lessons learned from opening a new facility steve myers, leetran director
TRANSCRIPT
Lessons Learned From Opening a New Facility
Steve Myers, LeeTran Director
LeeTran Headquarters• 23.9-acre site• Total project cost $42.9 million• $32.1 million in federal grants• 30,000 s.f. office, 45,000 s.f.
maintenance• Ground Breaking: March 25, 2013• Move-in January 2015
Create Synergy• Design/engineering: AECOM• Construction management: Gilbane
Building Co.Include CM during design:• Constructability reviews• Cost estimates• Value engineering
Aerial View 2/21/13
Project ManagerAn agency project manager is essential to bring
various disciplines to weekly review meetings to integrate systems:
• Audio/video• Security/surveillance• Telecom & IT systems• Access management• HVAC• Lighting
Continuity of Staff• Construction management team
remained on the project throughout two-year project.
• Changes to County team and LeeTran team during design.
• The more team members you can keep in place through the project, the less time loss will be spent on familiarization with the project.
Plan for ITIT systemsare criticalto buildingfunction:Integrateearly indesignphase
Multi-Department Review• Review plans in detail• How will the design function?• Don’t assume the architect
understands your business practices and processes.
• Perform weekly onsite inspections to prevent costly design errors.
Buy America• Be proactive in finding alternative
products• Wait for FTA waivers will disrupt project
schedule
Project Wrap-Up• Internal management of warranty
issues– Asphalt curing– ADA accessibility of call stations in
parking lot– Shop equipment didn’t match power
feeds• Expect adjustments in procedures
based on actual use– Key card access– Gate operations– Added lighting for safety