lecture earthworks
TRANSCRIPT
-
Lecture
Earthworks
1. Types of earthworks
2. Excavation & compaction materials
3. Design of cuttings & embankments
4. Specification of embankment fill materials
5. Example: Vajont Dam disaster
-
Types of earthworks
1. Cuttings
Road and railway cuts
Foundation excavations
2. Embankments
Constructed of engineered fill: road and rail
embankments & rock and earth fill dams
Non-engineered fills: loose tipped waste
dumps; e.g. landfill
When these structures fail?
-
Failing road cuttings; debris/rock falls
-
Failing road cuttings within road foundation material
-
CARSINGTON DAM an earth embankment in Derbyshire. This failed in 1984 during construction long before the reservoir was even filled.
(1) A slip surface developed through both the boot-shaped weak clay core and
a layer of periglacial head left on the shale bedrock beneath the placed and
compacted fill.
(2) The head was wrongly interpreted as in situ weathered shale, and the
design assumed an undisturbed angle of friction of = 20. Due to its origin the material contained shear surfaces with a residual angle of friction r = 12. This mistake and the rebuild cost 20 million at 1985 prices and the subsequent
litigation led to the company responsible being taken over.
(3) Incident could have been avoided: Periglacial head with shear surfaces at
residual strength is widespread on the shale of Derbyshire, therefore decent
applied geoscience investigations would have identified this as a potential
problem
-
(1) At 11:57 A.M. on June 1, 1976, in the Teton Canyon of Fremont
County, the collapse of an earth dam sent a wall of water toward
Idaho Falls.
(2) The subsequent flood killed 14 people and caused at least $1
billion in property damage. Ripping though Wilford, Sugar City,
Salem, Hibbard, and Rexburg.
(3) It destroyed 13,000 head of livestock, 3,500 farm buildings, and
4,000 homes. The federal government paid more than $300 million
to settle more than 7,500 claims.
-
Concrete Dam: St Francis
Dam, California 1928;
500 people killed.
Court of Inquiry blamed a
palaeomegaslide under the east abutment was
undetected
Scarp
-
Excavation/cutting design Removal of material without hazard requires
characterisation of rocks and soils involved;
Stability of cut slopes is critical factor in cutting
design, affected by:
1. Strength, frequency & orientation of rock
discontinuities such as joints and fracture sets
2. Water table level (affects effective strength of slope
material)
3. Changes in subsurface stress regime in response to
removal of overburden act to reduce cutting stability
-
Excavation/cutting design Different materials more able to resist shearing forces
than others. Ideal slope material has:
High shear strength, few discontinuities & low pore
water pressures (support steeper slope)
Results in a range of slope angles:
1. Massive igneous rocks and some metamorphic rocks
can support near vertical cuttings
2. Vertical slopes in horizontally bedded limestones
common (80-90)
3. Weak & fissile shales support slopes 45-70
4. SOILS: 10-40 (text book, Bell)
-
Cuttings: groundwater Short-term and long-term cutting stability
Pore
pressure, P
Factor of
Safety, F
1. Excavation causes
pore pressures to drop
considerably
- Response to fall in total
stress
- Materials expand
- FoS lowers sharply
2. Pore pressures
redistribute in
response to
overburden removal
3. Groundwater returns
to steady state
seepage flow
- Long term reduction in
FoS
1. 2.
3.
-
Excavation Considerations
1. Short & long term
slope stability
2. Reactivation of relict
structures
3. Construction methods
(next few slides)
4. Groundwater regime
during and after
construction
5. Heave (uplift) at base
of excavation
6. Risk of collapse
(tunnels)
-
(Pettifer and Fookes 1994)
NB point load index is a portable field test of
rock strength and is
approximately equal to
UCS/20
Which Excavation Method?
Rock strength increase
Fra
ctu
re s
pa
cin
g in
cre
ase
DIGGING
RIPPING
BLASTING
Point load machine
-
Soils and soft rocks: excavator and scraper
JCB.CO.UK
(Bell, 2007)
Digging method as a function of material
seismic velocity
Dig
gin
g m
eth
ods
Can dig through materials with low seismic velocities
JCB JS 360 Excavator
-
Soils and soft rocks: excavator and scraper
Cutting surface
in weak rocks
-
Soft to medium strong rocks: ripper plus scraper
Objective: break up the rock just enough
to allow its loading and transport
Rock rippability: depends on:
Intact strength, fracture index and
abrasiveness of rocks
Rippability a function of seismic velocity
(Bell 2007)
CAT D-9 Tractor with
ripper attachment
-
Rock cut blasting
Medium strong to strong rocks require blasting
Diggers remove the blast debris
-
Blast stem lines
Medium strong to strong rocks require blasting
-
Medium strong to strong rocks require blasting
To obtain a stable angle
in a rock face use
pre-split blasting
Delay time between blasts a function of burden, B
Subdrilling to depth B/3
-
Medium strong to strong rocks require blasting
How much dynamite to use?
-
Embankment Design Embankments built up of laying and compacting layers of soil
Engineering properties of embankment fill affected by amount
of compaction
1. Compaction; expulsion of air at ~constant MC increases water saturation
and dry density
Amount of compaction depends on the optimum design
performance of structure
Degree of compaction necessary dictates:
1. Compaction equipment used (rolls, tamps or vibrates)
2. Soil type (granular; natural MC, cohesive; optimum MC)
3. Quantity of material needed
4. Layer thickness geometry of proposed earthworks
-
Embankments: groundwater
Pore
pressure, P
Factor of
Safety, F
Short term and long term stability of embankments 1. Building embankment causes pore pressures
rise
- Response to increase in
total stress
- Materials contract
- FoS lowers as
overburden supported by
pore water
2. Pore pressures
redistribute until equal
with original regime
- FoS rise
3. Groundwater returns
to steady state
seepage flow
- FoS rises leading to
long-term stability
1. 2. 3.
-
Embankment Considerations 1. Interaction with existing
features (relict landslides,
cavities)
2. Influence of loading greater
than normal foundations
(piles, rafts)
3. Settlement and lateral
movements; phase project to
minimise
4. Locally sourced fill material
(project costs lower)
-
Engineered Fill Material Embankment built up of many 0.3 m lifts placed by scraper
(tight guidelines on construction procedure)
The material is then compacted after each lift
Proper placement and compaction ensures maximum
strength is obtained and settlement minimised
Embankment material is identified based on its compaction
qualities; related to: dry density/moisture content
relationship but also undrained shear strength,
consolidation characteristics
Embankments often contain layers of free-draining sandy
material to ensure settlement and pressure dissipation
occurs rapidly
Embankment design factor of safety: 1.5 (cover in prac.)
-
Laboratory Compaction Proctor test
Laboratory determination of
material compaction properties:
1. Build up three layers of sample
2. 25 blows per layer to compact
3. Measure dry density, MC and
air volume
4. Repeat
-
Laboratory Compaction Proctor test
Most desirable degree of compaction achieved at:
highest dry density which occurs at an optimum
moisture content and a high
shear strength
Too much compaction: 1. Samples crack/fissure
2. Moisture content rises
3. Reduces soil strength
In field: measure MC to
determine compaction
Increased
compaction
-
Field Compaction
(Bell, 2007)
-
Grid roller
-
The Vajont Dam disaster, Italy
1963
Deaths: 2043
Concrete dam completed in
1960
1963: 270M m3 of rock forming a
slab 200m thick moved 400 m at
20-30 m/s.
The sliding block landed in the reservoir creating a 100m high
flood wave that overtopped the
dam
Daves Landslide Blog: http://www.landslideblog.org/2008/12/vai
ont-vajont-landslide-of-1963.html
Worlds worst civil engineering disaster
-
Map of area (Waltham, 2009)
-
Sliding block
Back scarp Monte Toc
~1 km
-
Dam
~1 km
-
50 m Structure within slumped mass
-
Village of Casso
~1 km
-
Cross section through gorge before landslide Geology:
Downslope-dipping dolomitic limestones interbedded with thin plastic clay horizons 1963 main failure occurred along a reactivated clay horizon; ancient slip surface;
also minor 1960 rock slide
Sharp rise in groundwater level when reservoir filled
(Waltham, 2009)
-
Trigger Mechanisms 1. Minor landslide activated in Feb
1960 during first reservoir filling
event (impoundment)
2. October 1960: reservoir filled;
leading to high displacement rates
- Reservoir lowered; displacement
much reduced
3. November 1963: reservoir filled
and high rainfall lead to
catastrophic failure of rock slump
block
1.
2.
3. 4.
-
Trigger Mechanisms
4. Increasing the level of the
reservoir drove up pore water
pressures within the clay
interbeds, reducing shear
resistance (strength)
NB: importance of understanding
water within a landslide system!!
Key Outcome:
Understanding of ground
conditions imperative if
earthworks are to be
successfully constructed
-
Summary
Earthworks involves: design of stable slopes;
excavation of material; placement of fill
In the UK Earthworks construction is carried
out according to BS6031 and Eurocode 7
Minimise failure by understanding the effect of
earthworks on the site
-
Earth Dam during construction:
-
Earth Dam during construction: Dam
wall