Status Report – September 24, 2013 Presentation to the JCC Department of Public Works 1 Laguna Honda Hospital Replacement Program Remodel Project Highlights

Upload: others

Post on 21-Mar-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

Status Report – September 24, 2013

Presentation to the JCC

Dep

artmen

t of Pu

blic

Work

s

1

Laguna Honda Hospital Replacement Program

• Remodel Project Highlights

Page 2: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

Major AccomplishmentsLaguna Honda Hospital Replacement Program Bond

2

Remodel Project Accomplishments

1. Contract work is now completed. 2. Contractor completed work on Fire, Life, and Safety systems throughout the

renovated facility. Final test with OSHPD officials will occur this quarter.3. Construction in the Administration areas have been completed and approved for

occupancy by OSHPD officials. Laguna Honda staff has moved in.4. Simon auditorium has been completed.5. OSHPD approved electrical cutover plans, and permanent power of the existing

wings A & B has now been connected to power from the Pavilion building.6. The construction team is in communication with OSHPD officials on change

orders to the design of the emergency egress lighting in various areas of Simon Auditorium, Moran Hall, and other areas. We expect this work to be approved this quarter.

Page 3: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

Progress ScheduleLaguna Honda Hospital Replacement Program Bond

3

Remodel Schedule and Related Issues• The City has granted Turner’s request to extend Substantial Completion to

August 30, 2013, • OSHPD is in the process of reviewing and signing off completed work in the

renovated areas. Structural and plumbing work has been completed and signed off. Mechanical and electrical inspection is continuing.

• Contractors has completed all punchlist items. • The City and Stantec are currently in mediation regarding the Errors and

Omissions lawsuit filed in 2011. If a settlement is not reached, the lawsuit will proceed to court.

Page 4: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

Change Orders (Remodel)Laguna Honda Hospital Replacement Program Bond

4

Total to Date Thru CO #211Errors $ 750,077 Omissions $ 1,144,430 Site Conditions (Unforeseen Site Conditions) $ 10,669,033 City Request* $ 2,627,155 Client Request $ 101,071 OSHPD $ 5,397 Total $ 15,297,163

*Amount includes $1.3M for Phase 2 buyout

Page 5: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

Funding StatusLaguna Honda Hospital Replacement Program Bond

5

Page 6: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

Budget StatusLaguna Honda Hospital Replacement Program Bond

6

BUDGET STATUS

a b c=b/a d e=d/a

Initial BudgetRevised 

Budget #16

Expended/ Encumbered through 6/30/13

Expended/ Encumbered 

(by percentage)

Expended as of 6/30/13

Expenditures (by 

percentage) ForecastConstruction Cost:

Phase A ‐ Utility Modifications 2,460,095 10,051,447 10,051,447 100.00% 10,051,447 100.00% 10,051,447

Phase B ‐ Site Work & Demolition 2,143,361 7,282,914 7,282,914 100.00% 7,282,914 100.00% 7,282,914

Art Commision/Oyster Pt. Laundry/Construction Power 19,349,635 5,472,854 5,424,560 99.12% 5,379,514 98.29% 5,636,778Emergency Contract 80,000 80,000 100.00% 0 0.00% 80,000CM‐at‐Risk (Main Buildings) 229,345,602 366,000,000 365,645,084 99.90% 365,288,575 99.81% 366,000,000CM‐at‐Risk (Remodel) 58,000,000 55,751,614 96.12% 53,140,189 91.62% 57,065,000Site Work Package III 12,608,431 5,341,736 0.00% 0.00% 4,291,282Owner Controlled Insurance Program 17,323,400 17,355,029 100.18% 16,929,784 97.73% 17,500,000Phase C ‐ Construction 261,303,668 452,217,990 444,256,287 98.24% 440,738,062 97.46% 450,573,060

Phase D ‐ Hazardous Abatement Oversight (Wings C and H) 1,153,808 1,212,477 105.08% 1,192,641 103.37% 1,192,641

Phase E ‐ Hazardous Materials Abatement & Demolition of Clarendon Hall 12,827,128 4,233,928 2,516,184 59.43% 2,516,184 59.43% 4,233,928

Phase F ‐ Demolition Wings DEFGKLMO (moved budget to Phase C) 22,091,810

Program‐wide contingency (moved budget to Phase C) 8,395,146

1. Total Construction Cost (Phase A, B, C, D, E, F and Program‐wide Contingency) 309,221,207 474,940,087 465,319,309 97.97% 461,781,248 97.23% 473,333,990

2. Construction Services 77,378,793 107,731,967 109,949,208 102.06% 108,642,354 100.85% 109,338,064

Subtotal for Construction and Consultant Services 386,600,000 582,672,054 575,268,517 98.73% 570,423,602 97.90% 582,672,054

3. Assisted Living 15,000,000

Total Budget  401,600,000 582,672,054 575,268,517 98.73% 570,423,602 97.90% 582,672,054

LAGUNA HONDA HOSPITAL REPLACEMENT PROGRAM

AS OF JUNE 30, 2013

Page 7: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

Major AccomplishmentsLaguna Honda Hospital Replacement Program Bond

7

Page 8: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

May 2013 to September 2013Laguna Honda Hospital Replacement Program Bond

8

Page 9: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

May 2013 to September 2013Laguna Honda Hospital Replacement Program Bond

9

Page 10: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

May 2013 to September 2013Laguna Honda Hospital Replacement Program Bond

10

Page 11: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

May 2013 to September 2013Laguna Honda Hospital Replacement Program Bond

11

Page 12: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

May 2013 to September 2013Laguna Honda Hospital Replacement Program Bond

12

Page 13: Laguna Honda Hospital - SFDPH Replacement Project...Laguna Honda Hospital Replacement Program Bond 3 Remodel Schedule and Related Issues • The City has granted Turner’s request

QuestionsLaguna Honda Hospital Replacement Program Bond