INSPECTION & TEST PROCEDURES1. Visual and Mechanical Inspection
– Inspect physical and mechanical condition.
– Inspect anchorage, alignment and grounding.
– Prior to cleaning, perform as-found tests.– Clean unit.– Verify correct blade/contact alignment &
penetration, travel stop and mechanical operation.
– Verity fuses are support properly, clean contact surfaces and fuse clip tension.
INSPECTION & TEST PROCEDURES cont’d
– Inspect bolted electrical connections for high resistance by: use of a DLRO meter and by checking torque with a calibrate torque wrench.
– Verify phase-barrier mounting is intact.– Verify correct operation of control
devices & interlocks.– Use appropriate lubrication on moving
current-carrying parts and on moving or sliding surfaces.
– Perform as-left tests.
INSPECTION & TEST PROCEDURES cont’d
1. Electrical tests.– Measure contact resistance across the
contacts and fuse holders.– Perform insulation-resistance tests:
• Phase to Phase• Phase to GroundWith the contacts closed & open.
– Perform primary or secondary injection testing.
Vacuum Breaker Inspection Testing
The same procedures as above with the addition of the following:
• Perform a Hi-Pot test or a vacuum bottle integrity test across each vacuum bottle, with the contact in the open position.
Inspection and Testing Procedures
Perform the same test as performed on the air and vacuum breakers with the exception of:
1. Visual and Mechanical Inspection
• Inspect and service the operating mechanism.• Take a sample for gas analysis• Leak detection • Test the alarms, pressure & limit switches, gas
charge if necessary.• Slow close & open the breaker to allow for
inspection of the contact alignment, binding or other operations.
Inspection and Testing Procedures
1. Electrical testing.– DLRO (contact resistance)– Insulation testing (Megger test)– Perform a contact/pole resistance test.– Perform a trip and close test with the
control and a trip test with the relays.– Perform a power factor test on each pole
(open and closed) and each bushing.
Customer: Job# Date:Location: Sub ID:Make: Amp: Class:Ser #. CHARGE
CLOSE TRIP
AS FOUND
A phase B phase C phase
AS LEFT
A phase B phase C phase
AS FOUND AS LEFT
Breaker Open Breaker ClosedA phase A phase A phase A phaseB phase B phase B phase B phaseC phase C phase C phase C phase
AS FOUND AS LEFT
Breaker Open Breaker ClosedA phase A phase A phase A phaseB phase B phase B phase B phaseC phase C phase C phase C phase
Tested by: Date:Notes:
INSULATION RESISTANCE Readings in Megga-ohms
DC HIPOT TEST (AS LEFT ONLY) 22KV (1) MIN.
Breaker Open Breaker Closed
CONTACT RESISTANCE Readings in Micro-ohms
Breaker Open Breaker Closed
TAW Technical Field Services
Tel: 863-686-5667Fax: 863-683-9806
Lakeland, FL 338105070 Swindell Road
ON-SITE MEDIUM VOLTAGE TEST REPORT
Control Volts:
Addition Equipment to be Maintained
• Protective Relay calibration• Transformers testing• Transformer oil analysis• Surge/Lighting Arresters testing• Load Break Disconnect Switch• GOAB Switch inspection• Infrared Thermography
Transformer Testing• Transformer oil
analysis• Power factor testing
(Doble)• Insulation Resistance
(megger)• Turns to Turns Ratio
(TTR)• Contact Resistance • De-hydrate and De-
gas