lean process development: key questions to connect with ... · • process re-selection: in-line...
TRANSCRIPT
10/18/2016
1
© Copyright 2016, Lean Enterprise Institute, Inc., Cambridge, MA, lean.org. Lean Enterprise Institute, the
leaper image, and stick figure image are registered trademarks of Lean Enterprise Institute, Inc. All rights
reserved.
Lean Process Development:
Key Questions to Connect with
New Products
By Matt Zayko leanpd.org
© Copyright 2016, Lean Enterprise Institute, Inc.
What is the purpose of
Development in your organization?
“The purpose of Development is to create useful
knowledge and profitable operational value streams.”
--the late Allen Ward
Lean Product & Process Development Book,
LEI 2007
10/18/2016
2
© Copyright 2016, Lean Enterprise Institute, Inc.
What is the Operational Value Stream?
Raw Supplier Value Stream
Subassembly Supplier VS
Customers Final Assembly Value Stream
Fabrication Supplier VS
FIFO FIFO
Forming
1 Area
Feeder Line
2 lines PCT= 8
Fin ASM
3 Mixed PCT=12
FIFO
12 sec 12 sec 12 sec 12 sec 12 sec 12 sec
Product Flow
The Operational
Value Stream
is…..
….a series of
connected
processes
© Copyright 2016, Lean Enterprise Institute, Inc.
Development Casts a Large Shadow
5 5 2 0
7 0
%
Influence
on
Total Cost
100
90
80
70
60
50
40
30
20
10
0
5% 5% 20%
70%
10/18/2016
3
© Copyright 2016, Lean Enterprise Institute, Inc.
A Tale of Two Processes at Device Tech
“A bad process will defeat a good person
every time.”
--W. Edwards Deming
© Copyright 2016, Lean Enterprise Institute, Inc.
Device Tech’s Traditional Development Approach
Operations Process Selection Product Design
10/18/2016
4
© Copyright 2016, Lean Enterprise Institute, Inc.
The High Voltage Switch (HVS) at Device Tech
0.60
0.70
0.80
0.90
1.00
1.10
1.20
Jan-March April-June July-Sept Oct-DecWe
igh
ted
Vo
lum
e
Timeframe
Typical Seasonality for Switch Product
Normalized
© Copyright 2016, Lean Enterprise Institute, Inc.
Are you doing Kaizen…or Touzen?
• Operational Excellence in place at the Device Tech plant-
level after five years of focused effort, but…
• …every new product that launched in that same
timeframe required significant improvements to
incorporate the learning and operational standards
• Much of the improvement or kaizen activity the prior five
years had been valuable and necessary, but
• …a good portion of it was actually engineering re-work
or touzen due to poorly selected process flows
10/18/2016
5
© Copyright 2016, Lean Enterprise Institute, Inc.
Difference of Opinions…6 Months Prior to Launch
Metric Product Team’s Proposal
Operational Team’s Counterproposal
Cost per unit $2.26
Labor Efficiency 51%
Capital Spend $3.6 Million
Metric Product Team’s Proposal
Operational Team’s Counterproposal
Cost per unit $2.26 $1.88
Labor Efficiency 51% 86%
Capital Spend $3.6 Million $2.5 Million
© Copyright 2016, Lean Enterprise Institute, Inc.
Process Development Thinking at Device Tech:
6 Key Questions
• What is the current work for process development
with your new products?
• Where/What are the main failure modes?
• Where/What are the risks and opportunities?
• What is the ideal work for process development with
your new products?
• What is the improved future state of work for new
process development?
• What is the action plan to test out your future state
hypothesis?
10/18/2016
6
© Copyright 2016, Lean Enterprise Institute, Inc.
Phases of Development P
rocess D
evelo
pm
ent
Levels
Q1: What is the Current Work for Process Development?
© Copyright 2016, Lean Enterprise Institute, Inc.
Q2: What/Where are the Failure Modes?
• Too Much, Too Early (TMTE)
• Critical decisions are made too far in advance
• Knowledge incomplete
• Prematurely locks-in a process design
• Penny-Wise, Pound-Foolish (PWPF)
• Short-sighted decisions are made for local
optimization throughout the design cycle
• Results in overall performance reduction
• Too Little, Too Late (TLTL)
• Insufficient upfront design activity before launch
• Creates a flurry of rework after launch
10/18/2016
7
© Copyright 2016, Lean Enterprise Institute, Inc.
Q3: What/Where are the Risks & Opportunities?
© Copyright 2016, Lean Enterprise Institute, Inc.
Q4: What is the Ideal Process for Creating New Processes?
Context
• Scope
• Value Stream
Design
• Capacity Plan
Outputs •Short Lead Time
•Built-in Quality
•Flexible & Low
Cost Capacity &
Resources
•Simplicity &
Manageability
System Architect &
Expert Creation Team
4-2-1
Development Cycle Idea Delivery
Learning Executing
10/18/2016
8
© Copyright 2016, Lean Enterprise Institute, Inc.
Q5: What is the Future State for Doing Process
Development Work?
Phases of Development
Pro
cess D
evelo
pm
ent
Levels
© Copyright 2016, Lean Enterprise Institute, Inc.
Device Tech’s Lean Process Creation Team Experiment
• Pick System Architect(s): Technical Design Leader,
Operational Design Leader
• Select the Expert Creation Team Member Areas:
Operations, Production Control, Manufacturing
Engineering, Product Design, Quality, Equipment
Design, Purchasing, Test Engineering
• Understand the Timing: Six months until launch for the
HVS Process
10/18/2016
9
© Copyright 2016, Lean Enterprise Institute, Inc.
Lean Scorecard: Total Lifecycle Focus
© Copyright 2016, Lean Enterprise Institute, Inc.
Observations from Device Tech
PROCESS: Device Tech’s High Voltage Switch
Failure Modes What was Observed? What was the impact?
Too Much, Too Early HVS Project Team designs a semi-automated conveyor line to meet their goal of minimizing direct labor
10 Year Lifecycle Cost Difference = $5.6 Million between Concept 1 & 8
Penny-Wise, Pound-Foolish
HVS Project Team decides to combine Overweld and Leak Test to save space on their conveyor concept
Bottleneck of 28 seconds vs. 15 seconds would have required investing in a second line
Too Little, Too Late HVS Project Team hands-off the process design to the Chicago plant without any input from the Operational Team
Concept 1 is 20% more costly than Concept 2, and 138% more costly than Concept 8
Failure Modes What was Observed? What was the impact?
Too Much, Too Early HVS Project Team designs a semi-automated conveyor line to meet their goal of minimizing direct labor
10 Year Lifecycle Cost Difference = $5.6 Million between Concept 1 & 8
Penny-Wise, Pound-Foolish
HVS Project Team decides to combine Overweld and Leak Test to save space on their conveyor concept
Bottleneck of 28 seconds vs. 15 seconds would have required investing in a second line
Too Little, Too Late HVS Project Team hands-off the process design to the Chicago plant without any input from the Operational Team
Concept 1 is 20% more costly than Concept 2, and 138% more costly than Concept 8
Failure Modes What was Observed? What was the impact?
Too Much, Too Early HVS Project Team designs a semi-automated conveyor line to meet their goal of minimizing direct labor
10 Year Lifecycle Cost Difference = $5.6 Million between Concept 1 & 8
Penny-Wise, Pound-Foolish
HVS Project Team decides to combine Overweld and Leak Test to save space on their conveyor concept
Bottleneck of 28 seconds vs. 15 seconds would have required investing in a second line
Too Little, Too Late HVS Project Team hands-off the process design to the Chicago plant without any input from the Operational Team
Concept 1 is 20% more costly than Concept 2, and 138% more costly than Concept 8
10/18/2016
10
© Copyright 2016, Lean Enterprise Institute, Inc.
Metric Product Team’s Proposal
(Concept 1)
Operational Team’s Counterproposal
(Concept 2)
LPPD Team’s Final Proposal (Concept 8)
Cost per unit $2.26 $1.88 $0.95
Labor Efficiency
51% 86% 84%
Capital Spend
$3.6 Million $2.5 Million $0.5 Million
Total Lifecycle Cost
$9.8 Million $8.1 Million $4.1 Million
Results
Device Subs
Low Vol: Make-to-Order
High/Med Vol: Supermarket
Device Subassembly Cell
Straight Line for Plate & Final Assembly Cell
100
10b
50a 60a 90 70
20a
20b
10a
80
40 30
FIF
O
120 110b 110c 110a
Metric Product Team’s Proposal
(Concept 1)
Operational Team’s Counterproposal
(Concept 2)
LPPD Team’s Final Proposal (Concept 8)
Cost per unit $2.26 $1.88 $0.95
Labor Efficiency
51% 86% 84%
Capital Spend
$3.6 Million $2.5 Million $0.5 Million
Total Lifecycle Cost
$9.8 Million $8.1 Million $4.1 Million
Metric Product Team’s Proposal
(later, Concept 1)
Operational Team’s Counterproposal (later, Concept 2)
LPPD Team’s Final Proposal (Concept 8)
Cost per unit $2.26 $1.88 $0.95
Labor Efficiency
51% 86% 84%
Capital Spend
$3.6 Million $2.5 Million $0.5 Million
Total Lifecycle Cost
$9.8 Million $8.1 Million $4.1 Million
© Copyright 2016, Lean Enterprise Institute, Inc.
Key Learning at Device Tech
• Lifecycle Focus: Over 8x Payback for Upfront Engineering Effort
• Product Design Influence: Re-designed part eliminated Crimp step, reducing capital & manual time
• Quality Improvement: Crimp re-design improved quality & reduced key warranty issue
• Process Re-Selection: In-line bolt feeders reduced manual station time by 41% and process variability by 80%
• Resource Efficiency: People, Capital, Environmental
• Six different flexible process rates for Concept 8; One for Concept 1
• Learning Organization: People were given a chance to use their creative talents to add value for customers and Device Tech
• Knowledge Supermarket: Identified future opportunities for next generation product
• Simplified Process Management: Manual work close together, load & go stations close together
20
10/18/2016
11
© Copyright 2016, Lean Enterprise Institute, Inc.
How to embed LPPD
into the LPPD
System?
© Copyright 2016, Lean Enterprise Institute, Inc.
“Monday Morning”
• Pick a new product / process for your “learning laboratory”
• Nominate the system architect
• Take responsibility
• Link to product development for one overall Development Team
• Identify your responsible experts
• Be prepared to collaborate & co-locate
• Take a value stream view of the work
• Consider these phases
• 6Cs (Context, Concepts, Converge, etc.)
• 4:2:1 or some variation of set-based learning early-on
• Focus on the work & the key questions
• It will define the process
22
10/18/2016
12
© Copyright 2016, Lean Enterprise Institute, Inc.
Failure Modes Homework Template