life12 env/it/356 «bionad» «naturalised dyes replacing commercial colorants for environmentally...
DESCRIPTION
AGENDA 12:00[ICCOMCNR] Management and dissemination issues. In particular: BIONAD amendment New EC documents Cost analysis Final Report and related documents 13:00[All] General questions 13:00End of progress meeting 13:00 Tour of UNIFI premises and laboratories 13:30 Lunch LIFE12 ENV/IT/352 «BIONAD»TRANSCRIPT
LIFE12 ENV/IT/356 «BIONAD»
«Naturalised dyes replacing commercial colorants for environmentally friendly
leather dyeing and water recycle»
Start: 01/01/2014End: 30/06/2016
27/01/201624 month meeting
FirenzeUNIFI Premises
AGENDA
09:30 [UNIFI AND ICCOMCNR] Welcome and opening of the meeting
09:35 [All] Actions carried out by each partner and scheduled activities from July 2015 until the end of December 2015
11:00 [All] Open discussion on actions carried out11:15 [All] Coffee break11:30 [All] BIONAD Technical future issues:
[ICCOMCNR] Technical activities scheduled in the next six months of the project [All] Open discussion on actions to be carried out in the next six months of the project
LIFE12 ENV/IT/352 «BIONAD»
AGENDA
12:00 [ICCOMCNR] Management and dissemination issues. In particular:• BIONAD amendment• New EC documents• Cost analysis• Final Report and related documents
13:00 [All] General questions13:00 End of progress meeting13:00 Tour of UNIFI premises and laboratories13:30 Lunch
LIFE12 ENV/IT/352 «BIONAD»
LIFE12 ENV/IT/352 «BIONAD»
LIFE12 ENV/IT/352 «BIONAD»
Technical Actions carried out by each partner in the last six months
B6 Demonstration of naturalised dyes in leather dyeing at pilot scale level
B7 Demonstration of naturalised dyes at pre-industrial level for leather dyeing
C3 Monitoring of quality improvement for leather dyed with naturalised dyes
C4 Monitoring of dyeing effluents depuration using bacteria technology at pilot scale level
C5 Monitoring of the benefits from dyeing leather with naturalised colorants
C6 Monitoring of quality assessment for leather dyed with naturalised dyes
C7 Monitoring of technical-socio-economic assessment of the BioNad project
Presentations of:
UNIFIICCOMCNRBIOKIMICAINESCOPSERICHIM
LIFE12 ENV/IT/352 «BIONAD»
[All] Open discussion on actions carried out
LIFE12 ENV/IT/352 «BIONAD»
LIFE12 ENV/IT/352 «BIONAD»
Dissemination actions
D1 Naturalised dyes manual (July 2015-June 2016)D2 Leather sample books of hides dyed with naturalised dyes (July 2015-June 2016)D3 Training course for Italian tanneries (April 2015-June 2016)D4 Training course for Spanish tanneries (April 2015-June 2016)D5 Demonstration workshop in Italy (July 2015-June 2016)D6 Demonstration workshop in Spain (July 2015-June 2016)D7 Project website (April 2014-June 2014 )D8 Notice boards (January 2014-March 2014 )D9 Diffusion material preparation (January 2014-June 2016)
LIFE12 ENV/IT/352 «BIONAD»
Dissemination actions
D10 Articles and press releases (January 2014-June 2016)D11 Demonstration workshop, seminars, conferences and other events (January 2014-June 2016)D12 Dissemination to Institutions and policy makers (January 2014-June 2016)D13 International fairs and other events (January 2014-June 2016)D14 Digital supports for international diffusion (January 2014-June 2016)D15 Networking (January 2014-June 2016)D16 Layman's report (April 2016-June 2016)D17 After-LIFE Communication Plan (April 2016-June 2016)
LIFE12 ENV/IT/352 «BIONAD»
D1 Naturalised dyes manual (July 2015-June 2016)
•To be started (foreseen the production of a practical manual for tanneries)
LIFE12 ENV/IT/352 «BIONAD»
D2 Leather sample books of hides dyed with naturalised dyes (July 2015-June 2016)
To be started (foreseen at the end of the project that BIOKIMICA and INESCOP will produce two books (one for country) containing eachone 10 samples of project dyed leather accessible to industrial managers, Associations, Institutions, Technical Center, journalists and public)
LIFE12 ENV/IT/352 «BIONAD»
D3 Training course for Italian tanneries (April 2015-June 2016)
•To be started (foreseen that Biokimica organises a training course with 25-50 technicians from tanneries trained in natural products dyeing phase)
LIFE12 ENV/IT/352 «BIONAD»
D4 Training course for Spanish tanneries (April 2015-June 2016)
•To be started (foreseen that INESCOP organises a training course with 25-50 technicians from tanneries trained in natural products dyeing phase)
LIFE12 ENV/IT/352 «BIONAD»
D5 Demonstration workshop in Italy (July 2015-June 2016)
To be started (foreseen that Biokimica organises a workshop with the participation of 30 Italian tanning and leather expert and business people)
LIFE12 ENV/IT/352 «BIONAD»
D6 Demonstration workshop in Spain (July 2015-June 2016)
To be started (foreseen that INESCOP organises a workshop with the participation of 30 Spanish tanning and leather expert and business people)
LIFE12 ENV/IT/352 «BIONAD»
D7 Project website (April 2014-June 2014 and continuous updating)
•BIONAD website in English, Spanish and Italian: www.lifebionad.com•In the website:
Visit counter Link to LIFE+ Link to each beneficiary website Results update News update Coming up Reserved area Link with the Facebook page for event booking/registration • Website visitors: 47,498• Facebook page: 8 friends
LIFE12 ENV/IT/352 «BIONAD»
D8 Notice boards (January 2014-March 2014)
•ICCOMCNR produced 10 BIONAD Notice boards and gave them to all the beneficiaries•All the beneficiaries put the BIONAD Notice board in a public space •All the beneficiaries sent the photos of the BIONAD Notice board in a public space in each beneficiary premises
LIFE12 ENV/IT/352 «BIONAD»
D9 Diffusion material preparation (January 2014-June 2016)
•10,000 BIONAD brochures•1,500 BIONAD pendrives•INESCOP designed and produced 1,000 labels to identify leather samples as project gadget•1 BIONAD tissue poster•2 BIONAD specific posters by INESCOP•1 BIONAD roll-up•1 English, Italian and Spanish project presentations
LIFE12 ENV/IT/352 «BIONAD»
D10 Articles and press releases (January 2014-June 2016)
• 4 articles directly related to BIONAD in INESCOP’s EnvironmentNewsletter Sep’13, Feb’14, June 14, August 15• 4 indirect articles related to the participation of BIONAD to the CNR event (in local and web newspaper)• 1 TV interview during the LIFE CNR event in CNR premises on 25 March 2014• 2 articles (Italian and English) in Platinum journal• 1 technical article in “Dyes & Pigments” • 1 Article on Revista del Cuero of Colombia. Enero-Marzo 2014• 1 Article on Corriere Fiorentino on 05/11/2015
LIFE12 ENV/IT/352 «BIONAD»
D11 Demonstration workshop, seminars, conferences and other events (January 2014-June 2016)
• Meeting Leonardo Project: Step to sustainability 16-17 July 2013, Barsov – Rumanía• LIFE CNR event in CNR premises on 25 March 2014• University of Siena event about life, Siena 29 May 2014• Event of National School of Analytical and bioanalytical Methodologies in Mass Spectrometry in Parma 26-30 May 2014• BIONAD presentation at "Advanced course on the coupling of mass spectrometry with separation techniques in liquid phase" in Lucca, 23-26 June 2014• Event in Novartis company in Siena on 8 May 201• UNIFI LIFE event at Firenze on 24th October 2014
LIFE12 ENV/IT/352 «BIONAD»
D11 Demonstration workshop, seminars, conferences and other events (January 2014-June 2016)
• Workshop titled “Clean Technologies in the Tanning Industry”, Valencia (Spain), 7th November 2013• Workshop titled “Innovative Technologies in the Tanning Industry”, Valencia (Spain), 18th June 2014• LIFE+ Networking Event, 10 July 2014, Valencia (Spain) • LIFE+ Networking Event,19 November 2014, Ibi -Alicante (Spain)• LIFE+ Networking Event at the Valencia Chamber of Commerce ( Spain ), 14th July 2015 • BIONAD presentation at the event “ETICA E SPERIMENTAZIONI SCIENTIFICHE” of Società Chimica Italiana in Dipartimento di Chimica e Chimica Industriale, Universita di Pisa, on 22-23/01/2016• Dissemination at Milestone Sorisole (BG), 16 october 2015
LIFE12 ENV/IT/352 «BIONAD»
D12 Dissemination to Institutions and policy makers (January 2014-June 2016)
• All the BIONAD beneficiaries are responsible for the organisation of specific communication activities in order to disseminate the project actions and results to Institutions and policy makers. • The following preliminary contacts with institutions have been taken: o Councillor for the Environment of Pisa City - Italy o Environmental Department of Pisa Area - Italy o Senator of the Italian Government - Italy o Meeting of the Leonardo project “Competences pour l’Europe” (reference: 2012-1-IT1-LEO05-02837), Brasov (Romania), July 2013o Union for the Mediterranean Ministerial Conference on Environment and Climate Change, Athens (Greece), 13th May 2014•In the Annex Dissemination activities we will define a table with:Name of the policy maker contactedWhereTopics discussed and conclusions
LIFE12 ENV/IT/352 «BIONAD»
D13 International fairs and other events (January 2014-June 2016)
•Green week in Brussels 2-5 June 2014•UfM Ministerial Meeting on Environment and Climate 13 May 2014, Athens – Greece•Co-Shoes Fair, 22-23 October 2014, Alicante (Spain)•Co-Shoes Fair, Alicante (Spain), 22nd -23rd April 2015•Ecomondo Fair, Rimini, 3-6 november 2015•XXV Congress of Chimica Analitica of Società Chimica Italiana, Trieste, 13-17 September 2015•XXXIX International Colloquium Spectroscopicum, Figueira da Foz (Portugal), 29/08-03/09 2015
LIFE12 ENV/IT/352 «BIONAD»
D14 Digital supports for international diffusion (January 2014-June 2016)
•Each beneficiary started to define the specific video of each beneficiary activity•ICCOMCNR started to have some contacts with some expert video companies in order to organise the general structure of the video•ICCOMCNR started to work on the video text
LIFE12 ENV/IT/352 «BIONAD»
D15 Networking (January 2014-June 2016)•Cluster with OXATAN, SHOELAW, ECOFATTING, PODEBA, MICROTAN, SHOEBAT, CO2SHOE, SOREME, RESAFE, ECODEFATTING, LIFETAN (LIFE 9-10-11-12-13 projects)•BIONAD specific presentation at the CNR LIFE event at Pisa on 25th March 2014 •Networking contacts at the CNR LIFE event at Pisa on 25th March 2014•Networking contacts at the UNIFI LIFE event at Firenze on 24th October 2014•LIFE+ Networking Event, 10 July 2014, Valencia (Spain) •LIFE+ Networking Event,19 November 2014, Ibi -Alicante (Spain)•LIFE+ Networking Event at the Valencia Chamber of Commerce ( Spain) ,14th July 2015 •In the Annex Dissemination activities we will define a table with:
Day of the networking How (phone, meeting, etc.) Which projects Who (name of the participants) Topics discussed and conclusions
LIFE12 ENV/IT/352 «BIONAD»
D16 Layman’s report (April 2016-June 2016)
•To be started (foreseen a Layman’s report in English, Spanish and Italian)
LIFE12 ENV/IT/352 «BIONAD»
D17 After-LIFE Communication Plan (April 2016-June 2016)
•To be started (foreseen an After-LIFE Communication Plan in English, Spanish and Italian)Very important for the EC evaluation: the project is ended for the EC contribution, but is not ended for the work to do and the future application and the possible projects and businessShort report: overview of final results and table with future activitiesICCOMCNR will prepare the After-LIFE Communication Plan report to be attached to the Final Report as Deliverable
LIFE12 ENV/IT/352 «BIONAD»
ACTION E.1: Project management ACTION E.2: Monitoring
ICCOMCNR has continuous contact with all project partners for monitoring project activities
ICCOMCNR prepares and sends a summary of the project activities carried out to monitoring team at the end of each month
ICCOMCNR receives from each beneficiary technical inputs for the monitor month summary
Definition of management structures Definition of payment procedures of each beneficiary ICCOMCNR organised the kick-off meeting in January 2014 in
ICCOMCNR premises Biokimica organised the 6 progress meeting in June 2014 in
Biokimica premises Serichim organised the 12 progress meeting in January 2015 in
Serichim premises
LIFE12 ENV/IT/352 «BIONAD»
ACTION E.1: Project management ACTION E.2: Monitoring
Inescop organised the 18 progress meeting in July 2015 in Inescop premises
ICCOMCNR defined and sent the Partnership Agreement (following the EC scheme) and collected all the beneficiaries signatures
ICCOMCNR uses project progress indicators for monitoring project activities
ICCOMCNR revises the project progress indicators in each of the projects coordination meeting in order to check any irregularities
ICCOMCNR is checking the number and type of people reached by each dissemination activity in order to check if the diffusion actions have met their goals
LIFE12 ENV/IT/352 «BIONAD»
ACTION E.1: Project management
Definition of management structures
Management and technical committe• ICCOMCNR: Alessandro D’Ulivo• UNIFI: Roberto Bianchini• Biokimica: Marco Mazzoni• INESCOP: Mercedes Roig• SERICHIM: Pietro Delogu
Administrative committe• ICCOMCNR : Manuela Cempini• UNIFI: Silvia Borselli• Biokimica: Sabrina Vastola• INESCOP: Julio Gutierrez • SERICHIM: Giuseppina Vassallo
LIFE12 ENV/IT/352 «BIONAD»
ACTION E.1: Project management
Definition of payment procedures of each beneficiary
Each beneficiary has a specific payment responsible• ICCOMCNR: Alessandro D’Ulivo selects the project cost formally
approved by department director• UNIFI: Roberto Bianchini selects the project cost formally approved
by department director or DISPAA council• Biokimica, INESCOP and SERICHIM: Marco Mazzoni, Mercedes
Roig and Pietro Delogu select the project cost formally approved by company director and administration department
ICCOMCNR and UNIFI have specific project code and tender procedures
Biokimica, INESCOP and SERICHIM have separated project cost management and respect best value for money rules
LIFE12 ENV/IT/352 «BIONAD»
ACTION E.1: Project management
Definition of project accounting system and cost center
All beneficiaries have defined the following internal specific code (codice commessa) which identify the project and all costs and income related to the project:
ICCOMCNR: CUP B58I13000220006 UNIFI: CUP B58I13000220006 INESCOP: 6200200034 SERICHIM: PI14BIO1 BIOKIMICA: BIO2015
For ICCOMCNR and UNIFI VAT is a cost.
LIFE12 ENV/IT/352 «BIONAD»
ACTION E.1: Project management
Definition of project accounting system and cost center
All beneficiaries respects the procedure of the best value for money for selecting all the project external and consumable costs:
ICCOMCNR and UNIFI : public tender through MEPA SERICHIM, BIOKIMICA and INESCOP: historical supplier or
market analysis
All the beneficiaries approved only the costs: directly linked to, and necessary for, carrying out the BIONAD
project; reasonable, justified and comply with the principles of sound
financial management, in particular in terms of economy and efficiency;
compliant with applicable tax and social legislation; and actually incurred during the lifetime of the project, as defined in the
grant agreement, and which could be identifiable and verifiable
LIFE12 ENV/IT/352 «BIONAD»
BIONAD Technical future issues for the next six months
B7 Demonstration of naturalised dyes at pre-industrial level for leather dyeing C4 Monitoring of dyeing effluents depuration using bacteria technology at pilot scale level C5 Monitoring of the benefits from dyeing leather with naturalised colorantsC7 Monitoring of technical-socio-economic assessment of the BioNad project
LIFE12 ENV/IT/352 «BIONAD»
BIONAD Technical future issues for the next six months
[All] Open discussion on actions to be carried out in the next six months of the project
LIFE12 ENV/IT/352 «BIONAD»
BIONAD Dissemination issues balance
D1 Naturalised dyes manual: to be started (foreseen 1 manual) D2 Leather sample books of hides dyed with naturalised dyes (foreseen 2 Leather sample books of 10 hides ) D3 Training course for Italian tanneries (foreseen 1 Training course ) D4 Training course for Spanish tanneries (foreseen 1 Training course ) D5 Demonstration workshop in Italy (foreseen 1 workshop) D6 Demonstration workshop in Spain (foreseen 1 workshop) D7 Project website: update D8 Notice boards: OK D9 Diffusion material preparation: more posters (foreseen 25 Posters, 10,000 leaflets/brochures/factsheets, 2,500 various branded items, now 10,000 brochures, 2,500 gadgets, 3 posters, 1 roll-up, 2 presentations) D10 Articles and press release: more articles (foreseen 30 articles, now 13 and 1 TV interview)
LIFE12 ENV/IT/352 «BIONAD»
BIONAD Dissemination issues balance
D11 Demonstration workshop, seminars, conferences and other events: OK OK (foreseen maximum dissemination, now 14 events) D12 Dissemination to Institutions and policy makers: OK (foreseen successful communication, now 5 contacts/meetings) D13 International fairs and other events: OK (foreseen maximum dissemination, now 7 fairs/events) D14 Digital supports for international diffusion: start (foreseen project video) D15 Networking: OK OK (foreseen 10 projects, now 11) D16 Layman’s report : to be started (foreseen a Layman’s report in English, Spanish and Italian) D17 After-LIFE Communication Plan: to be started (foreseen an After-LIFE Communication Plan in English, Spanish and Italian
LIFE12 ENV/IT/352 «BIONAD»
ADMINISTRATIVE ISSUES
Change of MonitorAmendment Final Report and related documentsNew excel EC forms for project cost Partner costs December 2015Personnel daily ratesNext meetings
LIFE12 ENV/IT/352 «BIONAD»
CHANGE OF MONITOR
New Monitor: Paolo ROSA-CLOT
LIFE12 ENV/IT/352 «BIONAD»
AMENDMENT EVALUATION
“Following a careful assessment of your request, our services concluded that an amendment procedure is not justified....., the only proposed substantial change to the project budget consists of an increase of 14% in Personnel costs. Please be aware that all budget changes will be evaluated at the Final Report stage against the original budget reported in the Grant Agreement. The evaluation will depend on the overall technical achievements of the project, as well as on their value for money and cost-effectiveness.I take this opportunity to acknowledge the efforts of project team in terms of personnel and materials invested in order to tackle the challenging synthesis of naturalised dyes at pilot scale, as well as their use for semi-industrial scale tinctorial trials. I invite you to keep up with this high commitment to the project objectives.”
LIFE12 ENV/IT/352 «BIONAD»
FINAL REPORTICCOMCNR will be responsible of the production of the Final report which will be made up by:Progress report with the summary of technical, administrative and dissemination project issues Dissemination Annex DeliverablesPossible Technical Annexes Output indicatorsNew EC Financial forms with all the originals signatures from each partner Documents requested by the EC in the Mid-Term Report evaluationAudit document
The Final Report sending deadline is 30 September 2016The EC ok of the Final report will produce the project final
payment from the EC
LIFE12 ENV/IT/352 «BIONAD»
FINAL REPORT
Documents needed from each beneficiary
ICCOMCNR will check all the partner financial documents
for final original versions with signatures from each partner
ICCOMCNR will be responsible for the production of an audit
document signed by an external authorised auditor (already
selected) which will certify all the project financial data.
The selected auditor will check all the partner financial data and, if
necessary, will request to each partner more detailed documents.
LIFE12 ENV/IT/352 «BIONAD»
FINAL REPORT CHAPTERS 1. List of contents 2. Executive summary 3. Introduction 4. Administrative part 5. Technical part
• 5.1 Technical progress per action• 5.2 Dissemination actions• 5.3 Evaluation of project implementation• 5.4 Analysis of long-term benefits
6. Comments on the financial report• 6.1 Summary of costs• 6.2 Accounting system• 6.3 Partnership arrangements• 6.4 Auditor’s report• 6.5 Summary of costs per action
7. Annexes 8. Financial report and annexes
LIFE12 ENV/IT/352 «BIONAD»
FINAL REPORT
Deadline
Each partner will have to send to ICCOMCNR all the technical contribution no later than 30th of June 2016
Each partner has to send to ICCOMCNR all the dissemination contribution no later than 30th of June 2016
Each partner responsible for a Deliverable has to send to ICCOMCNR the Deliverable no later than 30th of June 2016
ICCOMCNR will send a draft of the Final Report to the Monitoring team no later than 10th of September 2016
ICCOMCNR will send to EC and Monitoring agency all the Final Report documents no later than 30th of September 2016
LIFE12 ENV/IT/352 «BIONAD»
NEXT DELIVERABLES
All the following Deliverables will be annexes of the Final Report : Quality assessment for leather dyed with naturalised dyes: Action C.6 After-LIFE Communication Plan: Action D.17 Dissemination materials, articles, press release and events: Action D.9 Dyeing effluents depuration using bacteria technology at pilot scale level: Action C.4 Layman's report : Action D.16 Naturalised dyes at pre-industrial level for leather dyeing: Action B.7Technical socio-economic benefits from dyeing leather with naturalised colorants: Action C.7
LIFE12 ENV/IT/352 «BIONAD»
New excel EC forms for project cost
LIFE12 ENV/IT/352 «BIONAD»
PARTNER COSTS December 2015
LIFE12 ENV/IT/352 «BIONAD»
PARTNER CLAIM
Personnel
Personnel December
2015 Travel
Travel December
2015
External assistan
ce
External assistance December
2015Consum
ables
Consumables December
2015Overhea
ds
Overheads December
2015 TOTAL
TOTAL December
2015
ICCOMCNR 244.000 272.409,26 9.140 4.710,21 87.400 75.584,00 105.000 34.211,20 30.000 27.084,03 475.540 413.998,70
UNIFI 143.000 152.621,01 9.140 2.150,71 20.300 5.098,38 105.000 51.507,88 20.000 14.796,46 297.440 226.174,44
SERICHIM 133.500 216.516,26 9.140 1.146,63 5.000 60.000 16.468,46 15.000 16.389,19 222.640 250.520,54
BIOKIMICA 175.500 243.083,00 9.140 1.221,00 15.400 30.000,00 80.000 17.549,00 20.000 20.429,71 300.040 312.282,71
INESCOP 118.500 107.144,08 7.790 5.125,42 16.000 3.421,88 20.000 17.849,35 11.106 9.347,85 173.396 142.888,58
TOTAL 814.500 991.773,61 44.350 14.353,97 144.100 114.104,26 370.000 137.585,89 96.106 88.047,24 1.469.056 1.345.864,97
Personnel daily rates
LIFE12 ENV/IT/352 «BIONAD»
Beneficiary: ICCOMCNR As per Project At December 2015
Actions Contract type
Category Daily rate Category Daily rate
B1, B7, C5, D1, D7, D8, D9, D13, D14, D15
Permanent staff
Chemical expert 200 Chemical expert 245, 126, 49
D10, D11, D12, D16, E1, E2
Permanent staff
Project manager 200 Project manager 406
Beneficiary: UNIFI
As per Project At December 2015 Actions Contract
type Category Daily rate Category Daily rate
B3, C1, C2, C4, D11, D12, D13, D15
Permanent staff
Chemical expert 200 Chemical expert 205, 227, 178, 165, 129
E1 Permanent staff
Project manager 200 Project manager 461
Beneficiary: SERICHIM
As per Project At December 2015 Actions Contract
type Category Daily rate Category Daily rate
B5, B6, B7, C7 Permanent staff
Synthesis of dyes expert
150 Synthesis of dyes expert 271, 378, 188, 198, 207, 229, 237, 278
E1 Permanent staff
Project manager 200 Project manager 278
Personnel daily rates
LIFE12 ENV/IT/352 «BIONAD»
Beneficiary: Biokimica As per Project At December 2015
Actions Contract type
Category Daily rate Category Daily rate
B2, B4, B6, C3, C6, D2, D3, D5
Permanent staff
Tanning expert 150 Tanning expert 120, 152, 184, 288, 384
E1 Permanent staff
Project manager 200 Project manager 440
Beneficiary: INESCOP
As per Project At December 2015 Action Contract
type Category Daily rate Category Daily rate
B2, B6, C3, C6, D4, D6 Permanent staff
Tanning expert 150 Tanning expert 150, 182, 262
E1 Permanent staff
Project manager 200 Project manager 267
Projects MEETINGs
LIFE12 ENV/IT/352 «BIONAD»
1st Kick off meeting in ICCOMCNR in Italy in January 2014 2nd Coordination and monitoring meeting in Biokimica in
S.Croce sull’Arno (Italy) on June 13th 2014 3rd Coordination and monitoring meeting in SERICHIM in
Torviscosa (Italy) on 29th January 2015 4th Coordination meeting in INESCOP in Elda (Spain) on
07th July 2015 5th Coordination meeting in UNIFI in Florence on 27th
January 2016
Next Project meetings Monitoring meeting in Biokimica in S.Croce sull’Arno (Italy)
on 11th February 2016 Final meeting in ICCOMCNR Italy on June 2016