larp accelerator systems status & plans 13 july 2009 doe review, fnal tom markiewicz/slac bnl -...
Embed Size (px)
TRANSCRIPT

LARP Accelerator Systems Status & Plans
13 July 2009
DOE Review, FNAL
Tom Markiewicz/SLAC
BNL - FNAL- LBNL - SLAC
US LHC Accelerator Research Program

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 2 / 35
The FY10 LARP Accelerator Systems Program
Instrumentation
– Beam Commissioning of Tune & Coupling feedback systems, Schottky Monitor, AC Dipole and Synchrotron Light Monitor
– Luminosity Monitor
– LLRF modeling and commissioning
Collimation
– Rotatable Collimator as a Phase II Secondary Collimator candidate
– T980 Crystal Collimation Study at the Tevatron
– UA9 Crystal Collimation Study at CERN’s SPS
– Hollow electron lens as a scraper for LHC
Accelerator Physics
– Electron lens as a Beam-Beam interaction compensator
– Control of E-cloud induced beam instability in SPS through RF feedback
– Crab Cavity R&D program
– PS2 Design Study

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 3 / 35
Task List & FY09
Budget as of
May’09 rev.
BNL FNAL LBNL SLAC Total
Accelerator Systems 575 521 1,005 1,350 3,451 Instrumentation 50 35 800 40 925Phase I 50 35 800 40 925Chromaticity Feedback (15) 15 0Luminosity Monitor 800 800Schottky 20 20AC Dipole 65 0 65LLRF 40 40
Collimation 180 211 0 1015 1406Phase I 0 0 0 0 0Cleaning Efficiency Study 0 0Phase II 180 211 0 1015 1406Rotatable Collimators 950 950Tertiary Collimation Study 0Crystal Collimation 180 211 0 65 456
T980 at Tevatron 0 166 0 166CRYSTAL at SPS 180 45 65 290
Irradiation Studies 0
Accelerator Physics 345 275 205 295 1,120 Studies 345 275 205 295 1,120
Electron cloud - - 90 65 155 Simulations - - 50 - 50 Ecloud FB at SPS 40 40 80 Grooved Chambers 25 25
Beam-beam 120 230 - 40 390 Simulation - 210 40 250 Wire Beam-Beam compensation 50 - - - 50 Electrons lens 70 20 - - 90
Discretionary 25.0 25.0 25.0 25.0 100 Crab cavities 200 20 40 40 300 PS2 Studies 50 125 175

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 4 / 35
Themes for this Presentation
2008 Review Recommendations– Develop a more strongly coupled and transparent relationship with
CERN management• Drop activities not deemed high priority by CERN
– Ensure that any “item to be delivered to CERN” is delivered• Manage such items as a separate project
– Develop a clear and open system to prioritize LARP projects
2009 Review Charge– Determine the priorities and levels of R&D effort LARP should
apply to position the U.S. for participation in the upcoming LHC upgrades• Multi-year plan• Timeline & resource requirements• Scientific and Technical risks

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 5 / 35
Program Oversight through Increased Communication
Accelerator Systems Advisory Committee created to parallel Magnet SC– Bruning (CERN), Fischer, Markiewicz, Prebys, Ratti, Peggs
ASAC meets (Webex) ~bi- weekly on general matters or as crisis management team– Task prioritization & Budget allocation– LARP Collaboration Meeting (CM) Planning– Luminosity Monitor Project Management
LARP Tasks have been coalesced into units large enough to warrant regular Webex meetings and see to it that these are held with additional participation of Program Leader, Deputy, L1, relevant L2 AND CERN Points of Contact– As opposed to reports of isolated work to general LARP
membership at semi-annual CMs

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 6 / 35
CERN and LARP Communication
Occurs at various CERN levels– CERN Point(s) of Contact:
• eg. Assmann (Collimation); Bravin (Lumi); Benedikt(PS2), …– CERN LARP contact: Oliver Bruning
• tasked with assimilating POC reports and upper management priorities – CERN middle managers: Ostijic (IR Upgrade Czar)– CERN key managers: Evans/Myers– CERN Director
Roughly mapping onto LARP– LARP Task Leader
• Markiewicz (Collimation); Ratti (Lumi); Wienands(PS2), … – LARP L1 (Markiewicz)– LARP APUL czar (Wanderer)– LARP Program Leader (Prebys)– OHEP (Strauss, Kovar)
• Oral “story” sometimes inconsistent and full set of players never in same room• Inadequate written correspondence• Improvement in both these areas required

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 7 / 35
CERN Input to FY10 LARP ProgramBruning Report to ASAC
Context:1) Lumi Mon assumed to be done by FY10 and not part of list; otherwise 1st priority2) Other "Done" projects, plus Lumi, will require some amount of funding for commissioning
activities: these include Schottky, AC Dipole, Chromaticity Feedback and any continued work on the Synchrotron Light Monitor
3) Bruning will go back again to CERN LLRF group & Myers to clarify CERN position on LLRF task
Ordered List:1) Rotatable Collimator2) PS23) SPS Ecloud control through RF feedback or other means4) Elens as collimation scraper5) R&D that will happen even if not supported by LARP:
- Elens Beam-Beam compensation (BNL & RHIC)- T980 (FNAL)- UA9 (existing CERN-Russian-Italian-US collaboration)
6) Crab: in this position because it requires a non-LARP framework to fund it7) H- emittance monitor for Linac 48) LLRF studies (despite "last place" rank LARP contribution appreciated as valuable &
support for commissioning should be provided; CERN management perspective is that CERN, not LARP, must "own" this role)

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 8 / 35
Extra-ordinary Meetings
US-CERN Meeting (2009 Jan 14)– Heuer, Myers, Evans, Bruning, Ostijic, Assmann, ..– Relevant AS take away point for LARP
• Crab activity perceived as LARP-driven. For CERN to proceed questions to be answered must include
– What is impact to LHC?– What can be measured?– What will be learned?– What is risk to LHC?
Phase II Collimation Conceptual Review (2009 April 2-3)– Full participation of Rotatable collimator team plus LARP management
• LHC will require– “Cryo-collimators” (collimators embedded in cold regions of LHC)– A new “High Radiation Materials Test Beam” (TT60 line) as part of MTP– Phase II secondaries of a type to be determined only after experience with
LHC and prototype testing in TT60

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 9 / 35
CERN Mid-Term-Planning Timeline
Priorities Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q41 LHC Operation assumed O O O O O Sh Sh O O Sh O O O Sh O O Sh Sh Sh O O1 SPS operation and exploitation O O O O O Sh O O O Sh O O O Sh O O Sh Sh Sh O O1 PS Operation and Exploitation O O O O O Sh O O O Sh O O O Sh O O Sh Sh Sh O O1 Booster Exploitation and Operation O O O O O Sh O O O Sh O O O Sh O O Sh Sh Sh O O1 Source/LINAC2 op and exploitation O O O O O Sh O O O Sh O O O Sh O O Sh Sh Sh Sh Sh
Linac3/LEIR/Ions Operation Sh Sh O O O Sh O O O Sh O O O Sh O O Sh Sh Sh O O1 LHC 3-4 magnet repair for spares C C C C1 Consolidation all accelerators C C C C C C C C C C C C C C C C C C C C C2 LINAC4 assumed C C C C C C C C C C C C C C C C Sh Sh Sh O O2 Inner Triplets assumed C C C C C C C C C C C C C C C C Sh Sh Sh O O1 AD assumed Sh Sh O O O Sh O O O Sh O O O Sh O O Sh Sh Sh O O1 AEGIS C? C? C? C? O? O? O? O? O? O? O? O? ? ?1 ELENA ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ??1 CNGS Sh Sh O O O Sh O O O Sh O O O Sh O O O Sh Sh O O1 East Hall (PS) Sh Sh O O O Sh O O O Sh O O O Sh O O O Sh Sh O? 0?1 ISOLDE (REX) Sh Sh O O O Sh O O O Sh O O O Sh O O O Sh Sh O? 0?1 nToF Sh Sh O O O Sh O O O Sh O O O Sh O O O Sh Sh O? 0?1 North Area (Compass etc) Sh Sh O O O Sh O O O Sh O O O Sh O O O Sh Sh O? 0?2 CAST/OSQAR ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ?? ??2 CTF3 Operation O O O O O O O? O? Sh O? O? O? Sh O? O? O? Sh O? O? O?2 CLIC/ILC St St St St St St St *St? St? Td? Td? Td? Td? Td? Td? Td? Td? Td? Td? Td? Td?2 Collimation Phase 2 St St St St St St St St St C? C? C? C? C? C? C? C?2 PS2 Study St St St St St St St St St St St *2 PS2 Construction C? C? C? C? C? C? C? C?2 SPL (LP) St St St St St St St St St St St *2 SPL Construction C? C? C? C? C? C? C? C?3 HIE ISOLDE C? C? C? C? C? C? C? C? C? C? C? C?3 High Field Quadrupoles R&D St St St St St St St St St St St St St St St St St St St St St3 Medical Applications St St St St St St St St St St St St St St St St St St St St3 Radiation Facilities (HiRadMat) C? C? C? C? C? C? C? C? C? O? O? O? Sh Sh O? O?
O Operation C Construction Sh Shutdown St StudiesO? * Council decision
20142010 2011 2012 2013
scar
city
of p
roto
ns

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 10 / 35
LARP Management OversightInstrumentation Task Meetings
Chromaticity FB, Schottky, AC Dipole, Synchrotron Light Monitor– No regularly scheduled “public” meetings– Contact between LARP & CERN POCs, esp. during commissioning trips– Reports at parallel sessions of CMs– No direct management oversight
Luminosity Monitor– Regular LBL staff mtgs and Ratti/Bravin mtgs during CERN trips– Biweekly status meetings since June 2008 with
• Prebys, Markiewicz, Bruning, Peggs, Ratti, Bravin, Corlett (LBL mgmt), 2 LBL EEs• Written status report distributed after each meeting
– Full grilling by AS at CM#11,CM#12 followed by plenary report to LARPLLRF
– SLAC 5 person group plus 2 CERN POCs call/exchange email– Many working trips to CERN– Work status presented at LARP CMs and at SLAC ARD seminars– No direct management oversight

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 11 / 35
LARP Management OversightCollimation Task Meetings
Rotatable Collimator
– Weekly staff (5) mtg at SLAC with web-posted progress report
– Biweekly webex/video with CERN collimation group (5-10 people)• Notes & slides posted
– Reports at parallel session of CM mtgs & included in plenary summary
– CERN-organized meetings (P-II Conceptual Review, Beams’07,..)
Crystal Collimation
– Bi-Weekly Webex meeting to which all members of both T980 (Fermilab expt.) and CERN SPS UA9 are invited
• Typically SLAC(5), BNL(1), Markiewicz, Prebys, Peggs & Scandale (CERN) attend• Approx. monthly reports from Mokhov on T980
– Unknown but large number of bi-lateral UA9 meetings in Europe
– Regular meetings of FNAL T-980 staff & FNAL resident visitors
– Semi annual mini crystal workshops & LARP CM presentations

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 12 / 35
LARP Accelerator Physics Task Meetings
Electron Lens for Beam-Beam Compensation– No regular working meetings (to my knowledge)– Annual mini-wkshps (eg. 12/3/08 at BNL) & reports at parallel session of
CMsEcloud
– Monthly Webex attended by CERN (3-4), SLAC (3) and LBL(3) and typically Fischer, Prebys & Markiewicz
– Semi-annual meetings in context of global Ecloud effort (eg. EC Mitigation-08 CERN, 12/08) and CARE series of workshops
– Reports in parallel session of CMsCrab Cavity
– Monthly international webex with large participation• UK, KEK, CERN (incl. LARP-residents), BNL, SLAC, FNAL, LBL, AES• Prebys, Markiewicz, Peggs, Strait
– Annual mini-workshop, ~quarterly mtgs at CERN, LARP CMs & CARE PS2
– Weekly/biweekly webex with BNL, FNAL, LBL & SLAC w/ Prebys & Markiewicz
– CM and CERN organized workshops

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 13 / 35
LARP Accelerator Systems Highlights
Luminosity Monitor: – All hardware is at CERN and all hardware that can be installed is installed
Rotatable Collimator:– First prototype jaw passes thermal mechanical tests– Majority of hardware for 3 more jaws (2 full collimators) in hand; fabrication in progress
PS2– 5 year plan focused on intensity-related effects involving the 4 LARP labs coordinated
with CERN; early resultsSPS Ecloud
– SPS measurements during 3 MD periods show effects that can be simulated; RF modeling to control instabilities has begun
Crab Cavity– Baseline design of cavity/coupler exists and SBIR to fabricate a cavity approved– Multinational, multilab effort working/meeting regularly to develop plan
Other– Crystal experiments UA9 and T980 installed full-time & taking data regularly– E-lenses for RHIC approved & feedback for LHC expected– LLRF model used to commission LHC system without beam;
beam commissioning planned– HW commissioning for Schottky, AC Dipole & Tune/Chromaticity FB complete– New Synchrotron Light Monitor designed, assembled & installed with LARP effort

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 14 / 35
Project Management
LARP Acc. Systems is producing hardware for CERN in 3 areas– Lumi Monitor– Rotatable Collimator– Roman Pot for SPS Crystal Collimation Expt #UA9
And is (was) considering delivering a crab cavity prototype
My thoughts:– Each of these would ideally be managed outside of LARP– Mission creep and external schedule slippage compound internal problems– Annual reviews necessary but not sufficient
• Aug. 2007 Lumi review & April ’08 CM10 did not foresee June’08 ‘crisis’– Monthly budget reporting with “earned value” necessary but not sufficient– Lumi has convinced me that some external manager(s) must follow
progress ~biweekly to fully understand the project in real time so that surprises do not happen
– TWM is trying to do this for the UA9 RP (reporting to Eric)– No one forces TWM to do this for RC

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 15 / 35
Luminosity Monitors2 per IP + One Spare
Detector Interface ChassisGAS Distribution/Monitoring Panel
PC for Local Monitoring1 per IP
DAQ Firmware
Shaper (& Chassis)Preamp/HV Assembly

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 16 / 35
Luminosity Monitor “Crisis” & Response
As Lumi is/will be the first LARP produced hardware installed in LHC it is essential that we deliver
June 2008 letter from CERN luminosity monitoring group leader Enrico Bravin raised concern that– Lumi might be be late for 2008 run– PMT system would be deployed for 2008– As long as robust system ready for 2009, no harm
Response:1. Major LARP support in FY09, before CY2009 run, to fully complete the
system (electronics fabrication, firmware, software & integration)2. Biweekly meetings of LARP ASAC w/Ratti-Bravin since June 29, 2008
– 20 meetings held with written reports (TWM)3. Greatly increased involvement of LBL management (Corlett + EE Head)
– MS Project maintained by LBL EE & kept up to date4. Ongoing discussions on how to minimize commissioning cost & handoff

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 17 / 35
Lumi Status: All Hardware Installed
Hardware Commissioning in Progress
All required Hardware Installed in LHC points 1 and 5:– Detectors (4) (plus spare at LBNL)– Preamps (4)– Shapers (4)– Detector Interface Units (2)– Gas Panels
Detailed list of noise issues, damaged RTDs, faulty power supplies, gas system leaks, unequal cable lengths, temperamental gas controllers all being worked on
Firmware– Phase I (Low Luminosity “Counting”) complete & being tested– Phase II (High Lum pulse height with centroid deconvolution) a
future project
System Modeling: New Toohig Fellow Ryoichi Miyamoto

LARP Rotatable Collimators for LHC Phase II Collimation
Gene Anzalone (CAD), Eric Doyle (ME-FEA, ret.), Lew Keller (FLUKA, ret.), Steve Lundgren (ME), Tom Markiewicz (Phys), Reggie Rogers (Mech Tech)
& Jeff Smith (PD)
BNL - FNAL- LBNL - SLAC
US LHC Accelerator Research Program
1) Adapt rotatable NLC design concept to LHC: “RC”
2) Build and test one collimator jaw with 10kW resistive heaters to verify thermo-mechanical performance
• Minimize deflection when absorbs with 60kW for 10 sec
3) Build a collimator that can be destructively beam tested at new TT60 facility yet which still rotates, provides clean collimation surfaces, whose cooling system survives and which is UHV
4) Build a fully functional collimator & test it at LHC

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 19 / 35
beam
LARP Rotatable Collimator
In TT60 vacuum tank:
•ports for camera to observe surface damage
•ports for laser micrometers to measure permanent distortion due to thermal shock
•DN250 end flanges for easy access to jaws after tests and cool-down
•CERN/LHC rack & pinion drives with water & cable quick-connects

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 20 / 35
LHC Phase II Base Concept
Glidcop Jaw - Cu Mandrel wrapped with CuNi coil – Hollow Glidcop Hub / Molybdenum Shaft with 2mm gap from Mandrel
• Beam spacing: 136mm OD
• Length 1.47 m flange–flange:
•930mm overall
•2 x 38mm 15° tapers
• 854mm long facets
Cu coolant supply tubes twist to allow jaw rotation
Hub area
Glidcop Cu Mo
Cantilever Mo shaft @ both ends
20 facets
Molybdenum Shaft
Copper Mandrel
Copper tubing wound in groove
Molybdenum Shaft
Copper Mandrel
Copper tubing wound in groove
Helical cooling channels 23mm below surface with 16m long 10mm square CuNi tube
2mm gap between shaft OD and mandrel ID

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 21 / 35
Glidcop Jaw – CuNi Coil- Cu Mandrel – Glidcop Hub - Molybdenum Shaft Design
365m
880m: Leff: 95cm→33cm
7ANSYS of Final Design
Proposal is to set 1st copper jaw at 8.5 (or to use C-C in this location)
Simulations show that remainder of system maintains efficiency
2mm gap

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 22 / 35
RC0 10kW Distortion Test

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 23 / 35
Second Generation Version of Collimator Assembly Support, Rotation Mechanism, and
RF transition to Vacuum Tank
Possible BPM location
RF Transition

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 24 / 35
Plan to Make 3 More Cylinder Jawsfor total of 4→Two Full Collimators
1st of 3 new mandrels finished March 28
6 Moly Half-shafts at SLAC
Plan:
RC1-SPS/TT60 end of 2009
RC2-LHC in 201n

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 25 / 35
Status of RC Program
1. Jaw support & rotation mechanism COMPLETE (June 2007)2. First full single jaw-hub-shaft unit COMPLETE (May 2008)3. Thermal distortion tests indicate performance in accord with FEA to ~10% (July
2008)4. Vacuum & flatness measurements all good
Since June 2009 DOE Review1. RF design finalized2. New concepts for vacuum tank, jaw support, braze process developed3. Copper mandrels for 3 new jaws bored and grooved4. Molybdenum support half-shafts and central glidcop hubs for 3 new jaws made5. Glidcop for 3 jaws obtained ($56k) and machined parts for 1 jaw ready6. 2nd jaw-hub-shaft unit being assembled & brazed week of July 13-17, 2009
Work to complete RC1:1. Finish 2nd jaw & modify 1st jaw so it is useable in collimator vessel2. Build supports & rotator mechanism and assemble with RF features in new vacuum
tank3. Metrology & vacuum tests at SLAC4. Mechanical motion tests on existing CERN system5. Ship to CERN

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 26 / 35
LARP RC Timeline for Discussion
2009 Build fully functional prototype
Vacuum & mechanical tests at SLAC
2010 Ship to CERN
Vacuum & mechanical tests at CERN
SPS Tests of impedance and BPMs
2011 Modest involvement in Phase I collimation commissioning
2012 Develop diagnostics for damage assessment
2013 Test prototype in TT60
2014 Apply lessons learned to production design
Build 2nd prototype for testing in LHC
- recent planning has always assumed a 2nd test in LHC
Given uncertainties: Build for 2010 SPS test and wait and see

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 27 / 35
Roman Pots & Flanges with Detector Housings with thin widows produced
by LARP/SLAC for UA9

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 28 / 35
Stepper Motor
400step/tour = 0.9o resolutionResolver with reduction gear
Slide Ball Screw(2mm lead)
Sliding Guidesfull metal
LVDT position sensors
Coulisse
switches
Movement resolution 2 mm/400 steps = 5 m (/16)
Stepper Motor
400step/tour = 0.9o resolutionResolver with reduction gear
Slide Ball Screw(2mm lead)
Sliding Guidesfull metal
LVDT position sensors
Coulisse
switches
Movement resolution 2 mm/400 steps = 5 m (/16)
Support Structure and Linear Screws Still to be Delivered to UA9 by
LARP/SLAC

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 29 / 35
Long Term PlanningGeneral Comments
• At CM12 a first cut of program and budget requests was submitted by each task
• One round of discussions with lab POCs and task leaders has occurred to better pin down– Lab-to-lab split– LARP-to-Off-project labor split– Individuals by name & status (staff, PD, GS) and their FTEs
• identify unitarity problems
• At this point, usual spreadsheet approach in $ assuming– One very coarse overhead loaded salary ($250k) used to convert
LARP funded FTEs to dollars– M&S and travel requests assumed to include lab overhead
• FY09 numbers have been constructed to reflect the actual budget (before contingency allocation)

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 30 / 35
FY09-FY14 Plan
LARP LABOR RATE $250k
FY MilestoneLARP Labor (FTE)
non-LARP Labor (FTE)
LARP M&S (k$)
LARP Travel (k$)
LARP Cost (k$)
LUMI Monitor 2.5 0 $200k $275k $1,100kSchottky 0 0 $0k $60k $60kTune & Chromaticity Feedback 0 0 $0k $50k $50kAC Dipole 0.2 0 $0k $90k $140kLLRF 3 5 $0k $220k $970kSLM Development and Studies 1 0.5 $0k $50k $300kH- Development for Linac4 2.25 0 $75k $90k $728kRotatable Collimator Task 7 0 $400k $130k $2,280kT-980 Crystal Collimation at Tevatron 2.7 5.5 $361k $105k $1,141kUA9 Crystal Collimation at SPS 0 1.5 $20k $225k $245kElectron Lens as Collimation Scraper 0 0 $75k $0k $75kE-lens for Beam-Beam Compensation 8.3 0 $20k $50k $2,145kSPS E-Cloud Study 10.2 10.625 $775k $300k $3,625kPS2 10.7 13.3 $230k $565k $3,470kCrab Cavities 5.8 0 $0k $250k $1,700kDiscretionary 0 0 $100k $0k $100kTotal Accelerator Systems 53.65 36.425 $2,256k $2,460k $18,129k

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 31 / 35
Accelerator Systems
5 Year Spending Profile
$0k
$500k
$1,000k
$1,500k
$2,000k
$2,500k
$3,000k
$3,500k
$4,000k
$4,500k
$5,000k
FY09 FY10 FY11 FY12 FY13 FY14
Electron Lens as Collimation Scraper
Discretionary
Crab Cavities
PS2
SPS E-Cloud Study
E-lens for Beam-Beam Compensation
UA9 Crystal Collimation at SPS
T-980 Crystal Collimation at Tevatron
Rotatable Collimator Task
H- Development for Linac4
SLM Development and Studies
LLRF
AC Dipole
Tune & Chromaticity Feedback
Schottky
LUMI Monitor
Not too bad for 1st try!

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 32 / 35
PS2 Plan w/ time, manpower, subtasks

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 33 / 35
PS2 Outyears

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 34 / 35
PS2 Program Milestones by subtask & year

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 35 / 35
PS2
FY MilestoneLARP Labor (FTE)
non-LARP Labor (FTE)
LARP M&S (k$)
LARP Travel (k$)
LARP Cost (k$)
PS2 10.7 13.3 $230k $565k $3,470kFY09 Prep for Design Report 2.6 $100k $100kFY10 Prep for Design Report 2.9 2.9 $115k $110k $950kFY11 Design Report Delivered 2.8 2.8 $115k $135k $950kFY12 Further Development Possible but not costed 1.75 1.75 $80k $518kFY13 Further Development Possible but not costed 1.75 1.75 $80k $518kFY14 Further Development Possible but not costed 1.5 1.5 $60k $435k
5 Year Spending Profile
$0k
$100k
$200k
$300k
$400k
$500k
$600k
$700k
$800k
$900k
$1,000k
1 2 3 4 5 6
PS2

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 36 / 35
Rama’s Input to this Excercise

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 37 / 35
CRAB
FY MilestoneLARP Labor (FTE)
non-LARP Labor (FTE)
LARP M&S (k$)
LARP Travel (k$)
LARP Cost (k$)
Crab Cavities 5.8 0 $0k $250k $1,700k
FY09Downselect of cavity design & CERN commitment to provide test location and infrastructure (Sept. 09)
0.8 $100k $300k
FY10 TDR in Fall 2010 2.5 $75k $700kFY11 Support for Cavity & Cryostat Construction 2.5 $75k $700k
FY12Continued Support for Cavity & Cryostat Construction
$0k
FY13Continued Support for Cavity & Cryostat Construction; Cavity Installation & Commissioning
$0k
FY14 Participation in & analysis of beam test $0k
5 Year Spending Profile
$0k
$100k
$200k
$300k
$400k
$500k
$600k
$700k
$800k
1 2 3 4 5 6
Crab Cavities

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 38 / 35
Rotatable Collimator
FY MilestoneLARP Labor (FTE)
non-LARP Labor (FTE)
LARP M&S (k$)
LARP Travel (k$)
LARP Cost (k$)
Rotatable Collimator Task 7 0 $400k $130k $2,280kFY09 Deliver TT60 RC Prototype to CERN 3 $200k $0k $950k
FY10Deliver LHC RC Prototype to CERN; SPS beam test of LHC Prototype BPM system
2 $100k $30k $630k
FY11 Test TT60 RC in TT60 1 $50k $50k $350k
FY12LHC Beam Test of LHC Prototype RC; Technology Choice of Phase II Collimators
1 $50k $50k $350k
FY13 Build RCs as part of APUL 0 $0kFY14 Build/Install RCs as part of APUL 0 $0k
5 Year Spending Profile
$0k
$100k
$200k
$300k
$400k
$500k
$600k
$700k
$800k
$900k
$1,000k
1 2 3 4 5 6
Rotatable Collimator Task
Plan based on schedule shown by Assmann at
April 2009 Collimation
Review

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 39 / 35
Luminosity Monitor
FY MilestoneLARP Labor (FTE)
non-LARP Labor (FTE)
LARP M&S (k$)
LARP Travel (k$)
LARP Cost (k$)
LUMI Monitor 2.5 0 $200k $275k $1,100k
FY09Finish electronics & Installation, finish DAQ (Phase 2) software
2 $200k $100k $800k
FY10 Significant Commissioning 0.5 $75k $200kFY11 Commissioning $25k $25kFY12 Commissioning $25k $25kFY13 Commissioning $25k $25kFY14 Commissioning $25k $25k
5 Year Spending Profile
$0k
$100k
$200k
$300k
$400k
$500k
$600k
$700k
$800k
$900k
FY09 FY10 FY11 FY12 FY13 FY14
LUMI Monitor

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 40 / 35
SPS Ecloud Feedback
FY MilestoneLARP Labor (FTE)
non-LARP Labor (FTE)
LARP M&S (k$)
LARP Travel (k$)
LARP Cost (k$)
SPS E-Cloud Study 10.2 10.625 $775k $300k $3,625k
FY09Beam tests June 2009 and model analysis leading to design study;
0.2 1.125 $25k $80k $155k
FY10
Continue SPS measurements; develop MATLAB model of Feedback; build back-end drive system to facilitate SPS measurements; decision on whether to proceed with a FB HW project
2 1.5 $75k $50k $625k
FY11Prototype technology development of FB HW system: measurement equipment; power amps, HF signal processing HW
2 2 $125k $50k $675k
FY12Prototype technology development of FB HW system
2 2 $175k $40k $715k
FY13Prototype technology development of FB HW system
2 2 $175k $40k $715k
FY14Prototype evaluated on SPS, detailed system design proposal (TDR) for installed
2 2 $200k $40k $740k
Scrubbing exercise reveals 2 FTE/year are presumed to be students (Good!), unitarity mildly violated (especially when discussed with lab POC & other work
planned) and 25% “padded”. Good discussion of how much off project help each lab could contribute by name. Out year program a wish-list (not necessarily bad).

LARP DOE Review - 13 July 2009 Acc.Systems Status - T. MarkiewiczSlide n° 41 / 35
FY10 Challenges in Accelerator Systems
• Commission Luminosity Monitor and scale back task• Deliver RC Prototype to SPS and scale back task• Launch Crab Cavity with correct level of effort ($),
matching CERN interests & schedule• Launch PS2 program• Measure & understand SPS Ecloud & to begin to model a
RF correction• Keep T980 and UA9 crystal efforts LHC application
focused.• Use LARP provided LLRF models to beam commission
LHC• Successfully beam commission all HW to which LARP
contributed• Decide if & how to begin E-Lens scraper task• Keep LHC beam-beam study personnel intellectually
involved while RHIC constructs E-lenses