lean manufacturing quiz i

18
LEAN MANUFACTURING QUIZ I 1. Value Stream Mapping looks at: a. The people, material, and information flow in a value stream  b. The material and information flows in a value stream c. The steps people take in designing and producing a product d. The detailed operation steps within cells 2. A product family matrix is used in value stream mapping to: a. Create a listing of all your products and the steps that are taken to produce them  b. Decide which products are most important to your customers c. Identify and group products into families based on whether they pass through similar steps in your downstream processes d. Divide the mapping teams up into groups with groups with individual mapping assignments 3. The recommended level for beginning to map a value stream for a product family is: a. Corporate wide  b. Door  to-door in an individual facility or plant c. Across multiple facilities d. At the process level, for example in a single work-cell 4. Calculate the Takt Time based on the following i nformation: Customer demand is 34,400 parts per month. The company works 5 days per week and on average 20 days per month. There are two, eight hour shifts. Lunch is 30 minutes per shift. Two, ten minute breaks are taken per shift. The calculated Takt Time is: a. 0.5 minutes per part or 30 seconds per part  b. 1 part per minute or 1 part every 60 sec c. 0.5 parts per minute

Upload: diep-nguyen

Post on 18-Oct-2015

253 views

Category:

Documents


0 download

TRANSCRIPT

  • 5/28/2018 Lean Manufacturing Quiz i

    1/18

    LEAN MANUFACTURING QUIZ I

    1. Value Stream Mapping looks at:

    a. The people, material, and information flow in a value stream

    b. The material and information flows in a value stream

    c. The steps people take in designing and producing a product

    d. The detailed operation steps within cells

    2. A product family matrix is used in value stream mapping to:

    a. Create a listing of all your products and the steps that are taken to produce them

    b. Decide which products are most important to your customers

    c. Identify and group products into families based on whether they pass through similar steps in your

    downstream processes

    d. Divide the mapping teams up into groups with groups with individual mapping assignments

    3. The recommended level for beginning to map a value stream for a product family is:

    a. Corporate wide

    b. Doorto-door in an individual facility or plant

    c. Across multiple facilities

    d. At the process level, for example in a single work-cell

    4. Calculate the Takt Time based on the following information: Customer demand is 34,400 parts per month.

    The company works 5 days per week and on average 20 days per month. There are two, eight hour shifts.Lunch is 30 minutes per shift. Two, ten minute breaks are taken per shift. The calculated Takt Time is:

    a. 0.5 minutes per part or 30 seconds per part

    b. 1 part per minute or 1 part every 60 sec

    c. 0.5 parts per minute

  • 5/28/2018 Lean Manufacturing Quiz i

    2/18

    d. 1 minute per part

    5. Data boxes on a value stream map should contain information based on:

    a. Engineering standards

    b. The average measurements over the last year

    c. The measurements on an ideal or typical day

    d. What you observe on the day you draw your map

    6. One of the biggest mistakes in implementing Lean Manufacturing is:

    a. Sub optimizing by conducting Kaizen events in areas without first taking a big picture view of the

    organization

    b. Not implementing improvements in line with organizational strategy

    c. Skipping the value stream mapping step

    d. All of the above

    7. A supermarket is used where:

    a. Processes are close together but have different cycle times

    b. A customer requires specialized products from the finished goods warehouse

    c. Continuous flow is not possible due to distance, unreliability, or where process serves multiple product

    families

    d. Pull can be implemented throughout the door-to-door value stream

    8. Creating value stream loops after future state mapping helps you to:

    a. Break your total value stream plan into manageable pieces and prioritize them

    b. Communicate your plan to senior management

  • 5/28/2018 Lean Manufacturing Quiz i

    3/18

    c. Assign kaizen teams to be responsible for each loop

    d. Develop measures for each loop based on improving lead times

    9. 5S (choose best answer below)

    a. Is about standardizing the way we do things

    b. Forms a foundation for all other improvement activities

    c. Is a key to reducing inventory to improve lead time?

    d. Cannot be used in an office or administrative area

    10. 5S efforts often fail to be sustained because:

    a. Everyone is involved

    b. Managers dont allow or make time for 5S activities and organizations fail to adequately implement the

    sustain step

    c. 5S isnt really value-added

    d. Managers implement 5S but employees dont do the work to keep it up

    11. A major barrier to inventory reduction and batch size reduction is:

    a. Long set-up changeover times

    b. 5S activities

    c. Lead time reduction

    d. Material handlers

    12. Set-up Time is typically classified in two categories as:

    a. Internal or external

  • 5/28/2018 Lean Manufacturing Quiz i

    4/18

    b. Value-added or non value added

    c. Motion and transport waste

    d. High cost and low cost

    13. Please circle the incorrect statement:

    a. Policy deployment is Management By Objectives (MBO)

    b. Policy deployment develops a one year plan reflecting the long-term vision and 3-5 year strategic planning

    objectives

    c. Policy deployment is a planning-implementation process that focuses on a few major long-term customer-

    focused breakthrough objectives

    d. Policy deployment ensures individuals are aligned and understands what improvements are important to

    work on

    14. Select the non-value added activity:

    a. Assembling two parts together

    b. Extrusion machine making parts

    c. Packing parts for shipment

    d. Picking up a part, putting it down and picking it up again

    15. Making something earlier or faster than required by the next process just-in-case is an example of

    which type of waste?

    a. Defect

    b. Motion

    c. Over production

    d. Over processing

  • 5/28/2018 Lean Manufacturing Quiz i

    5/18

    16. What is the goal of TPM?

    a. To fix equipment only when it breaks down

    b. To give an operator one more thing to do

    c. To utilize worker and machine effectiveness

    d. To reduce the involvement of other people

    17. Start pulling work through the system, look at the production scheduling and move towards daily orders

    with ________ cards.

    a. Kanban

    b. Manufacturing resource planning

    c. Material requirements planning

    d. Lean manufacturing

    18. The following are all examples of waste in business, except which one?

    a. Over production

    b. Unhappy suppliers

    c. Defective output

    d. Production waiting time

    19. A key feature of Kaizen is that improvements are achieved by making

    a. Close contact with consultants

    b. Many small change

    c. Less complicated products

    d. Large scale investment

  • 5/28/2018 Lean Manufacturing Quiz i

    6/18

    20. JIT aims to ensure that inputs into the production process only arrive

    a. When customers are ready to buy

    b. When they are needed by production

    c. When they are paid for

    d. When the supplier is ready

    LEAN MANUFACTURING QUIZ III

    1. Choose the statement that is not correct:

    a. LEAN and Six Sigma are both process improvement methodologies

    b. LEAN arose as a method to optimize auto manufacturing (Toyota)

    c. Six Sigma evolved as a quality initiative to reduce variance in Motorola

    d. Both methodologies are focused in how to optimize the process flow

    e. LEAN doesnt require the usage of advanced statistical tools

    2. What can be considered as Value for the Customer?

    a. Cost

    b. Delivery

    c. Reliability

    d. Response

    e. All of the above

    3. The 5 W to be considered during a Root Cause Analysis are:

    a. Who, What, When, Where and Why

    b. Who, Who, Who, Who and Who

  • 5/28/2018 Lean Manufacturing Quiz i

    7/18

    c. Why, Why, Why, Why, and Why

    d. Who, Why, Who, Why and When

    4. Lean is a system of to identify and eliminate wastes in production.

    a. Principles

    b. Methods

    c. Tools

    d. a, b & c

    5. Which is below increased through lean implementation?

    a. Inventory

    b. Cost

    c. Productivity

    6. One of lean principles is:

    a. Eliminate wastes

    b. Identify value

    c. Push system

    7. The purpose to identify and eliminate wastes in lean production is:

    a. Reduce production lead time

    b. Set up pull system

    c. Build kanban

    8. Wastes of motion is?

  • 5/28/2018 Lean Manufacturing Quiz i

    8/18

    a. Process that does not create value as customer standpoint

    b. Efforts of people that does not add value

    c. Parts movement

    9. Make more products than customer requires is waste of?

    a. Inventory

    b. Over production

    c. Defects

    10. Arrange the activities in right order (5S)

    a. Set in order, Sort, Shine

    b. Sort, Shine, Set in order

    c. Sort, Set in order, Shine

    11. A production system that all processes connected and follow customer demand is?

    a. Push system

    b. Pull system

    12. Customer demand is 100 products, and available working time is 15 hours, calculate the Takt Time?

    a. 540 sec

    b. 480 sec

    c. 620 sec

    13. In order to reduce cycle time, the first thing that a factory can consider is?

  • 5/28/2018 Lean Manufacturing Quiz i

    9/18

    a. Add more workers

    b. Reduce processing time

    c. Work 2 shifts

    14. Process A cycle time is 5sec, while process B is 7sec, calculate the WIP between A & B in 7.5 hours shift

    working?

    a. 2100

    b. 1543

    c. 0

    15. Process A cycle time is 5sec, while process B is 3sec, calculate the WIP between A & B in 7.5 hours shift

    working?

    a. 2100

    b. 3600

    c. 0

    16. Calculate the maximum output of this production line below?

    a. 1500

    b. 300

    c. 900

    17. Cycle time should be balanced with?

    a. Process time

    b. Takt Time

  • 5/28/2018 Lean Manufacturing Quiz i

    10/18

    c. Lead time

    18. For most unimproved processes, the amount of value-added work relative to incidental work and waste is

    approximately:

    a. 5%

    b. 20%

    c. 50%

    d. 80%

    19. Which of the following is considered value-added work?

    a. Changing the shape or character of a product or assembly.

    b. Eliminating all defects and the need for rework.

    c. Empowering employees to establish their own work standards.

    d. Activities that must be performed under present work conditions

    20. The greatest waste of all is the waste of:

    a. overproduction.

    b. mistakes.

    c. inventory.

    d. Overtime

    LEAN MANUFACTURING QUIZ II

    1. The main reason why a business will want to reduce waste is to

    a. Lower cost

    b. Reduce stock

    c. Improve customer service

  • 5/28/2018 Lean Manufacturing Quiz i

    11/18

    d. Increase capacity

    2. A benefit of using cell production is

    a. Products can be mass produced

    b. Quality is less important

    c. Less need for staff to trust each other

    d. Workers more likely to become multi skilled

    3. The lean production approach Kaizen is associated with the term

    a. Just in time

    b. Economies of scale

    c. Stock management

    d. Continuous improvement

    4. The concept of lean production originated in the

    a. Offices of New York

    b. Retail stores of Hong Kong

    c. Coal mines of Yorkshire

    d. Manufacturing plants of Japan

    5. Lean production is a management approach focused on

    a. Cutting out waste

    b. Adding value

    c. Improving motivation

  • 5/28/2018 Lean Manufacturing Quiz i

    12/18

    d. Increasing complexity

    6. What is the correct meaning of Takt Time?

    a. The fastest pace a process can run at without producing poor quality

    b. The demand or pace that customer places orders

    c. The speed of the slowest process in the line

    7. What is the meaning of Heijunka?

    a. Another word for Takt time

    b. Production smoothing to avoid large batches or swings in volume

    c. Fixed size batch production

    8. What is Poka Yoke?

    a. A Japanese phrase meaning error prevention

    b. A Japanese phrase meaning in line checking

    c. A Japanese phrase meaning line stop authority

    9. What is Jidoka?

    a. An optical sorting device

    b. 100% end of line inspection

    c. Automation with a 'human touch'

    10. In a lean work cell, the supervisors main responsibility is:

    a. Keeping production moving

  • 5/28/2018 Lean Manufacturing Quiz i

    13/18

    b. Keeping workers busy

    c. Achieving production counts

    d. Identifying and resolving abnormal conditions

    11. Pilot lean projects should be chosen based on:

    a. Impact to the customer and to the company

    b. Anticipated chance for success

    c. The number of people affected by the changes

    d. All of the above

    12. In a lean manufacturing work cell, who has authority to stop production?

    a. The line supervisor

    b. Machine operators

    c. The material handler

    d. All of the above

    13. Place the 5Ss in the proper order:

    a. Sort, Set-in-order, Shine, Sustain, Standardize

    b. Shine, Sort, Standardize, Set-in-order, Sustain

    c. Sort, Set-in-order, Shine, Standardize, Sustain

    d. Sustain, Set-in-order, Shine, Sort, Standardize

    e. Sort, Set-in-order, Standardize, Shine, Sustain

    f. Sustain, Standardize, Set-in-order, Shine, Sort

  • 5/28/2018 Lean Manufacturing Quiz i

    14/18

    14. Change over should be organized on the basis of:

    a. The cost of direct vs. indirect labor

    b. How many workers it takes to make the change

    c. Internal, external, and adjustment

    d. Machine utilization

    15. Queue means:

    a. A signal to start production

    b. A unit of measure

    c. Material should be pushed to the next operation when a batch is complete

    d. Waiting

    16. One-piece-flow means

    a. Batch

    b. Larger lot sizes

    c. One piece moves to the next operation

    d. Operators need to work harder

    17. Kanban is based on a model of:

    a. Shipyards

    b. Automotive assembly lines

    c. Supermarkets

    d. Job shop machining

  • 5/28/2018 Lean Manufacturing Quiz i

    15/18

    18. The term that relates to matching the output rate with customer demand in a JIT system is:

    a. Fill rate

    b. Takt Time

    c. Closed-loop JIT

    d. Single Minute Exchange of Die

    19. Which one of these is a system of lights used to signal problems in a lean production system?

    a. SMED

    b. Andon

    c. Kanban

    d. Jidoka

    20. Waste

    a. is part of a process and always inevitable

    b. is part of a process and always evitable

    c. is the usage of any resource during the process, which is not recognized by the customer as increasing the

    value they receive

    d. can not be seen on the shop floor

    WEEKLY VIETNAM BUSINESS QUIZ 06-JAN - 10-JAN

    How much did Vietnams industrial production value grew in 2013?

    7.40%

    7.45%

    8.40%

  • 5/28/2018 Lean Manufacturing Quiz i

    16/18

    8.45%

    How much did Vietnam's GDP rise in 2013?

    5.35%

    5.42%

    5.45%

    Retail sector growth in 2013?

    11.60%

    12.60%

    13.60%

    How many percent of people surveyed are now satisfied with high-quality made-in-Vietnam goods?

    69%

    70%

    71%

    According HSBC, how many percent of export growth in 2014 is?

    15%

    20%

    25%

    How many percent was Vietnam Logistics cost estimate in grossdomestic production?

    10%

  • 5/28/2018 Lean Manufacturing Quiz i

    17/18

    15%

    20%

    How many percent of Ha Noi price up in Lunar New Year 2014?

    7%

    10%

    13%

    According to Euromonitor, how much does Vietnamese beverage marketvalue?

    VND44 trillion

    VND54 trillion

    VND64 trillion

    How many kiosks and convenient store do HCMC plan to develop forLunar New Year?

    400

    410

    420

    How many businesses have been awarded for their impressive productsfollowing a three-month poll conducted by the Business Association ofHigh-Quality Vietnamese Goods?

    640

    650

    660

  • 5/28/2018 Lean Manufacturing Quiz i

    18/18

    Planning Input for Supply Chain

    Operations generate own estimates and not coordinate with other department

    Solely rely on Sales Plan from Sales

    Demand Plan that takes previous Sales Plan Achievement into account and future productlaunches and promotions

    No formal planning process in our company