LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD

Presented to Arizona State University DBIA Student ChapterCo-sponsored by DBIA Arizona Chapter and LCI Arizona CoPFebruary 24, 2015

Page 2: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

In the Beginning…

©2015 Umstot Project & Facilities Solutions, LLC

Page 3: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Built Environment

(+1.6M square feet)

Operating Budgets

(-US$46M)

+ 8

0 p

erce

nt

-16

percen

t

Why Did San Diego Community College District Start Its Lean Journey?

©2015 Umstot Project & Facilities Solutions, LLC

Page 4: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

What our team heard?

You want us to do what???

©2015 Umstot Project & Facilities Solutions, LLC

Page 5: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Let’s Think!!!

©2015 Umstot Project & Facilities Solutions, LLC

Page 6: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Current State

©2015 Umstot Project & Facilities Solutions, LLC

Page 7: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Current State

Future State

©2015 Umstot Project & Facilities Solutions, LLC

Page 8: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Current State

©2015 Umstot Project & Facilities Solutions, LLC

Page 9: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Project

Owner

Builder

Specialty Trades

Suppliers

Prefabrication

Maintenance & Operations

IT

FF&E

Energy Management

Building Users

Design TeamDesired State

©2015 Umstot Project & Facilities Solutions, LLC

Page 10: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

LEED & LCCA

LEAN

BIM

How to Get a Better Project…

©2015 Umstot Project & Facilities Solutions, LLC

Page 11: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Use Design-Build to Foster Lean Behaviors

©2015 Umstot Project & Facilities Solutions, LLC

Page 12: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Lean Fundamentals

Page 13: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

From: Teicholz (2013) ©2015 Umstot Project and Facilities Solutions, LLC

Non-Farm

Construction

Constant $ of Contracts/Labor Hours per Hourly Worker

Page 14: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Construction Labor Waste in the U.S.

Current Manufacturing

Waste 26%Support Activity 12%

Current Construction

Waste 57%Support Activity 33%

Value Added 10%

Source: Construction Industry Institute

Value Added 62%

©2015 Umstot Project and Facilities Solutions, LLC

Page 15: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

What is Lean Construction?

©2015 Umstot Project and Facilities Solutions, LLC

Lean Construction is a production management-based approach to project delivery to maximize value and minimize waste. - Lean Construction Institute

Page 16: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Lean Philosophies

Value • Value is defined by the owner

• Value is not cost

•Define customer value

•Identify and remove waste

•Innovate and perfect

©2015 Umstot Project & Facilities Solutions, LLCCourtesy: Southland Industries

Page 17: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

The Eight Wastes as Defined by Toyota (and Liker)

1. Overproduction

2. Waiting

3. Unnecessary transport

4. Over-processing

5. Excess inventory

6. Unnecessary movement

7. Defects

8. Unused employee creativity

18©2015 Umstot Project & Facilities Solutions, LLC

Page 18: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State
Page 19: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State
Page 20: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Cartoon By: JC Gatlin

Page 21: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Cartoon By: JC Gatlin

Page 22: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State
Page 23: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State
Page 24: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State
Page 25: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Typical Types of Design Waste:

• Iterative Design• Rework• Lack of Coordination Between Disciplines• Inefficient work flow• Over design of systems (diversity and factors of

safety)• Poor design that generates waste during construction• Designing over allowable budget

© 2015 Umstot Project & Facilities Solutions, LLC 26

Page 26: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Typical Types of Construction Waste:

• Rework• Requests for Information• Change orders• Inadequate Resources• Inefficient work flow• Workarounds• Multiple handling of material• Excess material• Waiting on supplies• Waiting on another trade• Safety losses• Improper sequencing of work

©2015 Umstot Project and Facilities Solutions, LLC

Page 27: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

https://www.gov.uk/government/uploads/

system/uploads/attachment_data/file/210

099/bis-13-955-construction-2025-

industrial-strategy.pdf

UK Construction 2025 Goals

©2015 Umstot Project & Facilities Solutions, LLC

Page 28: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

UK Construction 2025 Goals

©2015 Umstot Project & Facilities Solutions, LLC

Page 29: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

©2015 Umstot Project and Facilities Solutions, LLC

UK BIM Goals

Page 30: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Source: McGraw-Hill SmartMarketReport (2013)

Perceptions of Efficiency in Our Industry

©2015 Umstot Project & Facilities Solutions, LLC

Page 31: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

2-Second Lean (A Guide)

“Fix What Bugs You” – Paul Akers

©2015 Umstot Project & Facilities Solutions, LLC

Page 32: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Who is Going Lean?

©2015 Umstot Project and Facilities Solutions, LLC

Page 33: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

http://www.leanconstruction.org/training/lean-project-delivery-guide/

©2015 Umstot Project and Facilities Solutions, LLC

Page 34: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

San Diego CCD Lean Practices

Page 35: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Mesa College

San Diego Community College District (SDCCD)

Overview

The Second Largest Community College District in California – Serving 130,000 students

Sixth Largest in Nation

Three Colleges - City, Mesa and Miramar

Six Continuing Education Campuses

$1.555 B Locally Approved Capital Bonds

City College Miramar College Continuing Education

Page 36: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Total Cost of Ownership

50-year design life

100,000 square foot classroom building

Design and construction cost - $30 million

Capital Renewal: 2% of current replacement value (APPA benchmark)

O&M Budget $5.69/square foot

Inflation: 3%

©2015 Umstot Project & Facilities Solutions, LLC

Page 37: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

39

Total Cost of Ownership

53%

36%

11%

Total Cost of Ownership

Save 5% in Cap. Renewal

Save 10% in O&M

Savings

D&C: $30M Total NPV

Cap. R.: $101M $ 5M $1.1M

O&M: $149M $15M $3.4M

Total: $280M $20M $4.4M

©2015 Umstot Project & Facilities Solutions, LLC

Page 38: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

40

Early (and continued) Attitudes Toward Lean

We’ve tried that.

We already do that.

We don’t need it.

It won’t work here.

We don’t build cars.

We’re different.

The other guy needs it, not me.

We’re doing well, so why change?

Credit: Lean Construction Institute

©2015 Umstot Project & Facilities Solutions, LLC

Page 39: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

1. Target Value Design2. A3 Problem Solving and Reporting3. Set-Based Design4. Value Stream Mapping5. Building Information Modeling (BIM)6. The Last Planner™ System

Use of Lean Tools in Capital Project Delivery

©2015 Umstot Project & Facilities Solutions, LLC

Page 40: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Defining Values for SDCCD

• Enhance the student experience

• Flexibility in design to accommodate future changes in pedagogy

• Lower total cost of ownership

• Highly energy efficient buildings

• Reduce maintenance and operations costs

• Meet or exceed sustainability objectives

©2015 Umstot Project & Facilities Solutions, LLC

Page 41: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Value-Waste Nexus

• How to create value within fixed monetary constraints?

• Eliminate waste

• Enhance value with the savings from waste reduction

© 2015 Umstot Project & Facilities Solutions, LLC 43

Page 42: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Public Owner Benefits

Reduced Waste in Project Delivery

Sustainable Buildings

Reduced Total Cost

of Ownership

Enhanced Value

44©2015 Umstot Project & Facilities Solutions, LLC

Page 43: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

How to get there?

©2015 Umstot Project & Facilities Solutions, LLC

Page 44: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Design-Build Using Target Costing

©2015 Umstot Project & Facilities Solutions, LLC

Page 45: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

©2015 Umstot Project & Facilities Solutions, LLC

Page 46: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

©2015 Umstot Project & Facilities Solutions, LLC

Page 47: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Space Programming

Space Efficiency

Targeted Cost

Per Sq. Ft.

Target Costing - Project Budget Development

©2015 Umstot Project & Facilities Solutions, LLC

Page 48: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Target Value

Value Definition

BIM

Lean

Set-Based Design

LCCA

Concurrent Estimating

Keys to Target Value

©2015 Umstot Project & Facilities Solutions, LLC

Page 49: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

A3 Problem Solving – HVAC Design

©2015 Umstot Project & Facilities Solutions, LLC

Page 50: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

A3 Problem Solving – Structural System Design

©2015 Umstot Project & Facilities Solutions, LLC

Page 51: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

http://public.sdccdprops-n.com/Design/SDCCD%20-%20Building%20Design%20Standards/SDCCD%20BIM%20Standards%20Version%202.pdf ©2015 Umstot Project & Facilities Solutions, LLC

Page 52: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Which Design Would You Want?

©2015 Umstot Project & Facilities Solutions, LLC

Page 53: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Is Critical Path Method Scheduling Obsolete?

©2015 Umstot Project & Facilities Solutions, LLC

Page 54: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Schedule Performance

• SDCCD Experience: 34 Major Projects with CPM Scheduling 4 (12%) finished on time

• UC System Experience in past 10 years: More than 30% of projects delayed by more than 90 days

• Research by Glenn Ballard and Greg Howell indicated only 54% of planned weekly activities get completed on average.

• Last Planner® pull system – a better way (typically 80-90% percent promises kept)

©2015 Umstot Project & Facilities Solutions, LLC

Page 55: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Last Planner® System

©2015 Umstot Project and Facilities Solutions, LLC

1. Master Scheduling – setting milestones2. Phase (Pull) Planning – specifying handoffs3. Make Work Ready Planning – 6 week look-ahead4. Weekly Work Planning5. Learning - Measure Percent Promises Complete,

conduct root cause analysis and act on reasons for failure to keep promises

5 Major Elements of System

Who are the Last Planners?The foremen and superintendents

Page 56: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Last Planner® System Principles

©2015 Umstot Project and Facilities Solutions, LLC

1.All plans are forecasts and all forecasts are wrong. The longer the forecast the more wrong it is. The more detailed the forecast, the more wrong it is.

2.Plan in greater detail as you get closer to doing the work.3.Produce plans collaboratively with those who will do the

work.4.Reveal and remove constraints on planned tasks as a team.5.Make reliable promises.6.Learn from breakdowns.

Page 57: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

©2015 Umstot Project and Facilities Solutions, LLC

Source: Adrian Smith (2011)

Page 58: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State
Page 59: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Pull Planning

“Start with the end in mind.” – Steven Covey

©2015 Umstot Project and Facilities Solutions, LLC

Page 60: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Pull Planning Activities

©2015 Umstot Project and Facilities Solutions, LLC

Page 61: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

©2015 Umstot Project & Facilities Solutions, LLC

Page 62: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

©2015 Umstot Project & Facilities Solutions, LLC

Page 63: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Milestone Planning Design Phase

©2015 Umstot Project and Facilities Solutions, LLC

Page 64: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Pull Planning – 6 Week Lookahead

©2015 Umstot Project and Facilities Solutions, LLC

Page 65: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Pull Planning – 6 Week Lookahead

©2015 Umstot Project and Facilities Solutions, LLC

Page 66: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Pull Planning – 6 Week Lookahead

©2015 Umstot Project and Facilities Solutions, LLC

Page 67: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Pull Planning – 6 Week Lookahead

©2015 Umstot Project and Facilities Solutions, LLC Source: LCI (2009)

Page 68: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

© 2015 Umstot Project and Facilities Solutions, LLC

https://www.youtube.com/watch?v=i4VAyKjMMYg

Page 69: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

San Diego CCD Metrics Discussion

©2015 Umstot Project & Facilities Solutions, LLC

Page 70: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Wouldn't It Be Nice If You Could...

Average Savings of $900,000 on each of 15 projects

Reduce Average Schedule Delay by 56 days

Enhance Sustainability Objectives by 44%

Reduce Facilities Maintenance Costs by 53%

72©2015 Umstot Project & Facilities Solutions, LLC

Page 71: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

By the Numbers – The Database

35 COMPLETED

PROJECTS

US$584M CONTRACT

VALUE

8000 CHANGE ORDERS

73©2015 Umstot Project & Facilities Solutions, LLC

Page 72: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Change Order Analysis

•7.73% Total COs

•2.99% E&O COsPre-Lean

•4.43% Total COs

•1.88% E&O COsPost-Lean

74©2015 Umstot Project & Facilities Solutions, LLC

Page 73: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Interesting Finding

Without Lean: E&O 33% of COs

With Lean: E&O 36% of COs

75©2015 Umstot Project & Facilities Solutions, LLC

Page 74: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Who is on Time?

Pre-Lean

•1/19 (5%)

Post-Lean

•3/15 (20%)

76©2015 Umstot Project & Facilities Solutions, LLC

Page 75: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Average Delay (All Contract Types)

Lean w/ BIM: 25 days (n=8)

Pre-Lean w/o BIM: 80 days (n=12)

San Diego CCD Schedule Impacts –Lean (with BIM) vs. No Lean or BIM (20 projects)

©2015 Umstot Project & Facilities Solutions, LLC

Page 76: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Target Costing

11 Projects

Avg. Value:

US$21.8M

83% Met Target Cost; Avg. 7% Below Target Cost

78©2015 Umstot Project & Facilities Solutions, LLC

Page 77: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Target Value Design

• Six projects evaluated• Range of GMP: $4,707,408 to

$50,423,353• Average: $21,768,648• 5/6 (83%) met target budget• Averaged 7% under target budget

©2015 Umstot Project & Facilities Solutions, LLC

Page 78: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Target Value Design – Root Cause Analysis

• Lack of contemporaneous estimating and exclusion of specialty trades from early participation in project resulted in project exceeding target budget

• Counter measure: All subsequent projects required presentation of budget first

©2015 Umstot Project & Facilities Solutions, LLC

Page 79: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Potential Sustainability Features

• Higher building energy efficiency

• Extensive use of daylighting

• Use of natural ventilation tied to EMS

• Reduced water consumption

• Use of reclaimed water for irrigation, flushing

• Solid flooring without need for stripping and waxing

©2015 Umstot Project & Facilities Solutions, LLC

Page 80: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Sustainability as a Core ValueLEED Gold Projects

Direct Contract with Architect

Post-Lean

Target Value Design

82©2015 Umstot Project & Facilities Solutions, LLC

Page 81: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Value as Reduced Maintenance Costs

$3.93/sq.ft.

$1.91

$1.73

$1.46

83

Over 4 Years

©2015 Umstot Project & Facilities Solutions, LLC

Page 82: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

US$34.6 Million of Waste Eliminated

US$13.6M Total Savings in Reduced COs

US$7.7M Total Savings To Date with TVD

US$13.3M Total Savings over 3 Years in

Maintenance Costs

84©2015 Umstot Project & Facilities Solutions, LLC

Page 83: LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD9293995b8dbc90e36a83-6ce1483d732bd2ccb4d6803b7dc105ce.r78.cf2.rackcdn…LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State

Questions?

David Umstot, PE, CEMUmstot Project & Facilities Solutions, LLC2015 President, DBIA Western Pacific Region