Long-Baseline Neutrino FacilityLBNF
LBNF: Status and Plans
Elaine McCluskey, LBNF Project Manager
DUNE Collaboration Meeting
15 August 2017
LBNF
Topics
08.15.17 E McCluskey| LBNF Update2
• Updates:
- Milestones
- Far Site progress
- Beamline progress
- Miscellaneous
• Summary
LBNF
Near-term status of LBNC Milestones
08.15.17 E McCluskey| LBNF Update3
• Updates since May 2017 DUNE collaboration meeting:
- CM/GC contract award 9 August 2017
- Ross Shaft: work crew shift schedule changed in early August to allow
work to reduce workers safety concerns, will complete slightly later
without impact to future activities
- Main excavation final design delayed due to final contractual details
USFY Quarter Milestone 2016 Q4 2017 Q1 2017 Q2 2017 Q3 2017 Q4 2018 Q1 2018 Q2
LBNF milestones
2016 Q4 CD-3a approved 9/1/16 A
Q4 Pre-excavation final design complete 12/21/16 A
2017 Q2 CMGC contract in place 8/9/2017 A
Q4 Ross shaft refurbishment complete delayed
2018 Q2 Main excavation final design complete
LBNF
Far Site - Phases of Work and Status
4
1. Sanford Lab Reliability
Projects
FY16 – 19
• Ross shaft rehab
• Hoist motor
rebuilds, more…
2. Pre-Exec Const
FY18 - 19
• Rock disposal
systems
• Ross headframe
upgrade, more…
3. Exec & Surface
Construction
FY19 – 22
• Brow/CUC/Drifts/Utilities/Surf bldg/Chambers
4. Cryostats/Cryogenic Systems FY21 – 25
08.15.17 E McCluskey| LBNF Update
LBNF
Groundbreaking on 21 July 2017
08.15.17 E McCluskey| LBNF Update5
At SURF underground
At Fermilab
You Tube video available here
LBNF
Reliability Project – Ross Shaft Renovation
Work has progressed to 4,772 level (95% complete)
08.15.17 E McCluskey| LBNF Update6
• Ross Shaft constructed in
1930s. Legacy shaft
infrastructure cannot support
the structural loads and duty
cycle needed for LBNF, thus
rehabilitation was initiated in
2012 to modernize the shaft.
• Work is very close to the
bottom of the shaft – gets
more complicated as it
approaches bottom opening
and below the 4850L
• Extending completion due to
change in crew schedules
LBNF
Other Reliability Projects near-term
08.15.17 E McCluskey| LBNF Update7
• Ground Support – East/West Access
- Ground support deteriorated due to age and
flooding of the mine after shutdown.
- West and East Lab Access drifts will be
completely bolted to provide safe passage for
utilities and logistics.
• Oro Hondo Fan replacement
- Main exhaust fan – variable frequency drive
obsolete and starting to be problematic
- If fails, shuts down diesel equipment
underground
• Hoist Clutches & Brakes and Variable
Speed Drives
- Replace 1930’s technology that doesn’t meet
code and risks shaft operation and potentially
personnel safety
- Improve energy efficiency
Status:
• Underway
• Complete Dec 17
Status:
• Working to
accelerate
replacement plan to
ASAP
Status:
• In planning
• Start Jan 18
• Phased thru Feb 19
LBNF
FSCF Pre-excavation Construction Status
08.15.17 E McCluskey| LBNF Update8
• Construction to start by CM/GC in early 2018 (pending DOE appropriation)
- Underground rock handling (ore passes, skip loading, temporary grizzly, rock spill collection system)
- Rock crushing system
- Installing surface pipe conveyor to open cut
- Ross headframe reinforcement
- Shaft utilities: fiber optic and power cables, water and gas piping
- Electrical service on the surface to the shaft
• Surface rock conveyor ordered June 2017 -should be ready for installation late summer 2018
PROFILE OF ROCK CONVEYOR
LBNF
Final FSCF Design for Excavation & Building/Site
Infrastructure
08.15.17 E McCluskey| LBNF Update9
• Final design has two scope elements: main excavation (EXC),
and buildings/site infrastructure (BSI)
- Deliverables planned at 30%, 60%, 90%, and 100% of final design
• FD and cryo will participate in weekly design meetings with A/E
• Provides defined points for stakeholder review
• CM/GC provides independent cost/schedule estimates & constructability
reviews
- Design is under configuration control; all proposed changes are
evaluated for cost and schedule impact
LBNF
Cryogenic Systems Design Status
08.15.17 E McCluskey| LBNF Update10
• LN2 system: working on solicitation for design-fab-install
contract for this system
• Proximity Cryogenics on the mezzanine and LAr/GAr purification
system in Central Utility Cavern:
- Joint effort of Fermilab and CERN (Proxy cryo on mezzanine only).
- Developing work packages and understanding how to engage
possible partners.
LBNF
Proximity Cryogenics in the CUC – 3/3
07.17.17 David Montanari | Proximity Cryogenics in CUC3
LAr/GArPurification
ParticulateFilters
H2Generators
BoosterCompressors
LN2ColdBoxes
Regenblowers
PLCRacksinsitu
ParticulateFilters
H2Generators
LAr/GArPurification
LN2StorageDewars
Proxy CryoIn CUC
LBNF
• LBNF and DUNE have worked to better define penetrations needed for
FD and cryogenic systems
• Third evolution of CERN design for the steel structure design of cryostat
#1 accommodates single-phase detector penetrations
• CERN working to initiate design contract with membrane cryostat
designer, GTT, by early 2018
Cryostat Design Status
08.15.17 E McCluskey| LBNF Update11
• LBNF is holding
independent design
review of steel structure
next week at SURF
LBNF
Beamline/NSCF Status
08.15.17 E McCluskey| LBNF Update12
- Requires 4 (vs. 2) interaction length target and 3 (vs. 2) magnetic horns.
- Collaborating with RAL on the conceptual design of the optimized target
and its mounting in the first horn.
- LBNF is holding Beam Optimization Review to evaluate the conceptual
design, cost, and schedule on 5-6 October.
- EFIG will discuss incorporation of this design into the LBNF/DUNE plan
soon thereafter.
- Decision process described in DocDB 1900.
• Optimizing target and
focusing horns for better
sensitivity to CP
violation.
LBNF
Beamline/NSCF Status
08.15.17 E McCluskey| LBNF Update13
• Collaboration with IHEP/China:
- Testing prototype corrector magnet from IHEP at Fermilab
- Discussing additional collaboration on other beamline systems, e.g.
decay pipe beam window
• Collaboration with KEK – interested in supporting beamline,
discussions underway
LBNF is very interested in engaging with all partners who
might be interested in participating in design and
construction of the beam.
Please contact Elaine McCluskey and/or Vaia Papadimitriou.
LBNF
LBNF Project Reviews and Advisory Boards
08.15.17 E McCluskey| LBNF Update14
• DOE Reviews
• Independent progress reviews (IPR) required by DOE project management process
✓ February 2017 – IPR focused on entire Project (LBNF+DUNE-US)
• Next DOE IPR likely in Feb 2018
• Long-Baseline Neutrino Committee (LBNC) Reviews
- Weekly conferences with Chair, Laboratory, LBNF, and DUNE leadership.
- Multi-day reviews nominally three times/year. In 2017
✓ 23 – 26 March at Fermilab
✓ 22 – 26 June at CERN
• 26 – 29 October at SURF
• LBNF Strategic Project Advisory Committee (SPAC)
- Provides independent advice on issues and strategies related to project organization, management, and risks; engagement with international institutions, and project execution.
✓ February 2017 – focused on start of construction at Far Site
• Fall 2017 meeting is in planning
LBNF
LBNF Staffing Updates since May 2017 collaboration meeting
08.15.17 E McCluskey| LBNF Update15
• New people
- As the protoDUNEs are installed, Jack Fowler is transitioning to
become the LBNF/DUNE Systems Engineer
- Cryo-mechanical engineer hired in August
• Recruiting in progress
- Far Site Logistics Manager position – candidate interview
evaluations in progress
• Hiring planned for next 18 months
- Three field construction coordinators for LBNF construction work at
Sanford Lab
- Two additional procurement administrators for LBNF contracts
LBNF
Summary
08.15.17 E McCluskey| LBNF Update16
• Groundbreaking held at Far Site
• Far Site CM/GC contract awarded
• Beginning final design for CF
• Planning for construction activity to ramp up with pre-exavation
activities underway early 2018
• Continuing to add staff to ensure ability to execute
• Continuing outreach for nonDOE participation across LBNF
• Working funding profile closely with DOE to continue outyear
funding ramp up to continue timely construction progress
LBNF08.15.17 E McCluskey| LBNF Update17
Questions?
Animation Links:• LBNF/DUNE animation (YouTube)• Video page (FNAL website)
Social Media Links:• LBNF Facebook• DUNE Facebook• LBNF Twitter• DUNE Twitter
LBNF
LBNF Overview - “Near Site” – at Fermilab, Batavia, IL
• Primary proton beam @ 60-120GeV extracted from Main Injector
• Initial 1.2 MW beam power, upgradable to 2.4 MW
• Embankment allows target complex to be at grade and neutrino beam to be
aimed to Lead, South Dakota
• Decay region followed by absorber
• Four surface support buildings
• Facilities to support DUNE Near Detector
08.15.17 E McCluskey| LBNF Update19
Beamline design based on
Fermilab’s NuMI beam,
currently the most powerful
neutrino beam in the world
LBNF
LBNF Overview – “Far Site” – at Sanford Lab, Lead, SD
20
4850L caverns and drift layout
Single cryostat and portion of central utility cavern
LBNF facilities will support
DUNE experiment
08.15.17 E McCluskey| LBNF Update
• Conventional Facilities:
- Surface and shaft Infrastructure including utilities
- Drifts and two caverns for detectors
- Central utility cavern for conventional and cryogenic equipment
• Cryostats:
- Four membrane cryostats supportedby external steel frames
• Cryogenic Systems:
- LN2 refrigeration system for coolingand re-condensing gaseous Argon
- Systems for purification and recirculation of LAr
• Argon:
- 70kt LAr (~40kt “fiducial” mass)