Lahmeyer International 2013 Lahmeyer International 2013 PV-Greenfield in the Northern regions: Experiences in Consulting for Ghana’s public utility Holger Zebner, Lahmeyer International GmbH PDP Information Workshop: New Opportunities for Grid-connected Photovoltaic Solutions in Ghana: Market Segment and Potential Partners for German Industry Experts 10.12.2013, GIZ Representation, Berlin 1

Upload: vuongdiep

Post on 15-Dec-2016

226 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Lahmeyer International GmbH

Lahmeyer International 2013 Lahmeyer International 2013

PV-Greenfield in the Northern regions: Experiences in Consulting for Ghana’s public utility

Holger Zebner, Lahmeyer International GmbH PDP Information Workshop: New Opportunities for Grid-connected Photovoltaic Solutions in Ghana: Market Segment and Potential Partners for German Industry Experts 10.12.2013, GIZ Representation, Berlin

1

Page 2: Lahmeyer International GmbH

Lahmeyer International 2013 Lahmeyer International 2013

• Company Presentation • Typical Services • Selected Project References in Africa

Lahmeyer International and its Consulting in Africa

Page 3: Lahmeyer International GmbH

Lahmeyer International 2013

Water Supply &

Sanitation

Hydropower & Water

Resources

Energy

3

Company Data

Lahmeyer Group: 12 Affiliated Consolidated Companies

Foundation: 1966

Headquarter: Bad Vilbel, Germany

Employees (2012): 1560 (Group)

Turnover (2011): 147 million Euro (Group)

Sites: Company Sites and Subsidiaries in 21 Countries

Projects: In 165 Countries

Activity: Technical and economic planning and consulting services

Fields (Group):

Building & Transportation

Page 4: Lahmeyer International GmbH

Lahmeyer International 2013

Biomass & Waste

Wind Solar

4

Key Data Business Unit Renewables and Economics (BU2)

Lahmeyer History working in hydropower business since 50 years, in new and renewable energy

in Renewables: business since 25 years

Scope BU2: all non-traditional renewable energies: solar, wind, biomass&waste, geothermal

energy

Employees (2012): 59

Turnover (2012): 12 million Euro

Projects: In more than 60 Countries

Activity: Technical and economic planning and consulting services

Geothermal

Energy

Page 5: Lahmeyer International GmbH

Lahmeyer International 2013

Project Experience Worldwide

Lahmeyer Project

Lahmeyer Company

Local Office

Principal Business Areas

Projects in 165 countries

12 Lahmeyer affiliated consolidated companies

Company sites and subsidaries in 21 countries

Representatives in 15 countries

Page 6: Lahmeyer International GmbH

Lahmeyer International 2013

Range of Services

Betriebsphase

Feasibility Studies

Due Diligence

Conceptual Planning

Project Management and Quality Assurance

Planning, Tendering and Purchasing

Design Review

Operation and Maintenance Management

Construction and Erection Supervision

Training for Design, Project Management and Operation

Commissioning

Operation Phase Pre-Investment Phase Implementation Phase

Start of Operation

Market Analyses, Energy Economic Studies

Defects Liability Management

Option: Contract Award EPC

Rehabilitation

6

Detailed Design

Contract Management

Page 7: Lahmeyer International GmbH

Lahmeyer International 2013

Selected experiences in the region

7

Project Client

Renewable Energy Development Programme, Ghana Volta River Authority (VRA), Ghana

Feasibility Study on the 330 kV Riviera – Prestea Interconnection Reinforcement Project, Ghana, Côte d’Ivoire West African Power Pool (WAPP), Benin

Update of the Feasibility Study Interconnection Mali - Ivory Coast

Energie du Mali SA (EDM-SA)

Local Electrification Planning in the region of Ségou and Mopti, Mali

Agence Malienne pour le Développement de l’Energie

Domestique et de l’Electrification – AMADER

Master Plan for Rural Electrification of Mali (Plan Directeur d’Electrification Rurale du Mali - PDER), Mali Ministère des Mines, de l’Energie et de l’Eau –

Direction Nationale de l’Energie

Domestic Energy and Access to Basic Services in Rural Locations (PEDASB), Mali Agence Malienne pour le Développement de l’Energie

Domestique et de l’Electrification, AMADER

Implementation of Katsina Wind Farm, Nigeria Vergnet S.A., France

Wind Measurement and Windmapping, Nigeria

Bilfinger Berger AG, Germany

Connection of the 10 MW Wind Farm of Katsina to the National Grid of Nigeria Vergnet S.A., France

Feasibility Study for integrated Oil Palm Plantation and Biodiesel Plant, Nigeria

Nigerian National Petrol Cooperation - NNPC

Bumbuna HEP, Phase 2, Sierra Leone

Desert Lion Partners

Teak Wood Sawmill and Power Plant, Benin Nickel Saw Mills, Germany

Page 8: Lahmeyer International GmbH

Lahmeyer International 2013 Lahmeyer International 2013

• Contents • Timeline • Targets • Participants • Achievements

Renewable Energy Development Programme (REDP) of Volta River Authority (VRA)

Page 9: Lahmeyer International GmbH

Lahmeyer International 2013

Background: Electricity system of Ghana

9

The public institutions in the electricity sector: • Minstry of Energy and Petrolium • Energy Comission • GridCo

– System control via national dispatch centre, Tema – Transmission system operator

• VRA – Former all-inclusive utility – Now main generating company (~85%) – Distributor in Northern Regions (NEDCo) – Head office in Tamale

• Energy Company of Ghana (ECG) – Distributor in all regions except Northern Regions – Headquarter in Accra

Grid map by GridCO, Ghana

Page 10: Lahmeyer International GmbH

Lahmeyer International 2013

Background Info VRA

10

• The tradition full-services utility of the country.

• Remained as generation company after the unbundling of the electricity sector

• Operates most larger power plants (water dams, thermal units)

• The slogan: Setting the standard for public sector excellence in Africa

• Means: – Safety during works – Diligent maintenance and nothing

left in disorder – Responsibility for employees and the

energy supply of the nation

Page 11: Lahmeyer International GmbH

Lahmeyer International 2013

Renewable Energy Development Programme (REDP) at a glance

• Since 2010, VRA intensively develops renewable energy projects country-wide based on a formulated policy with the objective of promoting sustainable power generation through renewable energy resources.

• Referring to this policy, the company has chosen to develop – a wind farm project with a capacity of up to 150 MW and – a solar power project with a capacity of up to 10 MW

11

Page 12: Lahmeyer International GmbH

Lahmeyer International 2013

REDP Consultancy at a glance

• Wind Energy – Assistance in wind measuring programme; – review of feasibility studies and wind power feasibility appraisal; – design review; – contract advise; – construction supervision

• Solar Energy: – Design review (PV); – preparation of a CSP feasibility study; – pre-design and tender document preparation; – construction supervision,

• CDM facilitation for the wind and the PV solar projects; • RE Masterplan: Renewable energy development and integration planning; • Training the staff in renewable energies

12

Page 13: Lahmeyer International GmbH

Lahmeyer International 2013

REDP Consultancy for Solar Power

• PV – Basic design, – Preparation of tender documents, evaluation of tenders, assistance during contract

negotiations, compilation of contract documents, – Review and approval of drawings, – Project cost and time schedule control, – Site quality assurance, – Transfer of know-how and workshop, – Supervision of construction, erection and commissioning and – Services during warranty period.

• CSP – Assessment of technical options: Solar field; Site assessment; Solar resource. – Plant design including plant performance, economic analysis, – procurement and construction scheme.

13

Page 14: Lahmeyer International GmbH

Lahmeyer International 2013 Lahmeyer International 2013

• Site and design • Execution • Impressions of the plant

REDP SPP1: Ghana‘s first MW-sized green-field PV plant at Navrongo, UE

Page 15: Lahmeyer International GmbH

Lahmeyer International 2013

The project in brief

• Location: East of Navrongo, UER • Project development completely by VRA • Capacity: 2.543 MWp

• Tendered in early 2011 • Awarded to CWP, China, in February 2012

• Construction started in March 2012 • Commissioning in February 2013 • Commercial operation since April 2013

• 6 months of joint operation with Contractor • Now fully under control of VRA

15

Map by Openstreetmap contributors

Page 16: Lahmeyer International GmbH

Lahmeyer International 2013

Factory Acceptance and review

16

• Large utility companies are used to follow established processes

• Such procedures origin from implementation of complex large scale power plants

• Usually, extensive testing and design review is included

• But is this applicable in PV projects? • Example:

– Do we always need a Factory Acceptance Test?

– Quality can be assured by sending modules to an external lab or testing on-site!

Page 17: Lahmeyer International GmbH

Lahmeyer International 2013

Construction

17

Page 18: Lahmeyer International GmbH

Lahmeyer International 2013

Plant facilities

18

Page 19: Lahmeyer International GmbH

Lahmeyer International 2013

Control building at inauguration

19

Page 20: Lahmeyer International GmbH

Lahmeyer International 2013

Solar field

20

Page 21: Lahmeyer International GmbH

Lahmeyer International 2013

Solar field

21

Page 22: Lahmeyer International GmbH

Lahmeyer International 2013

Inverter room

22

Page 23: Lahmeyer International GmbH

Lahmeyer International 2013

Switchgear and internal roads

23

Page 24: Lahmeyer International GmbH

Lahmeyer International 2013

Control room

24

Page 25: Lahmeyer International GmbH

Lahmeyer International 2013

On-site operation supervision

25

Page 26: Lahmeyer International GmbH

Lahmeyer International 2013

Cleaning of modules

26

Page 27: Lahmeyer International GmbH

Lahmeyer International 2013 Lahmeyer International 2013

• Sites • Design • Costs and project characteristics

REDP SPP2: 2 PV plants in UWR with a total capacity of 12MWp

Page 28: Lahmeyer International GmbH

Lahmeyer International 2013

Site Information

28

• Northern Regions • Good GHI • Savannah

• Access • 1 ½ days of travel from South • 80% tarred roads

• Infrastructure • 34.5kV grid

(NEDCo) • Mobile telecom

• Financed by KfW • Engineering and Consultancy

by Lahmeyer International

Map by Nations Online Project

GHI map of Africa by Solargis.info

Page 29: Lahmeyer International GmbH

Lahmeyer International 2013

Site Information: Kaleo

29

Page 30: Lahmeyer International GmbH

Lahmeyer International 2013

Site Information: Lawra

30

Terrain profile by Google Earth

Imagery: Google Earth and providers

Page 31: Lahmeyer International GmbH

Lahmeyer International 2013

Basic Design: Concept

Characteristics: • Failure resistance by using proven components, set-ups and modularity • Well adapted to site conditions • Planned for remote operation but allowing local control • Employment of local staff for low-level activities during operation • Challenges

– Remote SCADA integration – Interconnection to single-feeder MV grid Load flow analysis and assessment of short circuit conducted The MV network can absorb the generation units and voltage stays within allowed limits.

31

Overall goal – Reliable energy output – O&M friendliness

Page 32: Lahmeyer International GmbH

Lahmeyer International 2013

Basic Design: Plant layout

32

Electrical layout • 1MWp blocks • Distributed inverters • SCADA ring • Outdoor switchyard

Civil layout • Central alley & maintenance ways • Technical area • External margins • Fence • Lights

Page 33: Lahmeyer International GmbH

Lahmeyer International 2013

Basic Design: Electrical system

33

Electrical • Modular • Straight:

240V 34.5 kV • Auxiliary systems • Monitoring &

control

Page 34: Lahmeyer International GmbH

Lahmeyer International 2013

Basic Design: Technical area for infrastructure

34

Infrastructure • Control Building • Gate house • Parking • Borehole • Waste disposal • Sewage

Page 35: Lahmeyer International GmbH

Lahmeyer International 2013

Basic Design: Technical room and outdoor switchyard

35

• Control & metering • Workshop & office • Auxiliary power: hybrid supply via trafo, backup, PV • Spare parts & workshop • Facilities

Page 36: Lahmeyer International GmbH

Lahmeyer International 2013

Basic Design: SCADA integration & grid connection

36

Page 37: Lahmeyer International GmbH

Lahmeyer International 2013

Expected cost share and commercial set-up

• Expected installation price similar typical to typical PV greenfield installations but the contract will include interconnection works, SCADA integration, O&M facilities and training amongst others.

• O&M – To be conducted by VRA – Contractor to provide remote support

• Contract model – FIDIC Yellow Book – VRA Engineering Services as Engineer

• Time Line – Award of Contract by end of Q2/2014 – Time for Completion: 11 months

Not like to typical investor driven projects Plants are to be regarded as part of the national

energy infrastructure!

37

Page 38: Lahmeyer International GmbH

Lahmeyer International 2013 Lahmeyer International 2013

• PQ SPP2 • Further programmes and projects

Outlook: What business opportunities can we expect in the mid-term?

Page 39: Lahmeyer International GmbH

Lahmeyer International 2013

SPP2: Tendering Procedure

Activity Duration Target date (estimate)

Estimated time frame for Prequalification Process

Publication of Prequalification Document 12.01.2014

Envisaged Closing 30 11.02.2014

Evaluation by VRA, Engineer and KfW 21 04.03.2014

Notice to qualified Applicants by VRA 5 09.03.2014

Estimated time frame for Tender Process:

Release of Tender Documents to pre-qualified Applicants

15 24.03.2014

Envisaged Closing 45 08.05.2014

Evaluation by VRA, Engineer and KfW 30 07.06.2014

Notice to qualified Applicants by VRA and issue of Letter of Award (estimate)

5 12.06.2014

39

Page 40: Lahmeyer International GmbH

Lahmeyer International 2013

SPP2: Pre-Qualification

40

Technical Criteria • Special key technical references:

– 1 EPC project of size larger than 1 MWp completed or under contract by a public authority, utility, concessionaire or governmental institution

– 3 projects executed outside the country of origin – 1 project executed in Africa – 1 project executed in tropical climate conditions between geographical latitude of 23 Degree

North and 23 Degree South. • Other technical criteria:

– The proficiency in English of the key staff shall be proven by a corresponding certificate to be submitted together with the Tender Documents.

– HSE procedures, quality and environmental management certifications are a must

Page 41: Lahmeyer International GmbH

Lahmeyer International 2013

SPP2: Pre-Qualification

41

Financial Capabilities • Able to back the guarantees

– Tender Security – Performance Security (Financial) – Technical Guarantees: Delay Liquidated Damages & Performance Liquidated Damages

• Financial strength necessary to carry out the obligations under the EPC contract Cash-Flow • Have a proven (audited) minimum annual turnover

Page 42: Lahmeyer International GmbH

Lahmeyer International 2013

Further options for co-operation with VRA

42

• Joint development & implementation of projects and plant • Support in energy management and contracting for distributed generation • Energy efficiency initiatives and network upgrade…

Page 43: Lahmeyer International GmbH

Lahmeyer International 2013

Thanks for your attention! I am looking forward to your follow-up communcation!

Contact Name Holger Zebner Position Consultant for Solar Power Plants Department Renewable Energies Tel.: +49 (0) 6101 / 55-1465 Fax: +49 (0) 6101 / 55-2101 Email [email protected]

Lahmeyer International GmbH, Friedberger Str. 173, 61118 Bad Vilbel, Germany