lhc scheduling applied to clic and ilc

9
LHC scheduling applied to CLIC and ILC TILC09 & GDE AAP review – Tsukuba April 2009 K. Foraz K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

Upload: mahogany-spence

Post on 01-Jan-2016

29 views

Category:

Documents


1 download

DESCRIPTION

LHC scheduling applied to CLIC and ILC. TILC09 & GDE AAP review – Tsukuba April 2009 K. Foraz. ILC - Civil engineering works. Shaft excavation and Cavern-halls construction based on same hypothesis as M. Gastal = unlimited resources Times derived from Amberg Studies. - PowerPoint PPT Presentation

TRANSCRIPT

LHC scheduling applied to CLIC and ILC

TILC09 & GDE AAP review – Tsukuba April 2009

K. Foraz

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

1

2

3

4

5

6

7

8

9

10

11-7(2.88km)

7-5(5.54km)

5-3(5.1km)

3-1(2.6km)

1-2(2.6km)

2-4(4.6km)

4-6(4.6km)

6-10(2.88km)

ILC - Civil engineering works

Tunnel excavationSite installation & shaft excavation

Cavern and halls Tunnel concrete and finishes

TBM installation

Shaft excavation and Cavern-halls construction based on same hypothesis as M. Gastal = unlimited resources

Times derived from Amberg Studies

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

1

2

3

4

5

6

7

8

9

10

11-7(2.88km)

7-5(5.54km)

5-3(5.1km)

3-1(2.6km)

1-2(2.6km)

2-4(4.6km)

4-6(4.6km)

6-10(2.88km)

ILC - Civil engineering works

Tunnel excavationSite installation & shaft excavation

Cavern and halls Tunnel concrete and finishes

TBM installation

Excavation : 9 TBM - 200m/wkConcrete and finishes: 400m/wk

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

1

2

3

4

5

6

7

8

9

10

11-7(2.88km)

7-5(5.54km)

5-3(5.1km)

3-1(2.6km)

1-2(2.6km)

2-4(4.6km)

4-6(4.6km)

6-10(2.88km)

ILC - Civil engineering works

Tunnel excavationSite installation & shaft excavation

Cavern and halls Tunnel concrete and finishes

TBM installation

Civil engineering will give you part of machines, and not meters

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

1

2

3

4

5

6

7

8

9

10

11-7(2.88km)

7-5(5.54km)

5-3(5.1km)

3-1(2.6km)

1-2(2.6km)

2-4(4.6km)

4-6(4.6km)

6-10(2.88km)

ILC - General Services

Piping & ventilationSurvey : geodesics & marking positions

Electrical general services Cabling

Assumptions: unlimited resources meaning 12 teams for each type of work and for each tunnel !!! (24 teams of electricians for instance)

Estimated progress rate per

team: around 120m/wks

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

1

2

3

4

5

6

7

8

9

10

11-7(2.88km)

7-5(5.54km)

5-3(5.1km)

3-1(2.6km)

1-2(2.6km)

2-4(4.6km)

4-6(4.6km)

6-10(2.88km)

ILC - Machine installation

Support installation and alignment (250m/wk)

Machine inst.: transport and interconnections (progress rate to be confirmed 100m/wk)

Assumptions: unlimited resources !!!!In summary for 7 years installation

9 TBM, 24 electricians teams, 12 cooling and ventilation teams, 12 teams for machine installation

Are you able to provide all the machine components in 9 months ???

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

Resources comparison with CLIC

What would be the ILC schedule if machine installation is performed with 2 teams,

& what shall be the other resources ?

CLIC (1)

CLIC(2)

ILC

Nb of TBM 2 9Nb of teams for elec. general services 4 24Nb of teams for cooling and ventilation 4 12Nb of teams for cabling 4 24Nb of teams for machine installation 2 12

7.2y 10.5y 6y

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

1

2

3

4

5

6

7

8

9

10

11-7(2.88km)

7-5(5.54km)

5-3(5.1km)

3-1(2.6km)

1-2(2.6km)

2-4(4.6km)

4-6(4.6km)

6-10(2.88km)

ILC Schedule smoothed

Support installation and alignment (250m/wk)

Machine inst.: transport and interconnections (progress rate to be confirmed 100m/wk)

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009

Resources comparison with CLIC

CLIC (1)

CLIC(2)

ILC

Nb of TBM 2 4Nb of teams for elec. general services 4 8Nb of teams for cooling and ventilation 4 4Nb of teams for cabling 4 8Nb of teams for machine installation 2 2

7.2y 10.5y 9.5y

K. Foraz - CERN TILC09 & GDE AAP review – Tsukuba April 2009