ligo-g010226-00-m summary remarks: management of ligo gary sanders california institute of...

21
LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research in Astronomy and Astrophysics June 14, 2001

Upload: ira-murphy

Post on 04-Jan-2016

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

LIGO-G010226-00-M

Summary Remarks: Management of LIGO

Gary Sanders

California Institute of Technology

NRC Committee on Organization and Management of Research in Astronomy and

Astrophysics

June 14, 2001

Page 2: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

2LIGO-G010226-00-M

This Presentation

Introduction to LIGO How we have managed LIGO How NSF has managed LIGO

Responses to Advance Questions

Page 3: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

3LIGO-G010226-00-M

LIGO Scope and Costs

The Laser Interferometer Gravitational Wave Observatory (LIGO) is:» a joint project of Caltech and MIT

» construct and operate two observatories with 4 km interferometers

» detect gravitational waves

» initiate ground-based gravitational wave astronomy

LIGO is supported through the NSF Division of Physics/Gravity Program» Construction cost $292 million (Major Research Equipment)

» Commissioning, early operations and R&D cost $79 million

» This funding covers 1994 - 2001

Page 4: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

4LIGO-G010226-00-M

Long Baseline Interferometry

Page 5: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

5LIGO-G010226-00-M

LIGO (Washington) LIGO (Louisiana)

LIGO Observatories

Page 6: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

6LIGO-G010226-00-M

LIGO Vacuum System

Page 7: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

7LIGO-G010226-00-M

LIGO 4 km Beam Tubes

Page 8: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

8LIGO-G010226-00-M

Optics Installation

Page 9: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

9LIGO-G010226-00-M

LIGO Fused Silica Optics

Surface figure rms  = 0.16 nm

Surface figure = / 6000

Page 10: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

10LIGO-G010226-00-M

LIGO Schedule

1996 Construction Underway (mostly civil)

1997 Facility Construction (vacuum system)

1998 Interferometer Construction (complete facilities)

1999 Construction Complete (interferometers in vacuum)

2000 Detector Installation (commissioning subsystems)

2001 Commission Interferometers (first coincidences)

2002 Sensitivity studies (initiate LIGO I Science Run)

2003+ LIGO I data run (one year integrated data at h ~ 10-21)

2006+ Begin ‘advanced’ LIGO installation

Page 11: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

11LIGO-G010226-00-M

Cost Schedule Performance

0

50

100

150

200

250

300

95-2

95-4

96-2

96-4

97-2

97-4

98-2

98-4

99-2

99-4

00-2

00-4

01-2

01-4

LIGO Quarter

$ M

illio

ns

Original Plan - $250M

Current Plan - $290M

Cooperative Agreement - $292M

Performance - $281M

Actuals Costs - $278M

Earned Value

Page 12: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

12LIGO-G010226-00-M

Features of the LIGO Construction Project

University (Caltech+MIT) managed, no national laboratory

Two green field sites Carried out as two major subprojects

» 2/3 of the project constructs buildings, clean labs, vacuum system designed for ultimate terrestrial detectors

» 1/3 of project constructs initial detectors

Page 13: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

13LIGO-G010226-00-M

Features of the LIGO Construction Project

Organized and executed like a bridge building project» Product oriented Work Breakdown Structure (WBS)» Scope and technical configuration defined and controlled» Cost and schedule integrated into a performance measurement baseline

with earned value analysis» Contingency funds managed centrally through a Change Control Board» Organization matches WBS

– Subsystem managers responsible to deliver products

» Subcontractors managed rigorously» Scientists fully integrated and aware of Voltaire’s maxim “le mieux est

l'ennemi du bien”– Scientists did not destabilize project but were also the source for project repair

and workaround

Big Science culture new to NSF and to Caltech/MIT scientists

Page 14: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

14LIGO-G010226-00-M

What LIGO Team Has Done

Construction» Executed a ~$300 technical construction project

» Adapted big science methods from DOE to an NSF project

Operating a scientific program» Organized a ~30 institution, ~300 scientist international

collaboration to carry out the– observational science and– advanced R&D

Page 15: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

15LIGO-G010226-00-M

What NSF Has Done

Through the Gravity Program, NSF has adapted elements of the same DOE model to an NSF environment to create an oversight function for LIGO

Cooperative Agreement and Project Management Plan created the formal framework

A dedicated program officer led the oversight and structured NSF review

Semiannual project reviews during construction used a standing committee with slowly varying membership to provide review of progress

Program officer employed an internal multidisciplinary team to coordinate NSF reviews and approvals with periodic meetings

» Gravity program, grants and agreements, legal, public affairs, government affairs, property management, budget,…

Page 16: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

LIGO-G010226-00-M

Responses to Questions

Page 17: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

17LIGO-G010226-00-M

"womb to tomb“ – Planning, Construction, Operations, …

1994 National Science Board recognized need to transition from construction to operation of LIGO. They authorized:» Preconstruction R&D - $20 million – through FY 1999

» Construction - $272 million (Major Research Equipment) – through FY 1999

» Early operations and commissioning - $69 million – FY 1997 – 2001

NSF Physics has done well in working with LIGO to assure a smooth transition from construction to early operations» DOE high-energy physics experience in NSF program office and

LIGO management provided the template

Page 18: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

18LIGO-G010226-00-M

“…resources to advance the science…”

LIGO was created as a capability» LIGO is not a single attempt to observe with the initial interferometers» 2/3 of investment is in the site, special buildings and vacuum system

– these are designed to house detectors whose sensitivity is close to the terrestrial limits

1996 NSF McDaniel panel on use of LIGO led to:» LIGO community organized as a LIGO Scientific Collaboration (LSC) to carry out

science» LIGO Laboratory created to operate LIGO and manage program» funding for R&D toward next generation detectors

– NSF has provided $10.2 million to LIGO – FY 1997 – 2001– LIGO community also funded at additional ~$4 million/year– NSF funds universities and LIGO Lab provides review and program integration and

infrastructure

2002 – 2006 program for initial science run and R&D under review at NSF now

NSF Physics/Gravity and LIGO have managed an appropriate balance between facility imperatives and scientific advancement

Page 19: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

19LIGO-G010226-00-M

“…strengths…weaknesses… supporting…astronomy…”

LIGO is an NSF Physics/Gravity activity» LIGO provided first very large project example for NSF» LIGO and NSF management of LIGO has been successful in project

execution

NSF LIGO experience has not been formally spread across NSF

NSF management consciously encouraged LIGO model in managing ALMA

ALMA is being managed by NSF/AST and NRAO in a manner consistent with LIGO approach

» LIGO experience was “borrowed” by NSF/AST and by NRAO» Oversight committee includes experienced LIGO and NASA managers

Page 20: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

20LIGO-G010226-00-M

Other agencies/NSF outside of Astronomy

DOE Office of Science has» experience and an established methodology for certifying and

assessing large projects– Temple/Lehman review process

» established national laboratories with project experience

» scientific communities with experience

LIGO applied selected elements of this methodology borrowing from DOE and national laboratory practices

NSF/LIGO model not formally described to or employed by other NSF programs, even in Physics Division

Page 21: LIGO-G010226-00-M Summary Remarks: Management of LIGO Gary Sanders California Institute of Technology NRC Committee on Organization and Management of Research

21LIGO-G010226-00-M

Some Observations

NSF has no established internal standards and processes defining how to develop large projects, assess readiness for construction, measure project performance and transition to operation

» Panels advise NSF on these questions for each project individually» Panels are used in different ways by different program officials» Program officials also have full-time jobs administering grant programs» Leads to “approve-review-coach-review-flunk-review-flunk-fire-reorganize-

review…” syndrome– Poor substitute for community and agency understanding of big science

MRE process has no established progression to incubate candidate projects to readiness for construction

Involvement of the scientific stakeholders in big projects varies greatly in different fields

» Particle physicists are very involved in their large projects» Astronomers are less involved during design resolution and construction