LARP Collaboration Meeting TQS01 - Progress. Shlomo Caspi Lawrence Berkeley National Laboratory April 26-28, 2006. Outline. TQS01 - Construction Design and Analysis Preliminary test results. Statement of work – TQS01. One of the main objectives: - PowerPoint PPT PresentationTRANSCRIPT
LARP Collaboration Meeting TQS01 - Progress
Shlomo Caspi
Lawrence Berkeley National Laboratory
April 26-28, 2006
S. Caspi04/19/23
Outline
• TQS01 - Construction
• Design and Analysis
• Preliminary test results
S. Caspi04/19/23
Statement of work – TQS01
One of the main objectives:
• Compare the magnet performance with the Compare the magnet performance with the design parametersdesign parameters.
S. Caspi04/19/23
TQS01 Main Features
• A 2 layers Nb3Sn Quadrupole
• A 10mm wide 27 strand cable. (0.7mm MJR strand)
• Short sample 4.2K (B,G,I) : 11.2T, 220T/m, 12.3kA
• Accumulated Lorentz stress : S_theta=-123MPa
• Accumulated axial force (4 quadrants) : F_z=350kN
S. Caspi04/19/23
2 layers
FillerKeys
4 pads
Bladder
Yoke
Aluminum shell
TQS01
•No collarsNo collars•BladdersBladders for coil azimuthal pre-stress for coil azimuthal pre-stress
B ~ 12 T, stress: 150 MPa, total axial force = 350 kN
The structure and assembly is different from any previous magnet of this kind
S. Caspi04/19/23
TQS01 – Construction
• Coil winding• Coil reaction• Instrumentation• Impregnation• Coil sub-assembly• Structure sub-assembly• Final assembly and pre-stress
S. Caspi04/19/23
Coil winding at FNAL
• A double layer
• Bronze island and end spacers
• Layer 1 wound on a mandrel and cured using a binder.
• Layer 2 wound on top of layer 1 and then cured.
S. Caspi04/19/23
Coils Shipped to LBNL
S. Caspi04/19/23
Prepare for Reaction
Two coils reacted together
S. Caspi04/19/23
Into Reaction Oven
S. Caspi04/19/23
Reaction Cycle (Coils 7 and 8)
•72 hr at 210 C
•48 hr at 400 C
•48 hr at 640 C
S. Caspi04/19/23
Post-Reaction
S. Caspi04/19/23
Coil - Instrumentation
Voltage tap
Strain gauge
Inner layer trace
Strain gauges and voltage tap attached to trace
S. Caspi04/19/23
Ready for Impregnation
S. Caspi04/19/23
Impregnation
Coil placed into impregnation
chamber
Controller
S. Caspi04/19/23
Impregnated Coils
Strain gauges placed on layer 1 island
Voltage traces
S. Caspi04/19/23
Coil-pack sub-assembly
Coil-pack is a sub-assembly of coils pads and fillers
Coil Pack is assembled, squared and bolted.
S. Caspi04/19/23
Structure sub-assembly, shell, yoke and intermediate gap keys
• 20” OD x 18” ID x 40”long, 6061-T6 aluminum shell, precision machined.
• 1018 steel yoke laminations, 2”-thick
S. Caspi04/19/23
SHELL & YOKE SUB-ASSEMBLY,cont’d
S. Caspi04/19/23
Final assembly
• Mating the coil pack with the shell & yoke sub-assembly.
S. Caspi04/19/23
End Support
bullets
End plate (89 mm thick)
Axial Aluminum rods (44 mm dia.)
Strain gauges
S. Caspi04/19/23
End plates assembly
S. Caspi04/19/23
Axial load components
S. Caspi04/19/23
Axial Pre-stress
S. Caspi04/19/23
Axial Pre-stress, cont’d
• 25 -Ton hydraulic actuator (9500 psi)
• Axial Loading Rig
S. Caspi04/19/23
Azimuthal pre-stress (bladder operation)
S. Caspi04/19/23
Complete assembly – return end
S. Caspi04/19/23
End splices
S. Caspi04/19/23
End splices (pizza box)
S. Caspi04/19/23
TQS01 lowered into cryostate
S. Caspi04/19/23
Outline
• TQS01 – Construction
• TQS01 – Design and AnalysisTQS01 – Design and Analysis
• TQS01 – Peliminary results (cool-down)
S. Caspi04/19/23
Integrated analysis and simulations
CAD (engineering)
FEM (magnetic)
FEM structure multi-physics
S. Caspi04/19/23
3D mechanical analysis: Lorentz forces
• ANSYS• x, y, and z coordinates of
each coil element center
• OPERA• Computation of J x B
(N/mm3) at each x, y, and z coordinate
• ANSYS• Computation of J x B Vel
(N)• Final force applied to each
coil node
S. Caspi04/19/23
TOSCA
Layer 1 |B|=12.15T in SS
Layer 2 |B|=12.0T END
I=13.5kA,1.9K
Maximum field:
Layer 1 - straight section
Layer 2 - end
S. Caspi04/19/23
Structural Analysis - ANSYS
Steps:
Assembly.Assembly.
Cool-down.Cool-down.
Lorentz forces 10-15 kALorentz forces 10-15 kA
Load Cases:• Combinations of azimuthal and axial pre-stress• Model with and without friction or glued• Blocked turns and individual turns
S. Caspi04/19/23
ANSYS model – straight section
Rule 1 - No azimuthalRule 1 - No azimuthal separation at the poleseparation at the pole
1
2
3
S. Caspi04/19/23
ANSYS model – coil ends
Island End-shoeSpacer
Rule 2 - No axial separation in the endRule 2 - No axial separation in the end
S. Caspi04/19/23
Structure – Shell - azimuthal
Shell and yoke mu=0.6, all other
surfaces with friction, mu=0.2
SS 4.2K SS 1.8K
Low assembly pre-stress
S. Caspi04/19/23
Structure – Axial rods
Low assembly pre-stress
S. Caspi04/19/23
Azimuthal stress in layer 1 (with friction)
± range
Short sample 4.2K
Short sample 1.9K
4.2 K
14kA
S. Caspi04/19/23
Training Mechanism
Straight sectionStraight section
• Axial tensile strain in the pole island held by friction releases when the coil pulls away due to insufficient azimuthal pre-stress.
End sectionEnd section
• Sliding and tarring between the coil and the island due to insufficient axial pre-stress.
S. Caspi04/19/23
Island axial strain- straight section
abrupt or slow
release of strain
S. Caspi04/19/23
release of axial strain
S. Caspi04/19/23
Ends and axial Lorentz Force
Lorentz axial force 351/413 (kN)
Applied axial force 800 (kN)
(with friction)
S. Caspi04/19/23
0 friction, limited axial load
S. Caspi04/19/23
Island axial displacements- end section
170 µmIsland
displacement
(with friction)
S. Caspi04/19/23
Outline
• TQS01 – Construction
• TQS01 – Design and Analysis
• TQS01 – Preliminary test resultsTQS01 – Preliminary test results
S. Caspi04/19/23
Strain Measurements
S. Caspi04/19/23
Cool-down
S. Caspi04/19/23
Rods – measured cool-down stress
4.3K4.3K
200K200K
S. Caspi04/19/23
Shell – measured cool-down stress
E
1 2 z
S. Caspi04/19/23
Shell – measured cool-down stress
4.3K4.3K
200K200K
E
1 2 z
S. Caspi04/19/23
Island – measured cool-down stress
•Axial tensile stress
•Compressive azimuthal stress
E
1 2 z
4.3K4.3K
S. Caspi04/19/23
Ratcheting During Cool-Down
S. Caspi04/19/23
Shell ratcheting during cool-down
S. Caspi04/19/23
Coil ratcheting during cool-down
ratcheting in theta
S. Caspi04/19/23
Coil ratcheting during cool-down
Minimum /no ratcheting in Z
S. Caspi04/19/23
Excitation
S. Caspi04/19/23
TQS01 4.45k Training
S. Caspi04/19/23
Layer 1 center island
Lay1-Lay2 ramp
S. Caspi04/19/23
Coil Center Details
SG-Z SG-Theta
Start of L1-L2 rampIsland discontinuity
S. Caspi04/19/23
Coil End Details
SG-Z
S. Caspi04/19/23
Island azimuthal strain during excitation
S. Caspi04/19/23
Island strain in θ, magnet center
S. Caspi04/19/23
Island strain in Z, magnet center
S. Caspi04/19/23
Island axial strain (center)
S. Caspi04/19/23
Island Stress
S. Caspi04/19/23
Island Stress over many quenches
S. Caspi04/19/23
Island strain in Z, lead end
S. Caspi04/19/23
Island axial strain (end)
S. Caspi04/19/23
Island axial strain (end)
S. Caspi04/19/23
StructureShell in θ, z
S. Caspi04/19/23
Shell azimuthal strain
S. Caspi04/19/23
Shell axial strain
S. Caspi04/19/23
Shell stress
S. Caspi04/19/23
Shell stress
S. Caspi04/19/23
StructureRods in z
S. Caspi04/19/23
Rods Stress
S. Caspi04/19/23
Rods Stress
S. Caspi04/19/23
Summary
• The most “engineered” magnet we ever built.
• Analyzed every component from assembly through cool-down and excitation and pushed Nb3Sn technological to new limits.
The design expectations are:
• Reach short sample prediction (field, current, stress)
• Get there with minimum training
S. Caspi04/19/23
Summary …
• First quench – Q1 at 80% of ss (176 T/m)
• Plateau – Q12 at 86% (190 T/m)
• Thermal cycle on TQS01
• Data reduction and analysis:• Strain gauge measurements• Quench locations• Refine ANSYS analysis
• If evidence suggests a problem in coil 6 ramp area:• Replace coil 6 with spare and retest• Section ramp area