bitumen 80\100 (coat 1 - 2 kg of bitumen, 0.015 cu.m, 12.5mm aggregate per sq.m; coat 2 - 1 kg of bitumen, 0.009 cu.m, 10 mm aggregates, per sq.m com plete) - Manually

Cutting bituminous road and making good the same in cluding supply of extra quantities of aggregates, g rit and bitumen required complete- bituminous road along with W.B.M layer and soling mechanized

Cutting and repairing of roads, including supply of required quantities of aggregate, grit and bitumen - Bituminous road

Department of Engineering Services, MoWHS

Page 205: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 202

RW0167

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00240 day LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00091 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00180 day MP0213 Road Broom ( TD - 96 ) 0.00022 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0001 Bitumen 80\100 0.00384 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.06000 cu.m RW0168

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00045 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00091 day MP0213 Road Broom ( TD - 96 ) 0.00045 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0001 Bitumen 80\100 0.00267 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.03000 cu.m RW0169

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00045 day MP0203 Pay Loader ( Cat -910) 0.00045 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00091 day MP0213 Road Broom ( TD - 96 ) 0.00045 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00045 day MT0001 Bitumen 80\100 0.00200 tonne MT0068 Crushed Rock - 40mm 0.02400 cu.m

RW0170

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00240 day LB0077 Labour 0.11290 day MP0200 Roller, CAT -CS551 0.00110 day MT0001 Bitumen 80\100 0.00230 tonne MT0040 Firewood (stacked volume) 0.00600 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.02400 cu.m RW0171

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00240 day LB0077 Labour 0.13180 day MP0200 Roller, CAT -CS551 0.00110 day MT0001 Bitumen 80\100 0.00267 tonne MT0040 Firewood (stacked volume) 0.00700 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.03000 cu.m

Premix carpet surfacing including a tack coat @ 0.7 5 kg bitumen per sq.m of road surface - 50mm thick with 6 cu.m of aggregate 10mm nominal size per 100 sq.m using 51.5 kg of bitumen 80/100 grade per cu.m of stone aggr egate (Mechanized)

Premix carpet surfacing including a tack coat @ 0.7 5 kg bitumen per sq.m of road surface - 25mm thick with 3 cu.m of stone aggregate per 100 sq.m and 51.5 kg of bitumen 80/100 grade per cu.m of stone aggregate (Mechanis ed)

Premix carpet surfacing including a tack coat @ 0.7 5 kg bitumen per sq.m of road surface - 20mm thick with 2.40 cu.m of stone aggregate 10mm nominal size per 100 sq.m and 51.5 kg of bitumen 80/100 grade per cu.m of stone a ggregate (Mechanized)

Premix Carpeting with 64 kg of bitumen 80\100 per c u.m of aggregates including a tack coat with bitume n of same quality @ 0.75 kg per sq.m of road surface - 20 mm thick wi th 2.4 cu.m, 10mm aggregate per 100 sq.m (Manually)

Premix Carpeting with 64 kg of bitumen 80\100 per c u.m of aggregates including a tack coat with bitume n of same quality @ 0.75 kg per sq.m of road surface - 25 mm thick wi th 3.0 cu.m, 10mm aggregate per 100 sq.m (Manually)

Department of Engineering Services, MoWHS

Page 206: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 203

RW0175

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00060 day LB0077 Labour 0.05200 day MP0200 Roller, CAT -CS551 0.00060 day MT0001 Bitumen 80\100 0.00100 tonne MT0040 Firewood (stacked volume) 0.00260 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.00900 cu.m

RW0176

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00182 day MP0200 Roller, CAT -CS551 0.00015 day MP0203 Pay Loader ( Cat -910) 0.00015 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00030 day MP0213 Road Broom ( TD - 96 ) 0.00015 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00015 day MT0001 Bitumen 80\100 0.00100 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.00900 cu.m RW0177

Coefficient for per sq.m

Code Description Quant Units LB0077 Labour 0.00320 day MP0200 Roller, CAT -CS551 0.00034 day MP0203 Pay Loader ( Cat -910) 0.00034 day MP0211 Truck/Tipper (Tata,1210SK32) 0.00091 day MP0213 Road Broom ( TD - 96 ) 0.00015 day MP0214 Asphalt/Bitumen Sprayer ( Hino) 0.00034 day MT0001 Bitumen 80\100 0.00138 tonne MT0071 Crushed Rock - 12.5 - 6mm 0.01120 cu.m

RW0178

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00060 day LB0077 Labour 0.05080 day MP0200 Roller, CAT -CS551 0.00060 day MT0001 Bitumen 80\100 0.00150 tonne MT0040 Firewood (stacked volume) 0.00390 cu.m MT0071 Crushed Rock - 12.5 - 6mm 0.01050 cu.m RW0179

Coefficient for per sq.m

Code Description Quant Units LB0039 Work Supervisor (Lajab) 0.00080 day LB0077 Labour 0.04360 day MP0200 Roller, CAT -CS551 0.00060 day MT0001 Bitumen 80\100 0.00096 tonne MT0040 Firewood (stacked volume) 0.00250 cu.m MT0043 Sand 0.00750 cu.m

Repainting, one coat of bitumen 80\100 @ 1 kg of bi tumen; 0.009 cu.m, 10mm aggregate per sq.m of road surface - Manually

Repainting one coat of bitumen 80/100 at a rate of 1 kg bitumen/sq.m & 0.9 cu.m of 10mm stone aggregat e per 100 sq.m - Mechanised

Providing seal coat with bitumen 80/100 grade of ap proved quality using 1.12 cu.m of stone aggregate 1 0mm size per 100 sq.m and 56 kg of bitumen 80/100 grade per cu.m of stone aggregate with a tack coat of 0.75 kg of

bitumen per sq.m of road surface complete - Mechan ized

Providing seal coat with bitumen 80\100 using 1.5 k g of bitumen per sq.m with 1.05 cu.m, 10mm aggregat e per 100 sq.m of road surface - Manually

Providing seal coat of premixed sand with bitumen 8 0\100 using 128 kg of bitumen per cu.m of sand and 0.75 cu.m of coarse sand per 100 sq.m of road surface - Manually

Department of Engineering Services, MoWHS

Page 207: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 204

RW0180

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.10550 day LB0033 Carpenter Gd.2 0.15600 day LB0036 Mason Gd.1 0.54324 day LB0039 Work Supervisor (Lajab) 0.00300 day LB0051 Mason Gd.2 0.54324 day LB0052 Painter Gd.1 0.02741 day LB0053 Plant Operator Gd.3 0.00210 day LB0077 Labour 2.13796 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00210 day MP0206 Concrete Vibrator(M/C5) 0.00210 day MT0043 Sand 0.02460 cu.m MT0070 Crushed Rock - 20mm 0.02670 cu.m MT0145 Cement (OPC / PSC) 0.01500 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 8.86200 kg MT0325 Ballies 75 to 125mm dia 0.42000 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01350 cu.m MT0710 Cement primer 0.01890 litre MT0725 Vinyl plastic emulsion paint (for cement plaster) 0.03267 litre RW0181

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.10013 day LB0033 Carpenter Gd.2 0.31512 day LB0036 Mason Gd.1 0.63598 day LB0039 Work Supervisor (Lajab) 0.01000 day LB0051 Mason Gd.2 0.63598 day LB0052 Painter Gd.1 0.09237 day LB0053 Plant Operator Gd.3 0.00700 day LB0077 Labour 2.94526 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00700 day MP0206 Concrete Vibrator(M/C5) 0.00700 day MT0043 Sand 0.07170 cu.m MT0070 Crushed Rock - 20mm 0.08900 cu.m MT0145 Cement (OPC / PSC) 0.04509 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 8.41050 kg MT0325 Ballies 75 to 125mm dia 0.84840 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02727 cu.m MT0710 Cement primer 0.06370 litre MT0725 Vinyl plastic emulsion paint (for cement plaster) 0.11011 litre RW0182

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.11013 day LB0033 Carpenter Gd.2 0.33540 day LB0036 Mason Gd.1 0.64818 day LB0039 Work Supervisor (Lajab) 0.01100 day LB0051 Mason Gd.2 0.64818 day LB0052 Painter Gd.1 0.11165 day LB0053 Plant Operator Gd.3 0.00770 day LB0077 Labour 3.09828 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00770 day MP0206 Concrete Vibrator(M/C5) 0.00770 day MT0043 Sand 0.07823 cu.m MT0070 Crushed Rock - 20mm 0.09790 cu.m MT0145 Cement (OPC / PSC) 0.04930 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 9.25050 kg MT0325 Ballies 75 to 125mm dia 0.90300 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02903 cu.m MT0710 Cement primer 0.07700 litre MT0725 Vinyl plastic emulsion paint (for cement plaster) 0.13310 litre RW0183

Coefficient for per each

Code Description Quant Units LB0036 Mason Gd.1 0.01240 day

Providing & fixing RC name board including primer a nd white zinc paint - Rectangular with post

Providing & fixing RC name board including primer a nd white zinc paint - Flat without post for one dir ection only

Providing & fixing RC name board including primer a nd white zinc paint - Flat without post for two dir ections only

Engraving letters on hard stone.......per letter pe r centimetre height

Department of Engineering Services, MoWHS

Page 208: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 205

RW0185

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.01650 day LB0033 Carpenter Gd.2 0.07800 day LB0036 Mason Gd.1 0.02275 day LB0039 Work Supervisor (Lajab) 0.00200 day LB0051 Mason Gd.2 0.02275 day LB0053 Plant Operator Gd.3 0.00140 day LB0077 Labour 0.36780 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00140 day MP0206 Concrete Vibrator(M/C5) 0.00140 day MT0043 Sand 0.01275 cu.m MT0070 Crushed Rock - 20mm 0.01780 cu.m MT0145 Cement (OPC / PSC) 0.00826 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 1.38600 kg MT0325 Ballies 75 to 125mm dia 0.21000 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.00675 cu.m RW0186

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.06013 day LB0033 Carpenter Gd.2 0.17004 day LB0036 Mason Gd.1 0.07193 day LB0039 Work Supervisor (Lajab) 0.01000 day LB0051 Mason Gd.2 0.07193 day LB0053 Plant Operator Gd.3 0.00700 day LB0077 Labour 0.95070 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00700 day MP0206 Concrete Vibrator(M/C5) 0.00700 day MT0043 Sand 0.05590 cu.m MT0070 Crushed Rock - 20mm 0.08900 cu.m MT0145 Cement (OPC / PSC) 0.03756 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 5.05050 kg MT0325 Ballies 75 to 125mm dia 0.45780 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01472 cu.m RW0187

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.11413 day LB0033 Carpenter Gd.2 0.26832 day LB0036 Mason Gd.1 0.12265 day LB0039 Work Supervisor (Lajab) 0.01900 day LB0051 Mason Gd.2 0.12265 day LB0053 Plant Operator Gd.3 0.01330 day LB0077 Labour 1.47753 day MP0205 Concrete Mixer(7/5 cu.ft) 0.01330 day MP0206 Concrete Vibrator(M/C5) 0.01330 day MT0043 Sand 0.10358 cu.m MT0070 Crushed Rock - 20mm 0.16910 cu.m MT0145 Cement (OPC / PSC) 0.07012 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 9.58650 kg MT0325 Ballies 75 to 125mm dia 0.72240 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.02322 cu.m

Providing & fixing precast boundary stone of RC 1:2 :4 (20mm aggregate) including finishing with mortar 1:3 (cost of excavation, refilling etc to be paid separately) - 150mm dia x 900mm high

Providing & fixing precast kilometre stone of RC 1: 2:4 (20mm aggregate) including finishing with morta r 1:3 complete as per standard design (cost of excavation, concreting , painting etc. shall be paid separately) - 35cm x 111cm x 25cm

Providing & fixing precast kilometre stone of RC 1: 2:4 (20mm aggregate) including finishing with morta r 1:3 complete as per standard design (cost of excavation, concreting , painting etc. shall be paid separately) - 50cm x 152.5cm x 25cm

Department of Engineering Services, MoWHS

Page 209: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 206

RW0188

Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03600 day LB0033 Carpenter Gd.2 0.12636 day LB0036 Mason Gd.1 0.05390 day LB0039 Work Supervisor (Lajab) 0.00600 day LB0051 Mason Gd.2 0.05390 day LB0053 Plant Operator Gd.3 0.00420 day LB0077 Labour 0.60718 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00420 day MP0206 Concrete Vibrator(M/C5) 0.00420 day MT0043 Sand 0.03556 cu.m MT0070 Crushed Rock - 20mm 0.05340 cu.m MT0145 Cement (OPC / PSC) 0.02350 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 3.02400 kg MT0325 Ballies 75 to 125mm dia 0.34020 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01094 cu.m RW0189

Coefficient for per each

Code Description Quant Units LB0052 Painter Gd.1 0.00400 day MT0722 Synthetic enamel paint 0.00040 litre RW0190 Coefficient for per each

Code Description Quant Units LB0052 Painter Gd.1 0.00260 day LB0076 Labour 0.00060 day MT0722 Synthetic enamel paint 0.00030 litre RW0195 Coefficient for per m

Code Description Quant Units LB0077 Labour 0.09000 day MT0326 Ballies 250 to 300mm dia 1.00000 m RW0196 Coefficient for per each

Code Description Quant Units LB0077 Labour 0.34200 day MT0326 Ballies 250 to 300 mm dia 1.80000 m RW0197 Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.04625 day LB0033 Carpenter Gd.2 0.25933 day LB0036 Mason Gd.1 0.04471 day LB0039 Work Supervisor (Lajab) 0.00336 day LB0051 Mason Gd.2 0.04471 day LB0053 Plant Operator Gd.3 0.00235 day LB0077 Labour 0.54599 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00235 day MP0206 Concrete Vibrator(M/C5) 0.00235 day MT0043 Sand 0.02256 cu.m MT0070 Crushed Rock - 20mm 0.02990 cu.m MT0145 Cement (OPC / PSC) 0.01442 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 3.88500 kg MT0325 Ballies 75 to 125mm dia 0.84327 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01209 cu.m

Providing & fixing precast kilometre stone of RC 1: 2:4 (20mm aggregate) including finishing with morta r 1:3 complete as per standard design (cost of excavation, concreting , painting etc. shall be paid separately) - 35cm x 93.5cm x 18cm

Lettering with paint of approved brand and manufact ure......per letter per centimetre ht

Relettering with paint of approved brand and manufa cture......per letter per centimetre ht

Supplying posts & struts - Local ballies, 250 mm mi n. girth

Supplying posts & struts - Local ballies 250 mm min girth , 1.8m long

Supplying posts & struts - Precast R.C posts, 1.8 m long

Department of Engineering Services, MoWHS

Page 210: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 207

RW0198 Coefficient for per each

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.02875 day LB0033 Carpenter Gd.2 0.23447 day LB0036 Mason Gd.1 0.03674 day LB0039 Work Supervisor (Lajab) 0.00210 day LB0051 Mason Gd.2 0.03674 day LB0053 Plant Operator Gd.3 0.00147 day LB0077 Labour 0.44418 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00147 day MP0206 Concrete Vibrator(M/C5) 0.00147 day MT0043 Sand 0.01575 cu.m MT0070 Crushed Rock - 20mm 0.01869 cu.m MT0145 Cement (OPC / PSC) 0.00980 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 2.41500 kg MT0325 Ballies 75 to 125mm dia 0.76244 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01093 cu.m RW0199 Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.04625 day LB0033 Carpenter Gd.2 0.25933 day LB0036 Mason Gd.1 0.05054 day LB0039 Work Supervisor (Lajab) 0.00802 day LB0051 Mason Gd.2 0.05054 day LB0053 Plant Operator Gd.3 0.00888 day LB0077 Labour 0.84180 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00888 day MP0206 Concrete Vibrator(M/C5) 0.00888 day MT0043 Sand 0.06641 cu.m MT0067 Crushed Rock - 50mm 0.08304 cu.m MT0070 Crushed Rock - 20mm 0.02990 cu.m MT0145 Cement (OPC / PSC) 0.02665 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 3.88500 kg MT0325 Ballies 75 to 125mm dia 0.84327 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01209 cu.m RW0200

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.02875 day LB0033 Carpenter Gd.2 0.23447 day LB0036 Mason Gd.1 0.03757 day LB0039 Work Supervisor (Lajab) 0.00276 day LB0051 Mason Gd.2 0.03757 day LB0053 Plant Operator Gd.3 0.00240 day LB0077 Labour 0.56622 day MP0205 Concrete Mixer(7/5 cu.ft) 0.00240 day MP0206 Concrete Vibrator(M/C5) 0.00240 day MT0043 Sand 0.02201 cu.m MT0067 Crushed Rock - 50mm 0.01184 cu.m MT0070 Crushed Rock - 20mm 0.01869 cu.m MT0145 Cement (OPC / PSC) 0.01154 tonne MT0208 Thermo - Mechanically Treated ( TMT ) bars (yield strength 500 MPa) 2.41500 kg MT0325 Ballies 75 to 125mm dia 0.76244 m MT0330 Rough-sawn timber (urban rate) - Class 'B', (Mixed Conifer) 0.01093 cu.m

RW0202

Coefficient for per m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.00460 day LB0036 Mason Gd.1 0.00060 day LB0051 Mason Gd.2 0.00060 day LB0077 Labour 0.00230 day MT0225 Barbed Wire 1.00000 m

Supplying posts & struts - Precast R.C struts 2.0 m long

Supplying posts & struts - RCC posts & struts, 1.8m long

Supplying posts & struts - RCC posts & struts, 2m l ong

Providing & fixing G.I barbed Wire Netting includin g fixing of post or struts, G.I staples, coal tarri ng in case of ballies complete (posts/struts, earthwork, concrete paid se parately) - 2.5mm , (12 SWG), 4 barbs form by

twisting two point wires, each two turns, pitch of barbs 75mm

Department of Engineering Services, MoWHS

Page 211: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 208

RW0205

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0230 G.I double knotted mesh - 100 x 100 x 8-gauge 1.00000 sq.m RW0206

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0281 G.I double knotted mesh - 100 x 100 x 12-gauge 1.00000 sq.m RW0207

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0232 G.I double knotted mesh - 150 x 150 x 8-gauge 1.00000 sq.m RW0208

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0233 G.I double knotted mesh - 150 x 150 x 12-gauge 1.00000 sq.m RW0209

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0244 G.I chain-link mesh - 50 x 50 x 8-gauge 1.00000 sq.m RW0210

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0245 G.I chain-link mesh - 50 x 50 x 12-gauge 1.00000 sq.m RW0211

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0242 G.I chain-link mesh - 75 x 75 x 8-gauge 1.00000 sq.m

Providing & fixing G.I double knotted mesh includin g fixing of post or struts, G.I staples, coal tarri ng in case of ballies complete (excluding the cost of posts/struts, earth work, concrete) - 4mm (8 SWG) x 100mm

Providing & fixing G.I double knotted mesh includin g fixing of post or struts, G.I staples, coal tarri ng in case of ballies complete (excluding the cost of posts/struts, earth work, concrete) - 2.5mm (12 SWG) x 100mm

Providing & fixing G.I double knotted mesh includin g fixing of post or struts, G.I staples, coal tarri ng in case of ballies complete (excluding the cost of posts/struts, earth work, concrete) - 4mm (8 SWG) x 150mm

Providing & fixing G.I double knotted mesh includin g fixing of post or struts, G.I staples, coal tarri ng in case of ballies complete (excluding the cost of posts/struts, earth work, concrete) - 2.5mm (12 SWG) x 150mm

Providing & fixing G.I chain-link mesh including fi xing of post or struts, G.I staples (excluding the cost of posts/struts, earthwork, concrete etc.) - 4mm (8 SWG) x 50mm

Providing & fixing G.I chain-link mesh including fi xing of post or struts, G.I staples (excluding the cost of posts/struts, earthwork, concrete etc.) - 2.5mm (12 SWG) x 50mm

Providing & fixing G.I chain-link mesh including fi xing of post or struts, G.I staples (excluding the cost of posts/struts, earthwork, concrete etc.) - 4mm (8 SWG) x 75mm

Department of Engineering Services, MoWHS

Page 212: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 209

RW0212

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0243 G.I chain-link mesh - 75 x 75 x 12-gauge 1.00000 sq.m RW0213

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0240 G.I chain-link mesh - 100 x 100 x 8-gauge 1.00000 sq.m RW0214

Coefficient for per sq.m

Code Description Quant Units LB0032 Blacksmith (metal-worker) 0.03480 day LB0036 Mason Gd.1 0.00420 day LB0051 Mason Gd.2 0.00420 day LB0077 Labour 0.01730 day MT0231 G.I chain-link mesh - 100 x 100 x 12-gauge 1.00000 sq.m

RW0215

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.00830 day LB0077 Labour 0.06333 day MT0225 G.I Barbed Wire 11.17000 m

RW0216

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.01000 day LB0077 Labour 0.06333 day

LB0033 carpenter Gd. 2 0.01300 day MT0225 G.I Barbed Wire 8.15200 m

MT0736 crude coal tar 0.07333 litreMT0035 kerosene 0.01300 litre

Providing & fixing G.I chain-link mesh including fi xing of post or struts, G.I staples (excluding the cost of posts/struts, earthwork, concrete etc.) - 2.5mm (12 SWG) x 75mm

Providing & fixing G.I chain-link mesh including fi xing of post or struts, G.I staples (excluding the cost of posts/struts, earthwork, concrete etc.) - 4mm (8 SWG) x 100mm

Providing & fixing G.I chain-link mesh including fi xing of post or struts, G.I staples (excluding the cost of posts/struts, earthwork, concrete etc.) - 2.5mm (12 SWG) x 100mm

Providing & fixing 1.2 m high fencing with 1.8 m R. C.C posts of standard design placed every 3 m apart , embedded in cement concrete blocks, every 15th post, last but o ne end post and corner post shall be strutted

on both sides and end post one side only, provided with nine horizontal lines and two diagonals of ba rbed wire 10 kg per 100 m ( min) between two posts fitted and fixed wit h GI staples on wooden plugs or GI binding wire

tied to 6mm bars nibs fixed while casting the post (cost of RCC posts, struts, earthwork and concrete to be paid for separately)

Providing & fixing 1.2 m high fencing with 1.8 m ba lli posts 250 mm girth ( min.) placed every 2.5 m apart, embedded in cement concrete blocks, every 15th post, last but o ne end post and corner post shall be strutted

on both sides and end post one side only, provided with six horizontal lines and two diagonals of barb ed wire 10 kg per 100 m ( min) between two posts fitted and fixed with GI staples driven into the posts complete

(cost of RCC posts, struts, earthwork and concrete to be paid for separately)

Department of Engineering Services, MoWHS

Page 213: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 210

RW0217

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.01670 day LB0077 Labour 0.09000 day

LB0033 carpenter Gd. 2 0.02160 day MT0225 G.I Barbed Wire 14.64000 m

MT0736 crude coal tar 0.12570 litreMT0035 kerosene 0.02260 litre

RW0218

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.33000 day LB0077 Labour 0.03300 day

RW0219

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.00833 day LB0077 Labour 0.05670 day MT0225 G.I Barbed Wire 11.10000 m

RW0220

Coefficient for per m

Code Description Quant Units LB0051 Mason Gd.2 0.01160 day LB0077 Labour 0.09000 day MT0225 G.I Barbed Wire 14.27000 m

RW0230

Coefficient for per kg

Code Description Quant UnitsLB0077 Labour 1.23000 dayMT0122 Sealed bag 1.00000 each

RW0231Coefficient for per 100.00 sq.m

Code Description Quant UnitsLB0077 Labour 0.17000 day

RW0232

Coefficient for per 1.00 sq.m

Code Description Quant UnitsLB0077 Labour 0.17000 day

Providing & fixing 2.4 m high fencing with 3.3 m ba lli posts 250 mm girth (min.) placed every 2.5 m a part, embedded in cement concrete blocks, every 15th post, last but o ne end post and corner post shall be strutted

on both sides and end post one side only, provided with twelve horizontal lines and two diagonals of b arbed wire 10 kg per 100 m ( min) between two posts fitted and fixed wit h GI staples driven into the posts complete

(cost of RCC posts, struts, earthwork and concrete to be paid for separately)

Providing & fixing 1.3 m high concrete rail and pal e fencing with 1.8 m R.C.C posts 2.2 m rails and 1. 25 m pales placed every 2.5 m apart, embedded in cement concrete bloc ks ( 450 mm x 450 mm x 700 mm),

of mix 1:5:10 ( 1 cement : 5 sand : 10 graded crus hed rock 40 mm nominal size ) ( cost of earthwork i n excavation, concrete work, posts, rails and pales to be paid fo r separately)

Providing & fixing 1.2 m high fencing with 1.2 m an gle posts ( 40mm x 40 mm x 6 mm) placed every 3 m centre to centre , embedded in cement concrete blocks, every 15th post , last but one end post and corner post shall be st rutted on both sides and end post one side only, provided with nin e horizontal lines and two diagonals interwoven wit h horizontal wires of barbed wire 10 kg per 100 m ( min) between two post s fitted and fixed with GI staples, turn buckles co mplete

( cost of posts, struts, earthwork and concrete to be paid for separately)

Providing & fixing 1.8 m high fencing with 1.8 m an gle posts ( 50mm x 50 mm x 6 mm) placed every 3 m centre to centre , embedded in cement concrete blocks, every 15th post , last but one end post and corner post shall be s trutted on both sides and end post one side only, provided with nin e horizontal lines and two diagonals interwoven wit h horizontal wires of barbed wire 10 kg per 100 m ( min) between two post s fitted and fixed with GI staples, turn buckles co mplete

(cost of posts, struts, earthwork and concrete to b e paid for separately)

Collection of Grass and pioneer plant seed, includi ng separation, drying in the sun and storing

Broadcasting of Grass/pioneer species seeds on slop es at the rate of 25 grams per sq.m

Direct Seeding of shrubs or tree seeds at 30 cm spa cing including digging holes up to 5 cm depth and covering with soil, with two seeds per planting hole

Department of Engineering Services, MoWHS

Page 214: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Material Coefficients (Civil Works) - 2013 211

RW0233

Coefficient for per 1.00 sq.m (at the rate of 11.00 number of cuttings per running meter)

Code Description Quant UnitsLB0077 Labour 0.20000 dayMT0046 Cuttings 11.00000 each

RW0234

Coefficient for per 1.00 sq.m (at the rate of 21.00 number of cuttings per running meter)

Code Description Quant UnitsLB0077 Labour 0.22000 dayMT0046 Cuttings 40.00000 each

RW0235

Coefficient for per 10 nos.

Code Description Quant UnitsLB0077 Labour 0.33000 dayMT0047 seedling 10.00000 each

RW0236

Coefficient for per sq.m.

Code Description Quant UnitsLB0077 Labour 0.12860 dayMT0393 cane baskets for carrying sods 0.05000 each

RW0237

Coefficient for per sq.m.

Code Description Quant UnitsLB0077 Labour 0.20000 dayMT0049 turf including transportation 1.00000 sq.m

RW0238

Coefficient for per sq.m.

Code Description Quant UnitsLB0077 Labour 0.05000 dayMT0048 Grass Slips 100.00000 each

Collection and Preparation of materials (woody cutt ings 2-4 cm diameter and 60 cm length ) and staking them 3/4 of the cuttings in the soil

Planting of wildlings (including the collection if wildlings from the wild) and planting them in pit s ize 30 cm x 30 cm

Sodding on slopes with sods, eg. Lemon grass (30 cm s centre to centre), titepati (1 metre centre to ce ntre) in contour lines. The sods should be placed even closer to each other if the slope is greater than 25 degree

Turfing of embankment with 30x30 cm turfs and fixed to the ground with wooden pegs, if slope is greate r than 25 degrees

Grass slip planting on slopes ( random or in line) at 10 cm apart and 5 cm deep

Collection and Preparation of materials (woody cutt ings 2-4 cm diameter and 50 cm length ) and staking them 3/4 of the cuttings in the soil

Department of Engineering Services, MoWHS

Page 215: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Materials Coefficients ( Civil Works) - 2013 1

Lead in K.M

d

Average Speed

No of Trips in 8 hours

X

No of Kms Covered in

8 hours shift = 2xd + 8

Cost of Loading, Unloading and

Stacking. 4 Labourers for 8

Hours @ Nu. 178.76 Per day

Hire Charges of Truck with

fuel @ Nu. 4480 per day

Total Cost = total of 5 & 6

Cost per trip =

Col 7/col 3

Increase in cost per km in comparision to previous KM.

1 2 3 4 5 6 7 8 9

1 20 7.27 22.55 715.04 4480.0 5195.04 714.32

2 21 6.72 34.88 715.04 4480.0 5195.04 773.07 58.75

3 21.5 6.25 45.53 715.04 4480.0 5195.04 830.60 57.53

4 22 5.87 54.93 715.04 4480.0 5195.04 885.52 54.92

5 22.5 5.54 63.38 715.04 4480.0 5195.04 937.99 52.48

6 23 5.26 71.09 715.04 4480.0 5195.04 988.19 50.19

7 23.5 5.01 78.19 715.04 4480.0 5195.04 1036.24 48.06

8 24 4.80 84.80 715.04 4480.0 5195.04 1082.30 46.06

9 24.5 4.61 91.01 715.04 4480.0 5195.04 1126.48 44.18

10 25 4.44 96.89 715.04 4480.0 5195.04 1168.88 42.41

11 25.5 4.29 102.48 715.04 4480.0 5195.04 1209.63 40.75

12 26 4.16 107.84 715.04 4480.0 5195.04 1248.81 39.18

13 26.5 4.04 112.99 715.04 4480.0 5195.04 1286.51 37.70

14 27 3.93 117.96 715.04 4480.0 5195.04 1322.81 36.30

15 27.5 3.83 122.78 715.04 4480.0 5195.04 1357.79 34.98

16 28 3.73 127.47 715.04 4480.0 5195.04 1391.53 33.73

17 28.5 3.65 132.03 715.04 4480.0 5195.04 1424.08 32.55

18 29 3.57 136.49 715.04 4480.0 5195.04 1455.51 31.43

19 29.5 3.50 140.86 715.04 4480.0 5195.04 1485.87 30.36

20 30 3.43 145.14 715.04 4480.0 5195.04 1515.22 29.35

21 30 3.33 148.00 715.04 4480.0 5195.04 1558.51 43.29

22 30 3.24 150.70 715.04 4480.0 5195.04 1601.80 43.29

23 30 3.16 153.26 715.04 4480.0 5195.04 1645.10 43.29

24 30 3.08 155.69 715.04 4480.0 5195.04 1688.39 43.29

25 30 3.00 158.00 715.04 4480.0 5195.04 1731.68 43.29

DATA SHEET 1 - CARRIAGE OF MATERIALS BY MECHANICAL TRANSPORT BY HILL ROADS

Page 216: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

26 30 2.93 160.20 715.04 4480.0 5195.04 1774.97 43.29

27 30 2.86 162.29 715.04 4480.0 5195.04 1818.26 43.29

28 30 2.79 164.28 715.04 4480.0 5195.04 1861.56 43.29

29 30 2.73 166.18 715.04 4480.0 5195.04 1904.85 43.29

30 30 2.67 168.00 715.04 4480.0 5195.04 1948.14 43.29

31 30 2.61 169.74 715.04 4480.0 5195.04 1991.43 43.29

32 30 2.55 171.40 715.04 4480.0 5195.04 2034.72 43.29

33 30 2.50 173.00 715.04 4480.0 5195.04 2078.02 43.29

34 30 2.45 174.53 715.04 4480.0 5195.04 2121.31 43.29

35 30 2.40 176.00 715.04 4480.0 5195.04 2164.60 43.29

36 30 2.35 177.41 715.04 4480.0 5195.04 2207.89 43.29

37 30 2.31 178.77 715.04 4480.0 5195.04 2251.18 43.29

38 30 2.26 180.08 715.04 4480.0 5195.04 2294.48 43.29

39 30 2.22 181.33 715.04 4480.0 5195.04 2337.77 43.29

40 30 2.18 182.55 715.04 4480.0 5195.04 2381.06 43.29

Note :

1. No of trips in 8 Hrs Shift

x = 8/ ( a+1)where a = 2d/sd = distance/lead in KmS = Average Speed Per Hour1 hour is added for time spent for loading and unloading

2 Diesel Consumption of truck is assumed as 5 Km per litre for hill roads, hire charge of TATA LB 1612 = Nu. 4480.003. Consumption of Mobil is assumed as 1 litre for a run of 250 Km4. In col 4 : Distance covered in 8 hours includes 8 kms to cover additional distance normally covered by the truck to reach the quarry/crusher from place of halting5. Labour Cost as per BSR 2013 = Nu. 178.76 per day

Page 217: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Materials Coefficients ( Civil Works) - 2013 3

Lead in K.M d

Average Speed

No of Trips in 8

hours = x

No of Kms Covered in 8 hours shift = 2xd + 8

Cost of Loading, Unloading and Stacking. 4 Labourers for 8 Hours @Nu. 178.76 Per day

Hire Charges of Truck with fuel @ Nu. 4480 per day

Total Cost = total of 5 & 6

Cost per trip = Col 7/col 3

Increase in cost per km in comparision to previous KM.

Average increase in cost for 5 km dis., 5 to 10 km, 10 km to 20 km etc.

1 2 3 4 5 6 7 8 9 10

1 25 7.41 22.81 715.04 4480.0 5195.04 701.33

2 25.5 6.92 35.66 715.04 4480.0 5195.04 751.24 49.91

3 26 6.50 47.00 715.04 4480.0 5195.04 799.24 47.99

4 26.5 6.14 57.16 715.04 4480.0 5195.04 845.42 46.18

5 27 5.84 66.38 715.04 4480.0 5195.04 889.89 44.47

6 27.5 5.57 74.84 715.04 4480.0 5195.04 932.75 42.85

7 28 5.33 82.67 715.04 4480.0 5195.04 974.07 41.32

8 28.5 5.12 89.98 715.04 4480.0 5195.04 1013.94 39.87

9 29 4.94 96.85 715.04 4480.0 5195.04 1052.44 38.50

10 29.5 4.77 103.35 715.04 4480.0 5195.04 1089.64 37.19 39.95

11 30 4.62 109.54 715.04 4480.0 5195.04 1125.59 35.95

12 30.5 4.48 115.45 715.04 4480.0 5195.04 1160.37 34.78

13 31 4.35 121.12 715.04 4480.0 5195.04 1194.02 33.65

14 31.5 4.24 126.59 715.04 4480.0 5195.04 1226.61 32.59

15 32 4.13 131.87 715.04 4480.0 5195.04 1258.17 31.57

16 32.5 4.03 136.99 715.04 4480.0 5195.04 1288.77 30.60

17 33 3.94 141.97 715.04 4480.0 5195.04 1318.44 29.67

18 33.5 3.86 146.82 715.04 4480.0 5195.04 1347.22 28.78

19 34 3.78 151.56 715.04 4480.0 5195.04 1375.16 27.94

20 34.5 3.70 156.19 715.04 4480.0 5195.04 1402.28 27.13 31.26

21 35 3.64 160.73 715.04 4480.0 5195.04 1428.64 26.35

22 35.5 3.57 165.18 715.04 4480.0 5195.04 1454.25 25.61

23 36 3.51 169.56 715.04 4480.0 5195.04 1479.14 24.90

24 36.5 3.46 173.87 715.04 4480.0 5195.04 1503.36 24.22

25 37 3.40 178.11 715.04 4480.0 5195.04 1526.92 23.56

26 37.5 3.35 182.30 715.04 4480.0 5195.04 1549.85 22.93

27 38 3.30 186.43 715.04 4480.0 5195.04 1572.18 22.33

28 38.5 3.26 190.52 715.04 4480.0 5195.04 1593.93 21.75

29 39 3.22 194.56 715.04 4480.0 5195.04 1615.12 21.19

30 39.5 3.18 198.55 715.04 4480.0 5195.04 1635.78 20.66 23.35

DATA SHEET 2 - MECHANICAL TRANSPORTATION OF MATERIALS IN PLAIN ROADS

Page 218: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Materials Coefficients ( Civil Works) - 2013 4

Note :

1. No of trips in 8 Hrs Shift

x = 8/ ( a+1)where a = 2d/sd = distance/lead in KmS = Average Speed Per Hour1 hour is added for time spent for loading and unloading

3. Consumption of Mobil is assumed as 1 litre for a run of 250 Km

quarry/crusher from place of halting5. Average Speed is assumed as 30 kmph for hill roads and 50 kmph for plain roads.6. Labour Cost as per BSR -2013 is Nu. 178.76 per day

2 Diesel Consumption of truck is assumed as 7 km per litre for plain roads, Hire charge with fuel of TATA LB 1612 is Nu. 4480

4. In col 4 : Distance covered in 8 hours includes 8 kms to cover additional distance normally covered by the truck to reach the

Page 219: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Materials Coefficients ( Civil Works)- 2012 11

1 2 3 4 5 5 to 10 km 10 to 20 km 20 to 30 km

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 Lime, moorum, building rubbish 6 cu.m 6 cu.m per cu.m

2 Dry earth 6 cu.m 4.8 cu.m per cu.m

3 Manure or Sludge 6 cu.m 5.7 cu.m per cu.m

4 Excavated Rock 6 cu.m 3 cu.m per cu.m

5

Sand, stone aggregates of less than

40 mm size 5 cu.m 5 cu.m per cu.m

6

Stone aggregates of more than 40

mm size 5 cu.m 4.6 cu.m per cu.m

7 stone boulders 5 cu.m 4.25 cu.m per cu.m

8 bricks 2000 nos 2000 nos per 1000 nos

9 tiles 3000 nos 3000 nos per 1000 nos

10 cement 8 tonnes 8 tonnes per tonne

11 GI, CI Pipes 7 tonnes 7 tonnes per tonne

12 Concrete 7 tonnes 7 tonnes per tonne

13 steel 8 tonnes 8 tonnes per tonne

14 bitumen 4.5 tonnes 4.5 tonnes per tonne

15 timber 7.5 cu.m 7.5 cu.m per cu.m

cost per trip with lead from 1.0km to 5.0 km

DATA SHEET - Analyses of rates for carriage of Materials by Mechanical Transport for different materials

cost per trip with lead from 5 to 30

kms

Cost per

trip

rate per unit

col14/col 4

cost per trip as arrived from column 8 of datasheets 1

and 2

cost per trip as arrived from column 8

of datasheets 1 and 2

Sl.noCarrying

Capacity of

Truck per

trip

Net

quantity

payable

after

deduction

of voids unit of rate

Materials

Page 220: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works

Labour and Materials Coefficient (Civil Works) – 2013

Carriage of materials by manual labour including loading, unloading and stacking for lead less than 0.5 km

1. Normal Carrying capacity of selected building materials up to a lead of first 50 m

by 8 nos labourers in an 8 hour shift is as below:

a. Lime, moorum, building rubbish – 25 cum b. Earth – 25 cum c. Excavated rock – 25 cum d. Sand or stone aggregate of less than 40 mm size – 20 cum e. Stone aggregate of size 40 mm or more – 20 cum f. Soling stone – 18 cum g. Bricks – 9000 nos h. Brick tiles – 15000 nos

For carrying the above quantity of materials to every further lead of 50 m or part thereof upto a distance of 0.5 km within a shift of 8 hours approximately, 1.75 extra. Labourers would be required. Add 10% for stacking the quantity of materials conveyed in 8 hours shift

2. Normal Carrying capacity of selected building materials up to a lead of first 50 m

by 9.5 nos labourers in an 8 hour shift is as below: a. Stone blocks and other heavy materials like GI, CI pipes less than 100 mm

dia – 36 tonnes b. cement – 45 tonnes c. steel – 20 tonnes d. timber - 35 cum e. stone ware pipes 600 mm long

• 100 mm dia – 1785 m or 2975 nos • 150 mm dia – 1086 m or 1810 nos • 200 mm dia – 777 m or 1295 nos • 230 mm dia – 607.2 m or 1012 nos • 250 mm dia – 465 m or 775 nos • 300 mm dia – 327 m or 545 nos

f. RCC pipes, steel cylinder RC pipes, CI and unreinforced cement pipes 3.66 m long

• 100 mm dia – 1317.6 m or 360 nos • 125 mm dia – 1083.36 m or 296 nos • 150 mm dia – 933.3 m or 255 nos • 200 mm dia – 629.50 m or 172 nos

For carrying the above quantity of materials to every further lead of 50 m or part thereof upto a distance of 0.5 km within a shift of 8 hours approximately, 1.5 nos extra labourers would be required. Add 10% for stacking the quantity of materials conveyed in 8 hours shift

Page 221: Labour and Materials Coefficient (Civil Works) - 2013 · Labour and Materials Coefficient (Civil Works) - 2013 Foreword The Department of Engineering Services of Ministry of Works