lecture earthworks

Upload: anthony-wright

Post on 17-Oct-2015

81 views

Category:

Documents


2 download

TRANSCRIPT

  • Lecture

    Earthworks

    1. Types of earthworks

    2. Excavation & compaction materials

    3. Design of cuttings & embankments

    4. Specification of embankment fill materials

    5. Example: Vajont Dam disaster

  • Types of earthworks

    1. Cuttings

    Road and railway cuts

    Foundation excavations

    2. Embankments

    Constructed of engineered fill: road and rail

    embankments & rock and earth fill dams

    Non-engineered fills: loose tipped waste

    dumps; e.g. landfill

    When these structures fail?

  • Failing road cuttings; debris/rock falls

  • Failing road cuttings within road foundation material

  • CARSINGTON DAM an earth embankment in Derbyshire. This failed in 1984 during construction long before the reservoir was even filled.

    (1) A slip surface developed through both the boot-shaped weak clay core and

    a layer of periglacial head left on the shale bedrock beneath the placed and

    compacted fill.

    (2) The head was wrongly interpreted as in situ weathered shale, and the

    design assumed an undisturbed angle of friction of = 20. Due to its origin the material contained shear surfaces with a residual angle of friction r = 12. This mistake and the rebuild cost 20 million at 1985 prices and the subsequent

    litigation led to the company responsible being taken over.

    (3) Incident could have been avoided: Periglacial head with shear surfaces at

    residual strength is widespread on the shale of Derbyshire, therefore decent

    applied geoscience investigations would have identified this as a potential

    problem

  • (1) At 11:57 A.M. on June 1, 1976, in the Teton Canyon of Fremont

    County, the collapse of an earth dam sent a wall of water toward

    Idaho Falls.

    (2) The subsequent flood killed 14 people and caused at least $1

    billion in property damage. Ripping though Wilford, Sugar City,

    Salem, Hibbard, and Rexburg.

    (3) It destroyed 13,000 head of livestock, 3,500 farm buildings, and

    4,000 homes. The federal government paid more than $300 million

    to settle more than 7,500 claims.

  • Concrete Dam: St Francis

    Dam, California 1928;

    500 people killed.

    Court of Inquiry blamed a

    palaeomegaslide under the east abutment was

    undetected

    Scarp

  • Excavation/cutting design Removal of material without hazard requires

    characterisation of rocks and soils involved;

    Stability of cut slopes is critical factor in cutting

    design, affected by:

    1. Strength, frequency & orientation of rock

    discontinuities such as joints and fracture sets

    2. Water table level (affects effective strength of slope

    material)

    3. Changes in subsurface stress regime in response to

    removal of overburden act to reduce cutting stability

  • Excavation/cutting design Different materials more able to resist shearing forces

    than others. Ideal slope material has:

    High shear strength, few discontinuities & low pore

    water pressures (support steeper slope)

    Results in a range of slope angles:

    1. Massive igneous rocks and some metamorphic rocks

    can support near vertical cuttings

    2. Vertical slopes in horizontally bedded limestones

    common (80-90)

    3. Weak & fissile shales support slopes 45-70

    4. SOILS: 10-40 (text book, Bell)

  • Cuttings: groundwater Short-term and long-term cutting stability

    Pore

    pressure, P

    Factor of

    Safety, F

    1. Excavation causes

    pore pressures to drop

    considerably

    - Response to fall in total

    stress

    - Materials expand

    - FoS lowers sharply

    2. Pore pressures

    redistribute in

    response to

    overburden removal

    3. Groundwater returns

    to steady state

    seepage flow

    - Long term reduction in

    FoS

    1. 2.

    3.

  • Excavation Considerations

    1. Short & long term

    slope stability

    2. Reactivation of relict

    structures

    3. Construction methods

    (next few slides)

    4. Groundwater regime

    during and after

    construction

    5. Heave (uplift) at base

    of excavation

    6. Risk of collapse

    (tunnels)

  • (Pettifer and Fookes 1994)

    NB point load index is a portable field test of

    rock strength and is

    approximately equal to

    UCS/20

    Which Excavation Method?

    Rock strength increase

    Fra

    ctu

    re s

    pa

    cin

    g in

    cre

    ase

    DIGGING

    RIPPING

    BLASTING

    Point load machine

  • Soils and soft rocks: excavator and scraper

    JCB.CO.UK

    (Bell, 2007)

    Digging method as a function of material

    seismic velocity

    Dig

    gin

    g m

    eth

    ods

    Can dig through materials with low seismic velocities

    JCB JS 360 Excavator

  • Soils and soft rocks: excavator and scraper

    Cutting surface

    in weak rocks

  • Soft to medium strong rocks: ripper plus scraper

    Objective: break up the rock just enough

    to allow its loading and transport

    Rock rippability: depends on:

    Intact strength, fracture index and

    abrasiveness of rocks

    Rippability a function of seismic velocity

    (Bell 2007)

    CAT D-9 Tractor with

    ripper attachment

  • Rock cut blasting

    Medium strong to strong rocks require blasting

    Diggers remove the blast debris

  • Blast stem lines

    Medium strong to strong rocks require blasting

  • Medium strong to strong rocks require blasting

    To obtain a stable angle

    in a rock face use

    pre-split blasting

    Delay time between blasts a function of burden, B

    Subdrilling to depth B/3

  • Medium strong to strong rocks require blasting

    How much dynamite to use?

  • Embankment Design Embankments built up of laying and compacting layers of soil

    Engineering properties of embankment fill affected by amount

    of compaction

    1. Compaction; expulsion of air at ~constant MC increases water saturation

    and dry density

    Amount of compaction depends on the optimum design

    performance of structure

    Degree of compaction necessary dictates:

    1. Compaction equipment used (rolls, tamps or vibrates)

    2. Soil type (granular; natural MC, cohesive; optimum MC)

    3. Quantity of material needed

    4. Layer thickness geometry of proposed earthworks

  • Embankments: groundwater

    Pore

    pressure, P

    Factor of

    Safety, F

    Short term and long term stability of embankments 1. Building embankment causes pore pressures

    rise

    - Response to increase in

    total stress

    - Materials contract

    - FoS lowers as

    overburden supported by

    pore water

    2. Pore pressures

    redistribute until equal

    with original regime

    - FoS rise

    3. Groundwater returns

    to steady state

    seepage flow

    - FoS rises leading to

    long-term stability

    1. 2. 3.

  • Embankment Considerations 1. Interaction with existing

    features (relict landslides,

    cavities)

    2. Influence of loading greater

    than normal foundations

    (piles, rafts)

    3. Settlement and lateral

    movements; phase project to

    minimise

    4. Locally sourced fill material

    (project costs lower)

  • Engineered Fill Material Embankment built up of many 0.3 m lifts placed by scraper

    (tight guidelines on construction procedure)

    The material is then compacted after each lift

    Proper placement and compaction ensures maximum

    strength is obtained and settlement minimised

    Embankment material is identified based on its compaction

    qualities; related to: dry density/moisture content

    relationship but also undrained shear strength,

    consolidation characteristics

    Embankments often contain layers of free-draining sandy

    material to ensure settlement and pressure dissipation

    occurs rapidly

    Embankment design factor of safety: 1.5 (cover in prac.)

  • Laboratory Compaction Proctor test

    Laboratory determination of

    material compaction properties:

    1. Build up three layers of sample

    2. 25 blows per layer to compact

    3. Measure dry density, MC and

    air volume

    4. Repeat

  • Laboratory Compaction Proctor test

    Most desirable degree of compaction achieved at:

    highest dry density which occurs at an optimum

    moisture content and a high

    shear strength

    Too much compaction: 1. Samples crack/fissure

    2. Moisture content rises

    3. Reduces soil strength

    In field: measure MC to

    determine compaction

    Increased

    compaction

  • Field Compaction

    (Bell, 2007)

  • Grid roller

  • The Vajont Dam disaster, Italy

    1963

    Deaths: 2043

    Concrete dam completed in

    1960

    1963: 270M m3 of rock forming a

    slab 200m thick moved 400 m at

    20-30 m/s.

    The sliding block landed in the reservoir creating a 100m high

    flood wave that overtopped the

    dam

    Daves Landslide Blog: http://www.landslideblog.org/2008/12/vai

    ont-vajont-landslide-of-1963.html

    Worlds worst civil engineering disaster

  • Map of area (Waltham, 2009)

  • Sliding block

    Back scarp Monte Toc

    ~1 km

  • Dam

    ~1 km

  • 50 m Structure within slumped mass

  • Village of Casso

    ~1 km

  • Cross section through gorge before landslide Geology:

    Downslope-dipping dolomitic limestones interbedded with thin plastic clay horizons 1963 main failure occurred along a reactivated clay horizon; ancient slip surface;

    also minor 1960 rock slide

    Sharp rise in groundwater level when reservoir filled

    (Waltham, 2009)

  • Trigger Mechanisms 1. Minor landslide activated in Feb

    1960 during first reservoir filling

    event (impoundment)

    2. October 1960: reservoir filled;

    leading to high displacement rates

    - Reservoir lowered; displacement

    much reduced

    3. November 1963: reservoir filled

    and high rainfall lead to

    catastrophic failure of rock slump

    block

    1.

    2.

    3. 4.

  • Trigger Mechanisms

    4. Increasing the level of the

    reservoir drove up pore water

    pressures within the clay

    interbeds, reducing shear

    resistance (strength)

    NB: importance of understanding

    water within a landslide system!!

    Key Outcome:

    Understanding of ground

    conditions imperative if

    earthworks are to be

    successfully constructed

  • Summary

    Earthworks involves: design of stable slopes;

    excavation of material; placement of fill

    In the UK Earthworks construction is carried

    out according to BS6031 and Eurocode 7

    Minimise failure by understanding the effect of

    earthworks on the site

  • Earth Dam during construction:

  • Earth Dam during construction: Dam

    wall