LARP Phase II Secondary Rotatable Collimator. 5 minute status report April 26th, 2010. SPS Tank and BPM housings. Resting on Base Plate. RF Foils. BeCu and Glidcop 0.25 and 0.2mm thick. Rotator mounted to Jaw. Rotator/actuator set-up for prototype tests. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: LARP Phase II Secondary Rotatable Collimator](https://reader036.vdocuments.net/reader036/viewer/2022081513/56814cb6550346895db9c1b4/html5/thumbnails/1.jpg)
LHC Rotatable Phase II CollimatorsLHC Collimation Working Group - 7 December 2009 1
LARP Phase II Secondary Rotatable Collimator
5 minute status report
April 26th, 2010
![Page 2: LARP Phase II Secondary Rotatable Collimator](https://reader036.vdocuments.net/reader036/viewer/2022081513/56814cb6550346895db9c1b4/html5/thumbnails/2.jpg)
LHC Rotatable Phase II CollimatorsLHC Collimation Working Group - 7 December 2009
SPS Tank and BPM housings
2
![Page 3: LARP Phase II Secondary Rotatable Collimator](https://reader036.vdocuments.net/reader036/viewer/2022081513/56814cb6550346895db9c1b4/html5/thumbnails/3.jpg)
LHC Rotatable Phase II CollimatorsLHC Collimation Working Group - 7 December 2009
Resting on Base Plate
3
![Page 4: LARP Phase II Secondary Rotatable Collimator](https://reader036.vdocuments.net/reader036/viewer/2022081513/56814cb6550346895db9c1b4/html5/thumbnails/4.jpg)
LHC Rotatable Phase II CollimatorsLHC Collimation Working Group - 7 December 2009
RF Foils
•BeCu and
Glidcop
0.25 and 0.2mm
thick
4
![Page 5: LARP Phase II Secondary Rotatable Collimator](https://reader036.vdocuments.net/reader036/viewer/2022081513/56814cb6550346895db9c1b4/html5/thumbnails/5.jpg)
LHC Rotatable Phase II CollimatorsLHC Collimation Working Group - 7 December 2009
Rotator mounted to Jaw
5
![Page 6: LARP Phase II Secondary Rotatable Collimator](https://reader036.vdocuments.net/reader036/viewer/2022081513/56814cb6550346895db9c1b4/html5/thumbnails/6.jpg)
LHC Rotatable Phase II CollimatorsLHC Collimation Working Group - 7 December 2009
Rotator/actuator set-up for prototype tests
6
http://www-project.slac.stanford.edu/ilc/larp/rc/Photos/2010-04-22_rotation_mechanism_test/DSCN2398.MOV
http://www-project.slac.stanford.edu/ilc/larp/rc/Photos/2010-04-22_rotation_mechanism_test/DSCN2400.MOV
![Page 7: LARP Phase II Secondary Rotatable Collimator](https://reader036.vdocuments.net/reader036/viewer/2022081513/56814cb6550346895db9c1b4/html5/thumbnails/7.jpg)
LHC Rotatable Phase II CollimatorsLHC Collimation Working Group - 7 December 2009
Next :Rotator qualification
•Align Rotator worm with respect to Jaw facet and pin worm to axle
•Grip inlet cooling tube and twist to test Rotator “stiffness” and facet backlash
•Grip outlet cooling tube and twist together with the inlet tube to simulate total backlash load
•Grip inlet cooling tube and actuate Motor drive to rotate Jaw against half the torque load
•Add outlet tube and repeat for total load required on Ratchet Actuator and Rotator
7
![Page 8: LARP Phase II Secondary Rotatable Collimator](https://reader036.vdocuments.net/reader036/viewer/2022081513/56814cb6550346895db9c1b4/html5/thumbnails/8.jpg)
LHC Rotatable Phase II CollimatorsLHC Collimation Working Group - 7 December 2009
Coming up:
•Mount RF Foils to RF bearings and determine which material and thickness is most suitable
•Weld Flanges on to BPM Housings
•Mount both Jaws, Tank and BPMs for Stretched Wire tests
8