laura manenti university college london · 2017. 9. 25. · laura manenti university college london...

15
3x1x1 results obtained so far Laura Manenti University College London 1

Upload: others

Post on 25-Jan-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • 3x1x1 results obtained so farLaura Manenti University College London

    1

  • Gained experience for ProtoDUNE-DP design, installation, and operation.

    For first time extraction efficiency over 3 m2 area and LEM amplification over 50x50 cm demonstrated (gain of 5 at 28 kV/cm)

    Purity in the ms electron lifetime range

    Excellent performance of the LAr pump for recirculation and the cryogenic system

    Stable operation at 500 V/cm (HVFT at -56 kV)

    Good S/N ratio for both collection views even without software noise removal

    Infrastructure for data transfer set up and tested with 140 k events recorded and being analysed so far

    Results achieved

    Goal/purpose:DP TPC technology works at large scale

    311 detector served as test bench for protoDUNE-DP

    2

  • 3

    Roadmap of the 3x1x1July 2017

    2015

    Sebastien Murphy ETHZ TPC Symposium 2016 Paris December 5-717

    Themembranecryostat

    Insulation:• 1 meter made from blocks of 30 cm thick

    Polyurethane+plywood.• 45 temperature sensors to measure temperature

    gradient.Membrane:• corrugated steel panels welded together.• Tightness of welds tested to 1e-9 mbar l/s.

    FirstmembranecryostatbuiltatCERN

    MembranecryostatusedforLNGtransportationLicensedbyGTT/France

    2015 - Cryostat constructed

    2016 - Detector installation completed

    Jan 2017 - Commission started

    Mar 2017 - Operation ‘frozen’ due to cryostat issues

    Jun 12th 2017 - Recirculation started

    Jun 21st 2017 - First track seen!

  • Recirculation of LAr with cryo pump

    Detector slow control system

    Online processing and storage

    LAr level measurement

    CRP mechanical frame and suspension system

    High voltage system

    FE electronics

    Performance of the muon trigger system

    PMTs

    LEM anode and extraction grid

    Results achieved

    4

  • 5

    LAr recirculation

    Goal is to achieve a purity at the ppt level

    Jun 12th: LAr recirculation startedJun 15th: a total of 7 volumes had been recirculatedPump and cartridges have been running continuously for 2 monthsWe would like to thank CERN cryogenic team for their daily support

  • 6

    Slow control system Online display to constantly monitor the different pressure and temperature sensors inside the detector and in side insulation space. A dedicated ELOG for the 3x1x1 with more than 400 entriesA Slack account for the collaboration was created with different channels to report the daily activities.

  • 7

    SW activities: online processing and storage

    We already have more than 140k events!Summary of all the runs recorded with the main details and number of events.Online storage and processing for protoDUNE-DP ➡Being tested on the 3x1x1. Files transferred to a local EOS and then moved to the CERN computing centre.All the necessary codes for 3x1x1 operation including online monitoring processes are functioning well and has been tested.

  • 8

    LAr level measurement

    • The level is adjusted and constantly monitored using 7 capacitive level meters on the CRP, and 5 along the drift cage. Since mid June, this information is also sent to the cryogenic system to constantly regulate the system to keep the level stable.

    • 4 cryogenic cameras are recording pictures continuously.

    DC level meters

    Evolution over one month

    Not real drops, we lost slow control information

    CRP level meters

  • 9

    Very high voltage system

    Mar

    Total resistance of the field cage:

    C. Cantini et al., “First test of a high voltage feedthrough for liquid Argon TPCs connected to a 300 kV power Supply”, JINST 12 P03021 arXiv:1611.02085

    • Very high voltage tests performed in May at different LAr levels.

    • Cathode and field cage powered up to 50 kV in stable conditions with the field cage terminated to ground.

  • 10

    Trigger1)Two Cosmic Ray Tagger (CRTS) panels installed in the short sides of the cryostat.

    • Each panel made in scintillation bars in x-y to provide 2D coordinates

    • Trigger rate of 0.3 Hz

  • 11

    Trigger

    2)Photomultipliers: Since beginning of July, the charge can receive also a trigger produced by the PMTs

    • Threshold trigger on the scintillation light received by the 5 PMTs.

    • Trigger rate 3 Hz.

    From this trigger, we can also perform additional measurements:• The rate of e—ion recombination depends on the drift field.

    • To understand if the drift field had an impact on the trigger rate, we evaluate the trigger rate as a function of the drift field up to 60 kV

    see Alberto’s talk

  • 12

    accessible cold amplifiers at 150 K.Sealed in chimney separate from main argon volume

    uTCA crate

    cold ASICs

    ASICs insertion via 2 m blade

    Test pulse at warm and at cold: 17 (1.3%) dead or problematic channels.Low noise condition at cold: 1.66 adc counts (1600 e-) RMS noise

    Chan

    nel

    050

    100

    150

    200

    250

    300

    Pedestal RMS [ADC] 123

    1000

    2000

    Pedestal RMS [# e-]

    Channel650 700 750 800 850 900 950Pe

    desta

    l RM

    S [A

    DC]

    1

    2

    3

    1000

    2000

    Pedestal RMS [# e-]

    Channel350 400 450 500 550 600Pe

    desta

    l RM

    S [A

    DC

    ]

    1

    2

    3

    1000

    2000

    Pedestal RM

    S [# e-]

    Channel0 50 100 150 200 250 300Pe

    desta

    l RM

    S [A

    DC]

    1

    2

    3

    1000

    2000

    Pedestal RMS [# e-]

    (20adc=3fC)

    Noise and dead channels in warm and cold

  • Induction field

    LEM field

    Extraction field

    13

    HV system configuration

    Ext grid

    All measurements in mm

    20

    55

    FFS

    LEMup

    LEMdown

    Anode

    21

    cathode

    980

    -56 kV

    -7.6 kV

    -6.5 kV-4.0 kV-1.0 kV

    0 kV

    shieldingPMTs

    Nominal values

    Drift field 500 V/cm

    > 2 kV/cm

    30 kV/cm

    5 kV/cm 1-1.5 kV/cm

    28-29 kV/cm

    1-2.3 kV/cm

    500-700 V/cm

    Values reached

    8

  • 76 4 DLAR DETECTOR COMPONENTS

    LEM field [kV/cm]24 26 28 30 32 34 36

    effe

    ctiv

    e ga

    in

    0

    20

    40

    60

    80

    100

    reso

    lutio

    n

    0

    0.1

    0.2

    0.3

    0.4

    0.5

    resolution view 0

    resolution view 1

    effective gain

    Extraction field [kV/cm]0 0.5 1 1.5 2 2.5 3 3.5 4

    effe

    ctiv

    e ga

    in

    0

    10

    20

    30

    40

    reso

    lutio

    n

    0

    0.1

    0.2

    0.3

    0.4

    0.5

    resolution view 0

    resolution view 1

    effective gain

    Induction field [kV/cm]0 1 2 3 4 5 6 7 8

    effe

    ctiv

    e ga

    in

    0

    10

    20

    30

    40

    reso

    lutio

    n0

    0.1

    0.2

    0.3

    0.4

    0.5

    resolution view 0

    resolution view 1

    effective gain

    FIG. 51: E↵ective gain and resolution of the charge deposition measurements on both view as a function of theLEM electric field.

    event acquired with a gain of 15. Further studies will be performed to check wether the chamber can

    be continuously operated at larger LEM fields and if higher gains in stable conditions can be reached.

    FIG. 52: Event display of a cosmic track with a gain of ∼ 15 obtained in the 3 liter chamber. (top): the rawwaveform showing the amplitude of the signals on both views. (bottom): drift time versus channel number ofthe reconstructed hits.

    Based on those studies in Table IV we summarise the typical high voltages applied across each stage

    of the detector equipped with the new anode and operated in the single grid configuration. An electric

    1

    10

    100

    1000

    100 1000

    (s)

    electric field (V/cm)

    A exp(B E1/2) / E

    A = 1.20x105 s V/cm

    B = -0.062 (cm/V)1/2

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    0 0.5 1 1.5 2 2.5 3 3.5 4

    extra

    ctio

    n ef

    ficie

    ncy

    electric field (kV/cm)

    fastfast + slow

    Induction Field [kV/cm]0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

    Colle

    ctio

    n Ef

    ficie

    ncy

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    1

    linear dependanceinterpolation assuming

    14

    HV system configuration

    In green the field values scanned so far.In orange the field values at most stable conditions.

    hdQds iview = Fshare ⇥Gain⇥ E↵extr ⇥ E↵ind ⇥dQds

    hdQds iview ⇠ 0.5⇥ 5⇥ 0.9⇥ 0.5⇥ 10 fC/cm = 11.5 fC/cm

    Gushchin et al, Sov. Phys. JETP 55 (1982) 860-862

    see Laura Z.’s talk

    LBNO TDR, CERN-SPSC-2014-013, 1409.4405

  • 15