landscape works specification

112
SLR Ref: 620.12664.00300-R01 Version No: -v0.1 March 2019 LANDSCAPE WORKS SPECIFICATION PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD Prepared for: Orchard (Pebble Creek) Developments Pty Ltd

Upload: others

Post on 23-Feb-2022

15 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: LANDSCAPE WORKS SPECIFICATION

SLR Ref: 620.12664.00300-R01 Version No: -v0.1 March 2019

LANDSCAPE WORKS SPECIFICATION PEBBLE CREEK DEVELOPMENT

ENTRY ROAD AND MOUNTAIN RIDGE ROAD

Prepared for:

Orchard (Pebble Creek) Developments Pty Ltd

Page 2: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 2

PREPARED BY

SLR Consulting Australia Pty Ltd ABN 29 001 584 612 Level 2, 15 Astor Terrace Spring Hill QLD 4000 Australia (PO Box 26 Spring Hill QLD 4004) T: +61 7 3858 4800 E: [email protected] www.slrconsulting.com

BASIS OF REPORT

This report has been prepared by SLR Consulting Australia Pty Ltd (SLR) with all reasonable skill, care and diligence, and taking account of the timescale and resources allocated to it by agreement with Orchard (Pebble Creek) Developments Pty Ltd (the Client). Information reported herein is based on the interpretation of data collected, which has been accepted in good faith as being accurate and valid.

This report is for the exclusive use of the Client. No warranties or guarantees are expressed or should be inferred by any third parties. This report may not be relied upon by other parties without written consent from SLR.

SLR disclaims any responsibility to the Client and others in respect of any matters outside the agreed scope of the work.

DOCUMENT CONTROL

Reference Date Prepared Checked Authorised

620.12664.00300-R01-v0.1 13 March 2019 Chloe Wegener Dean Butcher Dean Butcher

Page 3: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 3

CONTENTS 1 GENERAL ITEMS ...................................................................................................... 4

2 PRELIMINARIES ....................................................................................................... 8

3 EARTHWORKS AND DEMOLITION ........................................................................... 15

4 ENVIRONMENTAL .................................................................................................. 16

5 CONCRETE ............................................................................................................. 23

6 BLOCKWORK ......................................................................................................... 30

7 TIMBERWORK ....................................................................................................... 38

8 METALWORK ......................................................................................................... 45

9 STONEWORK ......................................................................................................... 47

10 SOFTWORKS .......................................................................................................... 48

11 COMPLETION – MAINTENANCE (POST PRACTICAL COMPLETION) ............................ 69

DOCUMENT REFERENCES

APPENDICES

Appendix A Materials and Finishes Schedule Appendix B Dulux Render Finish Appendix C Cutex Timber Stain and Oil Finish Appendix D Dulux Coloured Timber Finish

Page 4: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 4

1 GENERAL ITEMS

1.1 THE PROJECT GENERALLY

Pebble Creek Development, Entry Road and Mountain Ridge Road at 230 Mountain Ridge Road and 54 Rose Almond Street, South Maclean Described as lot 6 on RP193185 and Lot 9 on SP203507.

1.1 SCOPE

The general scope of work includes the hard and soft landscape works to the following areas:

• On-site works

• Off-site Council land including; road verges, public footpath and access ways, vegetated embankments.

The Contractor will be responsible for the construction of all of the landscape works to the above works as outlined on the drawings.

1.1.1 Site Visit

The Contractor is advised to visit the site to satisfy themselves as to local conditions, accessibility, storage space, the full extent and character of the works and the site, the nature of the ground, the level of the sub-soil water, the supply of materials and water and the execution of the contract generally. No claim will be allowed for any alleged inadequacy of the description herein. Site visits may be made by arrangement with the Supervising Officer.

1.1.2 Description of the Works

The work will comprise but not be limited to the following items:

• Removal of existing vegetation as required;

• Spreading of ameliorated topsoil and subsoil;

• Earthworks to meet proposed levels;

• Final trimming of earthworks for planted, grassed and hardscape areas;

• Subsoil and surface drainage in landscaped areas;

• Construction of rendered and stone faced block walls;

• Supply and installation of feature recycled timbers and acoustic fencing;

• Cultivation and preparation of mulched garden areas;

• Supply and spreading of organic mulches;

• Certification, Supply and installation of AS 2303:2015 compliant plant material;

• Preparation and laying of grassed areas;

• Maintenance of softscape and hardscape.

Page 5: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 5

1.1.3 The Program

Landscape works for the project are to be completed by 1st September 2019. Landscape Construction start date TBC.

1.1.1 The Drawings

The Contractor shall familiarise themselves with the contract drawings, the following specification and any related engineering listed under section 1 of this specification before tendering as no claim in respect of lack of knowledge of these will be entertained.

This documentation covers all work associated with the construction of Soft and Hard Landscape Works for a Fixed Price Contract and shall be read in conjunction with the following drawings and specifications.

1.1.4 Landscape Drawings The Contractors Subcontractor shall familiarise themselves with the relevant Australian Standards referred to in the specification and ensure that any subsequent amendments and additions are adhered to. The drawings to accompany this specification are: • 620.12664.00300- 100 Coversheet

• 620.12664.00300- 101 Legend

• 620.12664.00300- 102 Plant Schedule

• 620.12664.00300- 103 Safety in Design

• 620.12664.00300- 104 Safety in Design

• 620.12664.00300- 300 Landscape Plan

• 620.12664.00300- 301 Landscape Plan

• 620.12664.00300- 302 Landscape Plan

• 620.12664.00300- 303 Landscape Plan

• 620.12664.00300- 304A/304B Landscape Plan

• 620.12664.00300- 305A/305B Landscape Plan

• 620.12664.00300- 306A/306B Landscape Plan

• 620.12664.00300- 307 Landscape Plan

• 620.12664.00300- 308 Landscape Plan

Page 6: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 6

• 620.12664.00300- 309 Landscape Plan

• 620.12664.00300- 310 Landscape Plan

• 620.12664.00300- 311 Landscape Plan

• 620.12664.00300- 800 Landscape Details

• 620.12664.00300- 801 Landscape Details

• 620.12664.00300- 802 Landscape Details

• 620.12664.00300- 803 Landscape Details

• 620.12664.00300- 804 Landscape Details

• 620.12664.00300- 805 Landscape Details

• 620.12664.00300- 806 Landscape Details

• 620.12664.00300- 807 Landscape Details

• 620.12664.00300- 808 Landscape Details

• 620.12664.00300- 809 Landscape Details

• 620.12664.00300- 810 Landscape Details

• 620.12664.00300- 811 Landscape Details

• 620.12664.00300- 812 Landscape Details

• 620.12664.00300- 813 Landscape Details

• 620.12664.00300- 814 Landscape Details

Page 7: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 7

1.2 RELEVANT PARTIES

The Principal

Orchard (Pebble Creek) Development Pty Ltd PO Box 9094, G.C.M.C 9726 Steve Korn PH: 0412 172 998

Electrical Engineers

Robin Russell 204/6 Babarra Street Stafford QLD 4053 Steve Holland PH: 0438 619 884

Civil Contractor (Principle Contractor)

CCA Winslow 1587 Ipswich Road, Rocklea QLD 4106 Craig Timmins PH: 0431 627 762

Structural Engineers

Glynntucker Consulting Engineers PO Box 8284 Woolloongabba Brisbane QLD 4102 Shane Hull PH: (07) 3839 7238

Superintendent

SLR Consulting Level 2, 15 Astor Terrace, Spring Hill QLD 4000 Chloe Wegener PH: 0424 112 209

Civil Engineers

Peak Urban PO Box 1344, Buddina QLD 4575 Troy Schultz PH: 0488 124 478

Landscape Architects

SLR Consulting Level 2, 15 Astor Terrace, Spring Hill QLD 4000 Chloe Wegener (Project Manager) PH: 0424 112 209

Dean Butcher PH: 0438 851 096

Josh Clark PH: 0411 863 862

Landscape Lighting Engineers

Webb Australia Group PO Box 1005 Toowong QLD 4066 Rob Smith PH: 0438 646 688

Page 8: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 8

2 PRELIMINARIES

2.1 GENERAL

2.1.1 Directions

Directives, instructions and the like given in this specification, whether or not they include the expression, ‘the Contractor shall’ or equivalent, shall be deemed to be given to and accepted by the Contractor, unless otherwise stated in the Contract.

2.1.2 Publicity

Do not issue any information, publication document or article for publication concerning the project in any media without prior approval of Orchard (Pebble Creek) Development Pty Ltd. Refer to Orchard (Pebble Creek) Development Pty Ltd regarding any enquiries concerning the project from any media.

2.1.3 Advertising

Do not erect or display any signs or advertising other than an approved signboard.

2.1.4 Relations with Others

During the course of the Contract other works and operations within the Contract area may be in progress. Ensure that these other works and operations are not affected in any way by operations under this Contract.

2.1.5 Subcontractors Site Area

The Subcontractors access onto and around the site, and the use of the site for temporary works and constructional plant, include working and storage areas, locations of offices, workshops, sheds, roads, parking and the like, shall be restricted to those areas shown on the drawings or approved by the Contractor.

2.1.6 Site Meetings

Site meetings attended by the Contractor, appropriate sub-contractors and the Principle Contractor shall be held throughout the duration of the Contract at a frequency determined by agreement between the Superintendent and the Contractor. Keep minutes of such meetings and provide copies to each party within three working days after each meeting.

2.2 CONSTRUCTION

Figured dimensions shall take precedence over scale measurements and large scale drawings over small scale. Unless otherwise specified the Drawings and Specification shall include everything reasonable for the proper and entire completion of the work, notwithstanding any omission in the Specification or Drawings. Verify discrepancies between Specification and Drawings with the Superintendent before proceeding with the particular work. Failure to do so will not be taken as a reason to claim for extra work.

Page 9: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 9

2.3 TRADE PERFORMANCE

The Contractor shall be a member of the Landscape Industries' Association in their state and a certified/specialist rehabilitation contractor in their state as applicable within the contracted works.

2.4 PROTECTION REQUIREMENTS

The Contractor shall ensure all subcontractors are aware of the required protection measures.

2.4.1 Protection of Public and Private Services

The Contractor's attention is drawn to the fact that certain existing underground services are present on the site. The position of such services will be indicated on drawings provided by the Superintendent. The Contractor must allow for carrying out any exploratory work required to ascertain the exact position of such existing services and for taking all necessary precautions during excavations or other operations to avoid damage to services.

The Contractor shall protect existing services and shall be held responsible for ensuring that no damage is caused to any existing pipes, ducts, sewers, gas, water and electricity services mains, NBN, fibre optic or installations, telephone cables and overhead cables. Any such damage shall be reported immediately and the necessary repairs carried out at the Contractor's expense.

Where any portion of the works is close to, across or under any existing or new apparatus of public utilities or other parties, the Contractor shall protect, plate over, temporarily support and work around, over and under or adjacent to all apparatus in the manner designed to avoid damage, leakage, and danger, and to ensure uninterrupted operations all in accordance with the requirements laid down by the Statutory Authority or owner concerned.

Should any leakage or damage be discovered, the Contractor shall at once notify the Superintendent and Statutory Authority, and the Contractor shall afford every facility for the repair or replacement of the apparatus affected.

2.4.2 Fire Ants

Under the Fire Ant Eradication Program and the Plant Protection Regulation (2002) ensure that Fire Ants and Fire Ants eggs, do not enter the site via equipment, machinery, materials and or plant stock. It is the Contractors responsibility to ensure that they check the latest Fire Ant mapping on line, through the Department of Agriculture and Fisheries (DAF) website, to ensure they understand the most recent extents and movement restrictions.

The Contractor must have either an Approved Risk Management Plan (ARMP) and or have an Inspector Approval (IA), both through the BioSecurity Queensland. All inspections must be diarized and must be available upon request. If the Contractor requires further information regarding Fire Ants, it is their responsibility to contact BioSecurity Queensland to determine their obligations.

In the instance that Fire Ants are noted on site contact the Superintend immediately.

2.4.3 Fire Protection

Light no Fires.

Page 10: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 10

2.4.4 Trucking

Convey soils, earth, sand, loose debris and the like to or from the site in a manner that will prevent dropping of materials on streets, public and private areas. Cover all loads with taut heavy-duty purpose fitted tarpaulins to ensure no loss of load or dust. Contractor to ensure that they comply with all cover you load laws and regulations in the relevant state. Ensure that the wheels, tracks and body surfaces of all vehicles and plant leaving the site are free of mud and that mud is not carried onto adjacent paved streets or other areas. It is the Contractors responsibility to ensure that all roads, pathways and driveways are free of mud, waste and landscape debris throughout the duration of the contract. The Contractor shall protect, maintain and clean any roads, pathways and driveways throughout the duration of the contract at their own expense as required or directed by the Superintendent.

2.5 QUALITY AND STANDARDS

This section relates to Quality Control and is applicable to all landscaping.

2.5.1 Standards

The Contractor shall familiarise themselves and their operatives with the relevant Australian Standards referred to in this specification and any subsequent revisions thereof. These standards shall be the edition last published.

2.5.2 Good/ Best Practice

Where and to the extent that materials, products and workmanship are not fully detailed or specified they are to be:

• Of a standard appropriate to the Works and suitable for the purposes stated in or reasonably to be inferred from the project documents.

• In accordance with good Landscape/Horticultural practice.

2.5.3 General Quality of Products/ Materials

Ensure suppliers are familiar with relevant specification clauses and understand constraints and particular requirements of the project.

Products to be new unless otherwise specified.

For products and materials specified to an Australian Standard obtain certificates of compliance from manufacturers when requested by the Superintendent.

Ensure that the whole quantity of each product and material required to complete the work is of consistent kind, size, quality and overall appearance.

If materials are prone to deterioration or have a limited shelf life, order in suitable quantities to a programme and use in appropriate sequence.

Page 11: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 11

2.5.4 Checking Compliance of Products/ Materials

Check all delivery tickets, labels, identification marks and, the goods themselves to ensure that all products comply with the project documents. Where different types of any product are specified, check to ensure that the correct type is being used in each location. In particular, check that: -

All stock has been adequately protected for loading and in transit. It is the Contractor’s responsibility to ensure that all material arrives to site damage free. The Contractor shall refuse any damaged or defective goods that are transported or delivered to site by another party. Once the Contractor accepts goods on site they agree to take full responsibility of all aspects of the delivered goods.

The sources, types, qualities, finishes and colours are correct, and match any approved samples and or the landscape specification.

The correct species, cultivars, pot sizes, plant height, girth or spread have been supplied for each consignment from the supplier.

All materials should be clean, undamaged and otherwise in good condition.

Where appropriate protective covers should be intact with unbroken seals.

2.5.5 Protection of Products/ Materials/ Stock

Ensure adequate provision is made for the protection and storage of deliveries. In particular ensure that: -

Supplies are delivered in relation to programme; materials which may deteriorate with storage must not be stock-piled on site.

Adequate and appropriate provision is made for storage prior to deliveries arriving on site. All materials in storage are to be suitably protected from physical damage and extremes of weather and to minimise hazards persons, materials and equipment. Keep storage areas neat and tidy.

Do not use roads, driveways, paths hard standings and the like forming part of the works for access or storage unless prior written approval has been given.

The Contractor shall take the appropriate security measures on site to secure all goods stored or stockpiled on site. Any damaged or stolen good shall be replaced at the Contractors expense.

2.5.6 Suitability of Previous Work and Conditions

Before starting each new type of section of work, ensure that: -

Previous, related work is appropriately complete, in accordance with the project documents, to a suitable standard and in a suitable condition to receive the new work.

All necessary preparatory work has been carried out, including provision for services and access.

The environmental conditions are suitable, particularly that the weather and ground conditions are appropriate to the operation. Seasonal constraints are set out at the beginning of each operation within this specification.

Page 12: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 12

Remove all surplus materials, spoil, rubbish and litter from landscape areas as work progresses. Leave site in a clean and tidy condition, with soil/mulch swept off hard surfaces at the end of each and every working day.

2.5.7 General Quality of Workmanship

Operatives must be appropriately skilled and experienced for the type and quality of work and familiar with the terms of the specification.

Inspect products/materials/stock carefully before use and reject any which are defective.

Use products/materials only in the method and for the purpose recommended by the manufacturer.

Ensure appropriate quantities are utilized; provide adequate measures for mixing and spreading of all products or materials.

Set out components or stock to ensure correct positioning and spacing’s are achieved.

Protect finished work from subsequent operations and interference by others as project progresses.

2.5.8 Samples/ Approvals

Where approval of products or materials is specified submit samples or other evidence of suitability.

Do not confirm orders or use materials until approval of samples has been obtained.

Retain approved samples in good, clean condition on site for comparison with products and materials used in the Works. Remove when no longer required.

General - Inspection by the Superintendent must not be taken as approval of materials, products or work unless the Inspecting Officer confirms in writing his express approval.

Where the Contract requires the Contractor to provide samples, they shall be solely responsible for the consequences of delay resulting from failure to allow reasonable time for the assessment and approval of the samples, or from the rejection of samples which do not comply with the specification.

2.5.9 Provision of Samples

Items for which samples are required shall be in accordance with an approved sample, or within a range defined by approved samples, otherwise such items may be rejected. Do not order or fabricate such items until the relevant sample has been approved. Allow adequate time for the assessment and approval of samples.

2.5.10 Proprietary Items

A proprietary item shall be any item identified by graphic representation on the drawings, or by naming one or more of the following: manufacturer, supplier, installer, trade name, brand name, catalogue or reference number and the like.

Page 13: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 13

If the Contractor offers an alternative item having the required properties the item may be accepted at the Superintendents reasonable discretion. Any costs difference shall be treated as a variation and determined by the Superintendent as part of the approval process. Any technical information shall be forwarded to the Superintendent for information if requested.

2.5.11 Supervision and Inspections

Supervise the whole of the landscape works and provide a competent general foreman authorised to receive and carry out instructions from the Superintendent.

If the specification gives notice of inspection to be given in respect of any part of the work under the Contract, that part of the work shall not have further work placed thereon or be covered up or put out of view without the prior approval of the Superintendent. A minimum 2 working days’ notice shall be given to the Superintendent prior to inspection of such works. No claim for delay shall arise from the giving of insufficient or unreasonably short notice.

• Pre-inspection of the weed extents prior to treatment (as required)

• Set out of planting and guarding.

• Erosion and sedimentation controls (if required)

• Set out of pathways prior to construction

• Set out of concrete footings to entry wall

• Stone work following construction of sample panel and prior to finishing

• Set out of fencing

• Prior to backfilling planting areas with sub-surface drainage in place and connected to stormwater drainage

• Planting, staking and tying completed

• Turfing and seeding completed

• Upon completion of establishment period

2.6 TESTING

The Superintendent may require materials, goods, work or samples thereof to be tested to ensure that they comply with the standards specified, or with samples submitted. Where such tests indicate that the required standards have not been achieved, the costs of testing and of any subsequent re-testing are to be borne by the Landscape Contractor.

Any sampling shall be carried out by an authority registered with the National Association of Testing Authorities Australia (NATA) to perform the specified sampling and testing

2.7 WARRANTIES

Warranties or guarantees specified shall name Orchard (Pebble Creek) Development Pty Ltd as warrantee and shall be furnished by the warrantor direct to Orchard (Pebble Creek) Development Pty Ltd.

Page 14: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 14

2.8 INSURANCES

Prior to the contracted works commencing onsite the Contractor is to submit the following documents to the Superintendent:

• Insurance of all works under the contract in accordance with clause 16 of AS4000- 1997

• Public Liability Insurance in accordance with clause 17 of AS4000- 1997

• Insurance of Employees in accordance with clause 18 of AS4000- 1997

• Construction program in accordance with clause 32 of AS4000- 1997

• Occupational Health and Safety Documentation

The Contractor shall provide written approval of the insurance policies covering the works under contract and public liability insurance. The Contractor shall provide the required insurance Certificates of Currency with Orchard (Pebble Creek) Development Pty Ltd listed as an interested party in accordance with clauses 16 & 17 of AS4000-1997.

2.9 LANDSCAPE OPERATIONS

Unless otherwise specified or indicated in the tender drawings, the general landscaping operations shall be executed in accordance with all current relevant Australian Standards.

All operations herein described may be carried out with suitably approved machinery or by hand as the size of the areas or the accessibility dictates, and the need to work in such a manner must be reflected in the Contractor's rates.

The use of heavy machinery in excess of that required for the satisfactory construction of the work is prohibited. Where over-compaction results from the Contractor's own failure to comply with this Clause, they shall, at their own expense, undertake whatever works the Superintendent may deem necessary to relieve the compaction and/or restructure the subsoil/topsoil.

The Superintendent may suspend any operation if they consider the site conditions or weather conditions unsuitable to continue. Such a suspension cannot be considered a reason for any claim or loss by the Contractor or Subcontractor.

2.10 SETTING OUT

Check the levels and dimensions of the site against those shown on the drawings, and record the results on a copy of the drawings. Notify the Superintendent in writing of any discrepancies and obtain instructions before proceeding. Inform Superintendent when overall setting out is complete and before commencing operations.

2.11 COMPLETION Reinstatement Unless otherwise specified, reinstate all existing surfaces, items, structures and anything disturbed or damaged by the performance of the works, to its condition at the commencement of the Contract, other than that forming part of or directly modified by the new work. Remove and cart away debris, spoil and surplus building materials from the site and buildings, with the exception of those works associated with others prior to practical completion.

Page 15: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 15

3 EARTHWORKS AND DEMOLITION

3.1 INSPECTION

Inspect the site and ascertain the nature of excavation required and the working conditions that will be encountered prior to the commencement of work. The location of topsoil stockpiles, roadway and cut embankment profiles and water connection points must be taken into account.

3.2 DEMOLITION

Generally demolish and remove all works from the site where set-out on the relevant plans. All demolition works are to be carried out where possible prior to the commencement of the construction works. Due care must be taken in all cases to prevent damage to any existing site elements to be retained. This is to include but not be limited to existing vegetation, and services to be retained. Refer to the ‘ENVIRONMENTAL’ section for the requirements for the protection of vegetation on site.

3.3 EXCAVATION AND EARTHWORKS

Excavate or fill over the site as required to conform to the sub-grade levels as indicated in the documents for grassed, garden and hardscape areas. Excavate for sub-surface drains and any other service as hereafter specified. Backfill excavations throughout as specified herein after laying and testing of pipes etc.

The Contractor shall ensure measures to minimise erosion and siltation relative to the works outlined in this specification, including staging of the works, stabilisation of exposed surfaces, diversion drains and silt traps over and above those already installed in civil works.

Surface drainage shall be diverted clear of excavations and covers shall be provided where necessary for safety. Ensure that run-off is not concentrated onto adjoining properties and does not cause a nuisance thereto. Finished surfaces shall be graded in accordance with Construction Plans.

Erect barriers as required to prevent excavated material and rocks from intruding onto adjoining properties. Establish exact locations of services, drains, sewers and water supply lines and points prior to commencing works and ensure their protection during the works.

All obstructions encountered during excavations such as tree roots, old foundations, drains and boulders shall be removed. Due allowance shall be made for such work and no extras will be allowed for removal of such obstructions.

All major earthworks associated with this project shall be carried out by the civil contractor. Any trimming and minor earthworks required for the completion of the landscape works shall be a part of the Landscape contract.

3.4 PROTECTION OF COMPLETED EARTHWORKS

Following completion of earthworks carry out specified topsoiling, grassing, planting and mulching at the earliest practical date to minimise erosion. Refer section on Softscape.

Page 16: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 16

4 ENVIRONMENTAL

4.1 GENERAL

This section covers the following components and all works associated with them.

• Environmental Protection

• Vegetation Management

• Arboricultural Works

• Erosion Control

4.2 ENVIRONMENTAL PROTECTION

4.2.1 Environmental Protection

Generally comply with the provisions of this clause and any other environmental protection provisions in the Contract and with the requirements of any statute, by-law, standard and the like related to environmental protection.

The Contractor shall not discharge poisonous, noxious or polluting material into any “Controlled Waters”, either deliberately or accidentally. Polluting materials include silt, cement, concrete, oil, petroleum spirit, sewage or other debris and waste materials. "Controlled waters" include all watercourses and water contained in underground strata.

In planning and carrying out any works, precautions must be taken to secure the complete protection of watercourses and water in underground strata against pollution. If pollution should occur, then the site operator should advise the relevant Statutory Authority immediately and take prompt action to minimise the effect.

Any fines or penalties apply due to action taken by the Contractor on site shall be at the Contractors own expense.

4.2.2 Disposal of Contaminants

Generally dispose of solid liquid and gaseous contaminants in accordance with all statutory and contractual requirements.

Gaseous Contaminants: Discharge in a manner that they will be diluted with fresh air sufficiently to reduce toxicity to an acceptable level.

Liquid Contaminants: Subject to statutory and local requirements, liquid contaminants may be diluted with water to a level of quality acceptable in the sewer system. If this is not permitted store in approved vessels for disposal at approved locations.

Solid Contaminants: Dispose by removal from site to approved locations or as otherwise directed.

Page 17: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 17

4.2.3 Disposal of Refuse

Remove refuse from site (including food scraps and the like) resulting from work under the Contract. Handle refuse in a manner so as to confine the material completely and prevent dust emission.

4.2.4 Disposal of Spoil

Unless otherwise specified remove all spoil not required as part of the works from the site.

4.2.5 The Use of Chemical Pesticides and Herbicides

The Contractor should consider in every instance whether the use of chemicals is strictly necessary before application, and assess the product, site conditions and species to ensure minimum risk to their employees, other users of the site and the environment.

Herbicides must be applied by appropriately qualified/supervised persons in accordance with the Agricultural Chemicals Distribution Control Act 1966, Chemical Usage (Agricultural and Veterinary) Control Regulation 2017 at rates as identified on registered product labels, or on an Australian Pesticides and Veterinary Medicines Authority (APVMA) issued off-label permit where applicable. Refer to South East Queensland Ecological Restoration Framework for additional guidance.

The Contractor should consider in every instance whether the use of chemicals is strictly necessary before application, and assess the product, site conditions and species to ensure minimum risk to their employees, other users of the site and the environment. In particular, the Contractor must be extremely competent and knowledgeable with the herbicides being used on site, especially with the water ways (inclusive of banks that may be flooded seasonally) and ephemeral creek lines and gullies.

When using pesticides the Contractor must use a certified operator and take appropriate safety precautions in accordance with all current statutory regulations (i.e. business and operator to hold relevant ACDC licence(s)/ permits). The Contractor must have within their work vehicle a register of all the current SDS and or MSDS for the herbicides being used, it is the Subcontractor’s responsibility to ensure the register is current and that all personnel are informed on the use of said herbicides.

The Contractor must dispose of unused and unwanted containers and chemicals, including unused dilute tank mixtures, in a safe way in accordance with the methods approved by the relevant authorities. Disposal will be off site.

Unintentional spray overlap must be avoided. Spraying must stop whilst turning. The Subcontractor must mark the point where spraying has stopped for refilling or for breaks.

Herbicide must never drift, fall or run-off onto open water or onto adjacent sites, gardens or ground not intended for treatment.

The Contractor must keep full and accurate records of all pesticides and herbicides used the areas in question, the amounts and the date of completion.

The Contractor will be expected to use translocated chemicals in preference to contact products for the control of perennial weed growth.

Page 18: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 18

4.2.6 Wildlife Protection

The Contractor will be responsible for assessing any potential wildlife problem when tendering and during the course of the works. Allowance must be made for any protection or control of such pests the Subcontractor deems necessary. Subsequent fauna (wallaby, bush turkey or rabbit etc) damage to planting or other works will be deemed as defective work and subject to replacement as per the normal contract conditions. Any proposed method of protection or control of pests must be agreed with the Superintendent prior to use on site.

Any protection or methods of control should be considered in relation to the potential public access to the site.

4.2.7 Dust and Noise Control

Restrict dust caused by the Works to a minimum. Appropriate dust control methods are to be implemented by the Contractor as required or directed by the Superintendent. Take all practicable steps to minimise noise resulting from the Works.

4.3 EROSION AND SEDIMENT CONTROL

4.3.1 General

Take all precautions necessary to prevent erosion, contamination and sedimentation of the site, surrounding areas, water and drainage systems, in accordance with the Environmental Protection (Water) Policy 2009. Methods of protection shall include but not be limited to the following:

• Construction of temporary surface swales;

• Diversion and dispersal of concentrated flows to point where the water can pass through the site without damage;

• Construction and maintenance of silt traps (e.g. hay bales) to prevent the discharge of scoured materials to downstream areas;

• Provision of temporary grassing or other treatment (e.g. contour ploughing) to disturbed areas;

• Progressive restoration of disturbed areas;

• Construction of temporary siltation fencing.

Any erosion damage reinstatement or clean-up as a result of the contractor not adequately protecting the site, materials or the works shall be the responsibility of the Contractor.

4.3.2 Maintenance

After each rain event inspect, clean and repair if required temporary erosion and sediment control works. All temporary erosion and sediment control measures are to be maintained in a fully operational state until the completion of the works or the establishment period if deemed necessary.

4.3.3 Removal

Remove temporary erosion control measures when they are no longer required.

Page 19: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 19

4.4 VEGETATION MANAGEMENT AND PROTECTION

All existing native flora species/ patches are to be flagged and protected during the landscape works.

4.4.1 Protecting of Existing Vegetation

It is a requirement of the Development Approval Conditions that existing vegetation on site is to be retained and protected, as identified on the documents. The existing vegetation shall be fenced off on occupation of the site and shall not be removed unless instructed by the Superintendent.

Failure to comply with the specified protection works may result in an instruction to suspend the works.

Damage to or removal of existing vegetation to be protected must be reported to the Superintendent and remedial action should be taken to the satisfaction of the Superintendent.

Trees and shrubs that are damaged beyond repair shall be replaced with similar sized specimens at the Contractors own expense.

4.4.2 Protective Fencing

Protective fencing will have been erected prior to any demolition works being carried out and before any materials or machinery are brought on site, and prior to the erection of any site huts. All such fencing shall be maintained for the full contract period and may only be removed at the express consent of the Superintendent.

The fencing is to be 1800mm high galvanised relocatable chain wire protective fencing with concrete bases. Generally the fencing is to be located vertically below the extent of the trees' canopy drip line. All gate and access points are to be locked when the Contractor is not on site to ensure site security is maintained at all times throughout the duration of the contract.

Fencing is to be maintained in that position during the works or until adjoining building construction does not permit it to be retained.

For the removal of existing elements on site within the proposed extent of protective fencing, locally remove the fence to enable only the required elements to be removed. If the item is close to tree roots, branches or trunk the contractor is to remove/ excavate by hand to ensure no damage occurs to the vegetation. Upon successful removal of the existing item the protective fence is to be reinstated to the original position.

4.4.3 Works within Protected Areas

No work shall be undertaken within the protection areas without the express consent of the Superintendent. Where works are required within these areas, then all necessary excavations, earthworks and cultivations shall be undertaken by hand (unless express permission for specific operations is obtained from the Superintendent) and according to a method statement to be agreed by the Superintendent before any work begins on site.

No materials, fuel or plant shall be stored within the areas so enclosed. No materials, fuel or plant shall be stored within 15m of existing vegetation.

Page 20: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 20

All necessary excavations, earthworks and cultivations shall be undertaken by hand within the canopy spread of any existing vegetation unless express consent of the Superintendent is obtained for specific operations.

Existing site features and vegetation identified on drawings to be retained must be protected throughout the works. Any damage to such features shall be made good under the direction of the Superintendent at no additional cost to the Contract.

4.4.4 Additional Precautions outside Fenced Areas

In particular, care is needed to avoid damage in the following ways:

• Oil, bitumen, cement or other material likely to be injurious to a tree should not be stacked or discharged within the drip-line of the tree, and materials generally should also not be stacked or discharged within the drip-line of the tree.

• Concrete mixing should not be carried out within 15m of a tree.

• It is essential that fires not be lit on site.

• Trees to be conserved will not be used as anchorages for equipment used for removing stumps, roots or other trees, or for any other purposes.

• Notice boards, telephone cables, or other services should not be attached to any part of a tree.

• Care should be exercised when using cranes or similar equipment near the spread of the canopy of a tree. All machinery operators are to have the appropriate operation tickets and qualifications as per the applicable governing body requirements.

• Trees to be felled that are adjacent to or that lie within a continuous canopy of trees to be retained should be removed with particular care. In some cases a tree may have to be removed in sections to avoid damage.

4.4.5 Tree Removal

Remove trees marked 'Existing Trees to be Removed' as shown on plan. Care shall be taken when removing existing trees not to damage any trees to be retained. A qualified Arborist shall be present for the removal of any large trees in close proximity to those that are marked for retention, or that may cause damage to retained trees when removed.

Upon removal of trees, palms and vegetation the matter shall be mulched and disposed off site.

4.4.6 Removal of existing pavement surfaces around existing trees

This refers to all existing hard surfaces existing on site including but not limited to unit paving, concrete and bitumen.

The removal of existing pavement from around the base of existing trees to be retained shall be carried out with great care ensuring no damage occurs to any part of the tree.

If the area is within the extent protective fencing, the fencing shall be locally removed and upon removal of the surface shall be replaced as originally indicated. Surfaces near to trunks, roots and branches shall be removed by hand.

Page 21: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 21

4.4.7 Installation of services around trees

This refers to all proposed in-ground services including but not limited to water reticulation, storm water and sewerage piping, electrical cabling.

The installation of all in-ground services shall have minimal effect on all existing trees to be retained. All machine trenching shall be carried out with the smallest bucket available and any hand trenching shall be utilised around tree roots to minimise effects or damage.

When excavating/ trenching around any significant roots a nominated, qualified Arborist shall be given prior warning and shall be present on site to supervise the removal or redirection of the roots. No root removal shall be carried out without the advice or supervision of the Arborist.

Where possible locally redirect services around roots, trunks or tree protection zones as opposed to removal.

4.4.8 Installation of pavement surfaces adjoining existing vegetation

This refers to all proposed hard pavement surfaces including but not limited to bitumen, paths, edging, concrete and stonework.

The installation of all pavement surfaces shall have minimal effect on all existing trees to be retained. All machine trenching and excavation shall be carried out with the location of tree roots and branches in mind and hand excavation shall be utilised around tree roots to minimise effects or damage.

When excavating around any significant roots the nominated project Arborist shall be given prior warning and shall be present on site to supervise the removal or redirection of the roots. No root removal shall be carried out without the advice or supervision of the Arborist.

Where pavement surfaces and or their respective excavations are projected to have an impact on existing tree roots, trunk and branches, the contractor shall look at alternative surfaces to ensure the protection of the tree and guarantee the long term healthy growth of the specimen. Where possible locally redirect services around roots/ trunks as opposed to removal.

4.5 ARBORICULTURAL WORK

4.5.1 Remedial Work to Existing Vegetation

All remedial works to existing vegetation to be carried out by a nominated, qualified arborist (minimum level 5 Arborist qualification). In the event that the project arborist is unavailable, a qualified arborist, approved by the Superintendent shall carry out these works. These works shall include but not be limited to items of the existing vegetation such as trunk, roots and branches.

The Contractor is to monitor all civil and construction works with regards to effects of existing vegetation and will pre-empt any need to notify and utilise the arborist. The arborist shall be present on site for major milestones that include the interface with existing vegetation.

Page 22: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 22

The arborist is to utilise the most appropriate techniques when remediating vegetation at the interface with proposed built elements so as to minimise any damage to the vegetation. Where necessary investigate options that will negate the need for cutting, breaking or severing of limbs and roots. All damage by the contractor to an existing tree shall be reported to the arborist (and the Landscape Architect where a major incident has occurred) for immediate input and remedial actions.

Any arboricultural work required by the Superintendent shall be carried out to AS4373:2007 and any associated vegetation protection is to be in conjunction with AS 4970:2009.

In particular an arborist report may be required for trees that are impacted on by the civil works (i.e. stage batters, trunk main, services, general compaction from machinery).

Page 23: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 23

5 CONCRETE

5.1 GENERAL

This section covers all concrete materials and work required for relevant components of construction for this contract as detailed on the drawings and specified, including reinforced, precast concrete, formwork, reinforcement, joints and integral finishes.

Standard: Construct the concrete work in a safe manner using materials and methods complying with the relevant requirements of AS 3600:2018 and AS 3610:2018. For concrete structures used for retaining liquids comply also with the relevant requirements of AS 3735:2001.

Give not less than 24 hours’ notice so that the following may be inspected:

• Demonstration samples

• Set-out of work

• Prior to concrete placement with forms and reinforcement in place

• Finishing of concrete

5.2 INSPECTION

Notice: Give sufficient notice so that inspection may be made of the following:

• Base or subgrade prior to covering.

• Irrigation access sleeve installations;

• Trial set-out for paving samples;

• Reinforcement fixed in place.

• Completed formwork prior to concrete placing.

• Surfaces or elements to be concealed in the final work prior to covering.

Minimum notice required: 24 hours

5.3 TESTS

Concrete testing methods: Use the appropriate sampling and testing method specified in AS 1012. Sample the concrete on site.

Test records: For each required test maintain the records and reports of test results required by AS 1012, or similar information tests not covered by AS 1012. Submit a copy of each test report.

Performance Testing

Requirement: Sample, test and assess the concrete for compliance with the specified quality parameters to AS 1379.

Page 24: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 24

Frequency of sampling: Where project assessment of strength grade is specified, spread the site sampling evenly throughout the pour. The following minimum requirements apply in addition to those in AS 1379

5.4 CONTROL TESTS

5.4.1 Standard: to AS3600:2018, clause 19.6.2.8

Acceptance criteria:

• Average strength of all samples shall exceed the required value.

• Strength of any one sample shall be not less than 0.85 of the required value.

5.5 BASE COURSE

5.5.1 Preparation

Prepare the subgrade by grading to accommodate the thickness of the base course and paving. If necessary, loosen the ground to a depth of 200 mm and adjust the moisture content before compaction. Compact the ground to the required density. Do not place on top of base course materials to bring up to level to suit slab thickness.

5.5.2 Base course material

Minimum thickness (mm): 75

5.5.3 Placing

Spread and compact the base course to the required thickness and density. Adjust the moisture content as needed to facilitate compaction.

5.5.4 Required density

Cohesive subgrade soils:

• Minimum dry density ratio (standard compaction) to AS 1289.5.4.1:2017: 98%.

Base:

• Minimum dry density ratio (modified compaction) to AS 1289.5.2.1:2017: 95%.

• Density tests: 1 No per 200m2 on subgrade and on base course.

• CBR Tests: Allow for 1 No soaked CBR tests to be taken in a location nominated by the superintendent to confirm the pavement depth.

Compacted layer thickness

Tolerance: + unspecified, -5 mm.

Surface level tolerance

Absolute: ± 25 mm.

Page 25: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 25

5.6 INSITU MIXED CONCRETE

Except where specified, all material at the time of use is to comply with the relevant Australian Standard Specification and Codes.

Cement shall comply with AS 3972:2010 and be supplied fresh, stored in an approved shelter and kept thoroughly dry and uncontaminated. Cement shall be used in rotation as delivered, that is a first delivered, first used basis.

Water shall be reasonably clear and fit for drinking.

Aggregates generally shall be free from deleterious matter likely to adversely affect the strength and durability of the concrete or corrode the reinforcement. Store in various grades of stone and sand to ensure cleanliness and to prevent mixing.

Aggregates to conform to AS 2758:2017 and consist of crushed basalt or other approved hard stone free from honeycomb particles, stone dust and thin or flaky particles. Nominal size as per specified drawings.

Admixtures may only be used with approval or as specified on drawings.

To be mixed in the proportions of 4:2:1 of course grade aggregate to sand to cement all accurately gauged by volume, together with a minimum of water to produce a workable plastic mix.

5.7 PREMIXED CONCRETE

Premix concrete mixing and delivery to conform with all the requirements of AS 1379:2017.

All premix concrete shall be delivered in a mechanically powered revolving drum container.

Unless otherwise specified, all concrete poured on site is to be premixed from an approved supplier.

No water is permitted to be added on site.

Test slump of concrete in accordance with the Australian Standard Specification AS 1012 Part 3 2018 and provide certification to prove compliance.

Do not pour concrete when the shade temperature is over 30oC. When rain is imminent, the Subcontractor may pour at his own risk but if any damage results; work will be rejected and replaced with fresh concrete.

Minimum characteristic strengths at 28 days as defined by AS 3600:2018.

5.8 EMBEDDED ITEMS

Coverage of pipes, conduits, fittings and core holes will comply with AS 3600:2018. Other embedded items, including fixings, anchor bolts and the like, shall also comply with the size, spacing and cover requirements of the manufacturer unless otherwise shown on the drawings or specified.

In locating embedded items, do not cut or displace reinforcement, or cut hardened concrete unless prior approval has been obtained.

Page 26: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 26

5.9 REINFORCEMENT

Steel reinforcement to comply with requirements of relevant Australian Standard AS 1302, AS 1303 and AS 1304.

Rigidly hold in position the reinforcement during placement of concrete to ensure its required position in achieved. Cover, where not specified, shall comply with AS 3600:2018.

Use purpose-made concrete, metal or plastic supports. For exposure classification A1, provide a protective coating to ferrous metal which extends to the surface of the concrete. For exposure classifications more severe than A1 use plastic supports of adequate strength and of a shape appropriate to the location, or concrete supports of the same concrete quality as the concrete element.

5.10 CLEANING

At the time the concrete is placed, ensure that reinforcement is free from loose mill-scale, loose rust, mud, oil, grease, paint and other coatings which would reduce the bond between concrete and the reinforcement.

5.11 FIXING

At the time the concrete is placed, accurately fix reinforcement in accordance with the landscape drawings, but variations from position may be permitted not exceeding those specified herein. Ensure that reinforcing is free from bends not required by the drawings, kinks and similar defects and securely fastened and maintained in position until the concrete is placed.

5.12 SLABS

Support reinforcement in slabs on approved chairs. It is the Contractors/ Subcontractor's responsibility to ensure that the exposed concrete surface, after removal of formwork, does not show any blemish or indentation, etc., caused by the reinforcement supporting chair or block.

Cutting of reinforcement by other trades is not permitted except by special permission in which case additional reinforcing bars are to be inserted as directed.

5.13 SPLICES

When splices, not already shown on the contract drawings, are found necessary, submit details of the proposed splices for approval.

5.14 PLACING OF CONCRETE

Concrete shall be placed in horizontal layers, without separation of the aggregates and shall be compacted by vibration, tamping, spading or slicing.

Concrete shall not be dropped into place from a height greater than 1.5m.

Page 27: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 27

Any concrete that has developed initial set shall not be used. No concrete shall be mixed or placed while air temperature with the following 24 hours is or is likely to be below 4ºC or while the shade temperature exceeds 38ºC without the approval of the Superintendent or when rain is falling or is imminent.

Preparation for placing: Moisten the subgrade to ensure a firm, uniform moist surface at the time of placing. Remove loose material and debris from the surface. Do not operate construction equipment on the prepared surface. Do not use calcium chloride, salts, chemicals or other material in the mix to lower the freezing point of the concrete.

5.15 COMPACTING

During and immediately after placing, thoroughly compact the concrete by means of continuous tampering, spading, slicing or vibrating as specified.

5.16 CURING

Cure concrete for at least 72 hours continuously, following the time of placement. In hot weather extend the curing time to 7 days.

Accomplish curing by one or more of the following methods. Curing medium must by placed and wetted within 2 hours of completing concrete.

Surfaces by the cured by:

• Continuous water spray or

• Covering with polythene sheeting sealed at laps or

• Application of curing oil that is not detrimental to any finishes or

• Sand layer maintained in damp condition.

Maintain the formwork in position in a wet condition.

5.17 FORMWORK

To be adequate for the purpose and generally in accordance with the requirements of AS 3610:2018 and to achieve the surface finish as specified on the drawings.

Design and construct formwork so that the concrete, when cast in the forms, will have the dimensions, shape, profile, location and surface finish required by the contract. Make provision for dimensional changes, deflections and cambers resulting from the application of applied loads, temperature changes and concrete shrinkage and creep. Formwork to class 3 for insitu paths and the like, and class 1 for off-form features.

Do not disturb or remove formwork until the concrete in contact has hardened sufficiently to guarantee safe removal.

5.18 REJECTION OF CONCRETE

Hardened concrete may be rejected if:

Page 28: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 28

• It is porous, segregated or honeycombed in excess of that permitted by Australian Standards.

• It has displaced reinforcement.

• Construction tolerances have not been met.

• Required surface finishes have not been achieved.

• The concrete can be shown to be otherwise defective.

• Concrete has not been installed in line with the landscape specification or documents.

5.19 CONSTRUCTION OF TOLERANCES

The maximum permissible deviations from detailed level, line or grade shall be as follows:

Variation from plum or level Plus or minus 3mm in 300mm

Variation from established position in plan or building line

Plus or minus 10mmin 600mm

Sizes of members of thickness of slabs Plus 5mm, minus 0mm

Misplacement of footings from whichever dimensioned line

2% of footing width or 40mm, whichever is less.

5.20 PROTECTION

Protect the concrete from damage due to load over stresses, heavy shocks and excessive vibrations, particularly during the curing period.

Protect finished concrete surfaces from damage or staining.

Concrete shall be rejected if exposed surfaces are damaged. Rectification may be attempted only if approval is given by the Superintendent.

5.21 CLEANING

Clean and remove all excess rubbish concrete material. Do not wash, place or sweep concrete onto soil and planting areas.

5.22 JOINTING

Provide all construction, control and expansion joints to locations as set-out and detailed as specified on the drawings.

5.22.1 Expansion Joints

Cast in joint filler at maximum 6 m spacing (or as marked on drawings). Locate at junctions with fixed structures such as buildings and manholes, at path intersections. Do not tool off joint arises abutting the seal.

Page 29: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 29

Provide galvanized steel reinforcing rod dowels in expansion and contraction joints, where required. Embed each dowel normal to the plane of the joint, so that half the dowel lies on each side of the joint. Heavily grease or bitumen coat one half and fit an expansion cap to that end.

Joint Material: 10 mm Ableflex or similar approved flexible filler.

5.22.2 Tool Joints

Generally to be saw cut joints at 1m spacing (or as marked on drawings)

5.23 INTEGRAL CONCRETE FINISHES

The following concrete finishes shall be used for the works as set out in the contract drawings:

5.23.1 Finishes

Type 1 Concrete Footings

• Description: Concrete footings

• Reinforcement: As per landscape details

• Location: All fencing, feature timbers and stone faced wall footings as shown on

landscape plans. Type 2 Concrete Edge

• Description: 125 x 125mm Portland Grey Extruded Edge

• Finish: Extruded Edge

• Location: To garden, turf area interfaces as shown on landscape plans

Generally

Finished pavement surface: Provide a surface uniform in appearance and free from depressions in which water can lie, with a texture depth of 2 - 2.5 mm.

Page 30: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 30

6 BLOCKWORK

6.1 STANDARD

General

Materials, construction and detailing: To AS 3700:2018.

Masonry units: To AS/NZS 4455

Refer to the following sections: Concrete

6.2 INTERPRETATION

Definitions

Face units: Masonry units used in face work, including purpose-made units such as squints, sills and thresholds.

Face work: Masonry in which the form, or form and colour, of the face units and joints is visible in the completed works.

6.3 QUALITY

6.3.1 Inspection

Witness points

Stages: Give sufficient notice so that inspection may be made at the following stages:

• Bottoms of cavities, after cleaning out.

• Bottoms of core holes, before grouting.

• Control joints, ready for insertion of joint filler.

6.3.2 Tests

Masonry units test criteria

General: The criterion for the relevant test stated or recommended in AS/NZS 4455:2010, or the specified criterion (in which case the latter prevails).

6.4 MATERIALS AND COMPONENTS

Attribute Concrete Blocks

Source Boral Masonry or similar approved by Superintendent

Location Where scheduled or shown on drawings

Manufacturing dimensions (mm)

390 x 190 x 190 (200 series); 390 x 140 x 140 (150 series) Refer Engineers details for reinforcement and core filling.

Page 31: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 31

6.4.1 Steel Components Corrosion resistance rating to AS 3700:2018:

• Steel products (including reinforcement), at least: R2

6.4.2 Mortar Materials Cement type to AS 3972:2010: GP.

Lime: To AS 1672.1:2016

Sand: Fine aggregate with low clay content and free from efflorescing salts, selected for colour and grading.

Additives: Do not provide additives.

6.5 EXECUTION

6.5.1 Construction generally Cleaning

General: Clean masonry progressively as the work proceeds. Clean face work to remove mortar smears, stains and discolouration. Do not use acid.

Concealed work

Joints: Cut flush, and leave unstruck.

Set out so that no unit is cut smaller than 3/4 full width.

Joints and cutting

Set out masonry with joints of uniform width and minimise cutting of masonry units.

Holes, sleeves and chases: Build in during erection.

Depth of raking (other than face work): 5mm

Mortar

Standard: To AS 3700:2018.

Mix proportions: 1:3 cement: sand.

Bonds

Single leaf: Stretcher bond.

Face work: Stretcher bond.

6.6 COMPONENTS

6.6.1 Face work Single face walls Location: Refer to the drawings and finishes schedules.

Commencement

Position: Commence at least 1 full course for block work, or 2 full courses for brickwork, below adjacent finished ground level. Cut block work as necessary to achieve set downs and vertical dimensions as documented.

Page 32: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 32

Perforations

Exposed: Provide solid face units where perforations would otherwise be visible.

Joints

Surface: Work with a jointing tool to a dense smooth surface, except where the surface is to be bagged.

Joint profile: Ironed with a 12mm diameter rod.

Colour mixing

General: Where the colour of the face units is visible, evenly distribute the colour range of units. Prevent colour concentrations and "banding".

Weepholes

Form: Open perpends.

Maximum spacing: 720 mm.

Location: Provide weepholes to external leaves of cavity walls in the course immediately above flashings, and cavity fill, and at the bottoms of unfilled cavities.

6.6.2 Control Joints Filler material

Type: Provide compatible sealant and bond breaking backing materials which are non-staining to masonry. Do not provide bituminous materials with absorbent masonry units.

Foamed materials: Closed-cell or impregnated, not water-absorbing.

Bond breaking materials: Non-adhesive to sealant, or faced with a non-adhering material.

Primer: Required.

Installation

Cleaning: Clean joints thoroughly before sealing.

Joint width:

Vertical joints: maximum 12mm

Sealant depth: 0.67 - 1.0 times joint width.

Toothed joints

General: Not permitted.

6.7 REINFORCEMENT

6.7.1 Reinforced Masonry General Designation: Masonry strengthened with embedded steel reinforcement, other than bed joint reinforcement.

Cleaning core holes

Block work: Provide purpose-made cleanout blocks or machine cut a cleaning hole at the base of each reinforced core. Locate on the side of the wall which is to be rendered or otherwise concealed. Cover the hole with formwork and grout the core.

Page 33: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 33

Bond beams

Type: Provide bond beams made from purpose-made hollow concrete blocks with reinforcement grouted in place.

Reinforcement: As per landscape details

6.8 COMPLETION Cleaning

Leave works clean on completion.

6.9 WATERPROOFING (AS REQUIRED) General

Waterproofing is to be applied to block walls where they are exposed/ shall contain planting areas (soil etc.). Waterproofing of block work is to ensure adequate tanking so as to prevent moisture penetration.

Priming

Prior to water proofing the block work is to be primed with an approved Primer and Waterproofing agent equivalent to ‘Gripset GP’. Primer to be applied in strict accordance with manufacturer’s instructions.

Waterproofing

A waterproof bitumen rubber membrane is to be applied to the block work, equivalent to ‘Gripset 51’. Water proof membrane to be applied in strict accordance with manufacturer’s instructions.

6.10 RENDERING

6.10.1 Inspection Witness points

• Give sufficient notice so that inspection may be made at the following stages:

• Background immediately before plastering.

• Each completed coat before the application of subsequent coats.

• Completed work before decorative coating.

6.11 MATERIALS AND COMPONENTS

6.11.1 Plaster Materials

• Cement type to AS 3972:2010 : GP.

• Lime: To AS 1672.1:2006

• Sand: To AS CA27, graded to Table 1 of the Appendix.

• Admixtures: Do not provide.

Page 34: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 34

6.12 EXECUTION

6.12.1 Correction of Substrate

Before plastering make good any defects in the substrate. Hack off excessive projections. Fill voids and hollows with a mix not stronger than the substrate nor weaker than the first coat.

6.12.2 Untrue Substrate

One coat work: If the substrate is not sufficiently true to comply with the thickness limits for one coat, or has excessively uneven suction resulting from variations in the composition of the substrate, carry out the work in two coats.

6.12.3 Cleaning

Remove deleterious and loose material and leave the surface clean and dust free.

6.12.4 Embedded Items

Ensure that water pipes and other embedded items are sheathed to permit thermal movement. If ungalvanized steel items are to be embedded in gypsum plaster, provide rust protection treatment not inferior to prime painting with zinc rich primer.

6.12.5 Chases

If chases or recesses are more than 50 mm wide, cover with metal lath extending at least 75 mm beyond each side of the recess.

6.12.6 Suction

Control suction by dampening if necessary. Avoid over-wetting.

6.12.7 Dense Concrete

If not sufficiently rough to provide a mechanical key, roughen by scabbling or the like to remove 3 mm of the surface and expose the aggregate; then dash coat. If scabbling and dash coating does not provide a good key for external render, cover with a non-corrosive expanded metal lath.

6.12.8 Concrete Block Work

Dash coat.

6.12.9 Previously Painted Surfaces

Remove paint, hack at close intervals, or cover with expanded metal lath.

6.12.10 Dash Coat

Application: Mix to the consistency of a thick slurry and forcibly dash on to the background to give a roughcast coating 3 - 5 mm thick.

Page 35: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 35

Curing: Allow the dash coat to harden in damp conditions and protect it from drying out before applying the next coat.

6.12.11 Thickness Limits

• One coat work: 10 - 12 mm.

6.12.12 Tolerances

Finish plane surfaces within a tolerance of 6 mm in 3 m, determined by a 3 m straight edge placed anywhere in any direction. Finish corners, angles, edges, and curved surfaces within equivalent tolerances.

6.12.13 Proportioning

Apply successive coats no stronger (i.e. no richer in cement) than the substrate or undercoat to which they are applied.

6.12.14 Incidental Work

Return plastering into reveals, beads, sills, recesses and niches. Plaster faces, ends, and soffits of projections in the substrate, such as string courses, sills, pilasters and corbels. Run throating on soffits of external projections neatly finished. Trim around openings.

6.12.15 Joining Up

If joining up is unavoidable in a large area of work, make joints invisible in the finished work.

6.12.16 Cement Based Undercoats

Before applying the next coat, allow the undercoat to dry out, dust down, and, if necessary, dampen to give correct suction.

6.12.17 Keying General: Press plaster through the apertures of metal lath, and wings of casing beads.

Keying undercoats: In multi coat work, scratch comb each undercoat in two directions when it has stiffened.

6.12.18 Surface Finishes

Wood float: Provide an even texture by wood floating the finishing coat.

Fine sand textured finish: Provide an even surface by wood float and finish with a plastic foam float to a fine sand textured finish.

6.12.19 Curing

Cement-based work: Prevent rapid or uneven drying out.

6.12.20 Cement Render

Proportions (cement: lime: sand):

• Concrete block: 1:0:6.

Page 36: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 36

6.13 JOINTS

6.13.1 Movement Joints

General: Provide movement joints in the finish which coincide with movement joints in the substrate. Ensure that the substrate joint is filled with the specified jointing material, and is not bridged during plastering.

Plastering on metal lath: Provide movement joints to divide the plastering area into rectangular panels not exceeding 10 m2.

Depth: Extend the joint right through the plaster to the substrate.

Width: 3 mm, or the same width as the substrate joint, whichever is greater.

Joint filling (joints more than 3 mm wide): Fill with a resilient sealant.

6.13.2 V Joints

Provide V-joints, cut right through the plaster to the substrate, at the following locations:

• Junctions between different substrate materials.

• Abutments with other finishes.

• Abutments with metal door frames.

• Match existing dado joints in new work in Building No. 1 generally

6.14 REPAIR TO SET RENDER

Where existing set plaster walls are repaired or in filled finish to make joints invisible in finished work, a sample repair/junction is to be prepared for approval prior to work proceeding.

Repair wall finishes where chasing is required for installation of services.

Ensure thickness and surface finish match existing adjoining wall finish.

Remove all drummy areas of existing plaster where adjoining new or repaired work and extend new work to removed areas of drummy render.

6.15 CEMENT PAINT

Preparation: Clean down existing brickwork to remove all oil, grease, mould and loose material prior to application. Point up all damage or voids in mortar joints and brickwork.

Application:

• Dulux AcraTex Green Render Sealer (Refer Appendix B)

• Dulux AcraTev Acraprime Water Based (Refer Appendix B)

• Dulux AcraTex AcraShield Advance (Refer Appendix B)

Page 37: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 37

Sample: Prepare a 2m x 2m sample panel for approval by the Superintendent prior to proceeding.

Colour: Dulux Colour TBC by Landscape Architect prior to construction

6.16 COMPLETION

Cleaning

Leave works clean on completion.

Page 38: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 38

7 TIMBERWORK These works are to generally cover:

• Timber fencing;

• Timber Edging;

• Recycled Timber Posts.

7.1 STANDARDS

The works shall comply with AS 1148:2006, AS 1684:2010, AS 1720:2016, and AS 2796:2016.

Do not provide rainforest timber species unless plantation grown or otherwise specified.

7.1.1 Structural Timber Grading Standards

Hardwood: To AS 2082:2007.

Softwood: To AS 2858:2008.

Mechanical stress grading: To AS 1748:2011 and AS 1749.

Machine proof-grading: To AS 3519:2016.

7.1.2 Timber

Seasoned hardwood: AS 2796:2016.

Cypress pine: AS 1810:2016.

Australian grown conifers, other than radiata pine and cypress pine: AS 1782.

Grade: Type A, Category 4.

Thickness (mm):15mm

7.1.3 Durability

General: Provide timbers having natural durability appropriate to the conditions of use, or preservative-treated timber of equivalent durability.

Classification: To AS 1604:2012 Table F2.

Minimum requirements for dressed hardwood timbers:

• Durability Class 1 Timber

Minimum requirements for sawn timbers:

Page 39: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 39

• Durability Class 1 Timber, or

• Treated Durability Class 2 Timber

Lyctus susceptible timbers:

Do not provide timbers containing Lyctus susceptible sapwood.

7.1.4 Preservative Treatment

Standard: To AS 1604:2012.

Hazard classification: To AS 1604:2012 Table D1.

CCA preservative: Type I.

All timber to be preservative treated to a minimum level H4

General: Provide milled timbers with actual dimensions which are at least the stated dimensions, except for dimensions qualified by a term such as "nominal" or "out of" to which industry standards for finished sizes apply.

Unseasoned timber: If unseasoned timber is used, or if variations in moisture are likely, allow for shrinkage, swelling and differential movement.

7.2 FASTENERS

7.2.1 Deck Fixings

All decking fixings are to be 14 gauge, type 17 screws with a countersunk/ bugle head and a recessed hexagonal drive manufactured from stainless steel, grade 304. For fixings through top of decking timbers countersinking shall be carried out.

7.2.2 Other Timber Fixings

For all other timber fasteners, fixings are to be hot dip galvanised.

Page 40: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 40

7.3 TIMBER TYPES 7.3.1 Fencing Type 1A- Acoustic Fence Palings: • Timber Type: CCA Treated Pine, 90 x 19mm

• Rating: H3

• Fixing: 2 (No.) 50 x 2.5mm Screw Shank or Ring Shank HDG to each rail.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown. Rails: • Timber Type: CCA Pressure Treated Pine Palings, 38 x 100mm. All edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 2 (No.) Type 17 100mm Bungle Head HDG Batten Screw to each post.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown. Posts: • Timber Type: CCA Treated Harwood Post, 150 x 100mm. Front face (Road Side) to have

45mm chamfer. All other exposed edges to have 5mm aris.

• Rating: F17, H5

• Footing: 350ø mm Bored piers N20 Concrete with minimum 100KPA allowable Bearing

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut. Capping: • Timber Type: CCA Treated Hardwood, 150 x 25mm. All exposed edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 1 (No.) Type 17 Bungle Head HDG Batten Screws at min 600mm centres

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Fascia: • Timber Type: CCA Pressure Treated Pine, 100 x 25mm.

• Rating: F14, H3

• Fixing: Countersunk 1 (No.) Type 17 Bungle Head HDG Batten Screws at min 600mm centres

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut. Sleeper Kick Board: • Timber Type: CCA Treated Hardwood, 200 x 50mm. All exposed edges to have 5mm aris.

• Rating: F17, H5

• Fixing: 1 (No.) 10x 100mm Type 17 Gauge 14.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Sela Brown.

Page 41: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 41

7.3.2 Fencing Type 1B- Acoustic Fence with Retaining Wall Palings: • Timber Type: CCA Treated Pine, 90 x 19mm

• Rating: H3

• Fixing: 2 (No.) 50 x 2.5mm Screw Shank or Ring Shank HDG to each rail.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.

Rails: • Timber Type: CCA Pressure Treated Pine Palings, 38 x 100mm. All edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 2 (No.) Type 17 100mm Bungle Head HDG Batten Screw to each post.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.

Posts: • Timber Type: CCA Treated Harwood Post, 150 x 100mm. Front face (Road Side) to have

45mm chamfer. All other exposed edges to have 5mm aris.

• Rating: F17, H5

• Footing: 350ø mm Bored piers N20 Concrete with minimum 100KPA allowable Bearing

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Capping: • Timber Type: CCA Treated Hardwood, 150 x 25mm. All exposed edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 1 (No.) Type 17 Bungle Head HDG Batten Screws at min 600mm centres

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut. Fascia: • Timber Type: CCA Pressure Treated Pine, 100 x 25mm.

• Rating: F14, H3

• Fixing: Countersunk 1 (No.) Type 17 Bungle Head HDG Batten Screws at min 600mm centres

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Sleeper Kick Board and Sleeper Retaining: • Timber Type: CCA Treated Hardwood, 200 x 50mm. All exposed edges to have 5mm aris.

• Rating: F17, H5

• Fixing: 1 (No.) 10x 100mm Type 17 Gauge 14.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Sela Brown.

Page 42: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 42

7.3.3 Fencing Type 2A- Feature Acoustic Panel Fence Palings: • Timber Type: CCA Treated Pine, 90 x 19mm

• Rating: H3

• Fixing: 2 (No.) 50 x 2.5mm Screw Shank or Ring Shank HDG to each rail.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.

Rail Type 1: • Timber Type: CCA Pressure Treated Pine Palings, 38 x 100mm. All edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 2 (No.) Type 17 100mm Bungle Head HDG Batten Screw to each post.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.

Rail Type 2: • Timber Type: CCA Pressure Treated Pine Palings, 50 x 100mm. All edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 2 (No.) Type 17 100mm Bungle Head HDG Batten Screw to each post.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.

Posts: • Timber Type: CCA Treated Harwood Post, 150 x 100mm. Front face (Road Side) to have

45mm chamfer. All other exposed edges to have 5mm aris.

• Rating: F17, H5

• Footing: 350ø mm Bored piers N20 Concrete with minimum 100KPA allowable Bearing

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Capping: • Timber Type: CCA Treated Hardwood, 150 x 25mm. All exposed edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 1 (No.) Type 17 Bungle Head HDG Batten Screws at min 600mm centres

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Plywood Panelling: • Timber Type: Premium Plywood Panel, 32mm thick

• Rating: A Board

• Fixing: Counter Sunk hidden fixing Type 17 HDG Bungle Head Batten Screw

• Finish: 2 coats of Dulux Colour and finish type TBC prior to construction

Page 43: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 43

Sleeper Kick Board: • Timber Type: CCA Treated Hardwood, 200 x 50mm. All exposed edges to have 5mm aris.

• Rating: F17, H5

• Fixing: 1 (No.) 10x 100mm Type 17 Gauge 14.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Sela Brown.

7.3.4 Fencing Type 2B- Feature Acoustic Panel Fence with Retaining Wall Palings: • Timber Type: CCA Treated Pine

• Rating: H3

• Fixing: 2 (No.) 50 x 2.5mm Screw Shank or Ring Shank HDG to each rail.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.

Rail Type 1: • Timber Type: CCA Pressure Treated Pine Palings, 38 x 100mm. All edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 2 (No.) Type 17 100mm Bungle Head HDG Batten Screw to each post.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.

Rail Type 2: • Timber Type: CCA Pressure Treated Pine Palings, 50 x 100mm. All edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 2 (No.) Type 17 100mm Bungle Head HDG Batten Screw to each post.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.

Posts: • Timber Type: CCA Treated Harwood Post, 150 x 100mm. Front face (Road Side) to have

45mm chamfer. All other exposed edges to have 5mm aris.

• Rating: F17, H5

• Footing: 350ø mm Bored piers N20 Concrete with minimum 100KPA allowable Bearing

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Capping: • Timber Type: CCA Treated Hardwood, 150 x 25mm. All exposed edges to have 5mm aris.

• Rating: F14, H3

• Fixing: 1 (No.) Type 17 Bungle Head HDG Batten Screws at min 600mm centres

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Page 44: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 44

Plywood Paneling: • Timber Type: Premium Plywood Panel, 32mm thick

• Rating: A Board

• Fixing: Counter Sunk hidden fixing Type 17 HDG Bungle Head Batten Screw

• Finish: 2 coats of Dulux Colour and finish type TBC prior to construction

Sleeper Kick Board and Sleeper Retaining: • Timber Type: CCA Treated Hardwood, 200 x 50mm. All exposed edges to have 5mm aris.

• Rating: F17, H5

• Fixing: 1 (No.) 10x 100mm Type 17 Gauge 14.

• Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Sela Brown.

7.3.5 Feature Recycled Timber Posts

• Timber Type: Recycled Dressed Hardwood Posts, 150 x 150mm

• Rating: minimum F17, H5

• Fixings to Entry Wall: 10mm Thick HDG Stirrup. 2 (No.) M12 HDG Cuphead Bolts Countersunk to Road side.

• Footing: 350ø mm Bored piers N20 Concrete with minimum 100KPA allowable Bearing 200mm long M16 Bolt installed to base of timber post in footing as shown.

• Finish: TBC by Landscape Architect prior to construction.

7.4 TIMBER EDGING

Location: Planting, gravel and mulched areas at interface with turf, as shown on landscape plans.

Size: 100 x 50mm CCA Treater Pine Edge (as per AS1604:2000) with 450 x 50 x 50mm Hardwood Stakes.

Fixing: 2 x Hot dipped galvanised M10 Screws as per landscape detail Installation

General: Set edges flush with adjoining surfaces. Ensure that edging is level and to alignment shown on drawings.

Page 45: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 45

8 METALWORK These works are to generally cover:

• Feature Stainless Steel Patterning to Entry Wall

• Feature Aluminium Patterning to Fencing

• Entry Wall Lettering

8.1 STANDARDS

The works shall comply with AS 1397-2011, AS 1163-1991, AS 2759-2004.

8.2 STEELWORK

8.2.1 Stainless Steel Patterning to Entry Wall

• Steel Type: Laser Cut Stainless Steel, 5mm thick. Landscape Contractor to request patterning prior to fabrication. All edges to have a corner radius of 1.5mm.

• Grade: minimum 304

• Fixing: Fully welded M16 304 Stainless Steel pins chemset into block wall.

• Finish: Brushed finished to superintendent’s approval.

• Sample: Contractor to provide a sample to Landscape Architect prior to fabrication

8.2.2 Stainless Steel Patterning to Fencing Panelling

• Steel Type: Laser Cut Brushed Aluminium Sheet, 5mm thick. Landscape Contractor to request patterning prior to fabrication. All edges to have a corner radius of 1.5mm.

• Grade: minimum 3003

• Fixing: Fully welded M16 Aluminium pins bolted to back of plywood sheet

• Finish: Brushed finished aluminium to superintendent’s approval.

• Sample: Contractor to provide a sample to Landscape Architect prior to fabrication

8.2.3 Entry Wall Lettering ‘Pebble Creek and South Maclean’

• Steel Type: Laser Cut Stainless Steel, 8mm thick. Landscape Contractor to request lettering prior to fabrication. All edges to have a corner radius of 1.5mm.

• Grade: minimum 304

• Finish: Brushed finished to superintendent’s approval.

• Fixing: Fully welded M20 Stainless Steel pins chemset into block wall.

Page 46: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 46

8.2.4 Entry Wall Lettering ‘South Maclean’ • Steel Type: Laser Cut Stainless Steel, 8mm thick. Landscape Contractor to request lettering prior to fabrication. All edges to have a corner radius of 1.5mm.

• Grade: minimum 304

• Finish: Brushed finished to superintendent’s approval.

• Fixing: Fully welded M8 Stainless Steel pins chemset into block wall.

Page 47: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 47

9 STONEWORK

9.1 GENERAL

These works are to generally cover:

• Stone cladding to block wall

All stone paving, steppers, cladding and gravels to be laid as shown on the relevant details, and to levels and falls as shown on plans.

9.2 STONE CLADDING

9.2.1 Stone Cladding to Entry Wall

• Product Name: Alpine Stone (Walling and Corners)

• Supplier: Eco Outdoor

Page 48: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 48

10 SOFTWORKS

10.1 SCOPE OF WORKS

Works to include but not be limited to the following:

• Outline/ scope of works

• Planting Works;

• Mulching;

• Soiling Works;

• Weed treatment / management;

• Site Topsoil (type varies);

• Amelioration regime;

• Turfing;

• Erosion controls/stabilisation works.

The Subcontractor shall totally familiarise themselves with the Contract documents and site prior to submitting the tender. Failure to do so will not give rise to a variation or extension of time.

10.2 QUALITY

10.2.1 Workmanship

Requirement

Carry out works with experienced horticulturists to best trade standards. Site representative is to be experienced (5 year’s minimum) in landscape construction and establishment.

10.2.2 Inspections

Witness points – Inspection and sign-off by Superintendent

Give 48 hours’ notice so that inspection may be made at the following stages:

• After initial weed treatment (as required)

• Inspection of amelioration materials

• Set out completed

• Sub-grades cultivated or prepared for placing topsoil

• Subsoil drainage before topsoil placement

• Topsoil spread before planting

• Grassing bed prepared before turfing, seeding, or temporary grassing

• Plant holes excavated and prepared for planting ex ground planting stock

• Plant supply site delivery and agreement of their project acceptability (namely palms and large trees).

Page 49: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 49

• Plant material set out before planting.

• Planting, staking and guying completed.

• Grassing and turfing areas completed.

• Completion of planting works and planting establishment work.

10.2.3 Tests

Soil tests

Site Topsoil: If any soils are intended for use on site other than those specified in the following sections the Subcontractor is to submit to the Superintendent a full physical and chemical analysis of the soil either carried out by an agronomist or provided by the supplier.

10.3 SAMPLES General

General: Submit representative samples of each material, packed to prevent contamination and labelled to indicate source and content. Samples are to be submitted for review as a whole group and resubmitted until approved. All required test results to be submitted with samples.

Samples Required Minimum Sample Required

Organic Mulch 1 kg

Plants One of each species at nursery

Specimen trees and palms All stock at nursery

10.4 SUBMISSIONS

10.4.1 Suppliers

Submit statements from suppliers of materials, giving the following, where applicable:

• Particulars of the supplier's experience in the required type of work.

• Production capacity for material of the required type, sizes and quantity.

• Lead times for delivery of the material to the site.

10.4.2 Materials

Supplier's data:

Submit supplier's data including

• Certificate identifying seed species, purity, age and germination viability;

• Certificate from an independent authority that remediated topsoil is capable of supporting and growing of plants; and

• Material source of supply. Compost: Submit a certificate of proof of compost pH value.

Page 50: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 50

10.4.3 Execution

Construction Program: Submit a work program to the Superintendent in the form of a bar chart, for the landscape works within the first fortnight of contract appointment

Maintenance program: Submit a proposed planting maintenance program at the same time as the construction program.

Weed Management report: Submit a weed management report as required prior to commencing works on site.

Planting machine: If a planting machine is to be used as an alternative to hand planting, submit proposal.

Material stockpiling: Submit proposal for bulk stockpiling of material as part of the construction program.

Plants - bare rooted and ex-ground stock: Submit work proposal for the relocation of site stock and for imported advanced plant stock. Outline pruning and hormone treatment, cranage access, lifting methods, operation space, guying, fertilising and watering methods and timing.

10.5 WEED TREATMENT / MANAGEMENT

10.5.1 Weed Removal

The Contractor shall identify all vegetation to be removed. This includes all pasture grass within the open areas of the site and all weed species (environmental, noxious or otherwise) as follows:

• As defined by the Land Protection (Pests & Stock Route Management) Act 2002;

• Agricultural Chemicals and Distribution Control Act 1966;

• Australian Pesticides and Veterinary Medicines Authority (APVMA);

• As declared by the State;

• As included on the National Environmental Alert List;

• As identified by the Local Authority concerned.

All vegetation and weed removal is to be carried out using industry standard accepted safety procedures and equipment to ensure personal and environmental protection. Avoid damage to nearby trees and surroundings.

Grub out stumps and roots over 200mm diameter to a minimum depth of 100mm below sub-grade. Stumps less than 100mm diameter shall be cut off at ground level and treated to prevent regrowth.

Completely remove woody weeds within the extent of works. Apply herbicide where necessary to prevent regrowth. Treat herbaceous weeds with herbicide or physically remove. Use a non-residual herbicide at manufacturer's recommended rates. Remove vegetative spoil from site and dispose of at an approved disposal situation. Do not burn.

List methods of disposal of weed species.

The Contractor are to supply any ‘Off Label’ herbicide licences/permits to the Superintendent prior to using the combined application on site.

Brushcut existing long grass in areas nominated on plans and or, as directed by the Superintendent.

Page 51: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 51

10.5.2 Weed Management Plan

The Contractor shall provide a Weed Management Plan (WMP) prior to commencing works on site. The plan is to be reviewed and approved in writing by the Superintendent. The plan must include ALL herbicides that the Subcontractor intends to use, and in which locations and on the specific species, including ratios. In the instance the WMP is to be updated a reissue of the plan must be sent to the Principal for review, prior to use.

Table 2 describes the weed species that have been noted within the site (but not limited to these species) however upon being awarded the project, the Subcontractor should hold their own site investigation prior to completing their Weed Management Plan.

Table 2 Declared and Environmental Weeds Botanical Name Common Name Status

Ageratum houstonianum Blue Billy Goat Weed Environmental Weed

Ambrosia artemisiifolia Annual Ragweed Declared Pest Plant (Class 2)

Archontophoenix alexandrae Alexandra Palm Environmental Weed

Asparagus aethiopicus 'Sprengeri' Ground asparagus fern Declared Pest Plant (Class 3)

Baccharis halimifolia Groundsel Declared Pest Plant (Class 2)

Bidens pilosa Cobbler's pegs Environmental Weed

Celtis sinensis Chinese elm Declared Pest Plant (Class 3)

Chloris virgata Feathertop Rhodes Grass Environmental Weed

Cinnamomum camphora Camphor laurel Declared Pest Plant (Class 3)

Conyza bonariensis Fleabane Environmental Weed

Corymbia torelliana Cadaghi Environmental Weed

Cyperus polystachyos Bunchy Sedge Environmental Weed

Gomphocarpus physocarpus Balloon cotton Environmental Weed

Gompholobium foliolosum Fern-leaved Wedge Pea Environmental Weed

Ipomoea cairica Mile-a-minute Environmental Weed

Lantana camara Lantana Declared Pest Plant (Class 3)

Lantana montevidensis Creeping lantana Declared Pest Plant (Class 3)

Leucaena leucocephala Coffee bush Environmental Weed

Ludwigia peploides Water Primrose Environmental Weed

Page 52: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 52

Botanical Name Common Name Status

Megathyrsus maximus Guinea grass Environmental Weed

Melinus repens Red natal grass Environmental Weed

Ochna serrulata Ochna Environmental Weed

Passiflora suberosa Corky passion vine Environmental Weed

Pinus elliottii Slash Pine Environmental Weed

Pteridium esculentum Bracken Environmental Weed

Schinus terebinthifolius Broad-leaved pepper tree Declared Pest Plant (Class 3)

Senecio madagascariensis Fireweed Declared Pest Plant (Class 3)

Senna pendula Easter Cassia Environmental Weed

Sida cordifolia Flannel Weed Environmental Weed

Solanum mauritianum Wild tobacco Environmental Weed

Solanum nigrum Blackberry Nightshade Environmental Weed

Solanum seaforthianum Brazilian Nightshade Declared Pest Plant (Class 2)

Solanum torvum Devil's Fig Environmental Weed

Syragrus romanzoffiana Cocus Palm Environmental Weed

Tecoma stans Yellow Bells Declared Pest Plant (Class 3)

Typhya orientalis Bulrush Environmental Weed

10.5.3 ‘Off Target’ Damage

‘Off target’ must be kept to a minimum, in instances where herbicide applications are not deemed an appropriate method; hand pulling of weeds would be preferred. No desirable specimens, either planted or naturally regenerating/ or existing natives, are to be damaged by herbicide. Any such damage will be rectified at the contractor’s expense at an offset of 2:1. The extent of damage and the offset is to be to the discretion of Superintendent. Trees to be retained on site shall be protected in accordance with AS4970:2009 Protection of Trees on Development Sites.

The initial weeds treatment is to be completed prior to the commencement of the supplementary planting.

Page 53: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 53

10.5.4 Protecting of Existing Vegetation

The existing native vegetation to be retained and protected shall be fenced off (or flagged appropriately) on occupation of the site and shall not be removed unless instructed by the Superintendent. With the exception of the clear trunk of deadwood within the designated areas nominated on the plans. All deadwood must be removed from site.

Failure to comply with the specified protection works may result in an instruction to suspend the works.

Damage to or removal of existing native vegetation to be protected must be reported to the Superintendent and remedial action should be taken to the satisfaction of the Superintendent. Trees and shrubs that are damaged beyond repair shall be replaced with similar sized specimens at no extra cost to the contract.

No materials, fuel or plant shall be stored within the areas so enclosed. No materials, fuel or plant shall be stored within 5m of existing vegetation.

All necessary excavations, earthworks and cultivations shall be undertaken by hand within the canopy spread of any existing vegetation unless express consent of the Superintendent is obtained for specific operations.

Existing site features and vegetation identified on drawings to be retained must be protected throughout the works. Any damage to such features shall be made good under the direction of the Superintendent at no additional cost to the Contract.

10.5.5 Tree Removal

Care shall be taken when removing existing exotic trees not to damage any native trees to be retained. A qualified Arborist (AQF 5) shall be present for the removal of any large trees in close proximity to those that are marked for retention, or that may cause damage to retained trees when removed. Large trees can be left standing as a habitat feature, only where it is deemed to be a safe practice by an AQF Level 5 Arborist.

Upon removal of exotic trees, palms and vegetation matter shall be mulched and disposed off site to an appropriate official refuse centre.

10.6 LANDSCAPE DRAINAGE

10.6.1 Standards

AS 1254 Unplasticised PVC (UPVC) pipes and fittings for storm or surface water applications

AS 2032 Code of Practice for installation of PVC pipe systems.

AS 3500.1 National Plumbing and Draining Code: Water supply

AS 3500.3 National Plumbing and Draining Code: Stormwater drainage

10.6.2 General

The Contractor is to provide for sufficient surface and sub-surface drainage to garden and grass areas to ensure adequately drained soft landscaped areas free from surface ponding water and heavy/ waterlogged soils. Surface and sub-surface drainage is to aid in the healthy growth and continued thriving of all plant stock and grass areas.

Comply with the relevant Australian Standards to the extent that they are relevant and not over-ridden by the specification.

Page 54: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 54

10.6.3 Surface Drainage

When setting out lines and levels of gardens and turfed areas, ensure the accurate formation of grades and cross falls leading to surface catch drains and field inlets; so enabling the areas to dry quickly and surplus water to reach the drainage system in such a way that potential erosion channels and/or wet spots are avoided.

Minimum surface cross falls towards drains and outfalls unless otherwise stated shall be as follows:

• Mulched garden areas 1:40

• Turfed areas 1:80

10.6.4 Sub Surface Drainage

Construct drainage lines using 100mm slotted flexible PVC pipe to AS 2439. All drains to have a minimum 20-40mm diameter rounded gravel cover of 200mm in depth. Complete with house drainage grade uPVC pipe fittings for all junctions and bends. Install in accordance with the manufacturer's most recent written recommendations. Drainage lines are to be laid in accordance with details and generally (but not limited to) to be positioned at 3 meter centres for garden and grass areas in natural ground.

Geotextile Filter: To AS 3705:2012. Permeable polypropylene or polyester fabric capable of retaining 0.25mm particles. Place filter sock over slotted pipe work. Lap all joints to a minimum of 100mm. Tape joints at a maximum of 900mm centres with 50mm wide PVC waterproof tape.

Drainage Medium: Clean crushed blue metal (this is not a dress mulch).

Long falls on lines shall be a minimum of 1:100. Outfalls to lines to be into drainage pits, rubble pits or stormwater lines as indicated on plans.

Particular care shall be taken with placing and compaction of bedding materials and backfill so as not to damage or affect drainage, yet achieve firm consolidation.

10.7 SITE SOIL

10.7.1 Standards

AS 1289 Methods of testing soils for engineering purposes

AS 2223 Garden soil for domestic use

AS 4419 Soils

10.7.2 Interpretation

Definitions

Unwanted matter (in topsoil):

• Stones over 25 mm diameter.

• Clay lumps.

• Weeds and tree roots.

• Sticks and rubbish.

• Material toxic to plants.

Site topsoil texture classification:

Page 55: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 55

• Fine: Clay loam, fine sandy loam, sandy clay loam, silty loam, loam.

• Medium: Sandy loam, fine sandy loam.

• Coarse: Sand, loamy sand. Imported Growing Medium: Topsoil mixture that is brought onto site from an approved and accredited growing media supplier.

10.7.3 Preparation

Weed eradication

Herbicide: Eradicate weeds using environmentally acceptable methods, such as a non-residual glyphosphate herbicide in any of its registered formulae, at the recommended maximum rate. Spot spray only where necessary.

Manual: Regularly remove, by hand, rubbish and weed growth throughout grassed, planted, and mulched areas. Remove weed growth from an area 750 mm diameter around the base of the trees and palms to be retained. Continue eradication throughout the course of the works and during the planting establishment period.

Fill Materials

Fill and subsoil material used to make up levels shall be re-used from previous earthworks operations on site or imported as required and shall be excavated material which is composed of natural site subsoils but free from:

• Logs, stumps or other un-decomposed vegetative material.

• Materials susceptible to spontaneous combustion.

• Clay, of liquid limit exceeding 90 and/or plasticity index exceeding 65.

• Refuse and rubbish, including paper, plastics, rubber, metal and all type of containers.

• Concrete, bitumen, brick, steel, masonry rubble or other deleterious material.

• Toxic substances and compounds that would inhibit healthy plant life.

• Any material not capable of being satisfactorily compacted. Any such material shall be removed from site to the Landscape Subcontractors own tip.

Sandy subsoils are preferred for these works. Clay soils may be used when in a dry state, but extreme care is necessary to ensure the resulting subsoil profiles are not compacted or subject to excess moisture.

Earth mounds

Place clean filling in layers approximately 150 mm thick compacted to 85% of the dry density ratio of the surrounding soil as determined by AS 1289.5.4.1. Minimise slumping and further internal packing down. Construct changes in grade over a minimum width of 500 mm to smooth, gradual and rounded profiles.

10.7.4 Subsoil

Ripping

General: Rip parallel to the final contours wherever possible. Do not rip when the subsoil is wet or plastic. Do not rip within the dripline of trees and shrubs to be retained. Do not rip in the vicinity of existing buildings.

Ripping depths: Rip the subsoil to the following typical depths:

Page 56: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 56

• Compacted subsoil: 300 mm.

• Heavily compacted clay subsoil: 450 mm. Planting beds

Excavated: Trim excavation to bring the subsoil to soil depths specified below finished design levels. Shape the subsoil to fall to subsoil drains where applicable. Break up the subsoil to a further depth of 100 mm.

Cultivation

Cultivation depths (mm):

• Turfed and seeded areas in natural ground: Refer to Materials and Finishes Schedule

• Planting areas in natural ground: Refer to Materials and Finishes Schedule

Services and roots: Do not disturb services or existing required plant stock roots; if necessary cultivate these areas by hand.

Cultivation: Thoroughly mix in materials required to be incorporated into the subsoil. Cultivate manually within 300 mm of paths or structures. Prevent disturbance to footings of buildings and landscape retaining walls. Remove stones exceeding 25 mm, clods of earth exceeding 50 mm, and weeds, rubbish or other deleterious material brought to the surface during cultivation. Trim the surface to design levels after cultivation. Particular attention needs to be made with cultivating and removing of road base with car park planters. Grade sub-grade to sub-soil drains.

Additives

General: Apply additives after ripping or cultivation and incorporate into the upper 100 mm layer of the subsoil.

Gypsum: Incorporate *Natural Gypsum at the rate of 2t/Ha and lightly manually water into subsoil sufficient to begin chemical reaction.

Hydrocell: Incorporate Hydrocell into all planting works, as per Materials and Finishes Schedule

10.8 TOPSOIL

10.8.1 Amelioration Site Topsoil

10.8.1.1 Soil Test and Amelioration Regime The existing (insitu) site topsoil and or reclaimed site topsoil must be tested to determine if the soil requires a per plant amelioration regime implemented as well as a fertiliser tablet. The soil test must occur at the awarded Contractors earliest convenience so not to delay the works in any way. The Contractor must ensure that a full suite of the available existing in situ/ reclaimed site soil (or stockpiled site soil if available) is tested to ensure that the most appropriate amelioration regime is determined.

A full physical and chemical analysis of the soil either carried out by an agronomist or provided by soil scientist.The final report inclusive of soil amelioration regime must be issued to Superintendent for review, and the amelioration must be installed as per the outline within the report.

Minimum of 12 samples must be taken within the extent of works of the contracted site as per landscape documents.

The Contractor shall nominate a square metre cost must be allocated based upon previous experience with ameliorating site soil.

Page 57: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 57

These items may be removed from the contract, the removal of these items will be determine after awarding the tender.

10.8.2 Imported Topsoil (installed as directed by Landscape Architect)

10.8.2.1 Planting Areas General: Imported Premium Grade topsoil for all new planting areas shall be:

• List soil type, manufacturer and reference code where applicable or similar approved equivalent to comply with AS 4419 (2018).

Up to date pH testing and compliance with this standard is required prior to installation. Furnish Superintendent with written test for approval.

10.8.3 Placement

General: Spread the topsoil on the prepared subsoil and grade evenly, making the necessary allowances to permit the following:

• Required finished levels and contours may be achieved after light compaction.

• Grassed areas may be finished flush with adjacent hard surfaces such as kerbs, paths and mowing strips. Contamination: Where diesel oil, cement or other phytotoxic material has been spilt on the subsoil or topsoil, excavate the contaminated soil, dispose of it off the site, and replace it with imported topsoil to restore design levels.

Spreading: On steep batters, if using a chain drag, ensure there is no danger of batter disturbance.

Finishing: Feather edges into adjoining undisturbed ground or against adjoining surfaces.

10.8.4 Soil Gradients

Unless otherwise stated on the drawings, the following maximum gradients shall be adhered:

• Mulched Garden Beds 1:3

• Grassed Areas 1:4

10.8.5 Consolidation

Compact lightly and uniformly in 150 mm layers. Avoid differential subsidence and excess compaction and produce a finished topsoil surface that has the following characteristics:

• Finished to design levels.

• Smooth and free from stones or lumps of soil.

• Graded to drain freely, without ponding, to catchment points.

• Graded evenly into adjoining ground surfaces.

• Ready for planting.

10.8.6 Topsoil Depths and Application

Spread topsoil to the following consolidated typical depths: (refer to drawings for specific details)

• Garden beds in natural ground: Refer to Materials and Finishes Schedule

• Grassed areas generally: Refer to Materials and Finishes Schedule

Page 58: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 58

• Advanced trees in grassed and gardens: 300mm underlay and as detailed.

10.9 FERTILISER Provide proprietary fertilisers, delivered to the site in sealed bags marked to show manufacturer or vendor, weight, fertiliser type, N:P:K ratio, recommended uses and application rates. Store in a dry secure environment. Apply according to manufacturer’s recommendations (rate/reapplication/watering).

10.9.1 Fertiliser Schedule

Location Product Rate

Garden beds Slow Release - Osmocote or similar approved Man. Rec.

Tree plantings Slow Release - Osmocote or similar approved Man. Rec.

Grassing Growforce 301 or similar approved 100kg/Ha

10.10 TURFING

10.10.1 Supply

Obtain turf from a specialist grower of cultivated turf.

• Areas designated as “Turf” on drawings shall be freshly cut and of the following specification: A Grade Turf.

• Turf to be free from nutgrass or other noxious weeds or any other material deleterious to plant growth.

• Deliver the turf within 24 hours of cutting, and lay it within 36 hours of cutting. Prevent it from drying out between cutting and laying.

10.10.2 Fertilising

Primary

Before turfing, apply fertiliser of 14:15:10 N.P.K. or approved similar composition at the rate of 100g per m2 and rake into the prepared soil.

Secondary

In the last week of the Establishment Period and after mowing, apply Ammonium Sulphate fertiliser (20:0:0) N.P.K at the rate of 12g per m2 or other approved fertiliser at an equivalent rate of nitrogen. Prepare as a solution not stronger than 25g of fertiliser per litre of water and apply evenly to the turfed area. Lightly water after application.

10.10.3 Laying

General: Lay the turf in the following manner:

• In stretcher pattern with the joints staggered and close butted.

• Parallel with the long sides of level areas, and with contours on slopes.

• To finish flush, after tamping, with adjacent finished surfaces of ground, paving edging, or grass seeded areas.

Page 59: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 59

• Strip turf laying: Close butt the end joints and space the strips 300 mm apart. Apply a layer of top dressing between the strips of turf. Finish with an even surface.

10.10.4 Tamping

Lightly tamp to an even surface immediately after laying.

10.10.5 Pegging

On steep slopes peg the turf to prevent down-slope movement. Contractor to remove the pegs when the turf is established.

10.10.6 Watering

Water immediately after laying until the topsoil is moistened to its full depth. Continue watering to maintain moisture to this depth. Keep the grass in a healthy weed free condition. Refer section 12.10.3 for watering regime.

10.10.7 Mowing

Mow to maintain the grass height within the required range. Do not remove more than one third of the grass height at any one time. Carry out the last mowing within 7 days before the end of the planting establishment period. Remove grass clippings from the site after each mowing.

10.10.8 Top Dressing

When the turf is established, mow closely, remove cuttings and lightly top dress to a depth of 10mm with an approved top dress soil. Work the dressing well into the joints and correct any unevenness in the turf surface.

10.11 GRASS SEEDING

10.11.1 Site Preparation

Remove all weeds, debris, rubbish, stones and other coarse material from area to be seeded.

Decompact/Cultivate subgrade to minimum depth of 100mm.

Power harrow entire area to be seeded to remove ruts and hollows caused by cultivation.

Supplement organic content of existing sub-grade by applying chicken manure additive (400kg/ha.) or Dynamic Lifter to manufacturer’s specifications.

Adjust pH to range of 5.5-6.5 with application of lime or flowers of sulpur.

10.11.2 Application of Seed

Application of seed shall commence no more than one week after cultivation of existing sub-grade layer.

Apply an improved complete fertiliser (N.P.K. ratio 14:15:10) at rate of 100g/m2

(1 tonne/ha) not more than 48 hours before seeding commences.

Grass seed mix shall consist of:-

MATERIAL/ADDITIVE RATE

Green Couch 40kg/ha

Japanese Millet 20kg/ha

Page 60: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 60

Where the sowing of seed is a separate operation, the specified fertiliser shall be broadcast after watering and prior to seeding.

Where the sowing of the seed and the broadcasting of fertiliser can be achieved in one operation, the seed and fertiliser shall be broadcast after the watering.

After sowing of seed is complete, roll entire area to achieve an even, mowable surface finish.

10.11.3 Watering – Turf and Seeding

For seeded areas, water the bed thoroughly immediately after rolling until soil is wet to a minimum depth of 100 mm.

The watering in weeks 8 and 12 shall occur immediately after fertilisation.

The method used for watering shall not cause any erosion.

Further watering should be carried out as below:

WEEK AFTER GRASSING WATERING FREQUENCY

24 hours before Once only

Immediately after Once only

1 Once every day

2, 3, 4 Once every second day

5, 6, 7, 8, 9, 10, 11, 12 Twice every week

10.12 PLANTING

10.12.1 Plant Material Quality Specification – Nursery Stock

All plants shall be true to scheduled nomenclature, well formed, hardened off and disease free nursery stock. They shall be container grown in potting soil with root system firmly established but with no large roots growing out of the container. No plant shall be pot bound.

All trees supplied shall comply with AS2303:2018 Tree stock for landscape use.

The condition of plant stock shall be such that future growth shall be strong and typical of the species. Stock that shows signs of latent conditions evident of defective nursery practices (such as ‘spiralling') shall be deemed unacceptable.

The Contractor shall allow for an independent Horticultural certification of all stock prior to delivery to site.

The certification shall confirm the following:

• stock is disease free and healthy;

• rootball has adequately grown into the container appropriate to the specified size;

• Stock shows no evidence of spirally, being pot bound, or other undesired outcomes of growth at the nursery.

The stock (especially trees) shall be of a standard that should an independent inspection be carried out at a minimum of 12 months from date of planting, the stock (all parts of the tree) would deemed to be typical of a

Page 61: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 61

healthy, thriving specimen. This does not include external factors, post planting of which the nursery would not have control over.

All plants shall be grown in accordance with Nursery Association standards and AS 2303:2018. Correct nursery/ growing practices shall help to ensure the long term health and viability of the plant stock on site after planting.

Trunk and Branch Requirements:

Ensure that trunks and branches are free of dieback, cavities, sunburn and secretions. Trunk and branches are to be evenly tapered and textured typical of the specie. Plant material is to be matured enough to support themselves without staking. Branches should be evenly distributed, exhibit a full well formed canopy that occupies a minimum 1/3 of the overall current height. Specimens are to be prepared for their intended purpose. For ex-ground stock where canopy modification is intended, provide details of how each specimen’s visual character will be at time of delivery.

Foliage Requirements:

Foliage shall be evenly distributed across the crown in proportion to the branching structure as well as be of a true colour typical of the specie, dense and of good size. Ensure foliage is free of deficiencies and burn. Plant material is to be ‘hardened’ to full sun and exposed conditions by the supplier to ensure successful plant establishment into the site environment. For ex-ground stock apply an anti-transpirant.

Size and Form Requirements:

At the time of the last plant stock review prior to site delivery, plant material is to conform with the specified minimum plant sizes in the Plant Schedule. Plants shall not exhibit signs of having been stressed at any stage during their development due to inadequate watering, excessive shade/sunlight, suffered physical damage or have restricted habit due to growth in nursery rows.

10.12.2 Plant Material Quality Specification – Ex-ground Stock

All ex-ground stock shall be root-pruned, allowing adequate time, appropriate to the species for preparation; site conditions and season shall also be considered. Root ball sizing as a general rule should be large enough to support the specimen without being dependent on the use of guying. This is not to say that guying is not permitted, but is discouraged as the primary support mechanism for the weight stabilizing of the specimen. The roots of advanced plant material should be sound and free from breaks, torn or bruised bark, crown gall and nematodes. Structural roots where cut are to be dressed with 3 coats of bituminous fungicidal paint. Root ball sizing is to minimize stock, canopy modification and recovery time for re-establishment into the new environment. The root ball is to be square with a flat base, straight vertical sides and well balanced to help find its natural centre of gravity for a vertical position once placed. Maintain in a moist state throughout the preparation process. Wrap in Hessian secured with steel bonds to ensure that the base remains intact. Do not provide stock, which have been established from incompatible soils to that of site.

10.12.3 Myrtle Rust All stock is to be checked for Myrtle Rust. Myrtle Rust is a serious fungal disease that affects plants within the Myrtaceae family (e.g. Lilly Pilly, Eucalyptus, Tea Tree and Bottle-brush species) for further information on Myrtle Rust refer regularly to the Department of Agriculture and Fisheries, and or BioSecurity Queensland’s website to ensure that the Contractor has the most recent advice on Myrtle Rust.

The Contractor is to ensure all tools, plant and clothing has been cleaned prior to coming onto site if they have been working within a known Myrtle Rust area.

In the instance that Myrtle Rust is either found on the imported plant stock or within the site itself, firstly contact the Superintendent and then contact Biosecurity Queensland on 13 25 23.

Page 62: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 62

10.12.4 Approval The Superintendent may elect to inspect planting stock prior to planting, and will notify the Landscape Subcontractor of this intent in writing. Inspection of planting stock by the Superintendent prior to planting does not constitute acceptance of the planting material, and the Superintendent may reject planting material if it fails to comply with specified requirements at any stage of the works. If it is deemed more convenient, inspection of the stock prior to delivery may be arranged at the nominated nursery. The Landscape Subcontractor is to coordinate these visits 2 (two) weeks prior to delivery to site. The Superintendent is under no obligation to inspect stock at the nursery.

The Superintendent has the right to reject any plants not meeting the requirements of the specification and schedule.

The approval of stock (either prior to delivery, prior to planting, on practical completion or at off-maintenance) by the Superintendent is based on the conformance of the stock with following performance criteria:

• specified size parameters (height, canopy spread, girth size),

• container size,

• general appearance and health of the plant. The Superintendent may select at their discretion, 1 no. specimen per species on which to examine the general condition of the root ball (by removing the container/ bag). This however is not deemed approval of stock with inherent/ latent defects (as a result of nursery practices) leading to the long term growth and health of the plants.

As set out in section 8.12.1, the Contractor shall allow for an independent Horticultural certification of all stock prior to delivery to site. This certification shall be forwarded to the Superintendent.

When species and/or sizes of plants are unavailable obtain instructions from the Superintendent before proceeding. No substitutions shall be made without the prior approval of the Superintendent.

10.12.5 Delivery & Storage

Programming of delivery of plant material is to be arranged between the Contractor and the nursery to minimise delays to the plant program and to minimise damage to plants during the transportation and unloading. The Contractor must satisfy themselves as to the quality of the plants before arranging delivery of them. Claims for loss because of supply of inferior material will not be accepted.

Inspect stock with the Superintendent and the Contract Supplier once the stock has arrived on site prior to unloading.

Do not store stock on site temporarily. Deliver plant material to the site on a day-to-day basis, and plant immediately after delivery.

Store plants so they of their containers will not be damaged. Water and maintain all plants as necessary. Provide all lifting equipment for stock delivered to site. Inspect stock with the Superintendent and the Contract Supplier once the stock has arrived on site prior to unloading.

Protection: Prevent plant stock from damage. Inspect all stock for disease and pests. Report on recovery success and give notice of site plant stock, which will not recover from relocation.

Replacement: Replace damaged or failed plants with plants of the same type and size.

10.12.6 Plant Schedules

Refer to the plant schedules attached.

Page 63: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 63

Plant numbers on drawings override numbers in the schedule. Contractor is to check and verify all plant numbers and inform Superintendent of any major inconsistencies between the schedules and the drawings.

10.12.7 Preparation

Excavate or fill areas as necessary allowing for depths of modified site soil and mulch. Remove and destroy any grass or weed growth present. If noxious weeds are found, such as nut grass, in the area to be cultivated and prepared, inform the Superintendent before proceeding.

Decompact existing ground to a minimum of 100mm. In areas of cut or where compaction of the subgrade has occurred deep rip sub-grade to minimum depth of 200mm.

Carry out any sub-surface drainage works as specified and/or shown on drawings.

Spread soil as specified to depths as shown in details ensuring minimum thickness shown on drawings after settlement.

As the ground is worked, all garden areas are to be raised or crowned in the centre to assist in soil drainage unless in a designated overland flow path.

Finished level of soil at paths to allow for settlement and for the placement of mulch or turf as specified.

10.12.8 Individual Plantings in Grassed Areas

Excavate planter pits as per details. Break up the base of the hole to a further depth of 100 mm, and loosen compacted sides of the hole to prevent confinement of root growth. Create seepage channel drain where subsoil is a hardpan nature to discharge subsurface water.

10.12.9 Ripline Planting

Rip the row and excavate a plant hole for each plant large enough to accept the root ball plus 0.1 m³ of backfilling with topsoil. Clear weeds and other vegetative material within 300 mm radius of the plants. If planting holes are excavated by mechanical means increase the hole size by 100 mm and loosen compacted sides to prevent confinement of root growth.

10.12.10 Locations

If it appears necessary to vary plant locations and spacing’s to avoid service lines, or to cover the area uniformly, or due to modifications to driveway locations, or due to striking rock, or for other reasons, give notice.

10.12.11 Planting Conditions

Do not plant in unsuitable weather conditions such as extreme heat, cold, wind or rain. In other than sandy soils, suspend excavation when the soil is wet, or during frost periods.

10.12.12 Watering

Thoroughly water the plants before planting, immediately after planting, and as required to maintain growth rates free of stress throughout the contract period. Hand water if irrigation system is not operational. The Landscape Subcontractor is to allow for temporary establishment watering methods of shrub areas such as watering trucks in the event of water being unavailable.

10.12.13 Fertilising

Fertiliser shall be an approved prolonged release type. Place around plant approximately 1/3 the depth of root ball, but no more than 250mm depth and approximately 50mm away from root tips. Place at time of planting

Page 64: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 64

at the rate recommended by the manufacturer. Furnish evidence of manufacture's recommendations and the quantities actually used.

10.13 MULCHING Mulch

General: Provide mulch which is free of deleterious and extraneous matter such as soil, weeds and sticks.

Standard: To AS 4454.

10.13.1 Site Mulch (installed as directed by Landscape Architect)

In the instance that mulch can be sourced from site, it is the Contractors responsibility to check that the site mulch (sourced from site cut vegetation) has been ‘pasteurised’ prior to being used within the rehabilitation zones. Pasteurisation will significantly reduce the number of plant and animal pathogens as well as plant propagules (seed bank).

The following dot points are the minimum requirements to ensure the mulch has been pasteurised (based on AS4454-2012 – Composts, soil conditioners and mulches).

1. Designate a location on site that the mulch can be stored.

2. Site mulch stockpiles should not exceed 1.5-2 meters high; ensure access is available from all sides. The designated height is mainly for safety reasons and for the ease of turning the material.

3. Turn the outer material into the centre of the stockpile at a minimum of every three days, with the goal of the internal temperature reaching a minimum of 55˚C.

4. Turn the stockpile a minimum of three times (three separate events).

5. If the above process cannot be abided by, just ensure that the high temperature of 55˚C is reached while tilling the stock pile over a 2-3 week period.

6. Note: once the above process has been achieved, and if the site mulch stockpile is to be left for a prolonged period of time before being used. Ensure the mulch is at least turned on a 4-6 week basis, to keep the mulch viable.

Site Mulch Minimum requirements

• Site mulch to be free of deleterious and extraneous matter such as soil, turf, rocks and sticks.

• Site mulch to be double tub ground (preferable) and a maximum stick length of 150mm

• Material not permitted in mulch stock piles: weed species such as privet, camphor laurel, coral tree, poplar, willow, pine and lantana, other noxious weeds.

10.13.2 Imported Organic Mulch Types

• Imported Organic Mulch: Forest Blend Mulch (maximum stick length 50mm).

Material not permitted: Leaf and plant matter from any other species (especially weed species such as privet, camphor laurel, coral tree, poplar, willow, pine and other noxious weeds).

Page 65: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 65

10.13.3 Placing Mulch

General: Place mulch to the required depth, clear of plant stems. Spread mulch so that after settling it is smooth and evenly graded between design surface levels sloped towards the base of plant stems in plantation beds, and not closer to the stem than 50 mm in the case of gravel mulches.

Extent: To surrounds of plants planted in riplines and grass areas, provide mulch to 1000 mm diameter. Mulch areas to Ex-ground trees to be 1800 diameter.

Spread mulch to the following depths:

Feature Planting Areas: As per Materials and Finishes Schedule

Rehabilitation Planting Areas: As per Materials and Finishes Schedule

Mulch Only Areas: As per Materials and Finishes Schedule

10.14 SPRAYING Notice

Immediately give notice of evidence of insect attack or disease amongst plant material.

Spraying

Where required, spray with insecticide, fungicide or both.

10.15 STAKES AND TIES

10.15.1 Stakes

Material: Hardwood, straight, free from knots or twists, pointed at one end.

Installation: Drive stakes into the ground at least one third of their length, avoiding damage to the root system.

Stake sizes:

• For plants >2.5 m high: Three 50 x 50 x 2400 mm stakes per plant.

• For plants 1 - 2.5 m high: Two 50 x 50 x 1800 mm stakes per plant.

• For plants < 1 m high: One 38 x 38 x 1200 mm stake per plant.

10.15.2 Ties

Ties shall be 50mm wide hessian webbing or 25mm wide heavy-duty polythene strips. (Plastic coated ties are not acceptable). Fix ties in a figure of eight pattern and staple to stake with galvanised wire staples. In cases where strong ties are required past the maintenance period, 50mm UV stabilised woven polypropylene ties should be used.

10.16 GUYING Requirement

While guying is not encouraged for ex-ground planting in natural ground (if required, use discretion as to the appropriateness of its application), the Landscape Subcontractor is to be responsible for the stability of the tree for the period of establishment. Provide temporary support where necessary to trees (over 3m tall), root balls or stakes using galvanized steel cables. Galvanised cables to pass through reinforced rubber or hose when in contact with the tree. Any damage may result in tree replacement. Ensure enough slack is allowed in

Page 66: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 66

cable for minor movement and stabilisation of tree roots. All guying is to be sufficient to support the specimen from overturning in adverse conditions.

10.17 SITE PLANT STOCK SURGERY

10.17.1 Scope

Any remedial works to be carried out on site to mature or ex-ground stock shall be carried out by an experienced arboriculturalist.

10.17.2 Notice

Give 24 hours’ notice to the Superintendent to inspect damage and give approval to continue. Report the degree of likely visual adjustment to specimens as part of notice.

10.17.3 Qualifications

Employ suitably qualified and experienced persons to carry out tree surgery work in a safe and progressive manner. Provide evidence of all relevant current insurance certificates prior to work commencement.

10.17.4 Pruning

General: Comply with the recommendations of AS 4373. Balance the canopy for aesthetic and crown/root load criteria.

10.17.5 Operations

Remove dead and decayed wood or limbs that have been broken. Make neat cuts into live wood, which allows water to run off. If the trees show signs of deterioration after the work has been done, carry out a program of feeding or soil amelioration such as soil aeration, irrigation or incorporation of organic material. Continue this program until the end of the planting establishment period.

10.17.6 Precautions

Avoid damage to trees being treated or to nearby trees and surroundings. Do not use trees as anchors for winching operations or bracing. Provide bracing as necessary before cutting to prevent uncontrolled breakages and damage to surroundings.

10.17.7 Dressing

Prevent incursion of rot or disease after cutting.

10.17.8 Root Pruning

Do not unduly disturb the root system of plant stock that would threaten the stability of the specimen from supporting itself in an upright position.

10.17.9 Plant Waste

Where practical, mulch all material taken from pruned plant stock for re-use on garden beds. (Incorporate into imported mulch to diffuse impact). Otherwise all waste is to be removed from site. No waste from declared weed species and those highlighted by the local authority are to be used as mulch. Remove and dispose of this waste from site.

Page 67: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 67

10.18 WATERING

10.18.1 General The watering for the landscape works is to be carried out as specified in Irrigation section

10.18.2 Regulations The Landscape Subcontractor is to liaise with the Local Authority as to any water restrictions that may exist in the area.

10.19 TREE GUARDS

Supply and install tree guards to each tubestock as indicated on the drawings. Guards are to be 450mm x 200mm x 200mm Ezi-guard Tree Guards (or similar approved) and are to be installed as per the manufacturers specification. The plants are to be monitored during the establishment period, and once the plants have shown significant growth, the tree guards are to be removed from site to allow the plants to grow unaided. Tree guards are not to be used where over land flow may occur (i.e. swale, bio-retention basin.) Final numbers of guards to be confirmed on site.

10.20 HABITAT BOULDERS

Supply and install habitat boulders, sourced from the civil works, and placed into random groups of 3-5. Nominal sizes of rocks to range from 500mm to 1000mm (where possible). Ensure that the rocks are firmly positioned onto the ground, and will not move if they are walked upon.

10.21 EROSION CONTROL

10.21.1 TEC Mat Jute

In the instance erosion control is required, supply and install TEC Mat Jute mat to nominated areas. Jute Mat shall be ‘’Tec Mat Jute - Heavy’’ or a similar approved alternative, installed to manufacturers specification paying particular attention to trenching the matting into the ground at the top of slopes and pinning as per the manufacturers specification, and carefully overlapping of the mat (upstream roll laid over downstream roll). Use 300mm long u-pins to all matting. A nominated amount is to be priced for Jute Matting. Jute Matting to be coordinated with Mulch/Jute Squares so no double up can occur.

10.21.2 TEC Mat Jute Mesh

In the instance erosion control is required, supply and install jute mat to nominated areas. Jute Mat shall be “TEC Mat Jute Mesh” or a similar approved alternative, installed to manufacturers’ specification paying particular attention to trenching the matting into the ground at the top of slopes and pinning as per the manufacturers’ specification, and carefully overlapping of the mat (upstream roll laid over downstream roll). Use 300mm long u-pins to all matting. Jute mesh must be installed as per the manufacturer’s specification. A nominated amount is to be priced for Jute Meshing. Jute Mesh to be coordinated with Mulch/Jute Squares so no double up can occur.

Page 68: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 68

10.21.3 TEC Mat Fibre Mat (Squares)

Each plant must have a TEC Mat Fibre Mat Square, to nominated areas. Supply and install TEC Mat Fibre Mat (or similar approved) to nominated areas Ensure that at least 4 appropriately sized pins are used , where 2 pins are installed to the side of any potential overland flow.

10.21.4 TEC Mat Coir

In the instance erosion control is required, supply and install TEC Mat Coir to nominated areas. Coir mat shall be “TEC Mat Coir 9” or a similar approved alternative, installed to manufacturers’ specification paying particular attention to trenching the matting into the ground at the top of slopes and pinning as per the manufacturers’ specification, and carefully overlapping of the mat (upstream roll laid over downstream roll). Use 300mm long u-pins to all matting. Coir mat must be installed as per the manufacturer’s specification. A nominated amount is to be priced for TEC Mat Coir. TEC Mat Coir to be coordinated with Mulch, Jute Squares, Jute Mesh and Jute Mat so no double up can occur.

10.21.5 Sedimentation Fence

In the instance sedimentation control is required, supply and install sedimentation fence to nominated areas (as site instructed). Sedimentation fence to be Filter Fence with stakes (or similar approved), installed to manufacturers specification paying particular attention to trenching the matting into the ground. The fencing should be cleaned regularly, minimising build up to the rear of the fence. A nominated amount is to be priced for Jute Matting.

10.21.6 Site Sourced Erosion Controls

Site lopped trees can be utilised as in conjunction with the aforementioned erosion controls. Logs can be installed following the contours and fixed using hardwood 500mm x 50mm x 25mm stakes. Ensure stakes are cut flush to the top edge of the log. Logs are to be staggered to ensure any over land flow will be slowed and moved into a multiple of directions to minimise potential erosion issues. A log stock pile is to be nominated by the Principal Contractor, where the logs should be cut to man handleable sizes (no longer than 2.5m and using trees or branches of a girth of no greater than 160mm diameter). Existing felled logs are not to be removed from adjacent open or natural areas as these already have habitat value. The only exception for removing logs is within the Fire Load Reduction Zone.

Any hollows found in trees after felling are to be cut to a man handleable size and moved into the rehabilitation extents. However all trees should be checked for hollows prior to felling as these are conditioned to be protected as per section 6.5.6 - Significant Habitat Trees.

10.21.7 Coir Logs (Eco Log)

In the instance no site sourced erosion controls are available, over land flow can be mitigated with the use of 3m long x 300mm EcoLog Coir Log (or similar approved). A supply and install price must be supplied, for the coir logs including either the propriety pin and or 50mm x 50mm HW stake (and nominally length pending on soil type). The Hardwood peg must impale the coir logs to ensure the coir logs do not move. Otherwise installed as per the manufacturer’s specification. Coir logs placement as directed on site.

Page 69: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 69

11 COMPLETION – MAINTENANCE (Post Practical Completion)

11.1 PLANTING ESTABLISHMENT Establishment/ Maintenance Period

The planting establishment period commences at the date of practical completion as set out by the Superintendent in a written certification to the Landscape Subcontractor.

• General Softscape Areas: 12 weeks

11.2 GENERALLY Maintenance Period

General softscape maintenance shall commence upon the completion of the 12 week Establishment Period as set out by the Superintendent in a written certification to the Landscape Subcontractor.

• General Softscape Areas: 12 Months

11.2.1 Maintenance Requirements

Following the date of Practical Completion, the Contractor shall maintain all the landscape areas in accordance with the clauses within this section for the periods stated below.

The Contractor shall maintain the whole of the grassed and planted areas in a manner which ensures the establishment of healthy and vigorous plants and a close textured, weed free sward and which creates a tidy weed free appearance. Allowance shall be made in pricing for watering to maintain all subjects in a healthy moist condition to facilitate optimum conditions for early establishment.

Throughout the planting establishment period, carry out maintenance work including, watering, mowing, edging, weeding, rubbish removal, fertilising (including Kelpak root stimulants to all plant stock ≥ 100L), pest and disease control, reseeding, returfing, staking and tying, replanting, cultivating, pruning, hedge clipping, aerating, reinstatement of mulch, renovating, lawn top dressing, and keeping the site neat and tidy.

During the maintenance period the Contractor will be expected to: -

• Establish a regular pattern of site visits throughout the maintenance period.

• Carry out routine maintenance operations.

• Correct any defects, which become apparent during the earliest suitable weather conditions.

• Attend hand-over meetings with Orchard (Pebble Creek) Development Pty Ltd, Logan City Council and Economic Developments Queensland, and any regular meetings with the Superintendent to monitor defects and maintenance.

The Contractor will be deemed to have allowed for one monthly visit at a minimum within this period, but should not assume that this will be sufficient to discharge the requirements of the specification and should furnish the Superintendent a program of visits for Establishment and Maintenance periods.

11.2.2 Arisings and Deleterious Material

All debris, including grass clippings, unless otherwise stated and arising from the performance of the works shall promptly be removed from the site and the Contractor will be required to make good any damage at their own expense, or bear any cost incurred through his failure to comply with this requirement.

Page 70: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 70

11.2.3 Pesticides and Herbicides

The Contractor must only use chemicals specifically approved for the purpose for which it is intended and the conditions of approval for the chemicals and any relevant code of practice.

The Contractor will consider in every instance whether the use of chemicals is strictly necessary before application.

Herbicides used to kill perennial weed growth shall be appropriate foliar applied, non-residual, translocated herbicides.

11.2.4 Defects Liability (General Works) The defects liability period for general works will run for a period of 52 weeks from Practical Completion, concurrently with the plant establishment and maintenance periods.

The Contractor will be entirely responsible for the complete replacement of the following, due to defective materials or workmanship but excluding any damage sustained through vandalism:

• All hardscape items

• Concrete Works, Block Work and associated works

• Stone Works

• Fencing Works

• Furniture Items

• Other hard elements of the landscape works

The defects liability period for the general plant stock shall be for the duration of the establishment and maintenance periods.

Replacement items will be of equal size, species and quality to those specified, and the Contractor will be responsible for the complete repair and reinstatement to the reasonable satisfaction of the Inspecting Officer and for employer. Works to be carried out as soon as possible.

11.2.5 Programming Works

The Contractor will allow for carrying out all maintenance works in such a manner to avoid unreasonable disturbance of any buildings and adjoining works not part of the contract.

11.2.6 Litter

Remove all litter and deleterious material from planting, grass/turf and footpath areas at the time of each main visit (no less than monthly).

11.2.7 Handover Requirements

At Completion (the end of the maintenance period) the site will be presented in a pristine state. All shrub beds tree planting areas shall have been weeded, cleared of litter, all tree ties, stakes and other accessories shall have been checked, grass areas mown and associated hard surfaces pathways swept, prior to inspection.

11.2.8 Watering

Generally ensure that all plant and grass areas receive adequate water during the establishment and maintenance periods to enable them to establish and thrive. The Contractor is to set up a watering program

Page 71: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 71

for these periods for which he shall obtain approval from the Superintendent. Adequate coordination must be made with the Logan City Council and the respective tenants to ascertain the optimum times for obtaining and distributing water.

Minimise the occurrence of water spillage and distribution onto hard paved areas.

Repair any damaged components of the irrigation system as soon as possible. Monitor the major water delivery points of the system, such as pop ups to ensure the correct throw of water.

11.3 MAINTENANCE OF TREES General

Maintain tree stock to ensure the establishment and continued growth of all the planted trees to provide well-structured canopies and self-supporting root growth. All trees, especially ex-ground stock are to be monitored on a regular basis for signs of ill health and or disease. Independent advice shall be sought from an Arborist as to the condition of any failing stock and suggested remedial works shall be made by the Arborist.

11.3.1 Weed Control

Maintain tree pits/rooting area weed free throughout the establishment period. Trees in grass are to be maintained with mulch ring in a 1.0 m diameter circle around the trunk for the establishment period of this contract, and thereafter unless the Superintendent otherwise directs. Ex-ground planting may vary from this.

11.3.2 Watering

Ensure the continued and adequate watering of all areas during the maintenance period according to the relevant clauses on watering in the specification.

11.3.3 Stakes, Ties and Guying Systems

Inspect all tree stakes and ties and guying systems regularly. Adjust ties as necessary and replace damaged or broken accessories as and when necessary.

Allow for removing any redundant accessories from trees, which are well established. On ex-ground tree stock adjust any guys and turnbuckles as necessary to constantly maintain stability.

11.3.4 Tree Pits

Inspect tree pits in grass areas regularly for signs of settlement, allow for scraping back of bark mulch and supply of additional backfill and respreading of bark mulch as necessary. Allow for top up of bark mulch to specified depth at the end of the growing season to all tree pits in grass.

During dry weather conditions check mulch to ensure it does not become a fire hazard. If necessary, inform the Supervising Officer and thoroughly dampen the whole depth of mulch.

11.3.5 Pruning

Inspect tree canopies regularly for shape, dead and diseased wood. Allow for formative pruning under the direction of the Superintendent to ensure the development of an even crown of good shape.

Allow for pruning out of dead/diseased wood as necessary. Any of these works are to be carried out by a qualified arborist.

Page 72: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 72

11.3.6 Failures and Replacements

Advise Superintendent of any failures and allow for the removal from site of any trees, which fail to establish. Replace as soon as possible. Monitor and report any incidents of malicious damage.

11.3.7 Spraying and Dusting

The Contractor is to include in their prices for the spraying and dusting required against pests or diseases.

11.4 MAINTENANCE OF SHRUBS AND GROUNDCOVERS General

Maintain all planted areas to ensure the establishment and continued growth of all shrub/ground cover material. Areas shall be maintained in such a way as to ensure shrub and ground cover material is encouraged to form a mass planting effect.

11.4.1 Weed Control

All shrub and ground cover planting areas are to be kept weed free through the use of chemical, mechanical and hand weeding as appropriate to the type of planting, its prominence and species involved.

Translocated herbicides should be used in preference to contact products, and where applied in ornamental areas re-visits to remove dead growth will be required.

11.4.2 Pruning

Inspect planting areas regularly and prune out dead or diseased growth as and when discovered.

11.4.3 Ground Cover

Inspect areas of ground cover planting regularly. In areas of compacted soil surface lightly fork soil to improve establishment. Cut back plants significantly overhanging kerbs or paths in a manner appropriate for the species and to the approval of the Superintendent.

11.4.4 Dusting and Spraying

Allow for regular inspections and spraying and dusting as may be necessary to control pests and diseases on plant stock. Report any occurrences to the Superintendent.

11.4.5 Replacements

Monitor plant growth and allow for the removal from site of any plants, which fail to thrive, and the levelling up of the planting area. Advise the Superintendent of number of plant failures after each maintenance visit.

Monitor planting areas and report any incidents of malicious damage or theft.

11.4.6 Mulch

Inspect mulch depths to all planting areas regularly and allow for tidying and topping up levels to specified depths as required.

Page 73: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 73

11.4.7 Fertilising

Fertilising frequency schedule – Trees and Gardens:

Location Product N:P:K Rate

Gardens Natrakelp or sim approved As per package. 3 monthly applications as per man. recom.

Tree specimens Natrakelp or sim approved As per package. 3 monthly applications as per man. recom.

Note: All native plantings are to be fertilised with products < 3% phosphorous.

11.5 GRASS MAINTENANCE Mowing (General Areas)

Grass shall be cut as necessary to maintain a height of between 10-15mm.

All grass cuttings shall be boxed and removed from site. The Contractor shall take special care to avoid grass cuttings from littering adjacent surfacing.

11.5.1 Grass Edges

The Contractor shall after each cut ensure that edges abutting paths, boulders, road kerbs and trees are kept neat using a suitable edging tool to clean straight lines or smooth curves.

11.5.2 Defects and Damage to Grassed Areas

The Contractor shall replace any areas of grass seed or turf which are failing to thrive for reasons of workmanship inadequate maintenance and materials not in accordance with this specification entirely at his own expense, during the earliest suitable weather conditions and with turf which meets the original specification.

11.5.3 Shrinkage

Any shrinkage below finished levels shall be made good with fine topsoil and turf to match existing grass. Damage occurring through the spillage of oil, petrol, diesel or chemicals shall be made good by replacing with new grass turf to match existing. Such making good shall be entirely at the expense of the Contractor and to be carried out at the first practical opportunity.

11.5.4 Aeration

If it becomes necessary to aerate the soil this operation shall be undertaken with approved machinery when soil conditions are such as to ensure the proper penetration of the tines without causing damage to the grass.

11.5.5 Herbicide Treatment of Grass Areas

The Contractor shall spray actively growing grass areas with a suitable agreed selected herbicide to eliminate broad leafed weeds. Spray only in calm conditions and prevent spray drift onto adjacent planting. The Contractor will not spray within 3 days after or before a cut, when rain is imminent or in drought conditions. All chemicals to be applied as per manufacturer’s instructions.

11.5.6 Spot Weed killing

The Contractor shall spot treat all perennial weeds with a suitable agreed herbicide at the manufacturers' recommended strength and rate.

Page 74: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 74

Mowing Frequency

Growing Season Location Frequency

Active Irrigated Weekly

Inactive Irrigated Fortnightly

Active Non Irrigated Fortnightly

Inactive Non Irrigated Monthly

Fertilising Frequency Schedule – Grassed Areas

Season Product N:P:K Rate

Spring GF201 10.1:3.3:9.5 400 kg/Ha

Summer GF303 15.2:2.9:10.7 300 kg/Ha

Autumn GF420 10.8:3.8:20.3 400 kg/Ha

Winter GF420 10.8:3.8:20.3 400 kg/Ha

Note: Minimum 3 fertiliser applications per year.

11.6 TIMBER WORK

11.6.1 Fixings

Re-tighten or replace any screws, bolts and other fixings that have become loose or insecure since construction so as to guarantee the stability, integrity and or the original purpose of the structure/ item.

11.6.2 Finishes

Where called for in the specification, apply subsequent follow-up coats of stain, paint or oil finish as per the manufacturer’s instructions. If the manufacturer’s recommendations call for yearly reapplications, apply as required.

11.6.3 Finished Surfaces

Where the timber surface deteriorates or develops splinters, the contractor is to sand down, and make suitable the surface for contact as intended for the item. Any surface fault or unsafe element is to be rectified as part of the maintenance works.

11.7 COMPLETION

11.7.1 Product Warranty

Submit the supplier's written statement certifying that plants are true to the required species and type, and are free from diseases, pests and weeds.

11.7.2 Maintenance Manual

Submit maintenance logbook at completion of establishment period.

Page 75: LANDSCAPE WORKS SPECIFICATION

Orchard (Pebble Creek) Developments Pty Ltd Landscape Works Specification PEBBLE CREEK DEVELOPMENT ENTRY ROAD AND MOUNTAIN RIDGE ROAD

SLR Ref No: 620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx

March 2019

Page 75

11.7.3 Cleaning

Stakes and ties: Remove those no longer required at the end of the planting establishment period. Remove guying only if specimens are self-supporting.

Temporary fences: Remove temporary protective fences at the end of the planting establishment period.

Page 76: LANDSCAPE WORKS SPECIFICATION

620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx Page 1 of 2

APPENDIX A Materials and Finishes Schedule

Page 77: LANDSCAPE WORKS SPECIFICATION

MATERIALS and FINISHES SCHEDULEPEBBLE CREEK- ENTRY ROAD AND MOUNTAIN RIDGE ROAD- LANDSCAPE WORKS

Issue A Date: 13.03.2019

Code/Name Item Product Description SupplierSample required to be approved in addition to  specification.

Certification Notes

Existing Tree Existing TreeExisting trees to be retained and protected during construction of the landscape works.  Any damage to the tree shall result in the replacement of the tree at the contractors expense.

NA NO 

NA, unless tree is damaged in which case an arborist's report must be furnished by the contractor outlining extent and potential replacement 

Protection shall be star pickets and 3 evenly spaced strands of wire to be placed around drip line of tree. 

Contractor to have a level 5 Arborist supervision for all excavation works within 10m of exisitng tree protection zone. 

Proposed Trees Ex‐Ground, 45L and 25L Tree Stock

All trees planted in accordance with details and specification 100mm depth Site Mulch (transported from nominated location on site) Amerliorated site soil as shown in landscape detailsWatering tube‐ Minimum 50mm AG Tube with Geofabric Sock.Stakes and Hessian Ties installed as per landscape detail 2 x Fertiliser tablets per tree Install Hydrocell as per manufacturers specification 

Landscape Contractor to nominate Nursery/ Plant Supplier prior to supply on site

NO 

Certification by independant Horticulturalist of all plant stock (complies with AS 2303:2018) 

Certification that soil complies with AS 4419:2003.

Installation of site soil by landscape contractor.

Spraying of weed on existing site mulch stockpiles to occur prior to transport and spreading in final location.

Proposed Shrub and Groundcover Plant Stock

45L, 200mm and 50mm Tubestock All stock to be planted as per landscape detailsLandscape Contractor to nominate Nursery/ Plant Supplier prior to supply on site

NO 

Certification by independant Horticulturalist of all plant stock (complies with AS 2303:2018) 

Certification that soil complies with AS 4419:2003.

Installation of site soil by landscape contractor and per P1, P2 and P3.

P1 Planting Type 1‐ Feature Planting 

All components as per specification:150mm depth cultivated subgrade300mm depth ameliorated site topsoil 100mm depth Site Mulch (transported from nominated location on site) 2 x Fertiliser tablets per plantInstall Hydrocell as per manufacturers specification Shrub and groundcover planting to be installed as specified and as per Planting Plans and Schedules

NA NO Certification that soil complies with AS 4419:2003.

If treatment exceeds a grade of 1:2 landscape contractor to install Polyfabircs Tec Mat Jute Heavy (750g/m²) . Contractor to install 300mm pins, pinning rate to be as per manfacturers specification. On 100mm amerliorated site soil and per Planting type 3. 

Spraying of weed on existing site mulch stockpiles to occur prior to transport and spreading in final location.

Orchard (Pebble Creek) Developments Pty LtdProject: Pebble Creek Development SLR Job no: 620.12664.00300

SOFT WORKS

Page 78: LANDSCAPE WORKS SPECIFICATION

P2 Planting Type 2‐ Rehabilitation Planting  

All components as per specification:Dig a hole three times larger than pot size and backfill with Ameliorated site topsoil 100mm depth Site Mulch (transported from nominated location on site) 1 x Typhoon Native tablet per plantShrub and groundcover planting to be installed as specified and as per Planting Plans and Schedules

NA NO Certification that soil complies with AS 4419:2003.

If treatment exceeds a grade of 1:2 landscape contractor to install Polyfabircs Tec Mat Jute Heavy (750g/m²) . Contractor to install 300mm pins, pinning rate to be as per manfacturers specification. On 100mm amerliorated site soil and per Planting type 3. 

Spraying of weed on existing site mulch stockpiles to occur prior to transport and spreading in final location.

P3Planting Type 3‐ Rehabilitation Planting with Jute Mat  

All components as per specification:Dig a hole three times larger than pot size and backfill with Ameliorated site topsoil Polyfabrics TEC Mat Jute‐ Heavy (installed as per Manufactures specfication) with 300mm long steel u‐pins at 500mm centre.1 x Typhoon Native tablet per plantShrub and groundcover planting to be installed as specified and as per Planting Plans and Schedules

NA NO Certification that soil complies with AS 4419:2003.

If treatment exceeds a grade of 1:2 landscape contractor to install Polyfabircs Tec Mat Jute Heavy (750g/m²) . Contractor to install 300mm pins, pinning rate to be as per manfacturers specification. On 100mm amerliorated site soil and per Planting type 3. 

Spraying of weed on existing site mulch stockpiles to occur prior to transport and spreading in final location.

Mulch  Mulch  100mm depth Site Mulch (transported from nominated location on site)  NA NO  NO Spraying of weed on existing site mulch stockpiles to occur prior to transport and spreading in final location.

TU TurfA Grade Green Couch over100mm depth ameliorated site soil (by Civil Contractor)100mm depth cultivated subgrade (by Civil Contractor)

NA NO Yes‐ documentation highlighting turf grade and supplier

Site topsoil and cultivation of subgrade within turf areas by civil contractor. 

Coir Log Coir LogPolyfabrics EcoLog 300 x 3000mmPinned with a minimum of 5 Hardwood stakes. Stakes to exceed height (top) of EcoLog by a minimum of 150mm.

Polyfabrics: Tim Wood PH: (07) 3451 0500

NO  NO  Contractor to install on site as directed by landscape architect  

Coir Mat Coir MatPolyfabrics Tec Mat Coir 9300mm long pins, pinning rate as per manufacturers specification 

Polyfabrics: Tim Wood PH: (07) 3451 0500

NO  NO  Contractor to install on site as directed by landscape architect  

Rootbarrier Rootbarrier 600 Roll Widths ‐ 750gm/m2, 0.7mm Thickness Nylex or similar approved NO Comprehensive photographic documentation of installation to be taken by landscape contractor 

To be installed to all trees when adjacent to kerb, driveway, pathway or services as per typical detail.

Weed TreatmentWeed Treatment to existing areas prior to planting or construction as required

Undertaken in line with requirements of Landscape Specification NA NO  NO Allow minimum 1 week prior to planting to ensure weeds species are no longer active

Pebble Creek Entry Road and Mountain Ridge Road_ Materials Finishes Schedule 2 Appendix A

Page 79: LANDSCAPE WORKS SPECIFICATION

CE Concrete Edge Portland Grey Cement125 x 125mm extruded concrete edging to all garden areas adjoining other landscape finishes (Turf, Planting Areas)

NA NO  NO Construct concrete edge to planting area edges as per landscape plans 

TE Timber Edge 100 x 50mm CCA Treater Pine Edge (as per AS1604:2000) 450 x 50 x 50mm Hardwood Stakes Fixed with 2 x Hot dipped galvanised M10 Screws as per landscape detail 

NA NO  NO If required contractor to partially saw cut timber edging to allow timber to be curved without compromising integrity.

SSSub Soil Drainage ‐ installed to back of retaining walls.

100mm diam.geotextile socked perforated flexible pipe in 20mm drainage gravel trench to back of retaining wallwrapped in geotextileConnected to stormwater system 

NA NO Comprehensive photographic documentation of installation to be taken by landscape contractor.  

Entry WallStone faced wall for future Sign Element (park entry) ‐ Construct

Double Skin 200 series core‐filled, reinforced, free standing block wall.Alphine Stone facing shall be fixed to the front, side and top faces of the wall as per landscape details. 10mm thick render installed to back face (lot side) of entry wall. Colour TBC prior to construction. 2 coats of anti‐grafitti coating applied as per manufacturers recommendations.Wall, reinforcing, footings to be certified by contractor including provision for Form 16. 

Alphine Stone Facing Eco OutdoorPH: (07) 3034 6444

Yes‐ Contractor to provide a sample of grout mortor colour for stone works to 

wall. 

Contractor to certify Wall and provide Form 16 to Superintendent prior to the awarding of practical completion. 

Entry Wall Lettering Entry Sign Laser Cut Lettering

PEBBLE CREEK' Lettering: 8mm thick laser cut Grade 304 Brush finished Stainless Steel installed as per landscape details. All edges to have a corner radius of 1.5mm.

'SOUTH MACLEAN' Lettering: 8mm thick laser cut Grade 304 Brush finished Stainless Steel installed as per landscape details. All edges to have a corner radius of 1.5mm.

All lettering to be chemset to block entry wall. 

NA

Yes‐ Contractor to provide 100 x 100 sample of stainless 

steel finish prior to fabrication. 

No

Landscape Contractor to request lettering/ patterning prior to fabrication. 

All lettering to have no sharp edges and be rounded to a radius of 1.5mm.

Entry Wall Feature Patterning 

Feature Patterning 

8mm thick laser cut Grade 304 Brush finished Stainless Steel installed as per landscape details.

All edges to have a corner radius of 1.5mm.

NA

Yes‐ Contractor to provide 100 x 100 sample of stainless 

steel finish prior to fabrication. 

No

Landscape Contractor to request patterning prior to fabrication. 

Patterning to have no sharp edges and be rounded to a radius of 1.5mm.

Entry Wall Feature Timbers

Recycled Timber Posts 150 x 150 Dressed Recycled Timber Posts.  NA

Yes‐ Contractor to provide photographs of timbers or arrange site inspection to supplier with landscape 

architect prior to procurement. 

Contractor to certify feature posts and fencing and provide Form 16 to Superintendent prior to the awarding of practical completion. 

ENTRY WALL

HARD WORKS

Pebble Creek Entry Road and Mountain Ridge Road_ Materials Finishes Schedule 3 Appendix A

Page 80: LANDSCAPE WORKS SPECIFICATION

1.9m high Double Sided Acoustic Fence installed to property boundary. Stain Finished as below 

Pailings:Description: CCA Treated Pine, 90 x 19mm (H3). Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Rails:Description: CCA Pressure Treated Pine Palings, (F14,H3), 38 x 100mm. All edges to have 5mm aris.Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Posts:Description: CCA Treated Hardwood Post (F17, H5), 150 x 100mm. Front face (Road Side) to have 45mm chamfer. All other exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.Fascia:Description: CCA Pressure Treated Pine, (F14, H3), 100 x 25mm. All exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Sleeper Kick Board:Description: CCA Pressure Treated Pine, (F17, H5), 200 x 50mm. All exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Sela Brown.Capping:Description: CCA Treated Hardwood (F14, H3), 100 x 25mm. All exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.Fixings:All Fixing and screw to be HDG finished, unless otherwise stated on landscape plans. 

FENCING 

Fencing Type 1A‐ Acoustic FenceF1ACutek

Greg BoulterPH: 0455 028 006

NO Yes‐ Contractor to provide Form 16 for 

all aspects of the Fencing.Note all fencing installed to property boundary alignment. 

Pebble Creek Entry Road and Mountain Ridge Road_ Materials Finishes Schedule 4 Appendix A

Page 81: LANDSCAPE WORKS SPECIFICATION

1.9m high Double Sided Acoustic Fence installed to top of sleeper retaining wall. Stain Finished as below 

Pailings:Description: CCA Treated Pine, 90 x 19mm (H3). Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Rails:Description: CCA Pressure Treated Pine Palings, (F14,H3), 38 x 100mm. All edges to have 5mm aris.Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Posts:Description: CCA Treated Hardwood Post (F17, H5), 150 x 100mm. Front face (Road Side) to have 45mm chamfer. All other exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Fascia:Description: CCA Pressure Treated Pine, (F14, H3), 100 x 25mm. All exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.Sleeper Kick Board and Retaining Timber:Description: CCA Pressure Treated Pine, (F17, H5), 200 x 50mm. All exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Sela Brown.Capping:Description: CCA Treated Hardwood (F14, H3), 100 x 25mm. All exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.Fixings:All Fixing and screw to be HDG finished, unless otherwise stated on landscape plans. 

Note all fencing installed to property boundary alignment. F1BFencing Type 1B‐ Acoustic Fence with 

retaining wall

CutekGreg Boulter

PH: 0455 028 006NO 

Yes‐ Contractor to provide Form 16 for all aspects of the Fencing.

Pebble Creek Entry Road and Mountain Ridge Road_ Materials Finishes Schedule 5 Appendix A

Page 82: LANDSCAPE WORKS SPECIFICATION

1.9m high Double Sided Feature Panel Acoustic Fence installed to property boundary. Stain Finished as below 

Pailings:Description: CCA Treated Pine, 90 x 19mm (H3). Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Rails Type 1:Description: CCA Pressure Treated Pine Palings, (F14,H3), 38 x 100mm. All edges to have 5mm aris.Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Rails Type 2:Description: CCA Pressure Treated Pine Palings, (F14,H3), 50x 100mm. All edges to have 5mm aris.Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Posts:Description: CCA Treated Hardwood Post (F17, H5), 150 x 100mm. Front face (Road Side) to have 45mm chamfer. All other exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Capping:Description: CCA Treated Hardwood (F14, H3), 100 x 25mm. All exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.Plywood Panelling:Description: Premium Plywood Panel A Bond 32mm thickFinish: TBC prior to construction Sleeper Kick Board:Description: CCA Pressure Treated Pine, (F17, H5), 200 x 50mm. All exposed edges to have 5mm aris. Panelling to have feature routed patterning as per landscape details.Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Sela Brown.Fixings:All Fixing and screw to be HDG finished, unless otherwise stated on landscape plans. 

Fencing Type 2A‐ Feature Acoustic Panel Fence

F2ACutek

Greg BoulterPH: 0455 028 006

NO Yes‐ Contractor to provide Form 16 for 

all aspects of the Fencing.

Note all fencing installed to property boundary alignment. Landscape Contractor to request patterning for routing prior to 

fabrication. 

Pebble Creek Entry Road and Mountain Ridge Road_ Materials Finishes Schedule 6 Appendix A

Page 83: LANDSCAPE WORKS SPECIFICATION

1.9m high Double Sided Feature Panel Acoustic Fence installed to property boundary. Stain Finished as below 

Pailings:Description: CCA Treated Pine, 90 x 19mm (H3). Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Rails Type 1:Description: CCA Pressure Treated Pine Palings, (F14,H3), 38 x 100mm. All edges to have 5mm aris.Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Rails Type 2:Description: CCA Pressure Treated Pine Palings, (F14,H3), 50x 100mm. All edges to have 5mm aris.Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Sela Brown.Posts:Description: CCA Treated Hardwood Post (F17, H5), 150 x 100mm. Front face (Road Side) to have 45mm chamfer. All other exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.

Capping:Description: CCA Treated Hardwood (F14, H3), 100 x 25mm. All exposed edges to have 5mm aris. Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Colour Walnut.Plywood Panelling:Description: Premium Plywood Panel A Bond 32mm thickFinish: TBC prior to construction Sleeper Kick Board and Retaining Timber:Description: CCA Pressure Treated Pine, (F17, H5), 200 x 50mm. All exposed edges to have 5mm aris. Panelling to have feature routed patterning as per landscape details.Finish: 2 coats of Cutek Extreme Oil, Double Colourtone. Sela Brown.Fixings:All Fixing and screw to be HDG finished, unless otherwise stated on landscape plans. 

F2A and F2B‐ Feature Patterning

Feature Patterning 

5mm thick laser cut Brushed Aluminum installed as per landscape details. Minimum grade of 3003.

All edges to have a corner radius of 1.5mm.

NA

Yes‐ Contractor to provide 100 x 100 sample of 

Aluminum finish prior to fabrication. 

No

Landscape Contractor to request patterning prior to fabrication. 

Patterning to have no sharp edges and be rounded to a radius of 1.5mm.

Note all fencing installed to property boundary alignment. Landscape Contractor to request patterning for routing prior to 

fabrication. F2B

Fencing Type 2B‐ Feature Acoustic Panel Fence with retaining wall

CutekGreg Boulter

PH: 0455 028 006NO 

Yes‐ Contractor to provide Form 16 for all aspects of the Fencing.

Pebble Creek Entry Road and Mountain Ridge Road_ Materials Finishes Schedule 7 Appendix A

Page 84: LANDSCAPE WORKS SPECIFICATION

620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx Page 1 of 2

APPENDIX B Dulux Render Finish

Page 85: LANDSCAPE WORKS SPECIFICATION

AUDA1582Dulux AcraTex Green Render Sealer

Part A 19420802

Product Overview

DULUX AcraTex Green Render Sealer is a Water Based primer/ sealer designed specifically for the preparation of fresh "green" masonry surfaces to

minimise unsightly white salts or "efflorescence" migrating through the applied coating system and speed project coating schedules by reducing the traditional

concrete/render "Alkalinity passivation" wait period.

AcraTex Green Render Sealer deigned to reduce the normal site mixed cement render "28 day / Bagged Render 7-10 days wait cycle"

- Green Render Sealer can be applied over 2 day old cement render providing moisture content has stabilised.

Features And Benefits

Superior water and alkali resistance

Seals and Primes masonry surfaces

Penetrating binder

Water based,

Fast track coating

Ensures good, uniform adhesion of topcoat

Consolidates masonry surfaces

Low VOC

Reduces Scaffolding Hire costs

Uses And Typical Specifications

Uses Green Render Sealer can be used over all masonry surfaces to provide excellent system adhesion and integrity with long term durability.

The primer forms a barrier over alkali substrates limiting the reaction with atmospheric Carbon Dioxide thus reducing the formation of unsightly

white deposits or "efflorescence" on the surface typically associated with coating of highly alkaline "Fresh" masonry.

The primer allows for reduced substrate curing time prior to coating, thus fast tracking project work and reducing overall project costs and

construction time.

Typical

SystemsTypical System AUSA4953 Dulux AcraTex for New Brick/Blockwork [Exterior]

Preparation Guide REFER AUSA4953 Dulux AcraTex 968 AcraSkin Low Gloss / Dulux AcraTex 951 Coventry Coarse Sand Finish on New

Brick/Blockwork [Exterior] for full Preparation Guide.

Premium High Build Levelling and Acrylic Texture Finishing System for application over new & uncoated aged Brick

work & Block work.

Incorporating:

AcraTex RenderWall as a Cementitious surface leveling base coat render used to level out brick work & block work

irregularities to produce high quality even

surface readiness for application of a high acrylic texture finishing system .

AcraTex Green Render Sealer (GRS) deigned to reduce the normal site mixed cement render "28 day /Bagged Render

7-10 days wait cycle "

- Green Render Sealer (GRS) can be applied over 2 day old cement render providing moisture content has stabilised.

AcraTex 951 Coventry Coarse is a decorative, low build protective coating displaying excellent resistance to

weathering and atmospheric chemicals. The finish will resemble that of a coarse granual render which is sponge

floated.

AcraTex AcraSkin, weather-proofing topcoat, applied by conventional NAP roller to provide a paint like appearance

with excellent water impermeability, resistance to mould and mildew, high build crack bridging performance for long

term protection of cement render substrates.

Cement Render is hard and brittle due to the inherent nature of cement. Cement render will develop shrinkage cracks on

aging and continues to harden

(Hydration process) over its life cycle, further increasing risk of cracking. - Dulux does not recommend low build

(conventional) paint finishes over cement render. Not for immersion.

Refer Dulux Representative for specific project advice relative to site conditions.

Coat Product Spread Rate (m2/L) WFT (micron) DFT (micron)

Prep Coat Renderwall 0.3 4000 4000

1st Coat Green Render Sealer 8 125 44

Intermediate 951 Coventry Coarse 0.8 1333 1000

2nd Coat 968 AcraSkin 3.1 322 165

3rd Coat 968 AcraSkin 3.1 322 165

Minimum System DFT 5374

Notes REFER AUSA4953 Dulux AcraTex 968 AcraSkin Low Gloss / Dulux AcraTex 951 Coventry Coarse Sand Finish on New

Brick/Blockwork [Exterior] for full details.

Version 12.0 of AcraTex datasheet AUDA1582 approved on Friday, 3 June 2016 8:55:58 AM (UTC) Page 1 of 4

Page 86: LANDSCAPE WORKS SPECIFICATION

Precautions And Limitations

DO NOT TINT.

Green Render Sealer's ability to restrict the formation and transition of efflorescence relays on the formation of a continuous "barrier" layer, thus requiring

specific attention through the application process to ensuring adequate and consistent cover.

This product data sheets is to be read in conjunction with DULUX specification.

Ensure that you have adequate tinted stock to complete the job in one application. All material must be thoroughly cross-mix to ensure tint uniformity.

It is recommended to hold a volume of finish material for future maintenance touch-ups

Practical spreading rates will vary from quoted theoretical figures depending on substrate porosity, surface roughness, overspray losses, application

methods and environmental conditions (e.g. wind).

All preparation and painting must conform to AS2311: The Painting of Buildings

At Commencement of coating system application, to the substrate it shall be deemed that the Applicator has certified that the surface which the coating/s is to

be applied to, is fit to receive the specified coating(s) system.

Do not apply paint if Relative Humidity is above 85% or temperature is within 3°C of Dew Point.Do not apply if the surface temperature is greater than 40°C or below 10°C, or likely to fall below 10°C during the application or drying period.Dry times apply to a single coat at recommended spread rate and at 25°C and 50% Relative Humidity Allow longer times under cool, moist, or still conditions and or when applied at high film builds.

Protect from dew, rain and frost for 48 hours when apply at the recommended spread rate.

Avoid application in hot, windy conditions or on hot surfaces cool the surface by hosing with water and paint the cool damp surface.

Application techniques should be adjusted to achieve the recommended DFT and finishing standard.

To avoid "Picture Framing" of texture topcoats "wet on wet" cutting in & coating technique is recommended or apply multiple coats thinning the first coat.

When using Bright Reds, Oranges, Blues and Yellows or where very light (or dark) colours are applied over highly contrasting colours an extra coat maybe

required.

The coastal area is considered a marine environment and as such salt potentially can shorten the life of the coating systems. Care needs to be taken to wash

down all areas twice. Once to remove surface contaminants, and raise salts to the surface and then secondly to remove these salts. Due to the locality,

weather conditions and lag time between applications of the coating system it may require the need to wash again, between coats.

When the Applicator is preparing the site sample for approval he should advise the Project Superintendent if the substrate condition is not of sufficient

standard to produce the specified finish.

Where possible avoid dark colours - these will give raise to much higher surface temperature that may cause addition thermal stress and cooling demand to

the building envelope and/ or require extra engineering considerations (greater building costs).

Consult Dulux on the potential to use InfraCOOL Heat Reflective Coatings.

A DULUX warranty can be provided on request, when the FULL AcraTex system including a membrane topcoat/s is applied by a DULUX AcraTex trained

applicator, according to specification, & at the specified spreading rates, & to the surface preparation details described in the DULUX AcraTex Specification

Manual.

The dynamics of the substrate is outside the control of Dulux Australia and as such joint deformation or cracking is excluded from warranty terms.

Colour change is a natural part of a coating weathering and is excluded from warranty terms

Refer warranty document for full terms and conditions.

CEMENT RENDERS PRODUCE FINE CRACKS DURING DRYING AND CONTINUE TO CRACK & MOVE WITH VARIATIONS IN TEMPERATURE.

FOR ENHANCED PERFORMANCE USE A HIGH BUILD ELASTOMERIC (FLEXIBLE) COATING.

DULUX RECOMMENDS THE USE OF DULUX ACRASHIELD ADVANCE.

Fungi and Algae can exist on virtually any surface (even glass) provided the right conditions for growth are met.

Visible growth on painted surfaces is typically caused by contaminants present together with the presence of high enough levels of moisture to support

growth. Agents in paints become ineffective where they cannot “touch” the growth source (eg where growth emanates from deposits on the film). Additionally the active agents are “consumed” in the process such that protection is time limited where conditions support ongoing growth performance isgreatly improved with the inclusion of a membrane Top coat like Dulux AcraTex AcraShield Advance, Elastomeric 201 or AcraSkin.

Refer: http://www.dulux.com.au/specifier/our-brands/dulux-acratex/more-than-just-render

The exterior texture coatings should be cleaned on a regular basis. This will help maintain your overall aesthetic appearance and preserve your AcraTex

Texture coating system. Cleaning once every year will remove light soil as well as grime and airborne pollutants refer Dulux AcraTex Care & Maintenance

Guide. Refer http://www.dulux.com.au/specifier/our-brands/dulux-acratex/acratex-care-and-maintenance

Performance Guide

Weather Excellent - enhances system durability Salt Resists migration of soluable salts

Heat

Resistance

N/A - not tested Water Highly water resistant

Solvent N/A - Not tested Abrasion N/A - not tested

Acid N/A - not tested Alkali Excellent Alkali Resistance - Suitable over "green masonry"

after 2 days of idea curing conditions. Under adverse

conditions allow 14 days.

Version 12.0 of AcraTex datasheet AUDA1582 approved on Friday, 3 June 2016 8:55:58 AM (UTC) Page 2 of 4

Page 87: LANDSCAPE WORKS SPECIFICATION

Air Spray Airless Spray Brush Roller

Typical Properties

V.O.C

Content

20 Clean Up Clean up water

DO NOT THIN

Application

Method

Application

ConditionsSolids By Volume 35

Min Max Recommended

Wet Film Per Coat (microns) 125 125 125

Dry Film Per Coat (microns) 43.75 43.75 43.75

Recoat Time (min) 120

Theoretical Spread Rate (m2/L) 8 8 8

Typical

Properties

Notes

Brush, Roller and Airless spray

Brush and roll at the same time to avoid picture framing.

Product should be thoroughly mixed before use. Refer to the DULUX AcraTex Application Manual for detailed instructions.

A 10-20mm nap roller is used depending on the type of texture being overcoated.

Typical Airless Spray set up is: Graco Ultra 500 using 0.017-0.019 spray tip at approx. 1000 psi.

Application Guide

Surface

Preparation

Ensure alkaline surfaces have been aged for at least 2 days.

Concrete / Cement Render curing times may require extended curing times dependant on cure conditions.

All surfaces must be cured (substrate has reached a stable moisture content), clean, sound and free of all contaminates such as form

oils, release agents, mortar splashes, mould and algae. Surface imperfections misalignments and protrusions must be levelled and patched

and completely flush to surrounding surfaces. Metal, tie wire, etc. on surface must be removed or treated against corrosion.

Application :

Refer to the Acratex Texture Coatings Applicators Training Manual for detailed instructions.

Green Render Sealer may be applied by airless spray, roller or brush.

Applications must form a continuous "barrier" film to maximise efflorescence blocking.

Application

Procedure

And

Equipment

Brush, roller and airless spray

Brush and roll at the same time to avoid picture framing.

Product should be thoroughly mixed before use. Refer to the DULUX AcraTex Application Manual for detailed instructions.

A 10-20mm nap roller is used depending on the type of surface profile being overcoated.

Typical Airless Spray set up is: Graco Ultra 500 using 0.017-0.019 spray tip at approx. 1000 psi.

Health And Safety

MSDS

Number

000000022632 Using Safety

Precautions

Refer Material Safety Data Sheet for full detail.

Ensure protection from splashes to exposed skin and

eyes.

Ensure adequate ventiliation.

MSDS Link https://go.lupinsys.com/duluxgroup/harms/published_materials/fee62a9c4b8013f1e9ea398e9cbbcca2-published

Health

Effects

Refer Material Safety Data Sheet for full detail.

NOT classified as Hazardous according to criteria of

NOHC.

Flammability Non Flammable

Protective

Equipment

Refer Material Safety Data Sheet for full detail Storage Store out of direct sunlight in a cool area.

Disposal DO NOT pour down drains.

Refer local regulation for disposal of water based wastes.

In the case of emergency, please call 1800 033 111

Version 12.0 of AcraTex datasheet AUDA1582 approved on Friday, 3 June 2016 8:55:58 AM (UTC) Page 3 of 4

Page 88: LANDSCAPE WORKS SPECIFICATION

Transport And Storage

Pack A 19420802 Shipment

Name

Water Based Paint

Size Weight

15L 18kg

Flash Point N/A UN

Number

N/A

Dangerous

Goods

Class

N/A Package

Group

N/A

Images

DisclaimerDulux, Selleys and Other marks followed by ® are registered trademarks. Marks followed by the symbol of ™ are trademarks.

The data provided within the Duspec system is correct at the time of publication, however it is the responsibility of those using this information to check that it is current prior tospecifying or using any of these coating/product systems.DISCLAIMER: Any advice, recommendation, information, assistance or service provided by any of the divisions of DuluxGroup (Australia) Pty Ltd or its related entities (collectively,DuluxGroup) in relation to goods manufactured by it or their use and application is given in good faith and is believed by DuluxGroup to be appropriate and reliable. However, any advice,recommendation, information, assistance or service provided by DuluxGroup is provided without liability or responsibility PROVIDED THAT the foregoing shall not exclude, limit, restrictor modify the right entitlements and remedies conferred upon any person or the liabilities imposed upon DuluxGroup by any condition or warranty implied by Commonwealth, State orTerritory Act or ordinance void or prohibiting such exclusion limitation or modification. Coating/product systems can be expected to perform as indicated on the Duspec Spec Sheet solong as applications and application procedures of the individual products are followed as recommended on the appropriate Product data Sheet. "DuluxGroup" "Dulux" "Selleys" "Berger""Berger Gold Label" "Hadrian" "Walpamur" "Levene" "Acratex" and Other marks followed by ® are registered trademarks of DuluxGroup (Australia) Pty Ltd ABN 67 000 049 427. Marksfollowed by the symbol ™ are trademarks.

Please note that this document is only valid for 60 days from the date of issue.

DuluxGroup (Australia) Pty Ltd 1956 Dandenong Road, Clayton, Victoria 3168 AU ABN 67 000 049 427

Version 12.0 of AcraTex datasheet AUDA1582 approved on Friday, 3 June 2016 8:55:58 AM (UTC) Page 4 of 4

Page 89: LANDSCAPE WORKS SPECIFICATION

AUDA0441Dulux AcraTex Acraprime Water Based

Part A 194-20809

Product Overview

DULUX AcraTex AcraPrime Water Based acrylic primer/sealer conditions the surface and unifies substrate porosity.

Features And Benefits

Water based

Penetrates masonry surfaces

Seals masonry surfaces

Easy application and economical clean up.

Foundation for uniform adhesion & extended durability of texture coats

Ensures consistent appearance and finish of total system.

Uses And Typical Specifications

Uses DULUX AcraTex AcraPrime Water Based acrylic primer/sealer is applied to the substrate to unify the substrate porosity, it ensures maximum

adhesion and provides excellent key for following texture coats, particularly DULUX AcraTex 950 Roll On , 951 Trowel On , 952 Spray On ,

955 AcraShield.

Typical

SystemsTypical System Typical Minimum Specification Rendered Masonry Substrates

Preparation Guide PBK019 - BRICK / BLOCKWORK AND MASONRY

ASSESS SUITABILITY

Concrete, mortar and cement based products need to be fully cured for at least 28 days before painting.

REMOVE POWDER LAYERS & EFFLORESCENCE

Remove any powdery layers, laitance or efflorescence by detergent cleaning, wire brushing, water blasting or a

suitable chemical treatment.

CLEAN

Clean the surface thoroughly by water blasting or detergent cleaning, where a commercial cleaner is added to hot or

cold water and surface is washed / scrubbed thoroughly with a stiff bristle broom and then rinsed clean with fresh

water. This may need to be repeated on extremely dirty surfaces to ensure removal of efflorescence or other poorly

bonded surface material. Ensure that the surface is dry, clean and free from dust.

RENDERING OF NEW BRICK/ BLOCKWORK & MASONRY

(WHERE SPECIFIED TO LEVEL THE BRICK/MORTAR PATTERN)

: Trowel apply a basecoat of Dulux AcraTex Renderwall over entire substrate at approximately 6mm to 8mm in

thickness until flush.

A Screed or darby may be used to level the renderwall prior to floating with a plastic or wooden float.Renderwall can

be applied at a thickness as low as 4mm ( with addition of Acrabond a 100% acrylic resin at 250ml per mix) or above

12mm ( in two successive coats) relative to the degree of cover required, if desired 150grams Alkali mesh maybe

embedded into the base coat.

COATING CONSIDERATIONS FOR NEW RENDERS

All renders produce surface cracking whilst drying & curing which continue to expand & contract during daily

temperature fluctuations allowing water ingress and causing potential discolouration and coating failure.

The specified coating needs to accommodate the renders thermal dynamics, protect from atmospheric pollutants, salt

air, water ingress, alkali attack, dirt accumulation and carbon dioxide.

Recommendation is a High Build Acra-Tex Elastomeric Coating System.

Dark colours increase expansion/contraction of a substrate due to heat absorbed and should be avoided where

possible or extra design relief should be added to building's design.

The coastal area is considered a marine environment and as such salt potentially can shorten the life of the coating

systems. Care needs to be taken to wash down all areas twice. Once to remove surface contaminants, and raise salts

to the surface and then secondly to remove these salts.

Due to the locality, Weather conditions and lag time between applications of the coating system it may require the need

to wash again, between coats.

Coat Product Spread Rate (m2/L) WFT (micron) DFT (micron)

1st Coat Acraprime Water Based 10 65 20

2nd Coat 951 Trowel On Tuscany Coarse 0.8 1333 1000

3rd Coat 955 AcraShield 6.0 167 75

Minimum System DFT 1095

NotesDo not apply paint if Relative Humidity is above 85% or temperature is within 3°C of Dew Point.Do not apply if the surface temperature is greater than 40°C or below 10°C, or likely to fall below 10°C during theapplication or drying period.

Do not apply paint if the temperature is below 10°C or likely to fall below 10°C during the drying period.This specification must be read in conjunction with the appropriate technical data sheets.

When using this specification, the Applicator shall maintain records in accordance with AS3894 Parts 10, 11 and 12

and others as required by the Project Manager. These records shall be made available for inspection at any time by the

Version 21.0 of AcraTex datasheet AUDA0441 approved on Friday, 3 June 2016 8:25:07 AM (UTC) Page 1 of 5

Page 90: LANDSCAPE WORKS SPECIFICATION

Project Manager or authorised representative and submitted to the Principal Contractor upon completion of work.

CEMENT RENDERS PRODUCE FINE CRACKS DURING DRYING AND CONTINUE TO CRACK & MOVE WITH VARIATIONS IN

TEMPERATURE.

FOR ENHANCED PERFORMANCE USE A HIGH BUILD ELASTOMERIC (FLEXIBLE) COATING. DULUX RECOMMENDS THE

USE OF DULUX ACRASHIELD 955 .

At Commencement of coating system application to the substrate it shall be deemed that the Applicator has certified that

the surface which it is to be applied to is fit receive this specified coatings system.

When the Applicator is preparing the site sample for approval he should advise the Project Superintendent if the

substrate condition is not of sufficient standard to produce the specified finish.

Where a site mixed render or pre-mixed bagged render substrate is deemed friable & powdery, dried, cured & aged for

28 days or more AcraPrime water Based Primer is to be substituted with the deep penetrating AcraPrime Solvent Based

sealer for maximum surface consolidation

Where sound site mixed render or pre-mixed bagged render substrate have been not allowed to dry, cure & or aged for

28 days or more Green Render Sealer should be substituted with AcraPrime water Based Primer.

Where bright reds and yellows or very light colours are applied over highly contrasting colours an extra top coat maybe

also be required.

Ensure adequate batch tint lots to achieve coverage over single elevations to ensure colour consistency. It is

recommended to hold a volume of finish material for future maintenance touch-ups

Version 21.0 of AcraTex datasheet AUDA0441 approved on Friday, 3 June 2016 8:25:07 AM (UTC) Page 2 of 5

Page 91: LANDSCAPE WORKS SPECIFICATION

Precautions And Limitations

Do not thin or apply over damp substrate (except where specified to AAC).

Do not use DULUX AcraTex AcraPrime water Based under DULUX AcraTex RenderWall.

AcraPrime 501/1 is suitable for well clean, sound masonry that has cured for 28 days or longer. Where the substrate is less than 28 days and greater than 3

days curing Green Render Sealer is recommended.

Where the substrate is friable or powdery, substitute AcraPrime Deep Penetrating Solvent based sealer in lue of AcraPrime Water based.

or

Use AcraPrime Deep Penetrating Solvent based sealer if concrete is high in MPA value and there are concerns around adhesion to hard dense and /or

smooth concrete

To ensure colour uniformity and for optimum performance, Dulux recommend a full coating system including a MEMBRANE top coat.

For ALL systems the Texture &/or Base Coat should be tinted in accordance with AcraTex Tint Guide to the specified top coat colour

(or a colour as close as possible to the specified colour as product and tint rules allow). IMPORTANT: Not all colours are suitable for exterior use.

This product data sheets is to be read in conjunction with DULUX specification.

Ensure that you have adequate tinted stock to complete the job in one application. All material must be thoroughly cross-mix to ensure tint uniformity.

It is recommended to hold a volume of finish material for future maintenance touch-ups

Practical spreading rates will vary from quoted theoretical figures depending on substrate porosity, surface roughness, overspray losses, application

methods and environmental conditions (e.g. wind).

All preparation and painting must conform to AS2311: The Painting of Buildings

At Commencement of coating system application, to the substrate it shall be deemed that the Applicator has certified that the surface which the coating/s is to

be applied to, is fit to receive the specified coating(s) system.

Do not apply paint if Relative Humidity is above 85% or temperature is within 3°C of Dew Point.Do not apply if the surface temperature is greater than 40°C or below 10°C, or likely to fall below 10°C during the application or drying period.Dry times apply to a single coat at recommended spread rate and at 25°C and 50% Relative Humidity Allow longer times under cool, moist, or still conditions and or when applied at high film builds.

Protect from dew, rain and frost for 48 hours when apply at the recommended spread rate.

Avoid application in hot, windy conditions or on hot surfaces cool the surface by hosing with water and paint the cool damp surface.

Application techniques should be adjusted to achieve the recommended DFT and finishing standard.

To avoid "Picture Framing" of texture topcoats "wet on wet" cutting in & coating technique is recommended or apply multiple coats thinning the first coat.

When using Bright Reds, Oranges, Blues and Yellows or where very light (or dark) colours are applied over highly contrasting colours an extra coat maybe

required.

The coastal area is considered a marine environment and as such salt potentially can shorten the life of the coating systems. Care needs to be taken to wash

down all areas twice. Once to remove surface contaminants, and raise salts to the surface and then secondly to remove these salts. Due to the locality,

weather conditions and lag time between applications of the coating system it may require the need to wash again, between coats.

When the Applicator is preparing the site sample for approval he should advise the Project Superintendent if the substrate condition is not of sufficient

standard to produce the specified finish.

Where possible avoid dark colours - these will give raise to much higher surface temperature that may cause addition thermal stress and cooling demand to

the building envelope and/ or require extra engineering considerations (greater building costs).

Consult Dulux on the potential to use InfraCOOL Heat Reflective Coatings.

A DULUX warranty can be provided on request, when the FULL AcraTex system including a membrane topcoat/s is applied by a DULUX AcraTex trained

applicator, according to specification, & at the specified spreading rates, & to the surface preparation details described in the DULUX AcraTex Specification

Manual.

The dynamics of the substrate is outside the control of Dulux Australia and as such joint deformation or cracking is excluded from warranty terms.

Colour change is a natural part of a coating weathering and is excluded from warranty terms

Refer warranty document for full terms and conditions.

CEMENT RENDERS PRODUCE FINE CRACKS DURING DRYING AND CONTINUE TO CRACK & MOVE WITH VARIATIONS IN TEMPERATURE.

FOR ENHANCED PERFORMANCE USE A HIGH BUILD ELASTOMERIC (FLEXIBLE) COATING.

DULUX RECOMMENDS THE USE OF DULUX ACRASHIELD ADVANCE.

Fungi and Algae can exist on virtually any surface (even glass) provided the right conditions for growth are met.

Visible growth on painted surfaces is typically caused by contaminants present together with the presence of high enough levels of moisture to support

growth. Agents in paints become ineffective where they cannot “touch” the growth source (eg where growth emanates from deposits on the film). Additionally the active agents are “consumed” in the process such that protection is time limited where conditions support ongoing growth performance isgreatly improved with the inclusion of a membrane Top coat like Dulux AcraTex AcraShield Advance, Elastomeric 201 or AcraSkin.

Refer: http://www.dulux.com.au/specifier/our-brands/dulux-acratex/more-than-just-render

The exterior texture coatings should be cleaned on a regular basis. This will help maintain your overall aesthetic appearance and preserve your AcraTex

Texture coating system. Cleaning once every year will remove light soil as well as grime and airborne pollutants refer Dulux AcraTex Care & Maintenance

Guide. Refer http://www.dulux.com.au/specifier/our-brands/dulux-acratex/acratex-care-and-maintenance

Version 21.0 of AcraTex datasheet AUDA0441 approved on Friday, 3 June 2016 8:25:07 AM (UTC) Page 3 of 5

Page 92: LANDSCAPE WORKS SPECIFICATION

Air Spray Airless Spray Brush Roller

Performance Guide

Weather Suitable for exterior application when topcoated. Salt N/A

Heat

Resistance

Up to 90C when topcoated. Water Resists rain and condensation when topcoated.

Solvent Resists aliphatic hydrocarbons, sensitive to alcohols and

strong solvents.

Abrasion Resists abrasion when topcoated.

Acid N/A Alkali N/A

Typical Properties

V.O.C

Content

< 5 g/L untinted Clean Up Clean up water

Clean all equipment with water after use.

Application

Method

Application

ConditionsSolids By Volume 30

Min Max Recommended

Wet Film Per Coat (microns) 65 130 65

Dry Film Per Coat (microns) 20 40 20

Recoat Time (min) 2 Hours NA

Theoretical Spread Rate (m2/L) 10 5 10

Application Guide

Surface

Preparation

All surfaces must be cured, clean, sound and free of all contaminants such as form oils, release agents & mortar splashes. Surface

imperfections, misalignments and protrusions must be levelled & patched & completely flush to surrounding surfaces. Metal, tie wire, etc

on surface must be removed or treated against corrosion.

Substrate Moisture Content:

Moisture Content of dense concrete prior to coating should be less than 8% measured to a depth of at least 25mm and not be subject to

re-wetting from latent sub-surface moisture or external sources.

Typically this requires 8-12 weeks drying of dense precast or cast insitu concrete.

Accurate measurement of concrete moisture content requires specialist equipment (typically involving drilling and insertion of probes

embedded in an electrically conductive gel)

Indicative surface spot measurement using a device with fine surface needle probes (generally referred to as "Equivalent Wood Moisture

or EWM" ) is less reliable in discerning sub surface moisture and may produce variable results dependent on the density of the masonry

under test and the presence of any substrate salts which can affect conductivity. Some units can operate in search or survey mode

providing indications of potential sub surface areas of concern.

Typically, "EWM" content prior to coating should be less than 12% and it is recommended that area review includes sub surface surveying

to identify potential areas of concern.

Alternatively a practical test to confirm "concrete safe to paint" involves taping (sealing all edges) of a 1m x 1m clear plastic sheet the

concrete surface and leaving for 24 hours. Darkening of the concrete under the film or condensation on the underside of the film indicates

the presence of excessive moisture

.

Application

Procedure

And

Equipment

Brush, roller, conventional or airless spray.

Product should be thoroughly mixed before use.

Refer to the DULUX AcraTex Application Manual for detailed application instructions.

DULUX AcraTex AcraPrime Water Based may be applied by roller, conventional or airless spray. A brush is required to cut in around

edges and obstacles.

Typical airless set-up: Graco Ultra 500 using 0.011-0.013 spray tip at approx. 1000 psi.

Version 21.0 of AcraTex datasheet AUDA0441 approved on Friday, 3 June 2016 8:25:07 AM (UTC) Page 4 of 5

Page 93: LANDSCAPE WORKS SPECIFICATION

Health And Safety

MSDS

Number

14557202 Using

Safety

Precautions

Wear eye protection.

Health

Effects

For detailed information refer to product label and the

current Material Safety Data Sheet available through Dulux

Sales and Customer Service Offices 132377 AUS. Health

Effects: Splashes to the eye may cause eye irritation. For

detailed information refer to product label and the current

Material Safety Data Sheet available through Dulux Sales

and Customer Service Offices 132377 AUS. Health Effects:

Splashes to the eye may cause eye irritation.

Protective

Equipment

When spraying, inhalation of mists may produce respiratory

irritation.

Storage 0

In the case of emergency, please call 1800 033 111

Transport And Storage

Pack A 194-20809 Shipment

Name

Not dangerous goods.; No special transport requirements.

Size Weight

15 Litre 21.5 Kg

Flash Point NA UN

Number

NA

Dangerous

Goods

Class

NA Package

Group

NA

Images

DisclaimerDulux, Selleys and Other marks followed by ® are registered trademarks. Marks followed by the symbol of ™ are trademarks.

The data provided within the Duspec system is correct at the time of publication, however it is the responsibility of those using this information to check that it is current prior tospecifying or using any of these coating/product systems.DISCLAIMER: Any advice, recommendation, information, assistance or service provided by any of the divisions of DuluxGroup (Australia) Pty Ltd or its related entities (collectively,DuluxGroup) in relation to goods manufactured by it or their use and application is given in good faith and is believed by DuluxGroup to be appropriate and reliable. However, any advice,recommendation, information, assistance or service provided by DuluxGroup is provided without liability or responsibility PROVIDED THAT the foregoing shall not exclude, limit, restrictor modify the right entitlements and remedies conferred upon any person or the liabilities imposed upon DuluxGroup by any condition or warranty implied by Commonwealth, State orTerritory Act or ordinance void or prohibiting such exclusion limitation or modification. Coating/product systems can be expected to perform as indicated on the Duspec Spec Sheet solong as applications and application procedures of the individual products are followed as recommended on the appropriate Product data Sheet. "DuluxGroup" "Dulux" "Selleys" "Berger""Berger Gold Label" "Hadrian" "Walpamur" "Levene" "Acratex" and Other marks followed by ® are registered trademarks of DuluxGroup (Australia) Pty Ltd ABN 67 000 049 427. Marksfollowed by the symbol ™ are trademarks.

Please note that this document is only valid for 60 days from the date of issue.

DuluxGroup (Australia) Pty Ltd 1956 Dandenong Road, Clayton, Victoria 3168 AU ABN 67 000 049 427

Version 21.0 of AcraTex datasheet AUDA0441 approved on Friday, 3 June 2016 8:25:07 AM (UTC) Page 5 of 5

Page 94: LANDSCAPE WORKS SPECIFICATION

AUDA0432Dulux AcraTex AcraShield Advance

Part A 194 line Approvals CONFORMS TO AS4548.1, AS4548.2 : Long Life Coatings

for Masonry

Product Overview

Previously known as DULUX AcraTex 955 AcraShield

DULUX AcraTex 955 AcraShield Advance is a high build, pigmented, water based 100% acrylic coating available in matt, low gloss and gloss finishes.

It is designed to overcoat DULUX AcraTex textured coatings.

Features And Benefits

10 year warranty

Water based

Tintable

Durable acrylic

Flexible

AntiCarbonation Properties

Guaranteed long term exterior durability & water resistance.

Easy, safe and economical clean-up.

Extensive, deep colour range.

Resists pollution, chemical attack and dirt pick-up.

Crack bridging 6 times average film build.

Resitance of Diffusion of Carbon Dioxide.

Uses And Typical Specifications

Uses DULUX AcraTex 955 AcraShield Advance is used as a protective topcoat over DULUX AcraTex texture coatings. It substantially upgrades

the overall coating system durability & ensures greater colour consistency, especially over large areas. It significantly improves wash-ability,

reduces dirt accumulation, pollution and chemical attack especially on high profile textured coatings.

Typical

SystemsTypical System AUSA1132 Dulux AcraTex 955 AcraShield on Painted Masonry Surfaces

Preparation Guide REFER TO FULL SPECIFICATION AUSA1132 for PREARATION GUIDE

Premium System for Previously Painted Masonry Surface.

Incorporating AcraTex AcraPrime 501/2 Deep Penetrating Solvent based sealer and AcraTex 955 AcraShield ® is a midbuild water borne, highly flexible

100% acrylic elastomeric membrane weatherproofing coating with excellent water impermeability, carbonation

resistance, chloride ion resistance, and resistance to mould and mildew.

That can be applied by roller - conventional nap or low profile texture sleeves or airless spray to provide maximum

crack bridging and anti-carbonation performance.

Not for immersion. Independent test certification is available on request.

Coat Product Spread Rate (m2/L) WFT (micron) DFT (micron)

1st Coat Acraprime Solvent Based 10 107 15

2nd Coat AcraShield Advance 6.0 167 75

3rd Coat AcraShield Advance 6.0 167 75

Minimum System DFT 165

Version 36.0 of AcraTex datasheet AUDA0432 approved on Wednesday, 20 June 2018 9:30:49 PM (UTC) Page 1 of 4

Page 95: LANDSCAPE WORKS SPECIFICATION

Precautions And Limitations

To ensure colour uniformity and for optimum performance, Dulux recommend a full coating system including a MEMBRANE top coat.

For ALL systems the Texture &/or Base Coat should be tinted in accordance with AcraTex Tint Guide to the specified top coat colour

(or a colour as close as possible to the specified colour as product and tint rules allow). IMPORTANT: Not all colours are suitable for exterior use.

This product data sheets is to be read in conjunction with DULUX specification.

Ensure that you have adequate tinted stock to complete the job in one application. All material must be thoroughly cross-mix to ensure tint uniformity.

It is recommended to hold a volume of finish material for future maintenance touch-ups

Practical spreading rates will vary from quoted theoretical figures depending on substrate porosity, surface roughness, overspray losses, application

methods and environmental conditions (e.g. wind).

All preparation and painting must conform to AS2311: The Painting of Buildings

At Commencement of coating system application, to the substrate it shall be deemed that the Applicator has certified that the surface which the coating/s is to

be applied to, is fit to receive the specified coating(s) system.

Do not apply paint if Relative Humidity is above 85% or temperature is within 3°C of Dew Point.Do not apply if the surface temperature is greater than 40°C or below 10°C, or likely to fall below 10°C during the application or drying period.Dry times apply to a single coat at recommended spread rate and at 25°C and 50% Relative Humidity Allow longer times under cool, moist, or still conditions and or when applied at high film builds.

Protect from dew, rain and frost for 48 hours when apply at the recommended spread rate.

Avoid application in hot, windy conditions or on hot surfaces cool the surface by hosing with water and paint the cool damp surface.

Application techniques should be adjusted to achieve the recommended DFT and finishing standard.

To avoid "Picture Framing" of texture topcoats "wet on wet" cutting in & coating technique is recommended or apply multiple coats thinning the first coat.

When using Bright Reds, Oranges, Blues and Yellows or where very light (or dark) colours are applied over highly contrasting colours an extra coat maybe

required.

The coastal area is considered a marine environment and as such salt potentially can shorten the life of the coating systems. Care needs to be taken to wash

down all areas twice. Once to remove surface contaminants, and raise salts to the surface and then secondly to remove these salts. Due to the locality,

weather conditions and lag time between applications of the coating system it may require the need to wash again, between coats.

When the Applicator is preparing the site sample for approval he should advise the Project Superintendent if the substrate condition is not of sufficient

standard to produce the specified finish.

Where possible avoid dark colours - these will give raise to much higher surface temperature that may cause addition thermal stress and cooling demand to

the building envelope and/ or require extra engineering considerations (greater building costs).

Consult Dulux on the potential to use InfraCOOL Heat Reflective Coatings.

A DULUX warranty can be provided on request, when the FULL AcraTex system including a membrane topcoat/s is applied by a DULUX AcraTex trained

applicator, according to specification, & at the specified spreading rates, & to the surface preparation details described in the DULUX AcraTex Specification

Manual.

The dynamics of the substrate is outside the control of Dulux Australia and as such joint deformation or cracking is excluded from warranty terms.

Colour change is a natural part of a coating weathering and is excluded from warranty terms

Refer warranty document for full terms and conditions.

CEMENT RENDERS PRODUCE FINE CRACKS DURING DRYING AND CONTINUE TO CRACK & MOVE WITH VARIATIONS IN TEMPERATURE.

FOR ENHANCED PERFORMANCE USE A HIGH BUILD ELASTOMERIC (FLEXIBLE) COATING.

DULUX RECOMMENDS THE USE OF DULUX ACRASHIELD ADVANCE.

Fungi and Algae can exist on virtually any surface (even glass) provided the right conditions for growth are met.

Visible growth on painted surfaces is typically caused by contaminants present together with the presence of high enough levels of moisture to support

growth. Agents in paints become ineffective where they cannot “touch” the growth source (eg where growth emanates from deposits on the film). Additionally the active agents are “consumed” in the process such that protection is time limited where conditions support ongoing growth performance isgreatly improved with the inclusion of a membrane Top coat like Dulux AcraTex AcraShield Advance, Elastomeric 201 or AcraSkin.

Refer: http://www.dulux.com.au/specifier/our-brands/dulux-acratex/more-than-just-render

The exterior texture coatings should be cleaned on a regular basis. This will help maintain your overall aesthetic appearance and preserve your AcraTex

Texture coating system. Cleaning once every year will remove light soil as well as grime and airborne pollutants refer Dulux AcraTex Care & Maintenance

Guide. Refer http://www.dulux.com.au/specifier/our-brands/dulux-acratex/acratex-care-and-maintenance

SURFACTANT LEACHING FROM EXTERIOR WATER-BASED COATINGS

Occasionally amber, clear or white spots/streaks are seen on a newly painted surface within the first few weeks after application. They usually appear after

light rain or overnight dew and generally located in sheltered areas or areas with limited sun exposure. Under normal conditions surfactant contained in the

tinted paint colour is slowly leached to the surface and washed away by rain leaving no trace and is a normal part of drying of any exterior water-based

paint. Under certain atmospheric conditions and these surfactants leach or migrate to the paint surface, is concentrated forms and leaves clear or white

deposits upon drying. These conditions include cool or humid weather or painting cold substrate and in most cases these marks on the wall surfaces are

more noticeable on dark colours, such as browns or dark greens, etc..

The clear/white surfactants that have migrated to the wall surface areas will cause no down grading nor performance changes or long term durability

concerns of the paint films integrity and unfortunately have become an appearance issue instead.

They easily removed from the paint film within a week or so of their appearance by washing with warm water & commercial grade detergent or via Nifti or

Spray'n'Wipe followed by rinsing with fresh clean water.

Under severe conditions they may reappear once or twice until all the surfactant has been removed. It will be less noticeable each time, and can be removed

in the same manner as before. Refer http://www.dulux.com.au/pdf/tech-advice/DLX_TECH_Leaching.pdf

CEMENT RENDERS PRODUCE FINE CRACKS DURING DRYING AND CONTINUE TO CRACK & MOVE WITH VARIATIONS IN TEMPERATURE.

FOR ENHANCED PERFORMANCE USE A HIGH BUILD ELASTOMERIC (FLEXIBLE) COATING. DULUX RECOMMENDS THE USE OF DULUX ACRASHIELD 955.

Version 36.0 of AcraTex datasheet AUDA0432 approved on Wednesday, 20 June 2018 9:30:49 PM (UTC) Page 2 of 4

Page 96: LANDSCAPE WORKS SPECIFICATION

Air Spray Airless Spray Brush Roller

BLACK, BLUE BASE, BOLD YELLOW, DEEP, EXTRA BRIGHT, ORANGE, TRUE RED, ULTRA DEEP, VIVID WHITE

System Performance Testing Data

Test Result Name Test Method Unit of Measure Result Comments

ALL Test Results Independently Tested . . REFER TO SPECIFIC DATA SHEETS

AUSA1408 AcraShield Advance Low Gloss

AUSA1409 AcraShield Advance Matt

Performance Guide

Weather Excellent resistance to cracking, flaking and chalking as

topcoat of a full system.

Salt Resists salt spray.

Heat

Resistance

Up to 90C (dry). Water Contributes to outstanding moisture barrier properties of full

texture systems.

Solvent Resists alcohol and aliphatic hydrocarbons. Sensitive to

other stronger solvents.

Abrasion Very good resistance to abrasion.

Acid Resists dilute acids. Alkali Resists dilute alkali.

Typical Properties

V.O.C

Content

REFER TO SPECIFIC DATA SHEETS AUSA1408 AcraShield

Advance Low Gloss AUSA1409 AcraShield Advance Matt

Clean Up Clean up water

Clean all equipment with water after use.

Application

Method

Application

ConditionsSolids By Volume 45

Min Max Recommended

Wet Film Per Coat (microns) 167 222 167

Dry Film Per Coat (microns) 75 100 75

Recoat Time (min) 2 Hours NA

Theoretical Spread Rate (m2/L) 6 4.5 6

Dulux

Colour

Base

Application Guide

Surface

Preparation

Ensure the texture coating is completely dry, especially during winter.

The textured surface should be clean and of uniform texture and appearance.

Ensure adequate masking is used to protect adjacent surfaces.

Application

Procedure

And

Equipment

Brush, roller and airless spray

Brush and roll at the same time to avoid picture framing.

Product should be thoroughly mixed before use. Refer to the DULUX AcraTex Application Manual for detailed instructions.

DULUX AcraTex 955 AcraShield may be applied by brush, roller or airless spray.

A 10-20mm nap roller is used depending on the type of texture being overcoated.

Typical Airless Spray set up is: Graco Ultra 500 using 0.019-0.021 spray tip at approx. 1000 psi.

Version 36.0 of AcraTex datasheet AUDA0432 approved on Wednesday, 20 June 2018 9:30:49 PM (UTC) Page 3 of 4

Page 97: LANDSCAPE WORKS SPECIFICATION

Health And Safety

MSDS

Number

40163 Using

Safety

Precautions

When spraying, inhalation of mists may produce respiratory

irritation.

Health

Effects

For detailed information refer to the current Material Safety

Data sheet available through Dulux Sales and Customer

Service Offices 132377 AUS. Health Effects: Splashes to

the eye may cause eye irritation. For detailed information

refer to the current Material Safety Data sheet available

through Dulux Sales and Customer Service Offices 132377

AUS. Health Effects: Splashes to the eye may cause eye

irritation.

Protective

Equipment

Wear eye protection and when spraying wear a dust mask

Storage 0

In the case of emergency, please call 1800 033 111

Transport And Storage

Pack A 194 line Shipment

Name

Not dangerous goods.; No special transport requirements.

Size Weight

15 Litre 20.5 Kg

Flash Point NA UN

Number

NA

Dangerous

Goods

Class

NA Package

Group

NA

Images

DisclaimerDulux, Selleys and Other marks followed by ® are registered trademarks. Marks followed by the symbol of ™ are trademarks.

The data provided within the Duspec system is correct at the time of publication, however it is the responsibility of those using this information to check that it is current prior tospecifying or using any of these coating/product systems.DISCLAIMER: Any advice, recommendation, information, assistance or service provided by any of the divisions of DuluxGroup (Australia) Pty Ltd or its related entities (collectively,DuluxGroup) in relation to goods manufactured by it or their use and application is given in good faith and is believed by DuluxGroup to be appropriate and reliable. However, any advice,recommendation, information, assistance or service provided by DuluxGroup is provided without liability or responsibility PROVIDED THAT the foregoing shall not exclude, limit, restrictor modify the right entitlements and remedies conferred upon any person or the liabilities imposed upon DuluxGroup by any condition or warranty implied by Commonwealth, State orTerritory Act or ordinance void or prohibiting such exclusion limitation or modification. Coating/product systems can be expected to perform as indicated on the Duspec Spec Sheet solong as applications and application procedures of the individual products are followed as recommended on the appropriate Product data Sheet. "DuluxGroup" "Dulux" "Selleys" "Berger""Berger Gold Label" "Hadrian" "Walpamur" "Levene" "Acratex" and Other marks followed by ® are registered trademarks of DuluxGroup (Australia) Pty Ltd ABN 67 000 049 427. Marksfollowed by the symbol ™ are trademarks.

Please note that this document is only valid for 60 days from the date of issue.

DuluxGroup (Australia) Pty Ltd 1956 Dandenong Road, Clayton, Victoria 3168 AU ABN 67 000 049 427

Version 36.0 of AcraTex datasheet AUDA0432 approved on Wednesday, 20 June 2018 9:30:49 PM (UTC) Page 4 of 4

Page 98: LANDSCAPE WORKS SPECIFICATION

620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx Page 1 of 4

APPENDIX C Cutex Timber Stain and Oil Finish

Page 99: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

FACTSHEET No 2 Cutek Extreme Oil

When other timber coatings fail professionals turn to Cutek

Cutek Extreme Advanced Timber and Engineered Wood Protection

When you need a professional grade finish choose Cutek Extreme.

This high performing wood protection oil has been formulated by

experts to control moisture and minimise warping, cupping and splitting

- making your project last longer.

It resists water from the inside out, so it’s perfect for outdoor applications

on natural and thermally modified wood and it is strong enough to stand

up to Australia’s most challenging tropical climates. Cutek Extreme is

the only product in our range that’s suitable for use on bamboo and

engineered bamboo products.

Cutek Extreme comes as a clear oil which fades in the sun to a natural

silver patina but at slower rate that Cutek CD50. It may also be mixed

with any of our 10 colourtones to enhance and maintain the freshly oiled

natural look of your timber.

Cutek Extreme is NOT suitable for use on acetylated wood.

• Best for challenging environments – clear silvers at a slower rate than

CD50 or may be used colourtoned to retain the freshly oiled look

• Protects from the effects of moisture – minimises warping, cupping

and splitting

• The right choice for most engineered wood products.

Understanding colourtonesIt’s important to understand that CUTEK is a unique penetrating oil system designed to enhance the natural colour and

grain of wood. CUTEK is sold as a clear oil which can be used to protect the wood from moisture and moisture related

movement such as cupping, warping and splitting. Using just the clear oil will protect the wood, providing stability and

structural integrity while allowing it to naturally lighten to produce a silver weathered patina over time. The soft natural

Page 100: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

lightening and silvering of the wood represents a low care option and is becoming an increasingly popular way to leave

wood in weather exposed settings.

Wood projects using clear CUTEK oil that have silvered can easily be returned back to the wood’s original colour using

ProClean and high pressure washing followed by further applications of CUTEK clear oil.

However, if you desire to maintain the original colour of the wood then you need to purchase a Colourtone suited to your selected wood which will further enhance the natural colour and grain and help to maintain its “natural” colour over a longer period of time.

What to expect when using colourtone

Most wood care products on the market leave a build up of material on the surface of the wood. In the short term this

provides more colour, but in the long term the finish can be prone to peeling and flaking, which requires time and money

to repair.

The Cutek system is unique as it will fade over time rather than peel or flake. The initial Cutek Colourtone build on new

smooth wood projects only offers subtle amounts of pigment that enhance the wood. Timber that’s exposed fully to

the weather will lighten faster as the wood acclimatises over the first six months. A follow up application after this initial

weathering period will provide much greater Colourtone build as the wood becomes rougher and more open.

How to increase colour build on new wood

New wood is milled smooth and often has a mill glaze which will greatly restrict the initial colour build. Better results can be

achieved by creating a rougher surface and preparing the wood using Cutek Proclean in combination with a high pressure

washer. Sanding the new wood to 80 grit will give even better results as it removes mill glaze and creates a much rougher

surface which will enable higher colour build. Note The rougher the surface of the wood, the greater the colour build

and durability. Rough sawn or heavy brushed wood profiles will take more oil and colour so much bolder colour contrast

can be achieved. The amount of mill glaze if any that is present on any job can vary significantly depending on species

density, and machining method used. Note Sanded surfaces should be vacuumed or washed thoroughly to remove all

loose wood and dust.

Before you apply

Surface preparation is essentialIn order for Cutek Extreme to function properly it’s essential that it diffuses deeply into the timber. Anything that might

prevent penetration such as an existing coating, retained moisture, or not leaving sufficient time between coats must be

avoided or corrected before applying.

Preparation may involve thorough sanding or stripping to completely remove any previous film forming coating.

If stripping is required, we recommend using Cutek CD33 Naked and Cutek Proclean to prepare the surface

for Cutek oils.

Before using Cutek Extreme, it is vital to ensure the wood is clean, dry (moisture content less than 17%) and has no

existing paint, oil or stain.

Always remember that unless you want a clear finish that will lighten/silver off in a few months, it is important to mix a

Cutek Colourtone into the oil before use.

Make sure you prepare your timber before applying Cutek Extreme in order to get the best results.

Page 101: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

How to apply

New Wood

Ensure that timber to be coated is clean and dry. Cutek Extreme can be used on treated timber, however wood with mill

glaze, or pre-treated with wax and polymer processes such as LOSP may require cleaning first with Cutek Proclean.

Old, or Previously Coated Wood

Old, dirty, stained or weathered timber should be prepared by first applying Cutek Proclean restoration agent, then power

rinsing with a high-pressure washer set to under 750 p.s.i. (50 bar), with a fan jet pattern to avoid damage to the wood fibre.

Once the timber is thoroughly dry, apply two coats of Cutek Extreme.

Wood previously coated with a film forming product such as stains, linseed oil, paint, polyurethane, etc., must first be

restored with Cutek CD33 Naked paint stripper and Cutek Proclean prior to the application of Cutek Extreme. This

process can be complex, so view the videos on this website for more information.

The results achieved from restoration are dramatic and rewarding – the original natural colour and beauty of wood

can be restored.

Application Technique

Before you get started

Before you begin, note the hazards and precautions on our website and the can labelling, and ensure that you use the

correct safety equipment as detailed in the Safety Data Sheet.

Step by step application process

Avoid contact with plants, shrubs, trees and waterways. For best results, one coat of Cutek Extreme should be applied

to all faces of the wood prior to installing, with a second coat applied to the top surface once the first coat is

completely dry. Penetration time varies significantly, depending on species, temperature, porosity, and moisture content of

the wood. Thicker sections such as post, beams and logs will require additional coats, as Cutek Extreme has a cumulative

effect in the wood.

Apply each coat evenly with brush, paintpad or roller. When using Cutek Colourtone it is essential that the container

holding the oil be stirred frequently both before and during use. Two or three thin coats on finished wood and hardwoods

are better that one or two thick coats.

Wood must feel completely dry and non-greasy before application of the second coat.

Cleanup

Equipment may be cleaned with soap and water or turps. Oily rags and other oily materials may cause combustion fires.

Immediately after use you MUST (1) spread out all oily materials outside to dry, by flattening them out to their full size in

an airy spot at temperatures above 4 degrees Celsius, or (2) Wash them thoroughly with water and detergent and rinse.

Remove all oil from all clothes, tools, rags and any other materials contacted during use or as a result of an accidental spill.

All wash water is to be disposed of properly.

Page 102: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

Coverage

These figures represent typical averages for common decking and cladding timbers such as Western Red Cedar, Pine,

Spotted Gum, Jarrah, Ironbark, Ipe, Tiger deck, Cumaru and other Exotics, Thermal wood etc.

New hardwoods dressed 10–20m2/litre (400–800sq feet/gallon)

Old restored timber dressed 7–9m2/litre (300–400sq feet/gallon)

New timber rough sawn 7–9m2/litre (300–400sq feet/gallon)

Old restored timber rough sawn 4–7m2/litre (180–300sq feet/gallon)

Shingles and shakes 2–5m2/litre (84–212sq feet/gallon)

MaintenanceCutek Extreme will gradually fade over time rather than peel, split or crack, so the rejuvenation of timber coated with

Cutek Extreme is a simple fast and cost-effective process.

Cutek Extreme should be reapplied when the wood is no longer beading water, or as frequently as necessary to retain the

natural beauty and colour of the wood. Clear Cutek Extreme coated timbers require maintenance less frequently than

colourtoned Cutek Extreme coated timbers.

Recoat time varies widely according to many factors including the age and porosity of the wood, species, situation and

exposure to the weather. Typically, horizontal exterior smooth surfaces such as pool decks and handrails may require

coating every 6 months to two years, while vertical rough sawn cladding may require maintenance less frequently.

Page 103: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

FACTSHEET No 8 How to maintain Cutek

When other timber coatings fail professionals turn to Cutek

Surfaces that have been previously coated with Cutek oils that have faded, or started to “grey off” in the sun are easily

and quickly restored to their original appearance without the need for any sanding and stripping, by treatment with

Cutek QuickClean or Cutek Proclean, and the application of one or two further coats of a Cutek wood protection oil.

Cutek oils must be reapplied as frequently as necessary to retain the natural beauty and colour of the timber.

How to maintain Cutek oiled timber - step by step

1. Clean the timbers – Apply cleaner

If the timber is only dirty and faded, Cutek QuickClean may be all that you need to prepare the surface for another

coat of a Cutek oil. Cutek QuickClean is designed as a cost effective, biodegradable cleaner for the restoration of

uncoated, dirty and weathered timber. Cutek QuickClean is less powerful than Cutek Proclean, however it is less

hazardous, and will not damage substrates or vegetation adjacent to the timber surface being restored, eliminating

the need for containment or masking. If your timber is quite weathered and stained, better results will be obtained by

using Cutek Proclean.

Apply Cutek QuickClean liberally to the timber substrate with brush, roller, or garden sprayer. Let Cutek QuickClean do

most of the work by letting it dwell on the surface for 10 – 20 minutes, or such time as deemed to be necessary by the

test procedure. It may be necessary to scrub stubborn stains moderately with a stiff fibre brush.

2. Clean the timbers and remove the cleaner

Once Cutek QuickClean has cleaned the timber, it must be power water rinsed (hot water works best) off. For best

results wash off with high-pressure water at approximately 750 p.s.i. pressure. Clean from the lowest point and work

upwards methodically. ALWAYS clean off with a water jet that produces a “putty knife” shaped fan that is 40–50mm

wide about 100mm out from jet. Adopt a continuous “mowing action” working with power water fan-jet 100mm from

the face of the substrate. DO NOT use “turbojets” on timber. CAUTION must be used when cleaning soft timber to

reduce the pressure and avoid damaging the sapwood. The longer that Cutek QuickClean is left on the substrate,

the greater the rinse time required.

IMPORTANT

If the deck has been previously coated with another oil, other than Cutek, the timbers will

need to be stripped back to bare as most other oils on the market have a film-forming surface

polymer which forms a barrier which will inhibit the penetration of Cutek oils. Please refer to the

Factsheet No7.

Page 104: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

3. Recoating with Cutek oil

Following the cleaning of the timber with Cutek Quickclean or Proclean, it is important to complete the maintenance

process by coating the timber with an appropriate Cutek wood protection oil, following the procedure detailed in the

relevant factsheet.

CAUTION must be used when cleaning soft and hard timbers - reduce or increase pressure by allowing the fan to

get closer or further away from the substrate. Additionally, certain types of wood surfaces may leave a raised grain,

these area can be sanded once dried. If you only have a low pressure, low flow pressure cleaner, a turbo head can

be used with caution.

IMPORTANT

Cutek oils designed to gradually fade over time rather than peel off, split or crack as is the case

with many conventional film forming coatings. For this reason, the rejuvenation and maintenance

of Cutek coated surfaces is a simple, fast, and cost effective process. Recoat time varies widely

according to many factors including the age and porosity of the timber, species, situation, and

exposure to the weather so we are unable to offer any specific performance warranties.

Typically, horizontal exterior smooth surfaces exposed to full weather such as pool decks and

handrails may require recoating every 6 months to 2 years, while vertical rough-sawn cladding

may require maintenance less frequently.

Page 105: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

FACTSHEET No 4 Colourtones

When other timber coatings fail professionals turn to Cutek

Cutek Colourtones Advanced Timber and Engineered Wood Colour System

We make preserving the beautiful, natural look of timber easy.

All Cutek oils are sold clear, which allows the wood to age gracefully into

a beautiful silver patina on exposure to sunlight. However, if you’d like to

retain the natural freshly oiled colour of the timber you’re working with

you can simply add a colourtone to the clear oil. Choose one of our 10

colourtones which have been specifically developed to closely match

many popular wood species.

For best results, select a colourtone that stays close to the natural shade

of the timber species being coated.

Autumntone

Greymist

Chestnut

Goldtone

Rustic Gold

Black Ash

Burnt Red

New Bronzetone

Walnut

Sela Brown

Understanding colourtonesIt’s important to understand that CUTEK is a unique penetrating oil system designed to enhance the natural colour and

grain of wood. CUTEK is sold as a clear oil which can be used to protect the wood from moisture and moisture related

movement such as cupping, warping and splitting. Using just the clear oil will protect the wood, providing stability and

structural integrity while allowing it to naturally lighten to produce a silver weathered patina over time. The soft natural

lightening and silvering of the wood represents a low care option and is becoming an increasingly popular way to leave

wood in weather exposed settings.

Wood projects using clear CUTEK oil that have silvered can easily be returned back to the wood’s original colour using

ProClean and high pressure washing followed by further applications of CUTEK clear oil.

However, if you desire to maintain the original colour of the wood then you need to purchase a Colourtone suited to your selected wood which will further enhance the natural colour and grain and help to maintain its “natural” colour over a longer period of time.

What to expect when using colourtone

Most wood care products on the market leave a build up of material on the surface of the wood. In the short term

this provides more colour, but in the long term the finish can be prone to peeling and flaking, which requires time and

money to repair.

Page 106: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

The Cutek system is unique as it will fade over time rather than peel or flake. The initial Cutek Colourtone build on new

smooth wood projects only offers subtle amounts of pigment that enhance the wood. Timber that’s exposed fully to

the weather will lighten faster as the wood acclimatises over the first six months. A follow up application after this initial

weathering period will provide much greater Colourtone build as the wood becomes rougher and more open.

How to increase colour build on new wood

New wood is milled smooth and often has a mill glaze which will greatly restrict the initial colour build. Better results

can be achieved by creating a rougher surface and preparing the wood using Cutek Proclean in combination with a

high pressure washer. Sanding the new wood to 80 grit will give even better results as it removes mill glaze and creates

a much rougher surface which will enable higher colour build. Note…The rougher the surface of the wood, the greater

the colour build and durability. Rough sawn or heavy brushed wood profiles will take more oil and colour so much

bolder colour contrast can be achieved. The amount of mill glaze if any that is present on any job can vary significantly

depending on species density, and machining method used. Note, sanded surfaces should be vacuumed or washed

thoroughly to remove all loose wood and dust.

Selecting Colourtones

Our Colourtone system is designed to enhance the wood colour and grain you select. With this in mind, you

need to think about your original wood choice and the colour it most represents. Is it light to Golden, Brown,

Red or a combination? Here are a few common examples to help you understand.

Black Butt and Silver Top Ash… Light tones so Rustic Gold is a good choice.

Spotted Gum…Light creamy to brown and greys. Rustic Gold and Sela Brown will all look similar on new smooth wood.

Merbau and Red Iron Bark…red to brown tone so Autumn Tone, New Bronzetone, Burnt Red and Chestnut will all look

very similar on smooth wood.

Forest Reds and Jarrah…Red tones. Autumn Tone, New Bronzetone and Burnt Red are all close options and will look

similar on smooth wood.

Changing the original colour of any wood

For horizontal walk on surfaces such as decking, we recommend you select a Colourtone that is the closest match to

the wood you have selected, rather than attempt to change the colour. You can talk to any of our stockists for advice.

For cladding and screening, a much higher build of colour can be achieved which can completely change the original

tone of the wood. Even very light wood coloured species can become an almost solid Black, Grey, Red, Brown or Gold

if the wood surface is suitably rough and more coats or a higher pigment loading has been added.

In some circumstances you can double your Colourtone to achieve bolder effects on rough or brushed wood. We

advise that you contact us to discuss this option in more detail as we want to ensure you have the best information

possible.

Applying colourtonesOne colourtone size can be used in all pack sizes as follows:

• 1 x 250 ml Colourtone pot is required for a 5 litre can of CUTEK oil.

• 2 x 250 ml Coloutone pots per 10 litre can of CUTEK oil.

• 4 x 250 ml Colourtone pots per 20 litre can of CUTEK oil

Stir and mix the Colourtone well before adding into the clear oil. Continue to stir well with a flat stirrer, lifting from the

bottom, for about 2 minutes before use and give a quick stir about every 15 minutes during use to ensure even results.

Page 107: LANDSCAPE WORKS SPECIFICATION

cutek.com.au

For best results, one coat of clear CUTEK oil should be applied to all faces of the wood prior to installing, with a second

and third coat of colourtoned Cutek oil applied to the top surface once the first coat is completely dry. Two or three thin

coats on finished wood and hardwoods are better than one or two thick coats. CUTEK oils will take longer to absorb/

penetrate into dense hardwoods so thin coats are best so as to avoid delayed drying of the oil.

MaintenanceColourtoned Cutek oil will lighten/fade faster in full weather exposed areas whereas wood in protected areas will retain

colour with minimal maintenance over time.

Cutek is designed to gradually fade over time rather than peel, split or crack. Rejuvenation of faded timbers coated with

Cutek oils is a simple, fast and cost-effective process.

Clear or colourtoned CUTEK oil should be reapplied as frequently as necessary to retain the natural beauty and colour

of the wood. Assessment of this is subjective and it is important to realise that colour durability varies widely according

to many factors including the age and porosity of the wood, species, situation, exposure to the weather and how rough

the wood surface is.

Typically, horizontal exterior smooth surfaces exposed to full weather such as pool decks and handrails will require

re-coating more frequently (initially after 6 months, then annually) than vertical rough-sawn cladding (typically every

2-5 years).

Page 108: LANDSCAPE WORKS SPECIFICATION

620.12664.00300-R01-v0.1_Pebble Creek Entry Road and Mountain Ridge Road_Landscape Specification.docx Page 3 of 4

APPENDIX D Dulux Timber Colour Finish

Page 109: LANDSCAPE WORKS SPECIFICATION

AUSD3812Dulux Weathershield Low Sheen on New Timber [Exterior]

Description

DULUX WEATHERSHIELD® X10 Low Sheen Acrylic is a 100% acrylic self priming paint for exterior use. Its unique MaxiFlexStretch Technology gives a tough flexible finish, for long life protection from the extremes of weather. Dulux guarantees that this

product will not blister, flake or peel for 10 years.

Substrate And Substrate Preparation

Substrate

Notes:

SUBSTRATE DESCRIPTION

NEW TIMBER

New timber items should be delivered in a clean dry condition, just prior to installation. The timber should be inspected for physical defects,

such as splinters, cracks, woolly grain, machine marks, and knot holes and also for other defects such as sap and tannin stains, and resin

exudation from knots. Examine surfaces for wax or preservatives. Moisture content should be close to equilibrium moisture content, usually

10-17% for satisfactory staining or coating. Timber should stored out of the weather before painting. Timber left exposed to the weather for

as little as one month prior to painting will suffer from reduced paint adhesion and durability.

AGED TIMBER

Old timber surfaces should be inspected for dry rot, mould or fungus, excessive water content, grey and weathered timber, grain cracking,

resins, stains, old unsound paint, dirt and any surface contamination. These defects should be rectified prior to painting.

TANNIN RICH TIMBER

Tannins are water-soluble extractives present in some timbers such as meranti, merbau, kwila, western red cedar and tallowwood. These

tannins are leached out by water or moisture and can cause staining of surrounding areas. They are seen as dark coloured stains either

under or within a coating.

Tannin staining is most obvious in light coloured coatings, such as whites. Darker and wood-toned colours hide the tannin stains best. When

using light colours on tannin rich timbers, an appropriate primer should be used to seal the tannins in the wood. These products are

manufactured as smooth sheets consisting of wood fibres bound with either natural lignin or a small percentage of phenolic resin.

Hardboard is widely used as interior panelling but is vulnerable to moisture and therefore not suitable for exterior exposure or in high

condensation conditions. Repairing damaged hardboard is not generally practicable and it is advisable to completely replace any damaged

sections. These products are manufactured from timber fibre bound with thermosetting phenol formaldehyde resin. They contain wax which

may inhibit the drying of solvent based alkyd enamels and tannins which may bleed through water based coatings. As manufactured the

smooth surfaces provide an ideal surface for finishing but machined edges are more porous and may show fibre raising when primed.

Substrate

Preparation

Notes:

ASSESS SUITABILITY Ensure the wood is thoroughly clean and dry before commencing. If there is any doubt, measure moisture content

which must be between 10-17% before staining or finishing can commence.

REMOVE SURFACE CONTAMINANTS Examine the surface for the presence of sap, grease, oil, wax, tannin, building marks, or other

contaminants. Scrape off and remove residual contaminants by solvent cleaning. Use scraper to remove dirt and mortar splashes. Any

greyed wood fibres on aged timbers need to be removed by sanding and / or suitable chemical wood cleaner. CLEAN Clean to remove all

dirt, dust and all other surface contaminants by using a suitable cleaning agent and rinse off with clean water. Treat mould with a suitable

mould treatment.

REPAIR SURFACE IMPERFECTIONS Fill nail holes, cracks and other defects with a suitable wood filler and allow to dry thoroughly.

SANDING Sand dressed timber with fine sandpaper in direction of the grain and along the full length of the board. Round off all sharp edges

to a minimum of 2 mm radius in order to achieve an even film build and uniform paint coverage.

Coating System Summary

1st Coat: AU_DD02065: Dulux Precision High Opacity Stain Blocker

2nd Coat: AUDD0053: Dulux Weathershield Low Sheen

3rd Coat: AUDD0053: Dulux Weathershield Low Sheen

Please refer to the coating system details below

Version 11.0 of Dulux specification AUSD3812 approved on Monday, 10 December 2018 1:20:43 AM (UTC) Page 1 of 3

Page 110: LANDSCAPE WORKS SPECIFICATION

Air Spray Airless Spray Brush Roller

Air Spray Airless Spray Brush Roller

Coating System

Coat Type: 1st Coat Datasheet: AU_DD02065 Dulux Precision High Opacity Stain Blocker

Application

Methods:

Min Max Recommended

Theoretical Spread Rate * 12 12 12

Wet Film Per Coat (microns) 125 83 83

Dry Film Per Coat (microns) 60.5 40 40

Recoat Time ** 90 minutes indefinite 90 minutes

Coating

Application

Details:

Brush Roller, conventional spray or airless spray application.

Stir thoroughly before and during use.

For Stainblocking applications do not tint or thin.

Apply one even coat of PRECISION High Opacity Stain Blocker. For heavily stained surfaces and for paperfaced plasterboard where there is

a different texture between the paper and jointing compound or where extra filling and smoothness is required, apply a second coat of

PRECISION High Opacity Stain Blocker.

For optimal coverage and smoothness, apply with:

• Brush: High quality synthetic filament brush (Nylon or Polyester) Apply in full even coating direct from the container.

• Roller: Medium nap synthetic roller (10­13mm on smooth surfaces or 13­18mm on semi­rough or porous surfaces) Apply in full even coating

direct from the container.

• Spray: Do not thin for stain blocking applications. Suitable for application by all standard spray equipment.

Clean Brushes and Rollers with Mineral Turpentine prior to and after use.

Brush/Roller:

Coat Type: 2nd Coat Datasheet: AUDD0053 Dulux Weathershield Low Sheen

Application

Methods:

Min Max Recommended

Theoretical Spread Rate * 15.6 15.6 16

Wet Film Per Coat (microns) 58 71 64

Dry Film Per Coat (microns) 25 25 25

Recoat Time ** 2 Hours Indefinite

Coating

Application

Details:

Brush, roller, conventional and airless spray

*Some colours may require more than the recommended number of coats to achieve full opacity.

Stir contents thoroughly before and during use with a broad flat stirrer, using an upward lifting action.

Brush/Roller: Soak brush or roller in water before starting and use while still slightly damp.

*Over bare timber, apply 3 coats of Weathershield.

On bare galvanised iron within 1km of the sea, apply one coat of Dulux All Metal Primer followed by 2 topcoats of Weathershield.

On bare steel apply one coat of Dulux All Metal Primer followed by 2 topcoats of Weathershield.

On all other surfaces, including brick, masonry and prepainted surfaces, 2 coats only are required.

For Weathershield Chromamax Pigment Bases (True Red, Bold Yellow, Orange, Blue and Extra Bright bases), to ensure excellent durability

and opacity it is essential to apply a coat of Dulux 1 Step Acrylic Primer Sealer Undercoat prior to the application of two topcoats of

Weathershield. However, if the surface is previously painted in a pale colour and is in sound condition no primer is required.

Professional Painters refer to Duspec Specification Sheets to qualify for guarantee. Under hot or very windy conditions, up to 100 ml/litre of

DULUX Hot Weather Thinner may be added to ease application.

Airless or Conventional Spray: Suitable for application by all standard spray equipment. Apply wet even coats. If necessary thin with up to

100 ml/litre water to aid atomisation.

Version 11.0 of Dulux specification AUSD3812 approved on Monday, 10 December 2018 1:20:43 AM (UTC) Page 2 of 3

Page 111: LANDSCAPE WORKS SPECIFICATION

Air Spray Airless Spray Brush Roller

Coat Type: 3rd Coat Datasheet: AUDD0053 Dulux Weathershield Low Sheen

Application

Methods:

Min Max Recommended

Theoretical Spread Rate * 15.6 15.6 16

Wet Film Per Coat (microns) 58 71 64

Dry Film Per Coat (microns) 25 25 25

Recoat Time ** 2 Hours Indefinite

Coating

Application

Details:

Brush, roller, conventional and airless spray

*Some colours may require more than the recommended number of coats to achieve full opacity.

Stir contents thoroughly before and during use with a broad flat stirrer, using an upward lifting action.

Brush/Roller: Soak brush or roller in water before starting and use while still slightly damp.

*Over bare timber, apply 3 coats of Weathershield.

On bare galvanised iron within 1km of the sea, apply one coat of Dulux All Metal Primer followed by 2 topcoats of Weathershield.

On bare steel apply one coat of Dulux All Metal Primer followed by 2 topcoats of Weathershield.

On all other surfaces, including brick, masonry and prepainted surfaces, 2 coats only are required.

For Weathershield Chromamax Pigment Bases (True Red, Bold Yellow, Orange, Blue and Extra Bright bases), to ensure excellent durability

and opacity it is essential to apply a coat of Dulux 1 Step Acrylic Primer Sealer Undercoat prior to the application of two topcoats of

Weathershield. However, if the surface is previously painted in a pale colour and is in sound condition no primer is required.

Professional Painters refer to Duspec Specification Sheets to qualify for guarantee. Under hot or very windy conditions, up to 100 ml/litre of

DULUX Hot Weather Thinner may be added to ease application.

Airless or Conventional Spray: Suitable for application by all standard spray equipment. Apply wet even coats. If necessary thin with up to

100 ml/litre water to aid atomisation.

Comments

Application techniques should be adjusted to achieve the recommended DFT and finishing standard. To avoid "Picture Framing" of texture topcoats "wet on

wet" cutting in & coating technique is recommended or apply multiple coats thinning the first coat.

Do not apply paint if Relative Humidity is above 85% or temperature is within 3°C of Dew Point.Do not apply if the surface temperature is greater than 40°C or below 10°C, or likely to fall below 10°C during the application or drying period.Dry times apply to a single coat at recommended spread rate at 25C and 50% Relative Humidity. Allow longer times under cool, moist or still conditions.

Practical spreading rates will vary from quoted theoretical figures depending on substrate porosity, surface roughness, overspray losses, application

methods and environmental conditions (eg wind).

DisclaimerDulux, Selleys and Other marks followed by ® are registered trademarks. Marks followed by the symbol of ™ are trademarks.

The data provided within the Duspec system is correct at the time of publication, however it is the responsibility of those using this information to check that it is current prior tospecifying or using any of these coating/product systems.DISCLAIMER: Any advice, recommendation, information, assistance or service provided by any of the divisions of DuluxGroup (Australia) Pty Ltd or its related entities (collectively,DuluxGroup) in relation to goods manufactured by it or their use and application is given in good faith and is believed by DuluxGroup to be appropriate and reliable. However, any advice,recommendation, information, assistance or service provided by DuluxGroup is provided without liability or responsibility PROVIDED THAT the foregoing shall not exclude, limit, restrictor modify the right entitlements and remedies conferred upon any person or the liabilities imposed upon DuluxGroup by any condition or warranty implied by Commonwealth, State orTerritory Act or ordinance void or prohibiting such exclusion limitation or modification. Coating/product systems can be expected to perform as indicated on the Duspec Spec Sheet solong as applications and application procedures of the individual products are followed as recommended on the appropriate Product data Sheet. "DuluxGroup" "Dulux" "Selleys" "Berger""Berger Gold Label" "Hadrian" "Walpamur" "Levene" "Acratex" and Other marks followed by ® are registered trademarks of DuluxGroup (Australia) Pty Ltd ABN 67 000 049 427. Marksfollowed by the symbol ™ are trademarks.

Please note that this document is only valid for 60 days from the date of issue.

DuluxGroup (Australia) Pty Ltd 1956 Dandenong Road, Clayton, Victoria 3168 AU ABN 67 000 049 427

Version 11.0 of Dulux specification AUSD3812 approved on Monday, 10 December 2018 1:20:43 AM (UTC) Page 3 of 3

Page 112: LANDSCAPE WORKS SPECIFICATION

ASIA PACIFIC OFFICES

BRISBANE Level 2, 15 Astor Terrace Spring Hill QLD 4000 Australia T: +61 7 3858 4800 F: +61 7 3858 4801

CANBERRA GPO 410 Canberra ACT 2600 Australia T: +61 2 6287 0800 F: +61 2 9427 8200

DARWIN 5 Foelsche Street Darwin NT 0800 Australia T: +61 8 8998 0100 F: +61 2 9427 8200

GOLD COAST Ground Floor, 194 Varsity Parade Varsity Lakes QLD 4227 Australia M: +61 438 763 516

MACKAY 21 River Street Mackay QLD 4740 Australia T: +61 7 3181 3300

MELBOURNE Suite 2, 2 Domville Avenue Hawthorn VIC 3122 Australia T: +61 3 9249 9400 F: +61 3 9249 9499

NEWCASTLE 10 Kings Road New Lambton NSW 2305 Australia T: +61 2 4037 3200 F: +61 2 4037 3201

PERTH Ground Floor, 503 Murray Street Perth WA 6000 Australia T: +61 8 9422 5900 F: +61 8 9422 5901

SYDNEY 2 Lincoln Street Lane Cove NSW 2066 Australia T: +61 2 9427 8100 F: +61 2 9427 8200

TOWNSVILLE Level 1, 514 Sturt Street Townsville QLD 4810 Australia T: +61 7 4722 8000 F: +61 7 4722 8001

AUCKLAND 68 Beach Road Auckland 1010 New Zealand T: +64 27 441 7849

NELSON 6/A Cambridge Street Richmond, Nelson 7020 New Zealand T: +64 274 898 628