lessons learned from opening a new facility steve myers, leetran director

14
Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Upload: felicia-porter

Post on 06-Jan-2018

222 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Lessons Learned From Opening a New Facility

Steve Myers, LeeTran Director

Page 2: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

LeeTran Headquarters• 23.9-acre site• Total project cost $42.9 million• $32.1 million in federal grants• 30,000 s.f. office, 45,000 s.f.

maintenance• Ground Breaking: March 25, 2013• Move-in January 2015

Page 3: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director
Page 4: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Create Synergy• Design/engineering: AECOM• Construction management: Gilbane

Building Co.Include CM during design:• Constructability reviews• Cost estimates• Value engineering

Page 5: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Aerial View 2/21/13

Page 6: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Project ManagerAn agency project manager is essential to bring

various disciplines to weekly review meetings to integrate systems:

• Audio/video• Security/surveillance• Telecom & IT systems• Access management• HVAC• Lighting

Page 7: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Continuity of Staff• Construction management team

remained on the project throughout two-year project.

• Changes to County team and LeeTran team during design.

• The more team members you can keep in place through the project, the less time loss will be spent on familiarization with the project.

Page 8: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Plan for ITIT systemsare criticalto buildingfunction:Integrateearly indesignphase

Page 9: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Multi-Department Review• Review plans in detail• How will the design function?• Don’t assume the architect

understands your business practices and processes.

• Perform weekly onsite inspections to prevent costly design errors.

Page 10: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director
Page 11: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Buy America• Be proactive in finding alternative

products• Wait for FTA waivers will disrupt project

schedule

Page 12: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Project Wrap-Up• Internal management of warranty

issues– Asphalt curing– ADA accessibility of call stations in

parking lot– Shop equipment didn’t match power

feeds• Expect adjustments in procedures

based on actual use– Key card access– Gate operations– Added lighting for safety

Page 13: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director
Page 14: Lessons Learned From Opening a New Facility Steve Myers, LeeTran Director

Questions?